Académique Documents
Professionnel Documents
Culture Documents
implementing the education required for the employees and what as well as how, the
exact improvements to the company will be. Then we will include a detailed project
schedule, showing how the new improvements and anything associated with improving
the safety in the plant will be implemented. Lastly, we will include the resources
necessary to complete these actions.
Taking a walk around our manufacturing plant, we noticed several issues with
safety involving the employees, the equipment and the products. We will begin to
address all the issues regarding safety in each area of the plant. The most concerns
seem to steam from the equipment being used by the employees. Certain incidents that
have been brought to our attention have called for this change in action. We must act
swiftly to provide changes to this workplace so incidents with injuries are a thing of the
past. Some of the issues we noticed included but not limited to:
These were just a few of the various dangers we found throughout our company. Each
of these hazards will be addressed and fixed.
Injuries By Area
Welding Station; 10%
Our project plan will begin with a thorough inspection of the material and supplies
used throughout the plant. While we dont want to shut down the entire plant, we will
work area by area so not all operations are cancelled. We will work on each area, one
at a time. Each area will be specifically calculated as to not disrupt the flow of work. Our
team will inspect the entire plant and make a chart of the areas being inspected and
worked on. Each area will go through a phase of action. These actions include:
1.
2.
3.
4.
5.
6.
7.
8.
9.
With these steps we can ensure the proper changes are being done. We will begin by
stopping the equipment and halting the process of the first area of designation. Once
the designated area has been handed over to our team of professionals, we will begin
to examine the tools, equipment and any materials being used at that site. We will begin
inspecting for any hazards that coincide with broken tools or any action that could result
in injury. One incident reported to us was a piece of machinery severely cutting an
employees finger. These kinds of hazards will be double checked and ensured to not
produce that result again. All equipment inspected will be given a grade and based upon
the feedback, will be altered to ensure the safety of the operator. This might include
guards or wiring to protect the user from being able to hurt themselves. Materials used
during normal production will be inspected so that any dangers resulting from using
them will be eliminated. We will also provide a grade for the materials and supplies
being used and make note of what is being used and what isnt.
After inspection is completed, we will allow the employees to return to their
stations and operations will continue as normal. Our team is then instructed to spectate
the process and make note of various hazards, dangers
and risk we might come across. We want to see the area
working in real time, as this will give us a better view of
what were dealing with. We can see wrongdoings firsthand and see what needs to be fixed. Crucial
speculations may be made on the spot, but we prefer to
consult the actions as a team and roll out the fixes at a later time.
Once we are done inspecting the area and have the notes we need to begin the
fix, we will assess what we saw along with our recordings and begin a group meeting.
These meetings will take place after each area so only that area being worked on will
talked about. This will provide direct attention to the area at hand and reduce the risk of
missing out any details or fixes that need to be done. Our team will spend a certain
amount of time, usually as much as we need, to iron out what exactly needs to be done.
This will include conversing about the current state of operation, improper safety
procedures and how exactly to go about fixing the problems. The meetings will be
mandatory for each member and a final draft will be constructed at the end of the
meeting with fixes, improvements and an overall score for the area. This is also where
data will be analyzed and constructed. Records will be kept for everything we do as a
safekeeping.
Upon the conclusion of the meetings, we will have all the information needed to
begin the correction process for that specific area. We will sit down with the managers
or person in charge and present to them a manifest of our findings. Our goal is for the
manager to review our suggested improvements and implement them in a timely
fashion. We want the manager to be educated on what we want changed and how to go
about doing it. With his help, we will implement the changes. Along with what exactly
needs to be handled, will be a budget for the fixes and resources needed. All the work
will be done, it would only be a matter of getting the ok to begin the process.
Our work wont be completed until we see the improvements in real time. Once
the changes have been approved, we will work with the company to ensure the changes
happen. The corrections will be started as soon as possible, as time is key. Depending
on the severity of the hazards, and grading of the various equipment, materials, and
conditions, some aspects will be dealt with before others. We want to see the plant
become safer. After a certain period of time we will return to the site and observe any
changes being made. We have a schedule set in place to conduct our project and have
it completed within a reasonable time period. One of the ways we could improve up
future hazards is to require written job safety analysis like the one shown in figure 1.
Figure 1
We understand that a working plant is hard to stop and go, as it results in a loss,
but these changes would be necessary if the plant wants to continue operating. With the
changes will come a reduced rate of workplace incidents and overall safety for the
workplace. Our project only expects each section being worked on to be down for a
small period of time. In the following section, we will include a planned schedule to
conduct our project in the plant.
Project Schedule
There are 10 total areas in the plant, they are as follows:
1. Grinding Station 1
2. Grinding Station 2
3. Grinding Station 3
4. Cutting Station 1
5. Cutting Station 2
6. Cutting Station 3
7. Load/Unload Station
8. Filling Station
9. Packaging Station
10. Welding Station
Each station will get its own downtime and inspection. We plan on each station taking a
day to complete what we need to do, excluding fixing time. Each station will be down
the same amount of time. Each station will require 8 hours to work on. This is split in 4
different parts:
1.
2.
3.
4.
