Vous êtes sur la page 1sur 18

35

Underhand Cut-and-Fill Mining


at the Lucky Friday Mine

Clyde Peppin,*
Tom Fudge,*
Karl Hartman,*
Doug Bayer,*
and Terry DeVoe*

INTRODUCTION

The Lucky Friday Mine is located on the east end of the Coeur
d'Alene Mining District in the northern Panhandle of Idaho. The
mine site lies just east of the town of Mullan, 10 km (6 miles)
west of the Montana border (Figure 35.1). The Coeur d'Alene
Mining District has produced over 31,100 tonnes (1 billion
ounces) of silver, 8 million tonnes (8.8 million tons) of lead and
4 million tonnes (4.4 million tons) of zinc from 1885 through
1999. The Lucky Friday Mine has produced 6,350,293 tonnes
(7,371,181 tons) of ore to produce 3,570 tonnes (114,746,000
oz) of silver, 714,500 tonnes (787,600 tons) of lead, and
89,811 tonnes (99,081 tons) of zinc. 1
Production capacity of the Lucky Friday Unit in 2000 is over
1,000 tonne/d with a total work force of 210 employees.
Mechanized underhand cut-and-fill and mechanized overhand
cut-and-fill mining methods are used to extract silver, lead,
and zinc ore from the Lucky Friday and the Gold Hunter veins.
The ore-bearing minerals in both veins are tetrahedrite, galena,
and sphalerite. In 1999, the Gold Hunter vein supplied 75% of
the mill feed from two stopes mined using mechanized
overhand cut-and-fill and two stopes mined using mechanized
underhand cut-and-fill. Ore from the Lucky Friday vein was
produced from two stopes using mechanized underhand mining

produced from two stopes using mechanized underhand mining


methods. The average blended ore grade was 547 gm/tonne
(16 oz/ton) silver, 10% lead, and 2% zinc. In 1999, 280,200
tonnes (309,000 tons) of ore was milled and produced 138
tonnes (4,441,000 oz) of silver, 25,000 tonnes (27,600 tons)
of lead, and 1,720 tonnes (1,900 tons) of zinc in concentrates.
Underhand cut-and-fill mining is the method developed and
used to mine the Lucky Friday vein. This method was extended
to mining the Gold Hunter vein.

GEOLOGY
The Lucky Friday vein crops out as a thin, discontinuous vein in
the St. Regis Formation. Between the 1800 and 2000 levels
(approximately 600 m below the surface), the vein crosses into
the Revett Formation and extends along strike for over 457 m
(1,500 ft). Mineralization has been consistently strong at the
Revett-St. Regis contact to the current mining horizon 1,800 m
(5,930 ft) below the surface (Figure 35.2).

In the Revett Formation, the vein averages 1.2 to 1.8 m (4 to 6


ft) wide and dips nearly vertically to the southeast. From the
surface to about the 2000 level (600 m below the surface), the
Lucky Friday vein strikes east-northeast. Below the 2000 level
to the 5840 level (1,770 m below the surface), the vein
assumes a progressively northerly trend. The main Lucky
Friday vein is constrained on each end by prominent westnorthwest-trending strike-slip faults locally called the North and
South Control faults (Figure 35.3). On the upper levels,
mineralization was often very strong along these two
controlling faults, but in the lower Revett Formation, these

controlling faults, but in the lower Revett Formation, these


faults contain no economic mineralization. A stratigraphic offset
of 61 m (200 ft) or less is seen across the Lucky Friday vein.
The vein dips at an angle of about 85&##176;, which is about
10&##176; steeper than the host rocks. In the lower levels,
the vein locally reverses dip.
In plan view (Figure 35.3), the vein is S-shaped with a sinuous
middle portion that coincides with a steeply plunging anticline.
The vein takes this shape because of minor folds and major
faults. Several persistent faults offset the vein laterally up to 6
m (20 ft). There are numerous narrow veins in the hanging
wall and footwall of the main Lucky Friday vein; however, none
has proven to be economic.
Lucky Friday ore mineralogy is argentiferous galena and
sphalerite. The silver-bearing mineral is tetrahedrite that forms
tiny discrete inclusions in the galena. Gangue minerals include
quartz and siderite. The vein is easily identified, contrasting
sharply with the quartzite. Silver and lead grades are higher in
the quartzite of the Upper and Lower Revett Formation. Zinc
values are increasing and silver and lead grades are decreasing
slightly with depth. Average net smelter return (NSR) for 1999
from the Lucky Friday vein was $88.00 per ton.

