Schedule 3: Erection Price Component

Name of Work: Strengthening Of Distribution


Network in Bih
II, Balance Work Of Phase-I for 17 districts and Phase-II-Part
under Special Plan (BRGF) Sch
Districts: East Champaran and West
Bidder's Name & Address:

NIT

Sr. No.

Description

33/11 KV Substation Works - Partly outdoor type substation ( 2x 10


MVA ) (with 33 KV outdoor type bay 2 nos. and 11 KV bay indoor
type 8 Nos.)

Civil works: Design, supply of all material, T&P, labour etc for the
following civil works complete as per TS
1

Soil Investigation & Contour Survey of Substation area as per


Technical Specification

Earth Filling & Site Levelling

Earth work in PSS site with ordinary soil (vide classification of soil
item - A) obtained from borrow pits free from logs, stumps, roots,
rubbish or any other ingredients likely to deteriorate or affect the
stability of the (1.00 meter filling considered size 60*40) site surface
including breaking the clods maximum to 60 mm. cube, placing the
earth in layers not exceeding 225 mm in loose thickness, rough
dressing including cost of cutting and removing shrubs, roots falling
in borrow area all complete as per approved design & technical
specification and as per direction of Engineer in Charge (payment will
be made as per actual requirement per cubic meter)

Antiweded treatment and stone spreading in switchyard area


excluding road, Cable trench, Drainage etc (Stone Spreading 6 inches
over 4 inches lean cement concrete layer as per technical
specification, approved desgn and drawing and as per directon of
Engineer in Charge. (payment will be made as per actual requirement
per Square meter)

Construction of Boundary Wall including Barbed Wire Fencing on MS


angle over the Boundary Wall and one Gate per Substation, including
Supply, Fabrication, Fixing, Painting all complete as per approved
Drawing & Technical Specification and as per directon of Engineer in
Charge in all 33/11 kV new sub-stations (payment will be made as
per actual requirement per meter)

Security fencing along with one switchyard gate per Substation as


per Technical specifications in all 33/11 kV new sub-stations - to
isolate electrical yard and as per directon of Engineer in Charge in all
33/11 kV new sub-stations (payment will be made as per actual
requirement per meter)

Design, engineering and construction of Control Room Building ( Hall


of control room building -16 x 8 Mtr. (size may vary as per availability
of land) and Guard room, store room, Battery room, Incharge room &
Wash room etc.) including supply of T&P, Labour, Cement,
Reinforcement Steel, Form Work, Excavation etc, all complete as per
Technical Specification and Approved Drawing and as per directon of
Engineer in Charge in all 33/11 kV new sub-stations (payment will be
made as per actual requirement per Sq. meter plinth area)

Design, engineering and construction of Cable Trench of 0.75 Mtr


wide , 1.0 Mtr. depth, precast RCC Trench Cover, Water stops, Brick
Work wherever required including supply of T&P, Labour, Cement,
Sand, Reinforcement Steel, Steel Angles, Flats, Form Work,
Excavation and providingcement plaster (1:4) including floating coat
of cement punning (1.5 MM) with clean pores sand etc, all complete
as per Technical Specification, approved Drawing and as per directon
of Engineer in Charge in all 33/11 kV new sub-stations (payment will
be made as per actual requirement per meter)

Design, engineering and construction of Drainage System in the


Substation premises including supply of T&P, Labour, Cement, ,
bricks, Form Work, Excavation etc, all complete as per design,
Technical Specification and Tender Drawings in all 33/11 kV new substationas as per directon of Engineer in Charge in all 33/11 kV new
sub-stations (payment will be made as per actual requirement per
meter)

Design, engineering and construction of PCC road, footpath including


supply of T and P, labour, brick, stone and stonechips, earth, and
excavation, compaction etc. all complete as per Technical
specifications.

width of PCC road 3.75 m- in M20, 200 mm Thick over compacted


WBM in three layers (Grade-I-100 mm thick, Grade-II-75 mm thick,
Grade - III - 75mm thick) etc as per PWD Specification and direction of
Engineer In Charge. (payment will be made as per actual requirement
per meter)

width of footpath 1.5 m-PCC in M15, 150 mm Thick over Brick on


edge soling over 75 mm thick local sand filling etc as per PWD
Specification and direction of Engineer In Charge. (payment will be
made as per actual requirement per meter)

10

Stone pitching over sloping including supply of stone and surface


preparation as per drawing and as per direction of Engineer in
charge.(payment will be made as per actual requirement per Sq.
meter)

11

Sinking of tube well and installation of motor operated submersible


pump of suitable capacity with 1000 ltr. Sintex or reputed make water
tank including GI Pipe(heavy duty) pipe line and sanitary fittings
complete in all respect for toilets , drinking water and providing
water tap near the power transformer for watering the earth pit as
per requirement. The depth of Tube-Well should be minimum 80 mtr.

12

Design, Engineering and construction of transformer foundation,


erection, filtration, testing and commissioning of 33/11 kV, 3 ph, 50
Hz, ONAN, Cu Wound, Outdoor Conventional type Power Transformer
along with transformer oil, Buchholtz relay, breather, OTI & WTI,
Marshalling Box, Conservator tank, oil level indicator, valves, 2 sets of
50x8 mm GS Neutral Earthing strips with braided conductor on
bushing end supported with insulators, OTI & WTI Indicators, Vent
explosion plug, control wiring / cabling, cable supporting tray on the
body, transformer wheels, bushing and extended copper connector
made of 50x10 mm copper flat for connection of 11 KV side bushing
with suitable bolts nuts and washers of Brass etc as required . 2 sets
of body earthing with 50x8 mm GS Strip as per TS , approved drawing
and direction of Engineer in Charge.

10 MVA with off load tap changer

13

Design, Engineering, providing and construction of transformer


support/foundation, erection, testing and commissioning of 100 KVA,
11/0.433 kV, 3 ph, 50 Hz, ONAN, aluminium would outdoor type
(three star rated) Station Transformer on double pole structure
alongwith HG Fuse set, AB Switch/ Isolator, LA, Earthing, etc complete
to complete the erection testing & commissioning of SST as required
as per specifications, approved drawing and direction of Engineer in
Charge complete in all respect.

14

Excavation, erection, cement concrete foundation, erection, testing


and commissioning of all type of structures i.e. Gantry/Swing
bus/isolator/CT/PT/PI/S.S.T structures etc. made of joist / channel /
angle / flat of different sections as per approved drawings and
direction of Engineer in Charge complete in all respect

15

Design, Engineering and construction of foundation , erection, testing


and commissioning of 36kV, 1250A, 25kA for 3 seconds, 3-ph,
Outdoor type Vacuum Circuit breaker along with 36kV, 1-Phase,
25kA for 3 seconds, 800-400-200/1-1-1 Amp.or 800-400-200/1-1,
Amps outdoor type Current Transformer along with junction box (1 no
junction box for 3 no of 1-phase CTs)], Jumpers, earthing, supporting
structures, maintenance platform, marshalling box, control & Power
cabling between VCB and indoor control panel and required
accessories complete as per approved drawings, technical
specifications and direction of Engineer in Charge and scope of the
work.

16

Design, Engineering providing and installation of ISMC 75 channel on


top of indoor trench, erection of panels on ISMC 75 channels, welding,
testing and commissioning of 33kV indoor Control & Relay panel
along with E/F & O/C relays, control and power supply cabling in
trench between field equipment and panels, Mimic Diagram,
Voltmeter, Ammeter, Annunciation Windows with annunciation relays
and other components etc as per approved drawings, technical
specifications and scope of the work for controlling complete in all
respect

33 kV feeder Panel (without diffirential relays) with DLMS (modem


compactible ) Trivector Static Energy Meter complete

33 kV Transformer Panel (with diffirential relays) with DLMS (modem


compactible ) Trivector Static Energy Meter complete

17

Design, Engineering and construction , Erection, testing and


commissioning of 36kV, 800 A, 25kA , 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work,(with and without Earth Switch)

18

Design, Engineering , Erection, testing and Commissioning of 30 kV,


10kA, 1-ph Station Class Lightening Arresters with mounting on
erected structures, jumpering from bus bar, earthing connection
using 50x6mm GS flat, hardware etc as required, as per approved
drawings, technical specifications and scope of the work complete in
all respect (1 Set= 3 Nos)

19

Design, Engineering, Erection, testing and Commissioning of 9kV,


10kA, 1-ph Station Class Lightening Arrester with mounting on
erected structure, jumpering from bus bar, earthing connection using
50x6mm GS flat, hardware, etc as required as per approved
drawings, technical specifications and scope of the work. (1 Set=3
Nos)

20

Design, Engineering and construction , Erection, testing and


Commissioning of 36 kV, 1-Phase, 33kV/110 volt, Single core outdoor
type Potential transformer along with junction box (1 no junction box
for 3 no of 1-phase PTs) including control and power supply cabling,
earthing connection using 50x6mm GS flat and required accessories
etc., complete as per as per approved drawings, technical
specifications and scope of the work,

21

Design, Engineering and construction , erection, wiring, testing and


commissioning of 12 kV, 1250 A/630 A , 25kA, 3-ph, indoor type
Vacuum Circuit breaker along with 12 kV, 1-Phase, 25kA for 3
seconds, 600-300-150/5-5 A and 1200-600-300/1-1-1 A CT , PT, and
along with control and relay panel consisting of Ammeter, volt-meter,
E/F, O/C ,diff. Relay and 3 Phase Energy meter & accessories
complete cabling between VCB and indoor control panel and required
accessories complete as per approved drawings, technical
specifications and scope of the work,

For Transformer Protection

For Feeder Protection

For Bus Coupler

22

Installation, initial charging, cabling, interconnection cabling, testing


and commissioning of 30 V, 100 AH Pb Acid battery on battery stand
made of teak wood duly painted with anti acid resistive paint, battery
insulators, inter-battery wiring using 30 sqm copper single core multi
strand cable, terminal connectors, & all other accessories and
connectors as per as per approved drawings, technical specifications
and scope of the work complete in all respect,

23

Design, engineering, construction , Installation, interconnection


cabling, testing and commissioning of 30V, 40 Amp. Float-Cum-Boost
Battery Charger with full wave rectification for 230 V, 1 phase, 50 Hz
AC Input Supply with DCDB (as per supply schedule) as per approved
drawings, technical specifications and scope of the work complete in
all respect

24

Design, engineering, construction , Installation, interconnection


cabling, testing and commissioning of 30V Supply DCDB as per
approved drawings, technical specifications and scope of the work &
supply schedule complete in all respect.

25

Design, engineering, construction , Installation, interconnection


cabling, testing and commissioning of 433V, ACDB as per approved
drawings, technical specifications and scope of the work,

25

Excavation, laying, welding, refilling, earthing & grounding of MS Flat


as per Approved drawing and erection of riser up to various
equipment/structures as per scope of the work, specifications and
approved drawings,

75 x 8 mm MS flat for ground mat

50 x 6 mm Galvanized GS flat (risers)

25 mm dia MS Rod 3 m long for earth mat

26

Excavation, erection, testing and commissioning of 40 mm dia., 3000


mm long GI pipe earth electrode by providing test link, RCC pit, RCC
cover, placed on GI frame, Charcoal & Salt in alternate layer as per
REC Specification and other accessories complete as per approved
drawings, technical specifications and scope of the work for power
transformer neutral, station transformer neutral, lightening arresters
direct earthing.

27

Erection, testing and commissioning of Bus Bar, jumpering and


Dropper (Zebra Conductor), by using all types of insulators, clamps
and connectors (by providing & using) etc. with all accessories
complete in all respect.

28

Erection, testing and commissioning of Sub-Station Lighting System


(External+Internal) with proper illumination levels complete for
Switchyard, Control Room building, Main gate and Sub station
boundary including all associated materials etc complete in all
respect as per applicable TS and approved drawing.

