Vous êtes sur la page 1sur 2

Federal Register / Vol. 73, No.

61 / Friday, March 28, 2008 / Notices 16661

4. Necessity of the Collection of DEPARTMENT OF ENERGY Any questions regarding this


Information: The filing requirement Application should be directed to Keith
provides the basis for analysis of all Federal Energy Regulatory Tiggelaar, Director of Regulatory Affairs,
rates, fares, or charges whatsoever Commission Williston Basin Interstate Pipeline
demanded, charged or collected by any [Docket No. CP08–89–000; PF08–4–000] Company, P.O. Box 5601, Bismarck,
common carrier or carriers in North Dakota 58506–5601or by
connection with the transportation of Williston Basin Interstate Pipeline telephone at (701) 530-1560 or e-mail at
crude oil and petroleum products and is Company; Notice of Application keith.tiggelaar@wbip.com.
On November 15, 2007, the
used by the Commission for March 21, 2008. Commission staff granted Williston
determining the just and reasonable Take notice that on March 12, 2008, Basin’s request to utilize the National
rates that should be charged by the Williston Basin Interstate Pipeline Environmental Policy Act (NEPA) Pre-
regulated pipeline company. Based on Company (Williston Basin), P.O. Box Filing Process and assigned Docket No.
this analysis, a recommendation is made 5601, Bismarck, North Dakota 58506– PF08–4–000 to staff activities involving
to the Commission to take action 5601, filed an application pursuant to the Williston Basin’s expansion project.
whether to suspend, accept or reject the section 7(c) of the Natural Gas Act for Now, as of the filing of Williston Basin’s
proposed rate. The data required to be a certificate of public convenience and application on March 12, 2008, the
filed for pipeline rates and tariff filings necessity to construct and operate new NEPA Pre-Filing Process for this project
is specified by 18 Code of Federal natural gas facilities, the Sheyenne has ended. From this time forward,
Regulations (CFR) Chapter I, Parts 341– Expansion Project, consisting of Williston Basin’s proceeding will be
348. compression, piping, and measurement conducted in Docket No. CP08–89–000,
facilities, located in various counties in as noted in the caption of this Notice.
Jurisdiction over oil pipelines as it
North Dakota, all as more fully set forth Pursuant to section 157.9 of the
relates to the establishment of rates or in the application which is on file with Commission’s rules, 18 CFR 157.9,
charges for the transportation of oil by the Commission and open for public within 90 days of this Notice the
pipeline or the establishment or inspection. This filing is available for Commission staff will either: complete
valuations for pipelines, was transferred review at the Commission in the Public its environmental assessment (EA) and
from the Interstate Commerce Reference Room or may be viewed on place it into the Commission’s public
Commission (ICC) to FERC, pursuant to the Commission’s Web site at http:// record (eLibrary) for this proceeding, or
sections 306 and 402 of the Department www.ferc.gov using the ‘‘eLibrary’’ link. issue a Notice of Schedule for
of Energy Organization Act (DOE Act). Enter the docket number excluding the Environmental Review. If a Notice of
5. Respondent Description: The last three digits in the docket number Schedule for Environmental Review is
respondent universe currently field to access the document. For issued, it will indicate, among other
comprises on average 200 respondents assistance, please contact FERC Online milestones, the anticipated date for the
subject to the Commission’s Support at Commission staff’s issuance of the final
FERCOnlineSupport@ferc.gov or toll environmental impact statement (FEIS)
jurisdiction. The Commission estimates
free at (866) 208–3676, or for TTY, or EA for this proposal. The filing of the
that it will receive annually on average
contact (202) 502–8659. EA in the Commission’s public record
3 filings per year per respondent Specifically, Williston Basin’s for this proceeding or the issuance of a
(includes tariff changes and rate change proposed Sheyenne Expansion Project Notice of Schedule for Environmental
filings). consists of: (i) The installation of a new Review will serve to notify Federal and
6. Estimated Burden: 6,600 total 1,590 horsepower turbine-driven State agencies of the timing for the
hours, 200 respondents (average per compressor unit, Unit #4, at the completion of all necessary reviews, and
year), 3 responses per respondent, and Bismarck Compressor Station, along the subsequent need to complete all
11 hours per response (average). with station piping modifications and a Federal authorizations within 90 days of
new gas cooler, located in Burleigh the date of issuance of the Commission
7. Estimated Cost Burden to County, North Dakota; (ii) construction
respondents: The estimated total cost to staff’s FEIS or EA.
of the new Steele Compressor Station, There are two ways to become
respondents is $401,026. (6,600 located in Kidder County, North Dakota, involved in the Commission’s review of
hours ÷ 2080 hours per year × $126,384.) consisting of one 1,750 horsepower this project. First, any person wishing to
Statutory Authority: Part I, Sections 1, 6, electric-driven reciprocating compressor obtain legal status by becoming a party
and 15 of the Interstate Commerce Act (ICA), unit; (iii) install a control valve at the to the proceedings for this project
(Pub. L. 337, 34 Stat. 384.) Sections 306 and Cleveland Junction and a suction should, on or before the below listed
402 of the Department of Energy control valve for the Cleveland comment date, file with the Federal
Organization Act, 42 U.S.C. 7155 and 7172, Compressor Station, located in Energy Regulatory Commission, 888
and Executive Order No. 12009. Stutsman County, North Dakota; and First Street, NE., Washington, DC 20426,
(iv) construction of an approximately a motion to intervene in accordance
Kimberly D. Bose,
6,400 foot, 8-inch diameter steel with the requirements of the
Secretary. transmission lateral, the Casselton Commission’s Rules of Practice and
[FR Doc. E8–6414 Filed 3–27–08; 8:45 am] Ethanol Plant Lateral, and a Procedure (18 CFR 385.214 or 385.211)
BILLING CODE 6717–01–P measurement station, located in Cass and the Regulations under the NGA (18
County, North Dakota. Williston Basin CFR 157.10). A person obtaining party
estimates the cost of construction to be status will be placed on the service list
$7,487,160. Williston Basin states that maintained by the Secretary of the
sroberts on PROD1PC70 with NOTICES

