Vous êtes sur la page 1sur 50

Evaluation of ODOTs Culvert Boring Process

RFP Number: 2014-14


Bowling Green State University

Interim-Six-Weeks Report

Principal Investigator:
Dr. Alan Atalah
Associate Dean of Graduate Affairs
Bowling Green State University
College of Technology, Room 217
Construction Management
Bowling Green, Ohio 43403
Phone: 419-372-8354
Email: aatalah@bgsu.edu

March, 2014

TABLE OF CONTENTS
TABLE OF CONTENTS

LIST OF FIGURES

iii

LIST OF TABLES

iv

EXECUTIVE SUMMARY

PROBLEM STATEMENT

INTRODUCTION TO HORIZONTAL AUGER BORING (HAB)

Horizontal Auger Boring

History of Auger Boring

IN-HOUSE VERSUS CONTRACTING: ADVANTAGES & DISADVANTAGES

GOALS AND OBJECTIVES OF THE STUDY

WORK PLAN

LITERATURE REVIEW ON COST

COST BENEFIT ANALYSIS

12

Assumptions

12

Historical ODOT Estimate

13

Horizontal Auger Boring

13

Open-Cut

14

RS Means Estimate

14

Horizontal Auger Boring

14

Open-Cut

16

Ownership and Operation Cost of ABM: ODOT versus Contractor

19

ODOTs Design, Bidding, and Inspection Cost

20

SPECIFICATIONS FOR THE PROPOSED ABM & QUOTATIONS

21

Specifications for the Proposed Auger Boring System

21

Quotations for the Proposed Auger Boring System

22

ASSISTANCE/CONTRIBUTION FROM ODOT

23

PIPE BURSTING AND RAMMING TESTS

24

INTRODUCTION TO PIPE BURSTING (PB)

24

Pipe Bursting Systems

25

Pneumatic Pipe Bursting

26

Static Pipe Bursting

26

Hydraulic Pipe Bursting

27

Pipe Splitting

28
i

Pipe Reaming

29

Impactor Process

29

Tenbusch Method

30

When is Pipe Bursting a Preferred Solution?

30

Pipe Bursting Applicability and Limitations

32

INTRODUCTION TO PIPE RAMMING (PR)

35

LITERATURE REVIEW ON COST

36

COST ANALYSIS

36

Assumptions

36

ESTIMATE FOR PIPE BURSTING AND RAMMING TESTS

38

ODOT CONTRIBUTION TO PB AND PR TESTS

38

CONTRIBUTION FROM MANUFACTURERS

39

CONCLUSIONS AND RECOMMENDATIONS

39

Horizontal Auger Boring

39

Pipe Bursting and Pipe Ramming Research Tests

41

REFERENCES

42

ii

LIST OF FIGURES
Figure 1: Diagram showing the pipe jacking operation

Figure 2: Layout of an auger boring operation

Figure 3: Layout of an auger boring operation

Figure 4: Cost/LF to Cross I-75

Figure 5: Pipe bursting layout

24

Figure 6: Bursting heads for the different PB systems.

25

Figure 7: Pneumatic pipe bursting

26

Figure 8: Static Pipe Bursting-Sectional Pipe

27

Figure 9: Hydraulic bursting head (Xpandit) in both expanded and contracted positions

28

Figure 10: The static pull bursting head with accessories to cut reinforcing steel in RCP

28

Figure 11: Pipe splitting head (PIM Corporation 2007)

29

Figure 12: Reaming head

29

Figure 13: The Impactor process combines HDD with pipe bursting

30

Figure 14: The Tenbusch method

30

Figure 15: Cost comparison between pipe bursting and open cut replacements

31

Figure 16: The upper and lower limits of historical cost of pipe bursting per linear foot

32

Figure 17: The attenuation lines of the PPS versus distance from the source for different
construction pieces of equipment and the attenuations of the 95% PI upper limit lines for
the pneumatic bursting in soft soils and hard soils

34

Figure 18: Original culvert consumed by new casing

35

Figure 19: Pipe installation through ramming

35

iii

LIST OF TABLES
Table 1: Pros and Cons of ODOT In-house versus Contracting

Table 2: Qualitative costs for open-cut versus trenchless

10

Table 3: Cost factors for pipe Jacking and Microtunneling

11

Table 4: Elements of social costs

12

Table 5: Historical Estimates for Horizontal Auger Boring jobs

14

Table 6: Historical Estimates for Open-Cut Jobs

14

Table 7: RS Means Itemized Estimates for 100 LF of Horizontal Auger Boring Jobs

15

Table 8: RS Means Estimates per LF for Horizontal Auger Boring Jobs

16

Table 9: RS Means Itemized Estimates for Open-Cut Jobs

17

Table 10: RS Means Estimates for Open-Cut Jobs

19

Table 11: RS Means Estimate for Equipment cost to contractor per hour

19

Table 12: Estimate of equipment cost to ODOT per hour

20

Table 13: Summary of Prices for the Auger Boring Machine

22

Table 14: RS Means Itemized Estimates for Pipe Bursting Jobs

37

Table 15: RS Means Estimates per ft. for Pipe Bursting Jobs

37

Table 16: The Original Proposal Cost, Expanded Scope Proposal, and the Difference

41

iv

EXECUTIVE SUMMARY
According to the report Ohio Research Institute for Transportation and the Environment
(ORITE) issued in 2005, ODOT maintains and replaces over 100,000 culverts under Ohios
priority and general highways. Various construction alternatives can be employed in the
installation of new lines, and each method has its strengths and weaknesses relative to the others.
However, the selection of the appropriate method will be project based. The overall key
questions for this research are:

When it is recommended to use the open cut and auger boring techniques?

When do we hire a contractor and when do we use ODOTs work force?

The key question for this phase of the project was, is it economically justified for ODOT to
purchase a Horizontal Earth Boring Equipment to perform some of the culvert replacements?
To answer these questions, the research team performed the following activities:

Compared the auger boring and open cut costs per foot from bid prices (contractors) of a
small number of projects versus the ODOT cost estimates based on the RS Means
production rates. This comparison indicated that the contractors cost is lower than that
of ODOTs workforce. However, this comparison is unreliable due the small number of
bid prices and the insufficient information about the scope of work and the respective
prices.

Compared the auger boring costs per foot using RS Means assuming that the direct cost
for the ODOT crews and the contractors crews are identical but the overhead and profit
expenses are different. This comparison indicated that using ODOTs workforce and
ODOTs HAB equipment is more economical especially when you consider the
additional cost of supervision.

Compared the estimated cost per hour for HAB equipment based on the cost of
ownership, operation, and maintenance ($110/hr.) and the cost estimate using RS Means
($165/hr.). The lower cost of capital for ODOT offers another significant competitive
advantage for the ODOT crew. The number of culverts in the State of Ohio indicates that
the auger boring crew can be in operation for more days per year than the assumed 75
days/year (20%); the ownership cost can be cut in half if the number of operational days
doubles to 150 days/year.

The above cited comparisons indicate that purchasing the HAB equipment is an economical
alternative for ODOT. In addition, the training and development of a skillful workforce in this
technical area is a significant additional benefit from this purchase. Another critical factor is the
ability to handle the unforeseen conditions because the construction crew belongs to ODOT.
Following the directive from ODOT, the research team expanded the scope of this report to
include pipe bursting (PB) and pipe ramming (PR) tests. The addition will involve the
replacement of four culverts using pipe bursting and pipe ramming. The equipment
manufacturers will provide the pipe bursting and ramming systems required for the four culvert
replacements and provide one or two technicians to guide the boring and bursting operations.
The equipment manufacturers will direct the ODOT personnel on operating the systems.

In this report, the research team also included additional information related to pipe bursting and
ramming, cost estimates from literature and RS Means, and a cost estimate for the pipe ramming
and pipe bursting tests.
The expansion of the project was noted to have the following potential benefits:

The labor and equipment cost for replacing these additional test culverts will be greatly
leveraged because the manufacturers will supply the equipment and the technician to
direct ODOT crew.

The expanded scope will provide the required information to make a decision on whether
ODOT would benefit from acquiring a bursting system in the future for its in-house
operations.

The expanded scope will provide ODOTs construction crew valuable training and
development in the advanced technologies of replacing culverts.

The additional expenses for this expansion are costs that ODOT will still incur when
replacing these culverts and the research team anticipates cost savings as a result these
tests.

The expanded scope creates a win-win for ODOT and the manufacturers, and will serve
as a contribution to development in the trenchless construction industry where bursting
corrugated pipes is a big challenge.

The expanded scope of work will increase the cost to ODOT by $11,274 due to the cost savings
of $60,000 for the auger boring equipment. The project duration will increase by four month due
to the expansion.

PROBLEM STATEMENT
For the purpose of this interim report, culvert is defined as a structure that conveys water or
forms a passageway through an embankment and is designed to support a super-imposed earth
load or other fill material plus live loads. A culvert will consist of all of the following even
though they may support traffic loads directly: (1) any structure with a span, diameter, or multicell structure with total span less than 10 feet when measured parallel to the centerline of the
roadway and (2) any structure that forms a passageway or conveys water through an
embankment not inspected according to the definitions and terms of the Ohio Department of
Transportation Bridge Inspection Manual (Ohio Department of Transportation, 2012).
The above-ground infrastructure has been getting more attention and maintenance works than the
underground infrastructure because they are out of sight, out of mind. Consequently they are
failing due to lack of maintenance and proper asset management practices (Salem, et al., 2008).
These invisible infrastructures are the foundation of our current civilization and future
prosperity, and they deserve to be maintained, repaired, rehabilitated, and replaced in an
economical and safe manner that causes the minimum amount of inconvenience to the tax
payers. Trenchless technologies offer innovative alternatives to open cut construction that are
more economical and convenient when they are employed appropriately (Atalah A. , 2007).
Culverts are critical to drainage and transportation of fluids under highways. Culvert
construction in the United States became increasingly necessary with the freeway construction
projects initiated under the Eisenhower administration (1953-1961). They serve as conduits for
water to drain/pass from one side of the highway to the other. Many of these culverts were
designed for a 50-year life cycle, which is now ending (Camp, Boyce, & Tenbusch, 2010). The
Ohio Department of Transportation (ODOT) conducts regular inspections and evaluations on its
culverts, and based on this condition assessment, makes recommendations. Following the
assessment, it is determined whether the culvert(s) requires routine maintenance, rehabilitation,
or complete replacement. There are various reasons that may necessitate the replacement of a
culvert such as:
Squatted cross-section of culvert
Sagging of culvert
Collapse of culvert
Need for greater capacity
Increased load due to new construction
Corroded culvert
Eroded backfill
Eroded bedding
If the decision is made to replace the culvert, an appropriate replacement method must be
adopted. For the purpose of this interim report, this could be the conventional open-cut
construction method or horizontal auger boring (HAB). This replacement of old culverts can be
done by ODOT personnel or it can be contracted.
Cost-benefit analysis (CBA), also known as benefit-cost analysis (BCA), is a method that can be
used to choose the most feasible choice between or among competing alternatives. The CBA
method weighs the total expected costs against the total expected benefits of a given alternative
in an effort to determine its feasibility. It will be important to account for the main cost factors
3

including direct costs, indirect costs, and social costs. The social costs would include: road
damage, damage to adjacent utilities, damage to adjacent structures, noise and vibration,
pollution, vehicular traffic disruption, pedestrian safety, business and trade loss, damage to
detour roads, site safety, citizen complaints, and environmental impacts (Gangavarapu, Najafi, &
Salem, 2003). Vehicular traffic disruption is perhaps the most critical of these social costs.
This interim report will present a comparison of the cost of replacing culverts using horizontal
auger boring (bore and jack) and open-cut construction methods when the construction work is
done by ODOT and when it is contracted. This proposal focuses on jack and bore (auger boring)
technique.
INTRODUCTION TO HORIZONTAL AUGER BORING (HAB)
Pipe Jacking is a process of jacking a pipe with laser guided and manually controlled equipment
that requires personnel entry into tunnel boring head for operation as shown in Figure 1. It
requires soil with some stand up time, and it cannot handle high water head. The steering is done
using steering jacks and an articulated joint in the jacking shield using the guidance of a laser
beam positioned to be on the target path of the pipe. It is critical that the rate of excavation and
the rate of jacking to be synchronized to ensure stability of the soil, reducing the chance for
settlement and heave. The excavated material is transported from the face of excavation to the
jacking shaft using electric carts, flight augers, or conveyor belts. The jacking pipe carries axial
(horizontal) loads during the construction (jacking) phase from the hydraulic jacks and vertical
loads from soil, surcharge, and live loads both during and after jacking (Atalah A. , 1996). Auger
boring is a variation of the pipe jacking technique; it follows the same principles, but transports
the soils using flight augers inside a jacked casing pipe and using auger boring machine to jack
the casing and provide the torque needed to rotate the cutting head (Atalah A. , 1991).