MINE ACCESS AND SERVICES

The Lucky Friday and the Gold Hunter deposits are serviced
from the surface through the Lucky Friday's Silver shaft. The
Lucky Friday No. 2 shaft serves as a secondary access and
exhaust route. The Silver shaft is 5.5 m (18 ft) in diameter and
concrete lined. Total depth is 1,890 m (6,200 ft) with stations
at 2800, 4900, 5100, 5300, 5500, 5700, 5900, and 6100
levels. Skip loading facilities are at the 5370 and 5970 levels.

Hoisting is done with one Nordberg double-drum, double-clutch


hoist 12 ft in diameter with an 8-ft face. There are two 1,118kW (1,500-hp) dc motors driving the hoist. Muck hoisting
speed is 11.6 m/s (2,300 ft/min). Personnel are hoisted and
lowered at 7.6 m/s (1,500 ft/min). The hoist was designed to
hoist a 9.1-tonne (10-ton) payload from 2,286 m (7,500 ft)
without a cage attached. Currently, 4-m3 (140-ft3 ) bottom
dump skips are used with triple-deck cages beneath the skips.
Each deck of the cage can hoist 20 people, and the decks can
be removed to handle long loads. All supplies and equipment
must fit through a 1.7- by 1.7-m (5.7- by 5.7-ft) opening.
Compressed air is supplied by three Ingersoll Rand XLE
compressors. One I-R XHE is on standby. Total capacity is 142
m3/min at 7.6 bars (5,000 ft3/min at 110 psi). Normal usage is
about 60% of that volume.

about 60% of that volume.


Pumping mine water and waste water from the refrigeration
plants underground is done with Wilson Snyder plunger pumps
at the 2,800- and 5,300-ft levels. Normal pumping rate is 38 to
76 L/s (600 to 1,200 gal/min). That water is made up of
groundwater from the Lucky Friday vein at 9.5 L/s (150
gal/min) and water from chillers (depending on the time of the
year) at 28.4 to 63 L/s (450 to 1,000 gal/min). Installed
pumping capacity is 114 L/s (1,800 gal/min) with all three
pumps operating at once on both the 2800 and 5300 levels.

VENTILATION

Rock temperatures have been measured at 40.5&##176;C


(105&##176;F) at the 4900 level and 46&##176;C
(115&##176;F) at the 5900 level. To cool the working areas to
a maximum of 29&##176;C (85&##176;F) in the hottest part
of the year, two 230 RT chillers are required to cool the Lucky
Friday section of the mine. Other chillers are installed in the
Gold Hunter section.
Total mine air flow is 6,650 m3/min (235,000 ft3/min) supplied
by two 186-kW (250-hp) 130-mm (5-in) in diameter vane axial
fans drawing from the No. 2 shaft and a ventilation raise and
one 45-kW (60-hp) fan drawing from the No. 1 shaft. The 186kW fans operate at approximately 5.4 in of water gauge. The
45-kW fan operates at about 4.5 in of water gauge.
There are also three 224-kW (300-hp), 1,500-mm (60-in),
1,770-rpm booster fans located underground. Two of the
booster fans are in series on the 4050 level of the Gold Hunter
vein to draw 3,700 m3/min (130,000 ft3/min) through the Gold
Hunter, and the third is located on the 5660 sublevel of the
Lucky Friday to draw 2,700 m3/min (95,000 ft3/min) through
the Lucky Friday.
Auxiliary ventilation for each stope is supplied by two 56-kW
(75-hp), 760-mm (30-in) in diameter fans in series supplying
850 m3/min (30,000 ft3/min) to each stope. Exhaust from the
stopes flows to a ventilation raise system to the 5400 level
then the ramp system to the bottom of the No. 2 shaft at the
5100 level.

Cooling is supplied by one 50 RT spray cooler for each stope.


