Académique Documents
Professionnel Documents
Culture Documents
CHAPTER 1
Introduction
OF
THE
DIRECTORATE
FOR
RESEARCH
AND
2
NAPOLCOM, in its resolution numbered 92 -36, approved the revised
organizational structure of the PNP on October 11, 1993, by virtue of NHQ, PNP
General Order No. 834. PCSUPT MILTON F TIBURCIO was designated as the
Director of the Directorate for Research and Development.
Activation
The Directorate for Research and Development was activated on
November 1, 1993 and became Operational on January 16, 1994 imbibing a
conspicuous role in PNP organization which is to conduct research studies
pertaining to the criminalistics equipment and other peculiar and investigative
equipment/materials, communicationselectronic and transportation. Weapons
and clothing for effective and efficient law and order public safety function and to
uphold the furtherance and selfreliant development projects of the PNP.
MISSION
Assists and advises the Chief, PNP in the conduct of Research and
Development. Test and Evaluation (T&E) of Clothing, materiel, vehicles and
equipment required by the PNP for effective and efficient maintenance of Law and
Order and Public Safety, and in the formulation and implementation of the PNPs
Self Reliant Development Program.
FUNCTION
To conduct research and study on the latest technology and materiel;
To determine and develop specifications and standards for all PNP
equipment (UESB);
To conduct test and evaluation of clothing, materiel, vehicles and
equipment procured by the PNP;
To perform such other functions as the Chief, PNP may direct;
To coordinate, correlate and cooperate with government and non
government agencies in undertaking research and development activities;
To coordinate for the training, either local or foreign of PNP Personnel in
the areas of Research and Development and Test and Evaluation;
To formulate/update/improve Research and Development and Test and
Evaluation policies/procedures/capabilities, and;
To direct and supervise the formulation and implementation of the PNPs
Self Reliance Development Program.
CHAPTER 2
4
Section 2-1 Weapons Section
2.1
Weapons Section
In line with its functions, this section played a major role in the DOSTPNP
M16 barrels as well as to the testing and evaluation of the prototype rifle units.
Their work focused on the barrel performance of the units after going thru locally
made barrel replacement, hard chrome plating and barrel cutting. The divisions
specific tasks are to supervise and monitor the accuracy test, endurance firing
test, (5,000 rounds), thermal scanning, radiographic testing, magnaflux testing
and other procedural test consequently, the prototype rifle units have successfully
passed international test and evaluation standards.
In the near future, the division hopes to oversee the conduct of test and
evaluation of other essential parts of the M16 A1 rifle for its further refurbishment.
The division is also confident of facilitating the procurement of locally made
firearms as a result of own research and development undertaking, the
improvement of other weapons and equipments needed by the PNP.
2.1.1 DEFINITION OF TERMS:
1.
2.
3.
Accuracy Test test where the weapon when fired must hit the
object with a required number of rounds and the hit must remain in
fixed position and it should not exceed the required Mean Radius
Spread (MRS) or Mean Diameter Spread (MDS);
4.
Adverse Condition Test (Sand and Mud Test) the pouring of sand
on the weapon and its emerssion in mud for a required period of
time to determine its reliability and usability while under adverse
conditions;
5.
6.
7.
8.
9.
10.
11.
12.
13.
6
14.
15.
Dud Ammunition Cartridge that did not explode due to low order
detonation;
16.
17.
18.
19.
Firer - a designated person who has the ability to fire and shoot
accurately and who has the proficiency in weapons operation. The
designation shall be determined by the DRD in consultation with the
concerned proponents based on the kind of test to be conducted.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
Minor Defect a defect that is not likely to reduce materially the use
of the unit or product for its intended purpose; or a defect which is a
departure to the established standards but having little bearing on
the effective use or operation of the unit or product.
36.
37.
38.
39.
40.
41.
42.
Proof Load Test the firing of the weapon using a High Pressure
(HP) Cartridge.
43.
44.
45.
46.
Safe Action also known as striker fire action; a pistol design which
employs an internal striker mechanism to detonate the primer. In
operation, the pistol is normally in a partially cocked condition.
Pulling the trigger completes the cooking action and then releases
the striker mechanism to fire the pistol.
47.
48.
9
49.
Single Action a mode of operation that uses trigger to fire the pistol
only
50.
51.
52.
53.
54.
Trigger Pull Test a test used to determine the mass or force exerted
in pulling the trigger in accordance with the weapons standard
trigger pull.
55.
56.
10
1.
2.
3.
4.
5.
B.
There shall be DRD Technical Team(s) which shall be responsible for the
conduct of eligibility and acceptance tests. It shall be organized after the pre-bid
conference for Eligibility Test or after a Memo has been received indicating therein
the request for inspection or Acceptance Test. The number of Teams for Eligibility
Test will vary depending on the date of completion set by the BAC. In case of
Acceptance Test, regular members of the DRD Technical Committee shall
compose the Team. Members of the Team may come from other Division or
Section upon discretion of the Chairman, Technical Committee.
1.
Composition:
A Team shall be composed of the following:
a.
b.
c.
2.
Duties:
a.
b.
c.
C.
Composition:
11
2. Duties:
a.
b.
c.
d.
e.
The Bids and Awards Committee (BAC), whether the NHQ or PRO,
or the NHQ Negotiation Committee (NC) shall cause the conduct of
eligibility or post qualification test of grenade launchers. For
acceptance purposes, the Inspection and Acceptance Committee
(IAC), shall request the DRD to conduct the acceptance test;
B.
The proponents shall submit to the DRD two (2) samples of grenade
launchers for Eligibility or Post Qualification Test regardless of the
quantity to be procured;
C.
During the bidding, the BAC, through its Technical Working Group
(TWG) present, shall conduct visual inspection of the sample to
determine whether it conforms with the basic technical specifications
and features before the same is subjected to functional testing ;
D.
12
E.
F.
G.
The DRD shall provide Technical personnel who will oversee the
conduct of the Test at the selected testing places. The Test shall be
witnessed by representatives from other offices of the PNP, the
NAPOLCOM, the proponents and other persons if party in interest.
To the most, a video footage of the conduct of the test shall be taken
for future reference, and to the least, a combination of pictorial and
voice recording may suffice;
H.
The DRD may conduct Test and Evaluation of items even in the
absence of any procurement program and directive from the PNP
BAC, which will be termed as Product Evaluation. The product
evaluation result shall only be used as reference for any
recommendation, which DRD may deem appropriate;
I.
J.
Proponents shall shoulder all the expenses for the testing and
provide the ammunition to be used. They shall also submit the
names of their technicians, firers and representatives who may
attend the conduct of the test and evaluation. If testing by other
government entity is necessary, like the MIRDC, the expenses for
such purposes shall also be for the account of the proponent;
K.
13
L.
M.
N.
O.
Should there be any problem raised during the conduct of the test
on a particular sample, the Head, DRD Technical Committee shall
immediately suspend or stop the proceeding pending its resolution
or settlement;
P.
Q.
R.
The samples of the proponents that failed the test and evaluation
shall be returned to them except where a request for reconsideration
is pending. After the resolution of the request and the same failed
result is obtained, it is only then that the samples shall returned.
Only the samples of those who passed shall be retained until the
award of contract has been made. The samples of the non-winning
bidders shall be returned after the award of contract. The samples of
the winning bidder shall be retained for purposes of comparison with
the items that shall be delivered. Upon final acceptance of the items,
the samples shall be returned to the winning bidder. From the award
of contract up to delivery and acceptance, the samples shall not be
withdrawn nor they be replaced. Withdrawal or replacement shall be
14
ground for nullification of the award of contract as recommended by
the DRD.
A.
Purpose:
Equipment/Materials:
a.
b.
c.
d.
f.
g.
4.
Procedure:
a.
b.
15
c.
d.
5.
Standard:
a.
b.
c.
d.
B.
Zeroing
a.
b.
Equipment/Materials:
1.
2.
3.
4.
c.
Procedure:
1.
2.
d.
Standard:
1.
2.
2.
Measuring tape;
Gun Oil;
Improvised Target; and,
Ammunition Requirements (1 round).
Maintainability Test
a.
Purpose:
16
b.
Equipment/Materials:
1.
2.
c.
Procedure:
1.
2.
3.
4.
d.
Standard:
Grenade Launcher must fire without malfunction.
3.
Purpose:
Equipment/Materials:
1.
2.
c.
Procedure:
1.
2.
3.
4.
17
5.
6.
d.
Standard:
1.
2.
4.
There must be no dent on the primer of the chamberloaded dummy round or primed cartridge case; and,
Evidence of crack/split on barrel is classified as critical
defect and shall mean outright rejection.
Endurance Test:
a.
Purpose:
Equipment/materials:
1.
2.
3.
4.
c.
Procedure:
1.
2.
3.
4.
5.
6.
d.
Standard:
18
C.
1.
2.
Purpose:
Procedure:
a.
b.
c.
3.
Standard:
The result of the Magnaflux test should not contain any presence of
cracks or splits. Mere presence of cracks or splits on any submitted item(s)
shall mean outright rejection of the sample.
POLICY GUIDELINES IN THE CONDUCT OF ACCEPTANCE TEST
FOR GRENADE LAUNCHER 40MM
A.
Random Sampling
The sample size for Acceptance Test from the delivered items will be based
using the Military Standard 105-E, Normal Inspection Level II (see Table 1).
19
Procedure:
Pick samples at random based on the numbers tabulated above
from the boxes of the delivered firearms.
B.
Pre-firing Examination
1.
Purpose:
Equipment/Materials:
a.
b.
c.
d.
e.
f.
4.
Procedure:
a.
b.
c.
d.
5.
Standard:
a.
20
b.
c.
d.
C.
Zeroing
1.
Purpose:
Equipment/Materials:
a.
b.
c.
d.
3.
Procedure:
a.
b.
4.
Standard:
a.
b.
D.
Measuring tape;
Gun Oil;
Improvised Target; and,
Ammunition Requirements (1 round).
Functional Test:
1.
Purpose:
Equipment/Materials:
a.
b.
c.
d.
21
3.
Procedure:
Standard:
The Grenade Launcher must fire with out malfunction.
E.
Acceptance/Rejection:
1.
The results of the above-cited test criteria will be based on the 1.5%
of the Acceptance Quality Level (AQL) of Military Standard 105-E,
General Inspection Level II (see Table 2).
2.
Purpose:
Equipment/Materials:
a.
b.
c.
22
d.
e.
f.
g.
4.
Procedure:
a.
b.
c.
d.
5.
Standard:
a.
b.
c.
d.
B.
Weighing Scale
Permanent marker
Masking Tape
Ammunition requirements (14 rounds)
Accuracy Test
a.
Purpose:
Equipment / Material:
1.
