Académique Documents
Professionnel Documents
Culture Documents
INTRODUCTION
based from the United Nation Trade Commondity Statistics Database. There exist
a gap wherein the supply certainly cannot meet the demand in the ASEAN region.
Although eight manufacturing plants were identified on target market locations
producing BTX separately, the demand is still unsatisfied due its huge amount and
wide area of customers.
In line with this condition, the proponents are proposing a benzene, toluene
and xylenes manufacturing plant which will have a desired output to equally meet
the demand for BTX in the ASEAN region. The proposed BTX manufacturing plant
will process naphtha reformate into benzene, toluene and xylenes.
The proposed manufacturing plant will be strategically located in (7
6'4.32"S 11236'49.09"E) Manyar, Gresik Regency, East Java, Indonesia. One of
the reason is that East Java is considered to have the most attractive hourly wage
in Asia. This means that production costs are lower and thus, manufacturer profits
are higher. In terms of feedstock availability and accessibility, the target location is
70 kilometers from Tuban petrochemical plant which will be the primary supplier of
naphtha reformate feedstock. Tuban petrochemical plant has a rated output
capacity of 1 million metric tons of naphtha per year, a sufficient value to supply
the meet the required feedstock. Backup suppliers are PetroChina Dalian Refinery,
Liaoning, China and Ganga Rasayanie Pvt. Ltd., South India. Reserve supplier is
Petron Bataan Refinery, Philippines.The target location has sufficient manpower
and utilities to meet the requirements of the plant.
The target market of proposed plant are the ASEAN member countries
specifically Singapore, Cambodia, Indonesia and Vietnam. These four countries
were evaluated to have higher BTX import over export which indicates that these
countries have high demand for BTX. Singapore is the primary costumer for
benzene. Cambodia, Indonesia and Vietnam are the target consumers for toluene.
Cambodia and Indonesia are the target customer for xylenes.
The plant will continue to meet the demands for benzene, toluene and
xylenes of different countries of the target customers. The plant location is 1900
kilometers away from Singapore, 4700 kilometers from Vietnam and 4300
kilometers from Cambodia. These values indicate the efficient transportation of
BTX products to the target customers.
CHAPTER II
DESIGN OBJECTIVES
The main objective of the project proposal is to scientifically design a
Benzene, Toluene and Xylene (BTX) Manufacturing Plant with a desired output
capacity of 104,300 metric tons (MT) of BTX per annum.
Furthermore, the project proposal also targets to undertake the following
specific objectives taking into consideration technical, in order to achieve a realistic
technical, economic and environmental plant design.
1. To formulate three (3) design options for the Benzene, Toluene and
Xylene (BTX) Manufacturing Plant taking into consideration the following multiple
realistic constraints:
1.1 Technical Efficiency
1.2 Economic Feasibility
1.3 Environment Sustainability
2. To design the technical aspects of the plant taking into consideration the
following:
2.1 Plant Lay-out
2.2 Process Flow Diagram
2.3 Equipment Specification
2.4 Mass and Energy Balances
2.5 Required Capacity
2.6 Over-all Plant Efficiency
2.7 Technical Standards and Catalogues
To
formulate
recommendations.
the
corresponding
summary,
conclusions
and
CHAPTER III
TECHNICAL ASPECT
This chapter includes the calculation and preparation of the process flow
diagram, complete plant lay-out, equipment description and specifications, mass
balance and energy balance, required capacity and plant efficiency. Standards
were used to come up with a technically viable design. Technical catalogues were
used to carefully identify the design specifications of each equipment.
A. Design Option I
1. Process Description
Non-aromatics component along with the extracting solvent from naphtha will go to
raffinate stripping column to separate solvent then the solvent that was recovered
will be feed again to the extraction column while non-aromatics component will go
directly to the storage tank. On the other hand, aromatics components will pass
through the solvent recovery to remove solvent and improve the quality of
aromatics products. After this process, nearly pure aromatics will go through the
clay treater column to further remove present surface reactants. After all these
processes, aromatics will pass through the fractionation column to separate
Benzene, Toluene and Xylene by using the concept of difference in boiling point.
2. Plant Lay-out
Legend:
1 Area for Expansion
2 Process Area
3 Fire Fighting Unit
4 Control Room
5 Power Generation Unit
6 Laboratory
7 Plant Utilities
8 Waste Water Treatment
9 Emergency Water Storage
10 Workshop
11 Area for Expansion
12 Parking Area/Evacuation Area
13 Change Room
14 Canteen
15 Administration Building
16 Security
17 Material Recovery Facility
Height
Diameter
Orientation
Pressure
Temperature
Materials of Construction
Capacity
Flow
Type
Discharge Pressure
Temperature
Seal Type
Driver Type
Material
PUMP 1
90 gpm 120 gpm
Centrifugal
30psi
50C
Single mechanical seal
Standard motor
Carbon Steel
Height
Diameter
Temperature
Pressure
Application
Tray Type
Number of Trays
Tray Spacing
Tray thickness
Tray Material
Material of Construction
STRIPPING COLUMN
14m
.80m
56C
5.12 psi
Distillation
Sieve
34
0.6096 m
4.572x10-3m
Low and intermediate strength carbon
steel plates for pressure vessels
Carbon Steel Plates
Type
Process
Temperature
Pressure
Area
Material
Length
Shell
Inside Diameter
Incoming pipe
diameter
Outlet pipe diameter
Number of Tubes
Number of Passes
Material
Length
Tubes
Inside Diameter
Outside Diameter
Pitch
Incoming pipe
diameter
Outlet pipe diameter
Baffling Number of Baffles
Baffle spacing
COOLER 1
Liquid-Liquid
Distillation
25 C
15 psi
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
28
2, U-bend configuration
Copper, Schedule 40
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
1 in, schedule stainless steel
1 in, schedule stainless steel
2
1 in. schedule 40 stainless steel
Flow
Type
Pressure
Temperature
Material
PUMP 2
90 gpm 120 gpm
Rotary
30psi
20C
Cast iron
Flow
Type
Pressure
Temperature
Material
PUMP 3
90 gpm 120 gpm
Rotary
30psi
20C
Cast iron
Type
Process
Temperature
Pressure
Material
Area
Shell
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe
diameter
Outlet pipe diameter
Number of Tubes
Number of Passes
Material
Length
Inside Diameter
Outside Diameter
Pitch
Incoming pipe
diameter
Outlet pipe diameter
Number of Baffles
Baffle spacing
HEATER 1
Liquid-Liquid
Distillation
350 C
15 psi
Low and intermediate strength carbon steel
plates
1000ft2
Carbon Steel
2.1m
0.175m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
28
2, U-bend configuration
Copper, Schedule 40
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
1 in, schedule stainless steel
1 in, schedule stainless steel
2
1 in. schedule 40 stainless steel
Flow
Type
Discharge Pressure
Temperature
Material
PUMP 4
230 gpm
Rotary
30psi
20C
cast iron
Flow
Type
Discharge Pressure
Temperature
Seal Type
Driver Type
Material
PUMP 5
90 gpm 120 gpm
Centrifugal
30psi
50C
Single mechanical seal
Standard motor
Carbon Steel
Type
Process
Temperature
Pressure
Material
Area
Shell
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
Number of Tubes
Number of Passes
Material
Length
Inside Diameter
Outside Diameter
Pitch
Incoming pipe diameter
Outlet pipe diameter
Number of Baffles
Baffle spacing
COOLER 2
Liquid-Liquid
Distillation
25 C
15 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
28
2, U-bend configuration
Copper, Schedule 40
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
1 in, schedule stainless steel
1 in, schedule stainless steel
2
1 in. schedule 40 stainless steel
Flow
Type
Pressure
Temperature
Material
Speed
Power
PUMP 6
60gpm
Rotary
30psi
20C
Cast iron
1800rpm
25-20 hp
Flow
Type
Pressure
Temperature
Material
Speed
Power
PUMP 7
60gpm
Rotary
30psi
20C
Cast iron
1800rpm
25-20 hp
Flow
Type
Discharge Pressure
Temperature
Seal Type
Driver Type
Material
PUMP 8
75gpm
Centrifugal
5psi
50
Single mechanical seal
Standard motor
Carbon Steel
Type
Process
Temperature
Pressure
Material
Area
Shell
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe
diameter
Outlet pipe diameter
HEATER 2
Liquid-Liquid
Distillation
350C
15 psi
Low and intermediate strength carbon steel
plates
1000ft2
Carbon Steel
2.1m
0.175m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
Incoming pipe
diameter
Outlet pipe diameter
Number of Baffles
Baffle spacing
Tubes
Baffling
Number of Tubes
Number of Passes
Material
Length
Inside Diameter
Outside Diameter
Pitch
Incoming pipe diameter
Outlet pipe diameter
Number of Baffles
Baffle spacing
28
2, U-bend configuration
Copper, Schedule 40
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
1 in, schedule stainless steel
1 in, schedule stainless steel
2
1 in. schedule 40 stainless steel
Height
Diameter
Pressure
Temperature
Materials of Constructions
CARTRIDGE 1
7.6 m
1.2 m
15 psi
425C
Welded Carbon steels
Height
Diameter
Pressure
Temperature
Materials of Constructions
CARTRIDGE 2
7.6 m
1.2m
15 psi
425C
Welded Carbon steels
Height
Diameter
Orientation
Pressure
Temperature
Materials of Construction
Capacity
STORAGE VESSEL 3
3.70m
2.50m
Vertical
15 psi
100C
Carbon Steel Plates
600 gallons
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
Tubes
Baffling
PUMP 9
70gpm
Centrifugal
5psi
50C
Single mechanical seal
Standard Motor
Carbon Steel
Tubes
Baffling
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
55gpm
Centrifugal
5psi
50C
Single mechanical seal
Standard Motor
Carbon Steel
20m
1.039m
15psi
125C
3 beds with four stages
Carbon Steel Plates
Packed bed column
Height
Diameter
Orientation
Pressure
Temperature
Materials of Construction
Capacity
STORAGE VESSEL 4
5.20m
4.6m
Vertical
15 psi
125C
Carbon Steel Plates
3000 gallons
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
Liquid-Liquid
Distillation
25 C
15 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
Incoming pipe diameter
Outlet pipe diameter
Number of Baffles
Baffle spacing
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
1 in, schedule stainless steel
1 in, schedule stainless steel
2
1 in. schedule 40 stainless steel
Area
Shell
Tubes
Baffling
Flow
Type
Discharge Pressure
Temperature
Seal Type
Driver Type
Material
PUMP 11
50gpm
Centrifugal
5psi
50C
Single mechanical seal
Standard Motor
Carbon Steel
Flow
Type
Discharge Pressure
Temperature
Seal Type
Driver Type
Material
PUMP 12
60gpm
Centrifugal
5psi
50C
Single mechanical seal
Standard Motor
Carbon Steel
18m
0.98m
15 psi
160C
3 beds with four stages
Carbon Steel Plates
Packed bed column
Tubes
Baffling
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
Tubes
Baffling
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
Height
Diameter
Orientation
Pressure
Temperature
Materials of Construction
Capacity
STORAGE VESSEL 5
3.40m
2.20m
Vertical
15 psi
160
Carbon Steel Plates
400 gallons
Flow
Type
Discharge Pressure
Temperature
Seal Type
Driver Type
PUMP 13
10gpm
Centrifugal
0.4931psi
50C
Single mechanical seal
Standard Motor
Tubes
Baffling
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
Type
Process
Temperature
Pressure
Material
Area
Shell
Tubes
Baffling
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
STORAGE VESSEL
.70m
.50m
Vertical
15 psi
160C
Carbon Steel Plates
1 gallon
D. Material Balance
Assumptions:
1. All flow rates are steady.
2. Feed solvent and extracting solvent are immiscible.
3. Extracting solvent concentration remains constant.
4. All gases behave ideally.
5. No chemical reaction occurs during liquid-liquid extraction and extractive
distillation.