Chilled water at 9&##176;C (48&##176;F) from the chiller
station at the 5300 level is piped to the sublevel being
operated and into the spray coolers. Warm water at
approximately 21&##176;C (70&##176;F) from the spray
coolers is then pumped back to the chiller station. Waste heat
from the chillers is carried by water that flows through the
condensers on the chillers. This condenser water is piped to the
main pump station on the 5300 level.

MINE PRODUCTION
The Lucky Friday vein has produced over 7 million tonnes (7.7
million tons) of ore at an average grade of 533 gm/tonne
(15.49 oz/ton) silver, 10.68% lead, and 1.35% zinc. Production
from the Lucky Friday vein from 1994 through 1997 averaged
544 tonne/d (600 ton/d). Production from the Lucky Friday
vein in 1999 averaged 330 tonne/d (360 ton/d), which
represented about 25% of total production. Most of the Lucky
Friday Unit mill feed was produced from the Gold Hunter
deposit located approximately 1,524 m (5,000 ft) to the
northwest. Reduced production from the Lucky Friday vein
after 1998 was a result of higher-value ore mined from the
Gold Hunter deposit. Lucky Friday reserves are calculated to
the 5930 level, with known resources extending down to the
6290 level.

ROCK MECHANICS
The maximum principal stress in the Coeur d'Alene Mining
District is horizontal and typically strikes N 45&##176;W. In
the Lucky Friday Mine at the 5100 level, 1,554 m (5,100 ft)
below the surface, the magnitude of the major horizontal stress
was measured to be some 69 MPa (10,000 psi) oriented almost
perpendicular to the Lucky Friday vein. This high stress
combined with the brittle nature of the host Revett Quartzite
results in an environment that is prone to rock bursting.
To have a better understanding of the rock burst problem,
Hecla installed a microseismic monitoring system in the early
1970s. The U.S. Bureau of Mines (USBM) had previously
installed a seismograph to detect and study rock bursts and
large seismic events. In 1989, the USBM installed a
macroseismic system to allow waveform analysis of rock bursts
and seismic events. A macroseismic event is generally

and seismic events. A macroseismic event is generally


considered to have Richter-scale magnitude larger than 1.0.
Prior to 1986, the mining method used was overhand cut-andfill with raise access. Several levels were being mined at once
using the overhand system. In the early 1980s, there were as
many as 30 stopes in production to produce some 1,000
tonne/d (1,200 ton/d). As stoping progressed upward from
level to level, the sill pillars below a level became smaller and
smaller. These shrinking pillars had to support the high
horizontal and mining- induced stresses. As a result of the very
stiff and brittle Revett Quartzite host rock, sill pillars often
failed catastrophically, causing major damage to levels and
stopes.
To lessen the potential for these catastrophic failures, a new
mining method was selected that eliminated the formation of
highly stressed sill pillars. An underhand cut-and-fill mining
method using cemented sandfill resulted from a joint research
project by Hecla Mining Company, the Spokane Research
Center of the USBM, and the University of Idaho. This new
method shifted the high stresses to below the floor of the
stoping horizon similar to a longwall in a coal mine. Hence, the
acronym LFUL--Lucky Friday underhand longwall--was coined
to describe it.
Because the new method no longer allowed mining to take
place on multiple levels, only three or four stopes could be
mined at any one time along the advancing longwall front.
Therefore, each stope's productivity had to be increased from
15 to 20 tons per miner-shift to over 50 tons per miner-shift.
This improvement in productivity was accomplished by the
introduction of ramp access, load-haul-dump (LHD) machines,
and trucks.
While the LUFL mining method results in working under an
engineered and stable back, stope walls must be fully
reinforced with friction bolts and chain link mesh in order to
contain the effects of nearby rock bursts. Despite an increase
in the incidence of seismic events with increasing depth, the
LFUL mining method has greatly improved safety (Figure 35.4).

SAFETY
The underhand mining method and intense attention from
management and the workforce improved safety performance.
During the period between 1995 and 2000, there have been
two periods of more than 1 year with no lost-time accidents.
Figure 35.4 shows the improvement in injury rates since 1988
and the inception of the LFUL mining method.