2.
3.
4.
5.
6.
7.
23
c.
Firers:
e.
Procedure:
1.
2.
First four (4) rounds will be fired for first set to check the
pattern of the hit in the target. The remaining four (4)
rounds is for the second set which will be fired for record
purposes. Number of pellets hit and their spread/grouping
on the target paper must be recorded.
Standard:
The nine (9) pellets must hit the target at 7 and 15 meters
distance and must not exceed 6-inch mean radius. Yaw or miss on
the target is equivalent to 1-inch mean radius to be added to the
average mean radius of hits on the target.
2.
Interchangeability Test
a.
Purpose:
Equipment/Materials:
1.
2.
3.
c.
Procedure:
1.
Nomenclature of Parts
24
Receiver
Bolt
Magazine Spring
Barrel
Trigger Assembly
2.
3.
4.
d.
AB
AB
AB
AB
AB
BA
BA
BA
BA
BA
Standard:
Maintainability Test:
a.
Purpose:
Equipment/Materials:
1.
2.
c.
Procedure:
1.
2.
3.
4.
d.
Standard:
Shotgun must fire without malfunction.
4.
Endurance Test:
1.
Purpose:
25
Equipment / Materials:
a.
b.
c.
d.
3.
4.
Procedure:
a.
b.
Magazine Tube
Capacity
7 Rounds
5.
c.
d.
e.
Standard:
26
C.
a.
b.
Purpose:
3.
Procedure:
a.
b.
Mark the barrels with masking tape and indicate therein serial
numbers (if any) of shotgun where they belong then place it in
a shotgun case. Thereafter, seal the shotgun case with
masking tape and affix signature of all the proponents to
preserve their integrity.
c.
Standard:
The result of the magnaflux Test should not contain any presence of
cracks or splits. Mere presence of crack or split on any submitted Barrel
and Bolt Assembly shall mean outright rejection of the sample.
27
A.
Random Sampling
The sample size for Acceptance Test from the delivered items will be based
using the Military Standard 105-E, Normal Inspection Level II (see Table 1).
Procedure:
Pick samples in random based on the numbers tabulated above
from the boxes of the delivered firearms.
B.
Pre-firing Examination
1.
Purpose:
Equipment/Materials:
a.
b.
c.
d.
e.
f.
g.
4.
Procedure:
a.
28
5.
b.
c.
d.
Standard:
a.
b.
c.
d.
B.
Accuracy Test
1.
Purpose:
Equipment/Material:
a.
b.
c.
d.
e.
f.
g.
3.
Firers:
Only the PNP Technical Team is authorized.
4.
Procedure:
a.
29
b.
5.
First four (4) rounds will be fired to check the pattern of the hit
in the target. The remaining four (4) rounds is for the second
set which will be fired for record purposes. Number of pellets
hits and their spread/grouping on the target paper must be
recorded.
Standard:
The nine (9) pellets must hit the target at 7 and 15 meters distance
and must not exceed 6-inch mean radius. Yaw or miss on the target is
equivalent to 1-inch mean radius to be added to the average mean radius
of hits on the target.
C.
Interchangeability Test
1.
Purpose:
Equipment/Materials:
a.
b.
c.
3.
Procedure:
a.
b.
c.
d.
e.
BA
BA
BA
BA
BA
30
4.
Standard:
The shotgun must function properly without any binding of moving
parts.
D.
Acceptance/Rejection:
1.
The results of the above-cited test criteria will be based on the 1.5%
of the Acceptance Quality Level (AQL) of Mil Std 105-E, General
Inspection Level II (see Table 2).
2.
Purpose:
Equipment/Materials:
a.
b.
c.
d.
e.
f.
31
g.
4.
5.
Procedure:
a.
b.
c.
d.
Insert fully loaded magazine and fire the pistols to determine its
initial operability.
Standard:
a.
b.
c.
d.
e.
Trigger Pull:
Caliber
Maximum
Minimum
B.
.45
6.5 lbs
3.0 lbs
.40
6.5 lbs
3.0 lbs
9mm
6.0 lbs
4.0 lbs
Accuracy Test
a.
32
b.
Equipment/Material:
1)
2)
3)
4)
5)
6)
c.
or
Proponents
supplied
d. Procedure:
e.
1)
2)
First five (5) rounds will be fired for zeroing. The remaining
ten (10) round will be fired for record purposes. Number of
hits and their spread/grouping on the target paper must be
recorded.
Standard:
Interchangeability Test
a.
Purpose:
33
a)
b)
c)
c.
Procedure:
1)
Nomenclature of Parts
Receiver
Slide
Safety Lever
Trigger
Recoil Spring, Guide and/or
Plug
Firing Pin
Slide Stop
Hammer Busing (for Cal .45)
Main Spring Housing (for Cal
.45)
3.
AB
AB
AB
AB
2)
3)
4)
Maintainability Test
a.
b.
Equipment / Materials:
1)
2)
Ammunition Requirement
a)
b)
c)
34
c.
Procedure:
1)
2)
3)
4)
d. Standard:
Pistol must fire without malfuction.
4.
b.
Equipment/Material:
1)
2)
3)
4)
5)
6)
7)
Gun Oil
Sand Box
Ten (10) kilograms of sieved sand using a #30 wire mesh
Timer
3M Making tape (1)
Mud mixture compose of four and a half (4.5) kilograms of
garden soil and one (1) kilogram of clean and with seven
and a half (7.5) liters os water.
8) Electric Fan, 16-inch diameter fan blade
9) Weighing Scale
10) Basin
c.
2)
3)
4)
35
d.
5)
6)
7)
The firer shall clean the pistol, while removing the tape
with bare hands and blow the congestion on the area of
action;
8)
The pistol must fire at least three (3) successive rouds strarting
rom the chamber-loaded round.
e.
f.
2)
3)
4)
5)
6)
7)
36
5.
Purpose:
Equipment/Materials:
1)
2)
c.
Procedure:
1)
2)
3)
4)
5)
Insert the magazine, load and fire the pistol until the
ammunition has been expended.
6)
37
d. Standard:
6.
1)
There must be no dent on the primer of the chamberloaded dummy round or primed cartridge case;
2)
3)
4)
Purpose:
To determine the reliability and durability of the magazine.
b.
Equipment/Materials:
1)
2)
c.
Procedure:
1)
2)
3)
d.
Standard:
There must be no malfunction ande damage to the magazine.
7.
Endurance Test
a.
Purpose:
38
malfunctions, number of parts that become unserviceable and the
variation in accuracy and muzzle velocity.
b.
Equipment / Materials:
1)
2)
3)
4)
5)
c.
Estimated Duration of Test eight (8) hours only (8:00am12noon and 1:00pm-5:00pm)
d.
Procedure:
1)
2)
Caliber
.9mm
15
.45 Hi Cap
13
10 sec
.45 Std
10 sec
7 sec per
mag
.40
10
10 sec
10 sec per
mag
mag
13 sec per
mag
mag
9 sec per
mag
5 sec per
mag
7 sec per
mag
3)
4)
After firing each set, allow the pistol to cool down for five
(5) minutes. Swabbing of the barrel is allowed;
39
e.
5)
Field strip, clean and lubricate the weapon after every one
thousand (1000) rounds of firing for a duraion of ten (10)
minutes only;
6)
7)
8)
Standard:
1)
2)
8.
Proof Load Test (Shall follow immediately ten (10) minutes after
the Endurance Test
a.
Purpose:
To determine resistance of the weapon when fired using HighPressure (HP) cartridge tabulated below.
Caliber
9mm
.45
.40
Minimum Pressure
50,000 psi
22,000 psi
35,000 psi
b.
c.
Procedure:
1.
2.
The pistol will be fired using one (1) round of highpressure cartridge; and
After firing, check the empty cartridge for bulges, splits,
rings and other defects that may have been caused by
defective barrel.
40
d.
Standard:
Purpose:
Procedure:
a.
b.
Mark the sample with masking tape and indicate therein their
serial numbers where they belong then place it in a pistol case.
Thereafter, seal the pistol case with masking tape and affix
signature of all the proponents to preserve its integrity.
Bring the slide and barrel to Metals industry Research and
Development Center (MIRDC)-DOST for Magnetic Particle Test
(Magnaflux Test). This is the 10 th or the last parameter for the
Eligibility Test and Evaluation.
c.
3.
Standard:
The result og the magnaflux test should not contain any presence of
cracks or splits. Mere presence of crack or split on any submitted Slides
and Barrels, shall mean outrigh rejection of the sample.
POLICY GUIDELINES IN THE CONDUCT OF ACCEPTANCE TEST
FOR PISTOLS
A.
Purpose:
To determine the quality of the delivered firearms visavis the prequalified sample.
41
2.
Procedure:
Pick at random one (1) pistol each from the delivered and prequalified sample and send them both to MIRDC DOST to determine its
material / metal composition.
3.
Standard:
Random Sampling
Purpose:
Equipment/Materials:
a.
b.
c.
d.
e.
42
f.
g.
Masking Tape
Ammunition requirements per Pistol
1) 9mm Pistol 15 rds
2) Cal. 45 Pistol 7 rds (standard) /13 rds (High Cap)
3) Cal. 40 Pistol 10 rds
4.
5.
Procedure:
a.
b.
c.
d.
Insert fully loaded magazine and fire the pistols to determine its
initial operability.
Standard:
a.
b.
c.
d.
e.
Trigger Pull
Caliber
Maximum
Minimum
D.
.45
6.5 lbs
3.0 lbs
.40
6.5 lbs
3.0 lbs
9mm
6.0 lbs
4.0 lbs
Accuracy Test
1.
Purpose:
43
2.
Equipment/Material:
a.
b.
c.
d.
e.
f.
3.
4.
Procedure:
5.
a.
b.
c.
First Five (5) rounds will be fired for zeroing. The remaining ten
(10) rounds will be fired for record purposes. Number of hits
and their spread/ grouping on the target paper must be
recorded.
Standard:
The grouping of the ten-round shots must not exceed 6-inch mean
radius. Yaw or miss on the target is equivalent to 1-inch mean to be added
to the average mean radius of hits on the target.
E.
Interchangeability Test
1.
Purpose:
Equipment/Materials:
a.
b.
c.
44
1)
2)
3)
3.
Procedure:
a.
b.
Receiver
Slide
Safety Lever
Trigger
Recoil Spring, Guide and/or Plug
Firing Pin
Slide Stop
Hammer Bushing (for Cal.45)
Main Spring Housing (for Cal.45)
4.
c.
d.
e.
Standard:
The pistols must function properly without any binding of moving
parts.
F.
Acceptance / Rejection:
1.
2.
The results of the above cited test criteria will be based on the
1.5% of the Acceptance Quality Level (AQL) of Mil Std 105-E,
General Inspection Level II (see Table 2).