29

Erection, testing and commissioning of Fire Fighting Equipment as per


Supply Schedule

30

Design, engineering,Erection, testing and commissioning ofFully


automatic Capacitor bank with automatic control panel,
isolator,indoor type suitable Vacuum Circuit Breaker, mounting
structures, All types of cable (11 KV grade 185 sqmm, XLPE & control
cable etc.) & its accessories complete , earthing etc as required as
per technical specifications, approved drawings, scope of the works
of following capacities: (Banks in Muiltiple of 600 KVAR as per REC
Specification)

1200 KVAr

3600 KVAr

31

Erection, testing and commissioning of All types control cable and LT


power cable required for the commissioning of sub-station

32

Laying & termination, Testing and commissioning of 11 KV grade,


XLPE, power cable armored, aluminium conductor, stranded
complete in all respect as per Technical Specification.

1Cx 630 sqmm (Un -armoured)

3Cx 185 sqmm (armoured)

3Cx35 Sqmm (Un -armoured)

33

Design, Engineering and construction , Erection, testing and


commissioning of 12 kV, 630 A, 25 kA, 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work, (with and without earth Switch)

34

Erection, testing & commissioning of pipe bus by using IPS Aluminium


Pipe 65 mm. dia.with all types of Clamps and Connectors and
insulator as per TS & approved drawings
Sub Total

33/11 KV Substation Works - Partly outdoor type substation ( 2x 5


MVA ) (with 33 KV outdoor type bay 2 nos. and 11 KV bay indoor
type 4 Nos.)

Civil works: Design, supply of all material, T&P, labour etc for the
following civil works complete as per TS
1

Soil Investigation & Contour Survey of Substation area as per


Technical Specification

Earth Filling & Site Levelling

Earth work in PSS site with ordinary soil (vide classification of soil
item - A) obtained from borrow pits free from logs, stumps, roots,
rubbish or any other ingredients likely to deteriorate or affect the
stability of the (1.00 meter filling considered size 60*40) site surface
including breaking the clods maximum to 60 mm. cube, placing the
earth in layers not exceeding 225 mm in loose thickness, rough
dressing including cost of cutting and removing shrubs, roots falling
in borrow area all complete as per approved design & technical
specification and as per direction of Engineer in Charge (payment will
be made as per actual requirement per cubic meter)

Antiweded treatment and stone spreading in switchyard area


excluding road, Cable trench, Drainage etc (Stone Spreading 6 inches
over 4 inches lean cement concrete layer as per technical
specification, approved desgn and drawing and as per directon of
Engineer in Charge. (payment will be made as per actual requirement
per Square meter)

Construction of Boundary Wall including Barbed Wire Fencing on MS


angle over the Boundary Wall and one Gate per Substation, including
Supply, Fabrication, Fixing, Painting all complete as per approved
Drawing & Technical Specification and as per directon of Engineer in
Charge in all 33/11 kV new sub-stations (payment will be made as
per actual requirement per meter)

Security fencing along with one switchyard gate per Substation as


per Technical specifications in all 33/11 kV new sub-stations - to
isolate electrical yard and as per directon of Engineer in Charge in all
33/11 kV new sub-stations (payment will be made as per actual
requirement per meter)

Design, engineering and construction of Control Room Building ( Hall


of control room building -16 x 8 Mtr. (size may vary as per availability
of land) and Guard room, store room, Battery room, Incharge room &
Wash room etc.) including supply of T&P, Labour, Cement,
Reinforcement Steel, Form Work, Excavation etc, all complete as per
Technical Specification and Approved Drawing and as per directon of
Engineer in Charge in all 33/11 kV new sub-stations (payment will be
made as per actual requirement per Sq. meter plinth area)

Design, engineering and construction of Cable Trench of 0.75 Mtr


wide , 1.0 Mtr. depth, precast RCC Trench Cover, Water stops, Brick
Work wherever required including supply of T&P, Labour, Cement,
Sand, Reinforcement Steel, Steel Angles, Flats, Form Work,
Excavation and providingcement plaster (1:4) including floating coat
of cement punning (1.5 MM) with clean pores sand etc, all complete
as per Technical Specification, approved Drawing and as per directon
of Engineer in Charge in all 33/11 kV new sub-stations (payment will
be made as per actual requirement per meter)

Design, engineering and construction of Drainage System in the


Substation premises including supply of T&P, Labour, Cement, ,
bricks, Form Work, Excavation etc, all complete as per design,
Technical Specification and Tender Drawings in all 33/11 kV new substationas as per directon of Engineer in Charge in all 33/11 kV new
sub-stations (payment will be made as per actual requirement per
meter)

Design, engineering and construction of PCC road, footpath including


supply of T and P, labour, brick, stone and stonechips, earth, and
excavation, compaction etc. all complete as per Technical
specifications.

width of PCC road 3.75 m- in M20, 200 mm Thick over compacted


WBM in three layers (Grade-I-100 mm thick, Grade-II-75 mm thick,
Grade - III - 75mm thick) etc as per PWD Specification and direction of
Engineer In Charge. (payment will be made as per actual requirement
per meter)

width of footpath 1.5 m-PCC in M15, 150 mm Thick over Brick on


edge soling over 75 mm thick local sand filling etc as per PWD
Specification and direction of Engineer In Charge. (payment will be
made as per actual requirement per meter)

10

Stone pitching over sloping including supply of stone and surface


preparation as per drawing and as per direction of Engineer in
charge.(payment will be made as per actual requirement per Sq.
meter)

11

Sinking of tube well and installation of motor operated submersible


pump of suitable capacity with 1000 ltr. Sintex or reputed make water
tank including GI Pipe(heavy duty) pipe line and sanitary fittings
complete in all respect for toilets , drinking water and providing
water tap near the power transformer for watering the earth pit as
per requirement. The depth of Tube-Well should be minimum 80 mtr.

12

Design, Engineering and construction of transformer foundation,


erection, filtration, testing and commissioning of 33/11 kV, 3 ph, 50
Hz, ONAN, Cu Wound, Outdoor Conventional type Power Transformer
along with transformer oil, Buchholtz relay, breather, OTI & WTI,
Marshalling Box, Conservator tank, oil level indicator, valves, 2 sets of
50x8 mm GS Neutral Earthing strips with braided conductor on
bushing end supported with insulators, OTI & WTI Indicators, Vent
explosion plug, control wiring / cabling, cable supporting tray on the
body, transformer wheels, bushing and extended copper connector
made of 50x10 mm copper flat for connection of 11 KV side bushing
with suitable bolts nuts and washers of Brass etc as required . 2 sets
of body earthing with 50x8 mm GS Strip as per TS and as per
direction of Engineer in Charge

5 MVA with off load tap changer

13

Design, Engineering, providing and construction of transformer


support/foundation, erection, testing and commissioning of 100 KVA,
11/0.433 kV, 3 ph, 50 Hz, ONAN, aluminium would outdoor type
(three star rated) Station Transformer on double pole structure
alongwith HG Fuse set, AB Switch/ Isolator, LA, Earthing, etc complete
to complete the erection testing & commissioning of SST as required
as per specifications & drawings complete in all respect.as per
direction of Engineer in Charge

14

Excavation, erection, cement concrete foundation, erection, testing


and commissioning of all type of structures i.e. Gantry/Swing
bus/isolator/CT/PT/PI/S.S.T structures etc. made of joist / channel /
angle / flat of different sections as per approved drawings complete
in all respect as per direction of Engineer in Charge

15

Design, Engineering and construction of foundation , erection, testing


and commissioning of 36kV, 1250A, 25kA for 3 seconds, 3-ph,
Outdoor type Vacuum Circuit breaker along with 36kV, 1-Phase,
25kA for 3 seconds, 800-400-200/1-1-1 Amp.or 800-400-200/1-1,
Amps outdoor type Current Transformer along with junction box (1 no
junction box for 3 no of 1-phase CTs)], Jumpers, earthing, supporting
structures, maintenance platform, marshalling box, control & Power
cabling between VCB and indoor control panel and required
accessories complete as per approved drawings, technical
specifications and scope of the work. as per direction of Engineer in
Charge

16

Design, Engineering providing and installation of ISMC 75 channel on


top of indoor trench, erection of panels on ISMC 75 channels, welding,
testing and commissioning of 33kV indoor Control & Relay panel
along with E/F & O/C relays, control and power supply cabling in
trench between field equipment and panels, Mimic Diagram,
Voltmeter, Ammeter, Annunciation Windows with annunciation relays
and other components etc as per approved drawings, technical
specifications and scope of the work for controlling complete in all
respect

33 kV feeder Panel (without diffirential relays) with DLMS (modem


compactible ) Trivector Static Energy Meter complete

33 kV Transformer Panel (with diffirential relays) with DLMS (modem


compactible ) Trivector Static Energy Meter complete

17

Design, Engineering and construction , Erection, testing and


commissioning of 36kV, 800 A, 25kA , 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work,(with and without Earth Switch)

18

Design, Engineering , Erection, testing and Commissioning of 30 kV,


10kA, 1-ph Station Class Lightening Arresters with mounting on
erected structures, jumpering from bus bar, earthing connection
using 50x6mm GS flat, hardware etc as required, as per approved
drawings, technical specifications and scope of the work complete in
all respect (1 Set= 3 Nos)

19

Design, Engineering, Erection, testing and Commissioning of 9kV,


10kA, 1-ph Station Class Lightening Arrester with mounting on
erected structure, jumpering from bus bar, earthing connection using
50x6mm GS flat, hardware, etc as required as per approved
drawings, technical specifications and scope of the work. (1 Set=3
Nos)

20

Design, Engineering and construction , Erection, testing and


Commissioning of 36 kV, 1-Phase, 33kV/110 volt, Single core outdoor
type Potential transformer along with junction box (1 no junction box
for 3 no of 1-phase PTs) including control and power supply cabling,
earthing connection using 50x6mm GS flat and required accessories
etc., complete as per as per approved drawings, technical
specifications and scope of the work,

21

Design, Engineering and construction , erection, wiring, testing and


commissioning of 12 kV, 1250 A/630 A , 25kA, 3-ph, indoor type
Vacuum Circuit breaker along with 12 kV, 1-Phase, 25kA for 3
seconds, 600-300-150/5-5 A and 1200-600-300/1-1-1 A CT , PT, and
along with control and relay panel consisting of Ammeter, volt-meter,
E/F, O/C ,diff. Relay and 3 Phase Energy meter & accessories
complete cabling between VCB and indoor control panel and required
accessories complete as per approved drawings, technical
specifications and scope of the work,

For Transformer Protection

For Feeder Protection

For Bus Coupler

22

Installation, initial charging, cabling, interconnection cabling, testing


and commissioning of 30 V, 100 AH Pb Acid battery on battery stand
made of teak wood duly painted with anti acid resistive paint, battery
insulators, inter-battery wiring using 30 sqm copper single core multi
strand cable, terminal connectors, & all other accessories and
connectors as per as per approved drawings, technical specifications
and scope of the work complete in all respect,

23

Design, engineering, construction , Installation, interconnection


cabling, testing and commissioning of 30V, 40 Amp. Float-Cum-Boost
Battery Charger with full wave rectification for 230 V, 1 phase, 50 Hz
AC Input Supply with DCDB (as per supply schedule) as per approved
drawings, technical specifications and scope of the work complete in
all respect

24

Design, engineering, construction , Installation, interconnection


cabling, testing and commissioning of 30V Supply DCDB as per
approved drawings, technical specifications and scope of the work &
supply schedule complete in all respect.

25

Design, engineering, construction , Installation, interconnection


cabling, testing and commissioning of 433V, ACDB as per approved
drawings, technical specifications and scope of the work,

25

Excavation, laying, welding, refilling, earthing & grounding of MS Flat


as per Approved drawing and erection of riser up to various
equipment/structures as per scope of the work, specifications and
approved drawings,

75 x 8 mm MS flat for ground mat

50 x 6 mm Galvanized GS flat (risers)

25 mm dia MS Rod 3 m long for earth mat

26

Excavation, erection, testing and commissioning of 40 mm dia., 3000


mm long GI pipe earth electrode by providing test link, RCC pit, RCC
cover, placed on GI frame, Charcoal & Salt in alternate layer as per
REC Specification and other accessories complete as per approved
drawings, technical specifications and scope of the work for power
transformer neutral, station transformer neutral, lightening arresters
direct earthing.