STOPE DEVELOPMENT
Access from the Silver shaft to the Lucky Friday vein is via
ramps driven at 15% grade and a 3.2- by 3.3-m (10.5- by 11ft) cross section (Figures 35.3 and 35.5). At 27-m (90-ft)
vertical intervals, a sublevel is developed 100 m in the footwall
of the vein. Each sublevel provides access to mine eight 3.3-m(11-ft-) high cuts. Development is timed so that an entire
sublevel is completed as the ore is mined from the sublevel
above. Normal stoping progress is eight 3.3-m- (11-ft-) high
cuts per year.

Eight-hundred-fifty meters (2,800 ft) of development are


required each year to develop three stopes. An access ramp for
each stope is driven flat from the sublevel to within 60 m (200
ft) of the vein. In this flat section is installed a spray cooler, a
small storage area, and the controls for auxiliary ventilation of
the stope. A muck bay and a back section 4.3 m (14 ft) high
are cut in the sublevel so that 16-ton trucks can be side-loaded
with 2- or 3.5-yd3 LHDs. A ramp is driven up at +20% grade to
within 20 to 30 m (60 to 100 ft) of the vein. The grade of the
access ramp is established so that there will be at least 3 m
(10 ft) of flat ramp before the vein is intersected. A second
ramp is driven down at -20% to within 35 m (120 ft) of the
vein and flattened out for 5 m, or about two rounds. When all
eight cuts accessed from the sublevel above are completed, the
stope crew is moved to the predeveloped access and the +20%
ramp is advanced until the elevation of the of the back of the
advancing ramp is at the same elevation as the floor of the last
cut mined from above. The ramp is then flattened out and
driven across the vein and 7.5 m (25 ft) into the hanging wall
to create a muck bay. The miners in the stopes will muck the
rounds blasted on the previous shift into this muck bay. Later,
another crew will transfer the muck into trucks for haulage to
the Silver shaft ore pass (Figure 35.6).

Mining a Cut
A stope crew consists of two miners per shift responsible for
the complete cycle. Mining of the cut proceeds with each miner
drilling and blasting one 2.4-m- (8-ft-) long round per shift
each way from the access intersection. Before beginning to
muck out the round blasted on the previous shift, the miners
bar down any loose fill or rock above the muck pile. Then a
strip of 10-gauge chain link wire mesh is hung from Dywidag
rock bolts cast into the cemented sandfill on the previous cut.
This mesh provides overhead protection for the miner as the
round is being mucked out. Each miner mucks the round into
the muck bay in the stope intersection. Once the round is
mucked out, the miners then install additional 1-m- (3-ft-) long
friction bolts in the cemented fill overhead as needed to tighten
up the wire mesh. The walls of the stope are also supported
with 1-m- (3-ft-) long friction bolts on approximately a 1- by 1m (3- by 3-ft) pattern. When width allows and when ground
conditions warrant, more aggressive support is installed, i.e.,
1.2- and 1.8-m (4- and 6-ft) long friction bolts or 1.8-m (6-ft)
grouted rebar bolts. All bolt installation is done with jackleg
drills. When extremely poor ground conditions are encountered
or when seismic activity is very high in a stoping block,
shotcrete is used to support broken fill overhead or badly
fractured walls. The shotcrete is applied immediately after
mucking out, then bolts and wire are installed over the
shotcrete.
Once the round is supported, the next 2.4-m- (8-ft-) deep
round is drilled using a single-boom, diesel over hydraulic,
narrow-vein jumbo. Eighteen 38- or 44-mm (1.5- or 1.75-in)
holes are used to break a heading up to 3.1 m (10 ft) wide and
3.5 m (11.5 ft) high. An additional row of holes is added if the

