ertise in dry fix process. They are assisted by unskilled labourers. Their work
is in turn supervised by experienced Foremen. Site Engineer will be available fo
r co-ordination with other sub-contractors and Main Contractor and also to look
into the technical aspects. He will ensure that the overall work conforms to the
shop Drawing.
06FIXING MATERIALS USED
1.
Angles/anchor to be used:
o
'Z Type Angle 40 x 70 x 40 x 4mm. The sizes and the type of angle may va
ry depending upon the space between stone and the wall and other factors. The an
gles to be used will be of stainless grade 304
o
Accessories include bolts, nuts, shield, ext arm, pins and washers all o
f stainless steel grade 304
2.
Glue to be used: Italian Solid Cream glue Marmolit mixed with hardener
3.
Protective Coating: Sikagard 700S siloxane based water repellent
07MACHINERY AND TOOLS TO BE USED
1.
Stone Cutting Machines 2 Nos. of different sizes
2.
Grinding machine Dewalt and other makes
3.
Drilling machines
4.
Tool Box containing spirit level, measuring tape, water level, right ang
le, plump etc.
08SAFETY PROCEDURES
1.
All standard Health, Safety & Environment norms will be adhered to stric
tly.
2.
All the workmen will wear overalls, safety shoes, goggles, hand gloves a
nd helmets. Adequate lighting and ventilation will be ensured during installatio
n.
3.
It will be ensured that machinery and tools used are safe and always in
good condition. Where applicable only calibrated tools will be used
4.
Markings will be made on the wall by setting plumb to determine the exac
t locations
09MAINTENANCE
The stone cladding will be under 1-year maintenance period. Any installation def
iciencies that are noticed in stones already fixed are attended to within this p
eriod
10GENERAL
The Sub-Contractor reserves the right to amend the method from time to time in c
onsultation with the Main Contractor, depending upon the specific site condition
s