33926 Federal Register / Vol. 72, No.

118 / Wednesday, June 20, 2007 / Proposed Rules

airworthiness approvals for imports and information to the flightcrew in the provides terminating action for the
exports. The comment period closed on cockpit. However, we have been unsafe condition described in AD 2003–
June 11, 2007. informed that the navigation system 04–06, which was also addressed by the
By requests dated May 3, May 31, and manufacturer has developed effective previously mentioned NPRM, Docket
June 6, Hartzell Propeller, Inc. corrective actions to address the unsafe No. 2003–NM–67–AD. Therefore, that
(Hartzell), McCauley Propeller Systems condition identified in the NPRM. Since NPRM is redundant.
(McCauley), and the General Aviation we issued the NPRM, we have issued
FAA’s Conclusions
Manufacturers Association (GAMA), other rulemaking, which provides
respectively, asked that the comment corrective actions for the identified Upon further consideration, we have
period be extended by 60 days to permit unsafe condition. Accordingly, the determined that the proposed rule is not
a more careful review and consideration proposed rule is withdrawn. necessary. Accordingly, the NPRM is
of the proposed rule. FOR FURTHER INFORMATION CONTACT: hereby withdrawn.
The FAA has determined that Todd Thompson, Aerospace Engineer, Withdrawal of this NPRM constitutes
reopening the comment period for 45 International Branch, ANM–116, FAA, only such action, and does not preclude
days will allow Hartzell, McCauley, Transport Airplane Directorate, 1601 the agency from issuing another action
GAMA, and others sufficient time for a Lind Avenue SW., Renton, Washington in the future, nor does it commit the
more thorough review of applicable 98057–3356; telephone (425) 227–1175; agency to any course of action in the
issues and questions raised by the fax (425) 227–1149. future.
NPRM, and for the drafting of SUPPLEMENTARY INFORMATION: A Regulatory Impact
responsive comments. proposal to amend part 39 of the Federal
In order, therefore, to give all Since this action only withdraws a
Aviation Regulations (14 CFR part 39) to notice of proposed rulemaking, it is
interested persons additional time to add a new airworthiness directive (AD),
complete their comments, the FAA neither a proposed nor a final rule and
applicable to certain EMBRAER Model therefore is not covered under Executive
finds that it is in the public interest to EMB–135 and EMB–145 series
reopen the comment period for forty- Order 12866, the Regulatory Flexibility
airplanes, was published in the Federal Act, or DOT Regulatory Policies and
five (45) days. Register as a Notice of Proposed Procedures (44 FR 11034, February 26,
Issued in Washington, DC, on June 14, Rulemaking (NPRM) on March 11, 2004 1979).
2007. (69 FR 11549). The proposed rule would
Dorenda D. Baker, have required an inspection of the base List of Subjects in 14 CFR Part 39
Deputy Director, Aircraft Certification and support surfaces of the glide slope Air transportation, Aircraft, Aviation
Service. antenna and of certain electrical safety, Safety.
[FR Doc. 07–3050 Filed 6–15–07; 4:02 pm] connectors of the navigation system,
The Withdrawal
BILLING CODE 4910–13–P and applicable corrective actions if
necessary. That action resulted from Accordingly, the notice of proposed
reports of degradation in the rulemaking, Docket 2003–NM–67–AD,
DEPARTMENT OF TRANSPORTATION performance of the VOR/ILS/MB system published in the Federal Register on
due to the presence of moisture, dirt, March 11, 2004 (69 FR 11549), is
Federal Aviation Administration and corrosion between the base and the withdrawn.
support of the glide slope antenna and Issued in Renton, Washington, on June 13,
14 CFR Part 39 in the electrical connectors of the 2007.
[Docket No. 2003–NM–67–AD] navigation system. The proposed Ali Bahrami,
actions were intended to prevent the Manager, Transport Airplane Directorate,
RIN 2120–AA64 display of erroneous or misleading Aircraft Certification Service.
Airworthiness Directives; Empresa information to the flightcrew in the [FR Doc. E7–11928 Filed 6–19–07; 8:45 am]
Brasileira de Aeronautica S.A. cockpit due to degradation in the BILLING CODE 4910–13–P
(EMBRAER) Model EMB–135 and performance of the VOR/ILS/HM
EMB–145 Series Airplanes system.
Actions That Occurred Since the NPRM DEPARTMENT OF TRANSPORTATION
AGENCY: Federal Aviation
Was Issued
Administration, DOT. Federal Aviation Administration
ACTION: Proposed rule; withdrawal. Since the issuance of that NPRM, we
have received new data showing that 14 CFR Part 39
SUMMARY: This action withdraws a the degradation in the performance of
[Docket No. FAA–2007–28376; Directorate
notice of proposed rulemaking (NPRM) the VOR/ILS/MB system was not caused
Identifier 2007–NM–108–AD]
that proposed a new airworthiness by dirt and corrosion affecting the glide
directive (AD), applicable to certain slope antenna and certain navigation RIN 2120–AA64
EMBRAER Model EMB–135 and EMB– system connectors. The degraded
145 series airplanes. That action would performance was caused by a parasitic Airworthiness Directives; Boeing
have required an inspection of the base oscillation affecting an internal module Model 767–200, –300, and –300F Series
and support surfaces of the glide slope of the navigation system, and the Airplanes
antenna and of certain electrical navigation system manufacturer has AGENCY: Federal Aviation
connectors of the navigation system, provided service information detailing Administration (FAA), Department of
rwilkins on PROD1PC63 with PROPOSALS