3.5 m (11.5 ft) high. An additional row of holes is added if the


face is wider than 3.5 m (11.5 ft). The top two rows of holes
intersect the loose muck laid on the bottom of the cut above.
The top row is collared about 1 m (3 ft) below the bottom of
the loose muck and angled up so that the holes intersect the
loose muck about 1.5 m (4 ft) into the hole. Below this top
row, 2.4-m (8-ft) long holes are drilled to intersect the loose
muck at the end of the 2.4-m (8-ft) drill hole. Below this, four
more rows of holes are drilled 2.4 m (8 ft) deep.
Paper-wrapped emulsion explosive primed with nonelectric
blasting caps initiated by cap and fuse on detonating cord is
used for explosive. Plastic-wrapped explosives have not proven
to be efficient because the drill holes are extremely rough.
ANFO is not used because of the drill holes are wet, and the
mixture of ANFO with cement in the fill produces ammonia. The
round is timed so that the middle hole in the top row is shot
first.
Experience has shown that most rock bursts occur with the
blast or within the first hour after blasting. Therefore, blasting
is done only at the end of each shift. No blasting is done on
shift in the Lucky Friday to minimize the chance of triggering a
rock burst with a blast. Shifts are spaced at least 21/2 hr apart
to allow the seismic activity to settle down before the next shift
comes on.
Backfill
The underhand cut-and-fill mining system depends on
cemented backfill of consistent quality with uniaxial unconfined
compressive strengths greater than 1.5 MPa (250 psi) and less
than 4.5 MPa (650 psi), with the optimum being 3.4 to 3.8 MPa
(500 to 550 psi). Fill will typically achieve a compressive
strength of 1.4 to 1.9 MPa (200 to 300 psi) within 3 days.
Average strengths at 7, 14, and 28 days are 1.9, 2.6, and 3.8
MPa (280, 380, and 550 psi), respectively. The fill strength is
controlled by the amount of cement in the batch and the waterto-cement ratio. Pozzolith additives are being experimented
with at the time of this writing to improve the flow
characteristics of the paste in the delivery lines, reduce the
amount of cement needed to achieve optimum strength, and
improve the early strength of the fill.

Fill with compressive strength less than 1.5 MPa (250 psi) will
not support itself for more than 1 or 2 days at widths over 2.5
m (8 ft). Fill with strengths over 4.5 MPa (650 psi) is
susceptible to damage from seismic events and stope closure,
causing it to break into large blocks. Fill with compressive
strengths of 3.4 to 3.8 MPa (400 psi to 550 psi) will compress
during stope wall closure and during a seismic event will
fracture into smaller pieces and actually compress but not
break into large blocks and fall out.
Preparation for Backfilling
Once mining of a cut is complete, the stope is cleaned out, and
a 0.3-m (12-in) layer of broken waste rock, called prep rock, is
placed on the bottom of the stope with a 1-yd3 LHD. Dywidag
bolts 2 m (6 ft) long and 22 mm (7/8 in) in diameter are driven
into the loose prep rock on 1.2-m (4-ft) centers. A nut and
plate are attached to the top of the bolt, and tie wire is used to
stabilize the bolts vertically so they won't fall over during fill
placement (Figure 35.7).

When the next lift below is mined and as each round is blasted,
the loose muck cushions the fill from the blast and gives a little
expansion room for the blast. The loose muck falls away from
the fill and the bolts, leaving a short distance of bolt exposed.
The miner can then put wire mesh over the end of the bolt
sticking out of the fill, attach a nut and plate, and provide
overhead protection immediately.
This preparation method is used for stopes up to 5 m (16 ft)
wide. Any stope or area that exceeds 5 m (16 ft) in width will
have timber supports added to the prep. The 10- by 10-in
timbers are installed across the stope on 2.5-m (8-ft) centers.
Holes are drilled in the timbers so the Dywidag bolts can be