a. Pump 1
M1 = M2
M1 = 17,000 Kg/Hr
M2 = 17,000 Kg/Hr
b. Extraction Column
Raffinate Recovery = 36%
Feed + Lean Solvent = Raffinate + Rich Solvent
M2 + M3 = M4 + M5
17,000 Kg/Hr + 58,571 Kg/Hr = 0.36 (17,000 Kg/Hr) + M5
Rich Solvent = 69,451 Kg/Hr
M5 = 69,451 Kg/Hr
Raffinate = 6,300 Kg/Hr
M4 = 6,120 Kg/Hr
c. Stripper Column
Efficiency = 97%: Heuristics
Basis: Solvent-To-Extract Ratio = 2
M4 = M7 + M8
Rich Solvent = Extract + Solvent
Rich Solvent = 69,451 Kg/Hr
M8 = 2(M7)
69,451 Kg/Hr = M7 + M8
M7 = 23,150.33 Kg/Hr
d. Condenser 1
M9 = M7
M7 = 23,150.33 Kg/Hr
M9 = 23,150.33 Kg/Hr
e. Vessel 1
M9 = M10
M10 = 23,150.33 Kg/Hr
f. Pump 2
M10 = M11
M11 = 23,150.33 Kg/Hr
g. Pump 3
M12 = M13
M12 = 23,150.33 Kg/Hr
h. Pump 4
M8 = M14
M11 = 23,150.33 Kg/Hr
i. Pump 5
M5 = M15
M11 = 69,451 Kg/Hr
b. Heater 1
M18= M19
M19= 13,808.55 Kg/Hr
c. Clay Treater
Efficiency = 99%: Heuristics
M20 = 13,808.55 Kg/Hr
M21 = 13, 670.4645 Kg/Hr
d. Benzene Column
Efficiency = 93%: Heuristics
M21 = M22 + M23
Aromatics = 16.12% Benzene
M22 = M21 (93%) (16.12%)
M22 = (13,670.4645 Kg/Hr) (0.93) (0.1612)
M22 = 2,049.4214 Kg/Hr
e. Condenser 2
M22 = M24
M22 = 2,049.4214 Kg/Hr
M24 = 2,049.4214 Kg/Hr
f. Pump 7
M25 = M23
M23 =11,621.04314 Kg/Hr
M25 =11, 621.04314 Kg/Hr
g. Toluene Column
Efficiency = 93%: Heuristics
Aromatics = 72.52% Benzene
M25 = M26 + M27
M26 = (M21) (93%) (72.52%)
M26 = (13,670.4645Kg/Hr) (0.93) (0.7252)
M26 = 9,219.85 Kg/Hr
h. Condenser 3
M28 = M26
M26 = 9,219.85 Kg/Hr
M28 = 9,219.85 Kg/Hr
i. Pump 8
M29 = M27
M27 = 2,401.1931 Kg/Hr
M29 = 2,401.1931 Kg/Hr
j. Xylene Column
Efficiency = 93%: Heuristics
Aromatics = 11.36% Benzene
M29= M31 + M30
k. Condenser 4
M30= M32
M30= 1,444.2572 Kg/Hr
l. Condenser 5
M33 = M31
M31 = 956.9359 Kg/Hr
M18 = 956.9359 Kg/Hr
Pump 1
17,000
Extractor
69,451
Stripper
69,451
Condenser 1
23,150.33
Vessel 1
23,150.33
Pump 2
23,150.33
Pump 3
23,150.33
Pump 4
23,150.33
Pump 5
69,451
Recovery Column
23,150.33
Pump 6
13,808.55
Heater 1
13,808.55
Clay Treater
13,808.55
13,670.4645
Distillation Column
13,670.4645
2,049.4214
Condenser 2
2,049.4214
Pump 7
11,621.04314
Distillation Column
11,621.04314
Condenser 3
9,219.85
Pump 8
2,401.1931
Distillation Column
2,401.1931
Condenser 4
1,444.2572
Condenser 5
956.9359
13,808.55
9,219.85
1,444.2572
Benzene Product
2,049.4214 kg/hr
Toluene Product
9,219.85 kg/hr
1,444.2572 kg/hr
BTX Product
12,713.5286 kg/hr
E. Energy balance
This section contains the calculations for energy requirements of heat transfer
equipment used in the BTX Manufacturing Plant.
1. Heating Equipments
a. Stripper Column
Mass of incoming aromatics: 23,267 kg/hr
Specific heat of aromatics: 1.825 kj/kgoc
Temperature of incoming aromatics: 200oc
Temperature of leaving aromatics: 56 oc
Mass of incoming solvent: 45, 118.58 kg/hr
Specific heat of solvent: 1.997103 kj/g c
Temperature of incoming solvent: 200 oc
Temperature of leaving solvent: 56 oc
Specific heat of seawater: 3.985 kj/kgoc
Temperature of incoming cooling water: 17 oc
Temperature of leaving cooling water: 30 oc
Q = m Cp (T2 - T1)
Q = (58,571 Kg/Hr) (1.997103 kJ/g C) (473.15 K - 329.15 K)
Q = 168,444,014 kJ/hr
Q = 168,444,014 kJ/hr (1 hr/3600 s)
Q = 4,678.89 kW
b. Recovery Column
Cp of aromatics = 1.7867 kJ/Kg-K
T1 = 38C = 311.15 K
T2 = 56C = 329.15 K
Q1 = m Cp (T2 - T1)
Q1 = (50875.47 Kg/Hr) (1.7867 kJ/Kg-K) (450.15 K - 408.15 K)
Q1 = 1,636,185.64 kJ/hr
Q1 = 1,636,185.64 kJ/hr (1 hr/3600 s)
Q1 = 454.50 kW
c. Benzene Column
M = 13,987.2645 Kg/Hr
Cp of Benzene = 1.968 kJ/Kg-K
T1 = 425C = 698.15 K
T2 = 100C = 373.15 K
Q = m Cp (T2 - T1)
Q = (13,987.2645 Kg/Hr) (1.968kJ/Kg-K) (698.15 K - 373.15 K)
Q = 8,946,254.374 kJ/hr
Q = 8,946,254.374 kJ/hr (1 hr/3600 s)
Q = 2,485.07066 kW
d. Toluene Column
M = 9,433.5147.28 Kg/Hr
Cp of Toluene = 1.72 kJ/Kg-K
T1 = 100C = 373.15 K
T2 = 125C = 398.15 K
Q = m Cp (T2 - T1)
Q = (9,433.5147 Kg/Hr) (1.72 kJ/Kg-K) (398.15 K - 373.15 K)
Q = 405,641 kJ/hr
Q = 405,641 kJ/hr (1 hr/3600 s)
Q = 112.68 kW
e. Xylene Column
M = 2.096.9148 Kg/Hr
Cp of Xylene = 1.72 kJ/Kg-K
T1 = 125C = 398.15 K
T2 = 160C = 433.15 K
Q = m Cp (T2 - T1)
Q = (2.096.9148 Kg/Hr) (1.72 kJ/Kg-K) (433.15 K - 398.15 K)
Q = 126,224.21 kJ/hr
Q = 126,224.21 kJ/hr (1 hr/3600 s)
Q = 35.07 kW
f. Boiler
Q = (4, 678.89 + 454.50 + 2,424.4592 + 112.68 + 35.07) kW
Q = 3,342.2692 kW
Cp of steam = 1.996 kJ/Kg-K
T1 = 100C = 373.15 K
T2 = 350C = 623.15 K
Q = m Cp (T2 - T1)
342.2692 kW (1 kJ/s / 1 kW) (3600s/1 hr) = (Ms) (1.996 kJ/Kg-K) (623.15 K 373.15 K)
Ms = 2,469.2769 kg/hr
Stripping
4, 678.89
Solvent Recovery
454.50
Benzene Distillation
2,424.4592
Toluene Distillation
35.07
Xylene Distillation
112.68
7,705.5992 kW
2. COOLING EQUIPMENT
a. Stripper Column
Mass of incoming aromatics: 23,267 Kg/Hr
Specific heat of aromatics: 1.825 kj/kgoc
Temperature of incoming aromatics: 200OC
Temperature of leaving aromatics: 56 OC
Mass of incoming solvent: 45, 118.58 Kg/Hr
Specific heat of solvent: 1.997103 kj/g c
Temperature of incoming solvent: 200 OC
Temperature of leaving solvent: 56 OC
Specific heat of seawater: 3.985 kj/kgoC
Temperature of incoming cooling water: 17 OC
Temperature of leaving cooling water: 30 OC
[mCp(T2-T1)]AROMATICS + [mCp(T2-T1)]SOLVENT = [mCp(T2-T1)]CW
(23,267 Kg/Hr)(1.825 kJ/kgOC)(200OC-56 OC) + (45, 118.58 Kg/Hr)(1.997103
kJ/g C)(200OC-56 OC) = m (3.985 kJ/kgOC)(30 OC-17 OC)
b. Recovery Column
Mass of incoming aromatics: 69,771 Kg/Hr
Specific heat of aromatics: 1.825 kj/kgoc
Temperature of incoming aromatics: 56OC
Temperature of leaving aromatics: 38OC
Mass of incoming solvent: 58,571 Kg/Hr
Specific heat of solvent: 1.997103 kj/g c
Temperature of incoming solvent: 56 OC
Temperature of leaving solvent: 38 OC
Specific heat of seawater: 3.985 kj/kgoc
Temperature of incoming cooling water: 17 OC
Temperature of leaving cooling water: 30 OC
[mCp(T2-T1)]AROMATICS + [mCp(T2-T1)]SOLVENT = [mCp(T2-T1)]CW
(69,771 Kg/Hr)(1.825 kJ/kgOC)(56OC-38OC) + (58,571 Kg/Hr)(1.997103 kJ/g
C)(56OC-38OC) = m (3.985 kJ/kgOC)(30 OC-17 OC)
mCW = 258, 783.1112 Kg/hr
QA = 636.1129 KJ/s
QS = 584. 862 KJ/s
d. Benzene Column
Mass of incoming benzene: 2,096.9148 Kg/Hr
Incoming benzene temperature: 100c
Leaving benzene temperature: 25c
Specific heat of benzene: 1.968 kj/kgok
Incoming cooling water temperature: 30OC
Leaving cooling water temperature: 17 OC
Specific heat of sea water: 3.985 kj/kgoc
[mCp(T2-T1)]BW= [mCp(T2-T1)]CW
(2,096.9148 Kg/Hr)(1.968 kJ/kgOC)(100OC-25 OC) = m(3.985 kJ/kgOC)(30OC-17
OC)
e. Toluene Column
Mass of incoming toluene: 2,096.9148 Kg/Hr
Incoming toluene temperature: 125c
Leaving toluene temperature: 25c
Specific heat of toluene: 1.72 kj/kgoc
Incoming cooling water temperature: 30OC
Leaving cooling water temperature: 17 OC
Specific heat of sea water: 3.985 kj/kgoc
[mCp(T2-T1)]T= [mCp(T2-T1)]CW
(9,433.5147Kg/Hr)(1.72 kJ/kgOC)(125 C-25 C) = m(3.985 kJ/kgOC)(30OC-17 OC)
mCW = 31,320.614 Kg/hr
QT = 450.712 KJ/s
QCW = 450.712 KJ/s
f. Xylene Column
Mass of incoming xylene: 1,477.7265 Kg/Hr
Incoming xylene temperature: 160c
Leaving xylene temperature: 25c
Specific heat of xylene: 1.72 kj/kgoc
Incoming cooling water temperature: 30OC
Leaving cooling water temperature: 17 OC
Specific heat of sea water: 3.985 kj/kgoc
[mCp(T2-T1)]X= [mCp(T2-T1)]CW
(1,477.7265 Kg/Hr)(1.72 kJ/kgOC )(160C-25 C) = m(3.985 kJ/kgOC)(30OC-17 OC)
mCW = 6,738.980516 Kg/hr
Qx = 95.31 KJ/s
QCW = 95.31 KJ/s
g. C9+ Tank
mass of incoming C9+ aromatics: 979.1085 Kg/Hr
incoming C9+ aromatics temperature: 160C
Stripping
1,698.491 kW
Solvent Recovery
636.1129 kW
Benzene Distillation
85.97 kW
Toluene Distillation
450.712 kW
Xylene Distillation
95.31 kW
C9+ Aromatics
64.254 kW
3,021.8499 kW
F. Capacity Calculation
Feed Surge Tank
Feed = 17,000 kg/hr
= 759 kg/m3
= 870 kg/m
Minimum Level = 50%
V = 1, 444.2572 kg/hr (1 m/870 kg) (1.5)
V = (2.49 m3 / hr) (24 hr / day)
V = 59.76
G. Plant Efficiency
The plant efficiency can be calculated from the mass balance data:
Efficiency = (output)/ (input) x 100%
Efficiency = (BTX)/Naphtha Reformate x 100%
Efficiency = (12,713.5286 kg/hr) / (17000 kg/hr) x 100%
Efficiency = 74.79 %
2. Design Option II
A. Process Description
B. Plant Lay-out
Legend:
1 Area for Expansion
2 Process Area
3 Fire Fighting Unit
4 Control Room
5 Power Generation Unit
6 Laboratory
7 Plant Utilities
8 Waste Water Treatment
9 Emergency Water Storage
10 Workshop
11 Change Room
Area for Expansion
12 Parking Area/Evacuation Area
13 Canteen
14 Administration Building
15 - Area for Expansion
16 Security
17 Material Recovery Facility
C. Equipment Specification
Specification Sheet No. 1
Shell Material
Design Temperature
Design Pressure
Diameter
Length
Orientation
VESSEL A
A515 (Carbon Steel Plates for pressure
vessels for intermediate and higher
temperature service)
can withstand 150C
15psig
8 feet
14 feet
vertical
Design Temperature
Design Pressure
Diameter
Length
Orientation
PUMP B
Inline pump
Carbon Steel
175
300 gpm
Standard motor
Type
Material
Maximum Temperature
Maximum capacity
Driver Type
PUMP C
Inline pump
Carbon Steel
175
60 GPM
Standard motor
Type
Material
Maximum Temperature
Maximum capacity
Driver Type
PUMP D
Inline pump
Carbon Steel
175
20 gpm
Standard motor
Type
Material
Maximum Temperature
Maximum capacity
Driver Type
PUMP E
Inline pump
Carbon Steel
175
100 gpm
Standard motor
Type
Tube Material
Design Pressure
Design Temperature
Heat Duty
Boiler
Fire-tube boiler
A214 (Electric-resistance-welded
carbon steel heat exchanger and
condenser tubes)
500 psig
400C
25 million BTU per hour
Number of tray
Column temperature
Pressure
Height
Diameter
Tray Material
Feed tray
Type of tray
Tray spacing
Hole diameter
Hole spacing
Tray thickness
Weir height
STRIPPING COLUMN
A515 (Carbon Steel Plates for pressure
vessels for intermediate and higher
temperature service)
30
56
5psig
14m
1.25m
A285C (Low and intermediate strength
carbon steel plates for pressure
vessels.)
