Vous êtes sur la page 1sur 734

RCC Retaining Wall For Group I _ 3 to 4 m Ht. for 1m length & 1 no.

0.300

3.11
3.100

1.60
3.60

0.80
1.500
0.500
6

0.000
0.500

1.300
###
1.30

0.500

2.600
2
Sr.
No
1

Description

3
Unit

Nos

Length

Width

Depth

in ordinary soil

cum

1.00

2.80

2.10

Total
Plain cement concrete M 15 grade levelling
course below foundation and approach slab
complete as per Technical Specification
Sections 1700, 2100 and 2700.

Cum

1.00

2.80

0.10

1
1
1

1.00
1.00
1.00

2.60
0.80
1.30

0.50
0.000
0.000

Earthwork in Excavation of Foundation


for
1
RCC Retaining wall in all types of soil complete
as per drawings and Technical Specifications
Clauses 304, 309 & 2903.

cum

Total
Providing & Casting in situ controlled Cement
Concrete for RCC Work in Retaining Wall
Open
Foundation
including
necessary
formwork, vibrating, curing and finishing. As
per MoRT&H technical specification section
1700.

Cum

Part - 1
Part - 2
Part - 3

cum
cum
cum

Part - 4

cum

Total
Structural cement concrete for reinforced
concrete grade M-30 for sub structure
including
formwork,
machinery
and
workmanship complete as per drawing and
Technical Specification Sections 1500, 1700
and 2200.

Cum

Part - 5
Part - 6

cum
cum

Total
Providing and fixing in position TMT HYSD
reinforcement complete as per drawing and
Technical Specification Section 1600.

Cum

Retaining Wall (Base Slab)


Retaining Wall (Stem)

M.T
M.T
Total

1.00

1
1

1.00
1.00

1.30
1.24

0.50

0.300
0.200

0.00

3.100
1.550

@ 60.18 kg/cu.m
@ 83.46 kg/cu.m

Cum

Reinf. For Retaining Wall 1m Length


Bar
mark Shape

No. of
Spacing bars

Dia

Length of Total
bar
length

a1

20

140

3.61

28.85

a2

3.61

28.85

c1

20

215

2.825

14.13

c2

12

300

1.000

8.00

d1

12

170

19

1.000

19.00

d2

10

1.000

10.00

e1

16

240

2.125

10.63

e2

12

300

1.000

7.00

10

1.000

4.00

s1

10

300

1.325

5.30

s2

10

300

1.000

5.00

s3

10

300

1.825

7.30

s4

10

300

1.000

0.00

s5

10

300

3.525

14.10

s6

10

300

11

1.000

11.00

TOTAL STEEL for( Foundation + Substructure) kg/m


TOTAL STEEL for Foundation kg/m
TOTAL STEEL for substructure kg/m
Steel for Foundation in kg/cu.m
Steel for substructure in kg/cu.m

c1+c2+e1+e2+f+s1+s2+s3+s4
a1+a2+d1+d2+s5+s6

Quantity

5.880
5.880

0.280
0.280

1.300
0.000
0.000

0.000
1.300

0.930
0.310
1.240

0.078
0.103
0.182

Total
Wt.kg/m wt(kg)

2.47

71.15

0.00

0.00

2.47

34.83

0.89

7.10

0.89

16.87

0.00

0.00

1.58

16.77

0.89

6.21

0.62

2.47

0.62

3.27

0.62

3.08

0.62

4.50

0.62

0.00

0.62

8.69

0.62

6.78

181.73
78.24
103.50
60.18
83.46

71.549

147.8854

kg/cu.m
kg/cu.m

RCC Retaining Wall For Group II _ 4 to 5 m Ht. for 1m length & 1 no.
0.300

4.41
4.400

2.90
4.90

1.30
6

1.500

0.600
0.000
0.500

1.900
###
3

1.90

0.500

3.800

Sr.
No
1

Description

Unit

Nos

Length

Width

Depth

in ordinary soil

cum

1.00

4.00

2.10

Total
Plain cement concrete M 15 grade levelling
course below foundation and approach slab
complete as per Technical Specification
Sections 1700, 2100 and 2700.

Cum

1.00

4.00

0.10

1
1
1

1.00
1.00
1.00

3.80
1.30
1.90

0.50
0.000
0.000

Earthwork in Excavation of Foundation for


RCC Retaining wall in all types of soil complete
as per drawings and Technical Specifications
Clauses 304, 309 & 2903.

cum

Total
Providing & Casting in situ controlled Cement
Concrete for RCC Work in Retaining Wall
Open
Foundation
including
necessary
formwork, vibrating, curing and finishing. As
per MoRT&H technical specification section
1700.

Cum

Part - 1
Part - 2
Part - 3

cum
cum
cum

Part - 4

cum

Total
Structural cement concrete for reinforced
concrete grade M-30 for sub structure
including
formwork,
machinery
and
workmanship complete as per drawing and
Technical Specification Sections 1500, 1700
and 2200.

Cum

Part - 5
Part - 6

cum
cum

Total
Providing and fixing in position TMT HYSD
reinforcement complete as per drawing and
Technical Specification Section 1600.

Cum

Retaining Wall (Base Slab)


Retaining Wall (Stem)

M.T
M.T
Total

1.00

1
1

1.00
1.00

1.90
1.98

0.60

0.300
0.300

0.00

4.400
2.200

@ 52.61 kg/cu.m
@ 71.27 kg/cu.m

Cum

Reinf. For Retaining Wall 1m Length


Bar
mark Shape

No. of
Spacing bars

Dia

Length of Total
bar
length

a1

20

140

4.91

39.28

a2

4.91

39.28

c1

20

215

3.525

17.63

c2

12

300

10

1.000

10.00

d1

12

170

26

1.000

26.00

d2

13

1.000

13.00

e1

16

240

2.725

13.63

e2

12

300

1.000

9.00

10

1.000

4.00

s1

10

300

1.925

7.70

s2

10

300

1.000

7.00

s3

10

300

2.425

9.70

s4

10

300

1.000

1.00

s5

10

300

4.825

19.30

s6

10

300

15

1.000

15.00

TOTAL STEEL for( Foundation + Substructure) kg/m


TOTAL STEEL for Foundation kg/m
TOTAL STEEL for substructure kg/m
Steel for Foundation in kg/cu.m
Steel for substructure in kg/cu.m

c1+c2+e1+e2+f+s1+s2+s3+s4
a1+a2+d1+d2+s5+s6

Quantity

8.400
8.400

0.400
0.400

1.900
0.000
0.000

0.000
1.900

1.320
0.660
1.980

0.100
0.141
0.241

Total
Wt.kg/m wt(kg)

2.47

96.87

0.00

0.00

2.47

43.47

0.89

8.88

0.89

23.08

0.00

0.00

1.58

21.50

0.89

7.99

0.62

2.47

0.62

4.75

0.62

4.32

0.62

5.98

0.62

0.62

0.62

11.90

0.62

9.25

241.07
99.97
141.11
52.61
71.27

62.13156

196.1697

kg/cu.m
kg/cu.m

RCC Retaining Wall For Group II _ 5 to 6 m Ht. for 1m length & 1 no.
0.300

5.43
5.400

4.10
6.10

1.71
6

1.300

0.900
0.200
0.500

2.600
###
3

2.61

0.700

5.200

Sr.
No
1

Description

Unit

Nos

Length

Width

Depth

in ordinary soil

cum

1.00

5.40

2.10

Total
Plain cement concrete M 15 grade levelling
course below foundation and approach slab
complete as per Technical Specification
Sections 1700, 2100 and 2700.

Cum

1.00

5.40

0.10

1
1
1

1.00
1.00
1.00

5.20
1.70
2.60

0.50
0.100
0.100

Earthwork in Excavation of Foundation for


RCC Retaining wall in all types of soil complete
as per drawings and Technical Specifications
Clauses 304, 309 & 2903.

cum

Total
Providing & Casting in situ controlled Cement
Concrete for RCC Work in Retaining Wall
Open
Foundation
including
necessary
formwork, vibrating, curing and finishing. As
per MoRT&H technical specification section
1700.

Cum

Part - 1
Part - 2
Part - 3

cum
cum
cum

Part - 4

cum

Total
Structural cement concrete for reinforced
concrete grade M-30 for sub structure
including
formwork,
machinery
and
workmanship complete as per drawing and
Technical Specification Sections 1500, 1700
and 2200.

Cum

Part - 5
Part - 6

cum
cum

Total
Providing and fixing in position TMT HYSD
reinforcement complete as per drawing and
Technical Specification Section 1600.

Cum

Retaining Wall (Base Slab)


Retaining Wall (Stem)

M.T
M.T
Total

1.00

1
1

1.00
1.00

3.21
3.24

0.90

0.300
0.600

0.20

5.400
2.700

@ 40.25 kg/cu.m
@ 54.13 kg/cu.m

Cum

Reinf. For Retaining Wall 1m Length


Bar
mark Shape

No. of
Spacing bars

Dia

Length of Total
bar
length

a1

20

140

6.13

49.07

a2

6.13

49.07

c1

20

215

4.533

22.66

c2

12

300

13

1.000

13.00

d1

12

170

32

1.000

32.00

d2

16

1.000

16.00

e1

16

240

3.425

17.13

e2

12

300

12

1.000

12.00

10

1.000

4.00

s1

10

300

2.625

10.50

s2

10

300

1.000

9.00

s3

10

300

3.137

12.55

s4

10

300

1.000

3.00

s5

10

300

6.025

24.10

s6

10

300

18

1.000

18.00

TOTAL STEEL for( Foundation + Substructure) kg/m


TOTAL STEEL for Foundation kg/m
TOTAL STEEL for substructure kg/m
Steel for Foundation in kg/cu.m
Steel for substructure in kg/cu.m

c1+c2+e1+e2+f+s1+s2+s3+s4
a1+a2+d1+d2+s5+s6

Quantity

11.340
11.340

0.540
0.540

2.600
0.170
0.260

0.180
3.210

1.620
1.620
3.240

0.129
0.175
0.305

Total
Wt.kg/m wt(kg)

2.47

121.00

0.00

0.00

2.47

55.89

0.89

11.54

0.89

28.41

0.00

0.00

1.58

27.03

0.89

10.65

0.62

2.47

0.62

6.47

0.62

5.55

0.62

7.74

0.62

1.85

0.62

14.86

0.62

11.10

304.56
129.19
175.37
40.25
54.13

47.21855

247.8337

kg/cu.m
kg/cu.m

169450
169460
169459

62.754
62.635
62.6469
62.6945

20 OF 734

7
37
Sr.No

Exi ch.

Pr Ch.

Unit

Km.
178-193
New
New
New

Km.

NO

W(m)

H(m)

Width of
crash
barrier
m

1
1
1
1
1
1
2
1
1
2

4.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000

3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000

1
1
1

2.000
2.000
2.000

1
2
3
4
5
6
7
8
9
10

New
Reconstruction
Reconstruction
New
New
New

1.000
182+485
184+057
184+578
184+691
185+280
186+754
188+184
188+310
192+561

11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35

140-178
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

140+802
146+820
147+422
148+050
148+155
148+365
148+525
148+605
151+497
151+199
152+426
152+643
154+498
154+896
155+118
156+017
156+969
157+465
163+355
164+614
171+904
172+304
175+000
175+930
176+510

Pipe Culvert to Box culvert


178-193
36
New
178+440
178+840
37
New
38

New

178+917

Width of Median
side Kerb(One
Side)
m

0.5
0
0
0
0
0
0
0
0
0

0
4
4
4
4
4
4
4
4
4

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

2.000
2.000
2.000

0
0
0

4
4
4

0.5
0.5
0.5

Data for Proposed Box


Culvert (With Cushion)

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

Median
Width

SAI Consulting Engineers Pvt. Ltd.

21 OF 734

39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

179+275
179+418
179+725
179+842
180+005
180+425
180+765
181+775
181+870
182+440
182+745
183+120
183+332
183+558
183+757
184+312
185+164
185+501
185+817
186+121
186+479
186+638
186+874
187+248
187+447
187+656
187+937
188+050
188+739
188+898
189+168
189+398
189+940
190+208
190+597
191+007
191+307
191+802
192+028
192+259
192+734
193+525

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

81
82
83
84

150 to 178
New
New
New
New

150+875
151+675
151+704
152+000

1
1
1
1

3.000
3.000
2.000
2.000

3.000
3.000
2.000
2.000

0
0
0
0

4
4
4
4

0.5
0.5
0.5
0.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

22 OF 734

85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

152+436
152+622
153+450
156+415
156+514
157+196
157+770
158+477
159+080
159+332
159+890
159+905
160+670
160+866
161+450
162+085
162+712
163+715
163+861
164+055
164+070
164+200
164+596
164+606
164+660
165+050
165+354
165+550
165+980
165+985
166+105
166+285
166+705
166+941
166+952
167+354
167+620
167+684
167+694
168+100
168+497
168+734
168+885
169+005
169+175
169+320
169+459
169+660

1
2
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1

3.000
3.000
3.000
3.000
2.000
2.000
2.000
3.000
3.000
2.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
2.000
2.000
2.000
2.000
3.000
2.000
2.000
2.000
2.000

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

3.000
3.000
3.000
3.000
2.000
2.000
2.000
3.000
3.000
2.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
2.000
2.000
2.000
2.000
3.000
2.000
2.000
2.000
2.000

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

SAI Consulting Engineers Pvt. Ltd.

23 OF 734

133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

170+188
170+317
170+507
170+625
170+860
170+962
171+225
172+605
172+655
172+845
173+225
173+675
173+830
174+009
174+262
174+345
174+425
175+220
175+370
176+015
176+600
176+770
177+064
177+427
177+573

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
3.000
2.000
3.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
2.000

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
3.000
3.000
3.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
2.000

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

93+215
93+900
94+300
94+600
95+096
95+520

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

95+850
96+200
96+750
97+450
97+850
98+250
98+600
98+950
99+660
99+890
100+284
100+960
101+140
101+190
101+435
101+835

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

24 OF 734

New
New
New
New
New

101+880
102+100
102+485
102+865
103+100

1
1
1
1
1

2.000
2.000
2.000
2.000
2.000

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

2.000
2.000
2.000
2.000
2.000

0
0
0
0
0

4
4
4
4
4

0.5
0.5
0.5
0.5
0.5

SAI Consulting Engineers Pvt. Ltd.

25 OF 734

Depth of
Top Slab

Clear Height of
Box( Bottom of Top
Slab to Top of
Bottom of Slab)
m

0
0
0
0
0
0
0
0
0
0

4.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00

3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000

0.42
0.42
0.42
0.42
0.42
0.42
0.47
0.42
0.42
0.47

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00

3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000

0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47

0.5
0.5
0.5

0
0
0

2.00
2.00
2.00

2.000
2.000
2.000

0.25
0.25
0.25

Railing or Crash
Barrier Width
(footpath side)
m

Footpath
width (one
side)
m

2
2
2
2
2
2
2
2
2
2

7.500
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000

2
2
2

10.000
10.000
10.000

Nos of
Carriage Way
Carriageway Width ( One Side)

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

Clear
Span

SAI Consulting Engineers Pvt. Ltd.

26 OF 734

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000

0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25

2
2
2
2

10.000
10.000
10.000
10.000

0.5
0.5
0.5
0.5

0
0
0
0

3.00
3.00
2.00
2.00

3.000
3.000
2.000
2.000

0.42
0.42
0.25
0.25

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

27 OF 734

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

3.00
3.00
3.00
3.00
2.00
2.00
2.00
3.00
3.00
2.00
3.00
3.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
3.00
3.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
3.00
2.00
2.00
2.00
2.00
3.00
2.00
2.00
2.00
2.00

3.000
3.000
3.000
3.000
2.000
2.000
2.000
3.000
3.000
2.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
2.000
2.000
2.000
2.000
3.000
2.000
2.000
2.000
2.000

0.42
0.4
0.42
0.42
0.25
0.25
0.25
0.4
0.42
0.25
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.4
0.25
0.25
0.25
0.25

SAI Consulting Engineers Pvt. Ltd.

28 OF 734

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
3.00
3.00
2.00
3.00
3.00
3.00
2.00
2.00
2.00
2.00
2.00
2.00
3.00
2.00

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
3.000
3.000
3.000
3.000
3.000
2.000
2.000
2.000
2.000
2.000
2.000
3.000
2.000

0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.42
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00

2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000

0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25
0..25

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

29 OF 734

2
2
2
2
2

10.000
10.000
10.000
10.000
10.000

0.5
0.5
0.5
0.5
0.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

0
0
0
0
0

2.00
2.00
2.00
2.00
2.00

2.000
2.000
2.000
2.000
2.000

0..25
0..25
0..25
0..25
0..25

SAI Consulting Engineers Pvt. Ltd.

30 OF 734

Depth of
Proposed
Existing
Thickness of Thickness
Bottom
Formation
Ground Level
Wearing of Side Wall
Slab
Level ( Average)
( Average)
Coat
of Box
m
m
m
m
m

0.42
0.42
0.42
0.42
0.42
0.42
0.45
0.42
0.42
0.45

103.420
52.500
51.200
48.000
48.000
45.000
100.000
35.100
33.500
32.000

100.000

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.3
0.3
0.3

Slope of
Pitching

Slope of
Embankment

48.685
47.500
44.310
44.310
41.070
96.500
31.100
29.400
28.000

0.065
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075

0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42

1.5
2
2
2
2
2
2
2
2
2

1.5
2
2
2
2
2
2
2
2
2

33.705
35.000
34.803
36.874
36.76
36.166
35.678
35.434
32.2444
34.500
34.795
35.400
34.0454
33.178
33.3338
35.4864
33.5344
32.2615
36.684
42.000
49.500
45.900
35.750
41.000
38.200

31.200
31.010
32.050
33.200
33.240
33.160
33.250
33.150
31.010
30.380
31.790
31.390
31.300
30.650
30.000
32.900
30.900
30.000
34.170
37.900
45.220
41.910
31.780
37.000
34.270

0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075

0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

37.634
38.643

32.710
35.722

38.410

35.700

0.075
0.075
0.075

0.25
0.25
0.25

2
2
2

2
2
2

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

31 OF 734

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

37.300
36.860
37.580
38.290
39.892
41.672
43.290
51.000
49.990
56.170
56.520
40.067
54.750
53.960
52.790
50.600
45.450
45.240
42.100
40.520
39.440
38.970
38.770
40.600
45.385
48.605
53.148
34.750
34.440
34.930
36.102
37.110
39.095
40.074
45.898
48.188
41.428
38.400
36.206
33.130
30.840
30.064

32.415
33.100
34.000
33.992
35.400
38.800
40.540
46.900
46.820
48.400
52.200
37.443
51.775
47.665
48.450
47.697
42.300
41.169
39.545
37.738
36.214
35.250
35.000
38.076
42.242
45.966
50.890
31.400
30.879
31.300

0.42
0.42
0.3
0.3

39
34.1
33.4
33.35

35.010
30.050
30.460

33.4
34.587
37
38
36.5
36
36.45
35.8
32.7
30.45
28.305
26.8

30.410

0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075

0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

0.075
0.075
0.075
0.075

0.42
0.42
0.25
0.25

2
2
2
2

2
2
2
2

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

32 OF 734

0.42
0.42
0.42
0.42
0.3
0.3
0.3
0.42
0.42
0.3
0.42
0.42
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.42
0.42
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.42
0.3
0.3
0.3
0.3
0.42
0.3
0.3
0.3
0.3

36.3
35.9

32.35
31.9

39
37.5
33.2
32.8
33.5
36
37.8
35.6
35.5
36.9
35.7
34.9
35.3
36.2
37.2
37.1
37.4
38.2
38.1
41.9
41.9
41.9
43.3
45.2
46.7
51
51
52.5
54.4
57.4
55.3
55
52.2
52.3
52.8
52.7
56.45
60
62.7
64.1
62.3
62.3
62
60
57.2

35.08
34.51
30.23
29.83
29.51
31.94
34.9
31.61
31.51
33.93
32.74
31.911
32.3
33.3
34.17
34.18
34.5
35.3
35.17
38
36.8
38.9
40.39
42.3
43.75
48.1
48.1
49.6
51.45
54.433
52.4
52.1
49.3
49.388
49.9
49.74
53.52
56.7
59.74
61.186
58.31
59.356
59.3
57
54.017

0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

0.42
0.35
0.42
0.42
0.25
0.25
0.25
0.35
0.42
0.25
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.35
0.25
0.25
0.25
0.25

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
SAI Consulting Engineers Pvt. Ltd.

33 OF 734

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.42
0.42
0.3
0.42
0.42
0.42
0.3
0.3
0.3
0.3
0.3
0.3
0.42
0.3

59.4
57
54.6
53.8
54.5
54.65
51.3
44
44
43.6
43.7
40
36.7
36.9
37.9
38.6
35.4
34.8
35.8
35.8
38.6
39.1
44.3
44.5
46.5

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

39.644
39.035
39.549
40.271
40.119
39.28
39.548
38.743
39.354
38.73
39.358
38.532
38.758
39.251
38.753
38.8102
39.146
38.589
38.435
37.853
38.566

31.78
34
34.604
31.43
32.12
32.87
32.87
35.62
36.2
41.4
40.6
43.6

0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075

0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.42
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

36.214
36.975
36.489
36.953
36.15
37.018
36.836
36.495
36.234
36.381
36.004
35.75
35.882
36.19
36.2
36.206
36.1
36.046
35.65
35.67
35.583
35.398

0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075
0.075

0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

56.51
54.06
51.7
50.83
51.53
51.71
48.309
40.99
40.99
40.63
40.738
35.25
33.71

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

34 OF 734

0.3
0.3
0.3
0.3
0.3

38.656
38.934
38.23
39.748
39.048

35.157
35.386
35.608

0.075
0.075
0.075
0.075
0.075

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

0.25
0.25
0.25
0.25
0.25

2
2
2
2
2

2
2
2
2
2

SAI Consulting Engineers Pvt. Ltd.

35 OF 734

Projection of Height of
Bottom Slab Toe Wall

Width of
Toe Wall

Width of
Thickness
Thickness of
Thickness
approach No. of cell
of
inner wall
of PCC
slab
foothpath
m
m
m
m

0.9
0.9
0.9
0.9
0.9
0.9
0.3
0.9
0.9
0.3

1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5

1
1
1
1
1
1
2
1
1
2

0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

0.6
0.6
0.6

1.1
1.1
1.1

0.3
0.3
0.3

3.5
3.5
3.5

1
1
1

0
0
0

0
0
0

0.15
0.15
0.15

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

36 OF 734

0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6

1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

0.6
0.6
0.6
0.6

1.1
1.1
1.1
1.1

0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5

1
1
1
1

0
0
0
0

0
0
0
0

0.15
0.15
0.15
0.15

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

37 OF 734

0.6
0.3
0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6
0.6
0.6

1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

0
0.25
0
0
0
0
0
0.25
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.25
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

SAI Consulting Engineers Pvt. Ltd.

38 OF 734

0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6

1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6

1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5
3.5

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

39 OF 734

0.6
0.6
0.6
0.6
0.6

1.1
1.1
1.1
1.1
1.1

0.3
0.3
0.3
0.3
0.3

3.5
3.5
3.5
3.5
3.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

1
1
1
1
1

0
0
0
0
0

0
0
0
0
0

0.15
0.15
0.15
0.15
0.15

SAI Consulting Engineers Pvt. Ltd.

40 OF 734

BACK
FORNT
Height of PCC Width Thickness
Angle of
BATTERN BATTERN
Key
of Toe Wall of Apron
Skew
1 in
1 in
m
m
m

Width of
Curtain wall
for U/S side
m

Width of
Curtain wall
for D/S side
m

Depth of
Curtain wall
for U/S side
m

1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6

0
0
0
0
0
0
0
0
0
0

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15

1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2

0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7
0.7

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15

1.2
1.2
1.2

0.75
0.75
0.75

0.45
0.45
0.45

3
3
3

6
6
6

0
0
0

1.5
1.5
1.5

1.85
1.85
1.85

2.15
2.15
2.15

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

41 OF 734

1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15

1.2
1.2
1.2
1.2

0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45

3
3
3
3

6
6
6
6

0
0
0
0

1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

42 OF 734

1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15

SAI Consulting Engineers Pvt. Ltd.

43 OF 734

1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15

1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15
2.15

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

44 OF 734

1.2
1.2
1.2
1.2
1.2

0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45

3
3
3
3
3

6
6
6
6
6

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

0
0
0
0
0

1.5
1.5
1.5
1.5
1.5

1.85
1.85
1.85
1.85
1.85

2.15
2.15
2.15
2.15
2.15

SAI Consulting Engineers Pvt. Ltd.

45 OF 734

Depth of
Area of
Area of
Length of
Curtain wall Curtain wall Curtain wall Flexible Apron
for D/S side for U/S side for D/S side for U/S side
m
SQ.m
SQ.m
m

Length of
Flexible Apron
for D/S side
m

Thickness Thicknes
of Flexible s of Floor
Apron
Apron
m
m

Camber
%

2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175

3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.65
2.65
2.65

1.6925
1.6925
1.6925

2.175
2.175
2.175

3
3
3

6
6
6

0.75
0.75
0.75

0.45
0.45
0.45

2.5
2.5
2.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

46 OF 734

2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175

3
3
3
3

6
6
6
6

0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

47 OF 734

2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

SAI Consulting Engineers Pvt. Ltd.

48 OF 734

2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175
2.175

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

49 OF 734

2.65
2.65
2.65
2.65
2.65

1.6925
1.6925
1.6925
1.6925
1.6925

2.175
2.175
2.175
2.175
2.175

3
3
3
3
3

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

6
6
6
6
6

0.75
0.75
0.75
0.75
0.75

0.45
0.45
0.45
0.45
0.45

2.5
2.5
2.5
2.5
2.5

SAI Consulting Engineers Pvt. Ltd.

50 OF 734

side of
Cushion
RL of Top of Box
widening

2
2
2
2
2
2
2
2
2
2

0.300
0.695
0.580
0.570
0.570
0.810
0.330
0.880
0.980
0.830

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

-0.665
0.820
-0.417
0.504
0.350
-0.164
-0.742
-0.886
-1.936
0.950
-0.165
0.840
-0.425
-0.642
0.164
-0.584
-0.536
-0.909
-0.656
0.930
1.110
0.820
0.800
0.830
0.760

2
2
2

2.974
0.971
0.760

103.120
51.805
50.620
47.430
47.430
44.190
99.670
34.220
32.520
31.170
0.000
0.000
34.370
34.180
35.220
36.370
36.410
36.330
36.420
36.320
34.180
33.550
34.960
34.560
34.470
33.820
33.170
36.070
34.070
33.170
37.340
41.070
48.390
45.080
34.950
40.170
37.440
0.000
0.000
0.000
0.000
0.000
34.660
37.672
37.650

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

51 OF 734

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

2.935
1.810
1.630
2.348
2.542
0.922
0.800
2.150
1.220
5.820
2.370
0.674
1.025
4.345
2.390
0.953
1.200
2.121
0.605
0.832
1.276
1.770
1.820
0.574
1.193
0.689
0.308
1.400
1.611
1.680
0.752
0.573
0.145
0.124
7.448
10.238
3.028
0.650
1.556
0.730
0.585
1.314

34.365
35.050
35.950
35.942
37.350
40.750
42.490
48.850
48.770
50.350
54.150
39.393
53.725
49.615
50.400
49.647
44.250
43.119
41.495
39.688
38.164
37.200
36.950
40.026
44.192
47.916
52.840
33.350
32.829
33.250
35.350
36.537
38.950
39.950
38.450
37.950
38.400
37.750
34.650
32.400
30.255
28.750
0.000

2
2
2
2

0.870
0.930
0.990
0.990

38.130
33.170
32.410
32.360

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

52 OF 734

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

0.830
0.900
-3.120
0.800
1.040
1.020
1.020
0.890
0.940
0.950
0.870
0.870
1.020
1.010
1.039
1.050
0.950
1.080
0.970
0.950
0.950
0.980
0.780
1.980
1.050
0.960
0.950
1.000
0.950
0.950
0.950
1.000
1.017
0.950
0.950
0.950
0.962
0.950
-0.160
0.980
1.350
1.010
0.964
0.890
0.994
0.750
1.050
1.233

35.470
35.000
3.120
38.200
36.460
32.180
31.780
32.610
35.060
36.850
34.730
34.630
35.880
34.690
33.861
34.250
35.250
36.120
36.130
36.450
37.250
37.120
41.120
39.920
40.850
42.340
44.250
45.700
50.050
50.050
51.550
53.400
56.383
54.350
54.050
51.250
51.338
51.850
52.860
55.470
58.650
61.690
63.136
61.410
61.306
61.250
58.950
55.967

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

53 OF 734

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

0.940
0.990
0.950
1.020
1.020
0.990
1.041
#REF!
1.060
0.660
1.120
-3.858
-1.670
0.240
0.780
0.876
0.850
0.730
0.980
0.980
1.030
0.950
0.950
0.780
0.950

58.460
56.010
53.650
52.780
53.480
53.660
50.259
#REF!
42.940
42.940
42.580
43.858
38.370
36.660
37.120
37.724
34.550
34.070
34.820
34.820
37.570
38.150
43.350
43.720
45.550

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
DPR for Rehabilitation and Upgrading
Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

54 OF 734

2
2
2
2
2

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-1)

SAI Consulting Engineers Pvt. Ltd.

