Vous êtes sur la page 1sur 8

See

discussions, stats, and author profiles for this publication at: http://www.researchgate.net/publication/229284815

Construction claims in United Arab Emirates:


Types, causes, and frequency
ARTICLE in INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT JULY 2006
Impact Factor: 1.53 DOI: 10.1016/j.ijproman.2006.02.006

CITATIONS

DOWNLOADS

VIEWS

19

925

386

1 AUTHOR:
Essam K. Zaneldin
United Arab Emirates University
56 PUBLICATIONS 110 CITATIONS
SEE PROFILE

Available from: Essam K. Zaneldin


Retrieved on: 19 September 2015

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 24 (2006) 453459
www.elsevier.com/locate/ijproman

Construction claims in United Arab Emirates: Types, causes,


and frequency
Essam K. Zaneldin

Department of Civil and Environmental Engineering, United Arab Emirates University, P.O. Box 17555, Al Ain, United Arab Emirates
Received 3 November 2005; accepted 17 February 2006

Abstract
The construction industry in the United Arab Emirates is considered the largest single industry, yet, it is also very complex and the
most fragmented industry as it involves multidisciplinary participants. In this multidisciplinary environment, claims appear to hinder the
completion of construction and cause delays in delivering projects. This research presents the results of a study of the types, causes, and
frequency of construction claims in the emirates of Dubai and Abu Dhabi in UAE using a data from 124 claims for a variety of projects
in the two emirates. The data were analyzed and the results of this analysis along with recommendations on how to reduce/prevent claims
in construction are then presented.
 2006 Elsevier Ltd and IPMA. All rights reserved.
Keywords: Claims; Construction industry; Contracts; International projects

1. Introduction and background


The United Arab Emirates (UAE) government is investing billions of dollars every year in new facilities to improve
the infrastructure of the country. Modern cities have risen
from the barren desert, connected by a vast network of
rst-class roads and linked to the outside world by modern
airports and ports. Housing compounds, schools, hospitals, shopping malls, telecommunications, electricity and
water, luxury hotels, and recreational facilities have all
been provided in a short space of time. The majority of
these projects are being constructed in Dubai and Abu
Dhabi Emirates.
In view of the above, and considering the giant size of
these projects, it is not surprising that the number of claims
continues to increase. Construction claims are considered
by many project participants to be one of the most disruptive and unpleasant events of a project [1]. According to
Vidogah and Ndekugri [2], however, claims are becoming

Tel.: +971 3 713 3043; fax: +971 3 762 3154.


E-mail address: essamz@uaeu.ac.ae.

0263-7863/$30.00  2006 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2006.02.006

a way of life and, indeed, an indispensable part of modern


contract systems. In UAE, construction claims, normally
seen in almost every construction project, are direct results
of the ongoing growth in the construction industry in the
country. In general, claims are common in construction
projects and can happen as a result of several reasons that
can contribute to delaying a project and/or increasing its
costs. Finishing a project on schedule is a dicult task to
accomplish in the uncertain, complex, multiparty, and
dynamic environment of construction projects [3]. To
enhance the chances of success, contractors submitting
claims must closely follow the steps stipulated in the contract conditions, provide a breakdown of alleged additional
costs and time, and present sucient documentation [4].
On the other hand, project owners need to follow an overall comprehensive step-by-step procedure for tracking and
managing the claims submitted by contractors [57].
Once a claim has been presented, the owner and contractor can come to an agreement concerning the claim
and, thereby, create a change order or a modication, or
they may disagree and create a construction contract dispute. Analyzing the various types and causes of claims is
an important task to resolving these claims [8,9]. Since pro-