Figure 1. Diagram showing the pipe jacking operation

Horizontal Auger Boring


Horizontal auger boring (also called the bore and jack method) is a technique for forming a cased
horizontal bore hole through the ground, from a drive shaft to a reception shaft, by means of a
rotating cutting head. A rotating cutter head at the front of the casing is attached to the leading
end of an auger string. Spoil is transported back to the drive shaft by the rotation of helicalwound auger flights within the steel casing pipe. Vertical control, using a water level, is typical
(Iseley & Gokhale, 1997). The head is equipped with butterfly wing cutters that excavate the soil
in front of the casing with an over cut of half an inch to an inch to reduce the friction between the
soil and the casing (Center for Underground Infrastructure Research and Education, 2004).
Auger boring is generally used to install steel casing pipe in relatively soft stable ground
conditions such as clay, silt or sand with fine material in the soil matrix, above the water table.
The auger boring machine advances along a track, which is aligned to drive the casing pipe on
the designed installation line as shown in Figures 2 and 3. Once the machine reaches the end of
the track arrangement, the auger flight is disconnected from the machine and the machine is
retracted to the original starting point on the track allowing a new auger flight to be connected to
existing flight and new casing segment to be welded to the existing casing pipe. The excavation
and thrust process is repeated until the project is completed (The International Society for
Trenchless Technology, 2013). The auger chain is then withdrawn from the casing pipe and the
pipe is cleaned of all remaining soil. The carrier pipe can then be installed and the annular space
between the two pipes grouted.

Figure 2. Layout of an auger boring operation (The International Society for Trenchless
Technology, 2013) and ( Australasian Society for Trenchless Technology, 2010).
History of Auger Boring
Although this method has evolved over the past 55 years, the major developments have taken
place over the past 20 years and have resulted in increased bore lengths and accuracy. As early as
1936, the first boring machines were made from rear ends of old trucks. These machines were
first built by CRC machines and are one of the first machines. They were cradle auger boring
machines in which the whole system was suspended by pipe laying equipment. The auger boring
method was formally developed in the late forties by Vin Carthy, Salem Tool Company and
5

Charlie Kandal. The developments were simultaneous and independent of each other. Machines
were originally developed to drill horizontal blast holes into open cast coal mines in Somerset,
Pennsylvania where the use of explosives was not effective as the coal became contaminated
because of a high degree of disturbance due to the blast. These machines were used for boring
from the working face along the bottom of the fireclay stratum, skimming the top of coal (Center
for Underground Infrastructure Research and Education, 2004).

Figure 3. Layout of an auger boring operation (Nickol Boring Inc., 2013) and (Purdue
University, 2010).
In the 1940s, Charlie Kandal founded the Ka-Mo company which manufactured the Ka-Mo
auger boring machines which were electrically operated but later ones were gasoline powered.
The machine consisted of electric or air motors on a track with a series of holes in the track. By
1951, Ka-Mo claimed the capability to bore 5 inch diameter uncased holes up to 230 LF. In
1961, pipeline welder Al Richmond started manufacturing small Horizontal Earth Boring (HEB)
machines which had an engine on top of the gearbox and was driven with a chain. The machine
was driven on track with holes in the cross members and T-pins were used to hold it in the
ground. He later introduced the 24 inch machine, the Power Midget. Richmond also built 30
and 36 inch machines for bigger diameter installations.
In 1970, Leo Barbera built hydrostatic drive machines with a built in slip clutch. If the machine
hit a boulder or some other obstruction, it would switch to maximum torque but at the same time
block out the thrust. The machine would advance only when the condition was relieved. The
other manufacturers of HEB machines include McLaughlin Boring Systems, Horizontal
Equipment Manufacturing Inc., Michael Byrnes Manufacturing, Bor-It Manufacturing, Barbco,
The Robbins Company, and several other smaller manufacturing firms. There are several
contractors who manufacture their own boring equipment (Center for Underground Infrastructure
Research and Education, 2004).
Two of the latest developments in the auger boring industry are the pilot tube auger boring which
delivers a high level of accuracy on line and grade suitable for gravity applications and the small
boring unit which enables boring through soft to medium rock formations and mixed ground
conditions.

IN-HOUSE VERSUS CONTRACTING: ADVANTAGES & DISADVANTAGES


Table 1 shows some of the advantages and disadvantages of both in-house operations and the
contracting option. This should form part of the decision making process when choosing between
contracting and doing the job in-house.
Table 1: Pros and Cons of ODOT In-house versus Contracting
In-House

Pros
1. Flexibility in the work-including
scope and other details of the
project

Cons
1. Training required
2. Increased supervision
3. Owner assumes more of risks

2. Less dispute
3. No need for preparation of bid
documents

4. Inflexible staffing when the contractor


can increase and decrease the work
pool as the work demands

4. Design and construction can be on


going simultaneously.

5. Potential greater liability exposures


and increased insurance costs

5. Stability

6. Worker compensation and other


employee benefits increases

6. Loyalty-may lead to better work


Contractor 1. High efficiency

1. Delays due to greater complexity with


decision making on issues that need
owner approval

2. Specialty works

3. Has the flexibility of using


2. Delay in communicating upstream
specialized and professional labor
and downstream
on an as-needed basis as opposed to
3. Inconvenience of preparing of bid
developing in-house capabilities
material and going through the
that may not be optimal
bidding process
4. Avoids the need for overtime
expenses for jobs that spill beyond 4. May not be readily accessible when
needed
ordinary work hours or into the
weekends
5. Contract needed and legal costs will
5. The contractor bears some of the
risk

be incurred if counsel is hired to draw


up contract

6. Personnel Issues are avoided:


discipline, supervision, benefits
There are other factors that ought to be considered and that include:
1. Cost (direct, indirect and social costs)
2. Quality
3. Seasonality of work
4. Contractor availability
5. Agency policies or statutory requirements
7

GOALS AND OBJECTIVES OF THE STUDY


The main objective of this study is to compare the cost of replacing culverts using horizontal
auger boring (bore and jack) and open-cut construction methods when the construction work is
done by ODOT and when it is contracted, and to give recommendations on these construction
alternatives that will enhance efficiency. The different methods will be analyzed using the costbenefit analysis (CBA).
The following goals are set to help meet this objective.
1.

Conduct a preliminary CBA based on historical costs of contracted auger boring and
open-cut projects, and ODOT open-cut projects.

2.

Conduct CBA for ODOT auger boring and open cut projects by employing the use of
estimating tools, chiefly the RS Means.

3.

Collect auger boring machine (ABM) quotations and give recommendations for the
purchase of the ABM.

4.

Conduct time studies for the installation of culvert using the auger boring method and
ODOT personnel; conduct site tests; collect the relevant data from the project; and
conduct comprehensive CBA.

5.

Conduct comprehensive CBA based on historical costs and comprehensive industry


survey of bidding prices for contractor/consultant auger boring and open-cut projects
and ODOT open-cut projects.

6.

Conduct a sensitivity analysis on select parameters like depth, soil types, ground
water, and culvert diameter, etc.

7.

Give recommendations on the different alternatives, and suggest areas for possible
improvement on cost and productivity.

8.

Provide a decision making matrix to help ODOT select the most suitable technique
for the expected site conditions.

The first three goals have been fulfilled as discussed and shown in this report.
WORK PLAN
The work plan is broken down into two phases; each has a set of activities that are targeted at
meeting the goals and objectives of the project. Here is a summary of the activities of phase 1:

The research team conducted an extensive literature review related to direct and indirect cost
of auger boring and open cut construction alternatives. The literature review afforded a
preliminary determination of the most suitable condition for each method of construction
along with the cost-benefit analysis for each method.

The research team solicited and obtained sample historical bid prices of the methodologies
under study from ODOT.

The research team conducted a preliminary cost benefit analysis (CBA) that is based on the
literature review, historical data, and RS Means.

The team submitted this interim report eight weeks after commencement of the project that
presents the cost analysis of the four methods, a proposed ABM for phase 2 (complete with
specifications and costs), and recommendations based on the cost analysis.
LITERATURE REVIEW ON COST

A search for previous research on this topic was conducted. A search was run on the TRIS and
ITRD, the Web of Science, Google Scholar, Academic Search Complete, and Compendex
databases. Each of these databases contains citations to scholarly articles and papers on
numerous topics from thousands of international and local journals, technical reports, and
conference proceedings and papers.
Goduto and Atalah (2013) compared the design and construction costs of installing a 16
waterline underneath I-75 in Bowling Green, Ohio using four potential alternatives: open-cut
with detouring traffic, postponing the installation until resurfacing the interstate to install the line
by open-cut, horizontal directional drilling, and auger boring. The study concluded that it could
cost $604.50, $134.50, $57.47, and $173.44 per linear foot to install the pipe using Auger
Boring, Horizontal Directional Drilling, open-cut with postponing the installation until
resurfacing the interstate to install the line, and open-cut with detouring traffic, respectively as
shown in Figure 4. It is important to note that the study did not take into consideration social
costs which will be a critical factor in the analysis. The study did not involve any sensitivity
analysis which is important in giving us a picture of how the methods compare if there is a
change in depth, diameter of the pipe, or other critical parameters. This is another important
factor in this study.

$700.00
$600.00
$500.00
$400.00
$300.00
$200.00
$100.00
$0.00
Auger Boring

Horizontal
Directional
Drilling

Postpone the
project

Figure 4: Cost/LF to Cross I-75 (Goduto & Atalah, 2013).