Holes are drilled in the timbers so the Dywidag bolts can be


installed through the timber and into the loose muck every 1.2
m (4 ft) along the length of the timber. Cable is used to sling
the end of the timber and secure it to the ribs. Care is taken to
keep the ends of the timbers well away from the rock walls of
the stope so that as the stope walls converge, the timbers will
not buckle.
A wall of either muck or timber is built at the end of the section
to be filled so that the filled section will be no longer than
about 60 m (200 ft). Poor-quality fill is seen when sections
longer than this have been excavated
When the sand fill preparation is complete and the wall is built,
the stope is filled with cemented paste backfill and allowed to
cure 3 days before mining of the next cut below is begun.
Paste Backfill System
The backfill plant has two independent functions. The sand
plant makes the backfill sand from tailings from the flotation
zinc circuit. The batch plant mixes the sand with water and
cement to make a paste and pumps the paste to the Silver
shaft collar for distribution to the stopes (Figure 35.8).
Approximately 30% of the tailings from flotation go directly to
a 9-m (30-ft) in diameter, 3-m (10-ft) deep thickener. The
remaining 70% of the tailings are sent to a 25-cm (10-in)
cyclone. Cyclone overflow is sent to the tailings impoundment
and the underflow to the thickener. Thickener underflow at
65% solids by weight is pumped to an Eimco 3- by 4.3-m (10by 14-ft) vacuum drum filter for dewatering. Overflow from the
tub of the filter flows to an 2.4- by 3-m (8- by 10-ft) vacuum
filter. The filter cake from the two filters averages 12%
moisture and is transferred via 0.6-m (24-in) conveyor to a
sand storage building. Backfill sand is made whenever the
concentrator is operating. Table 35.1 lists the particle size
distribution for the backfill sand.

The batch plant portion of the plant combines the backfill sand,
cement, and water in batches that are pumped underground
through a 15-cm (6-in) in diameter, schedule 80, pipe in the
Silver shaft and a 10-cm (4-in) in diameter pipe on the level to
the stope. The proportions of sand, cement, and water in each
batch are computer controlled to ensure a consistent mix that
meets requirements for the backfill needed. The dewatered
sand is picked up with a bucket wheel reclaimer and dumped
on a conveyor feeding a sand hopper. Cement is transferred
from a silo to a cement weigh hopper. The weighed portions of
sand and cement are dropped into a Nikko high-intensity
concrete mixer where water is added under computer control.
Each batch is mixed for approximately 2 min, then dropped
into the pump hopper.
The most common batch used in the Lucky Friday is a mix with
10.5- to 11-in slump. The batch proportions are 2,558 kg
(5,640 lb) of moist sand at 12% to 13 % moisture, 304 kg
(670 lb) Type I/II portland cement, and 360 to 378 L (95 to
100 gal) of water. This mix yields a backfill with an unconfined
uniaxial compressive strength of 3.4 to 4.1 MPa (500 to 600
psi) at 28 days.

A Schwing, positive-displacement concrete pump is used to


pump the paste about 27 m ( 90 ft) vertically from the backfill
plant to the shaft collar. The pump speed is controlled
manually, and the process control computer starts and stops
the reclaimer and conveyor to match the pump speed. The
paste backfill can typically be pumped at 127 tonnes (140 tons)
of paste per hour.
The 15-cm (6-in) paste fill line in the shaft is vented at the top
to eliminate cavitation, which causes excessive pipe wear. The
air that is pulled down with the fill has not proven to be a
problem in the delivery lines and may help reduce the density
of the paste and thus reduce line pressures. Lines in the stopes
must be very well secured because of the high surging effect
caused by the entrapped air. The point of highest pressure in
the line occurs at the transition from the vertical section in the
shaft to the horizontal section on the level. Line pressures of 41
to 62 bars (600 to 900 psi) are typical at this point. The
pressure seen here is dependent on the length of the delivery
line, the slump of the paste, and the height to which the fill is
transported.
The operator in the batch plant monitors the line pressure and
adjusts the mix and pump speed to maintain a safe line
pressure. If the pressure at the transition rises above 83 bars
(1,200 psi), the programmable logic controller (PLC) will stop
the backfill pump until the pressure drops below 83 bars (1,200
psi). To reduce high line pressures, additional water may be
added to the mix to reduce the slump, but additional cement
must be added to maintain the proper water-to-cement ratio.
The pump speed can also be reduced to lower the pressures in
the delivery line.
Before backfill is mixed and pumped to a stope, flushing water
is sent through the line to wet the line, ensure the line is not
plugged, and provide a visual check for leaks. The stope miner
notifies the backfill plant when the flushing water reaches the
stope, then the batch plant is started. The flushing water
before a pour is kept out of the stope by installing a valve in
the delivery line just outside the stope. Telephone
communication with the batch plant is very critical so the batch
plant operator can judge the needs for cement and monitor
progress.

