Vous êtes sur la page 1sur 2

Federal Register / Vol. 72, No.

245 / Friday, December 21, 2007 / Notices 72699

also be viewed on the Commission’s would include economic analysis, DEPARTMENT OF ENERGY
Web site at http://www.ferc.gov using preparation of preliminary engineering
the ‘‘eLibrary’’ link. Enter the docket plans, and a study of environmental Federal Energy Regulatory
number excluding the last three digits in impacts. Based on the results of these Commission
the docket number field to access the studies, the Applicant would decide [ Project Nos. 12884–000 and 12920–000]
document. For assistance, call toll-free whether to proceed with the preparation
1–866–208–3676 or e-mail of a development application to Hydro Green Energy, LLC and FFP
FERCOnlineSupport@ferc.gov. For TTY, construct and operate the project. Project 31, LLC; Notice of Competing
call (202) 502–8659. A copy is also Applications Accepted for Filing and
available for inspection and r. Comments, Protests, or Motions To
Soliciting Comments, Motions To
reproduction at the address in item h Intervene: Anyone may submit
Intervene, and Protests
above. comments, a protest, or a motion to
m. Individuals desiring to be included intervene in accordance with the December 14, 2007.
on the Commission’s mailing list should requirements of Rules of Practice and Take notice that the following
so indicate by writing to the Secretary Procedure, 18 CFR 385.210, 385.211, hydroelectric applications have been
of the Commission. 385.214. In determining the appropriate filed with the Commission and are
n. Competing Preliminary Permit: action to take, the Commission will available for public inspection:
Anyone desiring to file a competing consider all protests or other comments a. Type of Applications: Preliminary
application for preliminary permit for a filed, but only those who file a motion Permit (Competing).
proposed project must submit the to intervene in accordance with the b. Applicants, Project Numbers, and
competing application itself, or a notice Commission’s Rules may become a Dates Filed: Hydro Green Energy, LLC
of intent to file such an application, to filed the application for Project
party to the proceeding. Any comments,
the Commission on or before the No.12884–000 on July 25, 2007.
protests, or motions to intervene must FFP Project 31, LLC filed the
specified comment date for the
be received on or before the specified application for Project No. 12920–000
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent comment date for the particular on August 6, 2007.
allows an interested person to file the application. c. The name of the Hydro Green
competing preliminary permit s. Filing and Service of Responsive Energy, LLC project is the ‘‘Mississippi
application no later than 30 days after Documents: Any filings must bear in all 6’’ Project. Name of the FFP Project 31,
the specified comment date for the capital letters the title ‘‘COMMENTS’’, LLC project is the Natchez Beam Light
particular application. A competing ‘‘RECOMMENDATIONS FOR TERMS Project. The projects would be located
preliminary permit application must AND CONDITIONS’’, ‘‘PROTEST’’, on the Mississippi River in Adams
conform with 18 CFR 4.30 and 4.36. ‘‘COMPETING APPLICATION’’ OR County, Mississippi and Concordia
o. Competing Development ‘‘MOTION TO INTERVENE’’, as Parish, Louisiana. Neither project uses a
Application: Any qualified development applicable, and the Project Number of dam or impoundment.
applicant desiring to file a competing the particular application to which the d. Filed Pursuant to: Federal Power
development application must submit to Act, 16 U.S.C. 791a–825r.
filing refers. Any of the above-named
the Commission, on or before a e. Applicants Contacts: For Hydro
specified comment date for the documents must be filed by providing Green Energy, LLC: Mr. Wayne F.
particular application, either a the original and the number of copies Krouse, Hydro Green Energy, LLC, 5090
competing development application or a provided by the Commission’s Richmond Avenue, #390, Houston, TX
notice of intent to file such an regulations to: The Secretary, Federal 77056, phone (877) 556–6566, and Mr.
application. Submission of a timely Energy Regulatory Commission, 888 James H. Hancock Jr., Balch & Bingham
notice of intent to file a development First Street, NE., Washington, DC 20426. LLP, 1710 Sixth Avenue North,
application allows an interested person A copy of any motion to intervene must Birmingham, AL 35203. For FFP Project
to file the competing application no also be served upon each representative 31, LLC: Mr. Dan Irvin, FFP Project 31,
later than 120 days after the specified of the Applicant specified in the LLC, 69 Bridge Street, Manchester, MA
comment date for the particular particular application. 01944, phone (978) 232–3536, and Ms.
application. A competing license t. Agency Comments: Federal, State, Maureen Winters, Project Manager,
application must conform with 18 CFR and local agencies are invited to file Devine Tarbell & Associates, 970 Baxter
4.30 and 4.36. comments on the described application. Boulevard, Portland, ME 04103.
p. Notice of Intent: A notice of intent f. FERC Contact: Kelly Houff, (202)
A copy of the application may be
must specify the exact name, business 502–6393.
obtained by agencies directly from the
address, and telephone number of the g. Deadline for filing comments,
prospective applicant, and must include Applicant. If an agency does not file protests, and motions to intervene: 60
an unequivocal statement of intent to comments within the time specified for days from the issuance date of this
submit, if such an application may be filing comments, it will be presumed to notice.
filed, either a preliminary permit have no comments. One copy of an All documents (original and eight
application or a development agency’s comments must also be sent to copies) should be filed with: Secretary,
application (specify which type of the Applicant’s representatives. Federal Energy Regulatory Commission,
application). A notice of intent must be Kimberly D. Bose,
888 First Street, NE., Washington, DC
served on the applicant(s) named in this 20426. Comments, protests, and
Secretary. interventions may be filed electronically
public notice.
mstockstill on PROD1PC66 with NOTICES

