Académique Documents
Professionnel Documents
Culture Documents
INDEX
Introduction
.1
A
strategic
approach
to
procurement
...2
Analysing
critically
the
alternative
routes3
procurement
Suitable
Advance
Procurement
Practice..4
Factors influencing the development of
an appropriate procurement strategy & its implementation..
.5
The
Most
Suitable
route
....6
Example
....7
1. INTRODUCTION
Construction
Project
Identifiable start,
Resources and plan
Smooth
adaption and
Identifiable end
and handover
2. Design-Build
3. Construction Management
4. Management Contracting
Client
Consultants
(fee contract)
Architect
(fee contract)
Named
Subcontractors
Main Contractor
(Standard lump sum
Subcontractors
Suppliers
(various contracts)
The contractors are now invited for tender, where they submit a price for
completing the work. For this the client will provide the contractor the
drawings, specification, bills of quantities etc. The client expects a firm
price from contractor within four to six weeks.
Brief
Design
Tendering
Constructio
n
In this procurement route all the decision by clients are made before
tendering. The contract sum can be possibly changed only if any change
in design arises or anything arises during work in progress. It is clients
responsibility and also risk of performance of design team. The
contractors responsibility is only for construction work.
It is not beneficial to choose contractor only on cost basis, because
contractor will bid low cost to get the contract and them might recover the
profit by claiming at work in progress. Due to the different process of
design and construction there rises an attitude of them and us between
designers and contractors. As this may affect the team spirit which can
show adverse effect on overall project.
ADVANTAGES:
Fair competition
Comparatively low tender cost
Reasonable public answerability
Traditional well known processes
Relatively easy application of changes
DISADVANTAGES:
RISKS:
Client
Clients
Consultants
Project
Manager
D & B Contractors
Consultants
(various contracts)
Subcontractors
Suppliers
(various contracts)
Figure 3.3: Typical project structure under the design and build
procurement route
[Procurement course notes, Oyegoke, A.S]
It can be beneficial for client as the contractor can offer other packages
like site selection, purchasing, obtaining necessary approvals, financing,
leasing etc.
Thus the design and build route is suitable for:
This route has very less chances of changes of design, as the contractor
controls design. Due to this time and cost is saved, which is beneficial for
client and the total project cost and time. The design and build method is
becoming increasingly popular in UK and around the world. As because
the client has all idea of regarding financial thing at early stage. Also the
client dont need to involve himself closely in the construction process.
Sequence
Brief
Competitio
n
Design
Constructio
n
Figure 3.4: Sequence of Design and Build procurement route
ADVANTAGES:
Essential buidabilty
Total financials are known at early stage of project
Duration of project is reduced, Compared to traditional route
Contractors design responsibility can be stretched
DISADVANTAGES:
RISKS:
Project
Manager
Clients
Designer
Management
contractor
(standard fee contract)
Works Contractor
(std lump sum
contract)
Works
Contractor
Works
Contractor
Supplier
Suppliers
(Various Contracts)
(various contract)
Contractual relationship
Sub
Consultant
Them and us attitude will be less seen in this route and communication
increases. It is easy for the management contractor to categorise clients
needs and interests. Most of the decision are made jointly, which makes
use of wider experience.
Brief
Design
Construct
Figure 3.6: Sequence of management contracting procurement route
ADVANTAGES:
DISADVANTAGES:
RISKS:
Medium COST risk as the client dont have exact project cost until
last package is let
Medium TIME risk as the duration of project depends upon package
selection
Low QUALITY/DESIGN risk as everyone involved in project are
working as a team.
Client
Construction
manager
Project
Manager
(fee Contract)
Works
contractor
Works
contractor
Works
contractor
Subcontractor
Suppliers
(various
Contract)
Clients
Designer
Consultant
(various
Contract)
Contractual relationship
Figure 3.7: Typical Project Structure under
management procurement route
[Procurement course notes, Oyegoke, A.S]
the
construction
Brief
Design
Construct
Figure 3.8: Sequence of construction management procurement route
ADVANTAGES:
DISADVANTAGES:
RISKS:
Medium COST risk as the total project cost is unknown till last
package is let
Medium TIME risk as no single organisation is responsible for delay
of project
Low QUALITY/DESIGN risk as the client will be working closely with
architect and other contractors
3. Partnering
4. Two stage tendering
5. Private Finance Initiative (PFI) / Public-Private Partnership
5. FACTORS
STRATEGY
INFLUENCING
DEVELOPMENT
OF
PROCUREMENT
The basic client values which are present in all construction projects,
albeit in to different extent are:
6. Route selection
The most suitable route for the above said project would be Design and
Manage route
Benefits of choosing this routes are:
This route is suitable for a complex and big project like this.