E.K. Zaneldin / International Journal of Project Management 24 (2006) 453459

ject participants are becoming more aware of the high costs


and risks associated with claims and their litigation, the
construction industry needs to develop methodologies
and techniques to reduce or prevent claims. Even though
construction claims are frequent and their resolution is difcult, many times legal advice is not sought because it is
not available or because it is expensive [10,11].
Several attempts were made in the literature to study the
types of construction claims and determine their main
causes and ways of avoiding them. Scott [7] conducted a
survey to investigate the causes and mechanisms that are
used to prepare and evaluate delay claims in United Kingdom. Hartman and Snelgrove [12] evaluated the eectiveness of written contract language to communicate risk
apportionment between contracting parties. Al-Khalil
and Al-Ghay [13] determined the most important causes
of delay claims in public utility projects in Saudi Arabia
based on the frequency and severity of these causes.
There is still, to a great extent, a lack of information
related to the causes of construction claims in UAE and
the ways to prevent or minimize them. This research, therefore, presents the results of a study of the types, causes, and
frequency of construction claims in the emirates of Dubai
and Abu Dhabi using a data collected for 124 claims
related to dierent projects in the two emirates. The data
are analyzed to identify problem areas and recommendations to reduce claims in construction projects are then
presented.
2. Scope of this study
Information for 124 claims related to dierent construction projects in Dubai and Abu Dhabi Emirates in UAE
were collected. The data were collected from 71 dierent
entities (29 contractors, 33 consultants, and 9 owners) in
the two emirates. The reason of choosing these two emirates is that they represent around 78% of all investments
in the country (see Fig. 1), according to the UAE industrial
statistics report [14]. Based on their main area of specialty,
the proles of the 71 entities are shown in Table 1. The 71
owners and rms were asked to provide information
related to types of projects, amounts of claims requested
by contractors, amounts awarded by owners, and the
method used to resolve each claim. The data for the 124
claims were mainly extracted from owners, consultants,
and contractors claims database. Data of claims that were
resolved by arbitration were examined against those listed

Al-Fujairah
Umm Al-Quwain

Emirate

454

9.2%
0.7%

Raas Al-Khaimah
Ajman

4.9%
1.6%

Sharjah

5.8%
23.3%

Dubai
Abu Dhabi
0.0%

54.5%
10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

Percent of Investment

Fig. 1. Percent of investments in all emirates in UAE.

in the UAE Arbitration Committee database while data


of claims that were resolved by litigation were examined
by reviewing Abu Dhabi and Dubai court rulings.
Owners and rms were also asked to provide information related to types of claims, causes of claims, and frequency of each type and cause by lling a questionnaire,
in which they choose one of ve possible options for the
frequency of each type and cause of claims: (1) never; (2)
rare; (3) average; (4) frequent; and (5) very frequent. The
data were then analyzed and a detailed analysis of the data
is shown in the following section.
3. Data analysis
The data collected represent various types of projects
constructed over a period of around ve years (from
2000 until 2004, inclusive). The types of projects include
buildings, roads and highways, water and sewer lines,
power plants, airports, in addition to a variety of other
types. The distribution of the types of projects is shown
in Fig. 2 with road and building projects having the highest
percentage among all other types (34.7% and 30.6%,
respectively). The data collected were analyzed and a
detailed discussion of the analysis is shown in the following
subsections.
3.1. Types of claims and their frequency
The data received indicated that the types of claims in
construction projects in UAE can be classied into six
main types: (1) contract ambiguity claims; (2) delay claims;
(3) acceleration claims; (4) changes claims; (5) extra-work

Table 1
Proles of respondents
Type of respondent

Number of
respondents

Number of claims

Company main area of specialty


Residential and commercial

Industrial

Roads and highways

Heavy construction

Owner
Designer/consultant
Contractor

9
33
29

18
57
49

12
10

1
2

15
11

5
6

Total

71

124

E.K. Zaneldin / International Journal of Project Management 24 (2006) 453459

455

Table 3
Ranking of each type of claims based on their frequencies

Other, 4.0%
Airports, 4.0%
Buildings,
30.6%

Water Lines,
11.3%

Sewer Lines,
12.1%

Power Plants,
3.2%

Roads, 34.7%

Fig. 2. Distribution of the types of the 124 projects.