27

Erection, testing and commissioning of Bus Bar, jumpering and


Dropper (Zebra Conductor), by using all types of insulators, clamps
and connectors etc. with all accessories complete in all respect.

28

Erection, testing and commissioning of Sub-Station Lighting System


(External+Internal) with proper illumination levels complete for
Switchyard, Control Room building, Main gate and Sub station
boundary including all associated materials etc complete in all
respect as per applicable TS and approved drawing.

29

Erection, testing and commissioning of Fire Fighting Equipment as per


Supply Schedule

30

Design, engineering,Erection, testing and commissioning ofFully


automatic Capacitor bank with automatic control panel,
isolator,indoor type suitable Vacuum Circuit Breaker, mounting
structures, All types of cable (11 KV grade 185 sqmm, XLPE & control
cable etc.) & its accessories complete , earthing etc as required as
per technical specifications, approved drawings, scope of the works
of following capacities: (Banks in Muiltiple of 600 KVAR as per REC
Specification)

1200 KVAr

3600 KVAr

31

Erection, testing and commissioning of All types control cable and LT


power cable required for the commissioning of sub-station

32

Laying & termination, Testing and commissioning of 11 KV grade,


XLPE, power cable armored, aluminium conductor, stranded
complete in all respect as per Technical Specification.

1Cx 630 sqmm (Un -armoured)

3Cx 185 sqmm (armoured)

3Cx35 Sqmm (Un -armoured)

33

Design, Engineering and construction , Erection, testing and


commissioning of 12 kV, 630 A, 25 kA, 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work, (with and without earth Switch)

34

Erection, testing & commissioning of pipe bus by using IPS Aluminium


Pipe 65 mm. dia.with all types of Clamps and Connectors and
insulator as per TS & approved drawings
Sub Total

Additional/Augmentation of Power Transformers

Civil works: Design, supply of all material, T&P, labour etc for the
following civil works complete as per TS

Earth Filling & Site Levelling

Gravel filling in switchyard area excluding road and footpath as per


TS.

Design, engineering and construction of Cable Trench of 0.75 Mtr


wide , 1.0 Mtr. depth, precast RCC Trench Cover, Water stops, Brick
Work wherever required including supply of T&P, Labour, Cement,
Sand, Reinforcement Steel, Steel Angles, Flats, Form Work,
Excavation and providingcement plaster (1:4) including floating coat
of cement punning (1.5 MM) with clean pores sand etc, all complete
as per Technical Specification, approved Drawing and as per direction
of Engineer in Charge. (Payment will be made as per actual
requirement per Mtr.)

Design, engineering and construction of Drainage System in the


Substation premises including supply of T&P, Labour, Cement, ,
bricks, Form Work, Excavation etc, all complete as per design,
Technical Specification and Tender Drawings in all 33/11 kV new substation as per direction of Engineer in Charge. (Payment will be made
as per actual requirement per Mtr.)

Substation works

Design, Engineering and construction of transformer foundation,


erection, filtration, testing and commissioning of 33/11 kV, 3 ph, 50
Hz, ONAN, Cu Wound, Outdoor Conventional type Power Transformer
along with transformer oil , Buchholtz relay, breather, OTI & WTI,
Marshalling Box, Conservator tank, oil level indicator, valves, 2 sets of
50x8 mm GS Neutral Earthing strips with braided conductor on
bushing end supported with insulators, OTI & WTI Indicators, Vent
explosion plug, control wiring / cabling, cable supporting tray on the
body, transformer wheels, bushing and extended copper connector
made of 50x10 mm copper flat for connection of 11 KV side bushing
with suitable bolts nuts and washers of Brass etc as required . 2 sets
of body earthing with 50x8 mm GS Strip as per TS and as per
direction of Engineer in Charge.

5 MVA

10 MVA

Dismantaling, Transportation from existing site to proposed site,


Installation, Erection, Testing and Commisiioning of 5 MVA released
Power Transformers with suitable Clamps, Connectors, bolts nuts
and washers of Brass etc as required with 2 sets each of body &
neutral earthing with 50x8 mm GS Strip as per TS completely
required for commissioning.

Modification of existing Power Transformer foundation required for


installation and commissionig of augmented 5/10 MVA Power
Transformers completely as per TS. (As per requirement)

Design, Engineering , erection, testing and commissioning of 36kV,


1250A, 25kA for 3 seconds, 3-ph, Outdoor type Vacuum Circuit
breaker along with 36kV, 1-Phase, 25kA for 3 seconds, 800-400200/1-1-1 Amp.or 800-400-200/1-1, Amps outdoor type Current
Transformer along with junction box (1 no junction box for 3 no of 1phase CTs)], Jumpers, earthing, supporting structures, maintenance
platform, marshalling box, control & Power cabling between VCB and
indoor control panel and required accessories complete as per
approved drawings, technical specifications, scope of the work and as
per direction of Engineer in Charge. (For released Power
Transformers)

Excavation, erection, cement concrete foundation, erection, testing


and commissioning of all type of structures i.e. Swing
bus/isolator/VCB/CT/PT/PI structure etc. made of joist / channel /
angle / flat of different sections as per approved drawings

10

Design, Engineering and construction of VCB foundation , erection,


testing and commissioning of 36kV, 1250A, 25kA for 3 seconds, 3-ph,
Outdoor type Vacuum Circuit breaker along with 36kV, 1-Phase,
25kA for 3 seconds, 800-400-200/1-1-1 Amp.or 800-400-200/1-1,
Amps outdoor type Current Transformer along with junction box (1 no
junction box for 3 no of 1-phase CTs)], Jumpers, earthing, supporting
structures, maintenance platform, marshalling box, control & Power
cabling between VCB and indoor control panel and required
accessories complete as per approved drawings, technical
specifications and scope of the work.

11

Design, Engineering providing and installation of ISMC 75 channel on


top of indoor trench, erection of panels on ISMC 75 channels, welding,
testing and commissioning of 33kV indoor Control & Relay panel
along with E/F & O/C relays, control and power supply cabling in
trench between field equipment and panels, Mimic Diagram,
Voltmeter, Ammeter, Annunciation Windows with annunciation relays
and other components etc as per approved drawings, technical
specifications and scope of the work for controlling:

33 kV Transformer VCB (with diffirential relays)

12

Design, Engineering and construction , Erection, testing and


commissioning of 36kV,800 A, 25kA, 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work, (with and without Earth Switch)

13

Design, Engineering and construction , erection, testing and


commissioning of 12kV, 1250A, 25kA for 3 seconds, 3-ph, Outdoor
type Vacuum Circuit breaker along with 12kV, 1-Phase, 25kA for 3
seconds, 1200-600-300/1-1-1 Amp.(having 3 secondary core),
outdoor type Current Transformer along with junction box (1 no
junction box for 3 no of 1-phase CTs)], Jumpers, earthing, supporting
structures, maintenance platform, marshalling box, control & Power
cabling between VCB and indoor control panel and required
accessories complete as per approved drawings, technical
specifications and scope of the work.

14

12 KV Control & Relay panel for 12 KV VCB (suitable for 30 V DC


tripping/closing coil and associated control Circuitry) alongwith, ElF &
O/C relays, Static energy meter (class 0.5 with communication port) ,
Mimic Diagram, Voltmete, Ammeter, etc complete as per REC

15

Excavation, laying, welding, refilling, earthing & grounding of


conductor as per Approved Electrical Layout for each sub station
with ten no of treated 40mm dia, 3000 mm long GI pipe (Medium
gauge) earth electode by providing test link, RCC pit, RCC cover,
placed on GI frame, Charcoal & Salt in alternate layer as per REC
Specification and other accessories complete as per approved
drawings, technical specifications and scope of the work for power
transformer neutral, station transformer neutral up to various
equipment/structures as per scope of the work, specifications and
approved drawings etc (treated earthing)

16

Erection, testing and commissioning of Bus Bar, jumpering and


Dropper (Zebra conductor), by using all types of insulators, clamps
and connectors etc. with all accessories complete in all respect.

17

Design, Engineering and construction , Erection, testing and


commissioning of 12 kV, 630 A, 25 kA , 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work,

18

Dismentling of existing dismentled materials and devolution of the


dismantled materials including storage, handling, insurance, loading,
unloading, transportation to store of Utility as per the direction of
Engineer-in-charge with propoer accounting as per the inventory.
Sub Total

Erection, testing commissioning of NEW 33 KV Line on rail pole


with ACSR wolf Conductor

Survey, route alignment & pole spotting, preparation of survey report


after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 33 KV


overhead line (by installing danger board and barbed Wires on
DP/TP/FP Structures) and pole numbering as per scope of work,
approved drawings and Technical specifications:

13 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat
Al-Paint and 1/6th part of the Rail pole from bottom with Black
enamel paint cf Reputed make) including fixing of (RCC Base Plate
of size 500x500x100 mm./Stone Base Plate of Size 450x450x50mm)
with cement concreting foundation and top mopping (1:4:8) (0.65
cmt per pole).

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Wolf Conductor


including mid point jointing sleeves fixing and jumpering, binding of
conductor with pin insulator and disc insulator by providing and
using Aluminium tape at DP and all cut-points and angle points by
using PG Clamp etc. including fixing & fitting of Danzer board, barbed
wire at DP/TP/FP as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 33 KV porcelain Disc insulator


assembly (1 set DI= 3 nos DI) 70 KN along with HW fittings complete
by providing Al. Tape in all respect as per TS & approved drawings.

Erection, Testing and Commissioning of 33 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

a)

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire for
connections complete in all respect and approved drawing as per TS.

b)

Excavation, Erecting, Testing and Commissioning of Coil type


untreated earthing by providing & using 8 SWG GI wire for
connections complete in all respect and approved drawing as per TS.

Excavation, Foundation and erection of galvanised Stay Set complete


in all respect as per supply schedule by providing 0.2 cum cement
concrete (1:4:8) PCC foundations as per scope of work, specifications
and approved drawings.

Design, Engineering and construction , Erection, testing and


commissioning of 36kV, 800 A, 25kA , 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work,(with and without Earth Switch)
Sub-Total

Erection, testing commissioning of Reconductoring of 33 KV Line


By ACSR Wolf Conductorr

Survey, route alignment & pole spotting, preparation of survey report ,


Inventory after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 33 KV


overhead line by providing and installing danger board and barbed Wires on
DP/TP/FP Structures and pole numbering as per scope of work, approved
drawings and Technical specifications:

11 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat AlPaint and 1/6th part of the Rail pole from bottom with Black enamel paint cf
Reputed make) including fixing of (RCC Base Plate of size 500x500x100
mm./Stone Base Plate of Size 450x450x50mm) with cement concreting
foundation and top mopping (1:4:8) (0.54 cmt per pole).

13 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat AlPaint and 1/6th part of the Rail pole from bottom with Black enamel paint cf
Reputed make) including fixing of RCC/Stone Base plate (500X500X100
mm) with cement concreting foundation and top mopping (1:4:8) (0.65 cmt
per pole).

PSC Pole 9 Mtr 400 Kg including fixing of RCC Base plate (500x500x100
mm) with brick blast or boulder refilling (50% depth of pole pit) and
ramming foundation with excavated soil with pouring water as required as
per scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection of galvanised fabricated steel materials- Channels, angle, flats for


over head line structures by providing and using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Wolf Conductor including mid


point jointing sleeves fixing and jumpering, binding of conductor with pin
insulator and disc insulator by providing and using Aluminium tape at DP
and all cut-points and angle points by using PG Clamp etc. as required (1
CKm= 1 km line length of 3 phase conductor)

Erection, testing and commissioning of 33 KV porcelain Disc insulator 70 KN


along with HW fittings complete in all respect as per TS & approved
drawings.