Open Cut

Najafi and Kim (2004) conducted a comparison of the life-cycle-cost of open-cut and trenchless
pipeline construction. The paper presented an investigation of the cost-effectiveness of
constructing underground pipelines with trenchless methods in urban centers relative to the cost
of conventional open-cut method. The analysis was qualitative but it paved way for more studies
to calculate the real life-cycle-cost of construction projects so that design engineers and project
owners can compare different alternatives and specify the most cost-effective and
environmentallyfriendly methods for contractors bids. Table 2 presents the results of the LCC
comparison.
Table 2: Qualitative costs for open-cut versus trenchless
Cost Factors for Direct Costs
Cost Factor
Open-Cut
Mobilization and Demobilization
Major
Shoring and Sloping Trench Walls
Major
Dewatering
Major
Spoil Removal
Major
Cost of Detour Roads
Major
Backfill and Compaction
Major
Reinstatement of Surface
Major
Construction Equipment Costs
Major to Minor
Labor Costs
Major
Material Costs
Minor
Cost Factors for Indirect Costs
Cost Factor
Open-Cut
Head Office Costs
Major
Field Office Costs
Major
Field Supervision Costs
Major
Cost of Temporary Utilities
Major
Cost Factors for Social Costs
Cost Factor
Open-Cut
Road Damage (Reduction in Life of Pavement,
Major
Approximately 40%)
Damage to Adjacent Utilities
Major
Damage to Adjacent Structures
Major
Noise and Vibration
Major
Dust and Air Pollution
Major
Vehicular Traffic Disruption
Major
Pedestrian Safety
Major
Business and Trade Loss
Major
Damage to Detour Roads
Major
Site Safety
Major
Environmental Impact
Major
Citizen Complaint
Major

10

Trenchless
Minor
Minor
Minor
Minor
Minor
Minor
Minor
Major to Minor
Minor
Major
Trenchless
Minor
Minor
Minor
Minor
Trenchless
Minor
Minor
Minor
Minor
Minor
Minor
Minor
Minor
Minor
Minor
Minor
Minor

Thomson, Sangster, & Kramer (1998) reviewed economics of three main classes of trenchless
technology work: (1) pipe jacking and Microtunneling for sewer installation, (2) horizontal
directional drilling or guided drilling for pressure pipelines and cable installations, and (3) sewer
pipeline renewal. The major markets of North America and Europe were investigated. The
prevailing costs in 1988 were compared with the direct costs of 1998 to establish the trends and
costs of the main trenchless technologies. Table 3 shows the cost factors that were considered in
the paper in comparing pipe jacking systems (including microtunneling) and open-cut.
Table 3: Cost factors for pipe jacking and microtunneling
Factor
Depth
Soil Conditions
Obstructions
Water Table
Shafts
Existing Utilities (Paving Included)
Reinstatement
Traffic

Open-Cut
Major
Major
Minor
Major
Minor
Major
Major
Major

Trenchless
Minor
Minor
Major
Minor
Minor
Major
Minor
Minor

Piehl (2005) summarizes the trenchless technologies most appropriate for U.S. Department of
Agriculture (USDA) Forest Service roadway culvert applications. His emphasis is on techniques
for replacing or rehabilitating corrugated metal pipe (CMP) culverts, 18 inches or greater in
diameter. The report also gives estimated costs for the trenchless methods and open-cut method.
The costs for replacement using pipe bursting were estimated to vary from $100 to $200 per
linear foot for 18-inch-diameter pipes and $850 per linear foot for 48-inch-diameter pipes. For
auger boring, the costs were estimated to be about $200 per linear foot for a pipe 18 inches in
diameter to $1,000 per linear foot for a pipe 60 inches in diameter.
Rehan and Knight (2007) sought to answer the question, Do trenchless pipeline construction
methods reduce greenhouse gas emissions? This is part of the social cost of the project. Their
preliminary analysis found that the use of trenchless construction methods can result in 78 to100
percent lower greenhouse gas emissions than open-cut pipeline installation methods. This is
attributed to shorter job duration using less construction equipment and limited or no disruption
to traffic flow when using trenchless. Their estimate did not include greenhouse gas emissions
resulting from: the production and transportation of additional quantities of asphalt concrete and
trench restoration materials; loss of pavement life; and/or pavement maintenance and
rehabilitation.
Gangavarapu, Najafi, and Salem (2003) compared the traffic delays and costs involved during
utility construction using open-cut and trenchless methods (auger boring). Case studies of two
sites involving utility construction were considered in the study. They studied the auger boring
technique and evaluated the construction factors that affect project productivity. The research
utilized two simulation techniques to simulate the auger boring process and evaluate the
productivity of auger boring systems. In the first case study that involved an installation crossing
a street, the cost for open-cut was $12,104.70 while that for auger boring was $9,219.50. The
project consisted of a 12-inch gravity flow pipe, an 18-inch gravity flow pipe, and an 8-inch
11

plastic cable conduit that were laid across a 30 foot wide road. Cost of auger boring method was
estimated at $190.00 per linear foot of pipe to be installed. The second case study involved the
installation of a new pipeline parallel to the road. In this case the cost for open-cut was $4,524.00
while that for auger boring was $9,187.00. This second project involved the construction of a 12inch diameter, 100-foot long storm water pipe at a depth of 5 feet. The cost per foot of pipe was
estimated as $90.00 for auger boring and 43.37 for open-cut. It is evident that the cost of traffic
disruption contributed significantly to the cost of the project while using open-cut when crossing
a pavement/road.
The cost of a culvert replacement project has three components: direct cost, indirect cost, and
social cost. The direct cost is the cost of furnishing the labor, material, and equipment needed
for the replacement. The indirect cost include the project overhead, mark up, design cost,
bidding cost, supervision cost, etc. The above cited direct and indirect cost elements can be
tracked and reasonably calculated. The social costs are the costs to the tax payer that are not
included in bid price or other contractual documents or tracked by other arrangements such as
those shown in Table 4.
Table 4: Elements of social costs
Vehicular traffic disruption (associated
delays, vehicle operational cost, and lost
production)
Utilities relocation
Effect on nearby business and their
associated trade losses
Damage to detour roads

Environmental burden and its associated noise,


air pollution, visual intrusion, and construction
mess
Damage to the road surface
Decreased safety for pedestrians and motorists
Site safety

With over 100,000 culverts under Ohios priority and general highways (Ohio Research Institute
for Transportation and the Environment (ORITE), 2005) and that ODOT maintains in the state of
Ohio, various construction alternatives can be used to install new lines. Each method has its
strengths and weaknesses relative to the others and the selection of the appropriate method will
be project based. For deep installations of new culverts and where traffic disruption can be
costly, HAB could be a suitable alternative. It is important to choose the right method for the
right set of circumstances.
COST BENEFIT ANALYSIS
This interim report presents a comparison of the cost of replacing culverts using horizontal auger
boring (bore and jack) and open-cut construction methods when the construction work is done by
ODOT and when it is contracted
Assumptions
The following assumptions were made for the purposes of this preliminary CBA:
1. The direct benefits of the projects are the same for horizontal auger boring and open-cut.
The assumption is that the finished culvert will perform the same functions irrespective

12

of the construction method used (same size and length, equal design life, and similar
capacity and flow rate.)
2. There is no damage to adjacent utilities or structures as a result of the auger boring or
open-cut operation.
3. The pavement to be cut (in the open-cut scenario) on the project site is in reasonably
good condition and has some anticipated years of life before resurfacing or
reconstruction.
4. The work is assumed to be completed on budget and schedule irrespective of the method
of construction.
5. For the historical ODOT cost estimates, the effect of inflation on the change in costs is
negligible.
Historical ODOT Estimate
30 culvert projects were selected from recent ODOT projects. The selected projects were limited
to Type A and Type B conduits. The Ohio Department of Transportation (2014) defines Type A
and Type B conduits as:

Type A conduits are sealed culvert cross drains under pavements, paved shoulders, and
embankments. These culvert cross drains are used to convey water from one side of the
roadway to the other. These culverts can be either smooth lined or corrugated. Type A
conduits are under pavement and open at both ends.

Type B conduits are storm sewers under pavements, paved shoulders, and commercial or
industrial drives. Storm sewers are used to convey water from one manhole or a catch
basin to the other. Storm sewers are always smooth lined. Type B conduits have one or
both ends closed with a drainage structure.

Horizontal Auger Boring


12 of the selected culvert projects were auger boring projects with culvert diameters ranging
from 12 to 48 and installed at depths ranging from 6 feet to 22 feet. A regression analysis was
conducted and the regression equation was used to generate the ODOT historical cost estimates
in Table 5. From the table we can deduce that the cost does increase with both the increase in
depth and increase in diameter of the product. The regression equation used to calculate the cost
per foot was:
Cost per ft. = -27.908 + 6.035*Diameter + 15.250*Depth
It is important to note that the small number of projects used in these preliminary study reduce
the reliability of this regression equation at this point; further more data from additional projects
will fine-tune the regression equation.

13

Table 5: Historical Estimates for Horizontal Auger Boring (Total Cost/ft.)

Diameter
24
36
48

Depth (ft.)
8 feet

6 feet
$208.43
$280.86
$353.28

$238.93
$311.36
$383.78

10 feet
$269.43
$341.86
$414.28

Open-Cut
18 of the selected culvert projects were open-cut projects with culvert diameters ranging from
12 to 48 and installed at depths ranging from 3.5 feet to 11 feet. The regression equation was
applied to the respective pipe sizes and depths of installation to get the cost estimates per linear
foot that are presented in the Table 6. The regression equation for cost per foot follows:
Cost per ft. = -79.234 + 5.244*Diameter + 8.434*Depth
Table 6: Historical Estimates for Open-Cut (Total Cost/ft.)

Diameter
24
36
48

Depth (ft.)
8 feet

6 feet
$97.23
$160.16
$223.10

$114.10
$177.03
$239.96

10 feet
$130.97
$193.90
$256.83

Similar to the HAB analysis, the cost per foot increases with the increase in diameter of the
product pipe and the increase in depth of installation. These historical costs are estimates at best
and may not be a true and accurate representation of the actual cost of installing a culvert using
the methodologies under study. We deduce this based on the assumptions made and the data used
to generate these costs.
RS Means Estimate
Horizontal Auger Boring
For the auger boring option, the construction process was broken down into the following
activities: mobilization, preparation of entry and exit pits, equipment setup, delivery and
preparation of pipe section, boring operation, restoration and site cleanup, and demobilization
The following assumptions were made in this estimation shown in Table 7:

100 ft. long bores

ODOT estimates are calculated with the following overhead rates: Labor (80%), Material
(15%), and Equipment (0%)

The location cost index of 98% is used to adjust the U.S. National RS Means calculations
to reflect local costs. All the direct costs include this 2% reduction

14

Table 7: RS Means Itemized Estimates for 100 LF of Horizontal Auger Boring Jobs
RS Means Description
Section

Units

Direct costs
Materials Labor

Total costs
Equip. Direct

Contractor ODOT

Horizontal boring casing only, 100 minimum,


not including jacking pits or dewatering.
L.F.
33 05 23.20 Roadwork thick wall, 24 diameter casing

$129.36

$125.44 $65.66

$320.46

$411.60

$440.22

Horizontal boring casing only, 100 minimum,


not including jacking pits or dewatering.
L.F.
33 05 23.20 Roadwork thick wall, 36"diameter casing

$237.16

$156.80 $81.83

$475.79

$597.80

$636.80

Horizontal boring casing only, 100 minimum,


not including jacking pits or dewatering.
L.F.
33 05 23.20 Roadwork thick wall, 48 diameter casing

$333.20

$167.58 $87.22

$588.00

$720.30

$772.04

Prepare jacking pits, including mobilization and


Ea.
33 05 23.20 demobilization for horizontal boring

$3,087.00

$3,552.50 $3,087.00

PVC Pipe Lining, excludes cleaning and video


inspection. Pipe relined with one pipe smaller L.F.
33 01 30.74 than the original, 24" diameter, original size

$24.01

$4.24

$2.26

$30.52

$33.87

$37.51

PVC Pipe Lining, excludes cleaning and video


inspection. Pipe relined with one pipe smaller L.F.
33 01 30.74 than the original, 36" diameter, original size

$79.38

$4.24

$2.26

$85.89

$95.33

$101.19

PVC Pipe Lining, excludes cleaning and video


inspection. Pipe relined with one pipe smaller L.F.
33 01 30.74 than the original, 48" diameter, original size

$164.64

$4.24

$2.26

$171.15

$189.97

$199.24

Note: Including overhead & profit means the total cost using the overhead and markup of local contractor and the ODOT means the
total cost when using the ODOT work force.
15

A factor of 112% is used to adjust the contractors cost to include the costs to ODOT for
contracted jobs. This factor of ODOTs overhead costs on contracted jobs includes an
additional 4% of the bid price for plan preparation and engineering, 6% of the bid price
for the inspection, and 2% of the bid price for accounting and administration.

