Vous êtes sur la page 1sur 34

PRELIMINARY FOUNDATION REPORT

MAIN POST TUNNELS


DOYLE DRIVE REPLACEMENT PROJECT
April 15, 2008

TABLE OF CONTENTS
Page
1.0

INTRODUCTION............................................................................................................... 1

2.0

SITE GEOLOGY AND SUBSURFACE CONDITIONS...................................................... 1


2.1
GENERAL SITE GEOLOGY ................................................................................. 1
2.2
SITE SPECIFIC SUBSURFACE CONDITIONS.................................................... 1
2.3
GROUNDWATER ................................................................................................. 2

3.0

SCOUR ............................................................................................................................. 3

4.0

CORROSIVITY ................................................................................................................. 3

5.0

SEISMICITY/LIQUEFACTION .......................................................................................... 3

6.0

FOUNDATION TYPE RECOMMENDATIONS.................................................................. 4

7.0

EARTH PRESSURES ....................................................................................................... 4


7.1
VERTICAL EARTH PRESSURES......................................................................... 4
7.2
LATERAL EARTH PRESSURES .......................................................................... 4

8.0

CONSTRUCTION CONCERNS........................................................................................ 5

9.0

ADDITIONAL FIELD WORK AND LABORATORY TESTING........................................... 5

LIST OF FIGURES
Figure 1
Figure 2

Locations of Geotechnical Explorations Main Post Tunnels


Subsurface Stratigraphy Along North Bound Main Post Tunnel

LIST OF APPENDICES
Appendix A
Appendix B

Shearwave Velocity Results for Boreholes MPTSB-R3 and MPTNB-R6


Caltrans Memorandum, dated February 5, 2008, Doyle Drive Replacement
Retaining Structures Preliminary Foundation Report

ii
Q:\131558\4a Arup Internal Project Data\4a-015 Geotech\4a-015-001 Reports and
Narratives\2008-04 Preliminary Foundation Report\2008-04-15 PFR - Main Post
Tunnel_Draft.doc

1.0

INTRODUCTION

This preliminary foundation report provides preliminary foundation recommendations for the
Main Post Tunnel structures, cut-and-cover tunnels located in San Francisco, California. The
proposed structure is part of the Doyle Drive Replacement project which will replace the freeway
which stretches from the west end of Lombard Street, through the Presidio of San Francisco,
ending at the Golden Gate Bridge toll plaza. The cut-and-cover tunnel will be landscaped above
to restore some of the natural beauty of the Presidio, which is now part of the U.S. National Park
System.

2.0
2.1

SITE GEOLOGY AND SUBSURFACE CONDITIONS

GENERAL SITE GEOLOGY

The bedrock at the site of the Main Post Tunnels is generally the Franciscan Formation. This
formation consists of a variety of heavily folded and sheared assemblages of Greywacke
sandstone, siltstone, chert, serpentinite, and Mlange Matrix (a plastic bedrock unit which is
similar to a gravelly clay). The hardness of these bedrock units typically range from very soft to
hard and may vary in short distances.
Overburden soils consist of mostly marine deposited sediments. Common sediment sequences
found elsewhere along the San Francisco Bay fringes are found at this site. The typical
sediments begin with Bay Mud at the surface underlain with marine deposits followed by Colma
Formation, which is a dense sand. Beneath the Colma Formation is typically Old Bay Clay, a
stiff overconsolidated clay. Another deeper sequence of sand and clay are sometimes
encountered.
The footprint of the project extending from the Battery Bluff to Lombard Street was originally
tidal marsh. This land was reclaimed in 1912 using hydraulic filling method. Up to 12 feet of fill
consisting of sandy clays and silts and clayey sands can be found in this portion of the site.
2.2

SITE SPECIFIC SUBSURFACE CONDITIONS

A site map of the Main Post Tunnels area is presented in Figure 1. This map shows the location
of the borings, as well as the proposed roadway and tunnel structure. Figure 2 presents a
generalized subsurface cross section, showing the soils encountered underneath the
northbound tunnel.
The general subsurface condition at the site of the Main Post Tunnels consists of a very deep
valley in the bedrock surface that has been filled by sediments. Little is know about the actual
contours of the bedrock in this segment of the project. Currently, only two boreholes extended
1
Q:\131558\4a Arup Internal Project Data\4a-015 Geotech\4a-015-001 Reports and
Narratives\2008-04 Preliminary Foundation Report\2008-04-15 PFR - Main Post
Tunnel_Draft.doc

