Vous êtes sur la page 1sur 2

Federal Register / Vol. 72, No.

232 / Tuesday, December 4, 2007 / Notices 68133

DEPARTMENT OF ENERGY There are two ways to become and interventions via the Internet in lieu
involved in the Commission’s review of of paper. See 18 CFR 385.2001(a)(1)(iii)
Federal Energy Regulatory this project. First, any person wishing to and the instructions on the
Commission obtain legal status by becoming a party Commission’s Web (http://
[Docket Nos. CP08–21–000] to the proceedings for this project www.ferc.gov) site under the ‘‘e-Filing’’
should, on or before the comment date link.
CenterPoint Energy Gas Transmission stated below, file with the Federal Comment Date: December 18, 2007.
Company; Notice of Application Energy Regulatory Commission, 888
Kimberly D. Bose,
First Street, NE., Washington, DC 20426,
November 27, 2007. a motion to intervene in accordance Secretary.
Take notice that on November 13, with the requirements of the [FR Doc. E7–23449 Filed 12–3–07; 8:45 am]
2007, CenterPoint Energy Gas Commission’s Rules of Practice and BILLING CODE 6717–01–P
Transmission Company (CEGT), 1111 Procedure (18 CFR 385.214 or 385.211)
Louisiana Street, Houston, Texas and the Regulations under the NGA (18
77002–5231, filed in Docket No. CP08– CFR 157.10). A person obtaining party DEPARTMENT OF ENERGY
21–000, an application pursuant to status will be placed on the service list
section 7(b) of the Natural Gas Act Federal Energy Regulatory
maintained by the Secretary of the
(NGA), to abandon its Lines ADT–2, Commission and will receive copies of Commission
ADT–6, ADT–8, ADT–10, and ADT–4, all documents filed by the applicant and [Docket Nos. CP08–28–000]
all located in Hemphill County, Texas, by all other parties. A party must submit
by sale to CenterPoint Energy Field 14 copies of filings made with the CenterPoint Energy Gas Transmission
Services, Inc. In conjunction with the Commission and must mail a copy to Company; Notice of Application
abandonment, CEGT seeks a the applicant and to every other party in
determination that the lines are November 27, 2007.
the proceeding. Only parties to the
gathering facilities exempt from the Take notice that on November 15,
proceeding can ask for court review of
Commission’s jurisdiction under NGA 2007, CenterPoint Energy Gas
Commission orders in the proceeding.
section 1(b), all as more fully set forth However, a person does not have to Transmission Company (CEGT), 1111
in the application, which is on file with intervene in order to have comments Louisiana Street, Houston, Texas
the Commission and open to public considered. The second way to 77002–5231, filed in Docket No. CP08–
inspection. This filing may also be participate is by filing with the 21–000, an application pursuant to
viewed on the Commission’s Web site at Secretary of the Commission, as soon as section 7(b) of the Natural Gas Act
http://www.ferc.gov using the possible, an original and two copies of (NGA), to abandon its Lines ADT–17,
‘‘eLibrary’’ link. Enter the docket comments in support of or in opposition AD–107, AD–107–A, AD–107–B, and its
number, excluding the last three digits, to this project. The Commission will Canadian Compressor Station, all
in the docket number field to access the consider these comments in located in Pittsburg County, Oklahoma,
document. For assistance, call (202) determining the appropriate action to be by sale to CenterPoint Energy Field
502–8659 or TTY, (202) 208–3676. taken, but the filing of a comment alone Services, Inc. In conjunction with the
Any questions regarding this will not serve to make the filer a party abandonment, CEGT seeks a
application should be directed to to the proceeding. The Commission’s determination that the facilities are
Lawrence O. Thomas, Director-Rates & rules require that persons filing gathering facilities exempt from the
Regulatory at CenterPoint Energy Gas comments in opposition to the project Commission’s jurisdiction under NGA
Transmission Co., P.O. Box 21734, provide copies of their protests only to section 1(b), all as more fully set forth
Shreveport, Louisiana 71151, or by the party or parties directly involved in in the application which is on file with
calling (318) 429–2804. the protest. the Commission and open to public
Pursuant to section 157.9 of the Persons who wish to comment only inspection. This filing may also be
Commission’s rules, 18 CFR 157.9, on the environmental review of this viewed on the Commission’s Web site at
within 90 days of this Notice the project should submit an original and http://www.ferc.gov using the
Commission staff will either: Complete two copies of their comments to the ‘‘eLibrary’’ link. Enter the docket
its environmental assessment (EA) and Secretary of the Commission. number, excluding the last three digits,
place it into the Commission’s public Environmental commentors will be in the docket number field to access the
record (eLibrary) for this proceeding; or placed on the Commission’s document. For assistance, call (202)
issue a Notice of Schedule for environmental mailing list, will receive 502–8659 or TTY, (202) 208–3676.
Environmental Review. If a Notice of copies of the environmental documents, Any questions regarding this
Schedule for Environmental Review is and will be notified of meetings application should be directed to
issued, it will indicate, among other associated with the Commission’s Lawrence O. Thomas, Director-Rates &
milestones, the anticipated date for the environmental review process. Regulatory at CenterPoint Energy Gas
Commission staff’s issuance of the final Environmental commentors will not be Transmission Co., P.O. Box 21734,
environmental impact statement (FEIS) required to serve copies of filed Shreveport, Louisiana 71151, or by
or EA for this proposal. The filing of the documents on all other parties. calling (318) 429–2804.
EA in the Commission’s public record However, the non-party commentors Pursuant to section 157.9 of the
for this proceeding or the issuance of a will not receive copies of all documents Commission’s rules, 18 CFR 157.9,
Notice of Schedule for Environmental filed by other parties or issued by the within 90 days of this Notice the
Review will serve to notify federal and Commission (except for the mailing of Commission staff will either: complete
mstockstill on PROD1PC66 with NOTICES