5th from the bottom
bubble cap tray
15.75in
5mm
15mm (triangular)
3mm
45 mm
D. Material Balance
Assumptions:
1. All flow rates are steady.
2. Feed solvent and extracting solvent are immiscible.
3. Extracting solvent concentration remains constant.
4. All gases behave ideally.
5. No chemical reaction occurs during liquid-liquid extraction and extractive
distillation.
Table 5. Aromatics Composition of Reformate
Benzene
11.98 %
Toluene
53.88 %
Xylene
8.44 %
C9 aromatics
5.00 %
Paraffin
20.7 %
j. Pump 3
M6 = M9
M6 = 56,615.95 kg/hr - - - - - - - - - - mass of aromatics
M9 =56,615.95 kg/hr - - - - - - - - - - mass of aromatics
k. Stripper Column
recovery = 99.85% of solvent
rich solvent = aromatics + solvent recovered
M6 = M10 + M11
56,616.95 = M10 + 42,875*0.9985
M10 = 13,806.26 kg/hr - - - - - - - - - - mass of aromatics
M11 = 42,810.69 kg/hr - - - - - - - - - - mass of mass of stripped solvent
o. Pump 6
M15 = M18
M15 = 11,657.60 kg/hr - - - - - - - - - - mass of mixed toluene, xylene &C9
M18 = 11,657.60 kg/hr - - - - - - - - - - mass of mixed toluene, xylene &C9
r. Pump 8
M20 = M23
M20 = 2,694.39 kg/hr - - - - - - - - - mass of mixed xylene &C9 aromatics
M23 = 2,694.39 kg/hr - - - - - - - - - mass of mixed xylene &C9 aromatics
3,356.93
42,810.69
13,599.17
1,941.57
1,912.45
8,963.21
8,828.76
1,404.04
1,382.98
1,941.57
8,963.21
1,404.04
12,308.82 kg/hr
E. Energy balance
This section contains the calculations for energy requirements of heat
transfer equipment used in the BTX Manufacturing Plant.
HEATING EQUIPMENT
a. Extractive Distillation Column
temperature of column:150 OC
temperature of incoming reformate: 50 OC
temperature of incoming solvent: 50 OC
specific heat of reformate: 1.7867 kJ/kgOC
specific heat of solvent: 4.184 kJ/kgOC
mass of reformate: 17,150 kg/hr
mass of solvent: 42,875 kg/hr
specific heat of steam: 1.996 kJ/kgOC
temperature of incoming steam: 300 OC
temperature of leaving steam: 100 OC
Extractive Distillation
Column
Benzene Fractionation
Column
Toluene Fractionation
Column
Xylene Fractionation
Column
Total energy requirement
851.16
mass of steam
requirement
52,612.95
148,717.99
2,456.33
501,477.59
1,607.30
79,943.22
392.53
724389.96 kW
57,069.11
COOLING EQUIPMENT
a. Non-aromatics Cooler
mass of incoming non-aromatics: 3,408.05 kg/hr
incoming non-aromatics temperature: 150 OC
leaving non-aromatics temperature: 30 OC
specific heat of non-aromatics: 1.7867 kJ/kgOC
incoming cooling water temperature: 17 OC
leaving cooling water temperature: 30 OC
specific heat of sea water: 3.985 kJ/kgOC
b. Aromatics Cooler
mass of incoming non aromatics: 13,806.26 kg/hr
incoming aromatics temperature: 56 OC
leaving aromatics temperature: 30 OC
specific heat of aromatics: 1.825 kJ/kgOC
incoming cooling water temperature: 17 OC
c. Stripper Column
mass of incoming aromatics: 13741.95 kg/hr
specific heat of aromatics: 1.825 kJ/kgOC
temperature of incoming aromatics:150 OC
temperature of leaving aromatics: 56 OC
mass of incoming solvent: 42,875 kg/hr
specific heat of solvent: 4.184 kJ/kgOC
temperature of incoming solvent: 150 OC
temperature of leaving solvent: 56 OC
specific heat of seawater: 3.985 kJ/kgOC
temperature of incoming cooling water: 17 OC
temperature of leaving cooling water: 30 OC
heat lost by aromatics and solvent is equal to heat gained by cooling water
[mCp(T2-T1)]AROMATICS + [mCp(T2-T1)]SOLVENT = [mCp(T2-T1)]CW
13,741.95*1.825*(150-56) + 42,875*4.184*(150-56) = m*3.985*(30-17)
m = 371,006.61 kg/hr - - - - - - - - - - required mass of cooling water
QA = 654.84 kJ/s - - - - - - - - - - heat loss by aromatics
QA = 4,684.09 kJ/s - - - - - - - - - - heat loss by solvent
QCW = 5,338.89 kJ/s - - - - - - - - - - heat gained by cooling water
d. Benzene Cooler
mass of incoming benzene: 1,941.57 kg/hr
incoming benzene temperature: 95 OC
leaving benzene temperature: 30 OC
specific heat of benzene: 1.856 kJ/kgOC
incoming cooling water temperature: 17 OC
leaving cooling water temperature: 30 OC
specific heat of sea water: 3.985 kJ/kgOC
e. Toluene Cooler
mass of incoming toluene: 8,963.21 kg/hr
incoming toluene temperature: 125 OC
leaving toluene temperature: 30 OC
specific heat of toluene: 1.809 kJ/kgOC
incoming cooling water temperature: 17 OC
leaving cooling water temperature: 30 OC
specific heat of sea water: 3.985 kJ/kgOC
f. Xylene Cooler
mass of incoming xylene: 1,404.04 kg/hr
incoming xylene temperature: 155 OC
leaving xylene temperature: 30 OC
specific heat of xylene: 1.841 kJ/kgOC
incoming cooling water temperature: 17 OC
leaving cooling water temperature: 30 OC
g. C9 Aromatics
mass of incoming C9+ aromatics: 1,290.35 kg/hr
incoming C9+ aromatics temperature: 155C
leaving C9+ aromatics temperature: 30C
specific heat of C9+ aromatics: 1.72 kJ/kgOC
incoming cooling water temperature: 30OC
leaving cooling water temperature: 17 OC
specific heat of sea water: 3.985 kJ/kgOC
[mCp(T2-T1)]T= [mCp(T2-T1)]CW
1,290.35*1.72*(155C-30 C) = m3.985*(30OC-17 OC)
mCW = 5,355.183 Kg/hr
QC9+ = 77.0625 KJ/s
QCW = 77.0625 KJ/s
Non-aromatics Cooler
Aromatics Cooler
Stripper Column
Benzene Cooler
Toluene Cooler
Xylene Cooler
C9+ Tank
Total energy requirement
202.97 kW
181.97 kW
654.84 kW
65.06 kW
427.88 kW
89.75 kW
77.0625 kW
1,609.6525 kW
A. Capacity Calculation
a. Feed Surge Tank
Feed = 17,150 kg/hr
= 759 kg/m3
Minimum Level = 50%
V = feed rate * time * (1m3/759kg)
= 17,150 * 2 * (1m3/759kg)
V = 45 m3
b. Non-aromatic Vessel
Feed = 3408.05 kg/hr
= 845 kg/m3
Minimum Level = 50%
V = feed rate * time * (1m3/845kg)
= 3408.05 * 2 * (1m3/845kg)
V = 8.07 m3
Mass of cooling
water requirement
14104.81
12645.63
371006.61
4521.40
29734.05
6236.94
14104.81
451754.25
c. Aromatic Vessel
Feed = 13,806.26 kg/hr
= 874 kg/m3
Minimum Level = 50%
V = feed rate * time * (1m3/874 kg)
= 13,806.26 * 2 * (1m3/874 kg)
V = 31.59 m3
d. Benzene Vessel
Feed = 1,941.75 kg/hr
= 876.5 kg/m3
Minimum Level = 50%
V = feed rate * time * (1m3/876.5 kg)
= 1,941.75 * 2 * (1m3/876.5 kg)
V = 4.43 m3
e. Toluene Vessel
Feed = 8,963.21 kg/hr
= 866.9 kg/m3
Minimum Level = 50%
V = feed rate * time * (1m3/866.9 kg)
= 8,963.21 * 2 * (1m3/866.9 kg)
V = 21.67 m3
f. Xylene Vessel
Feed = 1,404.04 kg/hr
= 864 kg/m3
Minimum Level = 50%
V = feed rate * time * (1m3/864kg)
= 1,404.04 * 2 * (1m3/864kg)
V = 3.25 m3
Efficiency =
100%
1912.45+8828.76+1382.98
17150
100%
= 70.69%
B. Plant Lay-out
Legend:
1 Process Area
2 Fire Fighting Unit
3 Control Room
4 Power Generation Unit
5 Laboratory
6 Plant Utilities
7 Waste Water Treatment
8 Emergency Water Storage
9 Parking Area/Evacuation Area
10 Workshop
11 Change Room
Area for Expansion
12 Canteen
13 Administration Building
14 Material Recovery Facility
15 Gate 1
16 Security
17 Gate 2
18 Area for Expansion
C. Equipment Specification
Specification Sheet No. 1
PUMP 1
Flow
Type
Discharge Pressure
Temperature
Seal Type
Driver Type
Material
120 gpm
Centrifugal
30psi
100C
Single mechanical seal
Standard motor
Carbon Steel
17 meters
0.93 meters
120 psi
200C
3 beds with four stages
Carbon Steel Plates
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
Liquid-Liquid
Distillation
100 kW
150 C
30 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
6.09 meters
0.44 meters
30 psi
100C
Sieve
18
0.02 m
0.005 m
Low and intermediate strength carbon
steel plates
Carbon Steel Plates
PUMP 2
120 gpm
Centrifugal
45 psi
150 C
Single mechanical seal
Standard motor
Carbon Steel
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
Liquid-Liquid
Distillation
100 kW
200 C
45 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
Type
Length
Diameter
Oreintation
Pressure
Temperature
Material of Construction
Capacity
SEPARATOR
Gas-Liquid
4.80 meters
1 meter
Horizontal
30 psi
150 C
Carbon Steel Plates
5000 gallons
WATER SEPARATOR
Liquid-Liquid
4.80 meters
1 meter
Horizontal
30 psi
150 C
Carbon Steel Plates
5000 gallons
10 meters
1.2 meters
45 psi
200 C
Sieve
30
0.04 m
0.002 m
Low and intermediate strength carbon
steel plates
Carbon Steel Plates
120 gpm
Centrifugal
65 psi
200 C
Single mechanical seal
Standard motor
Carbon Steel
14 meters
3 meters
55 psi
200 C
Sieve
33
0.40 m
0.005 m
Low and intermediate strength carbon
steel plates
Stainless Steel
120 gpm
Centrifugal
65 psi
200 C
Single mechanical seal
Standard motor
Carbon Steel
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
Liquid-Liquid
Distillation
100 kW
200 C
45 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
SEPARATOR 2
Liquid-Liquid
4.80 meters
1 meter
Horizontal
45 psi
200 C
Carbon Steel Plates
5000 gallons
120 gpm
Centrifugal
65 psi
200 C
Single mechanical seal
Standard motor
Carbon Steel
120 gpm
Centrifugal
65 psi
200 C
Single mechanical seal
Standard motor
Carbon Steel
Height
Diameter
Pressure
Temperature
Materials of
Constructions
CLAY TREATER
Cartridge 1
Cartridge 2
7.6 m
7.6 m
0.93m
1.2 m
30 psi
65 psi
100C
425C
Welded Carbon
Welded Carbon steels
steels
17 meters
0.93 meters
15 psi
100 C
3 beds with four stages
Packed bed column
Carbon Steel
120 gpm
Type
Centrifugal
Discharge Pressure
30 psi
Temperature
100 C
Seal Type
Driver Type
Standard motor
Material
Carbon Steel
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
Liquid-Liquid
Distillation
100 kW
150 C
30 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
20 meters
1.04 meters
15 psi
125 C
3 beds with four stages
Packed bed column
Carbon Steel Plates
120 gpm
Centrifugal
50 psi
180 C
Single mechanical seal
Standard motor
Carbon Steel
18 meters
0.98 meters
15 psi
180C
3 beds with four stages
Packed bed column
Carbon Steel Plates
Baffling
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
Tubes
Baffling
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
Liquid-Liquid
Distillation
100 kW
180 C
30 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
120 gpm
Centrifugal
50 psi
180 C
Single mechanical seal
Standard motor
Carbon Steel
Capacity
VESSEL A
3.05 m
1.22 m
Vertical
45 psi
150 C
A515 (Carbon Steel Plates for pressure
vessels for intermediate and higher
temperature service)
3000 gallons
Capacity
VESSEL B
5.2 m
2.3 m
Vertical
45 psi
150 C
A515 (Carbon Steel Plates for pressure
vessels for intermediate and higher
temperature service)
5000 gallons
