Académique Documents
Professionnel Documents
Culture Documents
Document No.
HSE-S011-400
Date
By
A1
HSEC
A2
HSEM
00
HSEM
Review
Sign
April 2007
Page 1 of 8
Preparation
It is essential that the following HSE standards are communicated to potential
contractors at the earliest stage of the tendering process. The work flow for pipeline
construction and the required safety equipment all have a cost impact which must be
accurately reflected in any bid.
The Wintershall-Libya HSE Department must be represented in any negotiation with
the contractor over the scope of the construction project, either before award of
contract or after, if such negotiations could possibly impact the implementation of these
HSE standards or alter the HSE risk.
HSE Concerns
Trenching, the lay-out of equipment and materials, including the stringing of the
pipeline, represent a significant risk to persons driving across the route of the pipeline.
Construction and material planning should always being organized so that the size of
the construction site is minimized. The site should be adequately marked with
warning signs for both day and night and conditions of poor visibility.
Crossing points (road, sand track, pipelines) needs special set ups. The frequency and
setup of crossing points should be risk assessed for each pipeline construction. This
may involve consultation and negotiation with the community and other companies.
Procedure
The following minimum standards shall be applied.
Beginning / End of Site
If the construction comes close to a road, a minimum distance has to be fixed on
location. At the end position, additional floodlights need to be installed and drums have
to be used to form a funnel, (see Figure 1.).
Page 2 of 8
onshore Libya
Minimum
Distance needs
to be fixed on
location
Sand
road
with
Drumway
markers
Page 3 of 8
onshore Libya
Page 4 of 8
Page 5 of 8
onshore Libya
of the construction site). A warning light (red or yellow, flashing or constant) shall be
secured to every fourth drum (400 m intervals).
B.4) Beginning and endpoint of the site to be secured with drums standing at 10 m
intervals. Area has to be lighted with floodlights during darkness.
B.5) Each individual pipe joint is to be marked with longitudinally fixed reflecting tape of
approximately 8 mm width. This tape should be mounted at 120 degree intervals on the
circumference of the pipe so that it is visible from all sides (see Figure 5.).
100
15m
10m
Pic 1
Reflecting tape
0.6m
min. 10m
0.4m
15m
Page 6 of 8
onshore Libya
8 mm
Page 7 of 8
Reference Documents
All construction companies should familiarise themselves with Wintershall-Libyas
general HSE requirements for contractors.
Page 8 of 8