State agencies of the timing for the environmental documents issued by the its environmental assessment (EA) and
completion of all necessary reviews, and Commission) and will not have the right place it into the Commission’s public
the subsequent need to complete all to seek court review of the record (eLibrary) for this proceeding; or
federal authorizations within 90 days of Commission’s final order. issue a Notice of Schedule for
the date of issuance of the Commission The Commission strongly encourages Environmental Review. If a Notice of
staff’s FEIS or EA. electronic filings of comments, protests Schedule for Environmental Review is

VerDate Aug<31>2005 17:38 Dec 03, 2007 Jkt 214001 PO 00000 Frm 00012 Fmt 4703 Sfmt 4703 E:\FR\FM\04DEN1.SGM 04DEN1
68134 Federal Register / Vol. 72, No. 232 / Tuesday, December 4, 2007 / Notices

issued, it will indicate, among other associated with the Commission’s of 20-inch diameter station piping and
milestones, the anticipated date for the environmental review process. appurtenances at its existing Rayne
Commission staff’s issuance of the final Environmental commentors will not be Compressor Station in Acadia Parish,
environmental impact statement (FEIS) required to serve copies of filed Louisiana. Columbia Gulf proposes to
or EA for this proposal. The filing of the documents on all other parties. provide an additional 180 MMcf/d of
EA in the Commission’s public record However, the non-party commentors firm delivery capacity into Florida Gas
for this proceeding or the issuance of a will not receive copies of all documents Transmission Company, LLC’s (FGT)
Notice of Schedule for Environmental filed by other parties or issued by the system from Columbia Gulf’s East
Review will serve to notify federal and Commission (except for the mailing of Lateral system at the existing point of
state agencies of the timing for the environmental documents issued by the delivery to FGT, by increasing the
completion of all necessary reviews, and Commission) and will not have the right operating pressure from 840 psig to
the subsequent need to complete all to seek court review of the
federal authorizations within 90 days of 1008 psig, which is the authorized
Commission’s final order.
the date of issuance of the Commission Maximum Allowable Operating
The Commission strongly encourages
staff’s FEIS or EA. electronic filings of comments, protests pressure (the existing capacity will not
There are two ways to become and interventions via the Internet in lieu increase). In addition, Columbia Gulf
involved in the Commission’s review of of paper. See 18 CFR 385.2001(a) (1) (iii) requests authorization to modify its
this project. First, any person wishing to and the instructions on the existing point of delivery to FGT in
obtain legal status by becoming a party Commission’s Web (http:// Lafayette, Louisiana, by constructing an
to the proceedings for this project www.ferc.gov) site under the ‘‘e-Filing’’ additional tap on its East Lateral Line
should, on or before the comment date link. 400 and a large meter and
stated below, file with the Federal Comment Date: December 18, 2007. appurtenances. Columbia Gulf estimates
Energy Regulatory Commission, 888 the cost of construction to be $17.5
First Street, NE., Washington, DC 20426, Kimberly D. Bose,
million.
a motion to intervene in accordance Secretary.
Any questions regarding the
with the requirements of the [FR Doc. E7–23452 Filed 12–3–07; 8:45 am]
Commission’s Rules of Practice and application should be directed to
BILLING CODE 6717–01–P
Procedure (18 CFR 385.214 or 385.211) Fredric J. George, Lead Counsel,
and the Regulations under the NGA (18 Columbia Gulf Transmission Company,
CFR 157.10). A person obtaining party DEPARTMENT OF ENERGY P.O. Box 1273, Charleston, West
status will be placed on the service list Virginia 22030–0146, call (304) 357–