q. Proposed Scope of Studies Under [FR Doc. E7–24761 Filed 12–20–07; 8:45 am] via the Internet in lieu of paper; see 18
Permit: A preliminary permit, if issued, BILLING CODE 6717–01–P CFR 385.2001(a)(1)(iii) and the
does not authorize construction. The instructions on the Commission’s Web
term of the proposed preliminary permit site under the ‘‘e-Filing’’ link. The
would be 36 months. The work Commission strongly encourages
proposed under the preliminary permit electronic filings. Please include the

VerDate Aug<31>2005 18:37 Dec 20, 2007 Jkt 214001 PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 E:\FR\FM\21DEN1.SGM 21DEN1
72700 Federal Register / Vol. 72, No. 245 / Friday, December 21, 2007 / Notices

project number (P–12884–000 or P– k. Competing Preliminary Permit: consider all protests or other comments
12920–000) on any comments or Anyone desiring to file a competing filed, but only those who file a motion
motions filed. application for preliminary permit for a to intervene in accordance with the
The Commission’s Rules of Practice proposed project must submit the Commission’s Rules may become a
and Procedure require all intervenors competing application itself, or a notice party to the proceeding. Any comments,
filing documents with the Commission of intent to file such an application, to protests, or motions to intervene must
to serve a copy of that document on the Commission on or before the be received on or before the specified
each person in the official service list specified comment date for the comment date for the particular
for the project. Further, if an intervenor particular application (see 18 CFR 4.36). application.
files comments or documents with the Submission of a timely notice of intent p. Filing and Service of Responsive
Commission relating to the merits of an allows an interested person to file the Documents: Any filings must bear in all
issue that may affect the responsibilities competing preliminary permit capital letters the title ‘‘COMMENTS’’,
of a particular resource agency, they application no later than 30 days after ‘‘RECOMMENDATIONS FOR TERMS
must also serve a copy of the document the specified comment date for the AND CONDITIONS’’,
on that resource agency. particular application. A competing ‘‘PROTEST’’,‘‘COMPETING
h. Description of Projects: The project preliminary permit application must APPLICATION’’ OR ‘‘MOTION TO
proposed by Hydro Green Energy, LLC conform with 18 CFR 4.30 and 4.36. INTERVENE’’, as applicable, and the
would consist of: (1) 5 arrays, each l. Competing Development Project Number of the particular
consisting of ten, 100 kilowatt Application: Any qualified development application to which the filing refers.
hydrokinetic turbine units, for a total applicant desiring to file a competing Any of the above-named documents
installed capacity of 5 megawatts, (2) a development application must submit to must be filed by providing the original
proposed transmission line no greater the Commission, on or before a and the number of copies provided by
than 2000 feet from the ‘‘node’’ array to specified comment date for the the Commission’s regulations to: The
the shore, (3) a mooring system which particular application, either a Secretary, Federal Energy Regulatory
does not require the use of pilings to competing development application or a Commission, 888 First Street, NE.,
permanently attach the units to the notice of intent to file such an Washington, DC 20426. A copy of any
bedrock but instead uses tethers and application. Submission of a timely motion to intervene must also be served
Danforth type anchors, and (4) notice of intent to file a development upon each representative of the
appurtenant facilities. The Hydro Green application allows an interested person Applicant specified in the particular
Energy, LLC project would have an to file the competing application no application.