Tubes
Baffling
Liquid-Liquid
Distillation
Material
Length
Inside Diameter
Incoming pipe diameter
Outlet pipe diameter
180 C
30 psi
Low and intermediate strength carbon
steel plates
1000ft2
Carbon Steel
1.95m
0.1625m
in, schedule 40 stainless steel
1 in, schedule 40 stainless steel
Number of Tubes
Number of Passes
28
2, U-bend configuration
Material
Copper, Schedule 40
Length
Inside Diameter
Outside Diameter
Pitch
1.905m
0.015875m
0.01905m
7/8 in, triangular pitch
D. Material Balance
a. Pump 1
M1 = M2
M1 = 15,500 Kg/Hr
M2 = 15,500 Kg/Hr
b. Extraction Column
Basis: Sulfolane Reflux = 42%
Raffinate Recovery = 33%
Feed + Solvent Reflux + Lean Solvent = Raffinate + Rich Solvent
M3 = 42,071.4 Kg/Hr
M2 + M3 + M4 = M5 + M6
15,500 Kg/Hr + 0.42 (100170 Kg/Hr) + 100,170 Kg/Hr = 0.33 (15500 Kg/Hr) +
M6
Rich Solvent = 152,626.4 Kg/Hr
M6 = 152,626.4 Kg/Hr
Raffinate = 5,115 Kg/Hr
M5 = 5,115 Kg/Hr
c. Condenser 1
M5 = M7
M5 = 5,115 Kg/Hr
M7 = 5,115 Kg/Hr
d. Wash Column
Efficiency = 98% : Heuristics
Assumption: 4,500 Kg/Hr Water Used
Water Wash-To-Water Ratio = 1.75
M9 = 1.75 (4,500 Kg/Hr)
M9 = 7,875 Kg/Hr
e. Stripper Column
Efficiency = 95%: Heuristics
Basis: Solvent-To-Extract Ratio = 2
f. Pump 2
M10 = M12
M10 = 50,875.47 Kg/Hr
M12 = 50,875.47 Kg/Hr
g. Condenser 2
M11 = M13
M11 = 96,663.38 Kg/Hr
M13 = 96,663.38 Kg/Hr
h. Separator 1
M13 = M3 + M14
96,663.38 Kg/Hr = 42071.4 Kg/Hr + M14
M14 = 59,679.53 Kg/Hr
i. Water Stripper
Effficiency = 80% : Heuristics
M9 + M14 = M15 + M16
M15 = 0.8 (M9)
M9 = 7,875 Kg/Hr
M15 = 6,300 Kg/Hr
j. Pump 3
M15 = M17
M15 = 6300 Kg/Hr
M17 = 6300 Kg/Hr
k. Regenerator
Efficiency = 98%: Heuristics
l. Recovery Column
Efficiency = 95 %: Heuristics
Extract = 50,875.47 Kg/Hr
M19 = 59,429.14 Kg/Hr
Water = 6,300 Kg/Hr
Extract + Solvent Regenerated + Water = Aromatics + Lean Solvent
50,875.47 Kg/Hr + 59,429.14 Kg/Hr + 6,300 Kg/Hr = M20 + 100,170 Kg/Hr
M20 = 16,434.61 Kg/Hr
m. Pump 4
M20 = M4
M20 = 100170 Kg/Hr
M4 = 100170 Kg/Hr
n. Condenser 3
M19 = M21
M21 = 16,434.61 Kg/Hr
M21 = 16,434.61 Kg/Hr
o. Separator 2
Basis: Water Recycled = 85%
M21 = 85% Water + M22
16,434.61 Kg/Hr = 0.85 (4,500 Kg/Hr) + M22
M22 = 12,609.61 Kg/Hr
p. Pump 5
Water used = 4,500 Kg/Hr
M23 = 0.85 (4,500 Kg/Hr)
M23 = 3,825 Kg/Hr
q. Pump 6
M22 = 12,609.61 Kg/Hr
M24 = M22
M24 = 12,609.61 Kg/Hr
b. Benzene Column
Efficiency = 95%: Heuristics
M2 = M3 + M4
Aromatics = 16.12% Benzene
M3 = M2 (95%) (16.12%)
M3 = (12,609.61 Kg/Hr) (0.95) (0.1612)
M3 = 1,928.63 Kg/Hr
M4 = M2 M3
M4 = 12,593.91 Kg/Hr 1,928.63 Kg/Hr
M4 = 10,665.28 Kg/Hr
Toluene Column Feed = 10,665.28 Kg/Hr
c. Condenser 4
M3 = M5
M3 = 1,928.63 Kg/Hr
M5 = 1,928.63 Kg/Hr
Benzene Product = 1,928.63 Kg/Hr
d. Pump 7
M4 = 10,665.28 Kg/Hr
M7 = M4
M7 = 10,665.28 Kg/Hr
e. Toluene Column
Efficiency = 95%: Heuristics
Aromatics = 72.52% Benzene
M7 = M8 + M9
M8 = (M2) (95%) (72.52%)
M8 = (12,593.91 Kg/Hr) (0.95) (0.7252)
M8 = 8,676.45 Kg/Hr
M9 = M7 M8
M9 = 10,665.28 Kg/Hr 8,676.45 Kg/Hr
M9 = 1,988.83 Kg/Hr
Xylene Column Feed = 1,988.83 Kg/Hr
f. Condenser 5
M10 = M8
M8 = 8,676.45 Kg/Hr
M10 = 8,676.45 Kg/Hr
Toluene Product = 8,676.45 Kg/Hr
g. Pump 8
M12 = M9
M9 = 1,988.83 Kg/Hr
M12 = 1,988.83 Kg/Hr
h. Xylene Column
Efficiency = 95%: Heuristics
Aromatics = 11.36% Benzene
M12 = M13 + M14
M12 = 1,988.83 Kg/Hr
i. Condenser 6
M13 =1359.13 Kg/Hr
M15= M13
M15 = 1,359.13 Kg/Hr
Xylene Product = 1,359.13 Kg/Hr
j. Pump 9
M14 = 629.70 Kg/Hr
M17 = M14
M17 = 629.70 Kg/Hr
k. Condenser 7
M17 = 629.70 Kg/Hr
M18 = m17
59429.14
16434.61
12609.61
12593.91
1928.63
8676.45
1359.13
629.70
1928.63 kg/hr
8676.45 kg/hr
1359.13 kg/hr
11964.21 kg/hr
E. Energy balance
This section contains the calculations for energy requirements of heat transfer
equipment used in the BTX Manufacturing Plant.
F. Stripper Column
Rich Solvent (Sulfolane)= 152,626.4 Kg/Hr
Cp of Sulfolane = 1.497 J/g C
Cp = 1.497 kJ/Kg-K
Rich solvent temperature =30C
T1 = 30C = 303.15 K
T2 = 408.15 K
Q = m Cp (T2 - T1)
Q = (152,626.4 Kg/Hr) (1.497 kJ/Kg-K) (408.15 K - 303.15 K)
Q = 23,990,580.68 kJ/hr
Q = 23,990,580.68 kJ/hr (1 hr/3600 s)
Q = 6,664.05 kW
g. Solvent Regenerator
Regenerated Solvent = 61,254.53 Kg/Hr
Cp of Sulfolane = 1.497 kJ/Kg-K
T1 = 135 C = 408.15 K
T2 = 166 C = 439.15 K
Q = m Cp (T2 - T1)
Q = (61,254.53 Kg/Hr) (1.497 kJ/Kg-K) (439.15 K - 408.15 K)
Q = 2,842,638.97 kJ/hr
Q = 2,842,638.97 kJ/hr (1 hr/3600 s)
Q = 789.62 kW
h. Recovery Column
Cp of aromatics = 1.7867 kJ/Kg-K
T1 = 135C = 408.15 K
T2 = 177C = 450.15 K
Q1 = m Cp (T2 - T1)
Q1 = (50,875.47 Kg/Hr) (1.7867 kJ/Kg-K) (450.15 K - 408.15 K)
Q1 = 3,817,766.49 kJ/hr
Q1 = 3,817,766.49 kJ/hr (1 hr/3600 s)
Q1 = 1,060.49 kW
Q2 = m Cp (T2 - T1)
Q2 = (59,429.14 Kg/Hr) (1.497 kJ/Kg-K) (450.15 K - 439.15 K)
Q2 = 978,619.65 kJ/hr
Q2 = 978,619.65 kJ/hr (1 hr/3600 s)
Q2 = 271.84 kW
i. Benzene Column
M = 12,593.91 Kg/Hr
Cp of Benzene = 1.92 kJ/Kg-K
T1 = 90C = 363.15 K
T2 = 100C = 373.15 K
Q = m Cp (T2 - T1)
Q = (12,593.91 Kg/Hr) (1.92 kJ/Kg-K) (373.15 K - 363.15 K)
Q = 241,803.07 kJ/hr
Q = 241,803.07 kJ/hr (1 hr/3600 s)
Q = 67.17 kW
j. Toluene Column
M = 10,665.28 Kg/Hr
Cp of Toluene = 1.72 kJ/Kg-K
T1 = 100C = 373.15 K
T2 = 125C = 398.15 K
Q = m Cp (T2 - T1)
Q = (10,665.28 Kg/Hr) (1.72 kJ/Kg-K) (398.15 K - 373.15 K)
Q = 458,607.04 kJ/hr
Q = 458,607.04 kJ/hr (1 hr/3600 s)
Q = 127.39 kW
k. Xylene Column
M = 1,988.83 Kg/Hr
Cp of Xylene = 1.72 kJ/Kg-K
T1 = 125C = 398.15 K
T2 = 160C = 433.15 K
Q = m Cp (T2 - T1)
Q = (1,988.83 Kg/Hr) (1.72 kJ/Kg-K) (433.15 K - 398.15 K)
Q = 119,727.57 kJ/hr
Q = 119,727.57 kJ/hr (1 hr/3600 s)
Q = 33.26 kW
l. Boiler
Q = (6,664.05 + 789.62 + 1742.66 + 67.17 + 127.39 + 33.26) kW
Q = 9,424.15 kW
Cp of steam = 1.996 kJ/Kg-K
T1 = 30C = 273.15 K
T2 = 177C = 450.15 K
Q = m Cp (T2 - T1)
9,424.15 kW (1 kJ/s / 1 kW) (3600s/1 hr) = (Ms) (1.996 kJ/Kg-K) (450.15 K 373.15 K)
33,926,940 kJ/hr = Ms (153.692 kJ/Kg)
Ms = 220,746.30 kg/hr
Steam = 220,746.30 kg/hr
Stripping
6664.05
Solvent Regeneration
789.62
Solvent Recovery
1742.66
Benzene Distillation
67.17
Toluene Distillation
127.39
Xylene Distillation
33.26
9424.15 kW
F. Capacity Calculation
e. Feed Surge Tank
Feed = 15500 kg/hr
= 759 kg/m3
Minimum Level = 50%
V = [15500 kg/hr (1 m3 / 759 kg)] (1.5)
V= 30.63 m3 / hr (24 hr / day)
V = 735 m3 / day
f. Raffinate Tank
Washed Raffinate = 1705.2 kg/hr
= 845 kg/m3
V = 1705.2 kg/hr (1 m3/ 845 kg)
V = (2.02 m3 / hr) (24 hr / day)
V = 48.43 m3/day
G. Plant Efficiency
The plant efficiency can be calculated from the mass balance data:
Efficiency = (output)/ (input) x 100%
Efficiency = (BTX)/Naphtha Reformate x 100%
Efficiency = (11,964.21 kg/hr) / (15,500 kg/hr) x 100%
Efficiency = 76.93 %
CHAPTER IV
ECONOMICS
CAPITAL EXPENDITURE
Capital expenditures, or capex, is money used to purchase, upgrade,
improve, or extend the life of long-term assets. Long-term assets are typically
property, infrastructure, or equipment with a useful life of more than one year
OPERATION EXPENDITURE
An operating
expense, operating
expenditure, operational
expense,
Raw materials
These are the major materials required to manufacture the product. The
quantities can be obtained from the demand projection and multiplied by the
operating hours per year to get the annual requirements. The price of naphtha
reformate is obtained from the prices of potential suppliers, but in the preliminary
stages of a project prices can be taken from the literature.
Utilities (services)
This operating cost includes electricity, fuel, steam, water for process and
cooling. The quantities required were obtained from the energy balances. Utility
price was based on table 6.5
Operating labor
This is the manpower needed to operate the plant: that directly involved
with running the process. Chemical plants do not normally employ many people
and the cost of operating labor would not normally exceed 15 per cent of the total
operating cost. Labor cost is normally calculated from an estimate of the number of
shift and number of personnel needed. On that note, this proposed manufacturing
plant employees work in a three shifts per day basis with 50 personnel in total.
Supervision
This heading covers the direct operating supervision: the management
directly associated with running the plant. The number required will depend on the
size of the plant and the nature of the process. The site would normally be broken
down into a number of manageable units. A typical management team for a unit
would consist of four to five shift foremen, a general foreman, and an area
supervisor (manager) and his assistant. The cost of supervision is calculated from
an estimate of the total number required and the current salary levels. On average,
one supervisor would be needed for each four to five operators.
Laboratory costs
The annual cost of the laboratory analyses required for process monitoring
and quality control is a significant item in most modern chemical plants. The costs
should be calculated from an estimate of the number of analyses required and the
standard charge for each analysis, based on experience with similar processes. As
a rough estimate the cost can be taken as 25 percent of the operating labor cost
Plant Overheads
Plant overheads Included under this heading are all the general costs
associated with operating the plant not included under the other headings; such
as, general management, plant security, medical and canteen. It would also
normally include the plant technical personnel not directly associated with and
charged to a particular operating area. The plant overhead cost is usually
estimated from the total labor costs. A typical estimate would be 50 percent of the
labor costs.
Local taxes
This term covers local taxes, which are calculated on the value of the site. A
typical figure would be 5 percent of capital expenditure.
Insurance
The cost of the site and plant insurance: the annual insurance premium paid
to the insurers; usually about five percent of capital expenditure.
Net Present Value is the difference between the present value of cash
inflows and the present value of cash outflows. NPV is used in capital budgeting to
analyze the profitability of a projected investment or project.