Erection, Testing and Commissioning of 33 KV porcelain Pin Insulators with


GI PIN complete in all respect as per TS & approved drawings.

Earthing

a)

Excavation, Erecting, Testing and Commissioning of Pipe type untreated


earthing by providing & using 8 SWG GI wire for connections complete in all
respect and approved drawing as per TS.

b)

Excavation, Erecting, Testing and Commissioning of Coil type untreated


earthing by providing & using 8 SWG GI wire for connections complete in
all respect and approved drawing as per TS.

Excavation, Foundation and erection of galvanised Stay Set complete in all


respect as per supply schedule by providing 0.2 cum cement concrete
(1:4:8) PCC foundations as per scope of work, specifications and approved
drawings.

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
pole and other dismentled material to the store of Utility with propoer
accounting as per the inventory.

Sub Total

33 KV Bay Extension
1

Excavation, erection, cement concrete foundation, erection, testing


and commissioning of all type of structures i.e. Gantry/Swing
bus/isolator/VCB/CT/PT/PI structures etc. made of Lattice structures
of equal angles sections, flat as per approved drawings.

Design, Engineering and construction , erection, testing and


commissioning of 36kV, 1250A, 25kA for 3 seconds, 3-ph, Outdoor
type Vacuum Circuit breaker along with 36kV, 1-Phase, 25kA for 3
seconds, 800-400-200/1-1-1 Amp. outdoor type Current Transformer
along with junction box (1 no junction box for 3 no of 1-phase CTs)],
Jumpers, earthing, supporting structures, maintenance platform,
marshalling box, control & Power cabling between VCB and indoor
control panel and required accessories complete as per approved
drawings, technical specifications and scope of the work.

Design, Engineering providing and installation of ISMC 75 channel on


top of indoor trench, erection of panels on ISMC 75 channels, welding,
testing and commissioning of 33kV indoor Control & Relay panel
along with E/F & O/C relays, control and power supply cabling in
trench between field equipment and panels, Mimic Diagram,
Voltmeter, Ammeter, Annunciation Windows with annunciation relays
and other components etc as per approved drawings, technical
specifications and scope of the work for controlling:

3a

33 kV VCB (without diffirential relays) and DLMS Trivector Static


Energy Meter complete.
Design, Engineering and construction , Erection, testing and
commissioning of 36kV, 800 A, 25kA 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work,

Erection, testing and commissioning of Bus Bar, jumpering and


Dropper (Zebra Conductor), by using all types of insulators, clamps
and connectors, Al tape etc. with all accessories complete in all
respect.

Design, Engineeringi , Erection, testing and Commissioning of 30 kV,


10kA, 1-ph Station Class Lightening Arresters with mounting on
erected structures, jumpering from bus bar, earthing connection
using 50x6mm GS flat, hardware etc as required, as per approved
drawings, technical specifications and scope of the work,

Excavation, laying, welding, refilling, earthing & grounding of MS Flat


as per Approved drawing and erection of riser up to various
equipment/structures as per scope of the work, specifications and
approved drawings,

Excavation, erection, testing and commissioning of 40 mm dia., 3000


mm long GI pipe earth electrode by providing test link, RCC pit, RCC
cover, placed on GI frame, Charcoal & Salt in alternate layer as per
REC Specification and other accessories complete as per approved
drawings, technical specifications and scope of the work for power
transformer neutral, station transformer neutral, lightening arresters
direct earthing.

Design, engineering and construction of Cable Trench of 0.75 Mtr


wide , 1.0 Mtr. depth, precast RCC Trench Cover, Water stops, Brick
Work wherever required including supply of T&P, Labour, Cement,
Sand, Reinforcement Steel, Steel Angles, Flats, Form Work,
Excavation and providingcement plaster (1:4) including floating coat
of cement punning (1.5 MM) with clean pores sand etc, all complete
as per Technical Specification, approved Drawing and as per direction
of Engineer In Charge (payment will be made as per actual
requirement per Mtr.)
Sub Total

33 KV Railway Crossing (Double Circuit)

Laying,termination, Erection, Testing & commissioning of 33 KV


grade 3-core 400 Sqmm XLPE power cable (Double Circuit) for
underground Railway Crossing including using jointing/Termination
Kit, GI pipe, CI pipe, clamps, conectors bolts, nuts, fixing and fitting
of barbed wire, pipe earthing etc. with all accessories complete in all
respect as per TS/ approved drawing

Sub Total
33 KV Metering System
Erection, testing, commissioning of 33 kV Metering system along with
DLMS Static Trivector Energy Meter alongwith combined CT- PT
metering unit 33KV/110 V, CT ratio-800-400/1A with bimetalic
connectors and DLMS Static Trivector feeder meter with
communication port of 33 KV/110 v of CT ratio-400/1 A with 12cx2.5
Sqmm Control Cable complete alongwith earthing and all associated
accessories complete in all respest
Sub Total

Construction of Single Circuit 11 KV Line with ACSR Dog


Conductor on Rail Pole :

Survey, route alignment & pole spotting, preparation of survey report


after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by installing danger board and barbed wire on DP/TP/FP
structure and pole numbering as per scope of work, approved
drawings and technical specifications:

13 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat
Al-Paint and 1/6th part of the Rail pole from bottom with Black
enamel paint cf Reputed make) including fixing of (RCC Base Plate
of size 500x500x100 mm./Stone Base Plate of Size 450x450x50mm)
with cement concreting foundation and top mopping (1:4:8) (0.65
cmt per pole).

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Dog Conductor


including mid point jointing sleeves fixing and jumpering by using PG
clamp, binding of conductor (by providing & using Al. tape) with pin
insulator and disc insulator at DP and all cut-points and angle points
etc. as required (1 CKm= 1 km line length of 3 phase conductor)

Erection, testing and commissioning of 11 KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

a)

b)

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation and erection of galvanised Stay Set as per supply
schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Erection, Testing and Commissioning of 12 kV AB Switch along with
Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications, scope of works and
approved drawings
Sub-Total

11 KV Lines on 13 M 52 Kg /M Rail Pole with ACSR Dog Conductor


(Double Circuit)

Survey, route alignment & pole spotting, preparation of survey report


after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by installing danger board and barbed wire on DP/TP/FP
structure and pole numbering as per scope of work, approved
drawings and technical specifications:

13 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat
Al-Paint and 1/6th part of the Rail pole from bottom with Black
enamel paint cf Reputed make) including fixing of (RCC Base Plate
of size 500x500x100 mm./Stone Base Plate of Size 450x450x50mm)
with cement concreting foundation and top mopping (1:4:8) (0.65
cmt per pole).

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Dog Conductor


including mid point jointing sleeves fixing and jumpering, binding of
conductor with pin insulator and disc insulator by providing and
using Aluminium tape at DP and all cut-points and angle points by
using PG Clamp etc. including fixing & fitting of Danzer board, barbed
wire at DP/TP/FP as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11 KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

a)

b)

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation and erection of galvanised Stay Set as per supply
schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Construction of Single Circuit 11 KV Line with ACSR Dog Conductor
on 9 M, 400 Kg PSC Pole :

Survey, route alignment & pole spotting, preparation of survey report


after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by installing danger board and barbed wire on DP/TP/FP
structure and pole numbering as per scope of work, approved
drawings and technical specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Dog Conductor


including mid point jointing sleeves fixing and jumpering, binding of
conductor with pin insulator and disc insulator by providing and
using Aluminium tape at DP and all cut-points and angle points by
using PG Clamp etc. including fixing & fitting of Danzer board, barbed
wire at DP/TP/FP as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11 KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.

Erection, Testing and Commissioning of 12 kV AB Switch along with


Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications, scope of works and
approved drawings
Sub-Total

11 KV Lines on 9 mtr./400 kgs PSC pole with ACSR Rabbit conductor

Survey, route alignment & pole spotting, preparation of survey report


after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by installing danger board and barbed wire on DP/TP/FP
structure and pole numbering as per scope of work, approved
drawings and technical specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Rabbit Conductor


including mid point jointing sleeves fixing and jumpering, binding of
conductor with pin insulator and disc insulator by providing and
using Aluminium tape at DP and all cut-points and angle points by
using PG Clamp etc. including fixing & fitting of Danzer board, barbed
wire at DP/TP/FP as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11 KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation and erection of galvanised Stay Set as per supply
schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Erection, Testing and Commissioning of 12 kV AB Switch along with
Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications, scope of works and
approved drawings
Sub-Total

11 KV Lines on 8 m/ 200 kgs PSC pole with Rabbit conductor

Survey, route alignment & pole spotting, preparation of survey report


after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by installing danger board and barbed wire on DP/TP/FP
structure and pole numbering as per scope of work, approved
drawings and technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Rabbit Conductor


including mid point jointing sleeves fixing and jumpering, binding of
conductor with pin insulator and disc insulator by providing and
using Aluminium tape at DP and all cut-points and angle points by
using PG Clamp etc. including fixing & fitting of Danzer board, barbed
wire at DP/TP/FP as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11 KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation and erection of galvanised Stay Set as per supply
schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Erection, Testing and Commissioning of 12 kV AB Switch along with
Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications, scope of works and
approved drawings
Sub-Total

11 KV Lines on 8 mtr./ 200 kgs PSC pole with ACSR Weasel


conductor

Survey, route alignment & pole spotting, preparation of survey report


after approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by installing danger board and barbed wire on DP/TP/FP
structure and pole numbering as per scope of work, approved
drawings and technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Weasel Conductor


including mid point jointing sleeves fixing and jumpering, binding of
conductor with pin insulator and disc insulator by providing and
using Aluminium tape at DP and all cut-points and angle points by
using PG Clamp etc. including fixing & fitting of Danzer board, barbed
wire at DP/TP/FP as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11 KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.

Erection, Testing and Commissioning of 12 kV AB Switch along with


Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications, scope of works and
approved drawings

O
1

Sub-Total
Reconductoring of 11 KV Line With ACSR Dog Conductor on
Rail pole
Survey, route alignment & pole spotting, preparation of survey report
, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by providing and installing danger board and barbed
Wires on DP/TP/FP Structures and pole numbering as per scope of
work, approved drawings and Technical specifications:

13 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat
Al-Paint and 1/6th part of the Rail pole from bottom with Black
enamel paint cf Reputed make) including fixing of RCC/Stone Base
plate (500X500X100 mm) with cement concreting foundation and top
mopping (1:4:8) (0.65 cmt per pole).

11 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat
Al-Paint and 1/6th part of the Rail pole from bottom with Black
enamel paint cf Reputed make) including fixing of (RCC Base Plate
of size 500x500x100 mm./Stone Base Plate of Size 450x450x50mm)
with cement concreting foundation and top mopping (1:4:8) (0.54
cmt per pole).

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Dog Conductor


including mid point jointing sleeves fixing and jumpering, binding of
conductor with pin insulator and disc insulator by providing and
using Aluminium tape at DP and all cut-points and angle points by
using PG Clamp etc. including fixing & fitting of Danzer board, barbed
wire at DP/TP/FP as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

a)

b)

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.

Excavation, Foundation and erection of galvanised Stay Set complete


in all respect as per supply schedule by providing 0.2 cum cement
concrete (1:4:8) PCC foundations as per scope of work, specifications
and approved drawings.

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
pole and other dismentled material to the store of Utility with propoer
accounting as per the inventory.

Sub-Total
Reconductoring of 11 KV Line With ACSR Dog Conductor on 9
mtr. 400 kg PSC pole

Survey, route alignment & pole spotting, preparation of survey report


, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by providing and installing danger board and barbed
Wires on DP/TP/FP Structures and pole numbering as per scope of
work, approved drawings and Technical specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm)) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Dog Conductor


including mid point jointing sleeves fixing and jumpering, binding (by
providing & using Al. tape) of conductor with pin insulator and disc
insulator at DP and all cut-points and angle points by providing and
using PG Clamp etc. as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

a)

b)

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.