average annual generation of 32.873 later than 120 days after the specified q. Agency Comments: Federal, state,
gigawatt-hours, which would be sold to comment date for the particular and local agencies are invited to file
a local utility. application. A competing license comments on the described application.
The project proposed by FFP Project application must conform with 18 CFR A copy of the application may be
31, LLC would consist of: (1) 2,950 4.30 and 4.36. obtained by agencies directly from the
proposed 20 kilowatt Free Flow m. Notice of Intent: A notice of intent Applicant. If an agency does not file
generating units having a total installed must specify the exact name, business comments within the time specified for
capacity of 59 megawatts, (2) a proposed address, and telephone number of the filing comments, it will be presumed to
transmission line, (3) a mooring system prospective applicant, and must include have no comments. One copy of an
comprised of either free standing pilings an unequivocal statement of intent to agency’s comments must also be sent to
or existing infrastructure which will submit, if such an application may be
the Applicant’s representatives.
anchor the units, and (4) appurtenant filed, either a preliminary permit
facilities. The FFP Project 31, LLC application or a development Kimberly D. Bose,
project would have an average annual application (specify which type of Secretary.
generation of 258.42 gigawatt-hours, application). A notice of intent must be [FR Doc. E7–24762 Filed 12–20–07; 8:45 am]
which would be sold to a local utility. served on the applicant(s) named in this BILLING CODE 6717–01–P
i. Locations of Applications: A copy of public notice.
the application is available for n. Proposed Scope of Studies Under
inspection and reproduction at the Permit: A preliminary permit, if issued, DEPARTMENT OF ENERGY
Commission in the Public Reference does not authorize construction. The
Room, located at 888 First Street, NE., term of the proposed preliminary permit Federal Energy Regulatory
Room 2A, Washington, DC 20426, or by would be 36 months. The work Commission
calling (202) 502–8371. This filing may proposed under the preliminary permit
[Project Nos. 12885–000 and 12923–000]
also be viewed on the Commission’s would include economic analysis,
Web site at http://www.ferc.gov using preparation of preliminary engineering Hydro Green Energy, LLC and FFP
the ‘‘eLibrary’’ link. Enter the docket plans, and a study of environmental Project 34, LLC; Notice of Competing
number excluding the last three digits in impacts. Based on the results of these Applications Accepted for Filing and
the docket number field to access the studies, the Applicant would decide Soliciting Comments, Motions To
document. For assistance, call toll-free whether to proceed with the preparation Intervene, and Protests
1–866–208–3676 or e-mail of a development application to
FERCOnlineSupport@ferc.gov. For TTY, construct and operate the project. December 14, 2007.
call (202) 502–8659. A copy is also o. Comments, Protests, or Motions To Take notice that the following
available for inspection and Intervene: Anyone may submit hydroelectric applications have been
mstockstill on PROD1PC66 with NOTICES

reproduction at the address in item e comments, a protest, or a motion to filed with the Commission and are
above. intervene in accordance with the available for public inspection:
j. Individuals desiring to be included requirements of Rules of Practice and a. Type of Applications: Preliminary
on the Commission’s mailing list should Procedure, 18 CFR 385.210, 385.211, Permit (Competing).
so indicate by writing to the Secretary 385.214. In determining the appropriate b. Applicants, Project Numbers, and
of the Commission. action to take, the Commission will Dates Filed: Hydro Green Energy, LLC

VerDate Aug<31>2005 18:37 Dec 20, 2007 Jkt 214001 PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 E:\FR\FM\21DEN1.SGM 21DEN1