DESIGN OPTION 1
EQUIPMENT
PROCESS
Raw materials
Extraction
Raffinate Stripping
Solvent Recovery
Clay Treater
Benzene Column
Toluene Column
Xylene Column
EQUIPMENT
Storage
Pump (1)
Packed Bed Column
Stripping Column
Cooler (1)
Storage Vessel (1)
Pump (2)
Pump (3)
Heater (1)
Pump (4)
Pump (5)
Solvent Recovery Column
Cooler (2)
Storage Vessel (2)
Pump (6)
Pump (7)
Heater (2)
Pump (8)
Heater Exchanger
Cartridge (2 columns)
Fractionation Column
Cooler (3)
Storage Vessel (3) (Product)
COST
$15,000.00
$4,000.00
$250,000.00
$450,000.00
$20,000.00
$20,000.00
$2,500.00
$2,500.00
$20,000.00
$2,000.00
$2,500.00
$450,000.00
$20,000.00
$12,000.00
$2,100.00
$2,100.00
$20,000.00
$4,000.00
$20,000.00
$22,000.00
$38,000.00
$20,000.00
$15,500.00
Pump (9)
Reboiler (1)
Pump (10)
Fractionation column
Cooler (4)
Storage Vessel (4) (Product)
Pump (11)
Pump (12)
Reboiler (2)
Fractionation column
$3,900.00
$20,000.00
$3,800.00
$40,000.00
$20,000.00
$16,000.00
$3,800.00
$3,800.00
$20,000.00
$38,000.00
Cooler (5)
Storage Vessel (5) (Product)
$20,000.00
$11,800.00
PROCESS
Xylene Column
EQUIPMENT
Reboiler (3)
Pump (13)
Cooler (6)
Storage Vessel (6) (Nonaromatics)
TOTAL
COST
$20,000.00
$3,500.00
$20,000.00
$11,000.00
$1,669,800.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
Installed Equipment Cost
$250,000.00
Labor
Factor
Cost
Factor
Cost
5
$12,500.00
133
$16,625.00
4
$10,000.00
50
$5,000.00
3
$7,500.00
100
$7,500.00
1
$2,500.00
150
$3,750.00
6
$15,000.00
40
$6,000.00
8
$20,000.00
75
$15,000.00
30
$7,500,000.00
50
$3,750,000.00
0.5
$12,500.00
300
$37,500.00
4
$10,000.00
80
$8,000.00
$7,590,000.00
$3,849,375.00
$11,439,375.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Factor, % in
PC
5
4
3
1
6
8
30
Painting
Miscellaneous
0.5
4
$450,000.00
Labor
Material
Factor, % in
Cost
MC
$22,500.00
133
$18,000.00
50
$13,500.00
100
$4,500.00
150
$27,000.00
40
$36,000.00
$13,500,000
.00
$22,500.00
$18,000.00
$13,662,000.00
$20,590,87.00
Factor, % in
PC
5
4
3
1
6
$27,000.00
$6,750,000.
00
$67,500.00
$14,400.00
$6,928,875.00
300
80
Painting
Miscellaneous
$29,925.00
$9,000.00
$13,500.00
$6,750.00
$10,800.00
75
50
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Labor Cost
8
30
0.5
4
$44,000.00
Labor
Material
Factor, % in
Cost
MC
$2,200.00
133
$1,760.00
50
$1,320.00
100
$440.00
150
$2,640.00
40
$3,520.00
$1,320,000.
00
$2,200.00
$1,760.00
$1,335,840.00
75
50
300
80
Labor
Cost
$2,926.00
$880.00
$1,320.00
$660.00
$1,056.00
$2,640.00
$660,000.
00
$6,600.00
$1,408.00
$677,490.00
$2,013,330.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Factor, % in
PC
5
4
3
1
6
8
30
Painting
Miscellaneous
0.5
4
$350,000.00
Labor
Material
Factor, % in
Cost
MC
$17,500.00
133
$14,000.00
50
$10,500.00
100
$3,500.00
150
$21,000.00
40
Labor Cost
$28,000.00
$105,000.0
0
$17,500.00
$14,000.00
$231,000.00
75
50
$21,000.00
$52,500.00
300
80
$52,500.00
$11,200.00
$191,625.00
$422,625.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Factor, % in
PC
5
4
3
1
6
Painting
Miscellaneous
$23,275.00
$7,000.00
$10,500.00
$5,250.00
$8,400.00
8
30
0.5
4
$38,000.00
Labor
Material
Factor, % in
Cost
MC
$1,900.00
133
$1,520.00
50
$1,140.00
100
$380.00
150
$2,280.00
40
$3,040.00
$1,140,000.
00
$1,900.00
$1,520.00
$1,153,680.00
75
50
300
80
Labor
Cost
$2,527.00
$760.00
$1,140.00
$570.00
$912.00
$2,280.00
$570,000.
00
$5,700.00
$1,216.00
$585,105.00
$1,738,785.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
$40,000.00
Labor
Factor, %
in PC
5
4
3
1
6
Material Cost
8
30
$3,200.00 75
$1,200,000.00 50
0.5
4
$2,000.00 300
$1,600.00 80
$1,214,400.00
$2,000.00
$1,600.00
$1,200.00
$400.00
$2,400.00
Factor, % in
MC
133
50
100
150
40
$1,830,300.00
$38,000.00
Labor
Material
Factor, % in
PC
5
4
3
1
6
Painting
Miscellaneous
Installed Equipment Cost
$2,660.00
$800.00
$1,200.00
$600.00
$960.00
$2,400.00
$600,000.0
0
$6,000.00
$1,280.00
$615,900.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Labor Cost
8
30
0.5
4
Material
Factor, % in
Cost
MC
$1,900.00
133
$1,520.00
50
$1,140.00
100
$380.00
150
$2,280.00
40
$3,040.00
$1,140,000.
00
$1,900.00
$1,520.00
$1,153,680.00
75
50
300
80
Labor
Cost
$2,527.00
$760.00
$1,140.00
$570.00
$912.00
$2,280.00
$570,000.
00
$5,700.00
$1,216.00
$585,105.00
$1,738,785.00
$20,000.00
Labor
Material
Factor
Foundation
5
Structural Steel
4
Process Building
3
Insulation
1
Instrumentation and Control
6
Electrical Installation
8
Piping
30
Painting
0.5
Miscellaneous
4
Cost
$1,000.00
$800.00
$600.00
$200.00
$1,200.00
$1,600.00
$6,000.00
$1,000.00
$800.00
$13,200.00
Factor
133
50
100
150
40
75
50
300
80
$24,150.00
Factor
Foundation
5
Structural Steel
4
Process Building
3
Insulation
1
Instrumentation and Control
6
Electrical Installation
8
Piping
30
Painting
0.5
Miscellaneous
4
Installed Equipment Cost
Cost
$1,330.00
$400.00
$600.00
$300.00
$480.00
$1,200.00
$3,000.00
$3,000.00
$640.00
$10,950.00
Cost
Factor
$1835.00 133
$1468.00
50
$1101.00 100
$367.00 150
$2202.00
40
$2936.00
75
$11010.00
50
$1835.00 300
$1468.00
80
$24,222.00
$36,700.00
Labor
Cost
$2,440.00
$734.00
$1101.00
$5505.00
$880.8.00
$2202.00
$5505.00
$5505.00
$1174.4.00
$20,093.7
$44,315.25
$101,300.00
Labor
Material
Factor
Cost
Foundation
5
$5,065.00
Structural Steel
4
$4,052.00
Process Building
3
$3,039.00
Insulation
1
$1,013.00
Instrumentation and Control
6
$6,078.00
Electrical Installation
8
$8,104.00
Piping
30
$30,390.00
Painting
0.5
$5,065.00
Miscellaneous
4
$4,052.00
$66,858.00
Factor
133
50
100
150
40
75
50
300
80
$122,319.8
$120,000.00
Labor
Material
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
Installed Equipment Cost
Cost
$6,736.45
$2,026.00
$3,039.00
$1,519.50
$2,431.20
$6,078.00
$15,195.00
$15,195.00
$3,241.60
$55,461.75
Factor
Cost
5
$6,000.00
4
$4,800.00
3
$3,600.00
1
$1,200.00
6
$7,200.00
8
$9,600.00
30
$36,000.00
0.5
$6,000.00
4
$4,800.00
$79,200.00
Factor
133
50
100
150
40
75
50
300
80
Cost
$7,980.00
$2,400.00
$3,600.00
$1,800.00
$2,880.00
$7,200.00
$18,000.00
$18,000.00
$3,840.00
$65,700.00
$144,900.00
$60,000.00
Labor
Material
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
Factor
5
4
3
1
6
8
30
0.5
4
Cost
$3,000.00
$2,400.00
$1,800.00
$600.00
$3,600.00
$4,800.00
$18,000.00
$3,000.00
$2,400.00
$39,600.00
Factor
133
50
100
150
40
Cost
$3,990.00
$1,200.00
$1,800.00
$900.00
$1,440.00
75
50
300
80
$3,600.00
$9,000.00
$9,000.00
$1,920.00
$32,850.00
$72,450.00
CAPITAL EXPENDITURES
Expenditures
Storages
Process Building
Ancillary Buildings
Site Development
Design and Engineering
Contractors Fee
Taxation
Land Cost
Offloading Facility
Fire Fighting
Quantity
50% PEC
25% PEC
30 % PEC
30% PEC
25% PEC
10% PEC
10% PEC
52000 square meter
TOTAL
Cost
$834,900.00
$417,450.00
$500,940.00
$500,940.00
$417,450.00
$166,980.00
$166,980.00
$3,006,120.00
$1,187,319.48
$1,700,00.00
$7,199,079.48
OPERATING EXPENDITURES
Expenditures
Raw Materials
TEG Solvent
Operating Labor
Maintenance, repairs and
contingency
Laboratory Testing
Office Supply/expenses
Legal fees
Insurance
Supervision
Local Taxes
Miscellaneous Maintenance
Plant Overheads
Electricity
Cooling Water
Steam for heating
Quantity
337.12$/ton
$0.04 per lb
47 persons
10% of Capital Expenditure
Cost
$48,828,460.8
$44,013,997.94
$1,107,600.00
$166,980.00
25% of Labor
5% of Capital Expenditure
5% of Labor
5% of Capital Expenditure
25% of Labor
5% of Capital Expenditure
5% of Capital Expenditure
50 % Labor
$276,900.00
$83,490.00
$55,380.00
$83,490.00
$276,900.00
$83,490.00
$83,490.00
$553,800.00
$1,300,000.00
$250,000.00
$300,000.00
$97,656,514.74
TOTAL:
Installed Equipment Cost
Extraction Column
Stripping Column
Clay Treater Column (2)
Recovery Column
Benzene Column
Toluene Column
Xylene Column
Heat Exchanger
Cooler
Pump
Storage Vessel
Boiler
TOTAL
$11,439,375.00
$20,590,875.00
$2,013,330.00
$422,625.00
$1738785.00
$1,830,300.00
$1738785.00
$24,150.00
$24,150.00
$144,900.00
$122,319.8
$72,450.00
$40,162,044.80
CAPITAL EXPENDITURES
Expenditures
Installed equipment Cost
Storages
Process Building
Ancillary Buildings
Site Development
Design and Engineering
Contractors Fee
Taxation
Land Cost
Offloading Facility
Fire Fighting
Quantity
50% PEC
25% PEC
30 % PEC
30% PEC
25% PEC
10% PEC
10% PEC
52,000 square meter
TOTAL
Cost
$40,162,044.80
$834,900.00
$417,450.00
$500,940.00
$500,940.00
$417,450.00
$166,980.00
$166,980.00
$3,006,120.00
$1,187,319.48
$1,700,00.00
$47,361,124.28
ECONOMIC INDICATORS
Cash Inflows:
Product
Benzene
Toluene
Xylene
Paraffin
C9 aromatics
(1 + )
$14,410,650.84x10
(1+0.05)10
$47,361,124.28
= $ 41,107,771.15
Rate of Return
=
100%
14,410,650.84
100%
$47,361,124.28
= 30.43%
DESIGN OPTION 2
DETAILED EQUIPMENT COSTS
Distillation Column Purchased Cost:
Material
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
Factor, %
in PC
5
4
3
1
6
8
30
0.5
4
Material Cost
$48,896.73
$39,117.39
$29,338.04
$9,779.35
$58,676.08
$78,234.77
$293,380.34
$4,889.67
$39,117.38
$601,429.78
$ 977,934.60
Labor
Factor,
% in MC
133
50
100
150
40
75
50
300
80
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
$65,032.65
$19,558.69
$29,338.04
$14,669.02
$23,470.43
$58,676.08
$146,690.20
$14,669.02
$31,293.91
$403,398.02
$ 1,982,762.40
$ 456,369.48
Labor
Factor
5
4
3
1
6
Cost
$22,818.47
$18,254.78
$13,691.08
$4,563.69
$27,382.17
Factor
133
50
100
150
40
8
30
0.5
4
$36,509.56
$136,910.84
$2,281.85
$18,254.78
$280,667.23
75
50
300
80
Cost
Cost
$30,348.57
$9,127.39
$13,691.08
$6,845.54
$10,952.87
$27,382.17
$68,455.42
$6,845.54
$14,603.82
$188,252.41
$ 925,289.12
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
Factor
5
4
3
1
6
8
30
0.5
4
Cost
$12,933.8038
$10,347.04304
$7,760.282277
$2,586.760759
$15,520.56455
$20,694.08607
$77,602.82277
$1,293.38038
$10,347.04304
$159,085.7867
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
