Académique Documents
Professionnel Documents
Culture Documents
hearing today.
NTPC
Share
Mumbai: The National Thermal Power Corp, which had been silent in the face of accusations by Reliance Industries
(RIL) in the past month, finally opened up on Thursday.Issuing a 'corporate disclosure', NTPC rubbished RIL's charge that
it was forcing consumers in Gujarat to pay more by refusing to buy its gas.
On the contrary, NTPC said, buying RIL's gas at $4.2 instead of the $2.34 that was initially offered will cost power
consumers an extra Rs 32,000 crore over the next 17 years.
In a series of letters, over the past month, RIL has said NTPC's decision to buy LNG abroad will raise power tariff in
Gujarat.
RIL's head of petroleum business, P M S Prasad said NTPC was buying spot gas for as high as $11.2 against a delivered
price of $6.7 offered by RIL.
This increased the cost of power by Rs 1,500 crore per year, Prasad said.
In its 'corporate disclosure' NTPC defended its decision to buy more expensive gas from the spot market till its dispute
with RIL is sorted out. It pointed out that buying gas at $4.2 from RIL, though profitable in the short-term, will impact its
legal standing in its fight with RIL to get gas at $2.34. It also pointed out that, unlike the RIL contract, it could stop
purchasing spot gas as soon as the Bombay High Court delivers its verdict.
Moreover, it pointed out, unlike RIL's terms and conditions, spot gas buys did not involve any 'take or pay' obligation and
therefore did not require NTPC to pay even if it did not use the gas.
"NTPC is a customer-focused power utility and it very well understands the impact of fuel price in the overall cost of
electricity and always makes efforts to source fuel at competitive price... NTPC has already been procuring spot RLNG at
competitive rates from market through tenders and without any take or pay liability. Since there is no take or pay liability
clause, generation of power from spot RLNG is done as per the schedule given by the beneficiaries [state electricity
board]," it pointed out.
The 'corporate disclosure' also answered RIL's question as to why NTPC was insisting on a lower price when it can easily
pass on its fuel price to the consumers. "NTPC is a long-term player in the field of power sector and works on corporate
ethics. For NTPC, fuel pass-through means protection of long-term interest of its customers by sourcing of fuel at the most
competitive price and NTPC always strives hard for keeping the fuel price at the lowest possible," it pointed out.
Morever, NTPC said, buying gas at $4.2 instead of the $2.34 promised by RIL in a tender process in 2004 would cost
power consumers an extra Rs 32,000 crore.
"The delivered price of gas considering the commodity price of $2.34/mmBtu works out to $3.30/mmBtu... The delivered
price [at $4.2] will work out to be $6.67/mmBtu. The variable cost of power considering $3.30/ mmBtu is Rs 1.07 per unit
and with $6.67 /mmBtu it works out to be Rs 2.17 per unit.
The expansion project of 2600 MW at Kawas & Gandhar will generate 19.36 billion units of electricity in a year. The total
savings in a year for purchase of this electricity by distribution companies and state electricity boards will be around Rs
2,130 crores per year. For 17 years, it works out to be around Rs. 32,000 crores and will directly benefit the consumers," it
argued.
NTPC also countered RIL's argument that NTPC was demanding very steep compensation from RIL if it failed to supply
gas, according to the tender. NTPC pointed out that RIL had agreed to the terms when it submitted its in the international
bidding process in 2004.
"After the bid evaluation process including unconditional acceptance of the GSPA (gas supply agreement), including
liability clause in the event of default of supply of gas, the bid of Reliance Industries was accepted on 16th June 2004 and
Letter of Intent (LOI) was issued to RIL for supply of 132 trillion Btu per annum (12 MMSCMD approx) natural gas at a
price of $ 2.34/ mmBtu... Price bid was submitted by all bidders without any condition. After the placement of LOI and its
acknowledgement by RIL, a contract came into existence with draft of GSPA," it said.
"As NTPC insisted upon RIL for executing the GSPA as per the draft finalised during bidding process, RIL instead of
honouring the contract and executing the GSPA unilaterally modified the GSPA in December, 2005 and signed and
forwarded the same to NTPC for countersigning. These unilateral changes were unacceptable to NTPC and were
unfavourable to customers. NTPC in these circumstances was constrained to file a suit against RIL for specific
performance in the Bombay High Court.," it added.