3.
The PNP shall adopt the prescribed sampling plan which could be
considered advantageoous to the government.
45
Purpose:
Equipment/Materials:
a.
b.
c.
d.
e.
f.
g.
4.
Procedure:
a.
b.
c.
d.
46
5.
Standard:
a.
b.
c.
d.
B.
Accuracy Test
a.
b.
Purpose:
To determine the accuracy of the rifle using
machine rest or equivalent.
Equipment / Materials:
a.
b.
c.
d.
e.
f.
c.
d.
b.
e.
50 meters
150 meters
200 meters
300 meters
400 meters
Standard:
47
to 1-inch mean radius to be added to the average mean radius of
hits on the target.
2.
Interchangeability Test
a.
Purpose:
Equipment/Materials:
1)
2)
3)
c.
Procedure:
1)
Nomenclature of Parts
Upper Assembly
Bolt Carrier
Cam Pin
Firing Pin
Buffer Spring
2)
3)
4)
Maintainability Test
a.
Purpose:
48
b.
Equipment/Materials:
1)
2)
c.
Procedure:
1)
2)
3)
4)
d.
Standard:
Rifle must fire without malfunction.
4.
Purpose:
Equivalent/Materials:
1)
49
2)
3)
4)
5)
6)
7)
8)
9)
3)
4)
5)
6)
7)
f.
g.
50
2)
3)
4)
5)
6)
h.
5.
Purpose:
To detemine the reliability and durability of the
magazine.
b.
Equipment/Materials:
1) One (1) magazine
2) One (1) complete load of ammunition
c.
Procedure:
1)
2)
3)
d.
6.
Standard:
There must be no malfunction and damage to
the magazine.
Cook-off Test
a. Purpose:
To detemine the barrel and metal strength of the
rifle if it fires without pulling the trigger (cook-off).
b.
Equipment/Materials:
1)
2)
3)
Ammunition Requirement:
Gun Oil
Bore brush
500 rounds
51
4)
c.
Flannel cloth
Procedure:
1)
2)
3)
4)
5)
6)
d.
7.
250 Rounds
Magazine
Number of
Capacity
Magazine
30
5
20
5
Standard:
the rifle.
Endurance Test
a.
Purpose:
To detemine the reliability of the under
prolonged firing condition. This could be measured by the
number of malfunctions, number of parts that become
unserviceable and the variation in accuracy and muzzle
velocity.
b.
Equipment/Materials:
1)
2)
3)
52
4)
Flannel cloth
c.
d.
Procedure:
1)
2)
3)
4)
5)
6)
7)
8)
e.
Standard:
1) Malfunctions or stoppages exceeding 97.5% reliability mark
is classified as critical and shall mean automatic rejection.
2) Evidence of crack or blown barrel or any moving parts is
automatically classified as critical and shall mean
automatic rejection.
8.
Proof Load Test (Shall follow immediately ten (10) minutes after
the Endurance Test)
53
a.
Purpose:
Material:
One (1) high pressure (HP) cartridge for all types of rifle.
c.
Procedures:
1)
2)
d.
The rifle will be fired using one (1) round of high pressure
cartridge; and
Afte firing, check empty cartridge for bulges, splits, rings,
and other defects that may have been caused by
defective barrel.
Standard:
Purpose:
Procedure:
a.
b.
c.
54
3.
Standard:
The result of the MAgnaflux test should not contain any presence of
cracks or splits. Mere presence of crack or split on any submitted item(s)
shall mean outright rejection of the sample.
POLICY GUIDELINES IN THE CONDUCT OF ACCEPTANCE TEST
FOR RIFLES
A.
Purpose:
To determine the quality of the delivered rifle(s) vis--vis the prequalified sample
2.
Procedure:
Pick at random one (1) rifle each from the delivered and pre
qualified sample then, send them both to MIRDCDOST to determine their
material/metal composition.
3.
Standard:
Result must render consistency in material/metal composition of the
items.
B.
Random Sampling
1.
Purpose:
55
charactiristics. It does not include range malfunction and subsequent re
inspection and safety precaution as required in functional firing.
2.
Equipment/Materials:
a.
b.
c.
d.
e.
f.
g.
4.
Procedure:
a.
b.
c.
d.
5.
D.
Standards:
a.
b.
c.
d.
Accuracy Test
56
1.
Purpose: To determine the accuracy of the rifle using machine rest
or equivalent.
2.
Equipment/Material
a.
b.
c.
d.
e.
f.
3.
4.
Procedures:
a.
b.
50 meters
150 meters
200 meters
300 meters
400 meters
c. Standard: The grouping of the ten-round shots must not exceed 6inch mean radius. Yaw or miss on the target is equivalent to 1-inch
mean radius to be added to the average mean radius of hits on the
target.
E.
Intechangeability Test
1.
Purpose:
To determine the reliability of the rifle when parts from identical rifle
are interchanged.
2.
Equipment/Materials:
a.
57
b.
c.
3.
Procedures:
a.
b.
Nomenclature of Parts
Upper Assembly
Bolt Carrier
Cam Pin
Firing Pin
Buffer Spring
c.
d.
e.
4.
Standard:
The rifle must function properly without any binding of moving parts.
F.
Acceptance/Rejection:
1.
2.
The results of the above-cited test criteria will be based on the 1.5%
of the Acceptance Quality Level (AQL) of Mil Std 105-E, General
Inspection Level II (see Table 2).
2.
58
Eligibility Test and Evaluation Parameters for Small Arms (Pistol &
Revolvers)
Phase I (Pre-firing Examination)
1.
2.
3.
Equipment/Materials:
3.1
3.2
3.3
3.4
4.
4.1
4.2
4.3
59
5.
Standard:
5.1
5.2
5.3
5.4
5.5
Accuracy Test
1.1
1.2
1.3
Procedure:
1.3.1 Using a machine rest or equivalent, first five (5) rounds
will be fired for zeroing.
1.3.2 The remaining ten (10) rounds will be fired for record
purposes. Number of hits and their sspread/grouping
on the paper must be noted.
1.4
Standard:
The weapon i.e. FAs will be fired at range or
distance of twenty five (25) meters. The grouping must not
exceed six (6) inches mean radius. Yaw or miss on the target
is equivalent to one and one half (1 ) inches mean radius to
be added to the average mean radius of hits on the target.
60
2.
Interchangeability Test
2.1
2.2
Purpose:
To determine the reliability of the weapons when
parts from identical pistol are interchanged.
Equipment/Materials:
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
Tools
Four target paper
Calculator
Measuring Device
Ammunition Requirement
2.5.1 9mm Pistol 15 rds
2.5.2 Cal. 45 pistol 7 rds (standard) 13 rds (high
cap)
2.5.3 Cal. 38 Revolver 12 rds
2.3
Procedure:
2.3.1 Two (2) identical weapons shall be dissassembled and
the following parts to be interchanged:
2.3.1.1 Receiver
2.3.1.2 Slide
2.3.1.3 Safety Gripper
2.3.1.4 Trigger
2.3.1.5 Recoil Spring Plug
2.3.1.6 Barrel
2.3.1.7 Firing Pin
2.3.1.8 Slide Stop
2.3.1.9 Hammer Bushing
2.3.1.10 Main Spring Housing
2.3.2 Assemble the interchanged parts and the fire one fully
loaded magazine with ammunition.
2.3.3 Standard:
The two (2) weapons must function
properly without any bending of moving parts. It should
hit the target area at a distance of twenty-five (25)
meters. Note the grouping in comparison to its former
shot group.
3.
Maintaniability Test
3.1
Purpose:
To determine the ease and speed assembly and
disassembly of the weapon and the number of parts from the
weapon from the maintenance standpoint.
3.2
Equipment/Materials:
61
Procedure:
3.3.1 Dissassemble and assemble the weapon and record
the time, (To be done three (3) times); and
3.3.2 Dissassemble the weapon and record the number of
parts.
3.4
Standard:
3.4.1 Note/record the average time spent and tools used.
3.4.2 Pistol must fire without malfunction.
4.
Purpose:
To determine the reliability (absence of
malfunction or stoppages) of the weapon under adverse
condition, such as when immersed in mud and dust.
4.2
Equipment/Material:
4.2.1 Ammunition Requirement
4.2.1.1 9mm Pistol - 30 rds
4.2.1.2 Cal. 45 pistol - 14 rds (standard) / 26 rds (high
cap)
4.2.1.3 Cal. 38 Revolver - 12 rds
4.2.2
4.2.3
4.2.4
4.2.5
4.2.6
Gun Oil
Sand Box
Nine (9) lbs of sieved sand using a mesh sieve
Timer
Masking tabe (1)
4.2.7 Mud mixture ten (10) lbs of garden soil and two (2) lbs
of clean sand with eight (8) quarts of water.
4.2.8 Electric Fan or Industrial Fan with sixteen (16) inches
fan blade.
4.2.9 Measuring Cup
62
4.3
Procedures:
a. Sand Test
4.3.a.1 The weapon shall be cleaned and lubricated lightly;
4.3.a.2 It shall be loaded with maximum number of rounds of
the magazine and the safety lock be placed ts
SAFE position and muzzle taped.
4.3.a.3 Put the loaded magazine to the pistol with chamber
load;
4.3.a.4 Place the weapon in the dust box in upside down
position, for one (1) minute and reverse position for
another one (1) minute.
4.3.a.5 Mix the dust containing nine (9) lbs of grade zero (0)
sand with one (1) lb silica core sand which passed
100% through a thirty (30) mesh sieve.
4.3.a.6 Pour this mixture at a rate of five (5) lbs per minute
through pole hole while blower is turned at handled
speed of sixty (60) rpm or use electric fan at
maximum speed selector. Pouring shall be atleast six
(6) inches above the basin or container with equal
pouring of sand.
4.3.a.7 The fier shall clean the pistol with bare hands and
then blow sharply on the congested area of action.;
and
4.3.a.8 The weapon then will be fired at maximum number of
rounds of the magazine full load.
b. Mud Test
4.3.b.1 The weapon shall be cleaned and oiled lightly and
muzzled taped to prevent entrance of mud into the
bore;
4.3.b.2 The weapon loaded with maximum number of rounds
of the magazine at safe position immersed
completely in the mud for a duration of fifteen (15)
seconds;.
4.3.b.3 Mud mixture shall be made in the proportion of
ten(10) lbs of garden soil and two (2) lbs of sand with
eight (8) quarts of water;
4.3.b.4 Retrieve the weapon from the basin and clean by
wiping with bare hands and by blowing sharply at the
congested area of action;
4.3.b.5 Remove tape, unlock safety and fire the total number
of ammunition; and
63
4.3.b.6 Standard: The weapon must fire satisfactorily the
chamber loaded round and without any malfunctions
or stoppages.