Excavation, Foundation and erection of galvanised Stay Set complete


in all respect as per supply schedule by providing 0.2 cum cement
concrete (1:4:8) PCC foundations as per scope of work, specifications
and approved drawings.

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
pole and other dismentled material to the store of Utility with propoer
accounting as per the inventory.

Q
1

Sub-Total
Reconductoring of 11 KV Line With ACSR Rabbit Conductor on
PSC Pole
Survey, route alignment & pole spotting, preparation of survey report
, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by providing and installing danger board and barbed
Wires on DP/TP/FP Structures and pole numbering as per scope of
work, approved drawings and Technical specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

PSC Pole 8 Mtr 200 Kg including fixing of RCC Base plate


(500x500x100 mm) with brick blast or boulder refilling (50% depth of
pole pit) and ramming foundation with excavated soil with pouring
water as required as per scope of work , approved drawing &
technical specification. Fixing of Danger Board on DP/TP/FP & Pole
numbering.

Erection of galvanised fabricated steel materials- Channels, angle,


flats for over head line structures by using Bolts, Nuts, Washer etc as
per approved drawing and TS

Erection, testing and commissioning of ACSR Rabbit Conductor


including mid point jointing sleeves fixing and jumpering, binding (by
providing & using Al. tape) of conductor with pin insulator and disc
insulator at DP and all cut-points and angle points by providing and
using PG Clamp etc. as required (1 CKm= 1 km line length of 3 phase
conductor)

Erection, testing and commissioning of 11KV porcelain Disc insulator


45 KN along with HW fittings complete in all respect as per TS &
approved drawings.

Erection, Testing and Commissioning of 11 KV porcelain Pin Insulators


with GI PIN complete in all respect as per TS & approved drawings.

Earthing

a)

b)

Excavation, Erecting, Testing and Commissioning of Pipe type


untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.
Excavation, Erecting, Testing and Commissioning of Coil type
untreated earthing by providing & using 8 SWG GI wire, pipe clamp,
bolts& Nuts etc. for connections as per TS/ REC construction
standard.

Excavation, Foundation and erection of galvanised Stay Set complete


in all respect as per supply schedule by providing 0.2 cum cement
concrete (1:4:8) PCC foundations as per scope of work, specifications
and approved drawings.

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
pole and other dismentled material to the store of Utility with propoer
accounting as per the inventory.

Sub-Total
11 KV Metering System

Erection, testing, commissioning of 11 kV Metering system along with


Static Trivector Energy Meter alongwith combined CT- PT metering
unit 11KV/110 V, CT ratio-600-300/5 A with bimetalic connectors and
DLMS Static Trivector feeder meter with communication port of 11
KV/110 v of CT ratio-300/5 A with 12cx2.5 Sqmm Control Cable,
earthing and all associated accessories complete in all respest

Sub total
11 KV Railway Crossing (Double Circuit)
Laying,termination, Erection, Testing & commissioning of 11 KV grade
3-core 300 Sqmm XLPE power cable (Double Circuit) for underground
Railway Crossing including using jointing/Termination Kit, GI pipe, CI
pipe, clamps, conectors bolts, nuts, fixing and fitting of anti-climbing
device with all accessories,Earthing in all respect etc. complete in all
respect as per TS, approved drawing

Sub Total
11 KV Bay Extension

Excavation, erection, cement concrete foundation, erection, testing


and commissioning of all type of structures i.e. Gantry/Swing
bus/isolator/VCB/CT/PT/PI structures etc. made of Lattice structures
of equal angles sections, flat as per approved drawings.

Design, Engineering and construction , erection, testing and


commissioning of 12 kV,630 A, 25kA for 3 seconds, 3-ph, Outdoor
type Vacuum Circuit breaker along with 12 kV, 1-Phase for 3
seconds , 25kA, 600-300-150/5-5 Amp. outdoor type Current
Transformer along with junction box (1 no junction box for 3 no of 1phase CTs)], Jumpers, earthing, supporting structures, maintenance
platform, marshalling box, control & Power cabling between VCB and
indoor control panel and required accessories complete as per
approved drawings, technical specifications and scope of the work.

Design, Engineering and construction, Erection, testing and


commissioning of 12 kV, 630 A, 25kA , 3-ph double break center
rotating type (DBCR), Gang Operated, isolator along with Support
Insulators, Operating Mechanism, Base Channel down Pipe and all
required accessories complete as per approved drawings, technical
specifications and scope of the work.

Design, Engineeringi , Erection, testing and Commissioning of 9 kV,


10kA, 1-ph Station Class Lightening Arresters with mounting on
erected structures, jumpering from bus bar, earthing connection
using 50x6mm GS flat, hardware etc as required, as per approved
drawings, technical specifications and scope of the work,

12 KV Control & Relay panel for 12 KV VCB (suitable for 30 V DC


tripping/closing coil and associated control) alongwith, ElF & O/C
relays, Static energy meter (class 0.5 with communication port) ,
Mimic Diagram, Voltmete, Ammeter, etc complete as per REC

Erection, testing and commissioning of Bus Bar, jumpering and


Dropper (Zebra/wolf Conductor),with using all type of insulator,
Clamps and connectors, Bolts, Nuts and Washers, Al. Tape etc with
all accessories complete in all respect.

Excavation, laying, welding, refilling, earthing & grounding of MS Flat


as per Approved drawing and erection of riser up to various
equipment/structures as per scope of the work, specifications and
approved drawings.

Excavation, erection, testing and commissioning of 40 mm dia, 3000


mm long GI pipe earth electrode by providing test link, RCC pit, RCC
cover, placed on GI frame, Charcoal & Salt in alternate layer as per
REC Specification and other accessories complete as per approved
drawings, technical specifications and scope of the work for power
transformer neutral, station transformer neutral, lightening arresters
direct earthing.

Design, engineering and construction of Cable Trench of 0.5 Mtr


wide , 1.0 Mtr. depth, precast RCC Trench Cover, Water stops, Brick
Work wherever required including supply of T&P, Labour, Cement,
Sand, Reinforcement Steel, Steel Angles, Flats, Form Work,
Excavation and providingcement plaster (1:4) including floating coat
of cement punning (1.5 MM) with clean pores sand etc, all complete
as per Technical Specification and approved Drawing and as per
direction of Engineer in charge (Payment will be made as per actual
requirement per Mtr.)
Sub-Total

Capacitor Banks

Design, engineering,Erection, testing and commissioning of Fully


automatic Capacitor bank with automatic control panel, isolator,
outdoor type suitable Vacuum Circuit Breaker, mounting structures,
All types of cable & its accessories complete , earthing etc as
required as per technical specifications, approved drawings, scope of
the works of following capacities: (Banks in Muiltiple of 600 KVAR as
per REC Specification):

1200 KVAR

3600 KVAr

Sub Total
V

Distribution Transformer Substations ( 200 KVA) on Rail pole

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 200 KVA

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support for DSS


and installation with DT numbering as per scope of work, approved
drawings and specifications:

13 m long 52 Kg/mtr. Rail Pole (Painted with 2 coat Red oxide, 2 coat
Al-Paint and 1/6th part of the Rail pole from bottom with Black
enamel paint of Reputed make) including fixing of (RCC Base Plate
of size 500x500x100 mm./Stone Base Plate of Size 450x450x50mm))
with cement concreting foundation and top mopping (1:4:8) (0.65
cmt per pole).

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 400/5 A ) with bar type CTs- 400/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 200 KVA
Distribution Transformer.

10

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

11

12

Erection, testing and commissioning of ACSR Dog Conductor for


jumpering by providing PG Clamps, bi-metallic/Al connectors,
hardware, Al Tape etc as required complete in all respect for
commissioning of DSS.
Excavation and erection of galvanised Stay Set as per supply
schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Distribution Transformer Substations ( 200 KVA) on 9 Mtr. 400
Kg PSC Pole

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 200 KVA

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support


for DSS and installation with DT numbering as per scope of
work, approved drawings and specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 400/5 A ) with bar type CTs- 400/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 200 KVA
Distribution Transformer.

10

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

11

Erection, testing and commissioning of ACSR Dog Conductor for


jumpering by providing and using Al tape PG Clamps, bi-metallic/Al
connectors, hardware etc as required complete in all respect for
commissioning of DSS.

12

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Distribution Transformer Substations 100 KVA on 9 Mtr. 400
kg PSC Pole

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 100 KVA

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support


for DSS and installation with DT numbering as per scope of
work, approved drawings and specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm)) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 200/5 A ) with bar type CTs- 200/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 100 KVA
Distribution Transformer.

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of ACSR Rabbit Conductor for


jumpering by providing and using Al Tape PG Clamps, bi-metallic/Al
connectors, hardware etc as required complete in all respect for
commissioning of DSS.

10

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Distribution Transformer Substations ( 100 KVA) on 8 Mtr. 200
kg PSC Pole

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 100 KVA

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support


for DSS and installation with DT numbering as per scope of
work, approved drawings and specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 200/5 A ) with bar type CTs- 200/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 100 KVA
Distribution Transformer.

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of ACSR Rabbit Conductor for


jumpering by providing PG Clamps, bi-metallic connectors, hardware
etc as required complete in all respect for commissioning of DSS.

10

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Distribution Transformer Substations 63 KVA on 8 Mtr. PSC
pole

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 63 KVA

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support


for DSS and installation with DT numbering as per scope of
work, approved drawings and specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 200/5 A ) with bar type CTs- 200/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 100 KVA
Distribution Transformer.

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of ACSR Rabbit Conductor for


jumpering by providing PG Clamps, bi-metallic connectors, hardware
etc as required complete in all respect for commissioning of DSS.

10

AA

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Augmentation of 100 KVA Distribution Transformer by 200
KVA new Distribution Transformer

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 200 KVA

Dismentling of existing dismentled Distt. Transformer including


storage, handling, loading, unloading, transportation to designated
store/proposed Site of Utility as per the direction of Engineer-incharge and handing over the material to the authorised
representative of Utility with propoer accounting as per the inventory.

AB

Sub-Total
Augmentation of 63 KVA Distribution Transformer by 100 KVA
Distribution Transformer (NEW)

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 100 KVA

Dismentling of existing dismentled Distt. Transformer including


storage, handling, loading, unloading, transportation to designated
store/proposed Site of Utility as per the direction of Engineer-incharge and handing over the material to the authorised
representative of Utility with propoer accounting as per the inventory.
Sub-Total

AC

Augmentation of 63 KVA Distribution Transformer by 100 KVA


Released Distribution Transformer (Released)

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type
Distribution Transformer filled with oil complete required for proper
commissioning of Distribution Transformers with all accessories and
fittings as per technical specifications and approved Drawing.

Three Phase 100 KVA (released DT will be Utilised)

Dismentling of existing dismentled Distt. Transformer including


storage, handling, loading, unloading, transportation to designated
store/proposed Site of Utility as per the direction of Engineer-incharge and handing over the material to the authorised
representative of Utility with propoer accounting as per the inventory.

AD

Sub-Total
R & M of Existing Distribution Substations

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by providing and installing danger board and barbed
Wires on DP/TP/FP Structures and DT numbering as per scope of
work, approved drawings and Technical specifications: for

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications.(1 Set = 3 Nos)

Erection, fixing and fitting of galvanised pre-fabricated steel


materials- channel, angle, flats of various size for DT structures with
bolts, nuts and washers etc. complete in all respect as per TS and
approved drawing.

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of LT bus bar distribution system


with kit-kat complete and jumpering Connections of 11 KV side
complete by providing & using P G clamp/ connectors in all respect
for commssioning of DSS.

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.