and applicable corrective actions if proven corrective actions. Accordingly, Transportation (DOT).
necessary. Since the issuance of the we issued AD 2006–22–05 (71 FR ACTION: Notice of proposed rulemaking
NPRM, we have received new data 62907, October 27, 2006), which (NPRM).
showing that the proposed inspection superseded AD 2003–04–06,
and corrective actions will not eliminate amendment 39–13054 (68 FR 8539, SUMMARY: The FAA proposes to adopt a
the display of erroneous or misleading February 24, 2003). AD 2006–22–05 new airworthiness directive (AD) for

VerDate Aug<31>2005 17:23 Jun 19, 2007 Jkt 211001 PO 00000 Frm 00010 Fmt 4702 Sfmt 4702 E:\FR\FM\20JNP1.SGM 20JNP1
Federal Register / Vol. 72, No. 118 / Wednesday, June 20, 2007 / Proposed Rules 33927

certain Boeing Model 767–200, –300, regarding this proposed AD. Send your fuel tank explosions and consequent
and –300F series airplanes. This comments to an address listed in the loss of the airplane.
proposed AD would require a one-time ADDRESSES section. Include the docket
Relevant Service Information
inspection of each fuel quantity number ‘‘FAA–2007–28376; Directorate
indication system (FQIS) wire harness Identifier 2007–NM–108–AD’’ at the We have reviewed Boeing Special
connector for corrosion of the shield-to- beginning of your comments. We Attention Service Bulletin 767–28–
backshell connection, corrosion on the specifically invite comments on the 0087, dated February 5, 2007. The
ground jumper, and damage to the overall regulatory, economic, service bulletin describes procedures for
ground jumper; a loop resistance test of environmental, and energy aspects of a detailed inspection of each FQIS wire
each FQIS wire harness; and related the proposed AD. We will consider all harness connector for corrosion of the
investigative and corrective actions if comments received by the closing date shield-to-backshell connection,
necessary. This proposed AD results and may amend the proposed AD in corrosion on the ground jumper, and
from reports of corrosion of the out-tank light of those comments. damage to the ground jumper. The
wire harness of the spar connector We will post all comments we service bulletin also describes
backshell for the FQIS. We are receive, without change, to http:// procedures for corrective action if
proposing this AD to detect and correct dms.dot.gov, including any personal necessary. The corrective action is
corrosion of the out-tank wire harness, information you provide. We will also either upgrading the wire harness by
which could prevent correct grounding post a report summarizing each installing a backshell assembly upgrade
of the lightning shield and result in total substantive verbal contact with FAA kit, or replacing the wire harness with
loss of the electrical grounding between personnel concerning this proposed AD. a new wire harness that has an
the lightning shield and the airplane Using the search function of that web improved backshell.
structure. This condition, in site, anyone can find and read the The service bulletin also describes
combination with flammable fuel comments in any of our dockets, procedures for a loop resistance test of
vapors, could result in fuel tank including the name of the individual each FQIS wire harness, and the
explosions and consequent loss of the who sent the comment (or signed the following related investigative and
airplane. comment on behalf of an association, corrective actions if necessary.
business, labor union, etc.). You may • If the resistance is lower than
DATES: We must receive comments on review DOT’s complete Privacy Act certain limits specified in the service
this proposed AD by August 6, 2007. Statement in the Federal Register bulletin, the procedures include a
ADDRESSES: Use one of the following published on April 11, 2000 (65 FR detailed inspection for damage of the
addresses to submit comments on this 19477–78), or you may visit http:// wire harness between the spar
proposed AD. dms.dot.gov. connector and the wheel well ground
• DOT Docket Web site: Go to terminals; and repair or replacement if
http://dms.dot.gov and follow the Examining the Docket