deep enough to encounter bedrock. In boring MPTNB-R5, bedrock was encountered at a depth
of 175 feet below existing ground surface. In boring MPTNB-R6, bedrock was encountered at a
depth of 232 feet below existing ground surface.
The surficial geologic unit in this area of the project is fill which extends from 0 to 12 feet. The
fill in this area was placed hydraulically to reclaim tidal marsh land in 1912. The fill is primarily
very loose sand with some silt and clay. The upper two to three feet has considerably more
fines and gravel.
Below the artificial fill is two to four feet of Bay Mud, a common young clay deposit found along
the coast of the San Francisco Bay. The Bay Mud is soft with undrained shear strength of
approximately 400 psf. Typically, it is high plasticity and relatively free of sand, however
because of the thin layer encountered at the site, most of the Bay Mud is sandy and some
appears to have liquid limits which may define the sediments as lean clay. Plant material is
typically found at the top of this unit confirming that the site was previously a marsh land.
Below the Bay Mud is typically a three to six feet layer of a marine deposited sand followed by a
marine deposited clay and then another marine deposited sand. The marine sand layers
typically contain from 5 to 35 percent fines and are in a medium dense condition. The marine
clay is very similar to the Bay Mud with low undrained shear strengths.
Below the marine deposits lies the Colma Formation unit. This unit is typically 50 to 60 feet
thick. The upper portion of the unit is referred to as Colma Sand, which is dense to very dense
with typically a trace of fines. There are pockets in the unit which may contain from 15 to
45 percent fines, however, these pockets account for less than one-fifth of the unit. The bottom
10 feet of this unit typically becomes clayey as the unit transitions into the Old Bay Clay.
Old Bay Clay is found underneath the Colma Formation. This unit is a low to high plasticity very
stiff clay with infrequent sandy lenses. The thickness of this unit is not well defined because of
depth of the boreholes within the Main Post Tunnels area. In the boreholes where it was
encountered, its thickness ranges from at least 30 feet at the west end of the tunnel to 89 feet
encountered in boring MPTNB-R6. At boring MPTNB-R6, the Old Bay Clay deposit is
separated by a 45-foot-thick layer of marine sand.
2.3

GROUNDWATER

There are a several groundwater zones found at the site, which are separated by aquatards.
Perched groundwater is found in the fill layer about three to five feet below the ground surface.
This water is most likely connected to the bay and fluctuates with the tides. Below the Bay Mud
in the sandy marine deposit there is an upper immediate groundwater zone where water levels
appear to be at the same elevation as the groundwater in the fill above the Bay Mud.
2
Q:\131558\4a Arup Internal Project Data\4a-015 Geotech\4a-015-001 Reports and
Narratives\2008-04 Preliminary Foundation Report\2008-04-15 PFR - Main Post
Tunnel_Draft.doc

In the Colma Sand, below the marine clays, a lower immediate groundwater zone is present.
The piezometric level of this groundwater zone is under artesian conditions with the water level
ranging from 1.9 to 3.8 feet below the existing site grade.
Finally, in the deeper marine sands encountered below the first and the second Old Bay Clay
units, a lower groundwater zone appears to be pressurized (i.e., artesian condition) with an
equivalent static head of about 11.5 feet above the existing ground surface.

3.0

SCOUR

Scour will not be a concern on this portion of the project. However, surface runoff will cause
erosion if engineered fill and native soils are not covered with vegetation.

4.0

CORROSIVITY

This site is anticipated to be corrosive due to its proximity to the San Francisco Bay and the past
existence of a tidal marsh. Corrosion samples have been collected from the site during the field
investigation and will be tested for their corrosivity properties. Sampling and testing of the site
soils and groundwater shall be in conformance with the Corrosion Guidelines for Foundation
Investigations (Caltrans, 2003).