Dismentling of existing dismentled materials and devolution of the


dismantled materials i.e Transformer angle, channel, clamp, AB
Switch, HG fuse Set etc. including storage, handling, insurance,
loading, unloading, transportation to store of Utility as per the
direction of Engineer-in-charge with propoer accounting as per the
inventory.
Sub Total

AE
1

Construction of 3 Phase 4 Wire LT Line on 8M, 200 Kg PSC


with ACSR Weasel Conductor in Vertical configuration
Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm)with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Weasel Conductor including mid point
jointing (by providing and using PG clamps, Al Tape) and jumpering , binding of
conductor with insulator, binding wire, fixing and fitting of LT PVC phase spacers etc.
complete in all respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- U clamp & stay clamp by


using Bolts, Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Sub-Total
AF

Construction of 3 Phase 4 Wire LT Line on 8M, 200 Kg PSC


with ACSR Weasel Conductor in Horizontal configuration

Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Weasel Conductor


including mid point jointing (by providing and using PG clamps, Al
Tape) and jumpering , binding of conductor with insulator, binding
wire, fixing and fitting of LT PVC phase spacers etc. complete in all
respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- angle, flats for over


head line structures by using Bolts, Nuts, Washer etc as per approved
drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including


supply of all materials like 8 SWG G.I. wire closely wound having 115
turns, 50mm dia & 450mm long coil (untreated without charcoal &
salt) in all type of soil including excavation, refilling with earth, fixing
of bolts, nuts, washers for connection with pole support/ metalic part
all complete as per TS & direction of Engineer-in charge (individual
pole earthing)
Sub-Total
Construction of 3 Phase 4 Wire LT Line on 8M, 200 Kg PSC
with ACSR Rabbit Conductor in Horizontal configuration

AG
1

Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Rabbit Conductor including mid point
jointing (by providing and using PG clamps, Al Tape) and jumpering , binding of
conductor with insulator, binding wire, fixing and fitting of LT PVC phase spacers etc.
complete in all respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- angle, flats for over head line
structures by using Bolts, Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Sub-Total
AH

R&M of 3-Ph, 4 Wire LT line with ACSR Rabbit conductor


1

Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Rabbit Conductor including mid point
jointing (by providing and using PG clamps, Al Tape) and jumpering , binding of
conductor with insulator, binding wire, fixing and fitting of LT PVC phase spacers etc.
complete in all respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- angle, flats for over head line
structures by using Bolts, Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
pole and other dismentled material to the store of Utility with propoer
accounting as per the inventory.
Sub-Total

AI

R&M of 3-Ph, 4 Wire LT line with ACSR Weasel conductor


1

Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Weasel Conductor including mid point
jointing (by providing and using PG clamps, Al Tape) and jumpering , binding of
conductor with insulator, binding wire, fixing and fitting of LT PVC phase spacers etc.
complete in all respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- angle, flats for over head line
structures by using Bolts, Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
pole and other dismentled material to the store of Utility with propoer
accounting as per the inventory.
Sub-Total

AJ

R&M of existing Single phase & 2 phase line with Conversion


in to Three Phase , 4 wire Line by ACSR Weasel conductor

Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size 500x500x100
mm./Stone Base Plate of Size 450x450x50mm) with brick blast or boulder refilling
(50% depth of pole pit) and ramming foundation with excavated soil with pouring water
as required as per scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Weasel Conductor with fixing & fitting of
shackle/ pin insulator including mid point jointing (by providing and using PG clamps,
Al Tape) and jumpering , binding of conductor with insulator, binding wire, fixing and
fitting of LT PVC phase spacers etc. complete in all respect. (1 CKm= 1 km line length
of 4 phase conductor )

Erection of galvanised fabricated steel materials- angle, flats for over head line
structures by using Bolts, Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
pole and other dismentled material to the store of Utility with propoer
accounting as per the inventory.

AK

Sub-Total
Erection, testing commissioning of New LT Line on 3 phase
ABC [3 X95Sq mm {Phase}+{1x70 Sq mm Messenger cum
Neutral wire}]

Survey, route alignment & pole spotting, preparation of


survey report , Inventory after approval of Engineer-incharge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support


for LT line and pole numbering as per scope of work,
approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate


of size 500x500x100 mm./Stone Base Plate of Size
450x450x50mm)) with brick blast or boulder refilling (50%
depth of pole pit) and ramming foundation with excavated
soil with pouring water as required as per scope of work ,
approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by


providing GI wire no.-8SWG for connections with nuts, bolts
and washers as per scope of work, technical specifications
and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB


Cables: (average span 40 to 45 m approx.) including all
erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for
work for Branching/termination etc.

3 phase ABC [3 X95Sq mm {Phase}+{1x70 Sq mm


Messenger cum Neutral wire}]

AL

Sub Total
Erection, testing commissioning of New LT Line on 3 phase
ABC [3 X70Sq mm {Phase}+{1x50 Sq mm Messenger cum
Neutral wire}]

Survey, route alignment & pole spotting, preparation of


survey report , Inventory after approval of Engineer-incharge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support


for LT line and pole numbering as per scope of work,
approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate


of size 500x500x100 mm./Stone Base Plate of Size
450x450x50mm) with brick blast or boulder refilling (50%
depth of pole pit) and ramming foundation with excavated
soil with pouring water as required as per scope of work ,
approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by


providing GI wire no.-8SWG for connections with nuts, bolts
and washers as per scope of work, technical specifications
and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB


Cables: (average span 40 to 45 m approx.) including all
erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for
work for Branching/termination etc.

3 phase ABC [3 X70Sq mm {Phase}+{1x50 Sq mm


Messenger cum Neutral wire}]

AM

Sub Total
Erection, testing commissioning of New LT Line on 3 phase
ABC [3 X50 Sq mm {Phase}+{1x35 Sq mm Messenger cum
Neutral wire}]

Survey, route alignment & pole spotting, preparation of


survey report , Inventory after approval of Engineer-incharge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support


for LT line and pole numbering as per scope of work,
approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate


of size 500x500x100 mm./Stone Base Plate of Size
450x450x50mm) with brick blast or boulder refilling (50%
depth of pole pit) and ramming foundation with excavated
soil with pouring water as required as per scope of work ,
approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by


providing GI wire no.-8SWG for connections with nuts, bolts
and washers as per scope of work, technical specifications
and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB


Cables: (average span 40 to 45 m approx.) including all
erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for
work for Branching/termination etc.

3 phase ABC [3 X50Sq mm {Phase}+{1x35 Sq mm


Messenger cum Neutral wire}]
Sub Total

AN

New LT Line on 1 phase ABC [1X16 Sq mm {Phase} + {1x25


Sq mm Messenger cum Neutral wire}]

Survey, route alignment & pole spotting, preparation of


survey report , Inventory after approval of Engineer-incharge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support


for LT line and pole numbering as per scope of work,
approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate


of size 500x500x100 mm./Stone Base Plate of Size
450x450x50mm) with brick blast or boulder refilling (50%
depth of pole pit) and ramming foundation with excavated
soil with pouring water as required as per scope of work ,
approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by


providing GI wire no.-8SWG for connections with nuts, bolts
and washers as per scope of work, technical specifications
and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB


Cables: (average span 40 to 45 m approx.) including all
erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for
work for Branching/termination etc.

1 phase ABC [1 X 16 Sq mm {Phase}+{1x35 Sq mm


Messenger cum Neutral wire}]
Sub Total
Total

BALANCE PART OF PHA


BA

Augmentation of 100 KVA Distribution Transformer by 200


KVA new Distribution Transformer

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 200 KVA

Dismentling of existing dismentled Distt. Transformer including


storage, handling, loading, unloading, transportation to designated
store/Proposed site of Utility as per the direction of Engineer-incharge and handing over the material to the authorised
representative of Utility with propoer accounting as per the inventory.

BB

Sub-Total
Augmentation of 63 KVA Distribution Transformer by 100 KVA
released Distribution Transformer

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 100 KVA

BC

Dismentling of existing dismentled Distt. Transformer including


storage, handling, loading, unloading, transportation to designated
store/Proposed site of Utility as per the direction of Engineer-incharge and handing over the material to the authorised
representative of Utility with propoer accounting as per the inventory.
Sub-Total
Distribution Transformer Substations ( 63 KVA ) on 8 Mtr. PSC
pole (New)

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type (Three
Star Rated) Distribution Transformer Filled with Oil completely with
all accessories and fittings as per technical specifications and
approved Drawing.

Three Phase 63 KVA

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support


for DSS and installation with DT numbering as per scope of
work, approved drawings and specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 200/5 A ) with bar type CTs- 200/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 63 KVA
Distribution Transformer.

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of ACSR Rabbit Conductor for


jumpering by providing PG Clamps, bi-metallic connectors, hardware
etc as required complete in all respect for commissioning of DSS.

10

BD

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Distribution Transformer Substations 100 KVA on 8 Mtr. 200
kg PSC Pole by Released DT
Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil
immersed naturally cooled, Aluminium wound outdoor type
Distribution Transformer Filled with Oil completely with all accessories
and fittings as per technical specifications and approved Drawing.

Three Phase 100 KVA (Released DT will be utilised)

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support


for DSS and installation with DT numbering as per scope of
work, approved drawings and specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 200/5 A ) with bar type CTs- 200/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 100 KVA
Distribution Transformer.

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of ACSR Rabbit Conductor for


jumpering by providing PG Clamps, bi-metallic connectors, hardware
etc as required complete in all respect for commissioning of DSS.

10

BE

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
Distribution Transformer Substations 63 KVA on 8 Mtr. PSC
pole by Release DT

Erection, Testing and Commissioning of 50 Hz, 11/0.433 KV, oil


immersed naturally cooled, Aluminium wound outdoor type
Distribution Transformer Filled with Oil completely with all accessories
and fittings as per technical specifications and approved Drawing.

Three Phase 63 KVA (release DT will be utilised)

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications. (1 Set= 3 Nos)

Excavation of pit, foundation, erection of following Support


for DSS and installation with DT numbering as per scope of
work, approved drawings and specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work as per approved drawing & technical specification.

Erection, fixing and fitting of galvanised fabricated steel materialschannel, angle, flats of various size for DTstructures with bolts, nuts
and washers etc. complete in all respect as per TS and approved
drawing.

Erection, fixing and fitting, Testing and Commissioning of Porcelain


Insulators with mounting hardware fittings etc. complete in all respect
as per TS and approved drawing.

11 KV 45 KN Disc Insulator with hardware fittings

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Erection, testing and Commissioning of LT Distribution box with LTCT


meter (CT Ratio 200/5 A ) with bar type CTs- 200/5 A metering, Al-Bus
bar of Adequate Size and LT control mechanism and connections from
LV Bushings to LTDB and LTDB to LT line with Cables by providing and
using Lugs,Washer etc. complete in all respect with one no. Of
TPMCCB as per technical specifications for Three Phase 63 KVA
Distribution Transformer.

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of ACSR Rabbit Conductor for


jumpering by providing PG Clamps, bi-metallic connectors, hardware
etc as required complete in all respect for commissioning of DSS.

10

BF

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.
Sub-Total
R & M of Existing Distribution Substations

Excavation of pit, foundation, erection of following Support for 11 KV


overhead line by providing and installing danger board and barbed
Wires on DP/TP/FP Structures and DT numbering as per scope of
work, approved drawings and Technical specifications: for

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification. Fixing of
Danger Board on DP/TP/FP & Pole numbering.

Erection, testing and Commissioning of 3-pole, Distribution Class 9


KV, 5 kA Lightening Arrester for Distribution Transformer Substation
by providing and erecting Hot Dip galvanised stranded wire 7/3.15
mm as per scope of work, approved drawings and technical
specifications.(1 Set = 3 Nos)

Erection, fixing and fitting of galvanised pre-fabricated steel


materials- channel, angle, flats of various size for DT structures with
bolts, nuts and washers etc. complete in all respect as per TS and
approved drawing.

