Year

Population Current and Future(Geometric method)


Average Daily Consumption(lit/day) /person
School Average Daily Demand (Lit/day)
Maximum Daily Demand (lit/day)
Maximum Daily Demand (M3/day)
Peak Hour Demand (lit/hr)
Peak Hour Demand (M3/hr)
Peak Hour Demand (M3/sec)
Capacity of Storage Tank (lit)
Capacity of Storage Tank (M3)
Cubic Meter

Method
Arithemtic Mean Method
Geometric Increase Method

2016
200
80
16000
20800
20.8
1733.333333
1.733333333
0.000481481
12480
12.48

2016
200
200

2036
530
80
42400
55120
55.12
4593.3333333333
4.6
0.00128
33072
33.072
30

2036
400
530.7

BILL OF QUANTITY
Project : SOMALILAND DEVELOPMENT FUND
WATER ENGINEER: MOHAMOUD ABDILAHI
CONSULTANT: HAIDMAN ENGINEERING CONSULTANT
Location: Lasanod School, Sool, Somaliland
DESCRIPTION
S.No
A. HDPE PIPES AND FITTINGS FOR TRANSMISSION LINE AND EXPANSION
WORKS
Supply pipes and fittings with coupling units and all accessories
for complete installation of the lines and fittings
Supply of HDPE materials-All Polyethylene material include for
supply and delivery to the work site of all pipes, fittings &
specials including all other associated accessories required for
complete installation.
1.1
1.1.1
1.1.2
1.1.3
1.1.4

Pressure pipes of standard 6m length for pure and brackish water


DN50mm
DN40mm
DN32mm
DN15mm

Sub total (1)


1.2
1.2.1
1.2.2
1.2.3
1.2.4
1.2.7
1.2.8

Fittings
Bends
DN50mm
DN50mm
DN40mm
DN40mm
DN15mm
DN15mm

90 degree bends
45degree bends
90 degree bends
45 degree bends
90 degree bends
45 degree bends

Sub total (2)


Unions
Supply, deliver, installation and testing Unions
1.2.9 DN50mm unions
1.2.10 DN40mm unions
1.2.11 DN32mm unions
1.2.12 DN15mm unions

Sub total (3)

1.2.13
1.2.14
1.2.15
1.2.16

Tee's
Supply, deliver, installation and testing Tee's
DN50/50/50mm 90 degree Tee
DN50/50/25mm 90 degree Tee
DN40/50/20mm 90 degree Tee
DN15/50/15mm 90 degree Tee

Sub total (4)

Reducers
1.2.17 DN50/60.3mm
1.2.18 DN25/60.3mm
1.2.19 DN20/33.4mm
DN15/33.4mm

Sub total (5)


Externally threaded nipples

1.2.21
1.2.22
1.2.23
1.2.24

Supply, deliver, installation and testing Externally threaded nipples


DN50mm
DN40mm
DN32mm
DN15mm

Sub total (6)


Pumps
Supply, deliver, installation and testing Ceterafugal pump,Cast iron,
1.2.25 complete with threaded ports in compliance with
ISO 228/1 Model: HFm 50B

Sub total (7)


Reverse Osmosis
1.2.26 Supply, deliver, installation and testing WMH Series Wall Mount High TDS
River Osmosis Systems

Sub total (8)


Float valve
Supply, deliver, installation, testing Storage tank float switch
1.2.27
arrangement with two way float switch

Sub total (9)


Supply, deliver, installation, testing elevated Water Storage Tank
(30 cubic meter capacity) having necessary connection
for Inlets, Out lets & Drain Pipe line, etc.

Sub total (10)


1.2.28

Supply, deliver, installation, testing Rainwater Harvest material,


fitting and pipes with first flush
Gutter:150*130*120mm, 1.7mm in thickness
Downspout:100*80mm, 1.9mm in thickness
Collection Pipe DN114,141,161 mm

Sub total (11)


Construction & Installations

Earth Works & Pipe Laying - Earth work rate shall include for back filling,
shoring,compaction as per the specifications and disposal of surplus
excavated material elsewhere as directed by the Engineer. Pipe laying
rate shall include for local transportation within the site, handling,
1.2.29 welding, and all other associated works required for complete installation
Excavation for pipe trenches in any materialLaying and Jointing or Fixing
in Open Trench HDPE pipes

Installation of HDPE Fittings,


The rate shall include excavation, shoring, dewatering,etc. necessary for
1.2.30 the complete installation