5.
Purpose:
To determine the reliability, quality and safety
characteristic of the weapon when dropped on a concrete
floor.
5.2
Equipment/Materials:
5.2.1 One (1) dummy round
5.2.2 Ammunition Requirements
5.2.2.1 9mm Pistol - 15 rds
5.2.2.2 Cal. 45 pistol 7 rds (standard /13 rds (high
cap)
5.2.2.3 Cal. 38 Revolver - 6 rds
5.3
Procedure:
5.3.1 The pistol will be loaded with dummy ammunition.
Powders were removed retaining the primer.
5.3.2 Load the dummy round and insert the magazine
containing fully loaded with ammunition.
5.3.3 Drop the weapon from a height of five (5) feet with the
following positions;
5.3.3.1 Horizontally upside down (free fall)
5.3.3.2 Vertically grip-side down (free fall); and
5.3.4 After dropping test, remove magazine, it shall be
inspected for external damage. Load the weapon and
fire the remaining ammunition.
5.4
Standard:
5.4.1 The hammer must not fall to battery position;
5.4.2 It must be able to fire the remaining ammunition to
determine its proper functioning.
5.4.3 The pistol shall be at hammer cock position;
5.4.4 The decocker shall be used if the pistol has this
feature; and
5.4.5 Evidence of crack/split on barrel or slide or frame is
classified as critical defect and must not continue the
test.
64
6.
7.
6.2
Equipment/Materials:
6.2.1 One (1) Magazine
6.2.2 Fifteen (15) rounds ammunition
6.3
6.4
6.5
Standard:
There must be no malfunction and damage to
the magazine.
Endurance Test
7.1
Purpose:
To determine the reliability of the weapon under
prolonged firing condition. This could be measured by the
number of malfunctions, number of parts that become
unserviceable and the variation in accuracy and muzzle
velocity.
VII.2 Equipment/Materials:
VII.2.1 Ammunition Requirement
VII.2.1.1Five Thousand (5,000) rounds for Rifle and
Submachine Gun
VII.2.1.2Five Thousand (5,000) rounds for Pistol
VII.2.1.3One Thousand Five Hundred (1,500) rounds
for Revolver
VII.2.2
VII.2.3
VII.2.4
VII.2.5
Gun Oil
Bore brush
Flannel clothe
Electric fan 16 blade
65
66
Maximum Allowable Average
Pressure of Service Loads
20,000 and under (a)
20,100 to 35,000 (b)
35,000 or over (c)
Proof Pressures
Minimum
Maximum
1.16 times a
1.7 times a
1.16 times b
1.6 times b
1.16 times c
1.5 times c
VII.6.2 Cartridges
intentionally
loaded
to
develop
incrementally increasing pressures, in excess of
PROFF pressures, are to be fired in accordance with
the schedule of Table II until the gun assembly
catastrophically fails or until the maximum pressure of
Table II is fired without catastrophic failure.
VII.6.3 All firings are to be from the same but randomly
selected-chamber in a multiple chambered gun.
Maximum Proof
Pressure
20,000 or less
20,100 to 30,000
30,100 to 40,000
40,100 to 50,000
50,100 or more
67
VII.7
68
VII.7.4 Evidence of crack or split on barrel or slide or frame is
also classified as critical defect and must not continue
the test.
VII.8 There shall be no cleaning of weapon other than prescribed
by paragraph 5.4 and 5.5 this parameter.
8
Maximum Pressure
50,000 psi
22,000 psi
70,000 psi
67,500 psi
65,000 psi
8.2
Material: One (1) high pressure (hp) cartridge for all types of
weapon.
8.3
Procedure:
8.3.1 The weapon will be fired using one (1) round of high
pressure cartidge; and
8.3.2 After firing, check the empty cartridge for bulges, splits,
rings, and other defects that maybe caused by
defective barrel.
8.4
Standard:
There must be no inclusion or cracks of any
manner at the barrel assembly especially at the edge of the
chamber and the muzzle and the hole of the slide stop and
barrel link.
Purpose:
To determine whether the sample weapon i.e. firearm
has withstood the pressures of firing incurred during or afte a series
of test which could not be seen or viewed by mans naked eyes by
using scientific procedure in determining the presence of cracks or
splits.
2.
Procedure:
69
2.1
2.2
2.3
3.
B.
Standard: The result of the magnaflux test should not contain any
presence of cracks or splits. Mere presence of crack or split to any
submitted Slides and Barrels, the pistol subject of Test is deemed
classified as FAILED.
Procedure:
1.1.1 Check the weapon to assure the completeness of
parts and determine correct specified dimensions; and
1.1.2 Examine the weapon for proper functioning in order to
assure that no hazard exists during firing.
Properties
Specifications/
Features
Observation Remarks
a)
b)
c)
d)
e)
Weight
Measurement
Trigger Pull
Safety
Muzzle Brakers/Flash
Suppressor
f) Rifling Twist
g) Sight Adjustment
h) Ability to fire rifle
Grenade (Optional)
i) Others
2.
70
2.1.3 Zeroing shall be done in any positions using five (5)
rounds of ammunition.
2.2 Standard: Shall exceed an extreme spread of six (6) inches
mean radius.
3.
4.
5.
6.
Zeroing
- 10 rds
Prone Position
25 meters
- 10 rds
(Unsupported)
1.5 MR
Prone Position
25 meters
- 10 rds
(Supported)
1.5 MR
Standing
25 meters
- 10 rds
(Unsupported)
1.5 MR
Standing
25 meters
- 10 rds
(Supported)
1.5 MR
71
6.4
7.
7.2
7.3
7.4
8.
NOTE:
The weapon must not fire or cook-off within five (5)
minutes starting from the time when one (1) round was
chambered.
9.
Adverse Condition:
a)
72
9.a.7 Pour dust or sand for a duration of one (1) minute each
position (top side and upside down) at a rate of 5 lbs
per minute;
9.a.8 Wipe the weapon with bare hands then blow it sharply
on the congested areas;
9.a.9 Ten (10) rounds of ammunition will be fired in semiautomatic mode while the remaining twenty (20) rds in
full automatic mode;
9.a.10 Inspect the rifle for any damage; and
9.a.11 Repeat the test three (3x) times.
b)
c)
10.
73
10.1
10.2
10.3
10.4
10.5
11.
NOTE:
Firer can use any position. Sandbag or bipod can used
as a rest. The average of two (2) test will be computed and
be used in scoring.
12.
Endurance Test
12.1
12.2
12.3
12.4
12.5
12.6
12.7
12.8
12.9
C.
74
1.
2.
SCOPE.
The test and evaluation for magazine box type covers
all types of magazines for rifle and pistol whether plastic, aluminum
and steel.
3.
4.
5.
PRE-FUNCTIONAL TEST
5.1
5.2
75
5.2.2.2 Firearms
5.2.2.3 Magazines
5.2.3 Standard:
Magazine must be easily inserted and
locked in the magazine well of riffle/pistol and must not
fall without pressing the magazine release lever.
5.3
6.
7.
6.2
Requirements:
6.2.1 Ammunition
6.2.2 Firearms
6.2.3 Magazine
6.3
Standard:
All must be able to feed all rouds to the riffle of
pistol magazine without malfunction or stoppage and must
render the bolt OPEN BOLT position after last round is fired.
76
7.1.1.4 Gasoline; and
7.1.1.5 A mixture of a 7% mineral oil (viscosity 40
60 cantistrokes at 100 degrees Fahrenheit
and viscocity of 60 70, 13.5 percent olele
acid and 1.5 percent friethanclamine)
7.2
Requirement:
7.2.1 Timer
7.2.2 Chemical bath as enumerated
7.2.3 Magazine
7.3
8.
9.
10.
Standard:
There must be no chemical alternation on the
magazine after six (6) days 144 hrs of immersion and clearing
selection.
8.2
Requirement:
8.2.1 Timer
8.2.2 Salt spray chamber
8.2.3 Magazine
8.3
Standard:
Ther must be no evidence of corrosion or rust
on the magazine.
9.2
Requirements:
9.2.1 Timer
9.2.2 Low temperature
9.2.3 Magazine (refer to pg7)
9.3
Standard:
There must be no evidence of deformation on
the magazine after heated at 60 degrees centigrade for 4 hrs.
DROP TEST
77
10.1
Procedure:
10.1.1 Subject four (4) fully loaded magazines to be dropped
from a height of five (5) feet (1.52 M) onto a concrete
floor.
10.1.2 Each magazine shall be dropped once on the following
position enumerated below:
10.1.2.1 Fed lip downward
10.1.2.2 Base down
10.1.2.3 Left side downward
10.1.2.4 Right side downward
10.1.3 It shall be fired in semi-automatic and automatic mode.
11.
12.
10.2
Requirements:
10.2.1 Ammunition
10.2.2 Drop test fixture
10.2.3 Firearms
10.2.4 Magazine
10.3
Standard:
There must be no evidence of deformation on
the magazine after drop test and the riffle must fire without
malfunction attributed to magazine defect.
MUD TEST
11.1
11.2
Mud Mixture
Garden Soil 4.5 kg.
Sand
- 1.0 kg.
Water
- 7.5 ltrs.
11.3
11.4
Standard:
The first 3 rounds must fire in semi- automatic
and automatic mode.
SAND TEST
78
13.
14.
12.1
12.2
Wipe off the dust at the top of the magazine and the first
round with bare hands.
12.3
12.4
12.5
Standard:
All rounds from the magazine must fire without
malfunction.
Procedure:
13.1.1
Load five (5) fully loaded magazines.
13.1.2
Set aside for one (1) week.
13.1.3
After one (1) week, functionally fire the riffle
with magazines subjected to spring compression
test inserted into it.
13.2
13.3
Standard:
All rounds must fire without stoppage or
malfunction.
Procedure:
14.1.1
Insert the fully loaded magazine to the
magazine well of the riffle / pistol.
14.1.2
Lock and release the magazine.
14.1.3
Repeat the procedure 14.1.1 and 14.1.2 until it
is done one hundred (100) times.
79
15.
D.
14.2
14.3
Standard:
All rounds must fire without stoppage or
malfunction.
ENDURANCE TEST
15.1
15.2
Testing Equipment/Materials
15.2.1 Ammunition
15.2.2 Firearms
15.2.3 Magazine
15.3
Random Sampling
1.1
Eiligibility Test
The sample size for this test is fixed at 800 rounds to be
used
for
the duration of test.
1.2
Acceptance Test:
1.2.1 Cartraged are inspected if the delivery is completed
per Purchase Order (PO) and Delivery Receipts (DR).
1.2.2 Sample size will vary depending on the quantity
purchased and delivered. (See Sampling Plan and
AQL)
2.