Box Data
Sr. NO.

Proposed
chainage (KM)

1
2
3
4
5
6
7
8

140-150
140+802
146+820
147+422
148+050
148+155
148+365
148+525
148+605

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26

150-178
150+875
151+199
151+497
151+675
151+704
152+000
152+426
152+436
152+622
152+643
153+450
154+498
154+896
155+118
156+017
156+415
156+514
156+969
157+196
157+465
157+770
158+477
159+080
159+332
159+890
159+905

Existing Chainagae
(KM)

No. of
Cell

Clear
Span

Clear
Height

Depth
Of Top
Slab

2
2
2
2
2
2
2
2

3
3
3
3
3
3
3
3

3
3
3
3
3
3
3
3

0.47
0.47
0.47
0.47
0.47
0.47
0.47
0.47

1
2
2
1
1
1
2
1
2
2
1
2
2
2
2
1
1
2
1
2
1
2
1
1
1
1

3
3
3
3
2
2
3
3
3
3
3
3
3
3
3
3
2
3
2
3
2
3
3
2
3
3

3
3
3
3
2
2
3
3
3
3
3
3
3
3
3
3
2
3
2
3
2
3
3
2
3
3

0.42
0.47
0.47
0.42
0.25
0.25
0.47
0.42
0.4
0.47
0.42
0.47
0.47
0.47
0.47
0.42
0.25
0.47
0.25
0.47
0.25
0.4
0.42
0.25
0.42
0.42

27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71

160+670
160+866
161+450
162+085
162+712
163+355
163+715
163+861
164+055
164+070
164+200
164+596
164+606
164+614
164+660
165+050
165+354
165+550
165+980
165+985
166+105
166+285
166+705
166+941
166+952
167+354
167+620
167+684
167+694
168+100
168+497
168+734
168+885
169+005
169+175
169+320
169+459
169+660
170+188
170+317
170+507
170+625
170+860
170+962
171+225

1
1
1
1
1
2
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1

2
2
2
2
2
3
2
2
2
2
2
3
3
3
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
2
2
2
2
3
2
2
2
2
2
2
2
2
2
2
2

2
2
2
2
2
3
2
2
2
2
2
3
3
3
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
2
2
2
2
3
2
2
2
2
2
2
2
2
2
2
2

0.25
0.25
0.25
0.25
0.25
0.47
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.47
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.4
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25

72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94

171+904
172+304
172+605
172+655
172+845
173+225
173+675
173+830
174+009
174+262
174+345
174+425
175+000
175+220
175+370
175+930
176+015
176+510
176+600
176+770
177+064
177+427
177+573

2
2
1
1
1
1
1
1
1
1
1
1
2
1
1
2
1
2
1
1
1
1
1

3
3
2
2
2
2
3
3
2
3
3
3
3
2
2
3
2
3
2
2
2
3
2

3
3
2
2
2
2
3
3
3
3
3
3
3
2
2
3
2
3
2
2
2
3
2

0.47
0.47
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.42
0.42
0.42
0.47
0.25
0.25
0.47
0.25
0.47
0.25
0.25
0.25
0.42
0.25

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

178-193
178+440
178+840
178+917
1
179+275
179+418
179+725
179+842
180+005
180+425
180+765
181+775
181+870
182+440
182+485
182+745
183+120
183+332
183+558
183+757

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

2
2
2
4
2
2
2
2
2
2
2
2
2
2
3
2
2
2
2
2

2
2
2
3
2
2
2
2
2
2
2
2
2
2
3
2
2
2
2
2

0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.25

21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55

184+057
184+312
184+578
184+691
185+164
185+280
185+501
185+817
186+121
186+479
186+638
186+754
186+874
187+248
187+447
187+656
187+937
188+050
188+184
188+310
188+739
188+898
189+168
189+398
189+940
190+208
190+597
191+007
191+307
191+802
192+028
192+259
192+561
192+734
193+525

1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1

3
2
3
3
2
3
2
2
2
2
2
3
2
2
2
2
2
2
3
3
2
2
2
2
2
2
2
2
2
2
2
2
3
2
2

3
2
3
3
2
3
2
2
2
2
2
3
2
2
2
2
2
2
3
3
2
2
2
2
2
2
2
2
2
2
2
2
3
2
2

0.42
0.25
0.42
0.42
0.25
0.42
0.25
0.25
0.25
0.25
0.25
0.47
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.47
0.25
0.25

Box Data

Proposed
Width of
Proposed
Depth of Thick.of Thick.of
No.of
Formatio
carriage Existing
Formatio
Bottom
Side
Inner Projection Carriage
n
way on G.L(D.S)
n Level
slab
wall
wall
way
Level(Ce
one side
(Edge)
ntre)
e
f
g
c
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.42

0.35
0.35
0.35
0.35
0.35
0.35
0.35
0.35

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

2
2
2
2
2
2
2
2

10
10
10
10
10
10
10
10

31.2
31.01
32.05
33.2
33.24
33.16
33.25
33.15

33.705
35
34.803
36.874
36.76
36.166
35.678
35.434

33.705
35
34.803
36.874
36.76
36.166
35.678
35.434

0.42
0.45
0.45
0.42
0.3
0.3
0.45
0.42
0.42
0.45
0.42
0.45
0.45
0.45
0.45
0.42
0.3
0.45
0.3
0.45
0.3
0.42
0.42
0.3
0.42
0.42

0.42
0.42
0.42
0.42
0.25
0.25
0.42
0.42
0.35
0.42
0.42
0.42
0.42
0.42
0.42
0.42
0.25
0.42
0.25
0.42
0.25
0.35
0.42
0.25
0.42
0.42

0
0.35
0.35
0
0
0
0.35
0
0.25
0.35
0
0.35
0.35
0.35
0.35
0
0
0.35
0
0.35
0
0.25
0
0
0
0

0.6
0.3
0.3
0.6
0.6
0.6
0.3
0.6
0.3
0.3
0.6
0.3
0.3
0.3
0.3
0.6
0.6
0.3
0.6
0.3
0.6
0.3
0.6
0.6
0.6
0.6

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10

35.01
30.38
31.01
30.05
30.46
30.41
31.79
32.35
31.9
31.39
0
31.3
30.65
30
32.9
35.08
34.51
30.9
30.23
30
29.83
29.51
31.94
34.9
31.61
31.51

39
34.5
32.2444
34.1
33.4
33.35
34.795
36.3
35.9
35.4
0
34.0454
33.178
33.3338
35.4864
39
37.5
33.5344
33.2
32.2615
32.8
33.5
36
37.8
35.6
35.5

39
34.5
32.2444
34.1
33.4
33.35
34.795
36.3
35.9
35.4
0
34.0454
33.178
33.3338
35.4864
39
37.5
33.5344
33.2
32.2615
32.8
33.5
36
37.8
35.6
35.5

0.3
0.3
0.3
0.3
0.3
0.45
0.3
0.3
0.3
0.3
0.3
0.42
0.42
0.45
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.42
0.3
0.3
0.3
0.3
0.42
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.35
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25

0
0
0
0
0
0.35
0
0
0
0
0
0
0
0.35
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.25
0
0
0
0
0
0
0
0
0
0
0

0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10

33.93
32.74
31.911
32.3
33.3
34.17
34.17
34.18
34.5
35.3
35.17
38
36.8
37.9
38.9
40.39
42.3
43.75
48.1
48.1
49.6
51.45
54.433
52.4
52.1
49.3
49.388
49.9
49.74
53.52
56.7
59.74
61.186
58.31
59.356
59.3
57
54.017
56.51
54.06
51.7
50.83
51.53
51.71
48.309

36.9
35.7
34.9
35.3
36.2
36.684
37.2
37.1
37.4
38.2
38.1
41.9
41.9
42
41.9
43.3
45.2
46.7
51
51
52.5
54.4
57.4
55.3
55
52.2
52.3
52.8
52.7
56.45
60
62.7
64.1
62.3
62.3
62
60
57.2
59.4
57
54.6
53.8
54.5
54.65
51.3

36.9
35.7
34.9
35.3
36.2
36.684
37.2
37.1
37.4
38.2
38.1
41.9
41.9
42
41.9
43.3
45.2
46.7
51
51
52.5
54.4
57.4
55.3
55
52.2
52.3
52.8
52.7
56.45
60
62.7
64.1
62.3
62.3
62
60
57.2
59.4
57
54.6
53.8
54.5
54.65
51.3

0.45
0.45
0.3
0.3
0.3
0.3
0.42
0.42
0.3
0.42
0.42
0.42
0.45
0.3
0.3
0.45
0.3
0.45
0.3
0.3
0.3
0.42
0.3

0.42
0.42
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.42
0.42
0.42
0.42
0.25
0.25
0.42
0.25
0.42
0.25
0.25
0.25
0.42
0.25

0.35
0.35
0
0
0
0
0
0
0
0
0
0
0.35
0
0
0.35
0
0.35
0
0
0
0
0

0.3
0.3
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6
0.3
0.6
0.3
0.6
0.6
0.6
0.6
0.6

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10

45.22
41.91
40.99
40.99
40.63
40.738
35.25
33.71
31.78
34
34.604
31.43
31.78
32.12
32.87
37
32.87
34.27
35.62
36.2
41.4
40.6
43.6

49.5
45.9
44
44
43.6
43.7
40
36.7
36.9
37.9
38.6
35.4
35.75
34.8
35.8
41
35.8
38.2
38.6
39.1
44.3
44.5
46.5

49.5
45.9
44
44
43.6
43.7
40
36.7
36.9
37.9
38.6
35.4
35.75
34.8
35.8
41
35.8
38.2
38.6
39.1
44.3
44.5
46.5

0.3
0.3
0.3
0.42
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.42
0.3
0.3
0.3
0.3
0.3

0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.25

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.6
0.6
0.6
0.9
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.9
0.6
0.6
0.6
0.6
0.6

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10
10
10
7.5
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10

32.71
35.722
35.7
100
32.415
33.1
34
33.992
35.4
38.8
40.54
46.9
46.82
48.4
48.685
52.2
37.443
51.775
47.665
48.45

37.634
38.643
38.41
103.42
37.3
36.86
37.58
38.29
39.892
41.672
43.29
51
49.99
56.17
52.5
56.52
40.067
54.75
53.96
52.79

37.634
38.643
38.41
103.42
37.3
36.86
37.58
38.29
39.892
41.672
43.29
51
49.99
56.17
52.5
56.52
40.067
54.75
53.96
52.79

0.42
0.3
0.42
0.42
0.3
0.42
0.3
0.3
0.3
0.3
0.3
0.45
0.3
0.3
0.3
0.3
0.3
0.3
0.42
0.42
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.45
0.3
0.3

0.42
0.25
0.42
0.42
0.25
0.42
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.42
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.42
0.25
0.25

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.9
0.6
0.9
0.9
0.6
0.9
0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6
0.6
0.6
0.6
0.6
0.9
0.9
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.3
0.6
0.6

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10

47.5
51.2
51.2
47.697
50.6
50.6
44.31
48
48
44.31
48
48
42.3
45.45
45.45
41.07
45
45
41.169
45.24
45.24
39.545
42.1
42.1
37.738
40.52
40.52
36.214
39.44
39.44
35.25
38.97
38.97
96.5
100
100
35
38.77
38.77
38.076
40.6
40.6
42.242 45.3854 45.3854
45.966 48.6052 48.6052
50.89 53.1478 53.1478
31.4
34.75
34.75
31.1
35.1
35.1
29.4
33.5
33.5
30.879
34.44
34.44
31.3
34.93
34.93
33.4
36.102
36.102
34.587
37.11
37.11
37
39.095
39.095
38
40.074
40.074
36.5
45.898
45.898
36
48.188
48.188
36.45
41.428
41.428
35.8
38.4
38.4
32.7
36.206
36.206
30.45
33.13
33.13
28
32
32
28.305
30.84
30.84
26.8
30.064
30.064

Camber
LHS
RHS
Directio
LHS
RHS
(Main
(Main
n Of
(Service
(Service
Carriage
Carriage
flow
Road)
Road)
way)
way)

RL of
Top of
Box

Earth
cushion

Skew
Angle

34.37
34.18
35.22
36.37
36.41
36.33
36.42
36.32

-0.665
0.82
-0.417
0.504
0.35
-0.164
-0.742
-0.886

0
0
0
0
0
0
0
0

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

New
New
New
New
New
New
New
New

38.13
33.55
34.18
33.17
32.41
32.36
34.96
35.47
35
34.56
3.12
34.47
33.82
33.17
36.07
38.2
36.46
34.07
32.18
33.17
31.78
32.61
35.06
36.85
34.73
34.63

0.87
0.95
-1.9356
0.93
0.99
0.99
-0.165
0.83
0.9
0.84
-3.12
-0.4246
-0.642
0.1638
-0.5836
0.8
1.04
-0.5356
1.02
-0.9085
1.02
0.89
0.94
0.95
0.87
0.87

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

Remarks

35.88
34.69
33.861
34.25
35.25
37.34
36.12
36.13
36.45
37.25
37.12
41.12
39.92
41.07
40.85
42.34
44.25
45.7
50.05
50.05
51.55
53.4
56.383
54.35
54.05
51.25
51.338
51.85
52.86
55.47
58.65
61.69
63.136
61.41
61.306
61.25
58.95
55.967
58.46
56.01
53.65
52.78
53.48
53.66
50.259

1.02
1.01
1.039
1.05
0.95
-0.656
1.08
0.97
0.95
0.95
0.98
0.78
1.98
0.93
1.05
0.96
0.95
1
0.95
0.95
0.95
1
1.017
0.95
0.95
0.95
0.962
0.95
-0.16
0.98
1.35
1.01
0.964
0.89
0.994
0.75
1.05
1.233
0.94
0.99
0.95
1.02
1.02
0.99
1.041

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

48.39
45.08
#REF!
42.94
42.94
42.58
43.858
38.37
36.66
37.12
37.724
34.55
34.95
34.07
34.82
40.17
34.82
37.44
37.57
38.15
43.35
43.72
45.55

1.11
0.82
#REF!
1.06
0.66
1.12
-3.858
-1.67
0.24
0.78
0.876
0.85
0.8
0.73
0.98
0.83
0.98
0.76
1.03
0.95
0.95
0.78
0.95

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

34.66
37.672
37.65
103.12
34.365
35.05
35.95
35.942
37.35
40.75
42.49
48.85
48.77
50.35
51.805
54.15
39.393
53.725
49.615
50.4

2.974
0.971
0.76
0.3
2.935
1.81
1.63
2.348
2.542
0.922
0.8
2.15
1.22
5.82
0.695
2.37
0.674
1.025
4.345
2.39

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

50.62
49.647
47.43
47.43
44.25
44.19
43.119
41.495
39.688
38.164
37.2
99.67
36.95
40.026
44.192
47.916
52.84
33.35
34.22
32.52
32.829
33.25
35.35
36.537
38.95
39.95
38.45
37.95
38.4
37.75
34.65
32.4
31.17
30.255
28.75

0.58
0.953
0.57
0.57
1.2
0.81
2.121
0.605
0.832
1.276
1.77
0.33
1.82
0.574
1.1934
0.6892
0.3078
1.4
0.88
0.98
1.611
1.68
0.752
0.573
0.145
0.124
7.448
10.238
3.028
0.65
1.556
0.73
0.83
0.585
1.314

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5

New
New
New
New
New
Reconstructio
n
New
New
New
New
New
Reconstructio
n
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

67 of 734

Box Culvert
Description

Sr.
No
1

excavation

Unit

m.
Pro.Ch
Length Width

1.000
Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 4.0
Nos

cum
cum
cum
cum

1
2
4

18.30
1.18
5.19

6.94
6.94
5.40

0.87
0.93
2.10

cum
cum
cum
cum
cum
cum

1
2
2
4
2

18.30
1.10
0.40
5.19
18.00

6.94
6.94
6.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

Part - 2

cum
cum

4
4

5.19
5.19

5.20
1.70

0.50
0.10

Part - 3

cum

5.19

2.60

0.10

Part - 4

cum

5.19

0.90

0.20

Part - 5
Part - 6

cum
cum

4
4

5.19
5.19

0.30
0.60

4.41
2.20

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

18.00
18.00
1.08
18.00
18.00
0.50
4.84
4.84
18.00
18.00

6.64
0.42
6.64
4.84
0.01125
15.22
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.

PCC
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab
3
RCC
Return
wall

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

RCC Box

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

SAI Consulting Engineers Pvt. Ltd.

68 of 734

Box Culvert
Description

Sr.
No
5

HYSD

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

50mm Bc

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab

12mm MA

Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

Approch sl

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.

DS

Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.

1 no. per 5.0m


9
FT Exp Jt

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

Unit

1 x 4.0
Nos

m.
Pro.Ch
Length Width

1.000
Depth

Cum

Kg
Kg
Kg
Kg
T

65
70
120
2

152.58
121.54
1.21
0.00

Cum
Cum

1
2

15.00
15.00

4.84
3.50

Sqm

15.00

4.84

cum

18.00

3.50

No
No

6.64

Rmt

18.0

0.05
0.05

0.3

SAI Consulting Engineers Pvt. Ltd.

69 of 734

Sr.
No
10
Earthwork
in
excavation

11
PCC in toe
wall &
Curtain
wall &
appron

Filter
below
Stone
pitching

12

13

14

15

Box Culvert
Description

Unit

m.
Pro.Ch
Length Width

1.000
Depth

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

8.05
15.10
15.10
40.68
15.10
15.10

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

8.05
8.05
15.10
15.10
40.68

0.75
0.30

0.20
1.10
1.693
2.175
0.15

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.19
18.00
31.80

0.6
0.6

3.108
3.840

cum
cum

41.08

cum
cum
cum
cum

2
1
1

40.68
15.10
15.10

cum
cum

40.68

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

16

1 x 4.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

3.00
6.00

1.30
2.15
2.65
0.45
0.75
0.75

0.3

3.00
6.00

0.30
0.75
0.75

0.80

4.84

SAI Consulting Engineers Pvt. Ltd.

70 of 734

Box Culvert
Description

Sr.
No
17

Unit

Weep Holes
Return wall
Side wall of box

1 x 4.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch
Length Width

5.19
18.0

1.000
Depth

3.91
3.00

Total
18

19

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

17

5.19

3.420

SAI Consulting Engineers Pvt. Ltd.

71 of 734

km.
Quantity

110.49
15.23
235.42
361.14

19.05
2.30
0.83
16.82
19.71
58.71

53.98
3.53
5.40
3.74
66.64
27.45
27.45
54.90

50.20
45.36
7.15
36.59
0.81
7.61
1.21
0.00
0.00
4.86
DPR for Rehabilitation and Upgrading
Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

72 of 734

km.
Quantity
152.58

9917.45
8507.76
145.20
0.00
18.57

3.63
5.25
8.88

177.60

37.80
37.80

4
4

36.00

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

73 of 734

km.
Quantity

31.41
48.70
74.03
36.61
33.98
67.95
292.67

4.83
10.63
25.56
32.84
12.20
86.07

38.71
82.94
127.22
127.22

49.29
49.29

24.41
33.98
67.95
126.33

65.08
65.08
0

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

74 of 734

km.
Quantity

82
108
190

603.49

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

75 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.69

5.94
5.94
5.40

0.87
0.93
2.10

135.91
13.04
348.82
497.77

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
7.69
22.00

5.94
5.94
5.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

23.43
1.97
0.71
24.92
24.09
75.12

Part - 2

cum
cum

4
4

7.69
7.69

5.20
1.70

0.50
0.10

79.98
5.23

Part - 3

cum

7.69

2.60

0.10

8.00

Part - 4

cum

7.69

0.90

0.20

5.54

Part - 5
Part - 6

cum
cum

4
4

7.69
7.69

0.30
0.60

4.80
2.40

98.74
44.32
44.32
88.63

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.64
0.42
5.64
3.84
0.01125
19.22
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 182+485
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

61.59
65.52
6.07
41.93
1.17
9.61
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

76 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 182+485
Length Width Depth

Cum

km.
Quantity
192.91

Kg
Kg
Kg
Kg
T

75
75
120
2

192.91
187.37
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.64

4
4

Rmt

22.0

44.00

14468.44
14053.09
115.20
0.00
28.64

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

77 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 182+485
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.69
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

3.503
3.840

64.64
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

78 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 182+485
Length Width Depth

7.69
26.0

4.31
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

134
156
290

26

7.69

3.215

1285.61

SAI Consulting Engineers Pvt. Ltd.

79 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.46

5.94
5.94
5.40

0.87
0.93
2.10

135.91
13.04
338.39
487.34

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
7.46
22.00

5.94
5.94
5.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

23.43
1.97
0.71
24.17
24.09
74.37

Part - 2

cum
cum

4
4

7.46
7.46

5.20
1.70

0.50
0.10

77.58
5.07

Part - 3

cum

7.46

2.60

0.10

7.76

Part - 4

cum

7.46

0.90

0.20

5.37

Part - 5
Part - 6

cum
cum

4
4

7.46
7.46

0.30
0.60

4.69
2.34

95.79
41.96
41.96
83.93

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.64
0.42
5.64
3.84
0.01125
18.76
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 184+057
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

61.59
65.52
6.07
41.93
1.17
9.38
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

80 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 184+057
Length Width Depth

Cum

km.
Quantity
192.68

Kg
Kg
Kg
Kg
T

75
75
120
2

192.68
179.71
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.64

4
4

Rmt

22.0

44.00

14451.19
13478.36
115.20
0.00
28.04

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

81 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 184+057
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.46
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

3.388
3.840

60.65
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

82 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 184+057
Length Width Depth

7.46
26.0

4.19
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

126
156
282

26

7.46

3.700

1435.30

SAI Consulting Engineers Pvt. Ltd.

83 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.44

5.94
5.94
5.40

0.87
0.93
2.10

135.91
13.04
337.48
486.43

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
7.44
22.00

5.94
5.94
5.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

23.43
1.97
0.71
24.11
24.09
74.31

Part - 2

cum
cum

4
4

7.44
7.44

5.20
1.70

0.50
0.10

77.38
5.06

Part - 3

cum

7.44

2.60

0.10

7.74

Part - 4

cum

7.44

0.90

0.20

5.36

Part - 5
Part - 6

cum
cum

4
4

7.44
7.44

0.30
0.60

4.68
2.34

95.53
41.76
41.76
83.52

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.64
0.42
5.64
3.84
0.01125
18.72
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 184+578
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

61.59
65.52
6.07
41.93
1.17
9.36
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

84 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 184+578
Length Width Depth

Cum

km.
Quantity
192.66

Kg
Kg
Kg
Kg
T

75
75
120
2

192.66
179.05
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.64

4
4

Rmt

22.0

44.00

14449.69
13428.83
115.20
0.00
27.99

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

85 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 184+578
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.44
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

3.378
3.840

60.31
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

86 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 184+578
Length Width Depth

7.44
26.0

4.18
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

126
156
282

26

7.44

3.690

1427.59

SAI Consulting Engineers Pvt. Ltd.

87 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.44

5.94
5.94
5.40

0.87
0.93
2.10

135.91
13.04
337.48
486.43

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
7.44
22.00

5.94
5.94
5.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

23.43
1.97
0.71
24.11
24.09
74.31

Part - 2

cum
cum

4
4

7.44
7.44

5.20
1.70

0.50
0.10

77.38
5.06

Part - 3

cum

7.44

2.60

0.10

7.74

Part - 4

cum

7.44

0.90

0.20

5.36

Part - 5
Part - 6

cum
cum

4
4

7.44
7.44

0.30
0.60

4.68
2.34

95.53
41.76
41.76
83.52

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.64
0.42
5.64
3.84
0.01125
18.72
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 184+691
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

61.59
65.52
6.07
41.93
1.17
9.36
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

88 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 184+691
Length Width Depth

Cum

km.
Quantity
192.66

Kg
Kg
Kg
Kg
T

75
75
120
2

192.66
179.05
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.64

4
4

Rmt

22.0

44.00

14449.69
13428.83
115.20
0.00
27.99

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

89 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 184+691
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.44
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

3.378
3.840

60.31
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

90 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 184+691
Length Width Depth

7.44
26.0

4.18
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

126
156
282

26

7.44

3.690

1427.59

SAI Consulting Engineers Pvt. Ltd.

91 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.94
5.94
5.40

0.87
0.93
2.10

135.91
13.04
285.77
434.72

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.94
5.94
5.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

23.43
1.97
0.71
20.41
24.09
70.61

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.64
0.42
5.64
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 185+280
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

61.59
65.52
6.07
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

92 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 185+280
Length Width Depth

Cum

km.
Quantity
191.52

Kg
Kg
Kg
Kg
T

75
75
120
2

191.52
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.64

4
4

Rmt

22.0

44.00

14364.19
10724.81
115.20
0.00
25.20

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

93 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 185+280
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

94 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 185+280
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

95 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.06

7.74
7.74
5.40

0.90
0.90
2.10

183.21
16.44
320.24
519.89

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
7.06
22.00

7.74
7.74
7.74
5.40
3.65

0.15
0.15
0.15
0.15
0.15

30.53
2.46
0.93
22.87
24.09
80.89

Part - 2

cum
cum

4
4

7.06
7.06

5.20
1.70

0.50
0.10

73.42
4.80

Part - 3

cum

7.06

2.60

0.10

7.34

Part - 4

cum

7.06

0.90

0.20

5.08

Part - 5
Part - 6

cum
cum

4
4

7.06
7.06

0.30
0.60

4.49
2.24

90.65
38.02
38.02
76.04

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
6.84
6.84
26.00
26.00

7.44
0.42
7.44
6.84
0.01125
17.96
0.125
0.75
0.00
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 186+754
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

87.05
65.52
7.53
83.58
2.34
8.98
1.71
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

96 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 186+754
Length Width Depth

Cum

km.
Quantity
262.03

Kg
Kg
Kg
Kg
T

75
75
120
2

262.03
166.69
1.71
0.00

Cum
Cum

1
2

20.00
20.00

6.84
3.50

Sqm

20.00

6.84

cum

22.00

3.50

No
No

7.44

4
4

Rmt

22.0

44.00

19651.94
12501.50
205.20
0.00
32.36

0.05
0.05

6.84
7.00
13.84

276.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

97 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 186+754
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
20.72
20.72
74.40
20.72
20.72

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
20.72
20.72
74.40

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.06
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

74.40
20.72
20.72

cum
cum

74.40

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

42.49
66.82
101.58
66.96
46.62
93.24
417.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.54
14.38
35.07
45.07
22.32
123.37

0.6
0.6

3.188
3.920

54.01
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

44.64
46.62
93.24
184.50

0.80

119.03
119.03

3.00
6.00

3.00
6.00

6.84

SAI Consulting Engineers Pvt. Ltd.