necessary.
instructions for sending your comments You may examine the AD docket on • If the resistance is higher than
electronically. the Internet at http://dms.dot.gov, or in certain limits specified in the service
• Government-wide rulemaking Web person at the Docket Operations office bulletin, the procedures include doing a
site: Go to http://www.regulations.gov between 9 a.m. and 5 p.m., Monday joint resistance test of the rear spar
and follow the instructions for sending through Friday, except Federal holidays. ground jumper, and troubleshooting and
your comments electronically. The Docket Operations office (telephone repairing the ground jumper connection
• Mail: U.S. Department of (800) 647–5527) is located on the if necessary.
Transportation, Docket Operations, M– ground floor of the West Building at the Accomplishing the actions specified
30, West Building Ground Floor, Room street address stated in the ADDRESSES in the service information is intended to
W12–140, 1200 New Jersey Avenue, SE., section. Comments will be available in adequately address the unsafe
Washington, DC 20590. the AD docket shortly after the Docket condition.
• Fax: (202) 493–2251. Management System receives them. The special attention service bulletin
• Hand Delivery: Room W12–140 on refers to Cinch Service Bulletin
the ground floor of the West Building, Discussion
CN1156–28–02, Revision C, dated July
1200 New Jersey Avenue, SE., There have been several reports of 31, 2006, as an additional source of
Washington, DC, between 9 a.m. and 5 corrosion of the out-tank wire harness of service information for installing a
p.m., Monday through Friday, except the spar connector backshell for the fuel backshell assembly upgrade kit and
Federal holidays. quantity indication system (FQIS). replacing the wire harness.
Contact Boeing Commercial Investigations by the airplane
Airplanes, P.O. Box 3707, Seattle, manufacturer and the wire harness FAA’s Determination and Requirements
Washington 98124–2207, for the service supplier found that the corrosion was of the Proposed AD
information identified in this proposed caused by moisture at the connection We have evaluated all pertinent
AD. between the lightning shield, a tin- information and identified an unsafe
FOR FURTHER INFORMATION CONTACT: plated copper braid, and the aluminum condition that is likely to exist or
Philip Sheridan, Aerospace Engineer, backshell. The moisture wicked up the develop on other airplanes of this same
Systems and Equipment Branch, ANM– copper braid and was trapped between type design. For this reason, we are
130S, FAA, Seattle Aircraft Certification the ferrule and the backshell. Corrosion proposing this AD, which would require
Office, 1601 Lind Avenue, SW., Renton, of the out-tank wire harness, if not accomplishing the actions specified in
Washington 98057–3356; telephone detected and corrected, could prevent the service information described
rwilkins on PROD1PC63 with PROPOSALS

(425) 917–6441; fax (425) 917–6590. correct grounding of the lightning shield previously.
SUPPLEMENTARY INFORMATION: and result in total loss of the electrical
grounding between the lightning shield Costs of Compliance
Comments Invited and the airplane structure. This There are about 482 airplanes of the
We invite you to submit any relevant condition, in combination with affected design in the worldwide fleet.
written data, views, or arguments flammable fuel vapors, could result in The following table provides the

VerDate Aug<31>2005 17:23 Jun 19, 2007 Jkt 211001 PO 00000 Frm 00011 Fmt 4702 Sfmt 4702 E:\FR\FM\20JNP1.SGM 20JNP1
33928 Federal Register / Vol. 72, No. 118 / Wednesday, June 20, 2007 / Proposed Rules

estimated costs for U.S. operators to


comply with this proposed AD.

ESTIMATED COSTS
Number of
Average labor Cost per
Action Work hours U.S.-registered Fleet cost
rate per hour airplane airplanes

Detailed inspection ......................................... 1 .................. $80 $80 ............................ 202 $16,160.


Loop resistance test ....................................... 2 to 3 ........... $80 $160 to $240 ............. 202 $32,320 to $48,480.