the project would increase firm capacity Commission and will receive copies of
into Williston Basin’s subsystem by 9.65 all documents filed by the applicant and
MMcf/d, with approximately 96 per by all other parties. A party must submit
cent of the additional capacity for the 14 copies of filings made with the
Tharaldson ethanol plant. Commission and must mail a copy to

VerDate Aug<31>2005 17:57 Mar 27, 2008 Jkt 214001 PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 E:\FR\FM\28MRN1.SGM 28MRN1
16662 Federal Register / Vol. 73, No. 61 / Friday, March 28, 2008 / Notices

the applicant and to every other party in DEPARTMENT OF ENERGY interconnect with and deliver natural
the proceeding. Only parties to the gas from the storage facility to the
proceeding can ask for court review of Federal Energy Regulatory Gulfstream and the FPL lateral
Commission orders in the proceeding. Commission pipelines;
[Docket No. CP08–13–000]
• Interconnection points with the
However, a person does not have to
Gulfstream pipeline at milepost (MP)
intervene in order to have comments 4.05 and with the FPL lateral at MP
considered. The second way to Floridian Natural Gas Storage
Company, LLC; Notice of Availability 4.18; and
participate is by filing with the • A metering and regulating station.
of the Draft Environmental Impact
Secretary of the Commission, as soon as Dependent upon Commission
Statement for the Floridian Natural Gas
possible, an original and two copies of approval, FGS proposes to have the
Storage Project
comments in support of or in opposition facilities installed and operational
to this project. The Commission will March 21, 2008. within 36 months of commencing
consider these comments in The staff of the Federal Energy construction; however, based on market
determining the appropriate action to be Regulatory Commission (FERC or conditions at the time of construction,
taken, but the filing of a comment alone Commission) has prepared this Draft the storage facility construction may be
will not serve to make the filer a party Environmental Impact Statement (EIS) separated into two phases.
to the proceeding. The Commission’s for the natural gas facilities proposed by The Draft EIS has been placed in the
rules require that persons filing the Floridian Natural Gas Storage public files of the FERC and is available
comments in opposition to the project Company, LLC (FGS) under the above- for public inspection at: Federal Energy
provide copies of their protests only to referenced docket. FGS’s proposed Regulatory Commission, Public
the party or parties directly involved in Floridian Natural Gas Storage Project Reference Room, 888 First Street, NE.,
the protest. (Project) would be located Room 2A, Washington, DC 20426, (202)
approximately two miles north of the 502–8371.
Persons who wish to comment only unincorporated municipality of A limited number of copies of the
on the environmental review of this Indiantown in Martin County, Florida. Draft EIS are available from the Public
project should submit an original and The Draft EIS was prepared to satisfy Reference Room identified above. In
two copies of their comments to the the requirements of the National addition, CD–ROM copies of the Draft
Secretary of the Commission. Environmental Policy Act. The FERC EIS have been mailed to affected
Environmental commenters will be staff concludes that the proposed landowners; various federal, state, and
placed on the Commission’s Project, with the appropriate mitigation local government agencies; elected
environmental mailing list, will receive measures as recommended, would have officials; environmental and public