98 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 186+754
Length Width Depth

7.06
26.0

3.99
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

114
156
270

26

7.06

3.500

1284.92

SAI Consulting Engineers Pvt. Ltd.

99 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.94
5.94
5.40

0.87
0.93
2.10

135.91
13.04
285.77
434.72

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.94
5.94
5.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

23.43
1.97
0.71
20.41
24.09
70.61

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.64
0.42
5.64
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 188+184
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

61.59
65.52
6.07
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

100 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 188+184
Length Width Depth

Cum

km.
Quantity
191.52

Kg
Kg
Kg
Kg
T

75
75
120
2

191.52
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.64

4
4

Rmt

22.0

44.00

14364.19
10724.81
115.20
0.00
25.20

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

101 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 188+184
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

102 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 188+184
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

103 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.94
5.94
5.40

0.87
0.93
2.10

135.91
13.04
285.77
434.72

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.94
5.94
5.94
5.40
3.65

0.15
0.15
0.15
0.15
0.15

23.43
1.97
0.71
20.41
24.09
70.61

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.64
0.42
5.64
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 188+310
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

61.59
65.52
6.07
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

104 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 188+310
Length Width Depth

Cum

km.
Quantity
191.52

Kg
Kg
Kg
Kg
T

75
75
120
2

191.52
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.64

4
4

Rmt

22.0

44.00

14364.19
10724.81
115.20
0.00
25.20

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

105 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 188+310
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

106 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 188+310
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

107 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

7.74
7.74
5.40

0.90
0.90
2.10

183.21
16.44
290.30
489.95

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

7.74
7.74
7.74
5.40
3.65

0.15
0.15
0.15
0.15
0.15

30.53
2.46
0.93
20.74
24.09
78.75

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
6.84
6.84
26.00
26.00

7.44
0.42
7.44
6.84
0.01125
16.64
0.125
0.75
0.00
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 192+561
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

87.05
65.52
7.53
83.58
2.34
8.32
1.71
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

108 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 192+561
Length Width Depth

Cum

km.
Quantity
261.37

Kg
Kg
Kg
Kg
T

75
75
120
2

261.37
146.04
1.71
0.00

Cum
Cum

1
2

20.00
20.00

6.84
3.50

Sqm

20.00

6.84

cum

22.00

3.50

No
No

7.44

4
4

Rmt

22.0

44.00

19602.44
10952.64
205.20
0.00
30.76

0.05
0.05

6.84
7.00
13.84

276.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

109 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 192+561
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
20.72
20.72
74.40
20.72
20.72

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
20.72
20.72
74.40

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

74.40
20.72
20.72

cum
cum

74.40

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

42.49
66.82
101.58
66.96
46.62
93.24
417.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.54
14.38
35.07
45.07
22.32
123.37

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

44.64
46.62
93.24
184.50

0.80

119.03
119.03

3.00
6.00

3.00
6.00

6.84

SAI Consulting Engineers Pvt. Ltd.

110 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 192+561
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

111 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.07

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
229.98
438.65

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
5.07
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
16.43
24.09
75.98

Part - 2

cum
cum

4
4

5.07
5.07

5.20
1.70

0.50
0.10

52.73
3.45

Part - 3

cum

5.07

2.60

0.10

5.27

Part - 4

cum

5.07

0.90

0.20

3.65

Part - 5
Part - 6

cum
cum

4
4

5.07
5.07

0.30
0.60

3.49
1.75

65.10
21.25
21.25
42.50

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
14.33
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 140+802
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.17
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

112 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 140+802
Length Width Depth

Cum

km.
Quantity
296.24

Kg
Kg
Kg
Kg
T

75
75
120
2

296.24
107.60
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22217.79
8069.67
215.70
0.00
30.50

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

113 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 140+802
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.07
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.193
3.920

26.68
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

114 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 140+802
Length Width Depth

5.07
26.0

3.00
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

62
156
218

26

5.07

2.505

660.42

SAI Consulting Engineers Pvt. Ltd.

115 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 146+820
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

116 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 146+820
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

117 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 146+820
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

118 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 146+820
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

119 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.57

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
252.47
461.15

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
5.57
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
18.03
24.09
77.58

Part - 2

cum
cum

4
4

5.57
5.57

5.20
1.70

0.50
0.10

57.89
3.78

Part - 3

cum

5.57

2.60

0.10

5.79

Part - 4

cum

5.57

0.90

0.20

4.01

Part - 5
Part - 6

cum
cum

4
4

5.57
5.57

0.30
0.60

3.74
1.87

71.47
24.98
24.98
49.97

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
15.32
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 147+422
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.66
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

120 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 147+422
Length Width Depth

Cum

km.
Quantity
296.73

Kg
Kg
Kg
Kg
T

75
75
120
2

296.73
121.43
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22254.99
9107.59
215.70
0.00
31.58

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

121 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 147+422
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.57
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.441
3.920

32.60
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

122 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 147+422
Length Width Depth

5.57
26.0

3.25
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

74
156
230

26

5.57

2.753

796.81

SAI Consulting Engineers Pvt. Ltd.

123 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.41

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
336.03
544.70

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
7.41
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
24.00
24.09
83.55

Part - 2

cum
cum

4
4

7.41
7.41

5.20
1.70

0.50
0.10

77.04
5.04

Part - 3

cum

7.41

2.60

0.10

7.70

Part - 4

cum

7.41

0.90

0.20

5.33

Part - 5
Part - 6

cum
cum

4
4

7.41
7.41

0.30
0.60

4.66
2.33

95.12
41.44
41.44
82.88

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
19.01
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 148+050
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
9.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

124 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 148+050
Length Width Depth

Cum

km.
Quantity
298.58

Kg
Kg
Kg
Kg
T

75
75
120
2

298.58
178.00
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22393.14
13349.73
215.70
0.00
35.96

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

125 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 148+050
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.41
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

3.362
3.920

59.76
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

126 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 148+050
Length Width Depth

7.41
26.0

4.17
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

124
156
280

26

7.41

3.674

1415.28

SAI Consulting Engineers Pvt. Ltd.

127 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.10

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
322.06
530.73

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
7.10
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
23.00
24.09
82.55

Part - 2

cum
cum

4
4

7.10
7.10

5.20
1.70

0.50
0.10

73.84
4.83

Part - 3

cum

7.10

2.60

0.10

7.38

Part - 4

cum

7.10

0.90

0.20

5.11

Part - 5
Part - 6

cum
cum

4
4

7.10
7.10

0.30
0.60

4.51
2.25

91.16
38.40
38.40
76.81

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
18.39
0.4
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 148+155
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall of median opening
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

1.075
0.3
3.00

91.14
65.52
7.89
87.86
2.34
19.77
5.75
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

128 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 148+155
Length Width Depth

Cum

km.
Quantity
308.84

Kg
Kg
Kg
Kg
T

75
75
120
2

308.84
167.97
5.75
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

23163.11
12597.89
690.24
0.00
36.45

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

129 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 148+155
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.10
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

3.208
3.920

54.66
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

130 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 148+155
Length Width Depth

7.10
26.0

4.01
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

114
156
270

26

7.10

3.520

1299.58

SAI Consulting Engineers Pvt. Ltd.

131 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.07

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
275.43
484.10

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.07
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
19.67
24.09
79.22

Part - 2

cum
cum

4
4

6.07
6.07

5.20
1.70

0.50
0.10

63.15
4.13

Part - 3

cum

6.07

2.60

0.10

6.31

Part - 4

cum

6.07

0.90

0.20

4.37

Part - 5
Part - 6

cum
cum

4
4

6.07
6.07

0.30
0.60

3.99
2.00

77.96
29.10
29.10
58.20

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.33
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 148+365
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.17
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

132 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 148+365
Length Width Depth

Cum

km.
Quantity
297.24

Kg
Kg
Kg
Kg
T

75
75
120
2

297.24
136.16
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22292.94
10212.07
215.70
0.00
32.72

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

133 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 148+365
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.07
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.694
3.920

39.25
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

134 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 148+365
Length Width Depth

6.07
26.0

3.50
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

86
156
242

26

6.07

3.006

949.13

SAI Consulting Engineers Pvt. Ltd.

135 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
4.92

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
222.99
431.66

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
4.92
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
15.93
24.09
75.48

Part - 2

cum
cum

4
4

4.92
4.92

5.20
1.70

0.50
0.10

51.13
3.34

Part - 3

cum

4.92

2.60

0.10

5.11

Part - 4

cum

4.92

0.90

0.20

3.54

Part - 5
Part - 6

cum
cum

4
4

4.92
4.92

0.30
0.60

3.42
1.71

63.12
20.15
20.15
40.30

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
14.02
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 148+525
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.01
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

136 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 148+525
Length Width Depth

Cum

km.
Quantity
296.08

Kg
Kg
Kg
Kg
T

75
75
120
2

296.08
103.42
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22206.24
7756.42
215.70
0.00
30.18

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

137 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 148+525
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.92
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.116
3.920

24.96
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

138 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 148+525
Length Width Depth

4.92
26.0

2.92
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

58
156
214

26

4.92

2.428

620.67

SAI Consulting Engineers Pvt. Ltd.

139 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
4.63

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
209.93
418.60

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
4.63
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
14.99
24.09
74.54

Part - 2

cum
cum

4
4

4.63
4.63

5.20
1.70

0.50
0.10

48.13
3.15

Part - 3

cum

4.63

2.60

0.10

4.81

Part - 4

cum

4.63

0.90

0.20

3.33

Part - 5
Part - 6

cum
cum

4
4

4.63
4.63

0.30
0.60

3.27
1.64

59.42
18.17
18.17
36.34

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
13.45
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 148+605
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
6.72
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

140 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 148+605
Length Width Depth

Cum

km.
Quantity
295.80

Kg
Kg
Kg
Kg
T

75
75
120
2

295.80
95.76
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22184.64
7182.05
215.70
0.00
29.58

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

141 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 148+605
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.63
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

1.972
3.920

21.90
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

142 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 148+605
Length Width Depth

4.63
26.0

2.78
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

52
156
208

26

4.63

2.284

549.66

SAI Consulting Engineers Pvt. Ltd.

143 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
2.53

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
114.71
323.38

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
2.53
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
8.19
24.09
67.74

Part - 2

cum
cum

4
4

2.53
2.53

5.20
1.70

0.50
0.10

26.30
1.72

Part - 3

cum

2.53

2.60

0.10

2.63

Part - 4

cum

2.53

0.90

0.20

1.82

Part - 5
Part - 6

cum
cum

4
4

2.53
2.53

0.30
0.60

2.22
1.11

32.47
6.74
6.74
13.48

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
9.25
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 151+497
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
4.62
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

144 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 151+497
Length Width Depth

Cum

km.
Quantity
293.70

Kg
Kg
Kg
Kg
T

75
75
120
2

293.70
45.95
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22027.20
3446.61
215.70
0.00
25.69

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

145 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 151+497
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

2.53
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

0.922
3.920

5.60
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

146 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 151+497
Length Width Depth

2.53
26.0

1.73
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

18
156
174

26

2.53

1.234

162.32

SAI Consulting Engineers Pvt. Ltd.

147 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 151+199
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

148 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 151+199
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

149 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 151+199
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

150 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 151+199
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

151 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.07

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
275.34
484.01

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.07
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
19.67
24.09
79.22

Part - 2

cum
cum

4
4

6.07
6.07

5.20
1.70

0.50
0.10

63.13
4.13

Part - 3

cum

6.07

2.60

0.10

6.31

Part - 4

cum

6.07

0.90

0.20

4.37

Part - 5
Part - 6

cum
cum

4
4

6.07
6.07

0.30
0.60

3.99
2.00

77.94
29.08
29.08
58.16

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.33
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 152+426
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.17
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

152 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 152+426
Length Width Depth

Cum

km.
Quantity
297.24

Kg
Kg
Kg
Kg
T

75
75
120
2

297.24
136.10
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22292.79
10207.62
215.70
0.00
32.72

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

153 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 152+426
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.07
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.693
3.920

39.22
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

154 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 152+426
Length Width Depth

6.07
26.0

3.50
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

86
156
242

26

6.07

3.005

948.50

SAI Consulting Engineers Pvt. Ltd.

155 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 152+643
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

156 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 152+643
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

157 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 152+643
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

158 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 152+643
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

159 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.55

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
251.78
460.46

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
5.55
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
17.98
24.09
77.53

Part - 2

cum
cum

4
4

5.55
5.55

5.20
1.70

0.50
0.10

57.73
3.77

Part - 3

cum

5.55

2.60

0.10

5.77

Part - 4

cum

5.55

0.90

0.20

4.00

Part - 5
Part - 6

cum
cum

4
4

5.55
5.55

0.30
0.60

3.73
1.87

71.27
24.86
24.86
49.73

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
15.29
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 154+498
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.65
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

160 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 154+498
Length Width Depth

Cum

km.
Quantity
296.72

Kg
Kg
Kg
Kg
T

75
75
120
2

296.72
121.00
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22253.85
9075.13
215.70
0.00
31.54

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

161 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 154+498
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.55
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.433
3.920

32.41
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

162 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 154+498
Length Width Depth

5.55
26.0

3.24
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

72
156
228

26

5.55

2.745

792.44

SAI Consulting Engineers Pvt. Ltd.

163 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.12

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
232.06
440.74

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
5.12
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
16.58
24.09
76.13

Part - 2

cum
cum

4
4

5.12
5.12

5.20
1.70

0.50
0.10

53.21
3.48

Part - 3

cum

5.12

2.60

0.10

5.32

Part - 4

cum

5.12

0.90

0.20

3.68

Part - 5
Part - 6

cum
cum

4
4

5.12
5.12

0.30
0.60

3.52
1.76

65.69
21.58
21.58
43.16

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
14.42
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 154+896
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.21
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

164 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 154+896
Length Width Depth

Cum

km.
Quantity
296.28

Kg
Kg
Kg
Kg
T

75
75
120
2

296.28
108.85
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22221.24
8164.06
215.70
0.00
30.60

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

165 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 154+896
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.12
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.216
3.920

27.20
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

166 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 154+896
Length Width Depth

5.12
26.0

3.02
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

62
156
218

26

5.12

2.528

672.53

SAI Consulting Engineers Pvt. Ltd.

167 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.73

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
305.16
513.84

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.73
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
21.80
24.09
81.35

Part - 2

cum
cum

4
4

6.73
6.73

5.20
1.70

0.50
0.10

69.97
4.57

Part - 3

cum

6.73

2.60

0.10

7.00

Part - 4

cum

6.73

0.90

0.20

4.84

Part - 5
Part - 6

cum
cum

4
4

6.73
6.73

0.30
0.60

4.32
2.16

86.38
34.89
34.89
69.77

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
17.65
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 155+118
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.82
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

168 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 155+118
Length Width Depth

Cum

km.
Quantity
297.89

Kg
Kg
Kg
Kg
T

75
75
120
2

297.89
156.16
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22342.11
11711.63
215.70
0.00
34.27

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

169 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 155+118
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.73
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

3.021
3.920

48.78
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

170 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 155+118
Length Width Depth

6.73
26.0

3.83
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

104
156
260

26

6.73

3.334

1166.28

SAI Consulting Engineers Pvt. Ltd.

171 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.23

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
237.36
446.03

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
5.23
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
16.95
24.09
76.50

Part - 2

cum
cum

4
4

5.23
5.23

5.20
1.70

0.50
0.10

54.42
3.56

Part - 3

cum

5.23

2.60

0.10

5.44

Part - 4

cum

5.23

0.90

0.20

3.77

Part - 5
Part - 6

cum
cum

4
4

5.23
5.23

0.30
0.60

3.57
1.79

67.19
22.44
22.44
44.88

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
14.66
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 156+017
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.33
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

172 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 156+017
Length Width Depth

Cum

km.
Quantity
296.40

Kg
Kg
Kg
Kg
T

75
75
120
2

296.40
112.07
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22230.00
8405.46
215.70
0.00
30.85

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

173 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 156+017
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.23
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.274
3.920

28.56
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

174 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 156+017
Length Width Depth

5.23
26.0

3.08
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

66
156
222

26

5.23

2.586

703.77

SAI Consulting Engineers Pvt. Ltd.

175 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.33

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
241.71
450.39

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
5.33
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
17.27
24.09
76.82

Part - 2

cum
cum

4
4

5.33
5.33

5.20
1.70

0.50
0.10

55.42
3.62

Part - 3

cum

5.33

2.60

0.10

5.54

Part - 4

cum

5.33

0.90

0.20

3.84

Part - 5
Part - 6

cum
cum

4
4

5.33
5.33

0.30
0.60

3.62
1.81

68.42
23.16
23.16
46.32

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
14.85
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 156+969
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.42
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

176 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 156+969
Length Width Depth

Cum

km.
Quantity
296.50

Kg
Kg
Kg
Kg
T

75
75
120
2

296.50
114.74
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22237.20
8605.70
215.70
0.00
31.06

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

177 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 156+969
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.33
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.322
3.920

29.70
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

178 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 156+969
Length Width Depth

5.33
26.0

3.13
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

68
156
224

26

5.33

2.634

729.99

SAI Consulting Engineers Pvt. Ltd.

179 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
4.58

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
207.88
416.56

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
4.58
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
14.85
24.09
74.40

Part - 2

cum
cum

4
4

4.58
4.58

5.20
1.70

0.50
0.10

47.66
3.12

Part - 3

cum

4.58

2.60

0.10

4.77

Part - 4

cum

4.58

0.90

0.20

3.30

Part - 5
Part - 6

cum
cum

4
4

4.58
4.58

0.30
0.60

3.25
1.62

58.85
17.87
17.87
35.74

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
13.36
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 157+465
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
6.68
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

180 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 157+465
Length Width Depth

Cum

km.
Quantity
295.75

Kg
Kg
Kg
Kg
T

75
75
120
2

295.75
94.58
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22181.26
7093.66
215.70
0.00
29.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

181 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 157+465
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.58
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

1.949
3.920

21.44
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

182 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 157+465
Length Width Depth

4.58
26.0

2.75
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

52
156
208

26

4.58

2.262

538.95

SAI Consulting Engineers Pvt. Ltd.

183 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.09

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
230.79
439.47

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
5.09
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
16.49
24.09
76.04

Part - 2

cum
cum

4
4

5.09
5.09

5.20
1.70

0.50
0.10

52.92
3.46

Part - 3

cum

5.09

2.60

0.10

5.29

Part - 4

cum

5.09

0.90

0.20

3.66

Part - 5
Part - 6

cum
cum

4
4

5.09
5.09

0.30
0.60

3.50
1.75

65.33
21.38
21.38
42.76

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
14.37
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 163+355
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
7.18
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

184 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 163+355
Length Width Depth

Cum

km.
Quantity
296.26

Kg
Kg
Kg
Kg
T

75
75
120
2

296.26
108.09
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22219.14
8106.56
215.70
0.00
30.54

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

185 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 163+355
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.09
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.202
3.920

26.88
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

186 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 163+355
Length Width Depth

5.09
26.0

3.01
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

62
156
218

26

5.09

2.514

665.14

SAI Consulting Engineers Pvt. Ltd.

187 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 164+614
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

188 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 164+614
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

189 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 164+614
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

190 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 164+614
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

191 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 171+904
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

192 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 171+904
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

193 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 171+904
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

194 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 171+904
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

195 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 172+304
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

196 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 172+304
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

197 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 172+304
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

198 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 172+304
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

199 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 175+000
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

200 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 175+000
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

201 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 175+000
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

202 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 175+000
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

203 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.40

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
290.30
498.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
6.40
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
20.74
24.09
80.29

Part - 2

cum
cum

4
4

6.40
6.40

5.20
1.70

0.50
0.10

66.56
4.35

Part - 3

cum

6.40

2.60

0.10

6.66

Part - 4

cum

6.40

0.90

0.20

4.61

Part - 5
Part - 6

cum
cum

4
4

6.40
6.40

0.30
0.60

4.16
2.08

82.18
31.93
31.93
63.86

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
16.99
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 175+930
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
8.50
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

204 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 175+930
Length Width Depth

Cum

km.
Quantity
297.57

Kg
Kg
Kg
Kg
T

75
75
120
2

297.57
146.04
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22317.54
10952.64
215.70
0.00
33.49

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

205 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 175+930
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.40
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

2.858
3.920

43.89
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

206 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 175+930
Length Width Depth

6.40
26.0

3.66
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

94
156
250

26

6.40

3.170

1054.98

SAI Consulting Engineers Pvt. Ltd.

207 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
7.92

8.09
8.09
5.40

0.90
0.90
2.10

191.49
17.18
359.25
567.92

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.06
0.40
7.92
22.00

8.09
8.09
8.09
5.40
3.65

0.15
0.15
0.15
0.15
0.15

31.92
2.57
0.97
25.66
24.09
85.21

Part - 2

cum
cum

4
4

7.92
7.92

5.20
1.70

0.50
0.10

82.37
5.39

Part - 3

cum

7.92

2.60

0.10

8.24

Part - 4

cum

7.92

0.90

0.20

5.70

Part - 5
Part - 6

cum
cum

4
4

7.92
7.92

0.30
0.60

4.92
2.46

101.69
46.74
46.74
93.47

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
8
2
2
0
1
2

26.00
26.00
1.05
26.00
26.00
0.50
7.19
7.19
26.00
26.00

7.79
0.42
7.79
7.19
0.01125
20.03
0.125
0.75
0.35
0.14

0.45
3.00
0.75
0.47

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 176+510
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

2 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

91.14
65.52
7.89
87.86
2.34
10.02
1.80
0.00
27.30
7.02

SAI Consulting Engineers Pvt. Ltd.

208 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

2 x 3.0
Nos

m.
Pro.Ch 176+510
Length Width Depth

Cum

km.
Quantity
299.09

Kg
Kg
Kg
Kg
T

75
75
120
2

299.09
195.16
1.80
0.00

Cum
Cum

1
2

20.00
20.00

7.19
3.50

Sqm

20.00

7.19

cum

22.00

3.50

No
No

7.79

4
4

Rmt

22.0

44.00

22431.54
14637.35
215.70
0.00
37.28

0.05
0.05

7.19
7.00
14.19

283.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

209 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 176+510
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.90
21.07
21.07
76.93
21.07
21.07

0.70
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.90
10.90
21.07
21.07
76.93

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

7.92
26.00
33.36

cum
cum

42.29

cum
cum
cum
cum

2
1
1

76.93
21.07
21.07

cum
cum

76.93

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

2 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.10
2.15
2.65
0.45
0.75
0.75

33.56
67.95
103.30
69.24
47.41
94.82
416.26

0.70
0.30

0.20
0.90
1.693
2.175
0.15

6.10
11.77
35.66
45.83
23.08
122.44

0.6
0.6

3.618
3.920

68.76
122.30
133.43
133.43

0.3

50.75
50.75

0.30
0.75
0.75

46.16
47.41
94.82
188.38

0.60

92.32
92.32

3.00
6.00

3.00
6.00

7.19

SAI Consulting Engineers Pvt. Ltd.

210 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

2 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 176+510
Length Width Depth

7.92
26.0

4.42
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

142
156
298

26

7.92

3.930

1618.53

SAI Consulting Engineers Pvt. Ltd.

211 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

32.25
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

96.74
11.34
187.34
295.42

cum
cum
cum
cum
cum
cum

1
2
2
4
2

32.25
1.27
0.40
4.13
27.95

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

19.35
1.53
0.48
13.38
30.60
65.34

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

31.95
31.95
1.20
31.95
31.95
0.50
2.50
2.50
31.95
31.95

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 178+440
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

35.46
31.95
5.00
19.97
1.44
5.38
0.63
0.00
0.00
8.63

SAI Consulting Engineers Pvt. Ltd.

212 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 178+440
Length Width Depth

Cum

km.
Quantity
107.82

Kg
Kg
Kg
Kg
T

75
75
120
2

107.82
82.15
0.63
0.00

Cum
Cum

1
2

20.00
25.95

2.5
3.50

Sqm

20.00

2.5

cum

27.95

3.50

No
No

3.70

2
2

Rmt

27.9

55.90

8086.23
6160.93
75.00
0.00
14.32

0.05
0.05

2.50
9.08
11.58

231.64

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

58.69
58.69

SAI Consulting Engineers Pvt. Ltd.

213 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 178+440
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
31.95
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
97.76
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

214 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 178+440
Length Width Depth

4.13
31.9

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
128
170

31.948

4.13

1.950

514.59

SAI Consulting Engineers Pvt. Ltd.

215 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 178+840
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

216 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 178+840
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

217 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 178+840
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

218 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 178+840
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

219 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.65

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
256.28
346.52

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.65
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
18.31
24.09
60.18

Part - 2

cum
cum

4
4

5.65
5.65

5.20
1.70

0.50
0.10

58.76
3.84

Part - 3

cum

5.65

2.60

0.10

5.88

Part - 4

cum

5.65

0.90

0.20

4.07

Part - 5
Part - 6

cum
cum

4
4

5.65
5.65

0.30
0.60

3.70
1.85

72.55
25.07
25.07
50.14

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.80
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 178+917
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.90
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

220 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 178+917
Length Width Depth

Cum

km.
Quantity
91.20

Kg
Kg
Kg
Kg
T

75
75
120
2

91.20
122.68
0.63
0.00

Cum
Cum

1
2

20.00
24.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6839.63
9201.31
75.00
0.00
16.12

0.05
0.05

2.50
8.40
10.90

218.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

221 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 178+917
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.65
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.398
2.550

32.51
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

222 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 178+917
Length Width Depth

5.65
26.0

3.20
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

74
104
178

26

5.65

2.710

796.20

SAI Consulting Engineers Pvt. Ltd.

223 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

32.17
1.35
4.13

4.00
4.00
5.40

-10.09
1.05
2.10

cum
cum
cum
cum
cum
cum

1
2
2
4
2

32.17
1.27
0.40
4.13
27.87

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

19.30
1.53
0.48
13.38
30.52
65.21

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

31.87
31.87
1.20
31.87
31.87
0.50
2.50
2.50
31.87
31.87

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 179+275
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.

-1298.00
11.34
187.34
-1099.32

A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

35.38
31.87
5.00
19.92
1.43
5.38
0.63
0.00
0.00
8.60

SAI Consulting Engineers Pvt. Ltd.

224 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 179+275
Length Width Depth

Cum

km.
Quantity
107.58

Kg
Kg
Kg
Kg
T

75
75
120
2

107.58
82.15
0.63
0.00

Cum
Cum

1
2

20.00
29.87

2.5
3.50

Sqm

20.00

2.5

cum

27.87

3.50

No
No

3.70

2
2

Rmt

27.9

55.74

8068.39
6160.93
75.00
0.00
14.30

0.05
0.05

2.50
10.45
12.95

259.09

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

58.53
58.53

SAI Consulting Engineers Pvt. Ltd.

225 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 179+275
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
31.87
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
97.52
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

226 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 179+275
Length Width Depth

4.13
31.9

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
128
170

31.87

4.13

1.950

513.33

SAI Consulting Engineers Pvt. Ltd.

227 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

3.11
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

9.33
11.34
187.34
208.00

cum
cum
cum
cum
cum
cum

1
2
2
4
2

3.11
1.27
0.40
4.13
-1.19

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

1.87
1.53
0.48
13.38
-1.30
15.95

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

2.81
2.81
1.20
2.81
2.81
0.50
2.50
2.50
2.81
2.81

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 179+418
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

3.12
2.81
5.00
1.76
0.13
5.38
0.63
0.00
0.00
0.76

SAI Consulting Engineers Pvt. Ltd.