claims; and (6) dierent site condition claims. To provide a


realistic idea about the frequency of each type of claims,
rms were asked to ll a questionnaire in which they
choose one of ve possible options for the frequency of
each type of claims, as mentioned in the previous section.
A weight in a scale from 0 to 4 was given for each of the
ve frequencies with a weight of 0 for never, 1 for rare,
2 for average, 3 for frequent and 4 for very frequent. No weight was given when no response was provided. The frequencies for each type of claims received
are listed in Table 2. Responses for the changes type of
claims, for example, indicated that one rm did not
respond, 4 rms responded as never, 9 responded as
rare, 22 responded as average, 21 responded as frequent, and 14 responded as very frequent. Data of
Table 2 were analyzed and a weighted average was calculated for each type of claims as follows:
X
Weighted Average
W i xX i =N ;
1
where Wi is the weight assigned to the ith option; Xi is the
number of respondents who selected the ith option; and N
is the total number of respondents (71 in this study).
To better understand the importance of each type of
claims, an importance index percentage was then calculated
as follows:
Importance Index Weighted Average  100=4.

Types of claims

Importance index (%)

Rank

Changes claims
Extra-work claims
Delay claims
Dierent site conditions Claims
Acceleration claims
Contract ambiguity claims

60.5
60.2
51.1
40.5
39.1
32.7

1
2
3
4
5
6

The importance index values for each type of claims are


shown in Table 3. For example, the weighted average for
the changes type of claims = (0 4 + 1 9 + 2 22 +
3 21 + 4 14)/71 = 2.42. The importance index for this
type of claims = (2.42 100)/4 = 60.5%. The results of this
analysis indicate that changes claims are the most frequent type of claims. This type of claims was ranked rst
with an importance index of 60.5%. Extra-work claims
Table 4
Ranking of each cause of claims based on their frequencies
Causes of claims

Importance
index (%)

Rank

Change or variation orders


Delay caused by owner
Oral change orders by owner
Delay in payments by owner
Low price of contract due to high competition
Changes in material and labor costs
Owner personality
Variations in quantities
Subcontracting problems
Delay caused by contractor
Contractor is not well organized
Contractor nancial problems
Bad quality of contractors work
Government regulations
Estimating errors
Scheduling errors
Design errors or omissions
Execution errors
Bad communication between parties
Subsurface problems
Specications and drawings inconsistencies
Termination of work
Poorly written contracts
Suspension of work
Accidents
Planning errors

55.0
52.5
51.4
48.9
48.6
46.1
45.1
44.7
44.0
43.7
43.7
43.7
42.6
40.1
39.1
39.1
38.4
37.7
37.7
37.0
35.6
35.6
33.8
33.8
33.1
32.7

1
2
3
4
5
6
7
8
9
10
10
10
13
14
15
15
17
18
18
20
21
21
23
23
25
26

Table 2
Frequency of each type of claims
Types of claims

No response

Never

Rare

Average

Frequent

Very frequent

Contract ambiguity claims


Delay claims
Acceleration claims
Changes claims
Extra-work claims
Dierent site conditions claims

7
3
5
1
2
1

14
6
14
4
4
11

23
14
19
9
10
22

15
20
15
22
18
23

8
21
10
21
23
9

4
7
8
14
14
5

456

E.K. Zaneldin / International Journal of Project Management 24 (2006) 453459

were ranked second with an importance index of 60.2%


while contract ambiguity claims were ranked last with
an importance index of 32.70%. The ranks of all types of
claims are listed in the last column of Table 3.

of 55% while delay caused by owner was ranked second


with an importance index of 52.5%. Planning errors cause
of claims was ranked last with an importance index of
32.7%. The ranks of all causes of claims are listed in Table 4.

