Académique Documents
Professionnel Documents
Culture Documents
i
if:,
or
li '.E* 04 ,0-iir,
sc
Ar
st
dr
--
I.
/41;
":
5 ..47. :ei
"f
lr
e:40
-1:4
41::: 44:41.
141.1144,
311
:(
1111 1 '1
1:11.44)1194,
4110
41.6
0.5!
e
40.
il 144
7:.
e7
a N.4
41/4' 4
-AV, 40, 44
It
'k
.4,
lir
t
444Skitv' tv
1 s.,
.0.
iftiq..16
'
0 '
'
*'" 317%%
Resources
PROJECT
MANAGEMENT
REFERENCE
MANUAL
REFERENCE MANUAL
CONTENTS
SUMMARY
GLOSSARY OF TERMS
INTRODUCTION
PLANNING A PROJECT
21
6.1 General
21
21
WHAT IS A PROJECT?
23
25
6.5 Networks
25
26
6.7 Estimating
27
27
28
PROJECT CONTROL
30
30
32
33
10
10
10
11
MANAGING A PROJECT
12
5.1 General
12
12
15
8.1 General
33
16
35
16
EXPEDITING A PROJECT
37
16
17
18
18
20
10 COMPLETING A PROJECT
APPENDICES
38
40
Estimates of costs
Budget allocations
Project reports
PLANNING PROJECTS
ORGANISATION ARRANGEMENTS
CONTROLLING PROJECTS
O Control means keeping the project on
track according to time, standard and bud-
Structure
matters.
O Work
Breakdown
The Client
DOCUMENTING A PROJECT
71 Calculations, data, records of discussions,
sketches, etc. are maintained on Technical
Officers as appropriate.
project.
FINALISING A PROJECT
[71 Project work is complete when:
time or EFT's.
completed
REFERENCE MANUAL
GLOSSARY OF TERMS
PROJECT OFFICER
Officer of a functional unit responsible for the performance of some aspect of project work.
BAR CHART
FUNCTIONAL MANAGER
PROJECT TEAM
The project officers assigned to the project, responsible to the Project Manager for management
expertise.
LIFECYCLE
STAGE
termination.
MILESTONES
Events within a project plan which serve as key indicators of planned progress.
STEERING COMMITTEE
The Project Director and the various Project Managers responsible for the management of the project.
NETWORK
TARGET
Specifically the "Project Evaluation Review Technique" but often applied to any network-based
planning technique.
TASK FORCE
Project Officers assigned to work full-time on a project under direct management and administrative
PHASE
PROJECT DIRECTOR
UNIT MANAGER
PROJECT MANAGER
REFERENCE MANUAL
lou INTRODUCTION
WHAT IS A PROJECT?
4p.
agement expertise.
and cross Unit and Divisional boundaries. Projects are often small to medium in scale but
complex. More consideration needs to be given
to secondary impacts and impacts outside the
Department. Sound project management is
still important.
These procedures formalise much of what
would be regarded as good project practice. But
without formal processes, good practice has
often lapsed in the face of urgency or expediency. The objective is not to tie officers up in
"red tape" or time wasting administration. It is
to encourage well thought out, efficiently managed and well documented projects.
Like anything new the procedures may seem
awkward at first and the temptation to fall
back on old ways of doing things will be
strong. Success will require the support of everyone involved. This will be essential if the
Department is to be business-like and efficient in the way it functions and in the
"product" it delivers.
REFERENCE MANUAL
thousands of people.
construction of a dam.
CI Construction
alr
11 Manufacturing
Design and development of products for
manufacturing.
systems etc.
11 Management
activities etc.
Information Systems
lier date.
and repairs.
the Lifecycle.)
ft-
REFERENCE MANUAL
includes:
the project.
MANAGEMENT BEGIN?
was adopted.
Two traps must be clearly recognised.
time.
takes.
ject undertaken and delegate the responsibility to the Project Director. A Unit
%b.
10
11
MANAGING A PROJECT
Figure I
5.1 GENERAL
LC)
a)
.011,
F-1
b.o
Project Manager.
71"
N-1
0/3
In most cases there will be a Project Director who has responsibility for initiating a
of its progress.
shown in Figure 2.
DIRECTOR
Division to manage the components of the project within that Division and provide the
12
Initiating a project.
13
Figure 2
be considered as an
WIN
Project
Director
rent
However adjustments,
amendments, additions
Unit
Manager
WHAT
(Project Plan)
financial year.
Project Director.
Divisional
Project
Manager
WHEN
(Project Schedule)
Unit
Project
Officer
MANAGER
reassess priorities.
HOW MUCH
(Budget Allocation)
plans.
direction.
formance.
OW.
14
avoid it?
15
REFERENCE MANUAL
be met.
Oa.
package plans.
cedural advice.
age performance.
Project Officers are accountable to their Unit
Manager for the administrative performance of
01.
COMMI1TEE
The Steering Committee is responsible for:
Identification of problems.
Assessment of progress.
16
17
REFERENCE MANUAL
"RP
1. Schedules
PROJECT
2. Project priority
3. Personnel resources
4. Technical opinions and performance
trade-offs
5. Administrative procedures
6. Personality
7. Costs
Schedules
later changed.
It is not sufficient to store heaps of paper in
folders. Some effort must be put into selecting,
18
Personnel Resources
the issue;
isation;
priority.
the alternatives ;
schedule.
parties.
Project Priority
priority.
operation.
to those concerned.
19
a resolution
REFERENCE MANUAL
the
agement.
6.1 GENERAL
Networks
Bar Charts
Budgets
PLANNING A PROJECT
plan are:
20
Targets
Cash Flows
the Cost
6.2 A LIFECYCLE
will go wrong.
at greater cost.
21