Académique Documents
Professionnel Documents
Culture Documents
The steel connection in building construction is mainly divided into two types:
(a) Welding
(b) Bolting
In this lecture, both types of steel connection will be discussed through the calculation
and real-life example.
-----------------------------------------------------------------------------------------
PART I: Welding
Welding is the process of joining metal parts by fusing them and filling in with molten
metal from the electrode. However, due to the high temperature of the welding
process, it should be carried out under close supervision. (Figure 1.1)
For example,
-Page 2-
November 2006
Figure 1.5:-Fillet Weld
(a) (b)
Figure 1.6:- Fillet weld design
- In lap joints the lap length should not be less than four times the thickness of
the thinner plate. (Figure 1.6(b)).
- The spacing between intermittent welds should not exceed 30mm nor 16t for
parts in compression nor 24t for parts in tension (when t is thickness of the
plate) (Figure 1.7)
-Page 3-
November 2006
Figure 1.7:- Fillet weld design
-Page 4-
November 2006
Part II: Bolting (or Rivet)
It is achieved by inserting high strength bolts into connecting holes between plates
and then tightened to a percentage of the allowable bolt tensile strength.
On the other hand, in a riveted joint, a heated rivet is forced into a hole connecting
two “plates”. As the rivet cool, a tension will be developed in the rivet and the plates
are forced together.
Figure 2.1:-Lap joint for bolt and rivet / Butt joint for bolt and rivet
Bolted Connections
Bolted connections are increasingly used instead of rivets and more often than welds
It is mainly because
(1) rivets may be too labor intensive, for example, it require heating up at the bolt;
(2) welds may cause secondary cracks if not properly performed.
-Page 5-
November 2006
Figure 2.2 Ordinary Bolts
It is specified in BS4190
- Two grades
- Grade 4.6 mild steel – yield strength 235MPa
- Grade 8.8 high yield steel 0 yield strength 627MPa
- Common diameter: 16, 20, 22, 24, 27 and 30mm
-Page 6-
November 2006
For example:
-Page 7-
November 2006
t = thickness of thinner plate connected
ε = (275 / p y ) 0.5
-Page 8-
November 2006
(3) Eccentric Connections: Bolts in direct shear and Tension
M = (FT / r1 ) × ∑ r 2
(
P × e = ( FT / r1 ) ∑ x 2 + ∑ y 2 )
P × e × r1
∴ FT = …..Eq(3)
∑ x2 + ∑ y2
On the other hand, force due to shear on each bolt = FS = P / (nos. of bolts)……Eq(4)
-Page 9-
November 2006
Then try to find out the maximum force on the bolt
Consider Bolt B,
Vertical force on bolt B =
Fs + FT cos φ …..Eq(5)
Horizontal force on bolt B =
FT sin φ ……Eq(6)
Resultant force on bolt B,
[
FR = (FS + FT cos φ ) + (FT sin φ )
2 2
] 1
2
…..Eq(7)
The bolt size can then be determined from the maximum force on the bolt.
-Page 10-
November 2006
Moment 2 sides
M = 2( Ft y1 + Ft y 22 / y1 + K)
= 2( Ft / y1 )( y12 + y 22 + K)
n
P ⋅ e = 2(Ft / y1 )∑ y i2
i =1
-Page 11-
November 2006
Example 1
In Figure Q.1, Calculate the Maximum bolt tension and the shear force on each bolt.
Figure Q.1
Solution:
y1 = 400mm
n=4
∑y
i =1
i = (100 2 + 200 2 + 300 2 + 400 2 ) = 300,000
150
By Eq(9), the shear force on each bolt = = 15kN
10
-Page 12-
November 2006
Example 2
In Figure Q.2, Calculate the tension force on the bolt A and shear force on each bolt.
Figure Q.2
Solution:
∑r 2
= ∑ x 2 + ∑ y 2 = 4(75 2 + 150 2 ) + 4(50 2 + 75 2 ) = 8(75 2 ) + 4(50 2 + 150 2 ) = 145,000
-Page 13-
November 2006
The tension force on bolt A is
P × e × r1 150 × 300 × 167.71
From Eq.(3), FT = = = 52.05kN
∑x +∑y
2 2 145,000
-Page 14-
November 2006