228 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 179+418
Length Width Depth

Cum

km.
Quantity
18.94

Kg
Kg
Kg
Kg
T

75
75
120
2

18.94
82.15
0.63
0.00

Cum
Cum

1
2

20.00
-3.19

2.5
3.50

Sqm

20.00

2.5

cum

-1.19

3.50

No
No

3.70

2
2

Rmt

-1.2

-2.38

1420.55
6160.93
75.00
0.00
7.66

0.05
0.05

2.50
-1.12
1.38

27.66

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

-2.50
-2.50

SAI Consulting Engineers Pvt. Ltd.

229 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 179+418
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
2.81
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
8.59
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

230 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 179+418
Length Width Depth

4.13
2.8

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
12
54

29.62

4.13

1.950

477.09

SAI Consulting Engineers Pvt. Ltd.

231 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.56
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

88.68
11.34
187.34
287.36

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.56
1.27
0.40
4.13
25.26

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.74
1.53
0.48
13.38
27.66
60.78

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.26
29.26
1.20
29.26
29.26
0.50
2.50
2.50
29.26
29.26

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 179+725
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.48
29.26
5.00
18.29
1.32
5.38
0.63
0.00
0.00
7.90

SAI Consulting Engineers Pvt. Ltd.

232 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 179+725
Length Width Depth

Cum

km.
Quantity
99.62

Kg
Kg
Kg
Kg
T

75
75
120
2

99.62
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.26

2.5
3.50

Sqm

20.00

2.5

cum

25.26

3.50

No
No

3.70

2
2

Rmt

25.3

50.52

7471.35
6160.93
75.00
0.00
13.71

0.05
0.05

2.50
8.14
10.64

212.82

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

53.05
53.05

SAI Consulting Engineers Pvt. Ltd.

233 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 179+725
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.26
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
89.54
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

234 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 179+725
Length Width Depth

4.13
29.3

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
118
160

29.26

4.13

1.950

471.29

SAI Consulting Engineers Pvt. Ltd.

235 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.00
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

92.99
11.34
187.34
291.66

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.00
1.27
0.40
4.13
26.70

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.60
1.53
0.48
13.38
29.23
63.22

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.70
30.70
1.20
30.70
30.70
0.50
2.50
2.50
30.70
30.70

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 179+842
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

34.07
30.70
5.00
19.19
1.38
5.38
0.63
0.00
0.00
8.29

SAI Consulting Engineers Pvt. Ltd.

236 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 179+842
Length Width Depth

Cum

km.
Quantity
104.00

Kg
Kg
Kg
Kg
T

75
75
120
2

104.00
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.70

2.5
3.50

Sqm

20.00

2.5

cum

26.70

3.50

No
No

3.70

2
2

Rmt

26.7

53.39

7799.84
6160.93
75.00
0.00
14.04

0.05
0.05

2.50
8.64
11.14

222.87

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.06
56.06

SAI Consulting Engineers Pvt. Ltd.

237 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 179+842
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.70
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
93.93
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

238 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 179+842
Length Width Depth

4.13
30.7

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
124
166

30.696

4.13

1.950

494.42

SAI Consulting Engineers Pvt. Ltd.

239 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.38
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

94.15
11.34
187.34
292.83

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.38
1.27
0.40
4.13
27.08

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.83
1.53
0.48
13.38
29.66
63.88

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

31.08
31.08
1.20
31.08
31.08
0.50
2.50
2.50
31.08
31.08

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 180+005
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

34.50
31.08
5.00
19.43
1.40
5.38
0.63
0.00
0.00
8.39

SAI Consulting Engineers Pvt. Ltd.

240 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 180+005
Length Width Depth

Cum

km.
Quantity
105.18

Kg
Kg
Kg
Kg
T

75
75
120
2

105.18
82.15
0.63
0.00

Cum
Cum

1
2

20.00
25.08

2.5
3.50

Sqm

20.00

2.5

cum

27.08

3.50

No
No

3.70

2
2

Rmt

27.1

54.17

7888.59
6160.93
75.00
0.00
14.12

0.05
0.05

2.50
8.78
11.28

225.59

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.88
56.88

SAI Consulting Engineers Pvt. Ltd.

241 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 180+005
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
31.08
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
95.12
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

242 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 180+005
Length Width Depth

4.13
31.1

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
126
168

31.084

4.13

1.950

500.67

SAI Consulting Engineers Pvt. Ltd.

243 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 180+425
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

244 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 180+425
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

245 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 180+425
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

246 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 180+425
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

247 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 180+765
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

248 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 180+765
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

249 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 180+765
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
14.56
14.56
23.41
14.56
14.56

0.75
0.00
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
14.56
14.56
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
14.56
14.56

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
0.00
71.37
21.07
32.76
65.51
218.26

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
24.64
31.66
7.02
76.89

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
32.76
65.51
112.31

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

250 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 180+765
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

251 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

30.60
1.35
4.13

4.00
4.00
5.40

0.45
1.35
2.10

55.08
14.58
187.34
257.00

cum
cum
cum
cum
cum
cum

1
2
2
4
2

30.60
1.70
0.40
4.13
26.30

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.36
2.04
0.48
13.38
28.80
63.06

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.30
30.30
1.50
30.30
30.30
0.50
2.50
2.50
30.30
30.30

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.00

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 181+775
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

1.20
0.25
0.5
0.3
0.00

0.00
0.00
7.99
18.94
1.36
5.38
0.63
0.00
0.00
8.18

SAI Consulting Engineers Pvt. Ltd.

252 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 181+775
Length Width Depth

Cum

km.
Quantity
41.85

Kg
Kg
Kg
Kg
T

75
75
120
2

41.85
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.30

2.5
3.50

Sqm

20.00

2.5

cum

26.30

3.50

No
No

3.70

2
2

Rmt

26.3

52.60

3139.05
6160.93
75.00
0.00
9.37

0.05
0.05

2.50
8.51
11.01

220.10

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

55.23
55.23

SAI Consulting Engineers Pvt. Ltd.

253 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 181+775
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

58.23
11.50
11.50
23.41
11.50
11.50

0.75
1.50
0.00

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

58.23
58.23
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.30
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
0.00
0.45
0.75
0.75

227.11
37.09
0.00
21.07
25.88
51.75
362.89

0.75
0.30

0.20
1.10
1.693
2.175
0.15

34.94
76.87
19.46
25.01
7.02
163.31

0.6
0.6

1.638
0.250

16.23
9.09
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

254 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 181+775
Length Width Depth

4.13
30.3

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
122
164

30.3

4.13

1.950

488.04

SAI Consulting Engineers Pvt. Ltd.

255 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 181+870
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

256 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 181+870
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

257 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 181+870
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

258 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 181+870
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

259 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

37.94
1.35
4.13

4.00
4.00
5.40

###
1.05
2.10

113.82
11.34
187.34
187.34

cum
cum
cum
cum
cum
cum

1
2
2
4
2

37.94
1.27
0.40
4.13
33.64

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

22.76
1.53
0.48
13.38
36.84
74.99

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

37.64
37.64
1.20
37.64
37.64
0.50
2.50
2.50
37.64
37.64

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 182+440
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

41.78
37.64
5.00
23.53
1.69
5.38
0.63
0.00
0.00
10.16

SAI Consulting Engineers Pvt. Ltd.

260 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 182+440
Length Width Depth

Cum

km.
Quantity
125.18

Kg
Kg
Kg
Kg
T

75
75
120
2

125.18
82.15
0.63
0.00

Cum
Cum

1
2

20.00
31.64

2.5
3.50

Sqm

20.00

2.5

cum

33.64

3.50

No
No

3.70

2
2

Rmt

33.6

67.28

9388.28
6160.93
75.00
0.00
15.62

0.05
0.05

2.50
11.07
13.57

271.48

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

70.64
70.64

SAI Consulting Engineers Pvt. Ltd.

261 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 182+440
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
37.64
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
115.18
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

262 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 182+440
Length Width Depth

4.13
37.6

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
152
194

37.64

4.13

1.950

606.27

SAI Consulting Engineers Pvt. Ltd.

263 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.04
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

93.12
11.34
187.34
291.80

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.04
1.27
0.40
4.13
26.74

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.62
1.53
0.48
13.38
29.28
63.29

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.74
30.74
1.20
30.74
30.74
0.50
2.50
2.50
30.74
30.74

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 182+745
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

34.12
30.74
5.00
19.21
1.38
5.38
0.63
0.00
0.00
8.30

SAI Consulting Engineers Pvt. Ltd.

264 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 182+745
Length Width Depth

Cum

km.
Quantity
104.13

Kg
Kg
Kg
Kg
T

75
75
120
2

104.13
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.74

2.5
3.50

Sqm

20.00

2.5

cum

26.74

3.50

No
No

3.70

2
2

Rmt

26.7

53.48

7809.90
6160.93
75.00
0.00
14.05

0.05
0.05

2.50
8.66
11.16

223.18

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.15
56.15

SAI Consulting Engineers Pvt. Ltd.

265 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 182+745
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.74
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
94.06
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

266 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 182+745
Length Width Depth

4.13
30.7

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
124
166

30.74

4.13

1.950

495.13

SAI Consulting Engineers Pvt. Ltd.

267 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.48

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
248.48
338.72

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.48
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
17.75
24.09
59.63

Part - 2

cum
cum

4
4

5.48
5.48

5.20
1.70

0.50
0.10

56.97
3.73

Part - 3

cum

5.48

2.60

0.10

5.70

Part - 4

cum

5.48

0.90

0.20

3.94

Part - 5
Part - 6

cum
cum

4
4

5.48
5.48

0.30
0.60

3.61
1.81

70.34
23.74
23.74
47.48

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.46
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 183+120
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.73
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

268 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 183+120
Length Width Depth

Cum

km.
Quantity
91.02

Kg
Kg
Kg
Kg
T

75
75
120
2

91.02
117.82
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6826.73
8836.40
75.00
0.00
15.74

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

269 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 183+120
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.48
26.00
7.76

cum
cum

5.00

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.312
2.550

30.39
79.56
31.06
31.06

0.3

5.99
5.99

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

270 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 183+120
Length Width Depth

5.48
26.0

3.12
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

70
104
174

26

5.48

2.624

747.46

SAI Consulting Engineers Pvt. Ltd.

271 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

16.25
16.25
5.40

0.75
1.05
2.10

320.53
46.07
187.34
553.94

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

16.25
16.25
16.25
5.40
3.65

0.15
0.15
0.15
0.15
0.15

64.11
6.20
1.95
13.38
24.09
109.73

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 183+332
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

272 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 183+332
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

273 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 183+332
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
0.00
51.75
193.84

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
0.00
51.75
65.79

0.80

37.45
37.45

0.00
6.00

0.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

274 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 183+332
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

275 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

34.99
1.35
4.13

4.00
4.00
5.40

2.16
2.46
2.10

302.46
26.58
187.34
516.38

cum
cum
cum
cum
cum
cum

1
2
2
4
2

34.99
1.27
0.40
4.13
30.69

4.00
4.00
4.00
5.40
3.65

1.56
1.56
0.15
1.56
1.56

218.48
15.90
0.48
139.26
349.73
723.85

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

34.69
34.69
1.20
34.69
34.69
0.50
2.50
2.50
34.69
34.69

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 183+558
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

38.51
34.69
5.00
21.68
1.56
5.38
0.63
0.00
0.00
9.37

SAI Consulting Engineers Pvt. Ltd.

276 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 183+558
Length Width Depth

Cum

km.
Quantity
116.18

Kg
Kg
Kg
Kg
T

75
75
120
2

116.18
82.15
0.63
0.00

Cum
Cum

1
2

20.00
28.69

2.5
3.50

Sqm

20.00

2.5

cum

30.69

3.50

No
No

3.70

2
2

Rmt

30.7

61.38

8713.46
6160.93
75.00
0.00
14.95

0.05
0.05

2.50
10.04
12.54

250.83

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

64.45
64.45

SAI Consulting Engineers Pvt. Ltd.

277 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 183+558
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
34.69
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
0.00
167.96

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
106.15
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
0.00
39.92

2.21

103.51
103.51

3.00
0.00

3.00
0.00

2.50

SAI Consulting Engineers Pvt. Ltd.

278 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 183+558
Length Width Depth

4.13
34.7

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
140
182

34.69

4.13

1.950

558.75

SAI Consulting Engineers Pvt. Ltd.

279 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.08
1.35
4.13

4.00
4.00
5.40

0.75
5.23
2.10

93.24
56.48
187.34
337.06

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.08
7.18
0.40
4.13
26.78

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.65
8.62
0.48
13.38
29.32
70.45

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.78
30.78
5.38
30.78
30.78
0.50
2.50
2.50
30.78
30.78

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
5.08
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 183+757
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

34.17
30.78
106.76
19.24
1.39
5.38
0.63
0.00
0.00
8.31

SAI Consulting Engineers Pvt. Ltd.

280 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 183+757
Length Width Depth

Cum

km.
Quantity
206.02

Kg
Kg
Kg
Kg
T

75
75
120
2

206.02
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.78

2.5
3.50

Sqm

20.00

2.5

cum

26.78

3.50

No
No

3.70

2
2

Rmt

26.8

53.56

15451.52
6160.93
75.00
0.00
21.69

0.05
0.05

2.50
8.67
11.17

223.46

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.24
56.24

SAI Consulting Engineers Pvt. Ltd.

281 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 183+757
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.78
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.00
0.00

27.55
37.09
56.38
21.07
0.00
0.00
142.09

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
94.19
31.06
31.06

0.3

21.34
21.34

0.30
0.00
0.00

14.04
0.00
0.00
14.04

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

282 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 183+757
Length Width Depth

4.13
30.8

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
124
166

30.78

4.13

1.950

495.77

SAI Consulting Engineers Pvt. Ltd.

283 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 184+312
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

284 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 184+312
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

285 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 184+312
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.00
0.75
0.75

27.55
37.09
56.38
0.00
25.88
51.75
198.64

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

286 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 184+312
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

287 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 185+164
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

288 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 185+164
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

289 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 185+164
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

0.20
2.15
2.65
0.45
0.75
0.75

4.24
37.09
56.38
21.07
25.88
51.75
196.40

0.75
0.30

0.20
0.00
1.693
2.175
0.15

4.24
0.00
19.46
25.01
7.02
55.74

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

-0.30

-14.04
-14.04

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

290 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 185+164
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

291 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

30.54
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

91.63
11.34
187.34
290.30

cum
cum
cum
cum
cum
cum

1
2
2
4
2

30.54
1.27
0.40
4.13
26.24

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.33
1.53
0.48
13.38
28.73
62.45

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.24
30.24
1.20
30.24
30.24
0.50
2.50
2.50
30.24
30.24

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 185+501
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

33.57
30.24
5.00
18.90
1.36
5.38
0.63
0.00
0.00
8.17

SAI Consulting Engineers Pvt. Ltd.

292 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 185+501
Length Width Depth

Cum

km.
Quantity
102.61

Kg
Kg
Kg
Kg
T

75
75
120
2

102.61
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.24

2.5
3.50

Sqm

20.00

2.5

cum

26.24

3.50

No
No

3.70

2
2

Rmt

26.2

52.48

7695.98
6160.93
75.00
0.00
13.93

0.05
0.05

2.50
8.48
10.98

219.69

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

55.11
55.11

SAI Consulting Engineers Pvt. Ltd.

293 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 185+501
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.00
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.24
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

0.00
37.09
56.38
21.07
25.88
51.75
192.16

0.00
0.30

0.20
1.10
1.693
2.175
0.15

0.00
9.33
19.46
25.01
7.02
60.82

0.6
0.6

1.638
2.550

16.23
92.54
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

294 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 185+501
Length Width Depth

4.13
30.2

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
122
164

30.242

4.13

1.950

487.11

SAI Consulting Engineers Pvt. Ltd.

295 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.34

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
242.22
332.46

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.34
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
17.30
24.09
59.18

Part - 2

cum
cum

4
4

5.34
5.34

5.20
1.70

0.50
0.10

55.54
3.63

Part - 3

cum

5.34

2.60

0.10

5.55

Part - 4

cum

5.34

0.90

0.20

3.84

Part - 5
Part - 6

cum
cum

4
4

5.34
5.34

0.30
0.60

3.54
1.77

68.57
22.70
22.70
45.40

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.18
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 185+817
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.59
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

296 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 185+817
Length Width Depth

Cum

km.
Quantity
90.89

Kg
Kg
Kg
Kg
T

75
75
120
2

90.89
113.97
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6816.38
8547.47
75.00
0.00
15.44

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

297 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 185+817
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
7.02
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
7.02

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.34
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

7.02
11.50
11.50

cum
cum

7.02

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
6.32
25.88
51.75
204.96

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
2.11
60.15

0.6
0.6

2.243
2.550

28.74
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

4.21
25.88
51.75
81.84

0.80

11.23
11.23

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

298 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 185+817
Length Width Depth

5.34
26.0

3.05
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

66
104
170

26

5.34

2.555

709.47

SAI Consulting Engineers Pvt. Ltd.

299 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 186+121
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

300 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 186+121
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

301 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 186+121
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

302 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 186+121
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

303 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

28.85
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

86.56
11.34
187.34
285.23

cum
cum
cum
cum
cum
cum

1
2
2
4
2

28.85
1.27
0.40
4.13
24.55

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.31
1.53
0.48
13.38
26.88
59.58

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

28.55
28.55
1.20
28.55
28.55
0.50
2.50
2.50
28.55
28.55

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 186+479
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

31.69
28.55
5.00
17.85
1.28
5.38
0.63
0.00
0.00
7.71

SAI Consulting Engineers Pvt. Ltd.

304 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 186+479
Length Width Depth

Cum

km.
Quantity
97.46

Kg
Kg
Kg
Kg
T

75
75
120
2

97.46
82.15
0.63
0.00

Cum
Cum

1
2

20.00
22.55

2.5
3.50

Sqm

20.00

2.5

cum

24.55

3.50

No
No

3.70

2
2

Rmt

24.6

49.10

7309.40
6160.93
75.00
0.00
13.55

0.05
0.05

2.50
7.89
10.39

207.86

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

51.56
51.56

SAI Consulting Engineers Pvt. Ltd.

305 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 186+479
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
28.55
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
87.37
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

306 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 186+479
Length Width Depth

4.13
28.6

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
116
158

28.552

4.13

1.950

459.89

SAI Consulting Engineers Pvt. Ltd.

307 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.84
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

89.52
11.34
187.34
288.20

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.84
1.27
0.40
4.13
25.54

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.90
1.53
0.48
13.38
27.97
61.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.54
29.54
1.20
29.54
29.54
0.50
2.50
2.50
29.54
29.54

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 186+638
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.79
29.54
5.00
18.46
1.33
5.38
0.63
0.00
0.00
7.98

SAI Consulting Engineers Pvt. Ltd.

308 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 186+638
Length Width Depth

Cum

km.
Quantity
100.47

Kg
Kg
Kg
Kg
T

75
75
120
2

100.47
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.54

2.5
3.50

Sqm

20.00

2.5

cum

25.54

3.50

No
No

3.70

2
2

Rmt

25.5

51.08

7535.40
6160.93
75.00
0.00
13.77

0.05
0.05

2.50
8.24
10.74

214.78

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

53.63
53.63

SAI Consulting Engineers Pvt. Ltd.

309 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 186+638
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.54
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
90.39
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

310 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 186+638
Length Width Depth

4.13
29.5

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
120
162

29.54

4.13

1.950

475.80

SAI Consulting Engineers Pvt. Ltd.

311 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.94
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

89.82
11.34
187.34
288.50

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.94
1.27
0.40
4.13
25.64

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.96
1.53
0.48
13.38
28.08
61.43

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.64
29.64
1.20
29.64
29.64
0.50
2.50
2.50
29.64
29.64

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 186+874
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.90
29.64
5.00
18.53
1.33
5.38
0.63
0.00
0.00
8.00

SAI Consulting Engineers Pvt. Ltd.

312 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 186+874
Length Width Depth

Cum

km.
Quantity
100.78

Kg
Kg
Kg
Kg
T

75
75
120
2

100.78
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.64

2.5
3.50

Sqm

20.00

2.5

cum

25.64

3.50

No
No

3.70

2
2

Rmt

25.6

51.28

7558.28
6160.93
75.00
0.00
13.79

0.05
0.05

2.50
8.27
10.77

215.48

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

53.84
53.84

SAI Consulting Engineers Pvt. Ltd.

313 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 186+874
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.64
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
90.70
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

314 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 186+874
Length Width Depth

4.13
29.6

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
120
162

29.64

4.13

1.950

477.41

SAI Consulting Engineers Pvt. Ltd.

315 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.28

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
239.41
329.65

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.28
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
17.10
24.09
58.98

Part - 2

cum
cum

4
4

5.28
5.28

5.20
1.70

0.50
0.10

54.89
3.59

Part - 3

cum

5.28

2.60

0.10

5.49

Part - 4

cum

5.28

0.90

0.20

3.80

Part - 5
Part - 6

cum
cum

4
4

5.28
5.28

0.30
0.60

3.51
1.76

67.77
22.24
22.24
44.48

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.06
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 187+248
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.53
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

316 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 187+248
Length Width Depth

Cum

km.
Quantity
90.82

Kg
Kg
Kg
Kg
T

75
75
120
2

90.82
112.25
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6811.73
8418.78
75.00
0.00
15.31

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

317 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 187+248
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.28
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.212
2.550

28.01
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

318 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 187+248
Length Width Depth

5.28
26.0

3.02
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

64
104
168

26

5.28

2.524

692.73

SAI Consulting Engineers Pvt. Ltd.

319 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 187+447
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

320 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 187+447
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

321 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 187+447
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

322 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 187+447
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

323 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.51

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
249.86
340.10

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.51
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
17.85
24.09
59.72

Part - 2

cum
cum

4
4

5.51
5.51

5.20
1.70

0.50
0.10

57.29
3.75

Part - 3

cum

5.51

2.60

0.10

5.73

Part - 4

cum

5.51

0.90

0.20

3.97

Part - 5
Part - 6

cum
cum

4
4

5.51
5.51

0.30
0.60

3.63
1.81

70.73
23.97
23.97
47.95

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.52
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 187+656
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.76
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

324 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 187+656
Length Width Depth

Cum

km.
Quantity
91.05

Kg
Kg
Kg
Kg
T

75
75
120
2

91.05
118.67
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6829.01
8900.51
75.00
0.00
15.80

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

325 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 187+656
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.51
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.327
2.550

30.76
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

326 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 187+656
Length Width Depth

5.51
26.0

3.13
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

70
104
174

26

5.51

2.639

755.96

SAI Consulting Engineers Pvt. Ltd.

327 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.75

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
215.26
305.50

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.75
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
15.38
24.09
57.25

Part - 2

cum
cum

4
4

4.75
4.75

5.20
1.70

0.50
0.10

49.35
3.23

Part - 3

cum

4.75

2.60

0.10

4.94

Part - 4

cum

4.75

0.90

0.20

3.42

Part - 5
Part - 6

cum
cum

4
4

4.75
4.75

0.30
0.60

3.25
1.62

60.93
18.48
18.48
36.96

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
11.99
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 187+937
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.00
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

328 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 187+937
Length Width Depth

Cum

km.
Quantity
90.29

Kg
Kg
Kg
Kg
T

75
75
120
2

90.29
97.90
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6771.80
7342.17
75.00
0.00
14.19

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

329 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 187+937
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.75
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.945
2.550

22.16
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

330 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 187+937
Length Width Depth

4.75
26.0

2.75
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

54
104
158

26

4.75

2.258

557.16

SAI Consulting Engineers Pvt. Ltd.

331 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.10
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

87.30
11.34
187.34
285.98

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.10
1.27
0.40
4.13
24.80

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.46
1.53
0.48
13.38
27.16
60.00

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

28.80
28.80
1.20
28.80
28.80
0.50
2.50
2.50
28.80
28.80

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 188+050
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

31.97
28.80
5.00
18.00
1.30
5.38
0.63
0.00
0.00
7.78

SAI Consulting Engineers Pvt. Ltd.

332 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 188+050
Length Width Depth

Cum

km.
Quantity
98.22

Kg
Kg
Kg
Kg
T

75
75
120
2

98.22
82.15
0.63
0.00

Cum
Cum

1
2

20.00
22.80

2.5
3.50

Sqm

20.00

2.5

cum

24.80

3.50

No
No

3.70

2
2

Rmt

24.8

49.60

7366.13
6160.93
75.00
0.00
13.60

0.05
0.05

2.50
7.98
10.48

209.60

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

52.08
52.08

SAI Consulting Engineers Pvt. Ltd.

333 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 188+050
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
28.80
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
88.13
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

334 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 188+050
Length Width Depth

4.13
28.8

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
116
158

28.8

4.13

1.950

463.88

SAI Consulting Engineers Pvt. Ltd.

335 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.52
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

88.57
11.34
187.34
287.24

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.52
1.27
0.40
4.13
25.22

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.71
1.53
0.48
13.38
27.62
60.72

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.22
29.22
1.20
29.22
29.22
0.50
2.50
2.50
29.22
29.22

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 188+739
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.44
29.22
5.00
18.26
1.31
5.38
0.63
0.00
0.00
7.89

SAI Consulting Engineers Pvt. Ltd.

336 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 188+739
Length Width Depth

Cum

km.
Quantity
99.50

Kg
Kg
Kg
Kg
T

75
75
120
2

99.50
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.22

2.5
3.50

Sqm

20.00

2.5

cum

25.22

3.50

No
No

3.70

2
2

Rmt

25.2

50.44

7462.66
6160.93
75.00
0.00
13.70

0.05
0.05

2.50
8.13
10.63

212.55

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

52.97
52.97

SAI Consulting Engineers Pvt. Ltd.

337 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 188+739
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.22
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
89.42
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

338 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 188+739
Length Width Depth

4.13
29.2

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
118
160

29.222

4.13

1.950

470.68

SAI Consulting Engineers Pvt. Ltd.

339 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.66
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

88.98
11.34
187.34
287.66

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.66
1.27
0.40
4.13
25.36

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.80
1.53
0.48
13.38
27.77
60.95

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.36
29.36
1.20
29.36
29.36
0.50
2.50
2.50
29.36
29.36

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 188+898
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.59
29.36
5.00
18.35
1.32
5.38
0.63
0.00
0.00
7.93

SAI Consulting Engineers Pvt. Ltd.

340 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 188+898
Length Width Depth

Cum

km.
Quantity
99.92

Kg
Kg
Kg
Kg
T

75
75
120
2

99.92
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.36

2.5
3.50

Sqm

20.00

2.5

cum

25.36

3.50

No
No

3.70

2
2

Rmt

25.4

50.72

7494.23
6160.93
75.00
0.00
13.73

0.05
0.05

2.50
8.18
10.68

213.52

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

53.26
53.26

SAI Consulting Engineers Pvt. Ltd.

341 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 188+898
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.36
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
89.84
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

342 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 188+898
Length Width Depth

4.13
29.4

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
118
160

29.36

4.13

1.950

472.90

SAI Consulting Engineers Pvt. Ltd.

343 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.63

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
255.56
345.80

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.63
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
18.25
24.09
60.13

Part - 2

cum
cum

4
4

5.63
5.63

5.20
1.70

0.50
0.10

58.59
3.83

Part - 3

cum

5.63

2.60

0.10

5.86

Part - 4

cum

5.63

0.90

0.20

4.06

Part - 5
Part - 6

cum
cum

4
4

5.63
5.63

0.30
0.60

3.69
1.84

72.34
24.94
24.94
49.89

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.77
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 189+168
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.88
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

344 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 189+168
Length Width Depth

Cum

km.
Quantity
91.18

Kg
Kg
Kg
Kg
T

75
75
120
2

91.18
122.23
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6838.43
9167.14
75.00
0.00
16.08

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

345 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 189+168
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.63
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.390
2.550

32.31
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

346 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 189+168
Length Width Depth

5.63
26.0

3.19
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

72
104
176

26

5.63

2.702

791.60

SAI Consulting Engineers Pvt. Ltd.