5.0

SEISMICITY/LIQUEFACTION

Structural design criteria has been proposed in the report titled Structural Design Criteria: Cutand-Cover Tunnels and Nonstandard Retaining Walls, Version 2, dated January 23, 2008. This
document summarizes the seismic demand placed on the structure. In addition, Geomatrix in
conjunction with Dr. Norm Abrahamson will be retained to perform a probabilistic seismic hazard
analysis, select time histories, and develop site specific rock motion spectra for the Main Post
Tunnels.
Liquefaction is anticipated at the Main Post Tunnels site. The hydraulic fill will most likely liquefy
in even a moderate seismic event similar to that of the recent Loma Prieta earthquake. During
this earthquake, damage caused by liquefaction was observed extensively in the neighboring
Marina district, which was hydraulically filled in the same reclamation project. In addition to the
fill, the upper marine sands, which are interbedded with marine clays, have a high potential to
liquefy in the event of a large magnitude earthquake. In the event of liquefaction at the site,
there is a potential for lateral spreading caused by soil movement towards the bay.
Suspension P-S velocity logging was performed in boreholes MPTSB-R3 and MPTNB-R6. The
velocity results for these two boreholes are presented in Appendix A of this preliminary
foundation report.
3
Q:\131558\4a Arup Internal Project Data\4a-015 Geotech\4a-015-001 Reports and
Narratives\2008-04 Preliminary Foundation Report\2008-04-15 PFR - Main Post
Tunnel_Draft.doc

6.0

FOUNDATION TYPE RECOMMENDATIONS

The Main Post Tunnel structures should be founded on Cost-in-Drilled-Hole (CIDH) piles
founded in the Colma Sand soil unit. This thick deposit of dense to very dense sand is ideal for
supporting the CIDH piles. The soils above the Colma Sand should not be considered to
provide any support to the piles due to the liquefaction potential of the sand layers and the clay
layers may in fact cause downdrag.
Regarding other pile types, driven piles may not be a viable option due to vibration and noise
concerns. If the driven piling option would be selected, a vibration and noise study and
monitoring will be required by the Presidio Trust. Also, small diameter displacement piles may
not be appropriate when considering the lateral load placed on these piles caused by lateral
spreading.
The most appropriate pile type is anticipated to be a fully cased CIDH large diameter piles
(about 5 to 8 feet in diameter). Steel reinforcement cages should be cast in place and rebar
should extend above the pile to tie-in with spanned bents of the tunnels. Based on previous
experience, it is estimated that an allowable skin friction of 1,400 psf can be achieved in the
dense Colma Sand.

7.0
7.1

EARTH PRESSURES

VERTICAL EARTH PRESSURES

Landscaping over the top of the tunnel structure will exert a distributed vertical load on the roof
of the structure. This dead load pressure from landscaping fill will be equal to 140 pcf times the
depth of the fill. For example, if there is 5 feet of fill material placed over the structure, the
applied distributed load from this material will be 700 psf.
There will be other vertical loads imposed on the structure from other sources such as traffic;
however, these loads are not considered in the scope of this preliminary foundation report.
7.2

LATERAL EARTH PRESSURES

Active lateral earth pressures will develop on the retaining walls at the ends of the tunnels. For
preliminary estimation of the active earth pressure at a particular depth, z in feet, the following
equation, pa (lbs/ft2) = 45 * z, should be used for Retaining Walls 9 and 10, located at the east
end of the Main Post Tunnels. For Retaining Wall 8 (Lincoln Retaining Wall Structure
34-016M), located at the west end of the south bound tunnel, Caltrans has prepared a
memorandum: Preliminary Foundation Report, dated February 5, 2008. The Caltrans
4
Q:\131558\4a Arup Internal Project Data\4a-015 Geotech\4a-015-001 Reports and
Narratives\2008-04 Preliminary Foundation Report\2008-04-15 PFR - Main Post
Tunnel_Draft.doc

memorandum presents preliminary soil design parameters for lateral earth pressures. A copy of
the Caltrans memorandum is attached under Appendix B.
At-rest lateral earth pressures will develop on the side walls of the tunnels with the placement of
the backfill. For preliminary estimation of the at-rest earth pressure at a particular depth, z in
feet, the following equation can be used. pat-rest (lbs/ft2) = 65 * z.
It is assumed that drainage behind retaining walls and the tunnel sidewalls will be provided to
relief hydrostatic pressure. Surcharges from traffic loading should be added where appropriate.
Seismic lateral earth pressures will be developed as part of a detailed seismic analysis and are
not included in this preliminary report.
The equations to determine preliminary pressures are given for an individual point. Over the
side of the tunnel walls, the earth pressures will be a trapezoidal distributed force. Resultants
may be easily determined using standard methods.