Factor
5
4
3
1
6
8
30
0.5
4
Cost
$12,281.8475
$9,825.478
$7,369.1085
$2,456.3695
$14,738.217
$19,650.956
$73,691.085
$1,228.18475
$9,825.478
$151,066.7243
$ 258676.08
Labor
Factor
Cost
133
$17,201.96
50
$5,173.522
100
$7,760.282
150
$3,880.141
40
$6,208.226
75
$15,520.56
50
$38,801.41
300
$3,880.141
80
$8,277.634
$106,703.8813
$ 524,465.7439
$ 245,636.95
Labor
Factor
Cost
133
$16,334.86
50
$4,912.739
100
$7,369.109
150
$3,684.554
40
$5,895.287
75
$1,4738.22
50
$36,845.54
300
$3,684.554
80
$7,860.382
$101,325.2419
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
$ 239117.38
Labor
Factor
Cost
5
$11,955.8692
4
$9,564.695356
3
$7,173.521517
1
$2,391.173839
6
$14,347.04303
8
$19,129.39071
30
$71,735.21517
0.5
$1,195.58692
4
$9,564.695356
$147057.1911
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
Installed Equipment Cost
Factor
Cost
133
$15,901.31
50
$4,782.348
100
$7,173.522
150
$3,586.761
40
$5,738.817
75
$14,347.04
50
$35,867.61
300
$3,586.761
80
$7,651.756
$98,635.92086
$484,810.4959
$ 339,017.3275
Labor
Factor
Cost
5
$16,950.86638
4
$13,560.6931
3
$10,170.51983
1
$3,390.173275
6
$20,341.03965
8
$27,121.3862
30
$101,705.1983
0.5
$1,695.086638
4
$13,560.6931
$208495.6564
Factor
Cost
133
$22,544.65
50
$6,780.347
100
$10,170.52
150
$5,085.26
40
$8,136.416
75
$20,341.04
50
$50,852.6
300
$5,085.26
80
$10,848.55
$139844.6476
$ 687357.6315
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
$41725.20958
Labor
Factor
Cost
5
$2086.260479
4
$1669.008383
3
$1251.756287
1
$417.2520958
6
$2503.512575
8
$3338.016766
30
$12517.56287
0.5
$208.6260479
4
$1669.008383
25661.00389
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
$ 122567.80
Labor
Factor
Cost
5
$6128.39015
4
$4902.71212
3
$3677.03409
1
$1225.67803
6
$7354.06818
8
$9805.42424
30
$36770.3409
0.5
$612.839015
4
$4902.71212
75379.19885
Factor Cost
133
$2774.726
50
$834.5042
100
$1251.756
150
$625.8781
40
$1001.405
75
$2503.513
50
$6258.781
300
$625.8781
80
$1335.207
17211.64895
$ 84597.86242
Factor
Cost
133
$8150.759
50
$2451.356
100
$3677.034
150
$1838.517
40
$2941.627
75
$7354.068
50
$18385.17
300
$1838.517
80
$3922.17
50559.21874
$ 248506.2206
$ 521565.1191
Labor
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
Factor Cost
5
26078.25596
4
20862.60476
3
15646.95357
1
5215.651191
6
31293.90715
8
41725.20953
30
156469.5357
0.5
2607.825596
4
20862.60476
320762.5482
Factor Cost
133
34684.08
50
10431.3
100
15646.95
150
7823.477
40
12517.56
75
31293.91
50
78234.77
300
7823.477
80
16690.08
215145.6116
$ 1061473.279
CAPITAL EXPENDITURE
Total Capital Expenditure
Installed equipment Cost
Storages
Ancillary Buildings
Site Development
Contractors Fee
Taxation
Land Cost
Offloading Facility
50% PEC
25% PEC
25% PEC
10% PEC
5% PEC
57.81 $/ m2
6497291.67
2,070,673.68
1,035,336.85
1,035,336.84
414,134.74
207,067.34
3,006,120.00
1187319.48
Fire Fighting
1,000,000.00
$ 16453280.6
TOTAL
OPERATION EXPENDITURE
MATERIAL
Raw materials
NFM Solvent
Operating Labor
Maintenance, repairs
and Contingency
Laboratory Testing
Office Expenses/supply
QUANTITY
307.12 $/ton
$500/ton
50 persons
10% of Capital
Expenditure
25% of Labor
5% of Capital
Expenditure
5% Labor
5% of Capital
Expenditure
25% Labor
5% of Capital
Expenditure
5% of Capital
Expenditure
50% Labor
Legal fees
Insurance
Supervision
Local Taxes
Miscellaneous
Plant Overheads
Electricity
Cooling water
Steam for heating
TOTAL
COST
44875760.16
9389625
4,055,555.56
2,393,511.58
1,013,888.89
1,196,755.79
202,777.78
1,196,755.79
1,013,888.89
1,196,755.79
1,196,755.79
2,027,777.79
1,500,000.00
300,000.00
500,000.00
$ 72059808.81
ECONOMIC INDICATORS
Cash Inflows:
Product
Benzene
Toluene
Xylene
Paraffin
C9 aromatics
TOTAL
Thousand tons
per year
16294.074
75221.0352
11782.99
28601.04
10993.782
Total Cost
16522191.04
52504282.57
18876349.98
9095130.72
3561985.368
$ 100559939.7
Income Tax:
Indonesias income tax for Foreign Industrial Company is 25%.
Net Income = Taxable Income x0.75
= 100559939.7 x 0.75
= $ 75419954.78
Net cash inflows = net income operating cost
= 75419954.78 - 72059808.81
= $ 3360145.97
(1 + )
3360145.97 10
(1+0.05)10
16453280.6
= $ 4175100.85
=
=
100%
3360145.97
100%
16453280.6
= 20.42%
DESIGN OPTION 3
EQUIPMENT
Pump (1)
Packed Bed Column
Cooler (1)
Wash Column
COST
$4,000.00
$250,000.00
$20,000.00
$100,000.00
Stripping Column
Pump (2)
Cooler (2)
Separator (1)
Water Separator
Regenerator
Pump (3)
Recovery Column
Pump (4)
Cooler (3)
Separator (2)
Pump (5)
Pump (6)
Cartridge (2 columns)
Pump (6)
Benzene Column
Cooler (4)
Pump (7)
Toluene column
Cooler (5)
Pump (6)
Xylene column
Cooler (6)
Pump (8)
Cooler (7)
Vessel A
Vessel B
Boiler
TOTAL
$450,000.00
$2,500.00
$20,000.00
$100,000.00
$100,000.00
$150,000.00
$2,000.00
$350,000.00
$2,500.00
$20,000.00
$50,000.00
$2,500.00
$2,500.00
$44,000.00
$2,100.00
$38,000.00
$20,000.00
$2,100.00
$40,000.00
$20,000.00
$2,100.00
$38,000.00
$20,000.00
$3,800.00
$20,000.00
$9,800.00
$11,000.00
$20,000.00
$2,178,900.00
CAPITAL EXPENDITURES
Expenditures
Storages
Process Building
Ancillary Buildings
Site Development
Design and Engineering
Contractors Fee
Taxation
Land Cost
Offloading Facility
Fire Fighting
Quantity
50% PEC
25% PEC
30 % PEC
30% PEC
25% PEC
10% PEC
10% PEC
52000 square meter
TOTAL
Cost
$1,089,450.00
$544,725.00
$653,670.00
$653,670.00
$544,725.00
$217,890.00
$217,890.00
$3,006,120.00
$1,187,319.48
$1,700,00.00
$8,115,459.48
OPERATING EXPENDITURES
Expenditures
Raw Materials
Sulfolane Solvent
Utilities
Quantity
337.12$/ton
$1.30 per kg
10% of Capital
Expenditure
10% of Capital
Expenditure
25% of Capital
Expenditure
25% of Labor
45% of Capital
Expenditure
5% of Labor
50% of Capital
Expenditure
10% of Capital
Expenditure
47 persons
15% of Labor
5% of Capital
Expenditure
5% of Capital
Expenditure
Miscellaneous
License Fees
Laboratory Testing
Office Supply/expenses
Legal fees
Transportation of products
Maintenance and Repairs
Operating Labor
Supervision
Insurance
Property Taxes
Miscellaneous Maintenance
Overhead Labor
Cost
$44,520,067.20
$130,021.00
$217,890.00
$217,890.00
$544,725.00
$544,725.00
$980,505.00
$108,945.00
$1,089,450.00
$217,890.00
$1,107,600.00
$326,835.00
$108,945.00
$108,945.00
$32,896.00
$108,945.00
$50,366,274.20
50 %of Labor
TOTAL:
$250,000.00
Material
Factor
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
5
4
3
1
6
8
Labor
Cost
$12,500.00
$10,000.00
$7,500.00
$2,500.00
$15,000.00
$20,000.00
Factor
133
50
100
150
40
75
Cost
$16,625.00
$5,000.00
$7,500.00
$3,750.00
$6,000.00
$15,000.00
Piping
Painting
Miscellaneous
30
0.5
4
$7,500,000.00 50
$12,500.00 300
$10,000.00 80
$7,590,000.00
$3,750,000.00
$37,500.00
$8,000.00
$3,849,375.00
$11,439,375.00
$100,000.00
Material
Factor
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and Control
Electrical Installation
Piping
Painting
Miscellaneous
5
4
3
1
6
8
30
0.5
4
Labor
Cost
Factor
$5,000.00
$4,000.00
$3,000.00
$1,000.00
$6,000.00
$8,000.00
$30,000.00
$5,000.00
$4,000.00
$66,000.00
Cost
133
50
100
150
40
75
50
300
80
$120,750.00
$150,000.00
Material
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Factor, % in
PC
5
4
3
1
6
$6,650.00
$2,000.00
$3,000.00
$1,500.00
$2,400.00
$6,000.00
$15,000.00
$15,000.00
$3,200.00
$54,750.00
Labor
Material
Cost
$17500.00
$14000.00
$10500.00
$3500.00
$21000.00
Factor, % in
MC
133
50
100
150
40
Labor
Cost
$23275.00
$7000.00
$10500.00
$5250.00
$8400.00
Control
Electrical Installation
Piping
Painting
Miscellaneous
8
30
0.5
4
$28000.00
$105000.00
$17500.00
$14000.00
$231000.00
75
50
300
80
$21000.00
$52500.00
$52500.00
$11200.00
$191625.00
$422,625.00
$450,000.00
Material
Labor
Factor, % in
Material
Factor, % in
PC
Cost
MC
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
5
4
3
1
6
Painting
Miscellaneous
0.5
4
8
30
$22,500.00
$18,000.00
$13,500.00
$4,500.00
$27,000.00
$36,000.00
$13,500,000
.00
$22,500.00
$18,000.00
$13,662,000.00
133
50
100
150
40
75
50
300
80
$29,925.00
$9,000.00
$13,500.00
$6,750.00
$10,800.00
$27,000.00
$6,750,000
.00
$67,500.00
$14,400.00
$6,928,875.00
$20,590,875.00
$150,000.00
Material
Factor, % in
Labor Cost
Labor
Material
PC
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
5
4
3
1
6
8
30
0.5
4
Cost
$7,500.00
$6,000.00
$4,500.00
$1,500.00
$9,000.00
$12,000.00
$45,000.00
$7,500.00
$6,000.00
$99,000.00
MC
133
50
100
150
40
$9,975.00
$3,000.00
$4,500.00
$2,250.00
$3,600.00
$9,000.00
$22,500.00
$22,500.00
$4,800.00
$82,125.00
75
50
300
80
$350,000.00
Material
Factor, % in
PC
Foundation
5
Structural Steel
4
Process Building
3
Insulation
1
Instrumentation and 6
Control
Electrical
8
Installation
Piping
30
Painting
0.5
Miscellaneous
4
Labor
Material
Cost
$17,500.00
$14,000.00
$10,500.00
$3,500.00
Factor, % in
MC
133
50
100
150
40
$21,000.00
75
$28,000.00
$105,000.00 50
$17,500.00 300
$14,000.00 80
$231,000.00
Labor Cost
$23,275.00
$7,000.00
$10,500.00
$5,250.00
$8,400.00
$21,000.00
$52,500.00
$52,500.00
$11,200.00
$191,625.00
$44,000.00
Material
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
Factor, % in
PC
5
4
3
1
6
8
30
0.5
4
Labor
Material
Cost
$2,200.00
$1,760.00
$1,320.00
$440.00
$2,640.00
$3,520.00
$1,320,000.
00
$2,200.00
$1,760.00
$1,335,840.00
Factor, % in
MC
133
50
100
150
40
$1,056.00
$2,640.00
$660,000.
00
$6,600.00
$1,408.00
$677,490.00
75
50
300
80
Labor
Cost
$2,926.00
$880.00
$1,320.00
$660.00
$2,013,330.00
$38,000.00
Labor
Factor, % in
Material
Factor, % in
Labor
PC
Cost
MC
Cost
133
50
100
150
40
$2,527.00
$760.00
$1,140.00
$570.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
5
4
3
1
6
Painting
Miscellaneous
0.5
4
8
30
$1,900.00
$1,520.00
$1,140.00
$380.00
$2,280.00
$3,040.00
$1,140,000.
00
$1,900.00
$1,520.00
75
50
300
80
$912.00
$2,280.00
$570,000.