3.2. Causes of claims and their frequency

3.3. Claim amounts requested by contractors and awarded by


owners

The data received indicated that there are 26 possible


causes of claims. Similar to what is explained in the previous subsection for types of claims, rms were asked to
choose one of ve possible options for the frequency of
each cause of claims: never, rare, average, frequent, and
very frequent with a weight for each in a scale from 0 to
4. Responses for the frequency of the change orders
cause of claims, for example, indicated that 4 rms did
not respond, 4 responded as never, 13 responded as
rare, 18 responded as average, 21 responded as frequent, and 11 responded as very frequent.
A weighted average was calculated using Eq. (1) for each
cause of claims and the importance index percentage was
then calculated using Eq. (2), as shown in Table 4. The
results of this analysis indicate that change orders are
the most frequent cause of claims with an importance index

100%

35
30
25
20
15

30

80%
60%

10
5
0

11

10

7
3

40%
20%

Cumulative Percentage for


the Number of Claims

120%

44

>2
0

12
.5
-1
5
15
-1
7.
5
17
.5
-2
0

10
-1
2.
5

57.
5

02.
5

2.
55

0%
7.
510

Frequency

50
45
40

Further analysis was also performed to nd the frequency of claims for dierent amounts requested by contractors and awarded by owners. In general, claim
amounts requested by contractors range from $111,350 to
$167,245,000. Fig. 3 shows the frequency of claims for different amounts requested by contractors. The gure indicates that the majority of claims (44 claims) are less than
or equal to $2.5 million. The next highest frequency (30
claims) is in the range from $2.5 to $5 million. A total of
only 11 claims are above $20 million. The solid line plotted
in Fig. 3 shows the cumulative percentage for the number
of claims for each range of claim amounts requested by
contractors. It can be observed from the gure that the
amounts requested by owners for around 60% of the claims
are less than $5 million.

Amounts Requested by Contractors (Millions of US$)

Fig. 3. Frequency of claims for amounts requested by contractors.

120%

65

60

100%
80%

40
60%
30
16

20

40%
14

10

10

20%

2
0%
>4

3.
54

33.
5

2.
53

22.
5

1.
52

11.
5

0.
51

0
00.
5

Frequency

50

Amounts Awarded by Owners (Millions of US$)

Fig. 4. Frequency of claims for amounts awarded by owners.

Cum ulati ve Percentage for


the Number of Claims

70

E.K. Zaneldin / International Journal of Project Management 24 (2006) 453459

457

Table 5
Summary of claim amounts based on project types
Type of project

Airports
Buildings
Power-plants
Roads
Sewer-lines
Water-lines
Others
Total

Number
of claims

Amounts requested
by contractors (US$)

Amounts awarded
by owners (US$)

Ratio of amount
awarded/amount
requested

5
38
4
43
15
14
5

82,439,674
216,414,118
34,692,123
289,461,685
356,301,608
138,126,605
36,173,170

8,027,358
32,481,009
27,137,759
42,416,886
14,897,655
30,570,853
29,635,870

0.10
0.15
0.78
0.15
0.04
0.22
0.82

124

1,153,608,983

185,167,390

0.16

On the other hand, the amounts awarded to contractors


by owners range from $0.00 to $21,674,650. Fig. 4 shows
the frequency of claims for dierent amounts awarded by
owners. As illustrated in the gure, the majority of claims
(65 claims) are below $0.5 million. The next highest frequency (16 claims) is in the range between $0.50 and $1
million followed by 14 claims in the range from $1 to
$1.5 million. The solid line of Fig. 4 shows the cumulative
percentage for the number of claims for each range of claim
amounts awarded by owners. As can be depicted from the
gure, the amounts awarded by owners for more than 76%
of the claims are less than $1.5 million.
To give a better understanding of these numbers, claim
amounts were grouped based on the type of project and the
ratios of the amounts requested by contractors and those
awarded by owners were then calculated, as shown in Table
5. These ratios indicated that, on average, only 16% of
claim amounts requested by contractors are awarded by
owners, as shown in the bottom of the last column of Table
5. This can also provide an idea about the risk associated
with each type of project. To owners, it can be assumed
that the higher the ratio, the higher the risk associated with
this type of projects. Based on this assumption, sewer-line
projects with only 0.04 ratio provided the lowest risk to
owners while power-plants with a ratio of 0.78 provided
the highest risk.
4. Case study
A sample case study of a claim is presented in this section. The case is about a contractor specialized in the construction of residential and commercial buildings. The
contractor was asked by an owner to build a 42-story residential building using a lump-sum type of contract. The
building consists of ve dierent apartment types. During
construction, the owner changed the internal layout of
one type and made changes to the internal nishes of
three types of apartments. The contractor submitted a
claim to the owner asking for $5,895,000 as a compensation for the additional costs resulting from the owners
changes. This amount is due to the changes in the specications of the internal nishes and, therefore, the con-