Erection, Testing and Commissioning of 12kV, 200A, 25kA, 3-ph, 3 Pin


type, Horizontal Mounting type, Gang Operated, AB Switch along
with Support Insulators, Base Channel down Pipe, Arcing Horns etc.
complete as per technical specifications etc.complete as per
technical specifications, scope of works and approved drawings

Erection, testing and commissioning of 3 pole, 12 KV HG fuse set


compleete on the DSS Structue complete in all respect for 3-ph DTs

Excavation, erection, testing and commissioning of a set of 3 Nos


pipe earthing using 40 mm dia GI pipe 3000 mm long, as per IS 1161
and as per REC construction drawings complete with H/w and lugs etc
by providing charcoal, salt,/Bitumen Clay in alternate layers and GI
Wires 8 SWG for connections as per scope of work, approved
drawings and technical specifications.(1 Set= 3 Nos earthing per DT)

Erection, testing and commissioning of LT bus bar distribution system


with kit-kat complete and jumpering Connections of 11 KV side
complete by providing & using P G clamp/ connectors in all respect
for commssioning of DSS.

Excavation and erection of galvanised Stay Set as per supply


schedule by providing 0.2 cum cement concrete (1:4:8) PCC
foundations as per scope of work, specifications and approved
drawings.

BG

Dismentling of existing dismentled materials and devolution of the


dismantled materials i.e Transformer angle, channel, clamp, AB
Switch, HG fuse Set etc. including storage, handling, insurance,
loading, unloading, transportation to store of Utility as per the
direction of Engineer-in-charge with propoer accounting as per the
inventory.
Sub Total
Erection, testing commissioning of New LT Line on 3 phase
ABC [3 X95Sq mm {Phase}+{1x70 Sq mm Messenger cum
Neutral wire}]
Survey, route alignment & pole spotting, preparation of survey report
, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for LT line


and pole numbering as per scope of work, approved drawings and
Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by providing


GI wire no.-8SWG for connections with nuts, bolts and washers as per
scope of work, technical specifications and approved drawings and
REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB Cables:


(average span 40 to 45 m approx.) including all erection accessories
required for successful erection of AB Cable Complete in all respect
as per approved drawing and Technical Specification etc as required
as per scope for work for Branching/termination etc.

BH

3 phase ABC [3 X95Sq mm {Phase}+{1x70 Sq mm Messenger cum


Neutral wire}]
Sub Total
Erection, testing commissioning of New LT Line on 3 phase
ABC [3 X70Sq mm {Phase}+{1x50 Sq mm Messenger cum
Neutral wire}]
Survey, route alignment & pole spotting, preparation of survey report
, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for LT line


and pole numbering as per scope of work, approved drawings and
Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by providing


GI wire no.-8SWG for connections with nuts, bolts and washers as per
scope of work, technical specifications and approved drawings and
REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB Cables:


(average span 40 to 45 m approx.) including all erection accessories
required for successful erection of AB Cable Complete in all respect
as per approved drawing and Technical Specification etc as required
as per scope for work for Branching/termination etc.

BI

3 phase ABC [3 X70Sq mm {Phase}+{1x50 Sq mm Messenger cum


Neutral wire}]
Sub Total
Erection, testing commissioning of New LT Line on 3 phase
ABC [3 X50 Sq mm {Phase}+{1x35 Sq mm Messenger cum
Neutral wire}]

Survey, route alignment & pole spotting, preparation of survey report


, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for LT line


and pole numbering as per scope of work, approved drawings and
Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by providing


GI wire no.-8SWG for connections with nuts, bolts and washers as per
scope of work, technical specifications and approved drawings and
REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB Cables:


(average span 40 to 45 m approx.) including all erection accessories
required for successful erection of AB Cable Complete in all respect
as per approved drawing and Technical Specification etc as required
as per scope for work for Branching/termination etc.

BJ
1

3 phase ABC [3 X50Sq mm {Phase}+{1x35 Sq mm Messenger cum


Neutral wire}]
Sub Total
Construction of 3 Phase 4 Wire LT Line on 8M, 200 Kg PSC
with ACSR Weasel Conductor in Vertical configuration
Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size 500x500x100
mm./Stone Base Plate of Size 450x450x50mm) with brick blast or boulder refilling
(50% depth of pole pit) and ramming foundation with excavated soil with pouring water
as required as per scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Weasel Conductor including mid point
jointing (by providing and using PG clamps, Al Tape) and jumpering , binding of
conductor with insulator, binding wire, fixing and fitting of LT PVC phase spacers etc.
complete in all respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- U clamp & stay clamp by using Bolts,
Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Sub-Total
BK

Construction of 3 Phase 4 Wire LT Line on 8M, 200 Kg PSC


with ACSR Weasel Conductor in Horizontal configuration

Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size 500x500x100
mm./Stone Base Plate of Size 450x450x50mm) with brick blast or boulder refilling
(50% depth of pole pit) and ramming foundation with excavated soil with pouring water
as required as per scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Weasel Conductor including mid point
jointing (by providing and using PG clamps, Al Tape) and jumpering , binding of
conductor with insulator, binding wire, fixing and fitting of LT PVC phase spacers etc.
complete in all respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- angle, flats for over head line
structures by using Bolts, Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Sub-Total
BL

Construction of 3 Phase 4 Wire LT Line on 8M, 200 Kg PSC


with ACSR Rabbit Conductor in Horizontal configuration

Route Survey

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size 500x500x100
mm./Stone Base Plate of Size 450x450x50mm) with brick blast or boulder refilling
(50% depth of pole pit) and ramming foundation with excavated soil with pouring water
as required as per scope of work as per approved drawing & technical specification.

Erection, testing and commissioning of ACSR Rabbit Conductor including mid point
jointing (by providing and using PG clamps, Al Tape) and jumpering , binding of
conductor with insulator, binding wire, fixing and fitting of LT PVC phase spacers etc.
complete in all respect. (1 CKm= 1 km line length of 4 phase conductor)

Erection of galvanised fabricated steel materials- angle, flats for over head line
structures by using Bolts, Nuts, Washer etc as per approved drawing and TS

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

BM
1

Spiral type earthing as per REC construction drawing J-1 including supply of all
materials like 8 SWG G.I. wire closely wound having 115 turns, 50mm dia & 450mm
long coil (untreated without charcoal & salt) in all type of soil including excavation,
refilling with earth, fixing of bolts, nuts, washers for connection with pole support/
metalic part all complete as per TS & direction of Engineer-in charge (individual pole
earthing)

Sub-Total
Guarding of 33 &11 KV line
Erection, testing and commisiioning of Guarding & Lacing per span by using
Fabricated structure, Eye hook, G. I. Wire, Bolts, nuts, washers etc. complete in all
respect as per approved drawing/REC standards.

Sub Total
BN

New LT Line on 1 phase ABC [1X16 Sq mm {Phase} + {1x25


Sq mm Messenger cum Neutral wire}]

Survey, route alignment & pole spotting, preparation of survey report , Inventory after
approval of Engineer-in-charge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support for LT line and pole
numbering as per scope of work, approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate of size 500x500x100
mm./Stone Base Plate of Size 450x450x50mm) with brick blast or boulder refilling
(50% depth of pole pit) and ramming foundation with excavated soil with pouring water
as required as per scope of work , approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by providing GI wire no.-8SWG


for connections with nuts, bolts and washers as per scope of work, technical
specifications and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB Cables: (average span 40 to 45


m approx.) including all erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and Technical Specification etc
as required as per scope for work for Branching/termination etc.

1 phase ABC [1 X 16 Sq mm {Phase}+{1x35 Sq mm Messenger cum Neutral wire}]

Sub Total

Special Plan (BRGF) PhaseCA

R&M of existing overhead 11 KV Line by 3 phase ABC 3X120 + 1X 100


Sq.mm

Survey, route alignment & pole spotting, preparation of survey report


, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for 11 KV


line and pole numbering as per scope of work, approved drawings
and Technical specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay


clamp, stay guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm
diameter solid GS stay rod & 7/12 SWG dia GI stranded wire by
providing 0.2 cum cement concrete (1:4:8) and 200x200x6 mm Stay
plate foundations as per scope of work, specifications and approved
drawings.

Installation, testing and commissioning of Coil Earthing by providing


GI wire no.-8SWG for connections with nuts, bolts and washers as per
scope of work, technical specifications and approved drawings and
REC Specification.

Erection, testing and Commissioning of 11 KV Line on AB Cables


including all erection accessories required for successful erection of
AB Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for work for
Branching/termination etc.

3 phase ABC [3 X 120 Sq mm {Phase}+{1 X 100 Sqmm]

CB
1

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
all dismentled material to the store of Utility with propoer accounting
as per the inventory.
Sub Total
R&M of existing overhead 11 KV Line by 3 phase ABC 3X70 +
1X 70 Sq.mm
Survey, route alignment & pole spotting, preparation of survey report
, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for 11 KV


line and pole numbering as per scope of work, approved drawings
and Technical specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm) with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay


clamp, stay guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm
diameter solid GS stay rod & 7/12 SWG dia GI stranded wire by
providing 0.2 cum cement concrete (1:4:8) and 200x200x6 mm Stay
plate foundations as per scope of work, specifications and approved
drawings.

Installation, testing and commissioning of Coil Earthing by providing


GI wire no.-8SWG for connections with nuts, bolts and washers as per
scope of work, technical specifications and approved drawings and
REC Specification.

Erection, testing and Commissioning of 11 KV Line on AB Cables


including all erection accessories required for successful erection of
AB Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for work for
Branching/termination etc.

3 phase ABC [3 X 70 Sq mm {Phase}+{1 X 70 Sqmm]

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
all dismentled material to the store of Utility with propoer accounting
as per the inventory.
Sub Total

CC

R&M of existing overhead 11 KV Line by 3 phase ABC 3X35 + 1X70 Sq.mm

Survey, route alignment & pole spotting, preparation of survey report


, Inventory after approval of Engineer-in-charge & redressal of ROW
issues.

Excavation of pit, foundation, erection of following Support for 11 KV


line and pole numbering as per scope of work, approved drawings
and Technical specifications:

PSC Pole 9 Mtr 400 Kg including fixing of (RCC Base Plate of size
500x500x100 mm./Stone Base Plate of Size 450x450x50mm)with
brick blast or boulder refilling (50% depth of pole pit) and ramming
foundation with excavated soil with pouring water as required as per
scope of work , approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay


clamp, stay guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm
diameter solid GS stay rod & 7/12 SWG dia GI stranded wire by
providing 0.2 cum cement concrete (1:4:8) and 200x200x6 mm Stay
plate foundations as per scope of work, specifications and approved
drawings.

Installation, testing and commissioning of Coil Earthing by providing


GI wire no.-8SWG for connections with nuts, bolts and washers as per
scope of work, technical specifications and approved drawings and
REC Specification.

Erection, testing and Commissioning of 11 KV Line on AB Cables


including all erection accessories required for successful erection of
AB Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for work for
Branching/termination etc.

3 phase ABC [3 X 35 Sq mm {Phase}+{1 X 70 Sqmm]

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
all dismentled material to the store of Utility with propoer accounting
as per the inventory.
Sub Total

CD

R & M of LT Line on 3 phase ABC [3 X95Sq mm {Phase}


+{1x70 Sq mm Messenger cum Neutral wire}]

Survey, route alignment & pole spotting, preparation of


survey report , Inventory after approval of Engineer-incharge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support


for LT line and pole numbering as per scope of work,
approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate


of size 500x500x100 mm./Stone Base Plate of Size
450x450x50mm) with brick blast or boulder refilling (50%
depth of pole pit) and ramming foundation with excavated
soil with pouring water as required as per scope of work ,
approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by


providing GI wire no.-8SWG for connections with nuts, bolts
and washers as per scope of work, technical specifications
and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB


Cables: (average span 40 to 45 m approx.) including all
erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for
work for Branching/termination etc.

