Académique Documents
Professionnel Documents
Culture Documents
PURPOSE OF
DOCUMENT
DOCUMENT NO.
DATE:23/12/2011
COPY NO:
ISSUED TO:
K.SELVARAJ
P.GOVINDARAJU
J .BALASUBRAMANIAN
DY ENGINEER
DGM
AGM/TSX
PREPARED
REVIEWED
APPROVED
System
Drum (FULL)
67
Circulating System
202
Economiser
114
Super Heater
220
Reheater
210
Total
813
315.00 Kg/sq.cm 2
Stage - II
78.0 kg/sq.cm 2
Hydrazine Hydrate :
300 Liters
600 liters
Stage II :
Ammonia
100 liters
Hydrazine Hydrate :
300 liters
: 300 liters
:
600 liters
3
LIST OF CONTENTS
1.0
PLANT DETAILS
2.0
OBJECTIVE
3.0
PROPOSAL
4.0
SERVICES REQUIRED
5.0
SAFETY PRECAUTIONS
6.0
EMERGENCY PROCEDURES
7.0
8.0
METHOD
9.0
PRESERVATION OF BOILER
10.0
COMPLETION CRITERIA
11.0
APPENDICES
STATUS
a) LOG SHEETS.
b) DRAWINGS
g) DM water shall be used for conducting drainable portion as well as non drainable
hydraulic test.
h) The hydrostatic test pressure shall be 1.5 times the design pressure
i) Recommended Hydrostatic Test Pressures are: (Refer project specific data for
correct values)
j) After completion of Stage IA Hydrostatic test the Boiler shall be drained and after
completion of Stage IB Hydrostatic test the Boiler shall be kept under
preservation.
4. SERVICES REQUIRED
a)
b)
: 7 + 0.2
Conductivity
Total hardness
: Nil
Total Silica
Chloride
: Nil
Sodium
: 0.003 ppm
l) Boiler Fill pump, Pressurising pump, other temporary pumps and tanks of required
capacity are ready with their respective pipe connections to Boiler.
m) Adequate lighting for effective checking of all the areas including inside the Boiler
is available.
n) Effective communication facility is available between Drum floor, pressurising
pump area and other operating areas.
o) Sky climbers / Scaffolding arrangements are provided inside the Boiler.
p) Boiler drain is suitably connected to storm water drain/ DM plant neutralizing pit..
q) All debris are removed manually from upper and lower drums (Ring headers),
buck stays etc.,
8.0 METHOD OF CONDUCTING HYDRO TEST
8.1 AIR TESTING THE PRESSURE PARTS
a) Before filling the boiler with water, an air tightness test is to be performed to detect
leakages due to valve left in open condition, missing X-ray plugs; any cuts etc. not
observed by visual inspection. This will reduce the DM water consumption and
time as well.
b) Boiler is to pressurised with air up to 2 kg/sq.cm 2
c) Boiler is inspected and leakages, if any found, are attended.
d) After completing the air tightness test vent valves are left in open position.
8.2 FILLING OF THE SYSTEM FOR HYDROSTATIC TEST
Stage IA & IB
a) The boiler water circulation system, economiser and Super-heaters are filled with
DM water through boiler fill pump and injecting ammoniated hydrazine water
simultaneously using hydro test pump. The same HYDRO TEST PUMP
(Pressurising pump) is used for pressurisation after ensuring filling the
boiler without any air entrapment by adopting techniques mentioned in 8.2 b
to c. Economiser recirculation line valves should be in wide-open position.
b) Confirmation of completion of filling of the entire system is done through the vents.
c) The vent valves are closed and opened several times to allow venting of
entrapped air.
d) On completion of filling the fill pump may be kept running in recirculation to supply
water to pressurising pump tank.