The direct cost and the total cost per foot estimates for auger boring jobs are presented in Table
8. The direct costs represent the costs for materials, equipment, and labor (without the labor
burden); which is assumed to be the same regardless of who does the work (ODOT or specialty
contractor). The Contractors price consists of direct cost, overhead, and profit (O&P).
Theoretically, the total cost represents the price that the contractor will charge the customer, but
the markup rate can be changed based on supply and demand. RS Means uses an estimated
materials overhead of 10%, labor burden of 55%, labor overhead of 10%, and equipment
overhead of 10% for estimating the quoted prices from the specialty subcontractor. This
contractor price was adjusted by a factor of 112% to reflect the cost to ODOT for the contracted
job. For estimating the total cost for ODOT, the assumptions of labor overhead of 80%, material
overhead of 15%, and equipment overhead of zero were used.
Table 8: RS Means Estimates per LF for Horizontal Auger Boring Jobs
Estimates Total per ft.
Direct
Contractors Price
$381.85
$538.72
$592.55
$816.10
$790.02
$1,059.29

24"
36"
48"

ODOTs cost
$508.60
$768.86
$1,002.15

The values in the table above show that the cost to ODOT when the job is done in-house is lower
than the cost for contracting.
Open-Cut
For open-cut, the construction process is broken down into: mobilization, detour & traffic
control, asphalt pavement demolition, excavating trench, placing bedding material, laying the
pipe, backfilling and compacting, restoration and site cleanup, and demobilization.
The following assumptions were made in the estimation shown in Table 9:

The trench width was calculated as: Trench Width = 1.25 * outside diameter + 1 foot
Cut pavement width extends 12" on either side of trench
ODOT estimates are calculated with the following overhead rates: Labor (80%), Material
(15%), and Equipment (0%)
Bedding Type 2 with 6" Thickness was used
Native material backfill was used for the trenches
A factor of 112% is used to adjust the contractors cost to include the costs to ODOT for
contracted jobs. This factor of ODOTs overhead costs on contracted jobs includes an
additional 4% of the bid price for plan preparation and engineering, 6% of the bid price
for the inspection, and 2% of the bid price for accounting and administration..
16

Table 9: RS Means Itemized Estimates for Open-Cut Jobs


RS Means
Section

Description

02 41 13.17 Demolish, remove pavement


and curb; pavement road
removal, bituminous roads 4"
to 6" thick (12")
31 23 16.13 Excavating trench, common
earth with no sheeting or
dewatering included, 6' to 10'
deep, 1 C.Y. excavator
w/trench box
31 23 23.16 Fill by burrow and utility
bedding for pipe and conduit,
not including compaction,
Crushed stone 3/4" to 1/2 "
31 23 23.16 Fill by burrow and utility
bedding for pipe and conduit,
compacting bedding in trench
31 23 16.13 Excavating trench, backfill
trench, F.E. loader, wheel
mtd., 1 C.Y. bucket, minimal
haul
31 23 23.23 Compaction, vibrating roller,
12" lifts, 4 passes
32 12 16.13 Plant mix asphalt paving with
no hauling included,
pavement replacement over
trench, 6" thick
33 41 13.40 Piping, storm drainage,
corrugated metal, Not
including excavation or

Units

Direct

Total costs
Contractor

ODOT

S.Y.

$7.53

$6.00

$13.52

$18.03

$19.55

B.C.
Y.

$1.75

$2.42

$4.17

$5.34

$5.58

$6.08

$2.40

$38.37

$45.08

$47.71

E.C.
Y.

$3.09

$0.37

$3.46

$5.15

$5.93

L.C.
Y.

$1.27

$0.73

$2.00

$2.73

$3.02

E.C.
Y.

$0.20

$0.66

$0.85

$1.03

$1.01

L.C.
Y.

24"
14 ga.

Direct costs
Matl
Labor
Equipt

$29.89

S.Y.

$23.03

$31.85

$2.75

$57.63

$76.93

$86.57

L.F.

$19.60

$11.03

$2.25

$32.88

$41.16

$44.64

17

RS Means
Section

01 54 36.50

01 54 36.50

01 54 36.50

01 54 36.50

Description
backfill. Corrugated metal
pipe, galvanized, bituminous
coated with pavedinvert, 20'
length
Mobilization upto 75 mi.
haul dist (150 mi. RT for mob
crew) excavator and loader
Above 150 H.P.
Mobilization upto 75 mi. haul
dis (150 mi. RT for mob
crew) Small equipment,
placed in rear of, or towed by
pickup truck
Demobilization upto 75 mi.
haul dist (150 mi. RT for
demob crew) excavator and
loader Above 150 H.P.
Demobilization upto 75 mi.
haul dis (150 mi. RT for
demob crew) Small
equipment, placed in rear of,
or towed by pickup truck
Total Mob and Demob

Units
36"
12 ga.
48"
12 ga.

Direct costs
Matl
Labor
Equipt

Direct

Total costs
Contractor

ODOT

L.F.

$32.83

$17.64

$5.93

$56.40

$69.09

$75.44

L.F.

$49.49

$21.07

$7.15

$77.71

$94.57

$101.99

2 No.

Ea

$191.10

$627.20

$818.30

$989.80

$971.18

2 No.

Ea

$69.58

$40.18

$109.76

$151.90

$165.42

2 No.

Ea

$191.10

$627.20

$818.30

$989.80

$971.18

2 No.

Ea

$69.58

$40.18

$109.76

$151.90

$165.42

$1,856.12

$2,283.40

18

$2,273.21

The total cost per foot estimates for open-cut jobs are presented in Table 10. Similarly, the direct
costs represent the costs for materials, equipment, and labor that the person installing pays and
do not include markups for profit and labor burden. The contractor cost represents the total cost
that the contractor will charge the customer and it includes the cost of materials plus 10% profit,
the cost of labor plus labor burden and 10% profit, and the cost of equipment plus 10% profit. It
is important to note that the contractors profit is directly affected by the forces of demand and
supply in the marketplace, and will vary based on the market conditions. This contractor figure
also includes a 112% adjustment to reflect the cost to ODOT for the job as described in the
assumptions. The ODOT costs are calculated with the following overhead rates: labor (80%),
materials (15%), and equipment (0%).
Table 10: RS Means Estimates for Open-Cut Total Cost/ft.
6 ft. deep

8 ft. deep

10 ft. deep

(In)
24"

Direct

102.92

147.97

142.91 104.74

150.62

145.40 106.56

153.26

147.89

36"

139.17

198.06

192.26 141.65

201.65

195.64 144.12

205.24

199.02

48"

173.23

245.41

237.37 176.35

249.94

241.64 179.47

254.47

245.91

Contractor ODOT

Direct

Contractor ODOT

Direct

Contractor ODOT

It is important to note that the social costs which include vehicular traffic disruption, effect on
nearby business and their associated commercial losses, damage to detour roads, environmental
burden and its associated noise, air pollution, visual intrusion, and construction mess, and
decreased safety were not part of the analysis in this first phase. The hypothesis is that the
trenchless options will have less social costs as compared to open-cut construction. Both
methods will be critical to ODOT and its ability to maintain the integrity of their structures.
Knowing when to use what method and whether to do it using the ODOT workforce or to
contract it will be the key question in phase 2 of the project.
Ownership and Operation Cost of ABM: ODOT versus Contractor
Based on both RS Means and the collected quotations, the research team analyzed the cost per
hour for ownership and operation of the ABM. This estimate included the cost of the machine,
the annual operating costs, the salvage value, depreciation, equipment overhead rate (EOR) and
the interest rate (assumed at 3%). From the RS Means, the 48 inch HAB equipment costs $89/LF
and the daily production is 15 LF/day, which means that the daily cost is equal to 89*15=$1335
and the hourly cost, assuming 8 hours/day, is 1335/8 = $166.88 as shown in Table 11.
Table 11: RS Means Estimate for Equipment cost to contractor per hour
Production (ft/day)
15

ft/hr.
1.875

Cost per ft.


$89.00

Cost per hr.


$166.88

The research team used an investment cost (I) of $228,416.63 (average of the collected lowest
three quotes), annual operating cost (AOC) of $23,370.55, and a salvage value (SV) of
$115,000.00. All the values are present values (costs at year zero). The estimates used were
based on the market value (auctioned) of a similar ABM that has been used for eight years, the
19

AOC obtained from various equipment manufacturers, and a first cost from the official
quotations that were obtained by Bowling Green State University from the manufacturers and
confirmed by prevailing costs of other similar construction equipment.
Based on these values (investment cost, AOC, and SV) and the assumed interest rate, the present
value (PV) was calculated to be $277,010.48, $300,381.03, and $323,751.58 for the equipment if
it is used for seven, eight, and nine years respectively, then sold. The annual worth (AW) was
calculated to be $44,461.94, $42,791.20, and $41,580.66 for equipment if it is used for seven,
eight, and nine years respectively, then sold. This formed the basis for the calculations in Table
12 which are estimates of the cost of the equipment to ODOT per hour. The research team
assumed a life of seven years (i.e. AW= $44,461.94) and calculated three different estimates: (1)
if the equipment is used for 75 days per year; (2) if the equipment is used for 100 days per year;
(3) if the equipment is used for 115 days per year. The fuel cost is estimated based on the horse
power of the engine (174 HP x 0.04 gal/HP/Hr.) $4.40 /gal of diesel. The equipment over head
rate (EOR) is a combination of interest expense rate, insurance, and storage costs; and it is
assumed to be around 10% for ODOT.
Table 12: Estimate of equipment cost to ODOT per hour
Days of work per yr.

Cost/hr.

Fuel

75
100
115

$74.10
$55.58
$48.33

$30.62
$30.62
$30.62

EOR = 10% Total Cost per hr.


$7.41
$5.56
$4.83

$112.13
$91.76
$83.78

Based on these calculations; the contracted HAB equipment cost is around $165 and the owned
HAB equipment cost is around $110. We can deduce that it would be more economical for
ODOT to do the work in-house than to contract. It is also clear that the more hours per year that
the equipment is in operation, the lower the cost per hour to ODOT. If ODOT will have a
specialized team that works on the auger boring jobs for a considerable number of days in a year,
then it would be reasonable to infer that there will be cost savings for ODOT if they do the work
in-house.
ODOTs Design, Bidding, and Inspection Cost
As it is the case for most construction projects, the owner covers many other expenses above the
bid prices such as the planning, design, bidding, inspection, and supervision expenses. If ODOT
is executing the work using their workforce, the bidding and the supervision expenses will be
saved. In this analysis a factor of 112% was used to give a more accurate estimate of the total
cost to ODOT for contracted jobs. The supervision expenses is small in magnitude if the work
proceeds without problems, but if unforeseen/changed soil conditions are encountered, these
expenses can significantly escalate. If ODOTs workforce is installing the pipe, the planning and
design expenses can be significantly lower as ODOT will internally adjust and adapt to the
unforeseen conditions with much less overhead expenses associated with the change order. This
is a significant part of the risk management plan of the project.