Visual Inspection
80
Cartridges are inspected visually for defect (see table for
calssification of defects) using sampling plan derived from MIL STD
-105D/E.
Standard:
Cartical Defect/Defective : Accept 0/ Reject
Major Defect/Defective : Aceept 0/ Reject
Minor Defect/Defective : Accept 11/ Reject
3.
1
7
16
Dimensional Inspection
3/ Reject 7
11/ Reject 16
5.
The force to extract the bullet from the cartridge case shall
not be less than 35 lbs using a sample of twenty five (25)
rounds;
Failure of two (2) or more to comply with the requirements
shall cause for the rejection of the lot. If one (1) cartridge
fails, a second sampling is permitted; snd
To be accepted, the number of failures shall not exceed a
total of two (2) for the first and second smapling.
Residual Stress Test (MNT)
5.1
5.2
6.
Accept
Accept
Leak Test
6.1
6.2
6.3
6.4
81
Standard
7.
Accept
3/
Reject
10
Ballistic Test
7.1
Purpose:
Procedures:
7.2.1 Pressure: The samples randomly taken from the same
lot, batch or stock that was visually and dimensionally
inspected will be subjected to chamber pressure test
and shall not exceed the allowable chamber pressure
for each type of caliber; and
7.2.2 Velocity: The samples randomly taken from that same
lot, batch or stock that was visually and dimensionally
inspected will be subjected to velocity test and shall
not be less than the allowable velocity for each type of
caliber.
7.2.3 Accuracy: The samples randomly taken from the same
lot, batch or stock that was visually and dimensionally
inspected will be subjected to accuracy test and shall
not be less than the allowable accuracy measured in
mean radius spread or mean diagonal spread for
each type of caliber.
8.
E.
The wepon FAs will be fired using four hundred eighty (480)
rounds of ammunition; and
The cartridge shall function without casualty at ambient
temperature.
OBJECTIVES:
1.1
1.2
1.3
1.4
82
1.5
2.
PROCEDURES:
2.1
SAMPLING:
2.1.1 The members of the NHQ PNP Inspection and
Technical Committee will randomly pick up the
prescribed quantity to represent the lot size using the
Military Standard 105D/E as the reference to be
subjected for acceptance.
2.1.2 Mark and secure the samples properly.
2.2
83
This nondestructive and field destructive test shall be
performed to measure the stability and safety of the
items when subjected to simulated field and storage
conditions.
2.2.2.1 Workmanship of the finished product will be
inspected in accordance to specifications.
(NonDestructive);
2.2.2.2 Temperature Test finished product will be
subjected to the required tenperature (______)
to determine the reaction of the mixture;
2.2.2.3 Drop Test finished product will be inspected
after dropping from a height if 5 feet (1.5
meters). All will be fired. (Field Destructive); and
2.2.2.4 Water proof or flash Test simulated rain
showers or submeerging it in the water two (2)
inches below the level for twenty five (25)
minutes in normal individual package. All will be
fired (Field Destructive)
2.2.2.5 Functional Test finished product will be fired.
(Field Destructive)
3.
ACCEPTANCE CRITERIA:
DEFECTS
AQL
CRITICAL
MAJOR
MINOR
0.65
2.5
4.0
LEVEL IIA
LEVEL IIIA
SINGLE SAMPLING
PLANS FOR NORMAL
INSPECTION
ACCEPT
REJECT
DOUBLE SAMPLING
PLANS FOR NORMAL
INSPECTION
ACCEPT
REJECT
1
3
5
2
4
6
0
3
5
3
7
9
The result of the above acceptance test shall be the basis for the NHQ PNP
Inspection and Acceptance Committee in the acceptance of said items(s) for use
of the Philippine National Police.
F.
84
Sample size can be determined from MIL STD 105D/E (see
Sampling Plan table) depending on the quantity delivered. Normally,
Inspection Level II is used. However, inspection Level I may be used when
less discrimination is needed or Inspection Level III for greater
discrimination. Four Special Inspectin Levels may be used where relatively
small sample sizes are necessary and large sampling risks can or must be
tolerated.
2.
DEFECTS
AQL
Special Inspection
LEVEL IIV
General Inspection
LEVEL IIII
SINGLE OR DOUBLE
SAMPLING PLANS FOR
NORMAL INSPECTION
ACCEPT
CRITICAL
MAJOR
MINOR
3.
REJECT
ACCEPT
REJECT
0.0
2.5
4.0
RANDOM SAMPLING
3.1
3.2
Procedure:
3.2.1 Letter from SAO PNP Wide requesting for Technical
Inspection;
3.2.2 Schedule the conduct of Random Sampling;
3.2.3 Prepare invitation letters/memo to DL, LSS, DC and
End users for PNP side and/or NAPOLCOM/PS
DBM to witness the acceptance test and random
sampling;
3.2.4 Conduct physical inventory and accounting;
3.2.5 Pick up of sample randomly; and
3.2.6 Mark and secure the samples properly prior to
acceptance test.
4.
VISUAL INSPECTION
85
4.1
4.2
Procedure:
4.2.1 Inspect the item/equipment for completeness as per
Purchase Order and Delivery Receipt;
4.2.2 Determine if it conforms to the NAPOLCOM Approved
PNP Specifications; and
4.2.3 Record all the data/information and observations.
4.2.3.1 Overall Features all samples
4.2.3.1.1 Configaration/Specifications;
4.2.3.1.2 Packing/Packiging; and
4.2.3.1.3 Dents, cracks, deep scratches
4.2.3.2 Missing parts
4.2.3.2.1 that affect safety; and
4.2.3.2.2 that affect functioning
4.2.3.3 Markings
4.2.3.3.1 Readable;
4.2.3.3.2 Nomenclature, lot number, date
loaded and manufacturers product
code;
4.2.3.3.3 Marking must not be easily erased;
and
4.2.3.3.4 Body of the item must be properly
marked.
5.
FUNCTIONAL TEST
A.
FIREARMS
A.1
Ammunition Requirement
A.1.1 Total number of ammunition needed in the
functional test, multiply the number of samples
to the magazine capacity of the firearms;
A1.2 Correction needed in the functional test; and
A1.3 Ammunition requirement is equal to the sum of
A.1.1 and A.1.2.
86
A.2
Functional Test
A.2.1 In the firing range, check whether the weapons
are functional;
A.2.2 Only the DRD Technical Team and firer
authorized by them are allowed to fire the
weapon;
A2.3 Fire the weapon in single and automatic mode
with the required number of ammunition;
A.2.4 Record the process until all samples are fired.
Members of DRD Technical Team are allowed to
take pictures and video footing. Others may be
allowed with permission from the Team Leader;
A.2.5 If found defective, chieck if the defect is within
acceptable level. If the defect is critical, apply
rejection and acceptance number; and
A.2.6 In case of rejection, a re test can be conducted
once the items and equipment are replaced.
B.
RIFLE
GRENADE
CTG 40MM AND CTG
40MM LINKED
B1.
SAMPLING
FUNCTIONAL TEST:
87
pictures and video footing. Others may be allowed with
permission from the Team Leader;
B.2.4 If found defective, check if the defect is within
acceptable level. If the defect is critical, apply
rejection/acceptance number;
B.2.5 In case of rejection, a re-test can be conducted once
the items and equipment are replaced; and
B.2.6 Before leaving the area, DUD cartridges or grenades
must be recovered and destroyed to avoid future
accidents.
C.
FUNCTIONAL TEST
FUNCTIONAL TEST
D.1.1 In the firing range or any suitable place/venue for
functional testing, check whether the items/equipment
is functional;
D.1.2 Only the DRD Technical Team and/or firer/shooters
authorized by them are allowed to conduct the test
with the required number of samples and ammunition;
D.1.3 Record the process until samples are fired. Duly
members of DRD Technical Team are allowed to take
pictures and video footing. Others may be allowed
with permission from the Team Leader;
88
D.1.4 I found defective, check if the defect is with
acceptable level. If the defect is critical, apply
rejection/acceptance number; and
D.1.5 In case of rejection, a re test can be conducted once
the items or equipment are replaced.
Transportation Section
The Transportation Section is one of the three (3) sections in the Weapons,
Transportation and Communications Division of the DRD who played a vital role in
the procurement process of mobility equipment of the PNP. Currently, this Section
simultaneously conducts test and evaluation of patrol cars and motorcycles in
response to the need of the PNP Field Units as well as to attain the goal of the
PNP to modernize its move capabilities.
2.2.1 DEFINITION OF TERMS:
1.
2.
3.
4.
5.
6.
7.
8.
9.
89
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
90
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
91
46.
47.
48.
49.
50.
51.
52.
53.
54.
55.
92
2.
In cases where there are more than four (4) proponents who
have joined the Eligibility Test, services from other Sections of
Weapons, Transportation and Communications Division
(WTCD) or Section from other Division can be tapped upon
discretion of the Chairman, Technical Committee.
3.
b.
c.
d.
e.
f.
g.
h.
i.
j.
4.
Duties:
a.
93
3)
4)
5)
6)
7)
b.
c.
B.
d.
e.
f.
94
received indicating therein the request for inspection and in the same
manner for Acceptance Test. The number of Teams for Eligibility Test will
vary depending on the completion set by the BAC. In case of Acceptance
Test, regular members of the DRD Technical Committee shall compose the
Team. Members of the Team may come from other DRD Divisions or
Sections upon discretion of the Chairman, Teechnical Committee.
1.
Compositon:
A Team shall be composed of the following:
a.
b.
c.
2. Duties:
a.
b.
c.
The BAC shall cause the conduct of eligibility and acceptance tests
of ordnance equipment and supplies as required in every
procurement activity;
B.
C.
The BAC shall conduct visual inspection on the sample and decide
whether to accept or reject it before the functional examination by
the DRD Technical Team;
D.
E.
95
F.
The DRD shall inform the BAC immediately after the lapse of
scheduled submmission of samples and the number of proponents
who submitted samples;
G.
The DRD shall brief and furnish all the proponents copies of the
policy guidelines and parameters to be used in the test. Suggestions
may be received by the DRD and may recommend its adoption by
BAC after which the guidelines and procedures become binding to
the proponents. Complaints may no longer be entertained after the
conduct of the Test and Evaluation;
H.
The DRD shall provide the Technical personnel that will oversee the
conduct of the Test at the selected testing places. The Test shall be
witnessed by representatives from other offices of the PNP,
NAPOLCOM, proponents and other interested persons. A video
footage of the conduct of test shall be taken for future reference;
I.
The DRD may conduct Test and Evaluation of items even in the
absence of any procurement program and directive from the PNP
BAC which will be termed as Product Demonstration. The product
evaluation result shall only be used as reference for any
recommendation which DRD may deem appropriate;
J.