00
$5,700.00
$1,216.00
$1,153,680.00
$585,105.00
$1738785.00
$40,000.00
Labor
Factor, % in
Material
Factor, % in
Labor
PC
Cost
MC
Cost
133
50
100
150
40
$2,660.00
$800.00
$1,200.00
$600.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
5
4
3
1
6
$2,000.00
$1,600.00
$1,200.00
$400.00
Painting
Miscellaneous
0.5
4
$1,214,400.00
8
30
$2,400.00
$3,200.00
$1,200,000.
00
$2,000.00
$1,600.00
75
50
300
80
$615,900.00
$1,830,300.00
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Factor, %
in PC
5
4
3
1
6
$960.00
$2,400.00
$600,000.
00
$6,000.00
$1,280.00
$38,000.00
Labor
Material Cost
$1,900.00
$1,520.00
$1,140.00
$380.00
$2,280.00
Factor,
% in MC
133
50
100
150
40
Labor Cost
$2,527.00
$760.00
$1,140.00
$570.00
$912.00
Control
Electrical Installation
Piping
Painting
Miscellaneous
8
30
0.5
4
$3,040.00
$1,140,000.00
$1,900.00
$1,520.00
$1,153,680.00
75
50
300
80
$2,280.00
$570,000.00
$5,700.00
$1,216.00
$585,105.00
$140,000.00
Material
Factor
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
5
4
3
1
6
8
30
0.5
4
Labor
Cost
$7,000.00
$5,600.00
$4,200.00
$1,400.00
$8,400.00
$11,200.00
$42,000.00
$7,000.00
$5,600.00
$92,400.00
Factor
Cost
133
50
100
150
40
$9,310.00
$2,800.00
$4,200.00
$2,100.00
$3,360.00
$8,400.00
$21,000.00
$21,000.00
$4,480.00
$76,650.00
75
50
300
80
Installed Equipment
Cost
$169,050.00
$26,100.00
Material
Factor
Labor
Cost
Factor
Cost
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
5
4
3
1
6
8
30
0.5
4
$1,305.00
$1,044.00
$783.00
$261.00
$1,566.00
$2,088.00
$7,830.00
$1,305.00
$1,044.00
$17,226.00
133
50
100
150
40
$1,735.65
$522.00
$783.00
$391.50
$626.40
$1,566.00
$3,915.00
$3,915.00
$835.20
$14,289.75
75
50
300
80
Installed Equipment
Cost
$31,515.75
$20,000.00
Material
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
Installed Equipment
Labor
Factor
Cost
Factor
5
4
3
1
6
$1,000.00
$800.00
$600.00
$200.00
133
50
100
150
40
8
30
0.5
4
$1,200.00
$1,600.00
$6,000.00
$1,000.00
$800.00
$13,200.00
75
50
300
80
Cost
$1,330.00
$400.00
$600.00
$300.00
$480.00
$1,200.00
$3,000.00
$3,000.00
$640.00
$10,950.00
$24.150.00
Cost
$20,000.00
Material
Foundation
Structural Steel
Process Building
Insulation
Instrumentation and
Control
Electrical Installation
Piping
Painting
Miscellaneous
Labor
Factor
Cost
Factor
5
4
3
1
6
$1,000.00
$800.00
$600.00
$200.00
133
50
100
150
40
8
30
0.5
4
$1,200.00
$1,600.00
$6,000.00
$1,000.00
$800.00
$13,200.00
75
50
300
80
Installed Equipment
Cost
Cost
$1,330.00
$400.00
$600.00
$300.00
$480.00
$1,200.00
$3,000.00
$3,000.00
$640.00
$10,950.00
$24.150.00
$11,439,375.00
$120,750.00
$422,625.00
$20,590,875.00
$181,125.00
$422,625.00
$2,013,330.00
$1738785.00
$1,830,300.00
$1738785.00
$169,050.00
$31,515.75
$24.150.00
$24.150.00
$40,699,140.75
$40,699,140.75
50% PEC
25% PEC
30 % PEC
30% PEC
25% PEC
10% PEC
10% PEC
52000 square meter
TOTAL
$1,089,450.00
$544,725.00
$653,670.00
$653,670.00
$544,725.00
$217,890.00
$217,890.00
$3,006,120.00
$1,187,319.48
$1,700,00.00
$48,814,600.23
ECONOMIC INDICATORS
Cash Inflows:
Product
Benzene
Toluene
Xylene
Paraffin
C9 aromatics
Production
16663363.2 kg/hr
74964528 kg/hr
11742883.2 kg/hr
14732928 kg/hr
5440608 kg/hr
TOTAL
$16,896,650.28
$52,325,240.54
$18,812,098.89
$4,685,071.10
$1,762,756.99
$94,481,817.81
= $70,861,363.36
Net cash inflows = net income operating cost
= $70,861,363.36 - $50,366,274.20
= $20,495,089.16
Payback Period = capital cost / net cash inflows
= $48,814,600.23/$20,495,089.16
= 2.39 years
Net Present Value = Total capital investment
(1 + )
$20,495,089.16x10
(1+0.05)10
$48,814,600.23
= $77,007,468.45
Rate of Return
100%
$20,495,089.16
100%
$48,814,600.23
=41.96%
CHAPTER VI
ENVIRONMENTAL MANAGEMENT
Environment sustainability is a one of the realistic constraints to be considered
in the design of the Benzene, Toluene and Xylene Manufacturing Plant. The BTX
plant should not be technically and economically feasible but be an aid in the
growth of the environment and community. An environment impact assessment
(EIA) was developed to determine potential impacts and identification of
procedures that may be used to mitigate these effects. The BTX manufacturing
plant, through the EIA, aims in the optimization of positive impacts and minimizing
negative impacts resulting from the proposed project.
A. General Information
Table 11. General Information of the Project
Title of the Project:
Type of Project:
Fuel
Oil
Gas
Flare stack
All source (except flare stack)
Gas Turbine
Gas
Oil
Parameter
particulate
Sulphur dioxide
Nitrogen oxide
hydrocarbon
Particulate
Sulphur dioxide
Nitrogen oxide
opacity
Nitrogen oxide
Opacity
opacity
opacity
Nitrogen oxide
Nitrogen oxide
Emission
Quality
Standard unit:
mg/Nm3
400
1500
1000
200
300
1200
1400
40%
400
40%
40%
40%
400
600
Note :
Gas Volume is in standard condition (25C and 1 atm)
Opacity is used as monitoring practical indicator
Combustion with oil and gas fuel. O2 correction is 3%
Quality standards of emission is applied for 95% normal operation time for 3
months.
Parameter
BOD 5
COD
Minyak dan
Lemak (Oils and
Fats)
Dissolved
sulphides
Ammonia (as
NH3-N)
Phenol Total
Temperature
pH
Liquid waste
volume per
maximum raw
material volume
Max.
Content
(mg/L)
80
160
Max
contamination
Load (gram/m3)
80
160
20
20
0.5
0.5
0.8
45 C
6-9
1000
0.8
measurement method
methode pengukuran
SNI 06-2503-1991
SNI 06-6989.2-2004 atau
SNI 06-6989.15-2004 atau
APHA 5220
SNI 06-6989.10-2004
Table 14. Quality Standard Drainage of Waste Water Disposal And Water
Coolers Petroleum Processing Activities (Baku Mutu Pembuangan Air
Limbah Drainase Dan Air Pendingin Kegiatan Pengolahan Minyak Bumi)
Jenis Air Limbah parameter
Max
measurement method
The Type Of
content methode pengukuran
Waste Water
(mg/L)
Drainage liquid
Oil and grease
15
SNI 06-6989.10-2004
waste
Total organic
110
SNI 06-6989.28-2005
carbon
Cooler liquid
Chlorine residue
2
Standard method 4500-Cl
m
Total organic
4.5
SNI 06-6989.28-2005 atau
carbon
APHA 5310
Note:
If drainage liquid waste mix with processing liquid waste, the mixed liquid waste
should meet quality standard of processing liquid waste disposal process.
Calculation is based on difference between outlet and inlet.
Table 15. Appendix III Indonesian Government Regulation Number 101 Year
2014 On The Management Of Hazardous And Toxic Waste. Quality Standard
Features on TCLP For Determination Of Toxic Waste Category B3.
TCLP-A
TCLP-B
(mg/L)
(mg/L)
6
3
210
4
150
0,9
15
60
3
0,3
21
21
3
40
0,4
300
1
0,5
35
0,5
25
0,15
2,5
10
0,5
0,05
3,5
3,5
0,5
5
0,05
50
75000
21
450
40
15000
900
12500
3,5
75
5
2500
150
3
0,004
1,2
0,5
0,0005
0,2
1. Klorobenzena chlorobenzene
Kloroform chloroform
120
15
24
2 Klorofenol chlorophenol
Kresol (total) cresol
120
800
5
100
2,4
0,4
300
90
15
12
6
50
15
2,5
3
1
80
0,52
90
180
10
0,065
15
30
Formaldehida formaldehyde
Heksaklorobutadiena hexabutadiene
200
0,18
25
0,03
800
8
100
1
56
6
7
1
1,1,1,2-Tetrakloroetana tetrachloroethane
40
1,1,2,2-Tetrakloroetana tetrachloroethane
Tetrakloroetena tetrachloroethane
Toluena Toluene
Triklorobenzena (total) trichlorobenzene
1,1,1-Trikloroetana trichloroethane
1,1,2-Trikloroetana trichloroethane
5,2
20
210
12
120
4,8
0,65
2,5
35
1,5
15
0,6
Trikloroetena trichloroethane
2,4,5-Triklorofenol trichlorophenol
2,4,6-Triklorofenol trichlorophenol
Vinil klorida vinyl chloride
Ksilena (total) xylene
2
1600
8
0,12
150
0,25
200
1
0,015
25
1,2-Diklorobenzena 1,2dichlorobenzene
1,4-Diklorobenzena 1,4 dichlorobenzene
1. 1,2-Dikloroetana 1,2- dichloroethane
1,1-Dikloroetena 1,1-dichloroethane
Diklorometana (metilen klorida) Dichloromethane (
methylene chloride )
1. 2,4-Diklorofenol 2,4 - diklorofenol
2,4-Dinitrotoluena 2,4 - Dinitrotoluene
Etilbenzena ethylbenzene
Ethylene diamine tetra acetic acid (EDTA)
Note:
1. TCLP (Toxicity Characteristic Leaching Procedure).
2. Hazardous waste category 1 (Limbah B3 Kategori 1) is wastes that have
contamination level more than TCLP-A.
3. Hazardous waste category 2 (Limbah B3 Kategori 2) is wastes that have
contamination level more than TCLP-B, and less than/same as TCLP-A
4. For Petroleum refinery wastes, category 1 consists of primary refinery sludge
from gravitational separation during processing or storage, secondary refinery
sludge, residue at the bottom of tank, solid slop.
5. Category 2: used catalysts, used active carbon beside waste with code A110d,
used filters (include clays spent filter), dust from air pollution control facilities.
Table 16. International Conventions Relating To Environmental and Social
Aspects
Year of Signing
Description
Conventions relating to flora and fauna
1992
Convention on Biological
Diversity, Rio de janeiro
1979
Convention on the
conservation of migratory
species of wild animals
1997, Kyoto
Comments
Applicable to the Plant
because some
ecosystems are in the
zone affected by the
planned Plant
Applicable because
igration routes of some
migrating animal species
might cross the zone
affected by the proposed
project.
Applicable because the
operation of the project
will cause certain
changes in amounts of
greenhouse gas
emissions.
Applicable because the
operation
1949
1923
1950
1959
1963
1979
1983
ILO convention 95
Protection of wages
ILO Convention 14.
weekly rest in industry
ILO Convention 87
Freedom of association
and protection of the right
to organize
ILO convention 105
abolition of forced labor
ILO convention 119
guarding of machinery
ILO convention 148
working environment (air
pollution, noise and
vibration
Ilo convention 155
occupational safety and
health
The convention is
applicable
The convention is
applicable. Measures for
regulation of labor issues
are to be taken at the
national, regional and
local levels, as well as
the level of different
sectors of economic
activities
applicable
applicable
applicable
applicable
applicable
applicable
2007
Revised
recommendations of the
organizations for
economic cooperation
and development (OECD)
referring to general
approaches for the
identification and the
assessment for the
identification and the
assessment of
environmental impact in
case of project financing.
Comments
The equator principles are
applied by the worlds
leading financial
organizations to make
decisions relating to
project financing. They
constitute a system of
indicator identification,
assessment and
prevention of potential
environment and social
risks. The principle apply
to all new project
financings with total
project capital costs of
USD 10M or more.
OECD recommendations
are applied by the worlds
leading financial
organizations when
making decisions related
to financing of project with
a repayment period of 2
years and more.
In general, the OECD
recommendations are
similar to the equator
principles regarding key
issues.
Site description
Infrastructures
Adjacent
industries
Road
TPC Indonesia
5.2 hectares
Quality
Seawater
Employment Issues
Agricultural, industrial
1,177,201 population (2010)
Religion is dominated by Islam
suspected terrorist activity
political demonstrations and protests
petty crimes
natural disaster
5.9 % unemployment rate (2014)
Climate
Temperature
Humidity
wind speed
and direction,
seasonal storm data
Water quality
Air quality
Noise
3,856,275 Ha
40,569,786 Ha
Garden
(building
and
business purposes, etc)
Forest
Irrigation reservoir
Lake
Entirely tropical
23C 33C
79%
8 km/h
9,778,637 Ha
5,550,015 Ha
492,160 Ha
169,740 Ha
Keep away from heat, sparks, and flame. Keep away from sources of
ignition. Store in a tightly closed container. Store in a cool, dry, wellventilated area away from incompatible substances.
