Académique Documents
Professionnel Documents
Culture Documents
Duration
Start
Finish
79 days
Wed 15/07/15
Mon 02/11/15
7 days
Wed 15/07/15
Thu 23/07/15
3 days
Wed 15/07/15
Fri 17/07/15
Wed 12/08/15
21 days
Wed 15/07/15
21 days
Wed 15/07/15
Wed 12/08/15
21 days
Thu 13/08/15
Thu 10/09/15
and
distribution
F. Make
electricalgear
connection on
boiler
G. Prepare steel matting for boiler
15 days
Fri 11/09/15
Thu 01/10/15
5 days
Fri 24/07/15
Thu 30/07/15
foundation
H.
Prepare steel matting for tank
foundation
I. Prepare steel matting for chimney
10 days
Fri 24/07/15
Thu 06/08/15
15 days
Mon 20/07/15
Fri 07/08/15
4 days
Mon 10/08/15
Thu 13/08/15
12
foundation
J. Cast all foundations after matting is
completed
K. Allow concrete to set for 28 days
28 days
Fri 14/08/15
Tue 22/09/15
13
L. Construct chimney
21 days
Wed 23/09/15
Wed 21/10/15
Fri 25/09/15
6
7
8
9
10
11
14
3 days
Wed 23/09/15
15
3 days
Mon 28/09/15
Wed 30/09/15
3 days
Wed 23/09/15
Fri 25/09/15
7 days
Mon 28/09/15
Tue 06/10/15
18
and
groutgauges, oil and steam
P. Attach
valves,
high and low
Q.
Placesight
flue glasses,
gas ducting,
15 days
Thu 13/08/15
Wed 02/09/15
19
forced-draught
induced
draught
R.
Connect flue fan,
gas duct
to chimney
3 days
Thu 22/10/15
Mon 26/10/15
20
21 days
Thu 01/10/15
Thu 29/10/15
21
14 days
Wed 07/10/15
Mon 26/10/15
22
U. Test boiler
2 days
Fri 30/10/15
Mon 02/11/15
16
17
Project: Project1
Date: Tue 25/08/15
13 Jul '15
M T W
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 1
20 Jul '15
M T W
27 Jul '15
M T W
03 Aug '15
M T W
Project: Project1
Date: Tue 25/08/15
10 Aug '15
M T W
17 Aug '15
M T W
24 Aug '15
M T W
31 Aug '15
M T W
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 2
07 Sep '15
M T W
14 Sep '15
M T W
p '15
T
21 Sep '15
M T W
Project: Project1
Date: Tue 25/08/15
28 Sep '15
M T W
05 Oct '15
M T W
12 Oct '15
M T W
19 Oct '15
M T W
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 3
26 Oct '15
M T W
02 Nov '15
M T W