347 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.28

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
239.32
329.56

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.28
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
17.09
24.09
58.97

Part - 2

cum
cum

4
4

5.28
5.28

5.20
1.70

0.50
0.10

54.87
3.59

Part - 3

cum

5.28

2.60

0.10

5.49

Part - 4

cum

5.28

0.90

0.20

3.80

Part - 5
Part - 6

cum
cum

4
4

5.28
5.28

0.30
0.60

3.51
1.76

67.74
22.23
22.23
44.45

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.05
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 189+398
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.53
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

348 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 189+398
Length Width Depth

Cum

km.
Quantity
90.82

Kg
Kg
Kg
Kg
T

75
75
120
2

90.82
112.20
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6811.58
8414.64
75.00
0.00
15.30

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

349 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 189+398
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.28
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.211
2.550

27.99
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

350 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 189+398
Length Width Depth

5.28
26.0

3.02
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

64
104
168

26

5.28

2.523

692.19

SAI Consulting Engineers Pvt. Ltd.

351 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.42

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
200.49
290.73

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.42
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
14.32
24.09
56.20

Part - 2

cum
cum

4
4

4.42
4.42

5.20
1.70

0.50
0.10

45.97
3.01

Part - 3

cum

4.42

2.60

0.10

4.60

Part - 4

cum

4.42

0.90

0.20

3.18

Part - 5
Part - 6

cum
cum

4
4

4.42
4.42

0.30
0.60

3.08
1.54

56.75
16.35
16.35
32.70

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
11.34
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 189+940
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.67
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

352 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 189+940
Length Width Depth

Cum

km.
Quantity
89.97

Kg
Kg
Kg
Kg
T

75
75
120
2

89.97
89.45
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6747.38
6708.90
75.00
0.00
13.53

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

353 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 189+940
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.42
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.783
2.550

18.91
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

354 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 189+940
Length Width Depth

4.42
26.0

2.59
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

46
104
150

26

4.42

2.095

481.51

SAI Consulting Engineers Pvt. Ltd.

355 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.38

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
198.59
288.83

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.38
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
14.18
24.09
56.06

Part - 2

cum
cum

4
4

4.38
4.38

5.20
1.70

0.50
0.10

45.53
2.98

Part - 3

cum

4.38

2.60

0.10

4.55

Part - 4

cum

4.38

0.90

0.20

3.15

Part - 5
Part - 6

cum
cum

4
4

4.38
4.38

0.30
0.60

3.06
1.53

56.21
16.08
16.08
32.17

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
11.26
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 190+208
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.63
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

356 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 190+208
Length Width Depth

Cum

km.
Quantity
89.92

Kg
Kg
Kg
Kg
T

75
75
120
2

89.92
88.38
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6744.23
6628.60
75.00
0.00
13.45

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

357 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 190+208
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.38
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.762
2.550

18.51
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

358 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 190+208
Length Width Depth

4.38
26.0

2.57
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

46
104
150

26

4.38

2.074

472.16

SAI Consulting Engineers Pvt. Ltd.

359 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

41.20
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

123.59
11.34
187.34
322.26

cum
cum
cum
cum
cum
cum

1
2
2
4
2

41.20
1.27
0.40
4.13
36.90

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

24.72
1.53
0.48
13.38
40.40
80.51

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

40.90
40.90
1.20
40.90
40.90
0.50
2.50
2.50
40.90
40.90

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 190+597
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

45.39
40.90
5.00
25.56
1.84
5.38
0.63
0.00
0.00
11.04

SAI Consulting Engineers Pvt. Ltd.

360 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 190+597
Length Width Depth

Cum

km.
Quantity
135.11

Kg
Kg
Kg
Kg
T

75
75
120
2

135.11
82.15
0.63
0.00

Cum
Cum

1
2

20.00
34.90

2.5
3.50

Sqm

20.00

2.5

cum

36.90

3.50

No
No

3.70

2
2

Rmt

36.9

73.79

10133.09
6160.93
75.00
0.00
16.37

0.05
0.05

2.50
12.21
14.71

294.27

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

77.48
77.48

SAI Consulting Engineers Pvt. Ltd.

361 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 190+597
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
40.90
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
125.14
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

362 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 190+597
Length Width Depth

4.13
40.9

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
164
206

40.896

4.13

1.950

658.71

SAI Consulting Engineers Pvt. Ltd.

363 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

46.78
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

140.33
11.34
187.34
339.00

cum
cum
cum
cum
cum
cum

1
2
2
4
2

46.78
1.27
0.40
4.13
42.48

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

28.07
1.53
0.48
13.38
46.51
89.97

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

46.48
46.48
1.20
46.48
46.48
0.50
2.50
2.50
46.48
46.48

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 191+007
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

51.59
46.48
5.00
29.05
2.09
5.38
0.63
0.00
0.00
12.55

SAI Consulting Engineers Pvt. Ltd.

364 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 191+007
Length Width Depth

Cum

km.
Quantity
152.13

Kg
Kg
Kg
Kg
T

75
75
120
2

152.13
82.15
0.63
0.00

Cum
Cum

1
2

20.00
40.48

2.5
3.50

Sqm

20.00

2.5

cum

42.48

3.50

No
No

3.70

2
2

Rmt

42.5

84.95

11409.51
6160.93
75.00
0.00
17.65

0.05
0.05

2.50
14.17
16.67

333.33

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

89.20
89.20

SAI Consulting Engineers Pvt. Ltd.

365 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 191+007
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
46.48
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
142.22
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

366 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 191+007
Length Width Depth

4.13
46.5

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
186
228

46.476

4.13

1.950

748.59

SAI Consulting Engineers Pvt. Ltd.

367 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

32.36
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

97.07
11.34
187.34
295.74

cum
cum
cum
cum
cum
cum

1
2
2
4
2

32.36
1.27
0.40
4.13
28.06

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

19.41
1.53
0.48
13.38
30.72
65.52

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

32.06
32.06
1.20
32.06
32.06
0.50
2.50
2.50
32.06
32.06

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 191+307
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

35.58
32.06
5.00
20.04
1.44
5.38
0.63
0.00
0.00
8.66

SAI Consulting Engineers Pvt. Ltd.

368 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 191+307
Length Width Depth

Cum

km.
Quantity
108.15

Kg
Kg
Kg
Kg
T

75
75
120
2

108.15
82.15
0.63
0.00

Cum
Cum

1
2

20.00
26.06

2.5
3.50

Sqm

20.00

2.5

cum

28.06

3.50

No
No

3.70

2
2

Rmt

28.1

56.11

8110.94
6160.93
75.00
0.00
14.35

0.05
0.05

2.50
9.12
11.62

232.39

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

58.92
58.92

SAI Consulting Engineers Pvt. Ltd.

369 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 191+307
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
32.06
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
98.09
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

370 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 191+307
Length Width Depth

4.13
32.1

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
130
172

32.056

4.13

1.950

516.33

SAI Consulting Engineers Pvt. Ltd.

371 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.43

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
246.30
336.54

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.43
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
17.59
24.09
59.47

Part - 2

cum
cum

4
4

5.43
5.43

5.20
1.70

0.50
0.10

56.47
3.69

Part - 3

cum

5.43

2.60

0.10

5.65

Part - 4

cum

5.43

0.90

0.20

3.91

Part - 5
Part - 6

cum
cum

4
4

5.43
5.43

0.30
0.60

3.59
1.79

69.72
23.38
23.38
46.75

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.36
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 191+802
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.68
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

372 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 191+802
Length Width Depth

Cum

km.
Quantity
90.98

Kg
Kg
Kg
Kg
T

75
75
120
2

90.98
116.47
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6823.13
8735.51
75.00
0.00
15.63

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

373 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 191+802
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.43
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.288
2.550

29.81
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

374 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 191+802
Length Width Depth

5.43
26.0

3.09
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

68
104
172

26

5.43

2.600

734.14

SAI Consulting Engineers Pvt. Ltd.

375 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.41
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

88.24
11.34
187.34
286.91

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.41
1.27
0.40
4.13
25.11

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.65
1.53
0.48
13.38
27.50
60.53

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.11
29.11
1.20
29.11
29.11
0.50
2.50
2.50
29.11
29.11

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 192+028
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.31
29.11
5.00
18.20
1.31
5.38
0.63
0.00
0.00
7.86

SAI Consulting Engineers Pvt. Ltd.

376 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 192+028
Length Width Depth

Cum

km.
Quantity
99.17

Kg
Kg
Kg
Kg
T

75
75
120
2

99.17
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.11

2.5
3.50

Sqm

20.00

2.5

cum

25.11

3.50

No
No

3.70

2
2

Rmt

25.1

50.22

7437.50
6160.93
75.00
0.00
13.67

0.05
0.05

2.50
8.09
10.59

211.78

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

52.74
52.74

SAI Consulting Engineers Pvt. Ltd.

377 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 192+028
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.11
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
89.08
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

378 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 192+028
Length Width Depth

4.13
29.1

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
118
160

29.112

4.13

1.950

468.91

SAI Consulting Engineers Pvt. Ltd.

379 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.59

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
253.56
343.80

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.59
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
18.11
24.09
59.99

Part - 2

cum
cum

4
4

5.59
5.59

5.20
1.70

0.50
0.10

58.14
3.80

Part - 3

cum

5.59

2.60

0.10

5.81

Part - 4

cum

5.59

0.90

0.20

4.02

Part - 5
Part - 6

cum
cum

4
4

5.59
5.59

0.30
0.60

3.67
1.83

71.78
24.60
24.60
49.20

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.68
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 192+259
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.84
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

380 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 192+259
Length Width Depth

Cum

km.
Quantity
91.14

Kg
Kg
Kg
Kg
T

75
75
120
2

91.14
120.98
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6835.13
9073.41
75.00
0.00
15.98

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

381 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 192+259
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.59
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.368
2.550

31.76
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

382 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 192+259
Length Width Depth

5.59
26.0

3.17
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

72
104
176

26

5.59

2.680

779.02

SAI Consulting Engineers Pvt. Ltd.

383 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.30

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
240.41
330.65

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.30
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
17.17
24.09
59.05

Part - 2

cum
cum

4
4

5.30
5.30

5.20
1.70

0.50
0.10

55.12
3.60

Part - 3

cum

5.30

2.60

0.10

5.51

Part - 4

cum

5.30

0.90

0.20

3.82

Part - 5
Part - 6

cum
cum

4
4

5.30
5.30

0.30
0.60

3.52
1.76

68.05
22.40
22.40
44.81

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.10
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 192+734
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.55
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

384 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 192+734
Length Width Depth

Cum

km.
Quantity
90.85

Kg
Kg
Kg
Kg
T

75
75
120
2

90.85
112.86
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6813.38
8464.37
75.00
0.00
15.35

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

385 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 192+734
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.30
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.223
2.550

28.27
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

386 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 192+734
Length Width Depth

5.30
26.0

3.03
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

66
104
170

26

5.30

2.535

698.65

SAI Consulting Engineers Pvt. Ltd.

387 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

28.93
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

86.78
11.34
187.34
285.46

cum
cum
cum
cum
cum
cum

1
2
2
4
2

28.93
1.27
0.40
4.13
24.63

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.36
1.53
0.48
13.38
26.97
59.71

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

28.63
28.63
1.20
28.63
28.63
0.50
2.50
2.50
28.63
28.63

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 193+525
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

31.78
28.63
5.00
17.89
1.29
5.38
0.63
0.00
0.00
7.73

SAI Consulting Engineers Pvt. Ltd.

388 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)
Total
Providing & laying Tar paper on
abutments/piers as bearing for receiving
RCC work in superstructure as per drawing
and Technical Specifications.

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 193+525
Length Width Depth

Cum

km.
Quantity
97.69

Kg
Kg
Kg
Kg
T

75
75
120
2

97.69
82.15
0.63
0.00

Sqm

28.63

7326.78
6160.93
75.00
0.00
13.56

0.3

0.00

Sqm

0.00

Cum
Cum

1
2

20.00
22.63

2.5
3.50

0.05
0.05

2.50
7.92
10.42

Sqm

20.00

2.5

cum

24.63

3.50

No
No

3.70

2
2

Rmt

24.6

49.26

208.40

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

51.72
51.72

SAI Consulting Engineers Pvt. Ltd.

389 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 193+525
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
28.63
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
87.60
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

390 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 193+525
Length Width Depth

4.13
28.6

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
116
158

28.628

4.13

1.950

461.11

SAI Consulting Engineers Pvt. Ltd.

391 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

35.58
0.93
2.10

4996.93
11.72
285.77
5294.41

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

2.04
0.42
2.04
0.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
0.00
0.78
0

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 150+875
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
0.00

22.28
0.00
2.20
0.00
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

392 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)
Total
Providing & laying Tar paper on
abutments/piers as bearing for receiving
RCC work in superstructure as per drawing
and Technical Specifications.

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 150+875
Length Width Depth

Cum

km.
Quantity
40.88

Kg
Kg
Kg
Kg
T

75
75
120
2

40.88
143.00
0.96
0.00

Sqm

26.00

3066.20
10724.81
115.20
0.00
13.91

0.00

Sqm

0.00

Cum
Cum

1
2

20.00
20.00

0.84
3.50

0.05
0.05

0.84
7.00
7.84

Sqm

20.00

0.84

cum

22.00

3.50

No
No

2.04

2
2

Rmt

22.0

44.00

156.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

393 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 150+875
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
0.00
0.00

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
0.00
2.65
0.45
0.75
0.75

41.88
0.00
0.00
46.48
39.42
78.84
206.62

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
0.420

42.45
13.10
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

394 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 150+875
Length Width Depth

6.30
0.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
0
92

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

395 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 151+675
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

396 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)
Total
Providing & laying Tar paper on
abutments/piers as bearing for receiving
RCC work in superstructure as per drawing
and Technical Specifications.

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 151+675
Length Width Depth

Cum

km.
Quantity
184.32

Kg
Kg
Kg
Kg
T

75
75
120
2

184.32
143.00
0.96
0.00

Sqm

26.00

13824.35
10724.81
115.20
0.00
24.66

0.3

0.00

Sqm

0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

0.05
0.05

3.84
7.00
10.84

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

397 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 151+675
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

398 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 151+675
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

399 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 151+704
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

400 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 151+704
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

401 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 151+704
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

402 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 151+704
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

403 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 152+000
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

404 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 152+000
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

405 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 152+000
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

406 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 152+000
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

407 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

46.78
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

217.31
11.72
285.77
514.80

cum
cum
cum
cum
cum
cum

1
2
2
4
2

46.78
1.10
0.40
6.30
42.48

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

37.47
1.77
0.64
20.41
46.51
106.80

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

46.48
46.48
1.08
46.48
46.48
0.50
3.84
3.84
46.48
46.48

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 152+436
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

98.38
117.12
5.43
74.96
2.09
8.22
0.96
0.00
0.00
12.55

SAI Consulting Engineers Pvt. Ltd.

408 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 152+436
Length Width Depth

Cum

km.
Quantity
318.74

Kg
Kg
Kg
Kg
T

75
75
120
2

318.74
143.00
0.96
0.00

Cum
Cum

1
2

20.00
40.48

3.84
3.50

Sqm

20.00

3.84

cum

42.48

3.50

No
No

5.04

4
4

Rmt

42.5

84.95

23905.34
10724.81
115.20
0.00
34.75

0.05
0.05

3.84
14.17
18.01

360.13

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

89.20
89.20

SAI Consulting Engineers Pvt. Ltd.

409 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 152+436
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
46.48
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
214.16
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

410 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 152+436
Length Width Depth

6.30
46.5

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
280
372

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

411 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.25
6.33

4.60
4.60
5.40

0.87
0.93
2.10

105.25
10.70
287.13
403.08

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.33
22.00

4.60
4.60
4.60
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.15
1.52
0.55
20.51
24.09
64.82

Part - 2

cum
cum

4
4

6.33
6.33

5.20
1.70

0.50
0.10

65.83
4.30

Part - 3

cum

6.33

2.60

0.10

6.58

Part - 4

cum

6.33

0.90

0.20

4.56

Part - 5
Part - 6

cum
cum

4
4

6.33
6.33

0.30
0.60

4.09
2.04

81.28
31.05
31.05
62.10

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.70
3.70
26.00
26.00

4.30
0.35
4.30
3.7
0.01125
16.61
0.125
0.75
0.25
0.14

0.42
3.00
0.78
0.4

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 152+622
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

46.96
54.60
4.63
38.48
1.17
8.31
0.93
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

412 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 152+622
Length Width Depth

Cum

km.
Quantity
161.16

Kg
Kg
Kg
Kg
T

75
75
120
2

161.16
143.37
0.93
0.00

Cum
Cum

1
2

20.00
20.00

3.7
3.50

Sqm

20.00

3.7

cum

22.00

3.50

No
No

4.30

2
2

Rmt

22.0

44.00

12086.96
10753.09
111.00
0.00
22.95

0.05
0.05

3.70
7.00
10.70

214.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

413 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 152+622
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.68
17.30
17.30
50.23
17.30
17.30

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.68
10.68
17.30
17.30
50.23

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.33
26.00
31.20

cum
cum

40.60

cum
cum
cum
cum

2
1
1

50.23
17.30
17.30

cum
cum

50.23

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.64
55.79
84.81
45.21
38.93
77.85
344.23

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.41
14.09
29.28
37.63
15.07
102.48

0.6
0.6

2.788
3.820

42.35
119.18
124.79
124.79

0.3

48.72
48.72

0.30
0.75
0.75

30.14
38.93
77.85
146.91

0.80

80.37
80.37

3.00
6.00

3.00
6.00

3.70

SAI Consulting Engineers Pvt. Ltd.

414 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 152+622
Length Width Depth

6.33
26.0

3.59
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.33

3.100

1020.40

SAI Consulting Engineers Pvt. Ltd.

415 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
0.06

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
2.72
136.63

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
0.06
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
0.19
24.09
47.76

Part - 2

cum
cum

4
4

0.06
0.06

5.20
1.70

0.50
0.10

0.62
0.04

Part - 3

cum

0.06

2.60

0.10

0.06

Part - 4

cum

0.06

0.90

0.20

0.04

Part - 5
Part - 6

cum
cum

4
4

0.06
0.06

0.30
0.60

0.99
0.49

0.77
0.07
0.07
0.14

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
3.96
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 153+450
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
1.98
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

416 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 153+450
Length Width Depth

Cum

km.
Quantity
178.08

Kg
Kg
Kg
Kg
T

75
75
120
2

178.08
0.91
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13356.35
68.45
115.20
0.00
13.54

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

417 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 153+450
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

0.06
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

-0.313
3.840

-0.05
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

418 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 153+450
Length Width Depth

0.06
26.0

0.49
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

2
156
158

26

0.06

0.000

0.00

SAI Consulting Engineers Pvt. Ltd.

419 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87000
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 156+415
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

420 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 156+415
Length Width Depth

Cum

km.
Quantity
184.32

Kg
Kg
Kg
Kg
T

75
75
120
2

184.32
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13824.35
10724.81
115.20
0.00
24.66

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

421 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 156+415
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

422 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 156+415
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

423 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 156+514
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

424 of 734

Box Culvert
Description

Sr.
No
5

Unit

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)
Total

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

m.
Pro.Ch 156+514
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Sqm

26.00

6725.63
6160.93
75.00
0.00
12.96
0.3

0.00

Sqm

0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

0.05
0.05

2.50
7.00
9.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

1 x 2.0
Nos

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

425 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 156+514
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

426 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 156+514
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

427 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 157+196
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

428 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 157+196
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

429 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 157+196
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

430 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 157+196
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

431 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 157+770
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

432 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 157+770
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

433 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 157+770
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
9.33
9.33
23.41
9.33
9.33

0.75
0.00
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
9.33
9.33
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
9.33
9.33

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
0.00
45.72
21.07
20.98
41.97
157.29

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
15.78
20.28
7.02
56.65

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
20.98
41.97
76.99

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

434 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 157+770
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

435 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.25
6.33

4.60
4.60
5.40

0.8700
0.93
2.10

105.25
10.70
287.13
403.08

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.33
22.00

4.60
4.60
4.60
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.15
1.52
0.55
20.51
24.09
64.82

Part - 2

cum
cum

4
4

6.33
6.33

5.20
1.70

0.50
0.10

65.83
4.30

Part - 3

cum

6.33

2.60

0.10

6.58

Part - 4

cum

6.33

0.90

0.20

4.56

Part - 5
Part - 6

cum
cum

4
4

6.33
6.33

0.30
0.60

4.09
2.04

81.28
31.05
31.05
62.10

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.70
3.70
26.00
26.00

4.30
0.35
4.30
3.7
0.01125
16.61
0.125
0.75
0.25
0.14

0.42
3.00
0.78
0.4

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 158+477
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

46.96
54.60
4.63
38.48
1.17
8.31
0.93
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

436 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 158+477
Length Width Depth

Cum

km.
Quantity
161.16

Kg
Kg
Kg
Kg
T

75
75
120
2

161.16
143.37
0.93
0.00

Cum
Cum

1
2

20.00
20.00

3.7
3.50

Sqm

20.00

3.7

cum

22.00

3.50

No
No

4.30

2
2

Rmt

22.0

44.00

12086.96
10753.09
111.00
0.00
22.95

0.05
0.05

3.70
7.00
10.70

214.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

437 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 158+477
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.68
17.30
17.30
50.23
17.30
17.30

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.68
10.68
17.30
17.30
50.23

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.33
26.00
31.20

cum
cum

40.60

cum
cum
cum
cum

2
1
1

50.23
17.30
17.30

cum
cum

50.23

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.64
55.79
84.81
45.21
38.93
77.85
344.23

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.41
14.09
29.28
37.63
15.07
102.48

0.6
0.6

2.788
3.820

42.35
119.18
124.79
124.79

0.3

48.72
48.72

0.30
0.75
0.75

30.14
38.93
77.85
146.91

0.80

80.37
80.37

3.00
6.00

3.00
6.00

3.70

SAI Consulting Engineers Pvt. Ltd.

438 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 158+477
Length Width Depth

6.33
26.0

3.59
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.33

3.100

1020.40

SAI Consulting Engineers Pvt. Ltd.

439 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 159+080
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

440 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)
Total
Providing & laying Tar paper on
abutments/piers as bearing for receiving
RCC work in superstructure as per drawing
and Technical Specifications.

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 159+080
Length Width Depth

Cum

km.
Quantity
184.32

Kg
Kg
Kg
Kg
T

75
75
120
2

184.32
143.00
0.96
0.00

Sqm

26.00

13824.35
10724.81
115.20
0.00
24.66

0.3

0.00

Sqm

0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

0.05
0.05

3.84
7.00
10.84

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

441 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 159+080
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

442 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 159+080
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

443 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 159+332
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

444 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 159+332
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

445 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 159+332
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

446 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 159+332
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

447 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 159+890
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall of median opening
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

1.075
0.3
3.00

55.04
65.52
5.43
41.93
1.17
17.67
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

448 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 159+890
Length Width Depth

Cum

km.
Quantity
193.78

Kg
Kg
Kg
Kg
T

75
75
120
2

193.78
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

14533.32
10724.81
115.20
0.00
25.37

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

449 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 159+890
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

103.87

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

124.64
124.64

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

450 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 159+890
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

451 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

0.00
0.00
5.40

0.87
0.93
2.10

0.00
0.00
285.77
285.77

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

0.00
0.00
0.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

0.00
0.00
0.00
20.41
24.09
44.50

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

4.20
0.00
4.20
3
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 159+905
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

45.86
0.00
4.52
32.76
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

452 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 159+905
Length Width Depth

Cum

km.
Quantity
99.55

Kg
Kg
Kg
Kg
T

75
75
120
2

99.55
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3
3.50

Sqm

20.00

cum

22.00

3.50

No
No

4.20

2
2

Rmt

22.0

44.00

7466.62
10724.81
115.20
0.00
18.31

0.05
0.05

3.00
7.00
10.00

200.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

453 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 159+905
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
0.00
78.84
309.59

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
0.00
78.84
109.82

0.80

82.62
82.62

0.00
6.00

0.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

454 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 159+905
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

455 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 160+670
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

456 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 160+670
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

457 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 160+670
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

458 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 160+670
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

459 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 160+866
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

460 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 160+866
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

461 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 160+866
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

462 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 160+866
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

463 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 161+450
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

464 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 161+450
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

465 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 161+450
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

466 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 161+450
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

467 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

1.69
1.05
2.10

177.86
11.34
187.34
376.53

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 162+085
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

468 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 162+085
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

469 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 162+085
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

470 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 162+085
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

471 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

0.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

0.90
11.34
187.34
199.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

0.30
1.27
0.40
4.13
-4.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

0.18
1.53
0.48
13.38
-4.38
11.19

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

0.00
0.00
1.20
0.00
0.00
0.50
2.50
2.50
0.00
0.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 162+712
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

0.00
0.00
5.00
0.00
0.00
5.38
0.63
0.00
0.00
0.00

SAI Consulting Engineers Pvt. Ltd.

472 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 162+712
Length Width Depth

Cum

km.
Quantity
10.38

Kg
Kg
Kg
Kg
T

75
75
120
2

10.38
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

778.13
6160.93
75.00
0.00
7.01

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

473 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 162+712
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
0.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
0.00
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

474 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 162+712
Length Width Depth

4.13
0.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
0
42

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

475 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 163+715
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

476 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 163+715
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

477 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 163+715
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

478 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 163+715
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

479 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 163+861
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

480 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 163+861
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

481 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 163+861
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

482 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 163+861
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

483 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 164+055
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

484 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 164+055
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

485 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 164+055
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

486 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 164+055
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

487 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 164+070
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

488 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 164+070
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

489 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 164+070
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

490 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 164+070
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

491 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 164+200
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

492 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)
Total
Providing & laying Tar paper on
abutments/piers as bearing for receiving
RCC work in superstructure as per drawing
and Technical Specifications.

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 164+200
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Sqm

26.00

6725.63
6160.93
75.00
0.00
12.96

0.3

0.00

Sqm

0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

0.05
0.05

2.50
7.00
9.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

493 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 164+200
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
25.88
25.88
23.41
25.88
25.88

0.75
0.00
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
25.88
25.88
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
0.00
126.85
21.07
58.22
116.44
350.13

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
43.79
56.28
7.02
120.66

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

494 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 164+200
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

495 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 164+596
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

496 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 164+596
Length Width Depth

Cum

km.
Quantity
184.32

Kg
Kg
Kg
Kg
T

75
75
120
2

184.32
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13824.35
10724.81
115.20
0.00
24.66

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

497 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 164+596
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
78.84
78.84
51.64
78.84
78.84

0.75
0.00
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
78.84
78.84
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
0.00
386.51
46.48
177.39
354.78
1007.04

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
133.44
171.48
15.49
341.02

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

498 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 164+596
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

499 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 164+606
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

500 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 164+606
Length Width Depth

Cum

km.
Quantity
184.32

Kg
Kg
Kg
Kg
T

75
75
120
2

184.32
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13824.35
10724.81
115.20
0.00
24.66

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

501 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 164+606
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

502 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 164+606
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

503 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 164+660
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

504 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 164+660
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

505 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 164+660
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

506 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 164+660
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

507 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 165+050
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

508 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 165+050
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

509 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 165+050
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

510 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 165+050
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

511 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 165+550
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall of median opening
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

1.075
0.3
2.00

28.86
26.00
5.00
16.25
1.17
11.57
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

512 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 165+550
Length Width Depth

Cum

km.
Quantity
95.86

Kg
Kg
Kg
Kg
T

75
75
120
2

95.86
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

7189.65
6160.93
75.00
0.00
13.43

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

513 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 165+550
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

0.00

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

0.00
0.00

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

514 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 165+550
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

515 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 165+354
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall of median opening
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

1.075
0.3
2.00

28.86
26.00
5.00
16.25
1.17
11.57
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

516 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 165+354
Length Width Depth

Cum

km.
Quantity
95.86

Kg
Kg
Kg
Kg
T

75
75
120
2

95.86
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

7189.65
6160.93
75.00
0.00
13.43

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

517 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 165+354
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

37.45

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

44.94
44.94

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

518 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 165+354
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

519 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.60
0.90
2.10

63.12
9.72
187.34
260.18

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.00
0.00
0.15
0.00
0.00

0.00
0.00
0.48
0.00
0.00
0.48

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 165+980
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

520 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 165+980
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

521 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 165+980
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
0.00
167.96

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
0.00
39.92

0.65

30.43
30.43

3.00
0.00

3.00
0.00

2.50

SAI Consulting Engineers Pvt. Ltd.