copies of the environmental documents, limited adverse environmental impact. interest groups; Native American tribes;
and will be notified of meetings The U.S. Army Corps of Engineers, local libraries and newspapers;
associated with the Commission’s the U.S. Environmental Protection intervenors; and other individuals that
environmental review process. Agency, and the U.S. Fish and Wildlife expressed an interest in the proposed
Environmental commenters will not be Service are cooperating agencies for the Project. Hard-copies of the Draft EIS
required to serve copies of filed development of this EIS. A cooperating have also been mailed to those who
documents on all other parties. agency has jurisdiction by law or special requested that format during the scoping
However, the non-party commenters expertise with respect to any and comment periods for the proposed
environmental impact involved with the Project.
will not receive copies of all documents
proposal and is involved in the NEPA
filed by other parties or issued by the Comment Procedures and Public
analysis.
Commission (except for the mailing of The general purpose of the proposed Meetings
environmental documents issued by the Project is to respond to the growing Any person wishing to comment on
Commission) and will not have the right demand for natural gas and natural gas the Draft EIS may do so. To ensure
to seek court review of the infrastructure in the United States, and, consideration prior to a Commission
Commission’s final order. more specifically, in Florida. The decision on the proposal, it is important
Motions to intervene, protests and Project would enhance access to that the Commission receives your
comments may be filed electronically additional, competitively-priced comments before the date specified
via the Internet in lieu of paper; see, 18 supplies of natural gas by providing below. Please carefully follow these
CFR 385.2001(a)(1)(iii) and the liquefaction, storage, and vaporization instructions to ensure that your
instructions on the Commission’s Web services to customers in Florida and the comments are received and properly
site under the ‘‘e-Filing’’ link. The southeastern United States. recorded.
Commission strongly encourages The Draft EIS addresses the potential • Send an Original and two copies of
environmental effects of construction your comments to: Kimberly D. Bose,
electronic filings.
and operation of the facilities listed Secretary, Federal Energy Regulatory
Comment Date: April 11, 2008. below. FGS proposes to construct and Commission, 888 First Street, NE.,
Kimberly D. Bose, operate: Room 1A, Washington, DC 20002.
• An approximately 53.1 acre • Reference Docket No. CP08–13–
Secretary. liquefied natural gas storage facility; 000.
[FR Doc. E8–6312 Filed 3–27–08; 8:45 am] • An approximately 4-mile-long, 12- • Label one copy of the comments for
BILLING CODE 6717–01–P inch-diameter receiving pipeline to the attention of Gas Branch 3.
interconnect with and receive natural • Mail your comments so that they
sroberts on PROD1PC70 with NOTICES

gas from the Gulfstream and/or Florida will be received in Washington, DC on


Power & Light (FPL) lateral pipelines; or before May 5, 2008.
• An approximately 4-mile-long, 24- The Commission strongly encourages
inch-diameter sendout pipeline that electronic filing of any comments,
would parallel the 12-inch pipeline and interventions or protests to this

VerDate Aug<31>2005 17:57 Mar 27, 2008 Jkt 214001 PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 E:\FR\FM\28MRN1.SGM 28MRN1