8
Stage II
a) The Reheater circuit is filled with DM water containing 200 ppm hydrazine and pH
9.5 10.0 (with ammonia) through fill line connected to boiler drain header. At the
same time chemical dosing is injected by hydro test pump as shown in the
scheme.
b) Isolators provided in the CRH & HRH lines should be kept in position and perfect
closing is ensured.
c) Confirmation of completion of filling of the entire system is done through the vents.
d) The vent valves are closed and opened several times to allow venting of
entrapped air.
e) On completion of filling the fill pump may be kept on recirculation to facilitate filling
of pressurising pump inlet tank
8.3. PRESSURISING THE SYSTEMS
a) Pressure is raised with the help of pressurising pump
b) Wherever valves are in tandem, both the valves should be checked for passing
one by one. All the drain valves, vent valves and NRVs should be checked for
passing, if any.
c) The pressure is raised up to 25 Kg/cm 2 and a thorough inspection of the Boiler is
done. For Stages IA & IB the pressure is raised in steps and held for 10 minutes at
100 & 200 Kg/cm2. The rate of rise of pressure should not be more than 10
Kg/cm2 per minute up to approximately 80% of the test pressure and should be 1
to 2 Kg/cm2 per minute beyond that value.
d) After reaching the test pressure, maintain/hold the pressure for 30 minutes.
8.4 HYDRAULIC TEST
a) The hydraulic test pressure reading is taken from the calibrated standard test
pressure gauge mounted near the pressurising pump with necessary correction
for the height of the Drum and simultaneously from the gauge mounted at a safe
location at Drum floor as per requirement of the statutory Inspection Authority.
b) The test pressure is maintained for 30 consecutive minutes in presence of
Inspection Authority.
c) The pressure is then reduced to 50 Kg/cm 2 and the entire pressure parts are
checked.
d) If leaks are found, it will be necessary to release the pressure and drain the
concerned portions. After the repairs the Boiler is refilled and the hydraulic test is
repeated.
e) Details of the leaks noticed during Hydraulic Tests are recorded as given below for
better understanding:
10
c) In case, the sample water does not meet the criteria for preservation of Boiler the
same is to be boosted up using Boiler fill pump and dosing arrangement and at
the same time venting sufficiently through the air vents in the top level of the
boiler.
d) No welding shall be carried out on pressure parts when the system is under
preservation or the system is filled.
e) Alternatively, preservation can also be done under nitrogen capping at 0.5 Kg/cm 2
by admitting nitrogen through vents of Drum and Super heaters.
Reheater system
a) Reheater system should also be preserved using treated DM water containing not
less than 200 ppm of Hydrazine and sufficient quantity of ammonia to have pH
value of 10.0 10.5 or by Nitrogen capping at 0.5 Kg/cm 2.
b) Reheater system should be filled through drain. Perfect isolation of the Reheater
circuit from Turbine should be ensured before pressurizing.
10.0 COMPLETION CRITERIA;
The test pressure in the official pressure gauge (Calibrated standard test
pressure gauge) is held for 30 consecutive minutes in presence of Inspection
Authority. The Boiler shall satisfactorily withstand such pressure without
appreciable leakage or undue deflection or distortion of its pressure parts for at
least 10 consecutive minutes
11
DATE :
QTY OF CHEMICALS
ADDED IN LITRE
DATE
TIME
AMMONIA
LITRES
BHEL
HYDRAZINE
HYDRATE
LITRES
ANALYSIS VALUE
AFTER DOSING
POINT
N2H4
pH
CONCEN.
ppm
CUSTOMER
12
DATE :
S.NO
BHEL
DATE
TIME
PRESSURE
HYDRO TEST
PUMP
DRUM
OUTLET in
ground level
REMARKS
CUSTOMER
13
DATE :
i) Ammonia
ii) Hydrazene Hydrate
S.NO
i) pH
:
ii) Hydrazene :
SAMPLE
COLLECTED AT
SH VENT
DATE
BHEL
TIME
N2H4
CONCEN
.
ppm
SYSTEM
PRESSURE
CHEMICAL ADDED
AMMONIA
LITRES
N2H4
LITRES
CUSTOMER
14
15