Académique Documents
Professionnel Documents
Culture Documents
SPH Chapter 20
Considerations
This presentation is meant to be an overview only
This presentation is not meant to replace manufacturers
approved procedures for installation and pulling of submersible
pumping systems
Guidelines / Content
HS&E
Proper Tooling
Pre-installation Checks
Installation
Commissioning
Pulling
SPH Chapter 20
SPH 191
Proper Tooling
All tools used should be of the proper design and in
good working order
Use properly designed and certified lifting clamps
and slings
Meters should be in good condition and regularly
calibrated to insure accuracy
SPH 191
Proper Tooling
SPH 191
Proper Tooling
Use properly designed and
certified lifting clamps and
slings
Appropriate
Equipment for
Clamp Design
SPH 191
Proper Tooling
SPH 191
Pre-Installation
Locate and verify equipment
Position equipment for lifting
Document serial numbers & specifications
Do pre-install equipment checks
Assess site risks
Tool Box Talk
Prepare work site
SPH 191
Pre-Installation
Pre-Installation
Document serial numbers & specifications
SPH 191
Pre-Installation
SPH 191
Pre-Installation
SPH 191
Installation Overview
SPH 193
Installation Overview
SPH 194
Installation Overview
SPH 194
Seal Filling
Seal Filling
Seal Filling
Motor
Fill
Valve
Seal Filling
Motor
Fill
Valve
Seal Filling
Motor
Fill
Valve
Seal Filling
Motor
Fill
Valve
Seal Filling
Installation Overview
SPH 194
Installation Overview
Running In Hole
Run rate should be steady, but allow time for cable
banding / clamping
SPH 195
Running In Hole
Run rate should be steady,
but allow time for cable
banding / clamping
Cable / By-pass
Tubing Clamp
SPH 195
Running In Hole
If a field cable splice is required, the process should be
done by certified personnel using the manufacturers
approved procedures & components
SPH 195
Running In Hole
SPH 195
SPH 198
Pulling
A unit that has shut down and does not restart
SPH 198
Pulling Report
SPH 198
Summary
Any Questions?