ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)
ResourceProgressCurvesinPrimaveraP6
Writtenby:2/5/201312:22:00AM
ThisdocumentdiscussesthefeaturesofP6thatcurrentlylinktheactualandforecastresource
curve,whiletouchingonsomeofthecurrentshortfallsinmanagingresourcesinP6.Indepth
coverageofeachfeaturedescribedhereinisbeyondthescopeofthisdocument.
Displayingacontiguousresourcecurvelinkingtheactualcurvewiththeremainingcurvehas
oftenseemednotpossibleinP6,duetomostP6teachingoccurringonlyontheResource
UsageProfile(wherethisisnotpossible).ThisabilityisavailableinP6usingtheActivity
UsageProfileortheTrackingfeature.
NotethatBaselineoptionsarenotavailableintheResourceUsageProfile,onlybudgeted
values.Budgetedvaluesessentiallydonotworkonceyouhaveprogressinyourschedule.
Question:WhatisthedifferencebetweenBudgetedvs.Baseline?TheyareNOTthesame.
SampleResourceUsageProfile
TheRemainingUnitscurvestartsatzero(0).Plannerswouldliketheactualcurveto
linkwiththeremainingcurve(likeitdidinP3).
TheBudgetedUnitsarespreadovertheactivitybythePlannedStartandPlanned
Finishdatesoftheactivity,whichwillchangewhenthedatadatemoves(for
activitiesnotstarted).
Note:TherearenoBaselineUnitsorBaselineCurvesavailableintheResource
UsageProfile.
ActivityUsageProfile
UsetheActivityUsageProfileinP6toviewcostorunitvaluesovertimeaccordingtothe
selectedtimescale.TheActivityUsageProfiledisplaysresourceallocationsforallactivities
orforselectactivities.
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx
1/8
22/08/2015
ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)
Thisprofilecandisplayresourcelabor,unitsandcostswithperiodicverticalbarsaswellasa
varietyofcumulativecurves(early,late,baseline,earnedvalue(EV))forperiodsbasedon
theselectedtimescale.
Thereareavarietyofcustomizationoptionsavailable.PleasereadtheP6Helpforadditional
informationorrefertoyourcompanyP6TrainingManuals.
SampleActivityUsageProfile
Steps
1.SelectView>ShowonBottom>ActivityUsageProfile(onthetoolbar)
2.Periodicamountsaredisplayedontheleftaxis,cumulativeamountsontherightaxis(They
arenotcustomizable)
3.Displaythetimescaleinweeksforbestresults,unlessyourdatadateisthecalendarmonth
end
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx
2/8
22/08/2015
ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)
4.CustomizeyourheadersandfootersinPrintPreview
Tocustomizetheactivityusageprofileoptions:
SelectDisplay(orrightclickinthegraph)>
ActivityUsageProfileOptions:
Stepstocreateanactualcurvelinkedtoaremainingunitscurve:
Resourceloadtheschedule.
Createandassignaprojectbaseline(allowsuseofthevariousEarnedValue(EV)unit
options)
Inordertogettheresultdesired,youwillneedtoensureyouselecttherightcumulative
curves.
TheResourceUnitsgraphabovewascreatedusingthefollowingoptions(ForLaborUnits):
BaselineBar
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx
3/8
22/08/2015
ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)
ActualBar
ActualCumulativeCurve
RemainingEarlyBar
PlannedValueLaborUnits
EstimateatCompletionLaborUnits
TheRemainingEarlyCurvebeginsatthedatadatestartingat0h(whichwasnotthecaseinP3).To
getalinkedcurve,eitherusetheEstimateatCompletionLaborUnitscurveorcombinethiscurve
withtheActualcurvetoclearlydifferentiatebetweenhistoricalvs.forecastvalues.
Oneoptionistoshowjustthecurves,withouttheperiodicbars(i.e.justshowthecurves).
Note:Ifyouremovethebars,someperiodicvaluesontheleftofthegraphwillstillshow,butignore
them(2,4,5,6,8hetc.).Usethecumulativevaluesontherightsideofthegraph.