Halting Operation
Observation Period
Consulting
Consult with Operation Manager
Each section will have its own time required for completion. You can find these numbers
below. Since there are 10 stations, a full 10 days will be required to complete the overall
project minus the fixing stage. The fixing stage will require a certain amount of time
agreed upon by the Operation Manager and our team. This could be anywhere from a
week to a month depending upon the Operation Manager and higher-ups. Because
some urgency might be required, various fixes may be implemented on the same day.
Power down
Standard closing procedure
Vacate area
Inspect equipment
Inspect supplies/materials
Consulting: 4 hours
Review summaries
Present information to Operation Manager
Consult about hazards
Draft plan to correct
Finalize draft
Consult budget
Consult schedule
Finalize documents
Once each respective station is completed, we will move onto the fixing stage. Again,
the time required will depend upon the fixes required. We will give an estimation of 1
month for each and every fix to be implemented.
Project Resources
In order for our project to be successful we will need certain resources that will
help us within the project. The necessary resources for this project will include, but not
limited to:
Research
Observations
Results
This list of required resources should serve as the necessary items needed to conduct
our project. With everything listed at our disposal we will be able to proceed with the
project without any obstacles or interruptions.
WBS
helps its user visually see whole tree and its branch of task and work assigned or
needed for a certain project. WBS stands for Work Breakdown Structure.
Benefits of WBS:
smaller parts which makes it easier for project managers and organizations to properly
assign help and resources. For Manufacturing Plant, you have teams that consist of
Grinding Team, Cutting Team, Load/Unload Team and Processing Team. Here is an
overall WBS of all areas in the plant and how they correspond with each other.
Manufacturin
g Plant
Grinding
Team
Cutting Team
Load/Unload
Team
Processing
Team
Station 1
Station 1
Filling
Section
Station 2
Station 1
Packaging
Station
Station 3
Station 1
Welding
Station
Projected Budget:
We used Microsoft Project to draw out our Projected Project Plan of insuring Workplace
safety. Here are overview of all the processes we have scheduled to carry out in our
Project Schedule.
10. Stopping all equipment
11. Close examination of the tools
12. Checklist of hazards
13. Resume operation of equipment
14. Spectate employees working in current working conditions
15. Review what we learned
16. Analyze data
17. Consult with higher-ups about findings
18. See changes/improvements in real time
Cost: Each of our 9 section are at least day long procedure. Typical work day is
8 hours a day with 9 sections this would take about two week to complete. Each step
requires another step in place before our proper Workplace Safety procedures can be
implemented.
For example Stopping All Equipment is the first step which requires all machine
in the designated area to stop. This step requires minimum of 8 hours work shift that to
halt causing all employees to be paid normally but with no work being performed while
proper workplace safety precedes are being tested and implemented. To calculate the
cost, we have to include the number of employees+hourly rate to count minimum cost of
this step. We can use $10/hr rate to calculate the cost based on the number of
employees for 8 hours.
For second step we are doing close examinations in which station is examined.
For example each Grinding Station + Cutting Station are inspected and closely
examined for proper height, gear and tools to oversee current safety procedures
currently being deployed at the stations. Cost here is again same as above which is
cost of number of employees stationed at each station + hourly rate of those
employees.
Third step includes checklist of all hazards in which could take less than 8 hours
to complete but we are giving our self at least 8 hours to complete this step to take
necessary steps on proper OSHA guidelines. In this step we are ensuring each stations
are properly marked with their designated safety risk and tools needed to operate in
these stations.
Fourth step that overlaps with Resume Operations of Equipment is Training and
Education. This is the main set of step that includes proper training is being issued by
the manufacturing plant and our consulting is providing sufficient knowledge of OSHA
guidelines to all manager, supervisors and employees working on each stations. They
must be aware of all dangers, safety risk, knowledge of tools and machines. With
proper training completed it is must to resume operations at manufacturing plant as
downtime is huge cost deliverable for any company as no one can afford to stay shut for
a long period of time. Any company or plant can take huge losses in case of any miss
handling of employees safety and to ensure this mostly all plants and companies are
open to spending loads of resources of time and money to proper insure them self in
case any lawsuit falls on them during any accident.
Review step would include overview of all knowledge and procedures we saw
while consulting. Collecting sufficient information is the key here to ensure proper
consulting takes place to ensure data is analyzed properly. While this is not the most
expensive step it still requires Management team and consulting team to sit down and
review the data. Cost here would be the time spend with management of different
stations. Usually one manager is employed at each station.
Analyze data is critical to any consulting firm to ensure their work and services
are valued. Consulting with upper Management required proper knowledge of current
steps of running heavy machine while measuring hazards seen across all stations.
Second to last step is Consulting the Management would impact the most as any
change you suggest must pass with the management before its implemented in any firm
or manufacturing plant. Any mislead or confusing information can break or make the
contract, usually upper managements are not interested in outside firm educating them
on proper workplace procedures. Cost would be the heaviest here as Upper
Management salary is most high across all firms and organizations.
Last step is to see how the improvements that were reviewed, analyzed and
consulted with the managements made any difference. If any changes were not
accepted follow must be done to ensure proper workplace safety is being followed and
why a certain recommendations was accept or rejected.