20

SPECIFICATIONS FOR THE PROPOSED ABM & QUOTATIONS


Based on the project requirements and the desired auger boring machine, specifications were
drafted to acquire the HAB machine for ODOT. The proposed specifications for the HAB
machine are shown in the next few paragraphs.
Specifications for the Proposed Auger Boring System
BGSU is seeking a quotation for an HAB system that can bore in soft soils and soft rock
conditions up to 48 in diameter. A separate quote is needed for the different components and
accessories such as water grade indicator, cutting heads, tracks, 100 LF augers of different
diameters, etc.
1. Main component and its General description
1.1.The horizontal earth boring machine will primarily consist of :
Track
Frame assembly
Saddle and saddle attachments
engine
drive train assembly
casing pusher and casing attachment
2. Operational requirements
2.1.Capable of drilling bore sizes 24, 30, 36, and 48.
2.2.Capable of drilling bores at least 300ft
2.3.Capable of drilling bores in various soil conditions ranging from soft and medium soil
(loose sand/soft clay to dense sand/stiff clay) to soft rock conditions.
3. Accessories and Consumables
3.1.Supply a list of all necessary accessories and their respective prices which include:
Saddle adapters for respective sizes
Casing adapters for respective sizes
Cutting heads for both soil (dirt) and soft rock conditions for sizes 24, 30, 36, and
48.
Water level/grade indicator
Flight augers (10ft sections) sizes 24, 30, 36, and 48 (10 sections for each size100 ft length)
3.2.Supply a list of spare parts are essential for maintenance and repair for the next 12
months and their respective costs
4. Documentation
4.1. The machine operating and service manuals and other necessary manuals (all in English)
should be provided
5. Delivery
5.1.Indicate delivery costs including the shipping costs and shipment insurance(if applicable)
to Columbus, Ohio

21

6. Commissioning and Training


6.1.The quotation should include training and providing the relevant literature for the crew
which will include:
The operators
Assisting crew
Maintenance technicians
7. Warranty
7.1.Provide a warranty period beginning from the time of commissioning (minimum 12
months)
8. After sales support
8.1.Estimate of the cost of maintenance, consumables supplies, spare parts, and other
operational costs.
8.2.Indicate the location and availability of maintenance and repair facilities and parts (both
spare parts and consumables)
Quotations for the Proposed Auger Boring System
Official quotations were obtained from six manufacturers. These quotations serve as the best
estimates for our investment cost in the auger boring option for ODOT work. Table 13 contains
the summary prices for the auger boring machine that were obtained from the manufacturers.
The actual quotations are in Appendix 1.
Table 13: Summary of Prices for the Auger Boring Machine
Item
Machine Price
Casing attachment & saddle
24" X 10' Auger
30" X 10' Auger
36" X 10' Auger
48" X 10' Auger
24" Dirt Cutter head
30" Dirt Cutter head
36" Dirt Cutter head
48" Dirt Cutter head
24" Rock Cutter head
30" Rock Cutter head
36" Rock Cutter head
48" Rock Cutter head
Water Level
Freight
Training
Total

Qty

Robbins

Bor-It

1 $179,500 $107,380
3 $12,750 $10,962
10 $26,500 $15,350
10 $31,000 $17,650
10 $34,000 $20,700
10 $39,500 $26,900
1
$2,650
$1,885
1
$3,000
$2,149
1
$3,250
$2,467
1
$3,850
$3,805
1
$3,950
$1,980
1
$4,350
$2,267
1
$4,550
$2,565
1
$5,000
$4,090
1
$4,500
$910
$1,250
Wk
$5,000
-

Michael Barbco American


Mc
Byrne
Augers
Laughlin
$154,388 $144,597 $140,340 $106,650
$8,475
$9,708
$9,111
$13,760
$18,840 $15,590
$19,950
$19,080
$21,920 $17,740
$22,000
$20,800
$23,890 $20,800
$23,950
$22,920
$29,440 $27,010
$29,000
$26,320
$1,505
$1,584
$1,694
$948
$1,895
$1,794
$1,733
$1,144
$2,475
$2,378
$1,806
$1,384
$3,020
$3,113
$2,149
$2,836
$2,312
$2,575
$2,119
$1,804
$2,650
$3,044
$2,457
$2,528
$3,830
$3,500
$2,772
$2,888
$4,604
$5,254
$3,053
$4,228
$680
$930
$566
$920
$1,875
$1,250
$1,250
$1,200
$6,800
$1,750
-

$364,600 $221,060 $288,599 $260,867


22

$265,700

$229,410

Item
10% Discount
Total with Discount

Qty

Robbins

Bor-It

Michael
Byrne

Barbco

American
Mc
Augers
Laughlin
$26,087
$26,570

$364,600 $221,060 $288,599 $234,780

$239,130

$229,410

Based upon the above table, the quotes from The Robbins Company and Michael Byrne are not
competitive. The quotes from Bor-It, Barbco, American Augers, and Mc Laughlin are
competitive. While Bor-It offers the lowest price, the difference is not significant, it is around
1%.
ASSISTANCE/CONTRIBUTION FROM ODOT

Identify needed 20 culvert crossings replacements to conduct productivity and time study.
Ten to be done using ODOT work force, five to be installed using auger boring, and five to
be installed using open cut. For the other ten crossings to be executed by contractor: five to
be installed using auger boring, and five to be installed using open cut. It is preferred if a
few contracted ones are considered before the other crossing to give the ODOT work force
the opportunity to practice with the presence of qualified contractor.

For the ten crossings to be done using ODOT work force, ODOT will provide the
information such as the geotechnical conditions, ground water table level, underground
utilities, size of culvert, traffic volume of on field test site locations to the research team. It is
standard operating procedures that geotechnical investigation will be conducted prior to any
boring operation-to the extent possible. The depth of the investigations depends on already
available information, magnitude of soil variation, and construction risks at this particular
site. The research team and ODOT will identify the level of depth in the geotechnical studies
based on the particulars of the jobsite.

ODOT personnel will conduct the boring operations.

ODOT will assist the research team in identifying ongoing contracted auger boring and open
cut operations under its highways and permit the research team to conduct time and
productivity studies.

ODOT will provide further historical data on culvert replacement projects that were
contracted and those that were done by ODOT personnel. ODOT will also provide the
research team with bid prices for all work items relevant to the culvert construction projects
such as pit construction, mobilization and demobilization, excavation, laying pipes, backfill,
etc.

ODOT will provide estimates, to the extent possible, of all costs relevant to this study.

23

PIPE BURSTING AND RAMMING TESTS


Following the introduction to the trenchless technology presentation in the ODOT headquarter
on December 10, 201, ODOT instructed BGSU to consider expanding the scope of the project to
include pipe bursting (PB) and pipe ramming (PR). While BGSU was collecting quotation for
the pipe bursting systems, the difficulty to burst corrugated pipes was raised. The manufacturers
indicated that they are willing to test their systems in actual corrugated pipe conditions. This
seemed to be win-win for the manufacturer, ODOT, and the trenchless industry.
The research team expanded the scope of this report to include pipe bursting (PB) and pipe
ramming (PR) in the next few pages. The additional piece involves replacement of four culverts
using the pipe bursting and pipe ramming methods. This part of the report will cover:

An introduction to pipe bursting.

An introduction to pipe ramming.

Applications and limitations of pipe bursting.

The estimates for pipe ramming and pipe bursting tests.

Recommendations to ODOT on the way forward.


INTRODUCTION TO PIPE BURSTING (PB)

Pipe bursting replacement is a technique for breaking the existing pipe by brittle fracture, using
force from within, applied mechanically, and the fragments of the old pipe are forced into the
surrounding ground. At the same time a new pipe, of the same or larger diameter, is drawn in
behind the bursting tool as shown in Figure 5. The pipe bursting device may be based on a
pneumatic tool to exert diverted forward thrust to the radial bursting effect required, or by a
hydraulic device inserted into the pipe and expanded to exert direct radial force. Generally a
PVC or HDPE pipe is installed in these operations (North American Society for Trenchless
Technology, 2013).

Figure 5. Pipe bursting layout (Plastic Pipe Institute, 2008)


24

As the existing pipe is broken, the new pipe is either pulled or jacked into place. The breaking of
the old pipe and installation of the new pipe are done concurrently. The new pipe can be of equal
or larger diameter than the existing pipe and will follow the same alignment as the existing pipe.
Pipe bursting was developed in the late 1970's in the UK by D.J. Ryan & Sons and British Gas
mainly for the replacement of small diameter gas lines. The process involved a pneumatically
driven, cone-shaped bursting head operated by a reciprocating impact process. This method was
patented in the UK in 1981 and in the United States in 1986; these patents expired in April, 2005
(Plastic Pipe Institute, Chapter 16- Pipe Bursting, 2008). The method was initially used to
replace cast iron gas distribution lines but has been continuously developed and is today used to
replace water lines, sewer mains and sewer service lines, gas lines, and communication ducts
worldwide. Typical replacement pipe sizes range from 50 to 400 mm (2 to 16 in.) in diameter,
and lengths between 50 and 100 m (150 and 300 ft) (Ariaratnam & Hahn, 2007). Replacement by
pipe bursting is commonly done size-for-size or one upsize above the diameter of the existing
pipe. Larger upsizes (up to three pipe sizes) have been successfully done, but the larger the
upsizing, the more the energy needed to burst the pipe and the more the ground movement
experienced from the displacement (Atalah A. , 2006).
Almost all types of pipes can be burst which include cast iron, cast in place concrete, clay,
reinforced concrete, and asbestos cement (AC). Flexible/ductile pipe material such as steel,
ductile iron, high density polyethylene (HDPE), and polyvinyl chloride (PVC) require
modifications/additions to the bursting head to cut the pipe prior to bursting. Reinforced concrete
cylinder pipes (RCCP) cannot be replaced using this method because of the heavy steel
reinforcement. Corrugated metal and plastic pipes are generally not good candidates for
traditional pipe bursting approaches. Because you can either pull the new pipe or push it in place,
almost all types of pipe can be installed using pipe bursting. This would include: high density
polyethylene (HDPE), polyvinyl chloride (PVC), clay, steel, fiberglass, polymer, ductile iron,
and concrete (Timberlake, 2011) (Plastic Pipe Institute, 2008) (The International Pipe Bursting
Association, 2012). Sectional pipes are pushed in place while the continuous pipes that can take
tension can be pulled behind the bursting head.
Pipe Bursting Systems
Pipe bursting systems are typically classified into three main classes based on the type of
bursting head used as shown in Figure 6:
(a) Pneumatic head

(b) Hydraulic head

(c) Static head

Figure 6. Bursting heads for the different PB systems.

Pneumatic pipe bursting, which uses pulsating air pressure to drive the head forward and
burst the old pipe. A small pulling device guides the head via a constant tension winch
and cable.

25

Hydraulic expansion, where the hydraulic head expands and closes sequentially as it is
pulled through the pipe, bursting the pipe on its way.

Static pull, where a static head with no moving internal parts is used. The head is simply
pulled through the pipe by a heavy-duty pulling device via a segmented drill rod
assembly or heavy anchor chain (Atalah, Sterling, Hadala, & Akl, 1998)

Pneumatic Pipe Bursting


In the pneumatic system, the bursting tool is a soil displacement hammer driven by compressed
air and operated at a rate of 180 to 580 blows per minute. The percussive action of the
hammering cone-shaped head is similar to hammering a nail into the wall; each hammer pushes
the nail a short distance as shown in Figure 7. With each stroke, the bursting tool cracks and
breaks the old pipe, the expander combined with the percussive action of the bursting tool, push
the fragments and the surrounding soil providing space to pull in the new pipe. The expander can
be front-end (attached to the front end of the hammer) for pipes smaller than 12 or back-end
(attached to the backend of the hammer) for pipes larger than 12. The frontend expander allows
withdrawing the hammer through the new pipe after removing the expander at the exit pit
(Plastic Pipe Institute, 2008).