Total

Summery

Items
1.7*sub-Total
1.7* sub total
1.7* sub total
1.7* sub total
1.7* sub total
1.7* sub total
1.7* sub total
1.2* sub total
1.7* sub total
1.2* sub total
1.1* sub total
Grand Total

Package: Supply,Installation,Testing
and Commissioning of Water supply
and Rain Water Harvesting system

Date: 20-Sep-2015
RATE (USD) Total (USD)

UNIT

QTY

m
m
m
m

48
48
35
32

20
12
13
9

960
576
455
288
2279

No
No
No
No
No
No

12
6
12
6
32
18

3
3
1
1
0.5
0.5

36
18
12
6
16
9
97

No
No
No
No

70
70
3
15

5
3
2
0.5

350
210
6
7.5
573.5

No
No
No
No

8
8
2
20

5
2
1
0.5

40
16
2
10
68

No
No
No
No

4
12
12
10

7
2
1
0.5

28
24
12
5
69

No
No
No
No

4
30
30
33

7
1.5
1
0.5

28
45
30
16.5
119.5

NO

200
200
200

NO

4000
4000
4000

NO

20

NO

8000

80

8000
8000

M
M
M

180
28
420

3
3
3

540
84
1260
1884

17,370

No
1
2
3
4
5
6
7
8
9
10
11

Price(USD)
2279
97
573.5
68
69
119.5
200
4000
80
8000
1884

Total (USD)
3874.3
164.9
974.95
115.6
117.3
203.15
340
4800
136
9600
3202.8
23,529

BILL OF QUANTITY
Project : SOMALILAND DEVELOPMENT FUND
CONSULTANT: HAIDAMAN ENGINEERING CONSULTANT
Location: Lasanod Hospital, Sanaag, Somaliland
DESCRIPTION
S.No
1
Supply of Pipes and Fittings
Supply of HDPE materials-l include for supply and delivery to the
work site of all pipes, fittings & specials including all other
associated accessories required for complete installation.
Pressure pipes of standard 6m length for pure and brackish water,
Standard: GB/T13663-2000, Length: 6m, Thickness: 2.0mm-82.4mm,
Pressure: PN6,PN8,PN10,PN12.5,PN16, 6Kg/cm2
1.1.1
1.1.3
1.1.3
1.1.4

DN50mm
DN40mm
DN32mm
DN15mm

Sub total (1)


1.2

1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
1.2.6
1.2.7
1.2.8

Fittings

PE Class:PE100, D15*90 -D50*45, Norminal Pressure: PN6, PN8, PN10


PN16, Model Number: DN15 MM~DN400MM, SDR:SDR33,SDR21,
SDR17,SDR13.6, Elbow,Tee,Unions, Reducers, Nipple Coupling ect.
Bends
DN50mm 90 degree bends
DN50mm 45degree bends
DN25mm 90 degree bends
DN25mm 45 degree bends
DN20mm 90 degree bends
DN20mm 45degree bends
DN15mm 90 degree bends
DN15mm 45 degree bends

Sub total (2)


1.2.9
1.2.10
1.2.11
1.2.12

Unions
DN50mm
DN40mm
DN32mm
DN15mm

Sub total (3)


Tee's
1.2.13 DN50/50/50mm 90 degree Tee
1.2.14 DN50/50/25mm 90 degree Tee

1.2.15 DN50/50/20mm 90 degree Tee


1.2.16 DN50/50/15mm 90 degree Tee

Sub total (4)

1.2.17
1.2.18
1.2.19
1.2.20

Reducers
DN50/60.3mm
DN25/60.3mm
DN20/33.4mm
DN15/33.4mm

Sub total (5)

1.2.21
1.2.22
1.2.23
1.2.24

Externally threaded nipples


DN50mm
DN25mm
DN20mm
DN15mm

Sub total (6)


Pumps
Ceterafugal pump,Cast iron, complete with threaded ports in compliance
1.2.25 with
ISO 228/1 Model: HFm 50B

Sub total (7)


Reverse Osmosis
1000BW Brackish Water Reverse Osmosis 3,000 gallons
per day (gpd) Model: 3000BW, TFC Brackish Water RO Membrane,316SS
High-Pressure Piping, Fittings, and Valves, Safety Pressure Relief Valve, 5Micron Sediment Prefilter,316SS Pump, Painted Steel or Powder-coated
1.2.26
Aluminum Frame, Fiberglass Pressure Vessels, Automatic Feed Water
Shut-off Valve

Sub total (8)