progress.
When the depth of the fill in the stope is 0.6 m (2 ft) higher
than the tops of the Dywidag bolts, the miner informs the
batch plant operator that the stope is full enough. The batch
plant then begins the shut-down sequence. The remaining fill in
the pump hopper, the batch being mixed, and the batch being
weighed must be completed and pumped out. Once these are
pumped into the system, water is pumped into the line to flush
the whole system clean. The batch plant operator informs the
miner when the water is entering the system. From 15 to 30
min later, the water reaches the stope. When the miner sees
flushing water at the stope valve, the valve is opened, the
miner notifies the batch plant operator, and the batch plant
operator turns off the water.
Experience has shown that excess water in the stope, either
from groundwater or flushing water, creates very poor backfill
quality. Before a fill is made, any water collected in the stope is
pumped out and only enough flushing water is directed into the
stope to be sure the pipe line from the flush valve to the end of
the stope is clear at the beginning and end of the pour.
When a cut has been filled, the mining crew begins to drill and
blast out the bottom of the access ramp beginning at a point
15 m (50 ft) from the sand wall. The gradient of the reentry is
set at -20%. Within this 15 m (50 ft), the bottom has been
taken up sufficiently to have a face of rock 3 m (10 ft) high
when the face is just under the recently poured sandfill.
This reentry time period of 3 to 5 days combined with one or
two shifts repairing ground support outside the stope allows
enough time for the most recent pour to gain sufficient
strength to stand up while mining under the fill.

COSTS

The highest single cost item for direct stoping cost is labor
(Table 35.2). Miners' pay is based on a guaranteed hourly
wage set by the labor-management agreement, and incentive
is paid to miners on a total-cut incentive system. A value is set
for the labor to mine a complete cut, and at the end of the cut,
the value is divided by the miner shifts to complete the cut.
Progress payments are made at the end of each 2-week pay
period based on an estimate of the percentage completed.

period based on an estimate of the percentage completed.


Hours spent during the filling of the stope and repair work
resulting from rock bursts or poor ground conditions are not
charged against the "contract."

Development costs are based on the cost of preparing the next


block of ore to be mined as the current block is being mined
and the cost of accessing a cut after filling a cut. Shared
services are costs such as compressed air, hoisting, pumping,
and refrigeration, main ventilation system, etc., that are
shared among all stopes.

ACKNOWLEDGMENTS
Contributors to this section on the Lucky Friday have been Tom
Fudge, Lucky Friday Unit manager; Randy Anderson, senior
geologist; Steve Thomas, mine planner; Karl Hartman,
ventilation engineer; Doug Bayer, senior engineer; Wilson
Blake, consultant; and Clyde Peppin, engineering supervisor, all
of the Lucky Friday Mine staff.

REFERENCES
Blake, W., and D.J. Cuvelier. Rock Support Requirements
in a Rockburst Prone Environment: Hecla Mining
Company's Lucky Friday Mine. Paper in Rock Support in
Mining and Underground construction: Proceedings of the
International Symposium on Rock Support, ed. By P.K.
Kaiser and D.R. McCreath (Sudbury, ON, June 16-19,
1992). Balkema, 1992, pp. 665-674.
Bolstad, D.D., Rock Burst Control Research by the US
Bureau of Mines, Proceedings of the 2nd International
Symposium on Rockbursts and Seismicity in Mines, ed.
by Charles Fairhurst (Minneapolis,

by Charles Fairhurst (Minneapolis,


June 8-10, 1988). Balkema 1990.
Lucky Friday Mine Staff.. Section 3, Chapter 6. In
Underground Mining Methods Handbook, ed. by W.A.
Hustrulid. AIME, 1982, pp. 549-557
Lucky Friday Unit, Hecla Mining Company. Policies and
Guidelines Handbook. 1999.
Noyes, R.R., G.R. Johnson, and S.D. Lautenschlager.
Underhand Stoping at the Lucky Friday Mine in Idaho.
Paper presented at the 94th Annual Meeting, Northwest
Mining Association, December 2, 1988, 14 pp.
Whyatt, J.K., T.J Williams., and W. Blake. In Situ Stress
at the Lucky Friday Mine (In Four Parts): 4.
Characterization of Mine In Situ Stress Field. USBM RI
9582, 1995.

1. Lucky Friday Mine, Hecla Mining Company, Mullen, ID.

Vous aimerez peut-être aussi