K.
L.
M.
96
request for scheduling duly approved by The Director for Research
and Development (TDRD) will determine its resumption;
N.
O.
P.
Q.
R.
A.
97
2.
3.
Equipment/Materials:
a.
b.
c.
d.
4.
5.
B.
Steel Tape
Vernier Caliper
Brochure of the Vehicle
Diessel Fuel
Procedure:
a.
b.
c.
Standard:
a.
b.
b.
Equipment/Materials:
1) Steel Tape
2) Diesel
3) Speedometer
4) Tachometer
5) Chalk
98
6)
Masking Tape
c.
d.
Procedures:
1)
2)
Speed
Average
Remark(s)
30 kph
45 kph
60 kph
80 kph
100 kph
e.
2.
Standard:
The prototype unit(s) should have stopping
power and reliable brake system.
Accelaration Test
a.
b.
Equipment/Materials.
1)
2)
3)
4)
Timer
Diesel Fuel
Speedometer
Tachometer
c.
d.
Procedure:
1)
2)
3)
4)
99
Required
Speed
0-45 kph
0-60 kph
0-80 kph
0-100 kph
e.
3.
Speed/Time
2
3
4
Ave
Remark(s)
Ascending/Gradeability Test
a.
b.
Equipment/Materials:
1)
2)
Diesel Fuel
Protractor
c.
d.
Procedures:
1)
2)
3)
4)
e.
4.
Required
Time
15 sec
30 sec
45 sec
60 sec
Trials
3
Remark(s)
b.
Equipment/Taterials.
1)
Calculator
100
2)
3)
4)
c.
d.
Procedure:
1)
2)
3)
4)
5)
6)
Speed
e.
5.
Diesel Fuel
Speedometer
Tachometer
Fuel
Consumed
(liters)
Mileage
km/liter
Remark(s)
b.
Equipment/Materials:
1)
2)
3)
Diesel Fuel
Speedometer
Tachometer
c.
d.
Procedure:
1)
101
2)
3)
e.
6.
Maneuverability Test
a.
Purpose:
To determine if the vehicle can manage to turn
360 degrees with a speed of 20 40 kph.
b.
Equipment/Materials:
1)
2)
3)
4)
5)
c.
Steel Tape
Diesel fuel
Speedometer
Chalk
Masking Tape
d. Procedure:
1)
2)
3)
e.
7.
Endurance Test
a.
b.
Equipment/Materials;
1)
2)
3)
c.
Diesel Fuel
Steel Tape
Towing Hook/Wire
102
d.
Procedure:
1)
2)
3)
4)
e.
Standard:
1)
2)
3)
4)
8.
Equipment/Materials:
1)
2)
c.
Procedure:
1)
d.
9.
Diesel Fuel
Smoke Emission Testing Machine
Standard: The vehicle must pass the smoke emission test set
by the government for environmental law compliance.
Pull/stability Test
a.
103
include underchassis and suspension system of the unit.
Usually, no human intervention on the steering system during
the conduct of the test.
b.
Equipment/Materials:
1)
2)
c.
Diesel Fuel
Camber/Wheel Balancing/Alignment Machine
Procedure:
Right after the smoke emission test, the vehicle will undergo
under chassis, camber slignment and wheel balancing test at any
service centers for pulling/stability tests.
d.
2.2.4.2
A.
B.
2.
Handling Test
1.
Definition of Terms:
a.
b.
c.
d.
104
d.1
Slalom Test
105
One (1) representing poor, 5 representing average and 10
representing excellent. The average result of the score attained
will be the score.
d.4 U Turn Test
106
1.
Definition of Terms:
a.
b.
c.
2.
Acceleration Test:
a.
b.
c.
Required
Speed
0 -45
0 -60
0 -80
0 -90
3.
Required
Speed
15 Sec
30 Sec
45 Sec
60 Sec
d.
f.
Rating
b.
c.
d.
107
e.
4.
Brake Test
a.
b.
c.
Speed
Braking Distance
2
3
Average
Remark/s
30 kph
45 kph
60 kph
D.
d.
e.
Definition of Term:
Market availability the availability of the motrocycle spare parts in
various urban centers nationwide.
E.
Endurance Test:
1.
Definittion of Term:
Endurance The quality, act or power of witrhstanding stress.
2.
3.
4.
108
F.
b.
c.
d.
e.
f.
Definition of Term:
Fuel Economy Means the savings is percentage on the total
distance traveled per fuel consumption with and without gadget.
2.
3.
4.
Speed
Distance, Km
Start
G.
Finish
Fuel
Consumed
(liters)
Mileage
(km/liter)
Remark/s
2.
Definition of Terms:
a.
109
b.
c.
d.
3.
4.
Equipments/Materials:
a.
b.
H.
Gasoline/Diesel
Services of smoke emission testing centers
5.
6.
7.
Testing Conditions:
1.
Proponent shall execute waiver or quit claim that the PNP shall not
be responsible for any damage on the motorcycle during the period
of test.
2.
3.
4.
5.
110
2.2.4.3
MEMORANDUM CIRCULAR
Number________________
POLICY GUIDELINES IN THE CONDUCT OF ELIGIBILITY AND
ACCEPTANCE TEST AND EVALUATION FOR PATROL JEEP
(DIESEL, 4X2/4x4)
A.
2.
3.
Equipment/Materials;
a.
b.
c.
d.
4.
Steel Tape
Vernier Caliper
Brochure of the Vehicle
Diesel Fuel
Procedure:
a.
b.
Standard:
111
B.
a.
b.
b. Equipment/Materials:
1)
2)
3)
4)
5)
6)
Steel Tape
Diesel Fuel
Speedometer
Tachometer
Chalk
Masking Tape
c.
d.
Procedures:
1)
2)
Speed
Stopping Distance
2
3
4
Average
Remark(s)
30 kph
45 kph
60 kph
80 kph
100 kph
e.
2.
Acceleration Test
112
a.
b.
Equipment/Materials:
1)
2)
3)
4)
c.
d.
Procedure:
1)
2)
3)
4)
Required
Speed
Required
Time
0-45 kph
0-60 kph
0-80 kph
0-100 kph
15 sec
30 sec
45 sec
60 sec
e.
3.
Timer
Diesel Fuel
Speedometer
Tachometer
1)
Speed/Time
Average
1
Remark/s
Ascending/Gradeability Test
a.
Purpose:
strong.
b.
Equipment/Materials:
Diesel Fuel
2)
Protractor
c.
d.
Procedures:
113
1)
2)
While negotiating the road, the driver will stop the vehicle
in the middle of the road by means of the service brake.
3)
4)
1
e.
4.
TRIALS
3
REMARK(S)
b.
Equipment/Materials:
1)
2)
3)
4)
Calculator
Diesel Fuel
Speedometer
Tachometer
c.
d.
Procedure:
1)
2)
The vehicle shall be filled to full tank with diesel fuel at the
starting point.
3)
4)
5)
114
6)
Speed
e.
5.
Distance
Travelled, Km
Start
Finish
Fuel
Consumed
(liters)
Mileage
km/liter
Remark(s)
b.
Equipment/Materials:
1)
2)
3)
Diesel Fuel
Speedometer
Tachometer
c.
d.
Procedure:
e.
6.
1)
2)
3)
Maneuverability Test
a.
b.
Equipment/Materials:
1)
Steel Tape
115
2)
3)
4)
5)
c.
d.
Procedure:
e.
7.
Diesel fuel
Speedometer
Chalk
Masking Tape
1)
2)
3)
Endurance Test
a.
b.
Equipment/Materials:
1)
2)
3)
Diesel Fuel
Steel Tape
Towing Hook/Wire
c.
d.
Procedure:
e.
1)
2)
3)
4)
Standard:
116
8.
1)
2)
3)
4)
b.
Equipment/Materials:
1)
2)
c.
Diesel Fuel
Smoke Emission Testing Machine
Procedure:
Right after the preceeding test, the vehicle will undergo smoke
emission test at DOTC/LTO accredited smoke emission test center.
d.
9.
Standard: The vehicle must pass the smoke emission test set
by the government for environmental law compliance.
Pull/Stability Test
a.
b.
Equipment/Materials:
1)
2)
c.
Diesel Fuel
Camber/Wheel Balancing/Alignment Machine
Procedure:
117
Right after the smoke emission test, the vehicle will undergo
under chassis, camber alignment and wheel balancing test at any
service centers for pulling/stability tests.
d.
2.3
Communications Section
Memorandum Circular
Number DRD -2004 -01
Test and Evaluation (T&E) Procedure for Multi-Trunked Radio
System (MTRS) and Other Similar Equipment
I.
OBJECTIVE:
118
ORGANIZATION:
SAMPLING PLAN:
TEST PARAMETERS:
B.
C.
D.
E.
V.
SCHEDULE OF ACTIVITY
A.
PHASE I:
119
Location: Suppliers/Manufacturers compound or the designated
delivery area/place stated in the P.O./Contract wherin the required
equipment for programming and Test Instruments and other needed
accessories are available. Inclosure 1 matrix will be used on the results of
General Examination and Sampling
Accounting of all delivered and or installed equipment and its
accessories as provided for in the approved P.O/Contract through the
Delivery Receipt (DR) from the supplier.
1.
General Examination:
a.
b.
c.
d.
e.
f.
2.
B.
PHASE II:
Location: Same as Phase I.
programming.
1.
Repeater/s (Trunked/Conversational)
a.1
a.2
a.3
a.4
a.5
b.
RF power output
Transmit Frequency Measurement
Transmit Max Deviation Measurement
Transmit Frequency Stability
Receiver Sensitivity
Handheld (Analog/Digital)
120
b.1
b.2
b.3
b.4
b.5
c.
2.
RF power output
Transmit Frequency Measurement
Transmit Max Deviation Measurement
Transmit Frequency Stability
Receiver Sensitivity
RF power output
Transmit Frequency Measurement
Transmit Max Deviation Measurement
Transmit Frequency Stability
Receiver Sensitivity
Central Controller
LED Indicator
Frail soft
Control Channel
Voice Channel Access
Configuration Manager Screen
Selective Radio Inhibit
Dynamic Regrouping
SMT Access
Snapshoot
121
b.
c.
d.
e.
f.
g.
h.
C.
PHASE III:
122
The determined distances will be based from the repeater
location or trunking repeaters site with increasing distancesw
mentioned-above. The area coverage from the repeater station
must increase from a distance of one (1) kilometer to a minimum of
fifty (50) kilometers without any barrier.
3.
General examination:
123
7.
8.
9.
Instrumentation test:
1.