maintained by the Secretary of the Federal Energy Regulatory 2359 or fax (304) 357–3206.
Commission and will receive copies of Commission Any person or the Commission’s Staff
all documents filed by the applicant and [Docket No. CP08–26–000] may, within 60 days after the issuance
by all other parties. A party must submit of the instant notice by the Commission,
14 copies of filings made with the Columbia Gulf Transmission file pursuant to Rule 214 of the
Commission and must mail a copy to Company; Notice of Request Under Commission’s Procedural Rules (18 CFR
the applicant and to every other party in Blanket Authorization 385.214) a motion to intervene or notice
the proceeding. Only parties to the
November 23, 2007. of intervention and, pursuant to section
proceeding can ask for court review of
Take notice that on November 13, 157.205 of the Commission’s
Commission orders in the proceeding.
However, a person does not have to 2007, Columbia Gulf Transmission Regulations under the Natural Gas Act
intervene in order to have comments Company (Columbia Gulf), 5151 San (NGA) (18 CFR 157.205) a protest to the
considered. The second way to Felipe, Suite 2500, Houston, Texas request. If no protest is filed within the
participate is by filing with the 77056, filed in Docket No. CP08–26– time allowed therefore, the proposed
Secretary of the Commission, as soon as 000, a prior notice request pursuant to activity shall be deemed to be
possible, an original and two copies of sections 157.205 and 157.210 of the authorized effective the day after the
comments in support of or in opposition Federal Energy Regulatory time allowed for protest. If a protest is
to this project. The Commission will Commission’s regulations under the filed and not withdrawn within 30 days
consider these comments in Natural Gas Act for authorization to after the time allowed for filing a
determining the appropriate action to be construct, own, and operate new natural protest, the instant request shall be
taken, but the filing of a comment alone gas compression facilities, located in treated as an application for
will not serve to make the filer a party Acadia Parish, Louisiana, all as more authorization pursuant to Section 7 of
to the proceeding. The Commission’s fully set forth in the application, which the NGA.
rules require that persons filing is on file with the Commission and open
comments in opposition to the project to public inspection. The filing may also The Commission strongly encourages
provide copies of their protests only to be viewed on the Web at http:// electronic filings of comments, protests,
the party or parties directly involved in www.ferc.gov using the ‘‘eLibrary’’ link. and interventions via the Internet in lieu
the protest. Enter the docket number excluding the of paper. See 18 CFR 385.2001(a)(1)(iii)
Persons who wish to comment only last three digits in the docket number and the instructions on the
on the environmental review of this field to access the document. For Commission’s Web site (http://
project should submit an original and assistance, contact FERC at www.ferc.gov) under the ‘‘e-Filing’’ link.
two copies of their comments to the FERCOnlineSupport@ferc.gov or call
Kimberly D. Bose,
mstockstill on PROD1PC66 with NOTICES

Secretary of the Commission. toll-free, (886) 208–3676 or TTY, (202)


Environmental commentors will be 502–8659. Secretary.
placed on the Commission’s Columbia Gulf proposes to construct [FR Doc. E7–23426 Filed 12–3–07; 8:45 am]
environmental mailing list, will receive two 1,775 horsepower skid-mounted BILLING CODE 6717–01–P
copies of the environmental documents, compressor units, for a total of 3,550
and will be notified of meetings horsepower and approximately 200 feet

VerDate Aug<31>2005 17:38 Dec 03, 2007 Jkt 214001 PO 00000 Frm 00013 Fmt 4703 Sfmt 4703 E:\FR\FM\04DEN1.SGM 04DEN1