Figure 7. Pneumatic pipe bursting (Najafi M. , Trenchless Technology: Planning, Equipment,


and Methods, 2013)
Static Pipe Bursting
In the static pull system, a larger tensile force is applied to the cone-shaped expansion head
through a pulling rod assembly or cable inserted through the existing pipe. As seen in Figure 8,
26

the cone transfers the horizontal pulling force into a radial force, breaking the old pipe and
expanding the cavity providing space for the new pipe (Plastic Pipe Institute, 2008). Sectional
pipes are pushed into place by hydraulic jacks while the continuous pipes are pulled behind the
cone.
(a) Sectional Pipe

(b) Continuous Pipe

Figure 8. Static Pipe Bursting-Sectional Pipe


Hydraulic Pipe Bursting
In the hydraulic expansion system, the bursting process advances from the insertion pit to the
reception (pulling) pit in sequences, which are repeated until the full length of the existing pipe is
replaced. In each sequence, one segment of the pipe (which matches the length of the bursting
head) is burst in two steps: (1). the bursting head is pulled into the old pipe for the length of the
segment, and (2). the head is expanded laterally to break the pipe as shown in Figure 9 (Atalah,
Sterling, Hadala, & Akl, 1998).
There are other additions/modification to the above mentioned pipe bursting systems that are
designed to replace flexible pipes, advance segmental pipes, or assist in the bursting. These
systems include:
1. Pipe Splitting
2. Pipe Reaming (Inneream)
3. Impactor (Earthtool) Process, and
4. Tenbusch Method

27

Figure 9. Hydraulic bursting head (Xpandit) in both expanded and contracted positions (Atalah,
Sterling, Hadala, & Akl, 1998).
Pipe Splitting
The North American Society for Trenchless Technology (NASTT) defines pipe splitting as a
replacement method for breaking an existing pipe by longitudinal slitting or cutting with
simultaneous insertion of a new pipe of the same or larger diameter behind the splitting tool
(NASTT 2005). Pipe splitting replaces ductile material pipes, which does not fracture using
pneumatic and static bursting techniques. This system has splitting wheels or cutting knives that
slit the pipe longitudinally. Figures 10 and 11 show examples of the pipe splitting heads.

Figure 10. The static pull bursting head with accessories to cut reinforcing steel in RCP (TT
Technologies, 2004).

28

Figure 11. Pipe splitting head (PIM Corporation 2007)


Pipe Reaming
Pipe reaming is a patented pipe replacement
technique that uses a conventional
horizontal directional drilling (HDD)
machine with minor modification. The drill
rods are pushed through the old pipeline
and connected to a special reamer (see
Figure 12). The new pipe string is attached
to the reamer via a swivel and towing head.
As the drill rig rotates and simultaneously
Figure 12. Reaming head (Plastic Pipe Institute,
pulls back the drill pipe, the old pipe is
2008).
grinded and replaced by the new HDPE
pipe. Removal of the old pipe is
accomplished by mixing the grinded material with the drilling fluid and transferring the mix to
an entry or exit point for removal via a vacuum truck. Directional drilling contractors can
inexpensively use modified reamers of various types depending on the pipe materials and ground
conditions. Pipe reaming is limited to non-metallic pipeline replacement. According to Nowak
Pipe Reaming, Inc., the patent holder for the InneReam System, the surrounding environmental
conditions (groundwater, sand, rock, concrete encasement, etc.) that prohibit other procedures
are not obstacles to successful installations (Hayward 2002).
Impactor Process
The patented Impactor process is another system that combines the HDD with pipe bursting as
shown in Figure 13. The bursting head (Impactor) receives air through the HDD stems. The
HDD is connected to the air supply and is positioned to drill out to a manhole. Then the HDD
stem is pushed through old pipe to the next manhole and drilled back to the entry manhole. The
Impactor device, after it is attached to the drill stem and to the replacement pipe, is pulled into
the old pipe. While pulling back, the Impactor system activates and bursts the old pipe. The
combined actions -of pulling using the HDD rig and of hammering of the Impactor devicebreaks up the old pipe and replaces it with the new pipe. The Impactor system can overcome
blocked old pipes.

29

Figure 13. The Impactor process combines HDD with pipe bursting (Plastic Pipe Institute, 2008).
Tenbusch Method
The Tenbusch method allows the installation of segmental pipes such as VCT, RCP, fiberglass,
ductile iron, etc. This method relies on hydraulic jacks that push the pipe similar to those used in
pipe jacking as shown in Figure 14. The major advantage of this method is that it annihilates the
need for a lot of space to connect and string the pipe.

Figure 14. The Tenbusch method


When is Pipe Bursting a Preferred Solution?
When faced with pipeline and culvert problems, installing a new line parallel to the old one, then
grouting the old one is an alternative that can be used. In that case, the new culvert could be
30

installed using open cut or other trenchless techniques for new installations such as auger boring.
Alternatively, the pipeline can be rehabilitated by inserting a new lining or replaced by pipe
bursting. There are several pipe lining technologies available such as cured in place pipe,
deform and reform, and slip-lining. The main advantage of the lining methods over pipe
bursting is the need for small or no access excavation to the pipeline. However, pipe bursting
has the advantage of increasing the pipe capacity by more than 100%. The unique advantage of
pipe bursting over pipe lining techniques is the ability to upsize the service lines. For pressure
applications, a 41% increase in the inside pipe diameter doubles the cross sectional area of the
pipe and consequently doubles the flow capacity of the line. For gravity applications, a 15% and
32% increase in the inside diameter of the pipe combined with the smoother surface of the new
pipe can produce an increase in the flow capacity of 100% and 200% respectively. Pipe bursting
is most cost advantageous compared to the lining techniques when (1) there are few lateral
connections to be reconnected within a replacement section, (2) the old pipe is structurally
deteriorated, and (3) additional capacity is needed.
Pipe bursting has substantial advantages over open cut replacements; it is much faster, more
efficient, and often less expensive than open cut especially in deep installations. The increased
depth requires extra excavation, shoring, and dewatering which substantially increases the cost of
open cut replacement. The increased depth has a minimal effect on the cost per foot for pipe
bursting as shown in Figure 15 (Poole et al 1985).

Cost of Installation

Pipe Bursting
Open cut favorable conditions
Open cut unfavorable conditions

Depth (LF)
Figure 15. Cost comparison between pipe bursting and open cut replacements (Poole et al 1985)
31

Figure 16 provides the upper and lower limits of historical cost of pipe bursting per linear foot
according to (Simicevic & Sterling., 2001). For 24 inch pipe replacement, the lower limit is $95
and the upper limit is $255. Cost saving from pipe bursting could be much more if the soil is
hard rock because deep rock excavation is extremely expensive in open cut. Additionally, open
cut can cause significant damage to nearby pavements, buildings, structures, and green areas
(Atalah 2004).
$600
$500

Size to Size - Lower


limit

Cost/LF

$400
$300
$200
$100
$6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48
Diameter (inch)
Figure 16. The upper and lower limits of historical cost of pipe bursting per linear foot according
to (Simicevic & Sterling., 2001).
Specific studies carried out in the US have shown that pipe bursting cost savings are as high as
44% with an average savings of 25% compared to open cut (Fraser et al 1992). In addition to the
direct cost advantage of pipe bursting over open cut, as a trenchless technique, it has several
indirect cost savings. Less traffic disturbance, reduced road or lane closure, less time for
replacement, lower business interruption, minimal interference with other utilities, superior
safety (for both operators and the public) due to reduced open excavation, and minimal
environmental intrusion are some examples of these indirect cost savings.
Pipe Bursting Applicability and Limitations
Pipe bursting is used to replace water lines, sewer mains, and gas lines; as well as sewer lateral
connections. Typical length of replacement run is between 300 feet and 500 feet; however,
longer drives have been completed successfully in favorable conditions. The size of pipes being
burst typically range from 2 to 30, although pipes of larger sizes can be burst. Pipe bursting is
32

commonly performed size-for-size and one-size upsize above the diameter of the existing pipe.
Larger upsize (up to three pipe sizes) have been successful, but the larger the pipe upsizing, the
more energy needed and the more ground movement will be experienced. It is important to pay
close attention to the project surroundings, depth of installation, and soil conditions when
replacing an existing pipe especially in unfavorable conditions such as expansive soils, repairs
made with ductile material, collapsed pipe, concrete encasement, sleeves, and adjacent utility
lines (Atalah, Sterling, Hadala, & Akl, 1998). For culverts with shallow cover, bursting may
cause surface heave which may damage the road. The impact area must be determined before the
operation to minimize the damage to the road. In addition such shallow pipes are more
economical to replace using open cut. There are culverts with shallow cover (less than 36) that
could pose a special challenge when considering pipe bursting as a replacement method.
In large diameter pipe bursting operations, particularly during upsizing, there is legitimate
concern about potential damage of nearby facilities and structures. Based on analysis of ground
movement and vibrations associated with large-diameter pipe bursting when the pipe trench is in
a rock formation, Atalah (2006) stated with 95% confidence that: sound residential structures
would be safe at a distance of 3.3m or more from the bursting head, commercial structures would
be safe at a distance of 2.6m or more from the bursting head, and buried structures would be safe
at a distance of 2.3m or more from the bursting head. See Figure 17.
Pipe bursting also has the following limitations: (1) excavation for the lateral connections is
needed, (2) expansive soils could cause difficulties for bursting, (3) a collapsed pipe at a certain
point along the old pipe may require excavation at that point to allow the insertion of pulling
cable or rod and to fix the pipe sag, (4) point repairs with ductile material can also interfere with
the replacement process, (5) if the old sewer line is significantly out of line and grade, the new
line will also tend to be out of line and grade although some corrections of localized sags are
possible, and (6) insertion and pulling shafts are needed specially for larger bursts (Atalah,
Sterling, Hadala, & Akl, 1998).

33

10
5 in/sec. - Threshhold of Damage to Buried Structures
4 in/sec. - Threshhold of Damage to Commercial Structures
2 in/sec. - Threshhold of Damage to Residential Structures

PPS (in/sec)

0.1

0.01
1

10
Distance (feet)
Crane
2-Ton Drop Ball
TNT
Rock Pipe Bursting

100
Jack Hammer
Pavement breaker
Soft Soil Pipe Bursting

Figure 17. The attenuation lines of the PPS versus distance from the source for different
construction pieces of equipment (Wiss 1980) and the attenuations of the 95% PI upper limit
lines for the pneumatic bursting in soft soils (Atalah 1998) and hard soils (Atalah 2004).

34

Corrugated pipes may prove challenging to burst


because the ridges tend to fold. The bursting tool
can however be used as a ramming tool to ram a
casing over the existing corrugated pipe which
can then be ejected leaving a new pipe in place
(Figure 18). This flexibility of the bursting tool
offers an alternative that may be the economic
application in given situations.
INTRODUCTION TO PIPE RAMMING (PR)
The International Society for Trenchless
Technology (2013) defines pipe ramming as a
non-steerable method of forming a bore by
driving a steel casing usually open-ended with a
Figure 18. Original culvert consumed by
percussive hammer from the drive pit to the exit
new casing (Camp, Boyce, & Tenbusch,
pit. Installation is achieved by driving the steel
2010)
casing, either closed-end (for small diameter
pipes, usually 4 to 8 in) or open-ended for larger diameter pipes (pipes up to 138 and 147 in
diameter have been installed).Typical casing pipe diameters installed by pipe ramming are 4 to
96 inches in diameter (Najafi M. , 2013). After driving the casing the soil is removed, the casing
cleaned and the carrier pipe installed.
For ODOTs applications, we can use pipe ramming to either install a new parallel barrel or to
consume the existing conduit. In the case of consumption, the old conduit can be ejected after the
casing has been rammed in place.
Installation begins with preparation of the launch shaft and setting up the casing support system
which could be I-beams, wooden rail systems, or any other support system used to secure the
pipe and prevent any vertical or horizontal drift during the ramming process. A cutting shoe is
attached to the lead pipe which is then lowered onto the tracks and adjusted for gradient and
direction. Pushing collets are
inserted on the other end of
the pipe. These help to lock
the ramming tool/hammer into
the casing, evenly distribute
the ramming force, and
protect the casing. The tool is
locked into the collets and the
casing rammed into the soil.
The hammer and collets are
then removed, the next pipe
section is welded or connected
and the process resumes
(Read, 2004). Once the
installation is complete, the
soil is removed from the
Figure 19. Pipe installation through ramming (Orton, 2010)
casing by applying
35

