1.0 OBJECTIVE
1.1 To define the requirement and describe the procedure for
earthwork,
Backfilling and compaction works for the utility building
2.0 SCOPE
2.1 Applicable to all the buildings and utilities.
3.0 REFERENCE
3.1 Project Approved Drawings
3.2 Project standard Spec.
3.3 British Standard BS test
4.0 GENERAL:
4.1 Approval of location and setting out is to be obtained from TEG engineer
prior to proceeding with BACKFILLING works.
4.2 Proper work permit should be in place before commencing the works
5.3.1 Lab test result done before backfilling will form the
reference to be conceded for compaction inspection.
5.3.2 Material inspection request form (MIR) shall be issued
at the start of the dumping material activity.
5.3.3 Work inspection request form (WIR) shall be issued at
the start of the backfilling activity to identify the location and
the expected time for inspection