RF Power Output:
1.1 Set the regulated power supply to the operating voltage of
the equipment
1.2 Set the radio on trnsmit operation.
1.3 Note the reading on the RF wattmeter.
1.4 Repeat the procedures for all programmed channels (from
the lowest to the highest).
1.5 Measure current drain
2.
Receiver Sensitivity:
2.1 Set the volume and gain control for the maximum output.
2.2 Note down the noise level indicated in the radio power
meter with the FM Signal Generator disconnected from
the antenna socket.
2.3 Reconnect the FM Signal Generator to the receiver
antenna. Set the generator to approximately one hundred
kilohertz (100 kHz) of the operating frequency of the
receiver to obtain a beat noise.
2.4 Adjust the generator signal strenght to obtain a reading in
the audio Power meter which is ten (10) times that of the
noise level previously taken.
3.
124
4.1. RF Power meter with reflect signal reading covering VHF
to HF bands
4.2. Frequency Counter, VHF to UHF Bands
4.3. Signal Geneator, RF and AF Signal capable of emitting,
0,1 microvolt to 0.50 volt, across all frequency range.
4.4. Power Supply (230VAC/12.3 VDC), at least 3 Amp.
4.5. Dummy loads wiith range acrosss encountered transmitter
power output - RF carrier deviation meter/RF modulation
meter.
4.6. VTVM or Digital Multi-meter.
C.
2.
3.
4.
125
5.
After the immersion, the unit with dry cloth for atleast five (5)
minutes to remove the water outside its ssurfaces. After which
the equipment will be subjected to test its RF power output,
sensitivity of the receiver, and frequency accuracy.
6.
Drop Test The set shall be dropped from a height of one half (
) meters to a one fourth (1/4) inches thick plywood, resting on
a concrete surface. This will be performed in all its six (6)
surfaces/angles. After which, the set will be subjected for RF
power output, receiver sensitivity, and frequency accuracy.
7.
8.
9.
D.
E.
126
I.
Purpose:
Policy Guidelines:
B.
C. The DRD shall receive and issue receipt for the samples from
the proponents and shall deposit same to the supply
custodian of the concerned section;
D. The DRD TWG shall conduct visual inspectin on the sample
unit and decide whether to accept or reject before the
fucntional examination. If upon visual examination and
evaluation, the submitted item is found non-conforming
with the standard specifications, no further testing shall be
127
conducted. Instead, the TWG shall notify the propoponent
through a letter the result of the test conducted. If NonConforming, Test and Evaluation Report will be forwarded to
BAC with the receipt of the sample and its corresponding
memorandum;
E.
F.
G.
H.
I.
The Head of the DRD TWG will oversee the conduct of the
Test at the selected testing places. The Test shall be
witnessed by representatives from other concerned
offices/units of the PNP, NAPOLCOM, proponents and other
interested persons. A video coverage/pictorial on the
conduct of test shall be taken;
J.
The DRD may conduct Test and Evaluation of the item which
will be termed as Product Evaluation even in the absence
of any procurement program and directive from the PNP
BAC. The product evaluation result shall only be used as
reference for any recommendation which DRD may
deem appropriate;
K.
L.
128
IV.
M.
N.
The Test and Evaluation may be postponed and rescheduled by the DRD TWG in the absence of the Proponent
or its authorized representative for meritorious reson. A
written request for rescheduling duky approved by The
Director for Research and Development (TDRD) will
determine its resumption;
O.
P.
Q.
Procedures
1. Dimensions
Width : 2.4 m in
TEST
RESUL
T
FINDIN
G
REMAR
KS
129
Height: 5.5 min
Depth : 0.8 min
2. Weight:
7.2 oz max w/ or w/o batteries
3. Display:
1.5 W x 2.2 H, high-contrast, 4level
gray
LCD
with
electro
luminescence backlighting
4. Antenna
Built-in quad helix, with remote
antenna capability
5. Keypad:
Nine multifunction backlit keys
B.
1. Receiver:
WAAS enable, 12 parallel channel
GPS receiver continuously tracks and
uses up to 12 satellites to compute
and update your position.
2. Acquisition Time:
Warm: Approx. 15 seconds
Cold: Approx. 45 seconds
Autolocate: Approx. 5 minutes
3. Update Rate:
One (1) second continuous or better
4. GPS Accuracy:
Position: 15 meters (49 feet) 95%
typical
Velocity: 0.05 meter/sec or 0.1 knot
RMS, steady state
5. Dynamics: 6 gs
6. Interfaces:
USB, RS@#@ w/ NMEA 0183, RTCM
104
DGPS
data
format
and
proprietary
7. Data Storage Life:
Indefinite,
no
memory
battery
required
8. Map Storage:
Internal, 24 MB Minimum
9. Power Source:
TEST
RESUL
T
FINDIN
G
REMAR
KS
130
2AA or 12V adapter cable, or up to 36
VDC external power
Battery Life: Up to 24 hours (typical
use)
10. With downloaded Metro Manila
Street Map up to Barangay level
11. Waterproof Test:
Immersed to water for three (3)
times.
CHAPTER 3
Introduction
131
The TAMANG BIHIS Campaign addresses the need to unify all efforts to
ensure that textiles and accoutrements of prescribed PNP uniforms are procured
only from authorized sources and sold only at the PNP Service Store System and
its outlets including PNP cooperatives and other accredited dealers and suppliers.
Clustered action plans have been formulated for the effective and
sustained implementation of the LOI. First is the dissemination of information to
manufacturers, dealers and suppliers as well as to PNP personnel regarding the
need for an aggressive campaign. Second is the intelligence and investigative
efforts on the modus operandi of these illegal entities including case build up
against them. Third is law enforcement thru active police operations, filing of the
necessary charges and imposition of immediate administrative sanctions. Fourth
is the establishment and full functioning of PNP Cooperatives and the issuance of
a Presidential Executive Order declaring PNP Cooperatives as distributors of
prescribed PNP uniforms, insignias and all other accoutrements, including the
materials for their production. The success of this campaign depends on the
cooperation and commitment of all parties concerned. The greater responsibility,
however, lies in its end user, the policeman, whose conscientious effort to curb
these unlawful acts by the Command, results to a better image for the PNP.
Function of CCED
Review and improve research and development and test and evaluation
procedures and capabilities regarding CCED requirements of the PNP.
Research and study the latest technology in scientific investigation including
relevant equipment and facilities;
Supervise and monitor the conduct of test and evaluation on Clothing
Criminalistic Equipment items procured by the PNP as to their feasibility and
acceptability; and
Perform other duties as directed by higher authorities.
3.2
132
I.
PURPOSE :
ORGANIZATION :
III.
POLICY GUIDELINES:
The Bids and Awards Committee (BAC) shall cause the conduct of
Eligibility/Post Bid Evaluation and Acceptance Tests of the item as required in
every procurement activity;
The DRD will determine the quantity of samples to be submitted for Test
and Evaluation;
The DRD shall receive and issue receipts for the samples from proponents
and shall deposit the same to the supply custodian of the concerned section;
The Technical Team shall conduct visual inspection on the sample unit(s)
and decide whether to accept or reject the same before the conduct of functional
examination. If upon visual examination and evaluation, the submitted item is
found non-conforming with the standard specifications, no further testing shall be
conducted. Test and Evaluation Report will be forwarded to the BAC with its
corresponding memorandum;
NO Suppliers TrademarkTM shall mean non-acceptance of the sample(s);
Samples will be forwarded to any Qualified Testing Institution thru a letter
request for destructive testing with the presence of the proponent(s) and other
concerned units;
No partial Test and Evaluation Report shall be issued by DRD;
The DRD Technical Team(s) will oversee the conduct of the Test at the
selected testing places. The Test shall be witnessed by representatives from other
133
concerned offices/units of the PNP and proponent/s. A video coverage/
photograph on the conduct of test will be taken;
The DRD may conduct Test and Evaluation of the item which will be termed
as Product Evaluation even in the absence of any procurement program and
directive from the PNP BAC. The product evaluation result shall only be used as
reference for any recommendation which DRD may deem appropriate.
The DRD Technical Team shall brief and furnish all the proponents copies
of the policy guidelines and parameters to be used in the test;
The Test Parameters must be conducted one after the other
(chronologically or as the case may require). Any problem arising from a particular
Test Parameter shall be made in writing addressed to Chairman, BAC (attn:
Secretariat). Failure on the part of any affected proponents to file or register
complaints within three (3) days after the conduct of Test and Evaluation shall be
deemed agreement to the overall conduct of the test;
All testing fees, needed equipment and other incidental expenses for use
in the Test and Evaluation shall be borne by the requesting proponents;
The proponent shall provide expert technician who will operate the
submitted item and answer all questions regarding it.
The proponents shall execute a waiver that the DRD Technical Team shall
not be held liable for whatever damage/s will be incurred by anybody to the item
being used during the conduct of Test and Evaluation;
The Test and Evaluation may be postponed and re-scheduled by the DRD
Technical Team in the absence of the Proponent or its authorized representative.
A written request for rescheduling duly approved by The Director for Research
and Development (TDRD) will determine its resumption;
The Eligibility/Post Qualification/ Acceptance Test and Evaluation results of
the item shall be valid only for a particular procurement period. A report that
contains the findings, conclusion and recommendations whether the sample is
conforming or not conforming based on NAPOLCOM-Approved Standard
Specifications and the approved test and evaluation procedures used will be
submitted to BAC thru TDRD;
Proponents whose samples have failed the Eligibility/Post Qualification/
Acceptance Test and Evaluation may request for a reconsideration addressed to
Chairman, BAC. Result of the retest shall be used in the next procurement activity
and shall not be binding in the current procurement program;
Sample/s submitted for testing will be retained for a period of one (1) year;
134
Unclaimed items after three (3) months from the retaining period shall be
forfeited; and
Sample/prototype unit(s) used in the testing will not be a part of the delivery
to the PNP in case the company wins the bidding.
IV.
Random sampling will be done where the delivered items are stored.
The sample size for Acceptance Test from the delivered items will be based
using the Military Standard 105-E tabulated below.
1.
2.
The sample must pass the Phase I and Phase II test parameters
following Military Standard 105-E, Normal Inspection with Acceptance
Quality Level (AQL) of 6.5 and 25 for major and minor defects, respectively.
(see Table 4)
3.2.2 Sample Test Parameters based on Specifications
3.2.2.1
135
II.
PTRI TEST
REPORT
DRD
FINDINGS
Staining: ( F1 F6 ) = 4 to 5
*8. DIST BET. WHITE PIN STRIPES :
8.0 mm
FINAL RESULT
LEGEND : * - Major Parameters
Note:
The report shall be valid only on the fabric samples submitted for
purposes indicated in the Letter Request. Any erasures/alteration and without
DRD seal will nullify such report.