compressed air or water from either end for small diameter casings. For large casings, augers can
be used to mechanically remove the soil from the inside of the pipe. For larger diameters, a small
backhoe or bobcat can be used. (Najafi M. , 2013)
According to Camp, Boyce, & Tenbusch (2010), an 18-in. (450-mm) diameter pipe ram can be
advanced up to approximately 150 ft. (50 m) in length. A 30-in. (750-mm) diameter pipe ram can
be advanced up to approximately 300 ft. (100 m) in length. A 144-in. (3,660- mm) diameter pipe
ram can be advanced up to approximately 200 ft. (60 m) in length. However, the drive length is
subject to many conditions (primarily the soil) and the distances given here are estimates that can
only be considered as a guideline
LITERATURE REVIEW ON COST
Atalah (2001) compared the cost of pipe bursting replacement method to open-cut construction
method for the repair of the Tripler Army Medical Center sewer line project. The project
consisted of replacing two existing sewer lines (16 and 18 in diameter) with a 937 of 20
ductile iron pipe. Though the project was specified, bid and built using open-cut, the paper
provided cost comparison between the two methods. The results of the analysis indicated that
pipe bursting was a more economical solution for the job when compared to open-cut. The cost
savings, in favorable conditions for pipe bursting, could amount to more than 10 to 15%. For this
particular job, the budgeted cost for the open cut was $ 321, 407 but as a result of changed
conditions, the actual cost to the contractor was over $ 600,000. The estimated cost of pipe
bursting was $ 227, 402 which is lower than the budgeted cost and about $ 400,000 lower than
the actual cost of open-cut for that project.
Lee, Najafi and Matthys (2007) compared the cost of an actual pipe bursting project on the
campus of Michigan State University (MSU) to estimated costs of several traditional open-cut
options To verify the reasonableness of the MSU pipe bursting cost, a cost estimate based on the
quantity of MSU pipe bursting project was prepared. To show the price range of pipe bursting
projects, a cost comparison with two other pipe bursting projects was also made. The paper also
briefly mentions other project aspects, such as time and social costs as additional benefits of pipe
bursting method. The analyses indicated that pipe bursting method is much more cost effective
and approximately two to three times less costly than the open-cut options.
Each construction method has its strengths and weaknesses relative to the other methods and
selection of the appropriate method will be project based. However, it is the research teams
proposal to use pipe bursting for installations not exceeding 24 and with adequate cover. For
installations exceeding 24, a specialized contractor can be used if ODOT elects to burst the
existing culvert. For deep installations of new culverts and where traffic disruption can be costly,
horizontal auger boring could be the suitable alternative. There are also cases where open-cut
will be the appropriate method but having all these options available to ODOT broadens the
range of options and will ensure efficiency.
COST ANALYSIS
Assumptions
Assumptions made for the purposes of this preliminary analysis are similar to those made in the
analysis for horizontal auger boring and open-cut options.
36

The direct benefits of the projects are the same for pipe bursting as for the other
construction alternatives. The assumption is that the finished culvert will perform the
same functions irrespective of the construction method used (same size and length, equal
design life, and similar capacity and flow rate.)
There is no damage to adjacent utilities or structures as a result of the construction
operation.
The work is completed on budget and schedule.
A city cost index of .98 is used to adjust the U.S. National average costs from the RS
Means calculations to local costs.
ODOT estimates are calculated with the following overhead rates: Labor (80%), Material
(15%), and Equipment (0%)
A factor of 112% is used to adjust the contractors cost to include the costs to ODOT for
contracted jobs. This factor of ODOTs overhead costs on contracted jobs includes an
additional 4% of the bid price for plan preparation and engineering, 6% of the bid price
for the inspection, and 2% of the bid price for accounting and administration.
Table 14 contains itemized estimates for pipe bursting jobs from the RS Means and the
respective total cost per linear foot for each item. Because RS Means does not break down the
pipe bursting cost/LF to material, labor, and equipment, we assumed that the direct costs of
materials, labor, and equipment constitute 30%, 45%, and 25% respectively of the total direct
cost. The contractor cost represents the total cost that the contractor will charge the customer and
it includes the direct cost plus the overhead and profit (O&P). The ODOT costs, which represent
the costs if the work is done in-house, are calculated with the following overhead rates: labor
(80%), materials (15%), and equipment (0%).
Table 14: RS Means Itemized Estimates for Pipe Bursting Jobs
Section #

Description

33 01 30.71

Pipe bursting 300' runs, replace with HDPE


pipe Not including excavation, shoring ,
backfill, or dewatering 6" to 15" diameter
Pipe bursting 300' runs, replace with HDPE
pipe Not including excavation, shoring ,
backfill, or dewatering 18" to 36" diameter
Pipe bursting mobilize and demobilize

33 01 30.71

33 01 30.71

Direct
$98.00

Total costs
Contractor ODOT
$107.80
$129.85

$196.00

$215.60

$259.70

$2,940.00

$3,234.00

$2,940.00

The total cost per foot estimates for pipe bursting jobs are presented in Table 15. The
contractors costs are adjusted by a factor of 112% to reflect the ODOT costs for the project
preparation and engineering, inspection, and administration.
Table 15: RS Means Estimates per ft. for Pipe Bursting Jobs
6-15"
18"-36"

Direct
$127.40
$225.40

Contractor
$156.96
$277.69
37

ODOT
$159.25
$289.10

For very shallow culverts, using pipe bursting may lead to damage on the surface because of the
displaced soil during the bursting operation. In such cases, this may not be the best alternative. If
the depth is considerable, pipe bursting will be the more economically attractive alternative.
ESTIMATE FOR PIPE BURSTING AND RAMMING TESTS
For this study, the research team has proposed four test sites. Two of the selected culverts will be
burst and the other two will be replaced by pipe ramming. The same bursting head will be used
to ram the casing over the existing culvert; ODOT will then extract the old culvert and install a
liner in its place. It is important that the selected culverts be low risk and low impact culverts; if
the bursting/ramming operation fails, no significant impact will occur. These culverts should be
in locations where we could use open-cut successfully with minimal cost implications. The
ODOT crew should be ready to open-cut the area and replace the culvert should this eventuate.
At least two of the four culverts should be made of corrugated pipe which is challenging to burst
and has often proved impossible to go through. These tests will allow us to assess a few
modifications to the bursting/ramming system to solve the problem.
The budget in Appendix 2 contains an estimate of the anticipated cost for these four culvert
replacement jobs. Based on the pipe bursting manufacturers equipment operation manual, the
required compressor must have a minimum 1236 CFM for ramming operations up to 30. The
pipes to be burst were assumed to be 18 and they are to be replaced size for size or upsized to
24 HDPE SDR 17. For the Ramming operations, the casing to be used will be 18 steel casings
with wall thickness. This will swallow (consume) any culverts with a smaller OD than the
18 casing.
ODOT CONTRIBUTION TO PB AND PR TESTS

ODOT will identify four (4) low risk culverts to be replaced. Two by pipe bursting
(preferably 18 diameter or smaller) and two by pipe ramming (preferably 24 diameter
or smaller). These culverts must be deeper than 10 times the outside diameter of the pipe
to avoid surface disturbance.

ODOT will provide the information such as the geotechnical conditions, ground water
table level, underground utilities, size of culvert, traffic volume of on field test site
locations to the research team. It is standard operating procedures that geotechnical
investigation will be conducted prior to any bursting operation-to the extent possible. The
depth of the investigations depends on already available information, magnitude of soil
variation, and construction risks at this particular site. The research team will work
ODOT personnel to determine the appropriate level of information needed.

ODOT personnel will prepare the pits for the pipe bursting and pipe ramming operations
following the specifications provided by the research team and the equipment
manufacturers.

ODOT will provide traffic control and other assistance that may be required for the
bursting and ramming operations.

ODOT will provide the labor, equipment and supplies for welding the Steel Casing,
fusion of HDPE, grouting the annular space, and fuel for the compressor.

38

ODOT will provide the research team with cost of all labor, equipment and supplies,
from ODOTs side, that were incurred in the pipe bursting and ramming operations to
enable the research team estimate the actual total cost.

If any of the bursting/ramming operations fail, ODOT will complete the installations
using open cut.
CONTRIBUTION FROM MANUFACTURERS

TT Technologies and Earth tool will provide the pipe bursting and ramming systems
required for the four culvert replacements

TT Technologies and Earth tool will provide one or two technicians to guide the boring
and bursting operations and serve as a teacher/trainer for the ODOT personnel.
CONCLUSIONS AND RECOMMENDATIONS

The research team attended the startup meeting and presented an overview of the trenchless
techniques that are available in the market place and that can be used to replace or line culverts.
Following the presentation, ODOT asked BGSU to investigate the additional cost for
incorporating pipe bursting and pipe ramming tests to the scope of work for the project.
This interim report of the project presents the costs of installations using the methods under
study, a proposed ABM for phase 2 (complete with specifications and costs), additional
information related to pipe bursting, cost estimates from literature and RS Means, an estimate for
the cost of the expanded scope (PB and PR tests), and recommendations on how ODOT should
proceed.
Horizontal Auger Boring
Based on the literature review, installing a 16 waterline underneath I-75 in Bowling Green,
Ohio, costs $604.50, $134.50, and $173.44 per linear foot when installed using Auger Boring,
Horizontal Directional Drilling, and Open-Cut with detouring traffic, respectively. For auger
boring, the costs were estimated to be about $200 per linear foot for a pipe 18 inches in diameter
to $1,000 per linear foot for a pipe 60 inches in diameter.
The research team solicited and obtained sample relevant historical bid prices of the
methodologies under study from ODOT. The analysis of the limited sample of bid prices that we
got from ODOT indicate that the average auger-boring-cost for a ten feet deep culvert was
$269.43, $341.86, and $414.28/LF for a 24, 36, and 48 culvert respectively. The average
open-cut-cost for a ten feet deep culvert was $130.97, $193.90, and $256.83 for a 24, 36, and
48 culvert respectively. The comparison of the auger boring cost per foot from bid prices of the
small number of projects versus the cost from the RS Means indicates that the contractors cost is
less than that of ODOT. However, this comparison is unreliable due the small number of bid
prices and the insufficient information about the scope of work and the respective prices.
The research team conducted preliminary cost estimates using RS Means. The estimates indicate
that the cost per foot for 24", 36", and 48" are $538.72, $816.10, and $1,059.29 respectively for
horizontal auger boring method using a contractor. Because the overhead structure for ODOT is
different in its structure than with a contractor, the estimated cost for the same diameters using
the ODOT workforce are $508.60, $768.86, and $1002.15/ LF respectively. The RS Means
39

estimates also indicate that the cost per foot for 24", 36", and 48" are $153.26, $205.24, and
$254.47 respectively for the open-cut method using a contractor. The estimated cost for the
same diameters using ODOTs workforce are $147.89, $199.02, and $245.91 / LF respectively.
This analysis indicates that doing the job in-house costs less than contracting. It is a more
accurate assessment of the two competing alternatives because we are using RS Means for both
alternatives.
The final analysis indicated that the ownership and operation cost of an ABM to the contractor is
around $165/hr. and the cost for ODOT to own and operate the ABM is around $110/hr. It is also
clear that the more hours per year that the equipment is in operation, the lower the cost per hour
to ODOT. The number of culverts in the State of Ohio indicates that the auger boring crew can
be in operation for more days per year than the assumed 75 days/year (20%); the ownership cost
can be cut in half if the number of operational days doubles to 150 days/year. The lower cost of
capital advantage for ODOT offers another significant competitive advantage. We can deduce,
from this analysis, that it would be more economical for ODOT to do the work in-house than to
contract.
Generally using ODOTs work force to replace culverts provides ODOT with more control over
the design and construction, which can reduce overall cost and time. It allows higher ability and
faster decision making to deal with unforeseen conditions because both the construction crew
and owner representative are ODOT employees. The ODOT construction crew can start work
with partial design and ground information since the construction crew will adjust and adapt to
the encountered conditions.
On the other hand, hiring an Engineering firm to design the project and a contracting firm to
install the conduit is more appropriate when the risk is high and the ground conditions are
unfavorable. They are better positioned to deal with these challenging conditions because they
are specialized in these types of work and do it on a daily basis. Small specialty contractors
often times have smaller overhead expenses than a large organization like ODOT. Further
discussion of these issues will be explored in Phase 2 of the project.
We recommend purchasing the ABM for the following reasons:

Two of the three above cited cost comparisons indicate that it will be more economical
for ODOT to purchase and operate the ABM.