522 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 165+980
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

523 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
41.85
2.10

78.90
451.98
187.34
718.22

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
58.97
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
70.77
0.48
13.38
24.09
124.50

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
42.00
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 165+985
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
276.72
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

524 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 165+985
Length Width Depth

Cum

km.
Quantity
361.40

Kg
Kg
Kg
Kg
T

75
75
120
2

361.40
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

27105.23
6160.93
75.00
0.00
33.34

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

525 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 165+985
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.00
0.00

27.55
37.09
56.38
21.07
0.00
0.00
142.09

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.00
0.00

14.04
0.00
0.00
14.04

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

526 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 165+985
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

527 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
103.85
2.10

78.90
1121.58
187.34
1387.82

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
146.65
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
175.98
0.48
13.38
24.09
229.72

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 166+105
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

528 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 166+105
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

529 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 166+105
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.00
0.00

27.55
37.09
56.38
21.07
0.00
0.00
142.09

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.00
0.00

14.04
0.00
0.00
14.04

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

530 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 166+105
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

531 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 166+285
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

532 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 166+285
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

533 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 166+285
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

0.20
2.15
2.65
0.45
0.75
0.75

4.24
37.09
56.38
21.07
25.88
51.75
196.40

0.75
0.30

0.20
0.00
1.693
2.175
0.15

4.24
0.00
19.46
25.01
7.02
55.74

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

534 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 166+285
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

535 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 166+705
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

536 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 166+705
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

537 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 166+705
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

2.00
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

73.48
37.09
56.38
21.07
25.88
51.75
265.63

2.00
0.30

0.20
1.10
1.693
2.175
0.15

11.30
9.33
19.46
25.01
7.02
72.13

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

538 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 166+705
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

539 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
-0.15
2.10

78.90
-1.62
187.34
264.62

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 166+941
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

540 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 166+941
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

541 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 166+941
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.00
0.00

27.55
37.09
56.38
21.07
0.00
0.00
142.09

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.00
0.00

14.04
0.00
0.00
14.04

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

542 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 166+941
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

543 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 166+952
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

544 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 166+952
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

545 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 166+952
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

546 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 166+952
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

547 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 167+354
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

548 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 167+354
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

549 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 167+354
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

550 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 167+354
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

551 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 167+620
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

552 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 167+620
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

553 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 167+620
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

-0.15
0.75
0.75

-7.02
25.88
51.75
70.60

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

554 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 167+620
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

555 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 167+684
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

556 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 167+684
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

557 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 167+684
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

558 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 167+684
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

559 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
5.98

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
271.25
405.16

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
5.98
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
19.38
24.09
66.94

Part - 2

cum
cum

4
4

5.98
5.98

5.20
1.70

0.50
0.10

62.19
4.07

Part - 3

cum

5.98

2.60

0.10

6.22

Part - 4

cum

5.98

0.90

0.20

4.31

Part - 5
Part - 6

cum
cum

4
4

5.98
5.98

0.30
0.60

3.95
1.97

76.78
28.33
28.33
56.65

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
15.80
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 167+694
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
7.90
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

560 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 167+694
Length Width Depth

Cum

km.
Quantity
184.00

Kg
Kg
Kg
Kg
T

75
75
120
2

184.00
133.44
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13800.35
10007.83
115.20
0.00
23.92

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

561 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 167+694
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.98
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.648
3.840

38.00
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

562 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 167+694
Length Width Depth

5.98
26.0

3.45
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

84
156
240

26

5.98

2.960

920.44

SAI Consulting Engineers Pvt. Ltd.

563 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 168+100
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

564 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 168+100
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

565 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 168+100
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

566 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 168+100
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

567 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 168+497
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

568 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 168+497
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

569 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 168+497
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

570 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 168+497
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

571 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 168+734
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

572 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 168+734
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

573 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 168+734
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

574 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 168+734
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

575 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 168+885
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

576 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 168+885
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

577 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 168+885
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

578 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 168+885
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

579 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.25
6.33

4.60
4.60
5.40

0.87
0.93
2.10

105.25
10.70
287.13
403.08

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.33
22.00

4.60
4.60
4.60
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.15
1.52
0.55
20.51
24.09
64.82

Part - 2

cum
cum

4
4

6.33
6.33

5.20
1.70

0.50
0.10

65.83
4.30

Part - 3

cum

6.33

2.60

0.10

6.58

Part - 4

cum

6.33

0.90

0.20

4.56

Part - 5
Part - 6

cum
cum

4
4

6.33
6.33

0.30
0.60

4.09
2.04

81.28
31.05
31.05
62.10

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.70
3.70
26.00
26.00

4.30
0.35
4.30
3.7
0.01125
16.61
0.125
0.75
0.25
0.14

0.42
3.00
0.78
0.4

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 169+005
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

46.96
54.60
4.63
38.48
1.17
8.31
0.93
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

580 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 169+005
Length Width Depth

Cum

km.
Quantity
161.16

Kg
Kg
Kg
Kg
T

75
75
120
2

161.16
143.37
0.93
0.00

Cum
Cum

1
2

20.00
20.00

3.7
3.50

Sqm

20.00

3.7

cum

22.00

3.50

No
No

4.30

2
2

Rmt

22.0

44.00

12086.96
10753.09
111.00
0.00
22.95

0.05
0.05

3.70
7.00
10.70

214.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

581 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 169+005
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.68
17.30
17.30
50.23
17.30
17.30

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.68
10.68
17.30
17.30
50.23

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.33
26.00
31.20

cum
cum

40.60

cum
cum
cum
cum

2
1
1

50.23
17.30
17.30

cum
cum

50.23

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.64
55.79
84.81
45.21
38.93
77.85
344.23

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.41
14.09
29.28
37.63
15.07
102.48

0.6
0.6

2.788
3.820

42.35
119.18
124.79
124.79

0.3

48.72
48.72

0.30
0.75
0.75

30.14
38.93
77.85
146.91

0.80

80.37
80.37

3.00
6.00

3.00
6.00

3.70

SAI Consulting Engineers Pvt. Ltd.

582 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 169+005
Length Width Depth

6.33
26.0

3.59
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.33

3.100

1020.40

SAI Consulting Engineers Pvt. Ltd.

583 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 169+175
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

584 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 169+175
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

585 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 169+175
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

586 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 169+175
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

587 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.63

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
255.38
345.62

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.63
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
18.24
24.09
60.12

Part - 2

cum
cum

4
4

5.63
5.63

5.20
1.70

0.50
0.10

58.55
3.83

Part - 3

cum

5.63

2.60

0.10

5.86

Part - 4

cum

5.63

0.90

0.20

4.05

Part - 5
Part - 6

cum
cum

4
4

5.63
5.63

0.30
0.60

3.69
1.84

72.29
24.91
24.91
49.83

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 169+320
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.88
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

588 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 169+320
Length Width Depth

Cum

km.
Quantity
91.18

Kg
Kg
Kg
Kg
T

75
75
120
2

91.18
122.11
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6838.13
9158.60
75.00
0.00
16.07

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

589 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 169+320
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.63
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

2.388
2.550

32.26
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

590 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 169+320
Length Width Depth

5.63
26.0

3.19
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

72
104
176

26

5.63

2.700

790.45

SAI Consulting Engineers Pvt. Ltd.

591 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 169+459
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

592 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 169+459
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

593 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 169+459
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

594 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 169+459
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

595 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

32.25
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

96.74
11.34
187.34
295.42

cum
cum
cum
cum
cum
cum

1
2
2
4
2

32.25
1.27
0.40
4.13
27.95

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

19.35
1.53
0.48
13.38
30.60
65.34

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

31.95
31.95
1.20
31.95
31.95
0.50
2.50
2.50
31.95
31.95

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 169+660
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

35.46
31.95
5.00
19.97
1.44
5.38
0.63
0.00
0.00
8.63

SAI Consulting Engineers Pvt. Ltd.

596 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 169+660
Length Width Depth

Cum

km.
Quantity
107.82

Kg
Kg
Kg
Kg
T

75
75
120
2

107.82
82.15
0.63
0.00

Cum
Cum

1
2

20.00
25.95

2.5
3.50

Sqm

20.00

2.5

cum

27.95

3.50

No
No

3.70

2
2

Rmt

27.9

55.90

8086.23
6160.93
75.00
0.00
14.32

0.05
0.05

2.50
9.08
11.58

231.64

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

58.69
58.69

SAI Consulting Engineers Pvt. Ltd.

597 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 169+660
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
31.95
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
97.76
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

598 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 169+660
Length Width Depth

4.13
31.9

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
128
170

31.948

4.13

1.950

514.59

SAI Consulting Engineers Pvt. Ltd.

599 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 170+188
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

600 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 170+188
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

601 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 170+188
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

602 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 170+188
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

603 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 170+317
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

604 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 170+317
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
8.40
10.90

218.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

605 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 170+317
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

606 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 170+317
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

607 of 734

Box Culvert
Description

Sr.
No
1

Unit

170+507
Depth

cum
cum
cum
cum

1
2
4

32.17
1.35
4.13

4.00
4.00
5.40

0.75000
1.05
2.10

cum
cum
cum
cum
cum
cum

1
2
2
4
2

32.17
1.27
0.40
4.13
27.87

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

Part - 3

cum

4.13

2.60

0.10

Part - 4

cum

4.13

0.90

0.20

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

31.87
31.87
1.20
31.87
31.87
0.50
2.50
2.50
31.87
31.87

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch
Length Width

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

SAI Consulting Engineers Pvt. Ltd.

608 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch
Length Width

170+507
Depth

Cum

Kg
Kg
Kg
Kg
T

75
75
120
2

107.58
82.15
0.63
0.00

Cum
Cum

1
2

20.00
29.87

2.5
3.50

Sqm

20.00

2.5

cum

27.87

3.50

No
No

3.70

Rmt

27.9

0.05
0.05

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
0.3

Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

609 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch
Length Width

170+507
Depth

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

0.75
0.30

0.20
1.10
1.693
2.175
0.15

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
31.87
7.76

0.6
0.6

1.638
2.550

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

3.00
6.00

1.30
2.15
2.65
0.45
0.75
0.75

0.3

3.00
6.00

0.30
0.75
0.75

0.80

2.50

SAI Consulting Engineers Pvt. Ltd.

610 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch
Length Width

4.13
31.9

170+507
Depth

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

31.87

4.13

1.950

SAI Consulting Engineers Pvt. Ltd.

611 of 734

km.
Quantity

96.51
11.34
187.34
295.19

19.30
1.53
0.48
13.38
30.52
65.21

42.95
2.81
4.30
2.97
53.03
14.56
14.56
29.12

35.38
31.87
5.00
19.92
1.43
5.38
0.63
0.00
0.00
8.60
DPR for Rehabilitation and Upgrading
Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

612 of 734

km.
Quantity
107.58

8068.39
6160.93
75.00
0.00
14.30

2.50
10.45
12.95

259.09

58.53
58.53

2
2

55.74

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

613 of 734

km.
Quantity

27.55
37.09
56.38
21.07
25.88
51.75
219.71

4.24
9.33
19.46
25.01
7.02
65.06

16.23
97.52
31.06
31.06

21.34
21.34

14.04
25.88
51.75
91.67

37.45
37.45
0

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

614 of 734

km.
Quantity

42
128
170

513.33

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

SAI Consulting Engineers Pvt. Ltd.

615 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.92
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

89.76
11.34
187.34
288.44

cum
cum
cum
cum
cum
cum

1
2
2
4
2

0.30
1.27
0.40
4.13
25.62

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

0.18
1.53
0.48
13.38
28.05
43.62

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.62
29.62
1.20
29.62
29.62
0.50
2.50
2.50
0.00
0.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 170+625
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.88
29.62
5.00
18.51
1.33
5.38
0.63
0.00
0.00
0.00

SAI Consulting Engineers Pvt. Ltd.

616 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 170+625
Length Width Depth

Cum

km.
Quantity
92.72

Kg
Kg
Kg
Kg
T

75
75
120
2

92.72
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.62

2.5
3.50

Sqm

20.00

2.5

cum

25.62

3.50

No
No

3.70

2
2

Rmt

25.6

51.24

6953.90
6160.93
75.00
0.00
13.19

0.05
0.05

2.50
8.27
10.77

215.34

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

53.80
53.80

SAI Consulting Engineers Pvt. Ltd.

617 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 170+625
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.62
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
90.64
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

618 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 170+625
Length Width Depth

4.13
0.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
0
42

29.62

4.13

1.950

477.09

SAI Consulting Engineers Pvt. Ltd.

619 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

29.56
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

88.68
11.34
187.34
287.36

cum
cum
cum
cum
cum
cum

1
2
2
4
2

29.56
1.27
0.40
4.13
25.26

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.74
1.53
0.48
13.38
27.66
60.78

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

29.26
29.26
1.20
29.26
29.26
0.50
2.50
2.50
29.26
29.26

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 170+860
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

32.48
29.26
5.00
18.29
1.32
5.38
0.63
0.00
0.00
7.90

SAI Consulting Engineers Pvt. Ltd.

620 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 170+860
Length Width Depth

Cum

km.
Quantity
99.62

Kg
Kg
Kg
Kg
T

75
75
120
2

99.62
82.15
0.63
0.00

Cum
Cum

1
2

20.00
23.26

2.5
3.50

Sqm

20.00

2.5

cum

25.26

3.50

No
No

3.70

2
2

Rmt

25.3

50.52

7471.35
6160.93
75.00
0.00
13.71

0.05
0.05

2.50
8.14
10.64

212.82

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

53.05
53.05

SAI Consulting Engineers Pvt. Ltd.

621 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 170+860
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
29.26
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
89.54
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

622 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 170+860
Length Width Depth

4.13
29.3

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
118
160

29.26

4.13

1.950

471.29

SAI Consulting Engineers Pvt. Ltd.

623 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.00
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

92.99
11.34
187.34
291.66

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.00
1.27
0.40
4.13
26.70

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.60
1.53
0.48
13.38
29.23
63.22

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.70
30.70
1.20
30.70
30.70
0.50
2.50
2.50
30.70
30.70

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 170+962
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

34.07
30.70
5.00
19.19
1.38
5.38
0.63
0.00
0.00
8.29

SAI Consulting Engineers Pvt. Ltd.

624 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 170+962
Length Width Depth

Cum

km.
Quantity
104.00

Kg
Kg
Kg
Kg
T

75
75
120
2

104.00
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.70

2.5
3.50

Sqm

20.00

2.5

cum

26.70

3.50

No
No

3.70

2
2

Rmt

26.7

53.39

7799.84
6160.93
75.00
0.00
14.04

0.05
0.05

2.50
8.64
11.14

222.87

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.06
56.06

SAI Consulting Engineers Pvt. Ltd.

625 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 170+962
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.70
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
93.93
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

626 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 170+962
Length Width Depth

4.13
30.7

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
124
166

30.696

4.13

1.950

494.42

SAI Consulting Engineers Pvt. Ltd.

627 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.38
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

94.15
11.34
187.34
292.83

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.38
1.27
0.40
4.13
27.08

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.83
1.53
0.48
13.38
29.66
63.88

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

31.08
31.08
1.20
31.08
31.08
0.50
2.50
2.50
31.08
31.08

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 171+225
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

34.50
31.08
5.00
19.43
1.40
5.38
0.63
0.00
0.00
8.39

SAI Consulting Engineers Pvt. Ltd.

628 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 171+225
Length Width Depth

Cum

km.
Quantity
105.18

Kg
Kg
Kg
Kg
T

75
75
120
2

105.18
82.15
0.63
0.00

Cum
Cum

1
2

20.00
25.08

2.5
3.50

Sqm

20.00

2.5

cum

27.08

3.50

No
No

3.70

2
2

Rmt

27.1

54.17

7888.59
6160.93
75.00
0.00
14.12

0.05
0.05

2.50
8.78
11.28

225.59

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.88
56.88

SAI Consulting Engineers Pvt. Ltd.

629 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 171+225
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
31.08
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
95.12
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

630 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 171+225
Length Width Depth

4.13
31.1

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
126
168

31.084

4.13

1.950

500.67

SAI Consulting Engineers Pvt. Ltd.

631 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 172+605
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

632 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 172+605
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

633 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 172+605
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
0.00
0.00
23.41
0.00
0.00

0.75
0.00
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
0.00
0.00
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
0.00
0.00
21.07
0.00
0.00
48.62

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
0.00
0.00
7.02
20.59

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

634 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 172+605
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

635 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

30.60
1.35
4.13

4.00
4.00
5.40

0.45
1.35
2.10

55.08
14.58
187.34
257.00

cum
cum
cum
cum
cum
cum

1
2
2
4
2

30.60
1.70
0.40
4.13
26.30

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.36
2.04
0.48
13.38
28.80
63.06

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.30
30.30
1.50
30.30
30.30
0.50
2.50
2.50
30.30
30.30

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
1.20
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 172+655
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
0.00

33.63
30.30
7.99
18.94
1.36
5.38
0.63
0.00
0.00
8.18

SAI Consulting Engineers Pvt. Ltd.

636 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 172+655
Length Width Depth

Cum

km.
Quantity
105.79

Kg
Kg
Kg
Kg
T

75
75
120
2

105.79
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.30

2.5
3.50

Sqm

20.00

2.5

cum

26.30

3.50

No
No

3.70

2
2

Rmt

26.3

52.60

7934.03
6160.93
75.00
0.00
14.17

0.05
0.05

2.50
8.51
11.01

220.10

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

55.23
55.23

SAI Consulting Engineers Pvt. Ltd.

637 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 172+655
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

0.00
11.50
11.50
23.41
11.50
11.50

0.75
1.50
0.00

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

0.00
0.00
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.30
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
0.00
0.45
0.75
0.75

0.00
37.09
0.00
21.07
25.88
51.75
135.78

0.75
0.30

0.20
1.10
1.693
2.175
0.15

0.00
0.00
19.46
25.01
7.02
51.50

0.6
0.6

1.638
2.550

16.23
92.72
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

638 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 172+655
Length Width Depth

4.13
30.3

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
122
164

30.3

4.13

1.950

488.04

SAI Consulting Engineers Pvt. Ltd.

639 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 172+845
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

640 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 172+845
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

641 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 172+845
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

642 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 172+845
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

643 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

37.94
1.35
4.13

4.00
4.00
5.40

0.75000
1.05
2.10

113.82
11.34
187.34
187.34

cum
cum
cum
cum
cum
cum

1
2
2
4
2

37.94
1.27
0.40
4.13
33.64

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

22.76
1.53
0.48
13.38
36.84
74.99

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

37.64
37.64
1.20
37.64
37.64
0.50
2.50
2.50
37.64
37.64

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 173+225
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

41.78
37.64
5.00
23.53
1.69
5.38
0.63
0.00
0.00
10.16

SAI Consulting Engineers Pvt. Ltd.

644 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 173+225
Length Width Depth

Cum

km.
Quantity
125.18

Kg
Kg
Kg
Kg
T

75
75
120
2

125.18
82.15
0.63
0.00

Cum
Cum

1
2

20.00
31.64

2.5
3.50

Sqm

20.00

2.5

cum

33.64

3.50

No
No

3.70

2
2

Rmt

33.6

67.28

9388.28
6160.93
75.00
0.00
15.62

0.05
0.05

2.50
11.07
13.57

271.48

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

70.64
70.64

SAI Consulting Engineers Pvt. Ltd.

645 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 173+225
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
37.64
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
115.18
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

646 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 173+225
Length Width Depth

4.13
37.6

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
152
194

37.64

4.13

1.950

606.27

SAI Consulting Engineers Pvt. Ltd.

647 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.04
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

144.21
11.72
285.77
441.69

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.04
1.10
0.40
6.30
26.74

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

24.86
1.77
0.64
20.41
29.28
76.96

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.74
30.74
1.08
30.74
30.74
0.50
3.84
3.84
30.74
30.74

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 173+675
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

65.07
77.46
5.43
49.58
1.38
8.22
0.96
0.00
0.00
8.30

SAI Consulting Engineers Pvt. Ltd.

648 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 173+675
Length Width Depth

Cum

km.
Quantity
215.44

Kg
Kg
Kg
Kg
T

75
75
120
2

215.44
143.00
0.96
0.00

Cum
Cum

1
2

20.00
24.74

3.84
3.50

Sqm

20.00

3.84

cum

26.74

3.50

No
No

5.04

4
4

Rmt

26.7

53.48

16158.06
10724.81
115.20
0.00
27.00

0.05
0.05

3.84
8.66
12.50

249.98

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.15
56.15

SAI Consulting Engineers Pvt. Ltd.

649 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 173+675
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
30.74
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
141.65
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

650 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 173+675
Length Width Depth

6.30
30.7

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
186
278

30.74

6.30

3.120

1208.45

SAI Consulting Engineers Pvt. Ltd.

651 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.04

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
273.97
407.88

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.04
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
19.57
24.09
67.13

Part - 2

cum
cum

4
4

6.04
6.04

5.20
1.70

0.50
0.10

62.82
4.11

Part - 3

cum

6.04

2.60

0.10

6.28

Part - 4

cum

6.04

0.90

0.20

4.35

Part - 5
Part - 6

cum
cum

4
4

6.04
6.04

0.30
0.60

3.98
1.99

77.55
28.83
28.83
57.66

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
15.92
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 173+830
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
7.96
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

652 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 173+830
Length Width Depth

Cum

km.
Quantity
184.06

Kg
Kg
Kg
Kg
T

75
75
120
2

184.06
135.21
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13804.85
10140.86
115.20
0.00
24.06

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

653 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 173+830
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.04
26.00
31.80

cum
cum

0.00

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.678
3.840

38.81
119.81
127.22
127.22

3.00
6.00

3.00
6.00

3.84

0.3

0.00
0.00

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62
0

SAI Consulting Engineers Pvt. Ltd.

654 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 173+830
Length Width Depth

6.04
26.0

3.48
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

86
156
242

26

6.04

2.990

939.10

SAI Consulting Engineers Pvt. Ltd.

655 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
6.13

0.00
0.00
5.40

0.75
1.05
2.10

0.00
0.00
278.06
278.06

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
6.13
22.00

0.00
0.00
0.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

0.00
0.00
0.00
19.86
24.09
43.95

Part - 2

cum
cum

4
4

6.13
6.13

5.20
1.70

0.50
0.10

63.75
4.17

Part - 3

cum

6.13

2.60

0.10

6.38

Part - 4

cum

6.13

0.90

0.20

4.41

Part - 5
Part - 6

cum
cum

4
4

6.13
6.13

0.30
0.60

3.94
1.97

78.71
28.96
28.96
57.93

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
14.76
0.125
0.75
0.00
0.14

0.30
3.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 174+009
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

28.86
39.00
5.00
16.25
1.17
7.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

656 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 174+009
Length Width Depth

Cum

km.
Quantity
104.68

Kg
Kg
Kg
Kg
T

75
75
120
2

104.68
136.64
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

7850.63
10247.83
75.00
0.00
18.17

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

657 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 174+009
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.21
15.50
15.50
39.07
15.50
15.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.21
10.21
15.50
15.50
39.07

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.13
26.00
26.88

cum
cum

37.10

cum
cum
cum
cum

2
1
1

39.07
15.50
15.50

cum
cum

39.07

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

39.80
49.99
75.99
35.16
0.00
69.75
270.69

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.12
13.47
26.23
33.71
11.72
91.26

0.6
0.6

2.638
3.550

38.80
110.76
107.54
107.54

0.3

44.51
44.51

0.30
0.75
0.75

23.44
0.00
69.75
93.19

0.80

62.51
62.51

0.00
6.00

0.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

658 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 174+009
Length Width Depth

6.13
26.0

3.44
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

86
156
242

26

6.13

2.950

940.34

SAI Consulting Engineers Pvt. Ltd.

659 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

34.99
1.18
6.30

5.34
5.34
5.40

0.72
0.78
2.10

134.53
9.83
285.77
430.13

cum
cum
cum
cum
cum
cum

1
2
2
4
2

34.99
1.10
0.40
6.30
30.69

5.34
5.34
5.34
5.40
3.65

0.00
0.00
0.15
0.00
0.00

0.00
0.00
0.64
0.00
0.00
0.64

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

34.69
34.69
1.08
34.69
34.69
0.50
3.84
3.84
34.69
34.69

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 174+262
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

73.43
87.42
5.43
55.95
1.56
8.22
0.96
0.00
0.00
9.37

SAI Consulting Engineers Pvt. Ltd.

660 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 174+262
Length Width Depth

Cum

km.
Quantity
241.37

Kg
Kg
Kg
Kg
T

75
75
120
2

241.37
143.00
0.96
0.00

Cum
Cum

1
2

20.00
28.69

3.84
3.50

Sqm

20.00

3.84

cum

30.69

3.50

No
No

5.04

4
4

Rmt

30.7

61.38

18102.83
10724.81
115.20
0.00
28.94

0.05
0.05

3.84
10.04
13.88

277.63

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

64.45
64.45

SAI Consulting Engineers Pvt. Ltd.

661 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 174+262
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
34.69
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
0.00
270.17

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
159.85
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
0.00
70.40

0.65

67.13
67.13

3.00
0.00

3.00
0.00

3.84

SAI Consulting Engineers Pvt. Ltd.

662 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 174+262
Length Width Depth

6.30
34.7

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
210
302

34.69

6.30

3.120

1363.73

SAI Consulting Engineers Pvt. Ltd.

663 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

31.08
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

144.39
11.72
285.77
441.88

cum
cum
cum
cum
cum
cum

1
2
2
4
2

31.08
1.10
0.40
6.30
26.78

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

24.90
1.77
0.64
20.41
29.32
77.04

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.78
30.78
1.08
30.78
30.78
0.50
3.84
3.84
30.78
30.78

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 174+345
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

65.16
77.57
5.43
49.64
1.39
8.22
0.96
0.00
0.00
8.31

SAI Consulting Engineers Pvt. Ltd.

664 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 174+345
Length Width Depth

Cum

km.
Quantity
215.70

Kg
Kg
Kg
Kg
T

75
75
120
2

215.70
143.00
0.96
0.00

Cum
Cum

1
2

20.00
24.78

3.84
3.50

Sqm

20.00

3.84

cum

26.78

3.50

No
No

5.04

4
4

Rmt

26.8

53.56

16177.76
10724.81
115.20
0.00
27.02

0.05
0.05

3.84
8.67
12.51

250.26

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

56.24
56.24

SAI Consulting Engineers Pvt. Ltd.

665 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 174+345
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
30.78
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.00
0.00

41.88
56.50
85.89
46.48
0.00
0.00
230.75

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
141.83
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

666 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 174+345
Length Width Depth

6.30
30.8

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
186
278

30.78

6.30

3.120

1210.02

SAI Consulting Engineers Pvt. Ltd.

667 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 174+425
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

668 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 174+425
Length Width Depth

Cum

km.
Quantity
184.32

Kg
Kg
Kg
Kg
T

75
75
120
2

184.32
143.00
0.00
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13824.35
10724.81
0.00
0.00
24.55

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

669 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 174+425
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.00
0.75
0.75

41.88
56.50
85.89
0.00
39.42
78.84
302.54

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

0.00

SAI Consulting Engineers Pvt. Ltd.