3.2.2.2
136
Dress Shoes, Low-Cut, Clarino (regular) as provided in NAPOLCOM
Resolution No. 99-016
II.
2.
3.
4.
5.
6.
7.
RDC
(ASCOM,PA)
FINDINGS
DEFECTS
NOTED
MAJOR MINOR
REMARKS
137
Density (g/ml) : 0.6 - 0.7
Water Absorp.@ 24 hrs (%):
55 - 65
8. Reverse Welt :
Shall be made of rubber material
Width : 1.0 cm 2.0 cm
9. Counter :
a. Leather Counter :
Shall be vegetable tanned
cowhides leather 2.6 to 2.9 mm
thickness after fitting.
Buffed on the grain side.
b. Fiberboard Counters :
The fiberboard counter shall be
full molded by a molding
equipment.
Thickness (mm) : 1.5 - 1.8
Weight : 1,300 g/m2
10. Tongue :
Shall be made of the same
material as the upper leather.
11. Heel :
The heel should be made of
Rubber black
Heel Nails : The heel nails shall be
Steel or wire type
No. of pcs : 8 - 11
Length
: 2.2 cm
Diameter
: 1.9 mm
12. Eyeletstay :
Shall be made of the same material
as the quarter
Width : 2.9 cm (min.)
13. Thread :
a. Upper Fitting Thread :
The thread of all upper fitting
operations shall be nylon or
polyester.
Breaking Strength : 2 kg (min.)
b. Running Thread :
The running thread for stitching
the welt and the sole shall be
nylon orpolyester
No. of Ply : 5 ply
Breaking Strength : 3 kg (min.)
c. Inseam :
138
Thread for stitching the welt and
the sole shall be Nylon
No. of Ply : 10 ply
Breaking Strength : 10 kg (min.)
14.
15.
16.
17.
18.
19.
d. Double Thread :
The thread for double stitching
of the upper shall be Nylon
No. of Ply : 2 ply
Yarn Size : 500 Denier
Breaking Strength : 2 kg (min.)
Box Toes :
Shall be cut from a material of a
woven
base
flannel
or
processed fabric impregnated with
pyroxylin or polystyrene compound.
Thickness : 1.10 mm to 1.5 mm
Plyrib :
The plyrib shall be made from
elastomeric fiberboard.
Width
: 6.0 mm (min.)
Thickness : 2.0 mm (min.)
Steel Shank: Shall be heavy steel
Shall be three (3) ribbed
Shall be properly placed in the
planter arch surface of the inner
sole.
Shall be with two (2) prongs or
riveted.
Gauge : No. 16
Length : 10.0 cm
Width : 2.5 cm
Bottom Filler :
The bottom filler shall be rubberized
foam coated with adhesive and
firmly pressed into the insole to
even out the bottom surface of the
shoe.
Eyelet:
Shall be blind, plain type
Shall be aluminum
Diameter : 2.0 mm
Thickness :
0.5 mm after
fabrication
and
shall
be
anodized.
No. of Pairs : 5 pairs
Laces :
The laces shall be braided nylon
139
Shall have plastic tips
Length : 70 cm (min.)
Diameter : 2.0 mm
Breaking Strength : 50.0 kg
20. Sock Lining :
Cut from split leather
Thickness : 1.0 mm
21. Reinforcing Tapes :
Shall be non-adhesive cotton tape
Width
: 1.6 cm (min.)
Thickness : 0.25 mm (max.)
TOTAL DEFECTS
CRITERIA :
1.
2.
3.
4.
5.
6.
140
REFERENCES:
CZ P-01 Gets NATO A pproval, CZ U.S.A., Internet Source.
H.P. White Laboratory, Inc - Small Arms Safety Examination and Procedures,
June 1988 issue, U.S.A.
Letter to Mitsubishi Motor Philippines Corporation dated May 20, 2004 re Plant
Visit.
Letter to Toyota Motor Philippines Corporation dated May 20, 2004 re Plant Visit.
Letter to Automobile Association Philippines
Association) dated June 2, 2004.
(formerly
Philippine
Motor
Memo from D, CES and TADL dated July 21, & 22, 2004, respectively.
Memo from DC Management and LSS dated July 12 & 14 2004, respectively.
Memo from TADRD dated July 7, 2004. Memorandum for TDCS/Chairman UESB
thru channel from TDRD re Addendum to NAPOLCOM Resolution No. 2004140 entitled E-MAP Glonal Positioning System (GPS) dated November
30,2006.
Memoranda from TDRD re Test and Evaluation dated November 2, 2004 and
January 2, 2005 respectively
Memo from TDRD, The Procurement System in the PNP dated October 13,2004;
Public Bidding re procurement of Global Positioning System (GPS) and other
items held at PNP Ante Room on December 18,2006, 10:00 A.M.
Memo to TMG and LSS dated April 20, 2004 re Proposed Vehicle and Motorcycle
Parameters Formulation.
Military Standard: Sampling Procedures and Tables for Inspection and Attributes,
May 10, 1989 Revised, U.S.A.
NAPOLCOM Resolution No. 95 -069 Approving the Standard Specifications for
PNP Anti Terrorist Equipment dated August 17, 1995.
NAPOLCOM Resolution No. 2002 -120 Approving the Standard Specifications
for Multi Trunked Radio System (MTRS) dated December 27, 2002.
141
National Institute of Justice (NIJ) Standard-0112.03 for Auto-loading Pistols for
Police Officers, July 1999 issue, U.S.A.
NHQ PNP Bids and Awards Committee (BAC) Resolutin No. 06-20 entitled
Creation of Technical Working Groups that will Perform Test and Evaluation
of Equipment Submitted by Suppliers in Connection with Procurement
Through Public Bidding.
NTC Memo Circular No. 2 -05 -88, Subject: Rules and Regulations Governing the
Manufacture, Acquisition, Sale and Service of Radio Communications
Equipment Series of 1988.
PNP DRD Memo, Addendum and Revision of WTCD WPNS Sec, 1994 Test
Firing Procedure for (Small Arms) Firearms, November 14, 2003.
PNP DRD Memo, DRD Technical Committee Operational Guidelines in the
Conduct of Pre-qualification Test of Pistol 9mm and Cal.45 1911-A1, 20
February 2004.
PNP DRD Memo re Summary of Information re Test and Evaluation, Undated.
PNP DRD Pre-qualification Test and Evaluation Test Firing Procedure for Small
Arms and Long Firearms, Undated.
RDC, PA, AFP Vehicle Test Parameters.
Standard Operating Procedure No. DRD-2004-02, Result of Eligibility Test and
Evaluation Its Application and the Disposition of Sample Firearms Used, 14
October 2004.
Test Parameter, U.S. Army Armament, Munitions and Chemical Command, Rock
Island, Illinois, U.S.A.
Test Result Space-Age Slide Action, from Benellis SuperNova Tactical By: Payton
Miller.
UESB Conferences dated September 29,2006 and October 12, 2006.
UESB Resolution No. 2004-36, Rationalization of the Conduct of PNP Test and
Evaluation approved and adopted on December 23,2004.
WTCD DRD Test Firing Procedure for (Small Arms) Firearms dated July 24, 2005.
142
LIST OF TABLES:
Table 1. Sampling Plan, Normal Inspection Level II
143
144
Special
Inspection
Level
S-2
A
A
A
B
B
B
C
C
C
D
D
D
E
E
E
General
Inspection
Level
I
A
A
B
C
C
D
E
F
G
H
J
K
L
M
N
145
Sample Size
Code Letter
Sampling
Plan
(Double)
Sample
Size
NUMBER OF DEFECTS
AQL 6.5 (Major)
AQL 25 (Minor)
Accept
Reject
Accept
Reject
0
3
1
4
2
6
3
8
5
12
7
18
11
26
3
4
4
5
5
7
7
9
9
13
11
19
16
27
A
1st
2
nd
2
2
st
1
3
C
nd
2
3
st
1
5
D
nd
2
5
1st
8
E
nd
2
8
st
1
13
F
nd
2
13
st
1
20
G
2nd
20
st
1
32
H
nd
2
32
st
1
50
J
nd
2
50
1st
80
K
nd
2
80
st
1
125
L
nd
2
125
st
1
200
M
2nd
200
st
1
315
N
nd
2
315
st
1
500
P
nd
2
500
1st
800
Q
nd
2
800
st
1
1250
R
nd
2
1250
ANNEX 1: AMMUNITION REQUIREMENTS
B
0
1
0
3
1
4
2
6
3
8
5
12
7
18
11
25
2
2
3
4
4
5
5
7
7
9
9
13
13
19
16
27
146
2. Product Evaluation at least 2 units sample pistols
TEST PARAMETERS
CALIBER
Ammo/Rds
Requirements per Sample
9mm
.45 Std
.45
Hi Cap
5.56mm/
9mm SMG
.38
7.62mm
1. Pre-firing Examination
2. Machine Test/Hand Rest
Accuracy Test
3. Interchangeability Test
4. Maintainability Test
5. Adverse Condition Test
a. Sand/Dust
b. Mud
c. Water
15
15
7
15
13
16
30
85
6
6
20
50
15
15
7
7
13
13
NA
NA
6
6
NA
NA
15
15
7
7
13
13
6
6
15
15
7
7
13
13
30
30
30
30
NA
6
NA
20
20
20
20
NA
5,000
3,000
0
5,000
3,000
0
5,000
3,000
0
5,000
3,000
0
3,000
1,800
0
5,000
3,000
0
a. Option 1
b. Option 2
c. Option 3
1
3
50
1
3
50
1
3
50
1
3
50
1
3
NA
1
3
50
Magnaflux Test
Anti-Cook Off Test
Hit-Dispersion Test
Maximum Effective Range
Area Target Capability
Cyclic Rate of Fire
Rate of Aimed Fire
Total
Option 1
Option 2
Option 3
Allowance (+ 5% of Total)
Option 1
Option 2
Option 3
Total (Overall)
Option 1
Option 2
Option 3
0
NA
NA
NA
NA
NA
NA
0
NA
NA
NA
NA
NA
NA
0
NA
NA
NA
NA
NA
NA
NA
330
100
60
90
30
30
0
NA
NA
NA
NA
NA
NA
NA
330
100
60
60
20
20
5,121
3,123
170
5,065
3,067
114
5,108
3,110
157
5,876
3,878
925
3,043
1,845
NA
5,741
3,743
790
259
157
10
255
153
6
252
150
3
294
192
45
157
95
NA
289
187
40
5380
3280
180
5320
3220
120
5360
3260
160
6170
4070
970
3100
1940
NA
6030
3930
830
10.
11.
12.
13.
14.
16.
17.
Annex 2. Inspection T&E Multi-Trunked Radio System (MTRS) and Other Similar
Equipment General Examination
147
148
149
150