Float valve
Water Level Liquid Sensor Float Switch for Storage tank and float switch
arrangement with two way float switch; Model Number:
1.2.27 GLT606,Material:SUS304\316,

Sub Total (9)

Construction & Installations

Earth Works & Pipe Laying - Earth work rate shall include for back filling,
shoring,compaction as per the specifications and disposal of surplus
excavated material elsewhere as directed by the Engineer. Pipe laying
rate shall include for local transportation within the site, handling,
1.2.28 welding, and all other associated works required for complete installation
Excavation for pipe trenches in any materialLaying and Jointing or Fixing
in Open Trench HDPE pipes

Installation of HDPE Fittings,


The rate shall include excavation, shoring, dewatering,etc. necessary for
1.2.29 the complete installation
Installation of Valves including supply and installation of
HDPEpipe works
Installation of 250 mm dia control Sluice Valve on the branch line as
depicted in drawings or directed by the Engineer.
PVC Rainwater Harvest material, fitting and pipes .Ethylene
polymer material, leed-free, good UV performance, Rain gutters,
1.2.30 First Flush: ,material :PVC High temperature resistance, antiaging, anti-oxidant, acid-base mold erosion resistance, oxidation
resistance.
Gutter:150*130*120mm, 1.7mm in thickness
Downspout:100*80mm, 1.9mm in thickness
Collection Pipe DN114,141,161 mm
1.2.29

Sub total (10)

1.2.31 Storage tank 15 cubic meters 60 Cubic meters

Sub total (11)


Total

BOQ Summery for Hospital

Items
1.7*sub-Total
1.7* sub total
1.7* sub total
1.7* sub total
1.7* sub total
1.7* sub total
1.7* sub total
1.2* sub total
1.7* sub total
1.7* sub total
1.1* sub total

Grand Total

Package: Supply,Installation,Testing and


Commissioning of Water supply and Rain
Water Harvesting system
Date: 28-Aug-2015
RATE (USD)
Total (USD)

UNIT

QTY

m
m
m
m

140
140
40
80

20
12
13
9

2800
1680
520
720
5720

No
No
No
No
No
No
No
No

7
7
26
26
39
39
39
39

3
3
1
1
0.75
0.75
0.5
0.5

21
21
26
26
29.25
29.25
19.5
19.5
191.5

No
No
No
No

4
40
50
50

5
3
2
0.5

20
120
100
25
265

No
No

4
15

5
2

20
30

No
No

15
20

1
0.5

15
10
75

No
No
No
No

4
8
30
13

7
2
1
0.5

28
16
30
6.5
80.5

No
No
No
No

4
40
40
13

7
1.5
1
0.5

28
60
40
6.5
134.5

NO

200

200
200

NO

NO

6000

20

6000
6000.00

120

M3

M3

M
M
M

310
60
1220

M3

3
3
3

930
180
3660
4770

3,000

3,000
20,557

No
1
2
3
4
5
6
7
8
9
10
11

Price(USD)
5720
191.5
265
75
80.5
134.5
200
6000.00
120
4770
3,000

Total (USD)
9724
325.55
450.5
127.5
136.85
228.65
340
7200
204
8109
3300

30,146.1

Year
Population Current and Future(Geometric method)
Average Daily Consumption(lit/day) /person
Hospital Average Daily Demand Lit/day
Maximum Daily Demand (lit/day)
Maximum Daily Demand (lM3/day)
Peak Hour Demand (lit/hr)
Peak Hour Demand (M3/hr)
Peak Hour Demand (M3/sec)
Capacity of Storage Tank (lit)
Capacity of Storage Tank (M3)
Cubic meter

2016
338
27.36686
9249.99868
12024.99828
12.02499828
1002.08319
1.00208319
0.000278356
7214.99897
7.21499897

Description

No

In patient
Out Patient
Delivers
Operations
Staff
Health directorate
Total
Lit/day
Average daily consumption per person

Method
Arithemtic Mean Method
Geometric Increase Method

75
200
5
4
50
4
338

2016
338
338

2036
676
27.36
18495.36
24043.968
24.043968
2003.664
2.0
0.00056
14426.3808
14.4263808
15

Average Consumption
per lit/day
80
10
100
100
5
25
320

2036
676
896.8

Product
6000
2000
500
400
250
100
9250
9250
27.36686

BOQ summery for School and Hospital


No
1
2
3

Item
Hospital
School
Total

Grand Total (USD)


30,146.05
23,529
53,675.05