tractor did not ask for any time extension. After


studying and analyzing the contractors claim, the owner
found that these changes do not worth more than
$950,000. After several meetings to negotiate this issue,
the two parties agreed to settle this claim for an amount
of $1,050,000. Although this represents only 17.8% of the
original amount requested, the contractor accepted this
amount as they are normally loath to use arbitration or
go to court to resolve disputes. This is because of the long
time and high costs associated with these two methods of
resolution. Several other cases of claims were also studied
and it was found that changes made by owners represent
the most frequent type and cause of claims in construction projects in UAE, which supports the ndings of this
study.
5. Methods used to resolve claims in UAE
According to the UAE Civil Procedures Code, disputing parties in any construction project may resolve and settle any claim using the normal resolution channels: (1)
negotiation; (2) mediation; (3) arbitration; or (4) litigation.
According to this study, the majority of construction
claims in UAE (77.1%) are resolved using negotiation, as
shown in Fig. 5. The gure also shows that only 4.9% of
claims were resolved using litigation. This conrms that
rms are quite reluctant to go for litigation because of
the long time and high costs and risks associated with this
method of resolution.

Litigation: 4.9%
Arbitration: 5.7%
Mediation: 12.2%

Negotiation: 77.1%

Fig. 5. Resolution methods and the frequency of their use.

458

E.K. Zaneldin / International Journal of Project Management 24 (2006) 453459

6. Recommendations of industry practitioners


Industry practitioners and experts from Dubai municipality and Abu Dhabi Planning Department were asked
to provide recommendations on how to prevent/reduce
claims and how to deal with such claims in case they happen. Based on their recommendations, the following are
some rules-of-thumb on how to reduce/prevent claims in
construction projects:
1. Allow reasonable time for the design team to produce
clear and complete contract documents with no or
minimum errors and discrepancies.
2. Establish ecient quality control techniques and
mechanisms that can be used during the design process to minimize errors, mismatches, and discrepancies in contact documents.
3. Have a clearly written contract with no ambiguity.
4. Read the contract several times before signing it to
understand any unclear clauses.
5. Have a third party to read contract documents before
the bidding stage.
6. Use special contracting provisions and practices that
have been used successfully on past projects. Useful
information can be found in ASCE booklet [15],
which is about avoiding and resolving disputes during
construction.
7. Develop cooperative and problem solving attitudes
on projects through a risk-sharing philosophy and
by establishing trust among partners (e.g., the owner
and the contractor). This concept is known in the literature as partnering.
8. Implement constructability during the dierent stages
of a project.
9. Establish a strategy on how to deal with tighter
scheduling requirements.
10. Have signed change orders before starting doing
these changes on site.
11. Maintain proper job records on a timely manner
including time sheets, diary records, reports, photographs, records of labors and weather and its eect
on progress, progress of the construction, site instructions, etc.