Doing HAB work in house provides higher level of flexibility in the work such as
allowing design and construction works to overlap, lesser disputes, and no bidding cost.

The ABM will provide an additional tool to replace old deteriorated culverts across the
State of Ohio.

Based on literature, there are conditions that favor the use of horizontal auger boring over
the conventional open-cut method.

The ABM will provide ODOTs construction crew valuable training and development in
the advanced technologies of replacing culverts.

40

Pipe Bursting and Pipe Ramming Research Tests


Based on literature review, the cost savings, in favorable conditions for pipe bursting, could
amount to more than 10 to 15%. Another collection of bid price data indicates that the cost of a
24 pipe replacement size for size ranges from $90 to $255/LF. For another 18 pipe
replacement size to size, the bursting cost was $242/LF and the open cut cost was $343. A
research conducted for the U.S. Department of Agriculture (USDA) Forest Service roadway
culvert applications concluded that the cost of replacing or rehabilitating culverts 18 inches in
diameter (size for size) using pipe bursting are estimated to vary from $100 to $200 per linear
foot, and for 48-inch-diameter pipes, the cost was $850 per linear foot
It is recommended to use pipe bursting for only deep installations to avoid surface disturbance
due to ground movements. The preferred condition for pipe bursting is when the old conduit is
made of rigid material with compressible soil (such as trench backfill) around the pipe. It is also
recommended that a specialized contractor in pipe bursting do bursting work for conduits larger
than 24 in diameter.
The expanded scope of work will increase the cost to ODOT by $71,273.22 as shown in Table
16, but due to the cost savings of $60,000 for the auger boring equipment, the net cost increase
will be $11,274. The project duration will increase by four month due to the expansion. The
supplies item of $38,995.00 covers the steel pipe, HDPE pipe, the freight expenses for bursting
equipment, and the rental cost for the required compressor. The remaining amount is the
additional cost for the training and productivity study for the four additional site visits, and the
stipend and fringe benefits for the student workers for the additional four months of work.
Details of the expanded scope schedule and budget is shown in Appendix 2.
Table 16: The Original Proposal Cost, Expanded Scope Proposal, and the Difference
Budget Category
Salaries & Wages
Fringe Benefits
Travel
Supplies
Equipment
Printing
Indirect Costs
Total

Original Proposal
$76,012.64
$16,930.95
$7,240.00
$$300,000.00
$500.00
$29,644.93
$430,328.52

Original + PB tests
$95,299.28
$20,466.74
$9,174.00
$38,995.00
$240,000.00
$500.00
$37,166.72
$441,601.74

PB tests only
$19,286.64
$3,535.79
$1,934.00
$38,995.00
$(60,000.00)
$$7,521.79
$11,273.22

We recommend expanding the scope of the project for the following reasons:

The labor and equipment cost for replacing these additional test culverts will be greatly
leveraged because the manufacturers will do the operations themselves

The expanded scope will provide the required information to make a decision on whether
ODOT would benefit from acquiring the bursting system in the future for its in-house
operations.

41

The expanded scope will provide ODOTs construction crew valuable training and
development in the advanced technologies of replacing culverts.

The additional expenses for this expansion are costs that ODOT will still incur when
replacing these culverts and the research team anticipates cost savings as a result these
tests.

The expanded scope creates a win-win for ODOT and the manufacturers, and will serve
as a contribution to development in the trenchless construction industry where bursting
corrugated pipes is an outstanding problem.
REFERENCES

Australasian Society for Trenchless Technology. (2010). Installation of New Pipelines. Retrieved
from Installation of New Pipelines:
http://www.astt.com.au/trenchless_technology/new_installations/
Ariaratnam, S. T., & Hahn, U.-H. (2007). Simplified model for numerical calculation of pull
forces in static pipe-bursting operations. Tunnelling and Underground Space Technology,
644654.
Atalah, A. (1991). Pipe Jacking Design and Construction. Ruston, LA: Louisiana Tech
University.
Atalah, A. (1996). Design of Microtunneling and Jacking Pipe. ASCE Specialty ConferencePipeline Crossings 1996. Burlington, VT: ASCE.
Atalah, A. (2001). Cost Comparison Between Open Cut Construction and Pipe Bursting for the
Repair of Tripler Army Medical Center Sewer Line Project. North American NO-DIG
2001. Nashville, TN.: Annual Conference of the North American Society of Trenchless
Technology.
Atalah, A. (2006). Safe Distance between Large-Diameter Rock Pipe Bursting and Nearby
Buildings and Burried Structures. Journal of Transportation Engineering, 350-356.
Atalah, A. (2006). The Safe Distance between Large-Diameter Rock Pipe Bursting and Nearby
Buildings and Buried Structures. ASCE Journal of Transportation Engineering.
Atalah, A. (2007). The need for Trenchless Replacement Techniques in the Developing
Countries. North American NO-DIG 07. San Diego, CA: North American Society of
Trenchless Technology.
Atalah, A., Sterling, R. S., Hadala, P., & Akl, F. (1998). The Effect of Pipe Bursting on Nearby
Utilities, Pavement and Structures - TTC book #TTC-98-01. Ruston, LA: Louisiana Tech
University.
Boyce, G. M., & Bried, E. M. (1994). Estimating the social cost savings of trenchless techniques.
No-Dig Engineering,, 1(2), 2-5.
Budhu, G., & Iseley, D. T. (1994). The Economics of Trenchless Technology Versus the
Traditional Cut and Fill in High-Activity Urban Corridors-A Research Concept in a Real
42

World Environment. NO-DIG 94, Annual Conference of the North American Society of
Trenchless Technology. Dallas, TX: North American Society of Trenchless Technology.
Camp, C., Boyce, G., & Tenbusch, A. (2010). Culvert Replacement Using Pipe Ramming,
Tunneling, and Pipe Jacking. North American Society for Trenchless Technology
(NASTT) No-Dig Show 2010, (pp. Paper A-5-05). Chicago, Illinois.
Center for Underground Infrastructure Research and Education. (2004). Horizontal Auger Boring
Projects - ASCE manuals and reports on engineering practice; no. 106. Roston, VA:
American Society of Civil Engineers.
Gangavarapu, B. S., Najafi, M., & Salem, O. (2003). Quantitative analysis and comparison of
traffic disruption using open-cut and trenchless methods of pipe installation. ASCE
International Conference on Pipeline Engineering and Construction: New Pipeline
Technologies, Security, and Safety (pp. 1714-1724). Baltimore, MD, United states:
American Society of Civil Engineers Texas Section.
Goduto, V., & Atalah, A. (2013). The Design and Construction Cost of a Water Line underneath
I-75 in Bowling Green, OH. NO-DIG 13 Conference (pp. TM1-T6-02). Sacramento, CA:
North American Society of Trenchless Technology.
Hollingshead, T., & Tullis, B. P. (2009). In-Situ Culvert Rehabilitation: Synthesis Study and
Field Evaluation; report No. UT-07.204. Salt Lake, UT: Utah Department of
Transportation.
International Society for Trenchless Technology. (2013). Glossary. Retrieved 2013, from
http://www.istt.com/glossary?letter=M
Iseley, T., & Gokhale, S. (1997). Trenchless installation of conduits beneath roadways - NCHRP
Synthesis 242. Washington, D.C.: Transportation Research Board/National Research
Council.
Lee, H., Najafi, M., & Matthys, J. (2007). Cost comparison of pipeline asset replacement: opencut and pipe bursting. ASCE International Pipeline 2007 Conference (pp. 1-11). Boston,
MA: American Society of Civil Engineers.
Najafi, M. (2013). Trenchless Technology: Planning, Equipment, and Methods. New York:
McGraw-Hill Companies, Inc.
Najafi, M. (2013). Trenchless Technology: Planning, Equipment, and Methods. New York:
McGraw-Hill Companies, Inc.
Najafi, M., & Kim, K. O. (2004). Life-cycle-cost comparison of trenchless and conventional
open-cut pipeline construction projects. ASCE Pipeline Division Specialty CongressPipeline Engineering and Construction (pp. 635-640). San Diego, California: ASCE
Pipeline Division.
Nickol Boring Inc. (2013). Auger Boring Machine. Retrieved from Nickol Boring Inc.:
http://www.nickolboring.com/specifications.html
43

North American Society for Trenchless Technology. (2013, September 15). Glossary of Terms
and Definitions. Retrieved from North American Society for Trenchless Technology:
http://www.nastt.org/glossary/T?page=2
Ohio Department of Transportation. (2012). Ohio Department of Transportation Culvert
Management Manual. Columbus, OH: Ohio Department of Transportation.
Ohio Department of Transportation. (2014, January). 603 Pipe Culverts, Sewers, and Drains.
Retrieved from Ohio Department of Transportation:
http://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/2009MOP/600%20In
cidentals/603/603%20Pipe%20Culverts.htm
Ohio Research Institute for Transportation and the Environment (ORITE). (2005). Risk
Assessment and Update of Inspection Procedures for Culverts. Columbus OH: Ohio
Department of Transportation.
Orton, C. (2010). Pipe Ramming For Oil And Gas Pipeline Applications. North American
Society for Trenchless Technology (NASTT) No-Dig Show 2010 (pp. Paper A-5-04 ).
Chicago, Illinois: North American Society for Trenchless Technology (NASTT).
Piehl, R. (2005). Summary of trenchless technology for use with USDA Forest Service culverts. .
Eugene, Oregon: US Department of Agriculture, Forest Service, Technology &
Development Program.
Plastic Pipe Institute. (2008). Chapter 16- Pipe Bursting. In P. P. Institute, Handbook of
Polyethylene Pipe-Second Edition. Irving, TX: Plastic Pipe Institute.
Purdue University. (2010). AUGER BORING. Retrieved from Trenchless Technology:
http://rebar.ecn..edu/Trenchless/secondpage/Content/AB.htm
Read, G. F. (2004). Sewers: Replacement and New Construction. Butterworth-Heinemann.
Rehan, R., & Knight, M. (2007). Do Trenchless Pipeline Construction Methods Reduce
Greenhouse Gas Emissions? Waterloo, Ontario: University of Waterloo.
Salem, O., Najafi, M., Salman, B., D. C., Patil, R., & Bhattachar, a. D. (2008). Use of Trenchless
Technologies for a Comprehensive Asset Management of Culverts and Drainage
Structures. Madison, WI: Midwest Regional University Transportation Center.
Simicevic, J., & Sterling., R. L. (2001). Guidelines for pipe bursting. Vicksburg, MS: US Army
Corps of Engineers, Engineering Research and Development Center (ERDC).
The International Pipe Bursting Association. (2012). Guideline for Pipe Bursting. Owing Mills,
MD: The International Pipe Bursting Association (IPBA).
The International Society for Trenchless Technology. (2013). Auger Boring. Retrieved from The
International Society for Trenchless Technology: http://www.istt.com/guidelines/augerboring

44

The International Society for Trenchless Technology. (2013). Glossary. Retrieved from The
International Society for Trenchless Technology: http://www.istt.com/glossary?letter=P
Thomson, J., Sangster, T., & Kramer, S. (1998). An overview of the economics of trenchless
technology. NO DIG ENGINEERING,, 5, 23-27.
Timberlake, M. (2011). Pipe Bursting Various Types Of Pipes. Underground Construction,
66(6), pp. 42-43.
TT Technologies. (2004). Groundoburst Static Pipe Bursting System. Retrieved from TT
Technologies, Inc.: http://www.tttechnologies.com/literature/Grundoburst%20Lit.pdf

45

Vous aimerez peut-être aussi