GeneralP6Settings(ActivityandProject,useDefaultWBSEarnedValueSettings)
DurationType=FixedDuration&Units
PercentCompleteType=Units%Complete
Resources=Driving
CalculationsTabSettingsintheProjectsWindowbelow:
TabularEarnedValueinformationintheActivitiesTable:
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx
4/8
22/08/2015
ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)
Note:Theabovecolumnshavebeenrenamedinthislayout.
TrackingFeature:
Summaryinformationallononepage
ProvidesresourceanalysisattheProjectorWBSlevel
Tips:
AvoidusingBudgetedValuesorCurvesonceyouhaveprogressintheschedule.
Ifyoudonthaveabaseline,youwillbedependentonplanneddates(whichslide).
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx
5/8
22/08/2015
ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)
ResourceActuals
TomoreaccuratelycaptureresourceactualsbyperiodrequiresusingtheFinancialPeriodsfeaturein
P6,otherwisetheoverallactualcurvewillbeincorrectasitsspreadovertheactivitylifetime.
InthecompanyP6Production&Stagingdatabases,thefinancialperiodsaresetuptomatchthe
companymonthlyfiscalperiodcutoffs.DuetoP6Limitations,thereisnoabilitytohavemultiple
variationsoffinancialperiodsinthecurrentversion(P68.2).Thenumberofperiodsislimitedand
cannotoverlap.
Thecumulativeindividualactualresourcecurveforeachresourceisadjustedeverytimethedatadate
ismoveduntiltheresourceiscomplete.Theactualresourcecurveisspreadbasedontheresource
curveassigned,justliketheforecastcurveisspread.Thecumulativecurveisasumoftheparts.
Theactualunitsarenotstored,bydefault,byanyperiod,butdistributedbasedontheresourcecurve
assigned(fromtheresourcestartdatethroughthedatadatetotheresourcefinishdate.
Thismeanstheactualperiodicamountswillbeadjustedoverthelifetimeoftheactivityduration,as
newactuals(earned)arerecordedforaresourceassignment.Thiswillaffectthehistoricalresource
curves,astheyarearollupofalltheactivitiesresourceassignments,distributedbythepercentages
allocatedtotheassignedresourcecurve.
InSummary,donotrelyontheaccuracyofthehistoricalprogressdatashowninP6.Inorderto
achievemoreaccuratehistoricaldata,storetheperiodicunitsinthefinancialperiodsfeatureinP6.
Theforecastbarsandcurvesareaccurate,butonlythehistoricalbaselineorPVcurveisaccurate,not
theactualcurve.
Resourceassignment(historical)withnocurve(linearbydefault)
ActivityUsageProfilewithalinearcurve
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx
6/8
22/08/2015
ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)
RelatedSearch
byWanderBurst
PopupBlocked
AllowOnce
AllowAlways
Options
RelatedSearches
Construction
Engineering
CivilEngineering
SameResourceassignmentwithcurveadded
Notethesignificantadjustmentoftheactualunitshistogramandcurve
ProjectControls
ProjectCost
Management
ConstructionAnd
ProjectManagement
SameActivityUsageProfilewithabellshapedcurve(samedataasabove)
ConstructionProjects
CostEngineering
WhilethegraphicsinP6arelimited,particularlywithcustomizationcapabilities,theydosavetime
versuscustomizinggraphsinexcel.
Itisimportant,priortoproceedingdownaP6resourcemanagementpath,toensurethateach
ProjectsunderstandingoftheabilitiesofP6arecorrect,priortoovercommittingandunderdelivering.
Itisoftenseenthatplannersandprojectsembarkonacomplexpath,withouttestingifthe
softwarewillsupporttherequirements.
http://www.projectcontrolsonline.com/Blogs/tabid/103/EntryId/105/ResourceProgressCurvesinPrimaveraP6.aspx
7/8
22/08/2015
ResourceProgressCurvesinPrimaveraP6(PrintFriendlyView)