Académique Documents
Professionnel Documents
Culture Documents
Student Name:
Registration No:
Module No and Title of the module:
Assignment no and Title of the Assignment:
Section H2 of the Royal University of Bhutans Wheel of Academic Law provides the following
definition of academic dishonesty:
Academic dishonesty may be defined as any attempt by a student to gain an unfair advantage in
any assessment. It may be demonstrated by one of the following:
Collusion: the representation of a piece of unauthorized group work as the work of a single
candidate.
Commissioning: submitting an assignment done by another person as the students own work.
Duplication: the inclusion in coursework of material identical or substantially similar to material
which has already been submitted for any other assessment within the University.
False declaration: making a false declaration in order to receive special consideration by an
Examination Board or to obtain extensions to deadlines or exemption from work.
Falsification of data: presentation of data in laboratory reports, projects, etc., based on work
purported to have been carried out by the student, which have been invented, altered or copied by
the student.
Plagiarism: the unacknowledged use of anothers work as if it were ones own.
Examples are:
1/ Discuss the relative merits of the separate and the combined systems of sewage,
and give the
conditions favorable for the adoption of each one of them.
Separate Sewer System
do not require on-site pre-treatment
or storage of the wastewater
It provides high level of comfort and
hygiene for the users.
It doesnt provide breeding ground
for vectors.
Stormwater can be harvested for
domestic purpose.
Moderate operation cost
Limited or no risk of sewerage
overflow
Surface runoff and rainwater can be
collected separately and can be
used for landscaping and
agricultural purpose
2/ Write short notes on: financing the sewage projects and types of sewerage.
Financing sewer projects
When the project is being initiated, the funding is done by the government. All the
expenditure starting from the digging trenches to the laying of pipe is done by the
government.
After its construction it`s responsibility is the city corporation where its running,
maintenance and operation is being looked after. For the maintenance and
operation cost, the money has to come from the users. It is being collected in terms
of taxation.
Tax is being collected on the basis of the amount of water being consumed by a
particular household for example. Its done on the basis of water consumed as it is
rational logic that sewage produced is directly proportional to the water consumed.
Types of Sewer
i. Combined sewers
Its a large network of underground pipe network where all the wastewater from the
industries, domestic, stormwater runoff are collected in one pipe.
The wastewater collected are transported to the wastewater treatment plant where
all the collected wastewater are treated together and discharged to a water body.
The sewer is designed to maintain a certain velocity so that the waste particles will
not accumulate in the pipe. It is generally maintained at a velocity of 0.6 to 0.75
m/s. if the slope cannot be maintained, pumping stations are being installed.
The primary sewer is laid at a depth of 1.5 to 3 m.
It is suitable for urban areas with resources to implement, operate and maintain the
system.
3/ Note down the various problems of sewer works observed at field. Document how
the problems are
I.
II.
III.
IV.
V.
4/ Differentiate between sanitary sewage and storm sewage. Discuss and explain
the Rational Formula
and its limitations in calculating the quantities of storm sewage.
Sanitary Sewage
It is for the conveyance of domestic
wastewater
It needs pumping
Storm Sewage
It is for stormwater runoff
Pumping is optional
Rational Formula
Rational method is used in calculating the peak flows from small drainages less than
200 acres. It is most accurate for runoff estimates from small drainages with large
amounts of impervious area.
The Rational Formula is:
Q = Cf C i A
Where:
Q = Peak flow in cubic feet per second (cfs)
Cf = Runoff coefficient adjustment factor to account for
reduction of infiltration and other losses during high intensity
storms
C = Runoff coefficient to reflect the ratio of rainfall to surface
runoff
i = Rainfall intensity (in/hr)
A = Drainage area in acres (ac)
5/ Mention the various aspects you would keep in view when designing a sewer.
We should consider the following aspects while designing the system:
6/ What are the advantages of the egg-shaped section, and under what conditions
of flow, does it become useful? Will you recommend its use for sanitary sewers, and
if not, why?
The advantages of using egg-shaped section are:
Proportionate
Depth
in circular sewers
0.25
0.2
0.15
0.1
0.05
Proportionate Velocity
in egg-shaped sewers
0.701
0.615
0.517
0.401
0.257
0.698
0.627
0.544
0.44
0.295
Some important facts about velocity of flow in partial-flow sewers are as follow:
I.
II.
III.
IV.
V.
VI.
iii.
iv.
v.
First we should determine the elevation at which the sewer is to be laid. Initial
and final elevation is measured at the interior point of the connecting pipe in
the middle portion of the pipe.
Then we should calculate the pitch or the fall of the pipe per run. A drop
greater than per foot is not adequate as water will flow faster than solids,
while a slope to small, less than 0.003, will be sufficient to carry solids away.
The recommended pitch for 4" pipe is 1/8" to 1/4" per foot.
After that trench is dug out and bedding material like sand is being laid if
required to reduce the possibility of sag.
After the trench has been dug out, the laying of the pipe is begun. Bell end of
the pipe is placed uphill and laying is started from the lower elevation. The
pitch should be maintained.
After laying, check for any leakages, whether the pipe is damaged in the
process.
vi.
Then place the sand and/or gravel over the pipe, enough to cover at least 10
over the sewer pipe. Start compacting the material with a rammer or any
other compaction equipment suitable for the type of pipe being installed.
Note: It is important to install a warning tape over the first layer of
compacted soil, so others will be aware when excavating that a pipe
is located under the detectable warning tape.
d. Weight of the material: The material selected for sewer should have less specific
weight, which will make pipe light in weight. The lightweight pipes are easy for
handling and transport.
e. Imperviousness: the sewage pipe should be impervious so that there is no
seepage of the wastewater to the outside surrounding.
f. Economy and cost: sewage pipes should be less costly so that the projects costs
less.
g. Hydraulically efficient: The sewer shall have smooth interior surface to have less
frictional coefficient.
Reference
http://construction.about.com/od/Specifications/ss/Sewer-Pipe-Installation-How-ToInstall-A-Sewer-Pipe.htm#showall
http://www.google.bt/imgres?
imgurl=http://civilengineerspk.files.wordpress.com/2014/03/combined-sewersystem1.jpg%253Fw%253D620&imgrefurl=http://civilexperts.blogspot.com/2014/05/design-of-sewer
system.html&h=312&w=620&tbnid=Pi9CFEffBWE_hM:&docid=xO1LAeLOEGN8QM&
ei=0d_ZVcjNOuO7QarvqjYCA&tbm=isch&ved=0CCIQMygIMAhqFQoTCIj65vu7v8cCFWtH2wodKx8Ki
w