2.4 Xylene
2.4.1 Hazard Identification
Mixed Xylene is classified as a flammable liquid. Other hazards of
xylene include skin corrosion/irritation, serious eye damage/eye irritation,
content
in
wastewater.
Potential Impact
Risks on
Health and
safety
Potential Impact
Risks on Labour
Employment and
Community
( )
Where:
SP = Steam produced
Hs = 1190 btu/lb, enthalpy of steam @ 100 PSIG
Hw = Enthalpy of feedwater @ saturation temperature
Be = Boiler efficiency
VHI = Fuel heating value of bunker fuel
G. Mitigating Measures
Table 23. Mitigating Measures
AMOUNT
Mitigation measures
DO 1
Wastewater No
process
water is
used
DO 2
No
process
water is
used
DO 3
Zero
Discharge
Policy
Sludge is
recycled by
GBG
Indonesia
Solid and
Hazardous
Waste
No solids
and
hazardous
waste is
produced
No solids
and
hazardous
waste is
produced
Hazardous
waste are
recycled by
Havenplus
Indo Ltd
Solid
wastes are
to
collected
by
municipal
waste
disposal
unit
Solid
wastes
are to
collected
by
municipal
waste
disposal
unit
Solid wastes
are to
collected by
municipal
waste
disposal unit
An
API
oil-water
separator should also be
used to separate gross
amounts of oil and
suspended solids from
the
wastewater
effluents/storm
water
runoff.
Using steam and sour
water strippers remove
hydrocarbons
Storage
equipment
should meet standards
for structural design and
integrity.
Dewatering technologies
can
be
used
to
significantly reduce the
volume of sludge, and
recycle oil and water
A Spill Response Plan
should be prepared, and
the
capability
to
implement
the
plan
should be in place.
The Spill Response Plan
should address potential
oil, chemical, and fuel
spills
from
facilities,
transport
vehicles,
loading and unloading
operations,
pipeline
ruptures, and proximity of
water bodies.
AMOUNT
DO 1
DO 2
Mitigation measures
DO 3
Deployment of vapour
recovery systems to
collect
the
VOCs
emitted during transfer
process operations.
Gaseous
emissions
1.29 x 103
MT per
year CO2
29.9 X 103
MT per
year CO2
Equipment
for
transferring the product
into and out of storage
will
consist
of
12.7 X 103
aboveground
piping,
MT per year hoses/loading
arms,
CO2
valves,
pumps,
instrumentation
and
alarms.
Installing an internal or
external floating roof
tank
to
minimize
evaporation losses of
the
product
being
stored.
Above Storage Tanks
(ASTs) should have a
secondary containment
area that contains spills
and allows leaks to be
more easily detected
H. Monitoring Plan
The proposed monitoring plan is designed to determine the effectiveness
of mitigation and to verify predictions and comply with the Indonesian
environmental laws.
Geographic Information System (GIS) monitoring will be implemented to
CHAPTER VI
EVALUATION OF DESIGN OPTIONS
Design options were evaluated using Pareto optimum method and the best
design option was chosen.
Table 24. Summary of Multiple Realistic Constraint VS Design Options
Mutiple
Realistic
Constraint
Technical
Economic
Environmental
Specific
Constraint
Design
Option I
Design
Option II
Design
Option III
Plant Overall
Efficiency
Net Present
Value (NPV)
Gaseous
Carbon
Dioxide
Emission
74.33 %
70.69%
76.93 %
USD 41.107
M
1.29 x 103
MT per year
CO2
USD 4.17 M
USD 77.01 M
29.9 X 103
MT per year
CO2
12.7 X 103
MT per year
CO2
Specific
Constraint
Design
option I
Design
Option II
Design Option
III
Normalization
Coefficient
(base of 10)
5
Plant
Overall
Efficiency
Net Present
Value
Gaseous
Carbon
Dioxide
Emission
74.33 %
(7.92)
70.69%
(5)
76.93 %
(10)
(7)
(5)
(8)
3.5
1.29 x 103 MT
per year CO2
(low)
(10)
29.9 X 103 MT
per year CO2
(high)
(5)
12.7 X 103 MT
per year CO2
(medium)
(8)
1.5
Based from the table and computations, design option I has a 79.1
evaluation value, design option II has 50 evaluation value and design option III has
90 evaluation value. Therefore, the best design option using Pareto Optimum
evaluation is design option III.
CHAPTER VII
PROJECT CONSTRUCTION AND EXECUTION PLAN
benzene, 98% or higher purity of toluene and 98% or higher purity of mixed
xylene.
Gas chromatography and capillary column gas chromatography are used
for determining the concentrations of known impurities in finished benzene,
toluene and xylene. This is an integral quality control tool that generally applied to
determine impurities each of the finished products.
PROJECT COMMISSIONING
Project commissioning is the process of assuring that all systems and
components of an industrial plant is designed, installed, tested, operated, and
maintained according to the operational requirements of the owner or final client.
On this design, commissioning lasts for four weeks. On this time span, engineers
and safety inspectors will check the installation of different equipment and its
controls to ensure plant safety. Then, plant will be operated and then check the
operating pressure and temperature to ensure the quality of products. After series
of test run, plant is now ready for production.
First Month
1st 2nd
Land Acquisition
Negotiation
Titling
Permits
Layouting and Site Preparation
Procurement / Bidding of materials
Foundation of Equipments
Buildings
Fabrication
Delivery
Equipment Installation
Insulation
Piping Installation
Electrical Installation
Instrumentation and Control
Painting
Safety Inspection
Dry-run
Operation Proper
3rd
4th
Gantt Chart
Second Month
1st 2nd 3rd 4th
Third Month
1st 2nd 3rd
4th
Fourth Month
1st 2nd 3rd
4th
Gantt Chart
Fifth Month
1st 2nd 3rd
Land Acquisition
Negotiation
Titling
Permits
Layouting and Site Preparation
Procurement / Bidding of materials
Foundation of Equipments
Buildings
Fabrication
Delivery
Equipment Installation
Insulation
Piping Installation
Electrical Installation
Instrumentation and Control
Painting
Safety Inspection
Dry-run
Operation Proper
4th
Sixth Month
1st 2nd
3rd
4th
Seventh Month
1st 2nd 3rd
4th
Eighth Month
1st 2nd 3rd
4th
Gantt Chart
Ninth Month
1st 2nd 3rd
Land Acquisition
Negotiation
Titling
Permits
Layouting and Site Preparation
Procurement / Bidding of materials
Foundation of Equipments
Buildings
Fabrication
Delivery
Equipment Installation
Insulation
Piping Installation
Electrical Installation
Instrumentation and Control
Painting
Safety Inspection
Dry-run
Operation Proper
4th
Tenth Month
1st 2nd 3rd
4th
Eleventh Month
1st 2nd 3rd
4th
Twelveth Month
1st 2nd 3rd
4th
Thirteenth Month
1st 2nd 3rd
Land Acquisition
Negotiation
Titling
Permits
Layouting and Site Preparation
Procurement / Bidding of materials
Foundation of Equipments
Buildings
Fabrication
Delivery
Equipment Installation
Insulation
Piping Installation
Electrical Installation
Instrumentation and Control
Painting
Safety Inspection
Dry-run
Operation Proper
4th
Gantt Chart
Fourteenth Month
1st 2nd 3rd 4th
Fifteenth Month
1st 2nd 3rd
4th
Sixteenth Month
1st 2nd 3rd
4th
Seventeenth Month
1st 2nd 3rd 4th
Land Acquisition
Negotiation
Titling
Permits
Layouting and Site Preparation
Procurement / Bidding of materials
Foundation of Equipments
Buildings
Fabrication
Delivery
Equipment Installation
Insulation
Piping Installation
Electrical Installation
Instrumentation and Control
Painting
Safety Inspection
Dry-run
Operation Proper
Gantt Chart
Eighteenth Month
1st 2nd 3rd 4th
Nineteenth Month
1st 2nd 3rd 4th
Twentieth Month
1st 2nd 3rd
4th
CHAPTER VIII
SUMMARY, CONCLUSION AND RECOMMENDATION
BIBLIOGRAPHY
Agatonovic, V. and E. Vaisman. 2005. Sulfolane impacted soil and
groundwater treatability study. EBA Engineering Consultants, Ltd. And University
of Calgary Tomographic Imaging and Porous Media Laboratory.
Al Harbi, A. 2004. Corrosion problem in sulfolane extraction unit (U 7300).
Second Middle East Nondestructive Testing Conference, Vol. 9, No. 4. April.
Alberta Environment. 2009. Alberta Tier 1 Soil and groundwater
remediation guidelines. February.
Barr Engineering. 2010. Site Characterization Work Plan, North Pole
Refinery, prepared for Flint Hills Resources Alaska, LLC. April.
Beveridge, J.,Mair and Mathu Hamaiengar, Analytical Chemistry, Vol.30,
No.2, February1958.
Booz, Allen and Hamilton, Inc. Foster D. Snell Division. Benzene Emission
Control Costs in Selected Segments of the Chemical Industry. Florham Pack,
New Jersey. June 1978.
Boucher and Jones Fuels. 2010. HT Severe Hydrocracking Clearly
Superior. www.boucherandjone.com/hydrocracking.htm, accessed May 11, 2010.
Cader, G.A., and B.B. Horton. Equipment Component Analysis for
Identification of Potential Fugitive Emission Sources. U.S. Environmental
Protection Agency, Research Triangle Park, North Carolina. June 1978.
Canadian Council of Ministers of the Environment (CCME). 2006.
Canadian Environmental Quality Guidelines for Sulfolane: Water and Soil,
Scientific Supporting Document.
Column
Design.
Copyright
1997.
http://lorien.ncl.ac.uk/ming/distil/distil0.htm
Doucette, W.J., J.K. Chard, B.J. Moore, W.J. Staudt and J.V. Headley.
2005. Uptake of sulfolane and diisopropanolamine (DIPA) by cattails (Typha
latifolia). Microchemical Journal, Vol. 81, pp. 41-49.
Douglas, James. Conceptual Design of Chemical Processes. McGrawHill, Inc., 1988, Section A.3.
Drazaj, B., Hocevar, S., and Pejovnik, S., "Zeolite, Synthesis, Structure,
Technology and Application", Elsevier Science Publishing Company, Inc., New
York, 1985.
Equilon Enterprises, LLC. 1998. RECAP Screening Option Report: RiskBased Assessment for the RCRA Corrective Measures Study, submitted to
Louisiana Department of Environmental Quality. November 1998.
Ethirajulu, K., Roy, A., Chemical Age of India, 38, 45 (1987).
2005,
Environmental
Information
Report,
TASNEE
APPENDIXES
APPENDIX A
(Demand Projection)
DEMAND PROJECTION
Demand projection is the activity of estimating the quantity of a product or
service that consumers will purchase in future. Demand forecasting involves
techniques including both informal methods, such as educated guesses, and
quantitative methods, such as the use of historical sales data or current data
from test markets. The demand projection of this project study is based in the
United Nations Commodity Trade Statistics Database.
200000000
180000000
160000000
140000000
120000000
100000000
80000000
60000000
40000000
20000000
0
2005
2010
2015
2020
2025
2030
2035
2040
2045
350000000
300000000
250000000
200000000
150000000
100000000
50000000
0
2005
2010
2015
2020
2025
2030
2035
2040
2045
50000000
45000000
40000000
35000000
30000000
25000000
20000000
15000000
10000000
5000000
0
2000
2005
2010
2015
2020
2025
2030
2035
2040
2045
small proportions in gasoline and jet fuel. It is a raw material in the production of
a monomer which is a simple compound with molecules that join together to form
polymers called terephthalic acid.
APPENDIX B
(Market Share)
MARKET SHARE
The target costumers of Benzene, Toluene and Xylene plant are the
ASEAN Country particularly Singapore, Cambodia, Indonesia and Vietnam.
Those are the countries where benzene, toluene and xylene are in great
demand. According to United Nations Commodity Trade Statistics Data Base,
among the ASEAN Countries, for benzene products, Singapore is the primary
costumer. While for toluene products, Cambodia, Indonesia and Vietnam are the
target consumers. And for xylene products the companys major costumer is
Indonesia.
Product
Country
Benzene
Singapore
246,272,210.00
196,267,253.00
Cambodia
233,820.00
Indonesia
92,117,424.00
Vietnam
88,372,340.00
448,728.00
Indonesia
35,248,531.00
Toluene
Xylene
Import (kg)
Export (kg)
Product
Country
Demand (kg)
Companies
Market Share
Benzene
Singapore
50,004,957.00
16,668,319.00
Cambodia
233,820.00
233,820.00
Indonesia
92,117,424.00
30,705,808.00
Toluene
Vietnam
87,923,612.00
43,961,806.00
Xylene
Indonesia
35,248,531.00
11,749,510.33
103,319,263.33
BTX
Manufacturing
Plant
33%
Petrochemical
Corporation of
Singapore Private
Limited
34%
Chemical ITOCHU
SINGAPORE
33%
BTX
Manufacturing
Plant
100%
BTX
Manufacturing
Plant
50%
Petrochemical
Corporation of
Singapore Private
Limited
50%
BTX
Manufacturing
Plant
33%
PT. BiWon
Chemical
34%
PT. Anugrah
Putra Kencana
33%
APPENDIX C
(Material Safety Data Sheet)