670 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 174+425
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

671 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
5.59

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
253.56
343.80

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
5.59
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
18.11
24.09
59.99

Part - 2

cum
cum

4
4

5.59
5.59

5.20
1.70

0.50
0.10

58.14
3.80

Part - 3

cum

5.59

2.60

0.10

5.81

Part - 4

cum

5.59

0.90

0.20

4.02

Part - 5
Part - 6

cum
cum

4
4

5.59
5.59

0.30
0.60

3.67
1.83

71.78
24.60
24.60
49.20

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
13.68
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 175+220
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
6.84
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

672 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 175+220
Length Width Depth

Cum

km.
Quantity
91.14

Kg
Kg
Kg
Kg
T

75
75
120
2

91.14
120.98
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6835.13
9073.41
75.00
0.00
15.98

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

673 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 175+220
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

5.59
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

0.20
2.15
2.65
0.45
0.75
0.75

4.24
37.09
56.38
21.07
25.88
51.75
196.40

0.75
0.30

0.20
0.00
1.693
2.175
0.15

4.24
0.00
19.46
25.01
7.02
55.74

0.6
0.6

2.368
2.550

31.76
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

674 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 175+220
Length Width Depth

5.59
26.0

3.17
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

72
104
176

26

5.59

2.680

779.02

SAI Consulting Engineers Pvt. Ltd.

675 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

30.54
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

91.63
11.34
187.34
290.30

cum
cum
cum
cum
cum
cum

1
2
2
4
2

30.54
1.27
0.40
4.13
26.24

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

18.33
1.53
0.48
13.38
28.73
62.45

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

30.24
30.24
1.20
30.24
30.24
0.50
2.50
2.50
30.24
30.24

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 175+370
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

33.57
30.24
5.00
18.90
1.36
5.38
0.63
0.00
0.00
8.17

SAI Consulting Engineers Pvt. Ltd.

676 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 175+370
Length Width Depth

Cum

km.
Quantity
102.61

Kg
Kg
Kg
Kg
T

75
75
120
2

102.61
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.24

2.5
3.50

Sqm

20.00

2.5

cum

26.24

3.50

No
No

3.70

2
2

Rmt

26.2

52.48

7695.98
6160.93
75.00
0.00
13.93

0.05
0.05

2.50
8.48
10.98

219.69

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

55.11
55.11

SAI Consulting Engineers Pvt. Ltd.

677 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 175+370
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.00
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
30.24
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

0.00
37.09
56.38
21.07
25.88
51.75
192.16

0.00
0.30

0.20
1.10
1.693
2.175
0.15

0.00
9.33
19.46
25.01
7.02
60.82

0.6
0.6

1.638
2.550

16.23
92.54
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

678 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 175+370
Length Width Depth

4.13
30.2

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
122
164

30.242

4.13

1.950

487.11

SAI Consulting Engineers Pvt. Ltd.

679 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 176+015
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

680 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 176+015
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

681 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 176+015
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
0.00
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
0.00

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

0.00
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
0.00
25.88
51.75
198.64

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
0.00
58.04

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

0.00
25.88
51.75
77.63

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

682 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 176+015
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

683 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 176+600
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

684 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 176+600
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

685 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 176+600
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

686 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 176+600
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

687 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

28.85
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

86.56
11.34
187.34
285.23

cum
cum
cum
cum
cum
cum

1
2
2
4
2

28.85
1.27
0.40
4.13
24.55

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

17.31
1.53
0.48
13.38
26.88
59.58

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

28.55
28.55
1.20
28.55
28.55
0.50
2.50
2.50
28.55
28.55

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 176+770
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

31.69
28.55
5.00
17.85
1.28
5.38
0.63
0.00
0.00
7.71

SAI Consulting Engineers Pvt. Ltd.

688 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 176+770
Length Width Depth

Cum

km.
Quantity
97.46

Kg
Kg
Kg
Kg
T

75
75
120
2

97.46
82.15
0.63
0.00

Cum
Cum

1
2

20.00
22.55

2.5
3.50

Sqm

20.00

2.5

cum

24.55

3.50

No
No

3.70

2
2

Rmt

24.6

49.10

7309.40
6160.93
75.00
0.00
13.55

0.05
0.05

2.50
7.89
10.39

207.86

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

51.56
51.56

SAI Consulting Engineers Pvt. Ltd.

689 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 176+770
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
28.55
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
87.37
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

690 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 176+770
Length Width Depth

4.13
28.6

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
116
158

28.552

4.13

1.950

459.89

SAI Consulting Engineers Pvt. Ltd.

691 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 177+064
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

692 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 177+064
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
20.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
7.00
9.50

190.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

693 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 177+064
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

694 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 177+064
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

695 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.18
6.30

5.34
5.34
5.40

0.87
0.93
2.10

122.18
11.72
285.77
419.67

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.10
0.40
6.30
22.00

5.34
5.34
5.34
5.40
3.65

0.15
0.15
0.15
0.15
0.15

21.07
1.77
0.64
20.41
24.09
67.98

Part - 2

cum
cum

4
4

6.30
6.30

5.20
1.70

0.50
0.10

65.52
4.28

Part - 3

cum

6.30

2.60

0.10

6.55

Part - 4

cum

6.30

0.90

0.20

4.54

Part - 5
Part - 6

cum
cum

4
4

6.30
6.30

0.30
0.60

4.11
2.05

80.89
31.05
31.05
62.11

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.08
26.00
26.00
0.50
3.84
3.84
26.00
26.00

5.04
0.42
5.04
3.84
0.01125
16.44
0.125
0.75
0.00
0.14

0.42
3.00
0.78
0.42

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 177+427
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 3.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
3.00

55.04
65.52
5.43
41.93
1.17
8.22
0.96
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

696 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 3.0
Nos

m.
Pro.Ch 177+427
Length Width Depth

Cum

km.
Quantity
184.32

Kg
Kg
Kg
Kg
T

75
75
120
2

184.32
143.00
0.96
0.00

Cum
Cum

1
2

20.00
20.00

3.84
3.50

Sqm

20.00

3.84

cum

22.00

3.50

No
No

5.04

4
4

Rmt

22.0

44.00

13824.35
10724.81
115.20
0.00
24.66

0.05
0.05

3.84
7.00
10.84

216.80

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

697 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 177+427
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

10.74
17.52
17.52
51.64
17.52
17.52

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

10.74
10.74
17.52
17.52
51.64

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

6.30
26.00
31.80

cum
cum

41.08

cum
cum
cum
cum

2
1
1

51.64
17.52
17.52

cum
cum

51.64

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 3.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

41.88
56.50
85.89
46.48
39.42
78.84
349.01

0.75
0.30

0.20
1.10
1.693
2.175
0.15

6.44
14.18
29.65
38.11
15.49
103.87

0.6
0.6

2.808
3.840

42.45
119.81
127.22
127.22

0.3

49.29
49.29

0.30
0.75
0.75

30.98
39.42
78.84
149.24

0.80

82.62
82.62

3.00
6.00

3.00
6.00

3.84

SAI Consulting Engineers Pvt. Ltd.

698 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 3.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 177+427
Length Width Depth

6.30
26.0

3.61
3.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

92
156
248

26

6.30

3.120

1022.11

SAI Consulting Engineers Pvt. Ltd.

699 of 734

Box Culvert
Description

Sr.
No
1

Unit

km.
Quantity

cum
cum
cum
cum

1
2
4

26.30
1.35
4.13

4.00
4.00
5.40

0.75
1.05
2.10

78.90
11.34
187.34
277.58

cum
cum
cum
cum
cum
cum

1
2
2
4
2

26.30
1.27
0.40
4.13
22.00

4.00
4.00
4.00
5.40
3.65

0.15
0.15
0.15
0.15
0.15

15.78
1.53
0.48
13.38
24.09
55.26

Part - 2

cum
cum

4
4

4.13
4.13

5.20
1.70

0.50
0.10

42.95
2.81

Part - 3

cum

4.13

2.60

0.10

4.30

Part - 4

cum

4.13

0.90

0.20

2.97

Part - 5
Part - 6

cum
cum

4
4

4.13
4.13

0.30
0.60

2.94
1.47

53.03
14.56
14.56
29.12

cum
cum
cum
cum
cum
cum
cum

1
2
2
1
4
2
2
0
0
2

26.00
26.00
1.20
26.00
26.00
0.50
2.50
2.50
26.00
26.00

3.70
0.25
3.70
2.5
0.01125
10.76
0.125
0.75
0.00
0.14

0.30
2.00
0.90
0.25

Total
Cement concrete M-25 grade in foundation/
levelling course in bridge/pipe culvert and
levelling course below approach slab etc.
including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1500 & 1700.
Box Portion
Key Portion
Retaining Wall
PCC For Approach slab

m.
Pro.Ch 177+573
Length Width Depth

Earthwork in excavation of foundation for


structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Box Portion
Key Portion
Retaining Wall

1 x 2.0
Nos

Total
Cement concrete M-25 grade in RCC return
wall including centering and shuttering all
complete as per drawing and Technical
Specifications Sections 1700, 2100 and
2900.
A. Foundation
Part - 1

B. Substructure

Reinforced cement concrete M-30 grade


including centering & shuttering but
excluding the cost of reinforcement, all
complete as per drawings and Technical
Specification
Sections 1700, 2100 and
2900.
Box Portion (Bottom Slab with Projection)
Box Portion (Side Wall)
Key Portion
Top Slab
Fillet
Perapet wall
Crash Barrier/kurb
Safety kerb
inner Wall
Corbel for approach slab

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

cum
cum

0.5
0.3
2.00

28.86
26.00
5.00
16.25
1.17
5.38
0.63
0.00
0.00
7.02

SAI Consulting Engineers Pvt. Ltd.

700 of 734

Box Culvert
Description

Sr.
No
5

Total
HYSD/TMT bar reinforcement for culverts,
underpass, retaining walls etc. complete as
per drawings and Technical Specifications
Section 1600.
Box (75 kg/cmt)
Retaining Wall
Parapet wall (120 kg/cmt)
Safety kerb (120 kg/cmt)

Total
6 A Providing and laying 50mm thick bituminous
concrete wearing coat in two layers over the
top of deck slab complete as per drawings
and Technical Specification Section 500 and
2700.
Road
Approach Slab
Total
6 B Providing and laying a layer of 12mm thick
Mastic Asphalt as per drawing and
Tech./spn.
7

1 x 2.0
Nos

m.
Pro.Ch 177+573
Length Width Depth

Cum

km.
Quantity
89.68

Kg
Kg
Kg
Kg
T

75
75
120
2

89.68
82.15
0.63
0.00

Cum
Cum

1
2

20.00
24.00

2.5
3.50

Sqm

20.00

2.5

cum

22.00

3.50

No
No

3.70

2
2

Rmt

22.0

44.00

6725.63
6160.93
75.00
0.00
12.96

0.05
0.05

2.50
8.40
10.90

218.00

Reinforced cement concrete M-30 grade in


approach slab including reinforcement for
bridges complete as per drawing and
Technical Specifications Clause 2704.
Total
Providing and fixing drainage spouts for
bridges as per Drawing and Technical
Specifications Clause 2705.
1 no. per 5.0m

Unit

Total
Providing and laying Filler Type expansion
joints complete as per drawing & Technical
Specification Section 2605.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

0.3

46.20
46.20

SAI Consulting Engineers Pvt. Ltd.

701 of 734

Sr.
No
1

Box Culvert
Description

Unit

m.
Pro.Ch 177+573
Length Width Depth

km.
Quantity

Protection Work For Box


Earthwork in excavation of foundation for
structures/bridges including pipe culverts in
all types of soil complete as per drawings
and Technical Specifications Clauses 304,
309 & 2903.
Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Cement
concrete
M-15
grade
in
foundation/ levelling course in bridge/pipe
culvert and levelling course below approach
slab etc. including centering and shuttering
all complete as per drawing and Technical
Specifications Sections 1500 & 1700.

cum
cum
cum
cum
cum
cum
cum

4
1
1
2
1
1

7.07
11.50
11.50
23.41
11.50
11.50

0.75
1.50
1.85

Toe Wall at Both Side ( Parallel to Flow)


Toe Wall at Both Side ( Parallel to Flow)
Curtain wall for U/S side
Curtain wall for D/S side
Apron Portion
Total
Filter material underneath stone pitching
on slopes complete as per drawing and
Technical Specifications Section 2500.

cum
cum
cum
cum
cum
cum

4
4
1
1
2

7.07
7.07
11.50
11.50
23.41

Behind return wall


Behind Side wall
Cone Shape

cum
cum
cum
cum

4
2
4

4.13
26.00
7.76

cum
cum

17.78

cum
cum
cum
cum

2
1
1

23.41
11.50
11.50

cum
cum

23.41

Total
Stone Pitching 300 mm thick on slopes
as
per
drawings
and
Technical
Specifications Section 2500.
Cone Shape
Total
Stone boulder apron 300 mm thick
complete as per drawings and Technical
Specifications Clause 2503
Floor Apron
Flexible Apron for U/S side
Flexible Apron for D/S side
Total
Providing and laying compacted earth
filling
as per Section 2500 of MOST
specification for Road & Bridge work.
Total

1 x 2.0
Nos

65 NB GI Pipe above Crash Barrier

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

RM

1.30
2.15
2.65
0.45
0.75
0.75

27.55
37.09
56.38
21.07
25.88
51.75
219.71

0.75
0.30

0.20
1.10
1.693
2.175
0.15

4.24
9.33
19.46
25.01
7.02
65.06

0.6
0.6

1.638
2.550

16.23
79.56
31.06
31.06

0.3

21.34
21.34

0.30
0.75
0.75

14.04
25.88
51.75
91.67

0.80

37.45
37.45

3.00
6.00

3.00
6.00

2.50

SAI Consulting Engineers Pvt. Ltd.

702 of 734

Box Culvert
Description

Sr.
No
8

Unit

Weep Holes
Return wall
Side wall of box

1 x 2.0
Nos

No
No

4
2

Painting of culvert number and span


arrangement as per Technical Specification
Secion 800.

No.

Providing Back filling behind abutment,


wing wall and return wall with Granular
Material complete as per drawing and
Technical specification and as per relevant
clauses 305 of specifications and as per
appendix 6 of IRC-78

cum

m.
Pro.Ch 177+573
Length Width Depth

4.13
26.0

2.44
2.00

Total
9

10

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar (Package-3)

km.
Quantity

42
104
146

26

4.13

1.950

418.78

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

6D.01 Earthwork in Excavation of foundation for structure


complete as per drawing and Technical Specification
Clause 304.
(i) in all types of soil)

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

0-3 depth
3-6 depth
(ii) in rock (blasting not requred)
6D.02 Cement concrete for plain/ reinforced concrete in
foundation (leveling course) below head wall complete
as per drawing and Technical Specification Sections
1700, 2100 and 2900.

Cu.m.

M-15
M-20
6D.03 Structural cement concrete for plain / reinforced
concrete for foundation including formwork, machinery
and workmanship complete as per drawing and
Technical Specification Sections 1500, 1700 and 2100.

Cu.m.
Cu.m.

(a) In foundation
(i) PCC M-20
(ii) RCC M-25
(iii) RCC M-30
(iv) M-35

Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-15
(ii) a PCC M-20
(ii) b RCC M-20
(iii) RCC M-25
(iv) RCC M-30
(v) RCC M-35
(v) RCC M-40

Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-20
(ii) M-25

Cu.m.
Cu.m.

(b) Substructure

(c) Super-structure

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

(iii) M-30 (Solid Slab)


M-30 (T-Beam)
(iv) M-35
(v) M-40 and above

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

RM
Cu.m.
Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.
Cu.m.
Cu.m.
Cu.m.

6D.04 Pre-stressed cement concrete T Girder/Box Girder in


superstructure complete as per drawing and Technical
Specifications Sections 1500, 1700 & 1800 excluding
reinforcement and H.T. strands.
(i) M-45
(ii) M-45 (Box Girder)
6D.05 Reinforced cement concrete M 30 in approach slab
including reinforcement complete as per drawing and
Technical Specification Section 1500, 1700 and 2700.

Cu.m.
Cu.m.

6D.06 Reinforced cement concrete crash barrier / railings


complete as per drawings and Technical Specification
Sections 1500, 1600, 1700 and 2700.
(a) RCC M-30 Precast Railing
(b) M-40 grade crash barrier
(c) M-30 grade kerbs
6D.07 Providing and fixing in position HYSD/TMT deformed
bars reinforcement complete as per drawing and
Technical Specification Section 1600.
a) Foundation

MT

b) Sub structure

MT

b) Super structure

MT

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.08 Low relaxation HT strands in post tensioned box


girder/T-beam girder including sheathing, anchorages,
prestressing and grouting complete as per drawing and
Technical Specification Section 1800.
Strands
6D.09 Providing and fixing tar paper bearing complete as per
Technical Specification Section 2000.

MT
sq.m.

6D.10 Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC 83 (Part II)
Section IV complete with all accessories as per drawing
& Technical Specifications Clause 2005.
cu.cm.
6D.11 Supplying , fitting and fixing bearings in position true to
line and level complete as per drawing and Technical
Specification Section 2000.
(i) POT/POT- PTFE bearing for Bridges (fixed)
(ii) POT/POT- PTFE bearing for Bridges (free/guided)
(iii) Pin bearing
6D.12 Providing and laying of strip seal expansion joints
complete as per drawing & Technical Specification
Section 2600.(40 mm)
6D.13 Providing and laying Filler Type expansion joints
complete as per drawing & Technical Specification
Section 2605.
6D.14 Providing and laying 50mm thick bituminous concrete
wearing coat in two layers over the top of deck slab
complete as per drawings and Technical Specification
Section 500 and 2700.

ton
ton
ton

RM

RM

Cu.m.

6D.15 Providing and laying a layer of 15mm thick Mastic


Asphalt as per drawing and Tech./spn.
sq.m.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.16 Drainage spouts of 100 mm diameter complete as per


drawing and Technical Specification Clause 2705.
No.
6D.17 Providing AC weepholes in retaining walls, abutments
and return walls complete as per drawings and
Technical Specification Clause 2706.
No.
6D.18 Providing and laying of R.C.C (M-20) in footpath, kerb
etc. excluding reinforcement as per drawing and
Technical specifications Sections 1500 & 1700
Cu.m.
6D.19 a) Dismantling damaged expansion joints, providing
and laying asphaltic plug type expansion joint in
existing bridges conforming to MoRTH Modified Interim
Specifications for expansion joints, to be installed under
supervision of specialist manufacturer
m
6D.20 b) Providing buried type expansion joints in
new/existing bridges complete as per approved drawing
and MoRTH Interim Specifications for expansion joints
to be installed under supervision of specialist
manufacturer as per Technical Specifications Clause A

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.21 Providing and laying of asphaltic plug joint to provide for


horizontal movement of 25 mm and vertical movement
of 2 mm, depth of joint varying from 75 mm to 100 mm,
width varying from 500 mm to 750 mm (in traffic
direction), covered with a closure plate of 200mm x
6mm of wieldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder,
carefully selected single size
aggregate of 12.5 mm nominal size and a heat resistant
foam caulking/backer rod,
all as per approved
drawings and specifications and as per relevant clauses
of Section 2600.
m
6D.22 Back filling behind abutments, wing walls and return
walls with selected granular material of approved
quality including all material, labour, equipment carriage
etc. all complete as per drawing and Technical
Specifications Clause 305.
6D.23 Providing and laying 600mm Thick Filter layer behind
Abutments and Retaining walls as per drawings,
complete. As per MoRT&H technical specification
section 2500.
6D.24 Filter Media Underneath Pitching in Slopes complete
as per drawing and Technical Specification Clause
2504.
6D.25 Providing and laying Stone Pitching on Embankment
Slopes for cone protection laying dry all complete as
per Technical Specification Clause 2504.
Cu.m.
6D.26 Bored cast in situ M 35 grade RCC pile of 1200 mm
dia. excluding reinforcement complete as per drawing
and technical specifications and removal of excavated
earth with all lifts and lead upto 1000 m
RM

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

#REF!
Additional in rock
1200 dia
1000 dia
750 dia
M-35 conc.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

RM
m
m
m
Cu.m.

6D.27 Load Testing


including loading with necessary
kentledge or any other suitable method as directed.
a) Initial test (2 piles )
b) Routine test (2 piles )
c) lateral load test (2 piles )
6D.28 Reinforced cement concrete M-30 in pile cap excluding
reinforcement complete as per drawings & Technical
Specifications Clause 1114, Sections 1500 & 1700.
M-30
M35
6D.29 Providing steel liner 6 mm thick for pile including
fabricating and setting out as per detailed drawing

M.T
M.T
M.T

Cu.m.

MT
6D.30 Sinking of wells through all type of soils and rock to be
measured from low water level (other then pneumatic
method of sinking) complete as per drawing and
Techncial Specifications Clause 1200.
(a) for 8 M dia well
(i) Depth 0-3 m.
(ii) Depth 3-10m
(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.
(b) for 7 M dia well
(i) Depth 0-3 m.
DPR for Rehabilitation and Upgrading
Munger-Bhagalpur-Mirzachauki NH-80 Bihar

m
m
m
m
m
m
m
m
SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

(ii) Depth 3-10m


(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.

Unit

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

m
m
m
m
m
m

6D.31 Providing and laying cutting edge of mild steel for well
foundation for bridges as per drawings and Technical
Specifications clause 1200 and 1900.

MT.

6D.32 Sand filling in wells as per drawings and technical


Specifications clause 1200.

Cu.m.

6D.33 Cement concrete for plains concrete reinforcement


concrete complete as per drawings and technical
Specifications (Excluding steel reinforcement) clause
1200, 1500, 1700.
(a) Well curb
- M-30
(b) Well cap
- M-35
(c) Bottom plug - M-15
(d) Intermediate plug
- M-30
(e) Well steining- RCC M-30
6D.34 Providing and laying chequered tiles/cota stone/IPS
flooring complete as per details

Cu m.
Cu m.
Cu m.
Cu m.
Cu m.

a) Chequered tiles
6D.35 Providing ,fixing,erecting and painting 65 NB GI pipe on
concrete crash barrier as per approved drawing and
Technical Specification Section 2700.

sq.m.

6D.36 Supply installance testing and commissioning of


External Light Pole including fitting clamp fixture, cable
earthing etc. complete as shown in drawing.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

RM

No.

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.37 Providing and applying 2 coats of water based cement


paint to unplastered concrete surface after cleaning the
surface of dirt,dust,oil grease, efflorescence and
applying paint @ 1 litre for 2 sq.m as per Technical
Specification Secion 800.
SQMT
6D.38 PVC Downtake pipe for drainage

RM

6D.39 Painting of structure number, span arrangement and


flow direction complete as per drawings and Technical
Specification Section 800.

No.

6D.40 Dismantling stone/cement masonary of parapets, piers,


return wall, abutment, wingwalls and arches in cement /
lined mortar including sorting the dismantled material,
disposal of unserviceable material and stacking the
serviceable material within a lead of 100 m
a.
b.

Epoxy bonding of new concrete to old concrete


sealing of crack/porous concrete with Epoxy Grout by
injection through niples complete as per clause 2803.1

c.

Replacement of the expansion joints complete as per


drawings

cum
Sqmt

kg

d.
Replacement of the damaged concrte railing.
e.
Replacement of the crash barrier
6D.41 Laying 300mm thick stone apron complete as per
drawings and Technical Specification Clause 2503.
6D.42 Providing and laying Compacted Earth Filling as per
Section 2500 of MOST specification for Road & Bridge
work.
6D.43 Structural Steelwork in superstructure including painting
as per technical specification Section 1900 (painting
shall conform to System (v) , Table 1900-3)

cum

cum

MT

Total

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

6D.01 Earthwork in Excavation of foundation for structure


complete as per drawing and Technical Specification
Clause 304.
(i) in all types of soil)

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

0-3 depth
3-6 depth
(ii) in rock (blasting not requred)
6D.02 Cement concrete for plain/ reinforced concrete in
foundation (leveling course) below head wall complete
as per drawing and Technical Specification Sections
1700, 2100 and 2900.

Cu.m.

M-15
M-20
6D.03 Structural cement concrete for plain / reinforced
concrete for foundation including formwork, machinery
and workmanship complete as per drawing and
Technical Specification Sections 1500, 1700 and 2100.

Cu.m.
Cu.m.

(a) In foundation
(i) PCC M-20
(ii) RCC M-25
(iii) RCC M-30
(iv) M-35

Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-15
(ii) a PCC M-20
(ii) b RCC M-20
(iii) RCC M-25
(iv) RCC M-30
(v) RCC M-35
(v) RCC M-40

Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-20
(ii) M-25

Cu.m.
Cu.m.

(b) Substructure

(c) Super-structure

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

(iii) M-30 (Solid Slab)


M-30 (T-Beam)
(iv) M-35
(v) M-40 and above

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

RM
Cu.m.
Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.
Cu.m.
Cu.m.
Cu.m.

6D.04 Pre-stressed cement concrete T Girder/Box Girder in


superstructure complete as per drawing and Technical
Specifications Sections 1500, 1700 & 1800 excluding
reinforcement and H.T. strands.
(i) M-45
(ii) M-45 (Box Girder)
6D.05 Reinforced cement concrete M 30 in approach slab
including reinforcement complete as per drawing and
Technical Specification Section 1500, 1700 and 2700.

Cu.m.
Cu.m.

6D.06 Reinforced cement concrete crash barrier / railings


complete as per drawings and Technical Specification
Sections 1500, 1600, 1700 and 2700.
(a) RCC M-30 Precast Railing
(b) M-40 grade crash barrier
(c) M-30 grade kerbs
6D.07 Providing and fixing in position HYSD/TMT deformed
bars reinforcement complete as per drawing and
Technical Specification Section 1600.
a) Foundation

MT

b) Sub structure

MT

b) Super structure

MT

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.08 Low relaxation HT strands in post tensioned box


girder/T-beam girder including sheathing, anchorages,
prestressing and grouting complete as per drawing and
Technical Specification Section 1800.
Strands
6D.09 Providing and fixing tar paper bearing complete as per
Technical Specification Section 2000.

MT
sq.m.

6D.10 Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC 83 (Part II)
Section IV complete with all accessories as per drawing
& Technical Specifications Clause 2005.
cu.cm.
6D.11 Supplying , fitting and fixing bearings in position true to
line and level complete as per drawing and Technical
Specification Section 2000.
(i) POT/POT- PTFE bearing for Bridges (fixed)
(ii) POT/POT- PTFE bearing for Bridges (free/guided)
(iii) Pin bearing
6D.12 Providing and laying of strip seal expansion joints
complete as per drawing & Technical Specification
Section 2600.(40 mm)
6D.13 Providing and laying Filler Type expansion joints
complete as per drawing & Technical Specification
Section 2605.
6D.14 Providing and laying 50mm thick bituminous concrete
wearing coat in two layers over the top of deck slab
complete as per drawings and Technical Specification
Section 500 and 2700.

ton
ton
ton

RM

RM

Cu.m.

6D.15 Providing and laying a layer of 15mm thick Mastic


Asphalt as per drawing and Tech./spn.
sq.m.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.16 Drainage spouts of 100 mm diameter complete as per


drawing and Technical Specification Clause 2705.
No.
6D.17 Providing AC weepholes in retaining walls, abutments
and return walls complete as per drawings and
Technical Specification Clause 2706.
No.
6D.18 Providing and laying of R.C.C (M-20) in footpath, kerb
etc. excluding reinforcement as per drawing and
Technical specifications Sections 1500 & 1700
Cu.m.
6D.19 a) Dismantling damaged expansion joints, providing
and laying asphaltic plug type expansion joint in
existing bridges conforming to MoRTH Modified Interim
Specifications for expansion joints, to be installed under
supervision of specialist manufacturer
m
6D.20 b) Providing buried type expansion joints in
new/existing bridges complete as per approved drawing
and MoRTH Interim Specifications for expansion joints
to be installed under supervision of specialist
manufacturer as per Technical Specifications Clause A

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.21 Providing and laying of asphaltic plug joint to provide for


horizontal movement of 25 mm and vertical movement
of 2 mm, depth of joint varying from 75 mm to 100 mm,
width varying from 500 mm to 750 mm (in traffic
direction), covered with a closure plate of 200mm x
6mm of wieldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder,
carefully selected single size
aggregate of 12.5 mm nominal size and a heat resistant
foam caulking/backer rod,
all as per approved
drawings and specifications and as per relevant clauses
of Section 2600.
m
6D.22 Back filling behind abutments, wing walls and return
walls with selected granular material of approved
quality including all material, labour, equipment carriage
etc. all complete as per drawing and Technical
Specifications Clause 305.
6D.23 Providing and laying 600mm Thick Filter layer behind
Abutments and Retaining walls as per drawings,
complete. As per MoRT&H technical specification
section 2500.
6D.24 Filter Media Underneath Pitching in Slopes complete
as per drawing and Technical Specification Clause
2504.
6D.25 Providing and laying Stone Pitching on Embankment
Slopes for cone protection laying dry all complete as
per Technical Specification Clause 2504.
Cu.m.
6D.26 Bored cast in situ M 35 grade RCC pile of 1200 mm
dia. excluding reinforcement complete as per drawing
and technical specifications and removal of excavated
earth with all lifts and lead upto 1000 m
RM

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

#REF!
Additional in rock
1200 dia
1000 dia
750 dia
M-35 conc.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

RM
m
m
m
Cu.m.