3 phase ABC [3 X95Sq mm {Phase}+{1x70 Sq mm


Messenger cum Neutral wire}]

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
all dismentled material to the store of Utility with propoer accounting
as per the inventory.
Sub Total

CE

R & M of LT Line on 3 phase ABC [3 X70Sq mm {Phase}


+{1x50 Sq mm Messenger cum Neutral wire}]

Survey, route alignment & pole spotting, preparation of


survey report , Inventory after approval of Engineer-incharge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support


for LT line and pole numbering as per scope of work,
approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate


of size 500x500x100 mm./Stone Base Plate of Size
450x450x50mm) with brick blast or boulder refilling (50%
depth of pole pit) and ramming foundation with excavated
soil with pouring water as required as per scope of work ,
approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by


providing GI wire no.-8SWG for connections with nuts, bolts
and washers as per scope of work, technical specifications
and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB


Cables: (average span 40 to 45 m approx.) including all
erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for
work for Branching/termination etc.

3 phase ABC [3 X70Sq mm {Phase}+{1x50 Sq mm


Messenger cum Neutral wire}]

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
all dismentled material to the store of Utility with propoer accounting
as per the inventory.
Sub Total

CF

R &M of LT Line on 3 phase ABC [3 X50Sq mm {Phase}


+{1x35 Sq mm Messenger cum Neutral wire}]

Survey, route alignment & pole spotting, preparation of


survey report , Inventory after approval of Engineer-incharge & redressal of ROW issues.

Excavation of pit, foundation, erection of following Support


for LT line and pole numbering as per scope of work,
approved drawings and Technical specifications:

PSC Pole 8 Mtr 200 Kg including fixing of (RCC Base Plate


of size 500x500x100 mm./Stone Base Plate of Size
450x450x50mm) with brick blast or boulder refilling (50%
depth of pole pit) and ramming foundation with excavated
soil with pouring water as required as per scope of work ,
approved drawing & technical specification.

Excavation and erection of galvanised Stay Set with 50x10 mm stay clamp, LT stay
guy insulator, nut bolts, turn buckles, 1.8 m long, 16 mm diameter solid GS stay rod &
7/12 SWG dia GI stranded wire by using Stone stay plate 450x450x50 mm Stay plate
foundations as per scope of work, specifications and approved drawings.

Installation, testing and commissioning of Coil Earthing by


providing GI wire no.-8SWG for connections with nuts, bolts
and washers as per scope of work, technical specifications
and approved drawings and REC Specification(untreated).

Erection, testing and Commissioning of LT Line on AB


Cables: (average span 40 to 45 m approx.) including all
erection accessories required for successful erection of AB
Cable Complete in all respect as per approved drawing and
Technical Specification etc as required as per scope for
work for Branching/termination etc.

3 phase ABC [3 X50Sq mm {Phase}+{1x35 Sq mm


Messenger cum Neutral wire}]

Dismentling of existing defective/damaged pole-support


(Rail/joist/tubular),conductor and other dismantled line materials
from existing line and devolution of the dismentled pole, structure,
conductor and other line materials including storage, handling,
insurance, loading, unloading, transportation to designated store of
Utility as per the direction of Engineer-in-charge and handing over the
all dismentled material to the store of Utility with propoer accounting
as per the inventory.
Sub Total
Total Part C
Grand TOTAL

ection Price Component

Network in Bihar Under Special Plan (BRGF) Phased Phase-II-Part-C for all 21 Districts of North Bihar
lan (BRGF) Schemes
aran and West Champaran
me & Address: 0
NIT No:- /PR/NBPDCL/2014

Unit

Unit
Quantity

Total
Quantity

Unit Price
for
Erection

Unit
Service
tax

Unit
Charges
including
Erection
and
Service
Tax

7=5+6

10=8+9

11=7x10

Total
Price for
Erection

PER S/S

Cubic
Meters

2400

4800

Sq. m

600

1200

Mtr

200

400

Mtr

40

80

Sqm

160

320

Mtr

120

240

Mtr

50

100

Mtr

60

120

Mtr

10

20

Sq. Meter

50

100

Per PSS

Set

Set

MT

16

32

Set

No

No

Set

18

Set

Set

18

Set

No

No

18

No

Set

No

No

No

MT

MT

MT

0.5

Set

40

80

Per PSS

Per PSS

Set

Set

Set

Per PSS

km

0.5

km

0.9

1.8

km

0.1

0.2

18

Set

Mtr.

50

100

PER S/S

Cubic
Meters

2400

9600

Sq. m

600

2400

Mtr

200

800

Mtr

40

160

Sqm

160

640

Mtr

120

480

Mtr

50

200

Mtr

60

240

Mtr

10

40

Sq. Meter

50

200

Per PSS

Set

Set

MT

14

56

Set

16

No

No

Set

36

Set

16

Set

20

Set

No

No

20

No

Set

No

No

No

MT

MT

MT

0.5

Set

40

160

Per PSS

Per PSS

Set

Set

Set

Per PSS

km

0.5

km

0.6

2.4

km

0.1

0.4

Set

20

Mtr.

50

200

No

Addl. 5
MVA

Addl.10
MVA

5-10
MVA

3.15-10
MVA

3.15/1.65 MVA

3.15-5
MVA
(Release
d)

1.6-5
MVA
(Release
d)

Total

Cu.m

25

Sq. m

25

Mtr

Mtr

Set

Set

Set

Nos

Nos

MT

2.5

Set

No

Set

Set

No

Set per
Power
Transfor
mer bay

Per
Power
Transfor
mer Bay

Set

Per
Transformer

0
127.31

CKm

127.31

No.

18

2292

Kg

700

89117

CKM

127

Set

764

Set

51

6493

Set

127

Set

16

2037

Set

764

Set

0.1

13

0
23.65

CKm

23.65

No.

118

Kg

47.3

Nos

24

Kg

300

7095

CKM

23.65

Set

142

Set

30

710

Set

24

Set

189

Set

142

Ckm

23.65

3
MT

2.5

7.5

Set

No

Set

Per Bay

Set

LS per
bay

Set

18

Mtr

15

Mtr

115

115

0
4

No

0
29.13

CKm

29.13

No.

16

466

Kg

425

12380.25

CKM

29.13

Set

174.78

Set

45

1310.85

Set

29

Set

14

408

Set

175

Set

0.1

0
29.13
CKm

29.13

No.

20

583

Kg

1100

32043

CKM

58.26

Set

12

350

Set

114

3321

Set

29

Set

18

524

Set

233

0
203.91

CKm

203.91

No.

20

4078

Kg

365

74427.15

CKM

203.91

Set

1223

Set

57

11623

Set

204

Set

18

3670

Set

1223

Set

0.1

20

0
354.79
CKm

354.79

No.

18

6386

Kg

365

129498.4

CKM

354.79

Set

2128.74

Set

51

18094.29

Set

355

Set

16

5677

Set

2129

Set

0.1

35

0
532.19
CKm

532.19

No.

18

9579

Kg

365

194249.4

CKM

532.19

Set

3193.14

Set

51

27141.69

Set

532

Set

16

8515

Set

3193

Set

0.1

53

0
0
CKm

No.

18

Kg

365

CKM

Set

Set

51

Set

Set

16

Set

Set

0.1

0
36.4
CKm

36.4

No.

36

No.

73

Kg

50

1820

CKM

36.4

Set

109

Set

15

546

Set

36

Set

109

Set

73

Ckm

36.4

0
54.6

CKm

54.6

No.

164

Kg

50

2730

CKM

54.6

Set

164

Set

18

983

Set

55

Set

164

Set

109

Ckm

54.6

0
0
CKm

No.

No

Kg

150

CKM

Set

Set

15

Set

Set

Set

Ckm

0
11

No.

11

0
1

KMs

0.115

0.115

0
6

MT

2.5

15

Set

Set

12

Set

Set

Per Bay

LS per
bay

Set

36

Mtr

30

0
6

Set

Set

0
49

No

49

Set

49

No

98

Kg

280

13720

Set

147

Set

49

Sets

49

No

49

Per DSS

49

Per DT

49

Set

98

0
114

No

114

Set

114

No

228

Kg

265

30210

Set

342

Set

114

Sets

114

No

114

Per DSS

114

Per DT

114

Set

228

0
127

No

127

Set

127

No

254

Kg

250

31750

Set

381

Set

127

Sets

127

No

127

Per DSS

127

Per DT

127

Set

254

0
127

No

127

Set

127

No

254

Kg

250

31750

Set

381

Set

127

Sets

127

No

127

Per DSS

127

Per DT

127

Set

254

0
213

No

213

Set

213

No

426

Kg

250

53250

Set

639

Set

213

Sets

213

No

213

Per DSS

213

Per DT

213

Set

426

0
89

No

89

per DT

89

0
154

No

154

per DT

154

0
76

No

76

per DT

76

0
313

No.

0.05

16

No.

0.05

16

Set

313

Kg

30

9390

Set

0.75

235

Sets

0.5

157

Per DSS

313

Per DT

313

Set

313

Per DT

313

0
245.13
CKms

245.13

No

20

4903

CKM

1.00

245.13

Kg

50

12256.5

Set

1226

Set

10

2451

0
571.97
CKms

571.97

No

20

11439.4

CKM

1.00

571.97

Kg

200

114394

Set

3431.82

Nos.

10

5719.7

0
0
Kms

No

20

CKM

1.00

Kg

200

Set

Nos.

10

0
0
CKms

No

20

CKM

1.00

Kg

60

Set

Nos.

Ckm

0
0
CKms

No

20

CKM

1.00

Kg

60

Set

Nos.

Ckm

0
275.3
CKms

275.3

No

551

CKM

1.00

275.3

Kg

200

55060

Set

551

Nos.

1377

Ckm

275.3

0
14.93

CKm

14.93

No

25

373

Set

90

Set

90

Ckm

14.93

0
27.88

CKm

27.88

No

25

697

Set

167

Set

167

Ckm

27.88

0
104.57

CKm

104.57

No

25

2614

Set

627

Set

627

Ckm

104.57

0
2

CKm

No

25

50

Set

12

Set

12

Ckm

0
0

ART OF PHASE-I
119

No

119

per DT

119

0
67

No

67

per DT

67

0
0

No

Set

No

Kg

250

Set

Set

Sets

No

Per DSS

Per DT

Set

0
30

No

30

Set

30

No

60

Kg

250

Set

7500

90

Set

30

Sets

30

No

30

Per DSS

30

Per DT

30

Set

60

0
30

No

30

Set

30

No

60

Kg

250

7500

Set

90

Set

30

Sets

30

No

30

Per DSS

30

Per DT

30

Set

60

0
1650

No.

0.05

83

No.

0.05

83

Set

0.5

825

Kg

30

49500

Set

0.75

1238

Sets

0.5

825

Per DSS

1650

Per DT

1650

Set

1650

Per DT

1650

0
11.66

CKm

11.66

No

25

292

Set

70

Set

70

Ckm

11.66

0
21.32

CKm

21.32

No

25

533

Set

128

Set

128

Ckm

21.32

0
81.64

CKm

81.64

No

25

2041

Set

490

Set

490

Ckm

81.64

0
36.74
Kms

36.74

No

20

735

CKM

1.00

36.74

Kg

50

1837

Set

184

Set

10

367

0
85.73
Kms

85.73

No

20

1715

CKM

1.00

85.73

Kg

200

17146

Set

514

Nos.

10

857

0
52.48
Kms

52.48

No

20

1050

CKM

1.00

52.48

Kg

200

10496

Set

262

Nos.

10

525

0
200
per span

200

0
2

CKm

No

25

50

Set

12

Set

12

Ckm

0
0

RGF) Phase-II PART-C


25
CKm

25

No

10

250

Set

100

Set

10

250

Ckm

25

Ckm

25

0
25
CKm

25

No

10

250

Set

100

Set

10

250

Ckm

25

Ckm

25

0
75

CKm

75

No

10

750

Set

300

Set

10

750

Ckm

75

Ckm

75

0
116

CKm

116

No

10

1160

Set

696

Set

696

Ckm

116

Ckm

116

0
290

CKm

290

No

10

2900

Set

1740

Set

1740

Ckm

290

Ckm

290

0
174

CKm

174

No

10

1740

Set

1044

Set

1044

Ckm

174

Ckm

174

0
0
0