Authority for This Rulemaking List of Subjects in 14 CFR Part 39 Inspection, Test, and Related Investigative
and Corrective Actions
Title 49 of the United States Code Air transportation, Aircraft, Aviation
(f) Within 48 months after the effective
specifies the FAA’s authority to issue safety, Safety.
date of this AD, do the actions in paragraphs
rules on aviation safety. Subtitle I,
The Proposed Amendment (f)(1) and (f)(2) of this AD, and do all
Section 106, describes the authority of
applicable related investigative and
the FAA Administrator. Subtitle VII, Accordingly, under the authority corrective actions, by accomplishing all the
Aviation Programs, describes in more delegated to me by the Administrator, actions specified in the Accomplishment
detail the scope of the Agency’s the FAA proposes to amend 14 CFR part Instructions of Boeing Special Attention
authority. 39 as follows: Service Bulletin 767–28–0087, dated
We are issuing this rulemaking under February 5, 2007. Do all applicable related
the authority described in Subtitle VII, PART 39—AIRWORTHINESS investigative and corrective actions before
Part A, Subpart III, Section 44701, DIRECTIVES further flight.
‘‘General requirements.’’ Under that (1) A detailed inspection of each FQIS wire
section, Congress charges the FAA with 1. The authority citation for part 39 harness connector for corrosion of the shield-
promoting safe flight of civil aircraft in continues to read as follows: to-backshell connection, corrosion on the
air commerce by prescribing regulations Authority: 49 U.S.C. 106(g), 40113, 44701. ground jumper, and damage to the ground
for practices, methods, and procedures jumper.
§ 39.13 [Amended]
the Administrator finds necessary for (2) A loop resistance test of each FQIS wire
safety in air commerce. This regulation 2. The Federal Aviation harness.
is within the scope of that authority Administration (FAA) amends § 39.13 Note 1: Boeing Special Attention Service
because it addresses an unsafe condition by adding the following new Bulletin 767–28–0087, dated February 5,
that is likely to exist or develop on airworthiness directive (AD): 2007, refers to Cinch Service Bulletin
products identified in this rulemaking Boeing: Docket No. FAA–2007–28376; CN1156–28–02, Revision C, dated July 31,
action. Directorate Identifier 2007–NM–108–AD. 2006, as an additional source of service
information for installing a backshell
Regulatory Findings Comments Due Date
assembly upgrade kit, and replacing the wire
We have determined that this (a) The FAA must receive comments on harness.
this AD action by August 6, 2007.
proposed AD would not have federalism
Alternative Methods of Compliance
implications under Executive Order Affected ADs
(AMOCs)
13132. This proposed AD would not (b) None.
have a substantial direct effect on the (g)(1) The Manager, Seattle Aircraft
Applicability Certification Office, FAA, has the authority to
States, on the relationship between the
national Government and the States, or (c) This AD applies to Boeing Model 767– approve AMOCs for this AD, if requested in
on the distribution of power and 200, –300, and –300F series airplanes, accordance with the procedures found in 14
certificated in any category; as identified in CFR 39.19.
responsibilities among the various
Boeing Special Attention Service Bulletin (2) To request a different method of
levels of government. 767–28–0087, dated February 5, 2007. compliance or a different compliance time
For the reasons discussed above, I for this AD, follow the procedures in 14 CFR
Unsafe Condition
certify that the proposed regulation: 39.19. Before using any approved AMOC on
(d) This AD results from reports of
1. Is not a ‘‘significant regulatory corrosion of the out-tank wire harness of the any airplane to which the AMOC applies,
action’’ under Executive Order 12866; spar connector backshell for the fuel quantity notify your appropriate principal inspector
2. Is not a ‘‘significant rule’’ under the indication system (FQIS). We are issuing this (PI) in the FAA Flight Standards District
DOT Regulatory Policies and Procedures AD to detect and correct corrosion of the out- Office (FSDO), or lacking a PI, your local
(44 FR 11034, February 26, 1979); and tank wire harness, which could prevent FSDO.
correct grounding of the lightning shield and
3. Will not have a significant result in total loss of the electrical grounding Issued in Renton, Washington, on June 13,
economic impact, positive or negative, between the lightning shield and the airplane 2007.
on a substantial number of small entities structure. This condition, in combination Ali Bahrami,
under the criteria of the Regulatory with flammable fuel vapors, could result in Manager, Transport Airplane Directorate,
Flexibility Act. fuel tank explosions and consequent loss of Aircraft Certification Service.
rwilkins on PROD1PC63 with PROPOSALS

We prepared a regulatory evaluation the airplane.


[FR Doc. E7–11926 Filed 6–19–07; 8:45 am]
of the estimated costs to comply with Compliance BILLING CODE 4910–13–P
this proposed AD and placed it in the (e) You are responsible for having the
AD docket. See the ADDRESSES section actions required by this AD performed within
for a location to examine the regulatory the compliance times specified, unless the
evaluation. actions have already been done.