7. Concluding remarks
This study can be used to identify several problem areas
in the construction process in UAE. Steps should be taken
to clarify any issues or conicts that may arise in these
common problem areas. One of the common problem
areas is the changes type of claims which, according
to this study, was the most frequent type of claims and
needs special consideration. Extra-work type of claims
came second and contract ambiguity was ranked last.
It can also be concluded from this study that change
orders are the most frequent cause of claims while delay

caused by owner was ranked second. Planning errors


were ranked last, indicating that it is the least frequent
cause of claims.
According to the results of this study, it is recommended that special consideration should be given to contract clauses dealing with change orders, disputes,
variations and extra works conditions, and delay. The best
means to cope with risk of construction claims is to reduce
or avoid them altogether. There are certain fundamental
means of reducing the number of claims encountered.
The main and essential steps that can be taken to minimize risks and deal with the aforementioned identied
causes include: (1) allowing reasonable time for the design
team to produce clear and complete contract documents;
(2) having a clearly written contract with no ambiguity
by using special contracting provisions and practices that
have been used successfully on past projects; (3) developing cooperative and problem solving attitudes on projects
through a risk-sharing philosophy between the owner and
the contractor.
It is expected that the ndings of this research will assist
all parties to a contract reduce liability by avoiding the
main causes of claims and, accordingly, minimize delays
and cost overruns in construction projects. The suggested
comments are also necessary for proper project management, which is far more advantageous and protable than
seeking advice of a construction claim consultants after the
dispute is entrenched. The latter course often takes place
too late and is too costly.
Acknowledgments
The author of this research thanks the Research
Aairs of the United Arab Emirates University and
gratefully acknowledge their support. The author also
thanks Dubai municipality and Abu Dhabi Planning
Department for the valuable information they provided
for this research.
References
[1] Ho SP, Liu LY. Analytical model for analyzing construction claims
and opportunistic bidding. Journal of Construction Engineering and
Management 2004;130(1):94104.
[2] Vidogah W, Ndekugri I. Improving management of claims: contractors perspective. Journal of Management in Engineering 1997;13(5):
3744.
[3] Kartam S. Generic methodology for analyzing delay claims.
Journal of Construction Engineering and Management 1999;
125(6):40919.
[4] Kululanga GK, Kuotcha W, McCaer R, Edum-Fotwe F. Construction contractors claim process framework. Journal of Construction
Engineering and Management 2001;127(4):30914.
[5] Abdul-Malak MA, El-Saadi MM, Abou-Zeid MG. Process model for
administrating construction claims. Journal of Management in
Engineering 2002;18(2):8494.
[6] Singh A, Sakamoto I. Multiple claims in construction law: educational case study. Journal of Professional Issues in Engineering
Education and Practice 2001;127(3):1229.

E.K. Zaneldin / International Journal of Project Management 24 (2006) 453459


[7] Scott S. Delay claims in UK contracts. Journal of Construction
Engineering and Management 1997;123(3):23844.
[8] Ren Z, Anumba C, Ugwu O. Multiagent system for construction claims
negotiation. Journal of Computing in Civil Engineering 2003;17(3):1808.
[9] Janney JR, Vince CR, Madsen JD. Claims analysis from riskretention professional liability group. Journal of Performance of
Constructed Facilities 1996;10(3):11522.
[10] Barrie DS, Paulson BC. Professional construction management. New
York: McGraw-Hill; 1992.
[11] Diekman J, Nelson E. Construction claims: frequency and severity.
Journal of Construction Engineering and Management 1985;111(1):
7481.

459

[12] Hartman F, Snelgrove P. Risk allocation in lump-sum contracts


concept of latent dispute. Journal of Construction Engineering and
Management 1996;122(3):2916.
[13] Al-Khalil M, Al-Ghay M. Important causes of delay in the public
utility projects in Saudi Arabia. Construction Management and
Economics 1999;17(5):64755.
[14] UAE industrial statistics report 2004. Ministry of Finance and
Industry, Abu Dhabi, United Arab Emirates; 2004.
[15] ASCE technical committee on contracting practices of the
underground technology research council. Avoiding and resolving
disputes during construction: successful practices and guidelines.
New York: ASCE; 1991.

Vous aimerez peut-être aussi