6D.27 Load Testing


including loading with necessary
kentledge or any other suitable method as directed.
a) Initial test (2 piles )
b) Routine test (2 piles )
c) lateral load test (2 piles )
6D.28 Reinforced cement concrete M-30 in pile cap excluding
reinforcement complete as per drawings & Technical
Specifications Clause 1114, Sections 1500 & 1700.
M-30
M35
6D.29 Providing steel liner 6 mm thick for pile including
fabricating and setting out as per detailed drawing

M.T
M.T
M.T

Cu.m.

MT
6D.30 Sinking of wells through all type of soils and rock to be
measured from low water level (other then pneumatic
method of sinking) complete as per drawing and
Techncial Specifications Clause 1200.
(a) for 8 M dia well
(i) Depth 0-3 m.
(ii) Depth 3-10m
(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.
(b) for 7 M dia well
(i) Depth 0-3 m.
DPR for Rehabilitation and Upgrading
Munger-Bhagalpur-Mirzachauki NH-80 Bihar

m
m
m
m
m
m
m
m
SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

(ii) Depth 3-10m


(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

m
m
m
m
m
m

6D.31 Providing and laying cutting edge of mild steel for well
foundation for bridges as per drawings and Technical
Specifications clause 1200 and 1900.

MT.

6D.32 Sand filling in wells as per drawings and technical


Specifications clause 1200.

Cu.m.

6D.33 Cement concrete for plains concrete reinforcement


concrete complete as per drawings and technical
Specifications (Excluding steel reinforcement) clause
1200, 1500, 1700.
(a) Well curb
- M-30
(b) Well cap
- M-35
(c) Bottom plug - M-15
(d) Intermediate plug
- M-30
(e) Well steining- RCC M-30
6D.34 Providing and laying chequered tiles/cota stone/IPS
flooring complete as per details

Cu m.
Cu m.
Cu m.
Cu m.
Cu m.

a) Chequered tiles
6D.35 Providing ,fixing,erecting and painting 65 NB GI pipe on
concrete crash barrier as per approved drawing and
Technical Specification Section 2700.

sq.m.

6D.36 Supply installance testing and commissioning of


External Light Pole including fitting clamp fixture, cable
earthing etc. complete as shown in drawing.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

RM

No.

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description Proposed Chainage km


Unit

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.37 Providing and applying 2 coats of water based cement


paint to unplastered concrete surface after cleaning the
surface of dirt,dust,oil grease, efflorescence and
applying paint @ 1 litre for 2 sq.m as per Technical
Specification Secion 800.
SQMT
6D.38 PVC Downtake pipe for drainage

RM

6D.39 Painting of structure number, span arrangement and


flow direction complete as per drawings and Technical
Specification Section 800.

No.

6D.40 Dismantling stone/cement masonary of parapets, piers,


return wall, abutment, wingwalls and arches in cement /
lined mortar including sorting the dismantled material,
disposal of unserviceable material and stacking the
serviceable material within a lead of 100 m
a.
b.

Epoxy bonding of new concrete to old concrete


sealing of crack/porous concrete with Epoxy Grout by
injection through niples complete as per clause 2803.1

c.

Replacement of the expansion joints complete as per


drawings

cum
Sqmt

kg

d.
Replacement of the damaged concrte railing.
e.
Replacement of the crash barrier
6D.41 Laying 300mm thick stone apron complete as per
drawings and Technical Specification Clause 2503.
6D.42 Providing and laying Compacted Earth Filling as per
Section 2500 of MOST specification for Road & Bridge
work.
6D.43 Structural Steelwork in superstructure including painting
as per technical specification Section 1900 (painting
shall conform to System (v) , Table 1900-3)

cum

cum

MT

Total

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

6D.01 Earthwork in Excavation of foundation for structure


complete as per drawing and Technical Specification
Clause 304.
(i) in all types of soil)

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Cu.m.

0-3 depth
3-6 depth
(ii) in rock (blasting not requred)
6D.02 Cement concrete for plain/ reinforced concrete in
foundation (leveling course) below head wall complete
as per drawing and Technical Specification Sections
1700, 2100 and 2900.

Cu.m.

M-15
M-20
6D.03 Structural cement concrete for plain / reinforced
concrete for foundation including formwork, machinery
and workmanship complete as per drawing and
Technical Specification Sections 1500, 1700 and 2100.

Cu.m.
Cu.m.

(a) In foundation
(i) PCC M-20
(ii) RCC M-25
(iii) RCC M-30
(iv) M-35

Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-15
(ii) a PCC M-20
(ii) b RCC M-20
(iii) RCC M-25
(iv) RCC M-30
(v) RCC M-35
(v) RCC M-40

Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-20
(ii) M-25

Cu.m.
Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

(b) Substructure

(c) Super-structure

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Total
Qty.

Rate
(in Rs.)

0
#REF!
0
0

63
81
90

0
#REF!
0

3325
3525

0
0
0
#REF!
0
0
0
0
0
0
#REF!
0
0
0
0
0

3525
3920
3859
4020
3518
3728
4058
4761
4467
3500
4000
4463
4961

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

#REF!
(iii) M-30 (Solid Slab)
M-30 (T-Beam)
(iv) M-35
(v) M-40 and above

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Total
Qty.

Rate
(in Rs.)

0
0
0
0
0
0

5233
5135
5193
5787

#REF!

Cu.m.
Cu.m.
Cu.m.
Cu.m.

6D.04 Pre-stressed cement concrete T Girder/Box Girder in


superstructure complete as per drawing and Technical
Specifications Sections 1500, 1700 & 1800 excluding
reinforcement and H.T. strands.
(i) M-45
(ii) M-45 (Box Girder)
6D.05 Reinforced cement concrete M 30 in approach slab
including reinforcement complete as per drawing and
Technical Specification Section 1500, 1700 and 2700.

Cu.m.
Cu.m.

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

0
0
0

4500

#REF!

7020

0
0
#REF!
0

1547
5787
5233

6D.06 Reinforced cement concrete crash barrier / railings


complete as per drawings and Technical Specification
Sections 1500, 1600, 1700 and 2700.
(a) RCC M-30 Precast Railing
(b) M-40 grade crash barrier
(c) M-30 grade kerbs
6D.07 Providing and fixing in position HYSD/TMT deformed
bars reinforcement complete as per drawing and
Technical Specification Section 1600.

RM
Cu.m.
Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

0
a) Foundation

MT

b) Sub structure

MT

b) Super structure

MT

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

62121

#REF!

62196

62840

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

Total
Qty.

Rate
(in Rs.)

MT

0
0

100000

sq.m.

133

cu.cm.

ton

0
0

ton
ton

0
0

666

RM

8524

#REF!

4420

Cu.m.

8542

sq.m.

313

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.08 Low relaxation HT strands in post tensioned box


girder/T-beam girder including sheathing, anchorages,
prestressing and grouting complete as per drawing and
Technical Specification Section 1800.
Strands
6D.09 Providing and fixing tar paper bearing complete as per
Technical Specification Section 2000.
6D.10 Supplying, fitting and fixing in position true to line and
level elastomeric bearing conforming to IRC 83 (Part II)
Section IV complete with all accessories as per drawing
& Technical Specifications Clause 2005.
6D.11 Supplying , fitting and fixing bearings in position true to
line and level complete as per drawing and Technical
Specification Section 2000.
(i) POT/POT- PTFE bearing for Bridges (fixed)
(ii) POT/POT- PTFE bearing for Bridges (free/guided)
(iii) Pin bearing
6D.12 Providing and laying of strip seal expansion joints
complete as per drawing & Technical Specification
Section 2600.(40 mm)
6D.13 Providing and laying Filler Type expansion joints
complete as per drawing & Technical Specification
Section 2605.
6D.14 Providing and laying 50mm thick bituminous concrete
wearing coat in two layers over the top of deck slab
complete as per drawings and Technical Specification
Section 500 and 2700.

RM

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

666

6D.15 Providing and laying a layer of 15mm thick Mastic


Asphalt as per drawing and Tech./spn.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

Total
Qty.

Rate
(in Rs.)

No.

690

No.

101

Cu.m.

166

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.16 Drainage spouts of 100 mm diameter complete as per


drawing and Technical Specification Clause 2705.
6D.17 Providing AC weepholes in retaining walls, abutments
and return walls complete as per drawings and
Technical Specification Clause 2706.
6D.18 Providing and laying of R.C.C (M-20) in footpath, kerb
etc. excluding reinforcement as per drawing and
Technical specifications Sections 1500 & 1700
6D.19 a) Dismantling damaged expansion joints, providing
and laying asphaltic plug type expansion joint in
existing bridges conforming to MoRTH Modified Interim
Specifications for expansion joints, to be installed under
supervision of specialist manufacturer
6D.20 b) Providing buried type expansion joints in
new/existing bridges complete as per approved drawing
and MoRTH Interim Specifications for expansion joints
to be installed under supervision of specialist
manufacturer as per Technical Specifications Clause A

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Total
Qty.

Rate
(in Rs.)

938

#REF!

6D.21 Providing and laying of asphaltic plug joint to provide for


horizontal movement of 25 mm and vertical movement
of 2 mm, depth of joint varying from 75 mm to 100 mm,
width varying from 500 mm to 750 mm (in traffic
direction), covered with a closure plate of 200mm x
6mm of wieldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder,
carefully selected single size
aggregate of 12.5 mm nominal size and a heat resistant
foam caulking/backer rod,
all as per approved
drawings and specifications and as per relevant clauses
of Section 2600.
m
6D.22 Back filling behind abutments, wing walls and return
walls with selected granular material of approved
quality including all material, labour, equipment carriage
etc. all complete as per drawing and Technical
Specifications Clause 305.
6D.23 Providing and laying 600mm Thick Filter layer behind
Abutments and Retaining walls as per drawings,
complete. As per MoRT&H technical specification
section 2500.
6D.24 Filter Media Underneath Pitching in Slopes complete
as per drawing and Technical Specification Clause
2504.

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

386

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

677

Cu.m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

767

Cu.m.

618

RM

6D.25 Providing and laying Stone Pitching on Embankment


Slopes for cone protection laying dry all complete as
per Technical Specification Clause 2504.
6D.26 Bored cast in situ M 35 grade RCC pile of 1200 mm
dia. excluding reinforcement complete as per drawing
and technical specifications and removal of excavated
earth with all lifts and lead upto 1000 m

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

Total
Qty.

Rate
(in Rs.)

RM
m

0
0

9381

7451

4568

Cu.m.

M.T
M.T
M.T

0
0
0

648
648
10795

Cu.m.

0
0
0

3978
4113

MT

65027

m
m
m
m
m
m
m

0
0
0
0
0
0
0
0
0
0
0

#REF!
Additional in rock
1200 dia
1000 dia
750 dia
M-35 conc.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.27 Load Testing


including loading with necessary
kentledge or any other suitable method as directed.
a) Initial test (2 piles )
b) Routine test (2 piles )
c) lateral load test (2 piles )
6D.28 Reinforced cement concrete M-30 in pile cap excluding
reinforcement complete as per drawings & Technical
Specifications Clause 1114, Sections 1500 & 1700.
M-30
M35
6D.29 Providing steel liner 6 mm thick for pile including
fabricating and setting out as per detailed drawing
6D.30 Sinking of wells through all type of soils and rock to be
measured from low water level (other then pneumatic
method of sinking) complete as per drawing and
Techncial Specifications Clause 1200.
(a) for 8 M dia well
(i) Depth 0-3 m.
(ii) Depth 3-10m
(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.
(b) for 7 M dia well
(i) Depth 0-3 m.
DPR for Rehabilitation and Upgrading
Munger-Bhagalpur-Mirzachauki NH-80 Bihar

9680
13414
17714
33229
78948

7915

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

Total
Qty.

Rate
(in Rs.)

m
m
m
m
m
m

0
0
0
0
0
0
0

13015
17187
32236
76588

6D.31 Providing and laying cutting edge of mild steel for well
foundation for bridges as per drawings and Technical
Specifications clause 1200 and 1900.

MT.

70818

6D.32 Sand filling in wells as per drawings and technical


Specifications clause 1200.

Cu.m.

203

(a) Well curb


- M-30
(b) Well cap
- M-35
(c) Bottom plug - M-15
(d) Intermediate plug
- M-30
(e) Well steining- RCC M-30
6D.34 Providing and laying chequered tiles/cota stone/IPS
flooring complete as per details

Cu m.
Cu m.
Cu m.
Cu m.
Cu m.

0
0
0
0
0
0

3325
4850
4020
4063
3732
4102

a) Chequered tiles
6D.35 Providing ,fixing,erecting and painting 65 NB GI pipe on
concrete crash barrier as per approved drawing and
Technical Specification Section 2700.

sq.m.

0
0

#REF!
(ii) Depth 3-10m
(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.33 Cement concrete for plains concrete reinforcement


concrete complete as per drawings and technical
Specifications (Excluding steel reinforcement) clause
1200, 1500, 1700.

6D.36 Supply installance testing and commissioning of


External Light Pole including fitting clamp fixture, cable
earthing etc. complete as shown in drawing.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

RM

No.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

276

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Proposed Chainage km

Total
Qty.

Rate
(in Rs.)

SQMT

62

RM

200

#REF!

297

cum
Sqmt

0
0

522

kg

620

0
0
0

1927
135
228

#REF!

618

cum

609

MT

0
0

62840

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.37 Providing and applying 2 coats of water based cement


paint to unplastered concrete surface after cleaning the
surface of dirt,dust,oil grease, efflorescence and
applying paint @ 1 litre for 2 sq.m as per Technical
Specification Secion 800.
6D.38 PVC Downtake pipe for drainage
6D.39 Painting of structure number, span arrangement and
flow direction complete as per drawings and Technical
Specification Section 800.

No.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

6D.40 Dismantling stone/cement masonary of parapets, piers,


return wall, abutment, wingwalls and arches in cement /
lined mortar including sorting the dismantled material,
disposal of unserviceable material and stacking the
serviceable material within a lead of 100 m
a.
b.

Epoxy bonding of new concrete to old concrete


sealing of crack/porous concrete with Epoxy Grout by
injection through niples complete as per clause 2803.1

c.

Replacement of the expansion joints complete as per


drawings

d.
Replacement of the damaged concrte railing.
e.
Replacement of the crash barrier
6D.41 Laying 300mm thick stone apron complete as per
drawings and Technical Specification Clause 2503.
6D.42 Providing and laying Compacted Earth Filling as per
Section 2500 of MOST specification for Road & Bridge
work.
6D.43 Structural Steelwork in superstructure including painting
as per technical specification Section 1900 (painting
shall conform to System (v) , Table 1900-3)
Total

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

cum

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Amount

Reference of
SOR

(in Rs.)
6D.01 Earthwork in Excavation of foundation for structure
complete as per drawing and Technical Specification
Clause 304.
(i) in all types of soil)

Cu.m.

12.1(I)A(i)

(ii) in rock (blasting not requred)


6D.02 Cement concrete for plain/ reinforced concrete in
foundation (leveling course) below head wall complete
as per drawing and Technical Specification Sections
1700, 2100 and 2900.

Cu.m.

0
0

12.1.B(ii)

M-15
M-20
6D.03 Structural cement concrete for plain / reinforced
concrete for foundation including formwork, machinery
and workmanship complete as per drawing and
Technical Specification Sections 1500, 1700 and 2100.

Cu.m.
Cu.m.

0
#REF!
0

12.4

0-3 depth
3-6 depth

(a) In foundation
(i) PCC M-20
(ii) RCC M-25
(iii) RCC M-30
(iv) M-35

Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-15
(ii) a PCC M-20
(ii) b RCC M-20
(iii) RCC M-25
(iv) RCC M-30
(v) RCC M-35
(v) RCC M-40

Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Cu.m.

(i) M-20
(ii) M-25

Cu.m.
Cu.m.

(b) Substructure

(c) Super-structure

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

0
0
0
#REF!
0
0
0
0
0
0
#REF!
0
0
0
0
0
0

12.8 B
12.8 E case II
12.8 G case II
12.8 H case II
13.5 A (p)
13.5 B (p)
13.5 E (r) case II
13.5 F (r) case II
13.5 G (r) case II
13.17

14.1 A case II (i) r


14.1 B case II (i) r

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

(iii) M-30 (Solid Slab)


M-30 (T-Beam)
(iv) M-35
(v) M-40 and above

Cu.m.
Cu.m.
Cu.m.
Cu.m.

Amount

(in Rs.)
0
0
0
0
0
0

Reference of
SOR

14.1 C case II (i) r


14.1C Case II (ii) (r)
14.1D Case II (ii) (r)
14.1.E case II (ii)

6D.04 Pre-stressed cement concrete T Girder/Box Girder in


superstructure complete as per drawing and Technical
Specifications Sections 1500, 1700 & 1800 excluding
reinforcement and H.T. strands.
(i) M-45
(ii) M-45 (Box Girder)
6D.05 Reinforced cement concrete M 30 in approach slab
including reinforcement complete as per drawing and
Technical Specification Section 1500, 1700 and 2700.

Cu.m.
Cu.m.

0
0
0

14.1F (ii) (r)


14.1F (iii) (r)

Cu.m.

#REF!

14.11

RM
Cu.m.
Cu.m.

0
0
#REF!
0

14.6
14.1.E case II (ii)
14.1 C case II (i) r

6D.06 Reinforced cement concrete crash barrier / railings


complete as per drawings and Technical Specification
Sections 1500, 1600, 1700 and 2700.
(a) RCC M-30 Precast Railing
(b) M-40 grade crash barrier
(c) M-30 grade kerbs
6D.07 Providing and fixing in position HYSD/TMT deformed
bars reinforcement complete as per drawing and
Technical Specification Section 1600.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

a) Foundation

MT

12.40

b) Sub structure

MT

#REF!

13.6

b) Super structure

MT

14.2

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Amount

Reference of
SOR

(in Rs.)
6D.08 Low relaxation HT strands in post tensioned box
girder/T-beam girder including sheathing, anchorages,
prestressing and grouting complete as per drawing and
Technical Specification Section 1800.
Strands
6D.09 Providing and fixing tar paper bearing complete as per
Technical Specification Section 2000.

MT

0
0

14.3

sq.m.

Market rate

cu.cm.

13.14

ton

0
0

13.16

ton
ton

0
0

13.16
13.13

RM

14.22

RM

#REF!

14.18

Cu.m.

14.4

sq.m.

14.5 (Rate increased


from 12mm to 15 mm.

6D.10 Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC 83 (Part II)
Section IV complete with all accessories as per drawing
& Technical Specifications Clause 2005.
6D.11 Supplying , fitting and fixing bearings in position true to
line and level complete as per drawing and Technical
Specification Section 2000.
(i) POT/POT- PTFE bearing for Bridges (fixed)
(ii) POT/POT- PTFE bearing for Bridges (free/guided)
(iii) Pin bearing
6D.12 Providing and laying of strip seal expansion joints
complete as per drawing & Technical Specification
Section 2600.(40 mm)
6D.13 Providing and laying Filler Type expansion joints
complete as per drawing & Technical Specification
Section 2605.
6D.14 Providing and laying 50mm thick bituminous concrete
wearing coat in two layers over the top of deck slab
complete as per drawings and Technical Specification
Section 500 and 2700.
6D.15 Providing and laying a layer of 15mm thick Mastic
Asphalt as per drawing and Tech./spn.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Amount

Reference of
SOR

(in Rs.)
6D.16 Drainage spouts of 100 mm diameter complete as per
drawing and Technical Specification Clause 2705.
No.

14.9

No.

13.8

Cu.m.

8.1b

6D.17 Providing AC weepholes in retaining walls, abutments


and return walls complete as per drawings and
Technical Specification Clause 2706.
6D.18 Providing and laying of R.C.C (M-20) in footpath, kerb
etc. excluding reinforcement as per drawing and
Technical specifications Sections 1500 & 1700
6D.19 a) Dismantling damaged expansion joints, providing
and laying asphaltic plug type expansion joint in
existing bridges conforming to MoRTH Modified Interim
Specifications for expansion joints, to be installed under
supervision of specialist manufacturer
6D.20 b) Providing buried type expansion joints in
new/existing bridges complete as per approved drawing
and MoRTH Interim Specifications for expansion joints
to be installed under supervision of specialist
manufacturer as per Technical Specifications Clause A

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Amount

Reference of
SOR

(in Rs.)
6D.21 Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement
of 2 mm, depth of joint varying from 75 mm to 100 mm,
width varying from 500 mm to 750 mm (in traffic
direction), covered with a closure plate of 200mm x
6mm of wieldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder,
carefully selected single size
aggregate of 12.5 mm nominal size and a heat resistant
foam caulking/backer rod,
all as per approved
drawings and specifications and as per relevant clauses
of Section 2600.
m

14.19

Cu.m.

#REF!

13.9 A

Cu.m.

#REF!

13.10

Cu.m.

#REF!

15.5

Cu.m.

15.4 (A)

RM

6D.22 Back filling behind abutments, wing walls and return


walls with selected granular material of approved
quality including all material, labour, equipment carriage
etc. all complete as per drawing and Technical
Specifications Clause 305.
6D.23 Providing and laying 600mm Thick Filter layer behind
Abutments and Retaining walls as per drawings,
complete. As per MoRT&H technical specification
section 2500.
6D.24 Filter Media Underneath Pitching in Slopes complete
as per drawing and Technical Specification Clause
2504.
6D.25 Providing and laying Stone Pitching on Embankment
Slopes for cone protection laying dry all complete as
per Technical Specification Clause 2504.
6D.26 Bored cast in situ M 35 grade RCC pile of 1200 mm
dia. excluding reinforcement complete as per drawing
and technical specifications and removal of excavated
earth with all lifts and lead upto 1000 m

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Additional in rock
1200 dia
1000 dia
750 dia
M-35 conc.

Unit

Amount

Reference of
SOR

RM
m

(in Rs.)
0
0

12.25A

12.24A

12.23A

Cu.m.

M.T
M.T
M.T

0
0
0

12.37
12.37
12.37

Cu.m.

0
0
0

12.38C (ii)
12.38D(II)

MT

12.22

m
m
m
m
m
m
m

0
0
0
0
0
0
0
0
0
0
0

6D.27 Load Testing


including loading with necessary
kentledge or any other suitable method as directed.
a) Initial test (2 piles )
b) Routine test (2 piles )
c) lateral load test (2 piles )
6D.28 Reinforced cement concrete M-30 in pile cap excluding
reinforcement complete as per drawings & Technical
Specifications Clause 1114, Sections 1500 & 1700.
M-30
M35
6D.29 Providing steel liner 6 mm thick for pile including
fabricating and setting out as per detailed drawing
6D.30 Sinking of wells through all type of soils and rock to be
measured from low water level (other then pneumatic
method of sinking) complete as per drawing and
Techncial Specifications Clause 1200.
(a) for 8 M dia well
(i) Depth 0-3 m.
(ii) Depth 3-10m
(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.
(b) for 7 M dia well
(i) Depth 0-3 m.
DPR for Rehabilitation and Upgrading
Munger-Bhagalpur-Mirzachauki NH-80 Bihar

12.14 B (i)
12.14 B (ii)
12.14 B (iii)
12.14 B (iv)

12.13 B (i)
SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Amount

m
m
m
m
m
m

(in Rs.)
0
0
0
0
0
0
0

6D.31 Providing and laying cutting edge of mild steel for well
foundation for bridges as per drawings and Technical
Specifications clause 1200 and 1900.

MT.

12.10

6D.32 Sand filling in wells as per drawings and technical


Specifications clause 1200.

Cu.m.

12.21

(a) Well curb


- M-30
(b) Well cap
- M-35
(c) Bottom plug - M-15
(d) Intermediate plug
- M-30
(e) Well steining- RCC M-30
6D.34 Providing and laying chequered tiles/cota stone/IPS
flooring complete as per details

Cu m.
Cu m.
Cu m.
Cu m.
Cu m.

0
0
0
0
0
0

12.8 A
12.11 A (iii) case II
12.11 F (iii) case II
12.11 C (i) case II
12.11 D (i) case II
12.11 B (vi) case II

a) Chequered tiles
6D.35 Providing ,fixing,erecting and painting 65 NB GI pipe on
concrete crash barrier as per approved drawing and
Technical Specification Section 2700.

sq.m.

0
0

Market rate

RM

#REF!

14.26

No.

8.28

(ii) Depth 3-10m


(iii) Depth 10-20 m.
(iv) 20-30m.
(v) 30-40m.
(xiv)40-50 m.
(xv) 50-60 m.

6D.33 Cement concrete for plains concrete reinforcement


concrete complete as per drawings and technical
Specifications (Excluding steel reinforcement) clause
1200, 1500, 1700.

6D.36 Supply installance testing and commissioning of


External Light Pole including fitting clamp fixture, cable
earthing etc. complete as shown in drawing.

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

Reference of
SOR

12.13 B (ii)
12.13 B (iii)
12.13 B (iv)

SAI Consulting Engineers Pvt. Ltd.

BILL NO. 6 : MAJOR BRIDGES , MINOR BRIDGE ,ROB,VUP,FLYOVER


Item
No.

Description

Unit

Amount

Reference of
SOR

(in Rs.)
6D.37 Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the
surface of dirt,dust,oil grease, efflorescence and
applying paint @ 1 litre for 2 sq.m as per Technical
Specification Secion 800.
6D.38 PVC Downtake pipe for drainage
6D.39 Painting of structure number, span arrangement and
flow direction complete as per drawings and Technical
Specification Section 800.

SQMT

14.16

RM

Market rate

No.

#REF!

Market rate

cum
Sqmt

0
0

16.10

kg

16.7

0
0
0

16.18
16.19

cum

#REF!

15.1

cum

4.2 (iii)

MT

0
#REF!

14.2

6D.40 Dismantling stone/cement masonary of parapets, piers,


return wall, abutment, wingwalls and arches in cement /
lined mortar including sorting the dismantled material,
disposal of unserviceable material and stacking the
serviceable material within a lead of 100 m
a.
b.

Epoxy bonding of new concrete to old concrete


sealing of crack/porous concrete with Epoxy Grout by
injection through niples complete as per clause 2803.1

c.

Replacement of the expansion joints complete as per


drawings

d.
Replacement of the damaged concrte railing.
e.
Replacement of the crash barrier
6D.41 Laying 300mm thick stone apron complete as per
drawings and Technical Specification Clause 2503.
6D.42 Providing and laying Compacted Earth Filling as per
Section 2500 of MOST specification for Road & Bridge
work.
6D.43 Structural Steelwork in superstructure including painting
as per technical specification Section 1900 (painting
shall conform to System (v) , Table 1900-3)
Total

DPR for Rehabilitation and Upgrading


Munger-Bhagalpur-Mirzachauki NH-80 Bihar

SAI Consulting Engineers Pvt. Ltd.

Vous aimerez peut-être aussi