8.0

CONSTRUCTION CONCERNS

Difficult CIDH pile installation should be anticipated. The CIDH piles should be installed with
temporary full casing to ensure a quality pile. A drilling polymer may be required while installing
the piles in order to counter balance the artesian groundwater conditions.
Although not historical, there is a building at about Station 62+00 adjacent to the proposed
south bound Main Post Tunnel that may require underpinning due to slope excavation required
for the new tunnel. The bluff excavation most likely will require some type of top bottom shoring
system.
Soft and unstable subgrade conditions will likely be encountered and may require stabilization to
operate construction equipment.
The relatively high perched groundwater and artesian conditions in the Colma Sand will require
construction dewatering.

9.0

ADDITIONAL FIELD WORK AND LABORATORY TESTING

Two additional exploratory boreholes located between MPTSB-R1 and MPTSB-R2, on top of
the bluff are recommended. This bluff will require a temporary shoring wall to install the tunnel
structures and the adjacent building may require underpinning.

5
Q:\131558\4a Arup Internal Project Data\4a-015 Geotech\4a-015-001 Reports and
Narratives\2008-04 Preliminary Foundation Report\2008-04-15 PFR - Main Post
Tunnel_Draft.doc

The laboratory testing program for the 2007/2008 exploration work has not been executed as of
the issuing of this preliminary foundation report. The program will consist of laboratory tests that
will determine the geotechnical engineering properties of the major soil units.
The recommendations contained in this preliminary foundation report are not final. Any
questions regarding the above preliminary recommendations should be directed to the attention
of Francis R. Greguras at 415-946-0255.

6
Q:\131558\4a Arup Internal Project Data\4a-015 Geotech\4a-015-001 Reports and
Narratives\2008-04 Preliminary Foundation Report\2008-04-15 PFR - Main Post
Tunnel_Draft.doc

WEST
A

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

80

1400
80

EAST
A'

Elevation (NAVD88), ft

BAY MUD

MARINE DEPOSITS

D
N
B
-R
1

COLMA SAND

-40

40

-40
TRANSITION SANDS
OLD BAY CLAY

-80

-80

DEEP
SANDS

-120

-120

OLD
BAY
CLAY

-160

-200
COLLUVIUM

-160

-200

BEDROCK

-240
0

100

200

300

400

500

600

700

800

Horizontal Distance, ft

900

1000

1100

Elevation (NAVD88), ft

FILL

M
(6 PT
0' N
O Bffs R
et 6
,S
ou
th
)
M
(4 PT
0' N
O Bffs R
et 5
,S
ou
th
)

Proposed Grade
of Roadway

M
PT
N
B
-R
4

Proposed Grade
of Tunnel Invert

M
(5 PT
0' N
O Bffs R
et 3
,N
or
th
)

M
PT
N
B
-R
1

40

M
(2 P T
5' N
O Bffs R
et 2
,N
or
th
)

Limits of Main Post Tunnel

1200

1300

-240
1400

DOYLE DRIVE PREFERRED ALTERNATIVE


Subsurface Stratigraphy, Section A-A'
Along North Bound Main Post Tunnel

Figure 2

APPENDIX A
Shearwave Velocity Results
Boreholes MPTSB-R3 and MPTNB-R6

SAN FRANCISCO DOYLE DRIVE BORING MPTSB-R3


VELOCITY (FEET/SECOND)
0

1000

2000

3000

4000

5000

6000

7000

8000
0

R1-R2 Vs

R1-R2 Vp

4
6

10
20

8
30

10
12

40
50

16
18

60

20
70

22
24

80

26
90

28
30

100

32
110

34
36

120

38
130

40
42
0

250

500

750

1000

1250

1500

1750

VELOCITY (METERS/SECOND)

2000

2250

2500

DEPTH BGL (FEET)

DEPTH BGL (METERS)

14

SAN FRANCISCO DOYLE DRIVE BORING MPTNB-R6


VELOCITY (FEET/SECOND)
0

2000

4000

6000

8000

10000

12000

0
R1-R2 Vs

R1-R2 Vp

20

10
40
15

DEPTH BGL (METERS)

25

80

30

100

35

120

40
140
45
160

50

180

55
60

200

65
220
70
240

75

260

80
0

500

1000

1500

2000

2500

3000

VELOCITY (METERS/SECOND)

3500

4000

DEPTH BGL (FEET)

60

20

APPENDIX B
Copy of Caltrans Memorandum
Dated February 5, 2008
Doyle Drive Replacement Retaining Structures Preliminary Foundation Report

Vous aimerez peut-être aussi