Académique Documents
Professionnel Documents
Culture Documents
1.
2.
3.
4.
5.
Introduction
Planning
Design (through DAP)
Break
Design (DAP through PS&E)
Bid and Award
Construction
Summary
2
February 1, 2010
Project location
Projects in urban locations have more stakeholders
(e.g. city government, neighborhoods)
Require great care in design and in construction
planning (get in, get it done, get out)
Stakeholder involvement
State & local elected officials, local & regional
governments, Regional/District offices
Nine state agencies, eighteen federal agencies, 9
federal recognized tribes
Citizen groups and individual citizens, business
organizations
Project Delivery
Module 1
Planning and Program Development
Planning
How projects
are identified,
scoped and
approved
Management
systems
IAMPs
Refinement
plans
Stakeholder
Involvement
Transportation
Planning
Management
System
Scoping
STIP
Approval
Regional Transportation
Plans (RTPs)
Transportation Planning
Coordination
Establish local jurisdiction and public
support for transportation solutions
and management actions
Integrate local land use and
transportation plans. Establish state
and local plan consistency (TSP to
STP and Statewide Modal Plans)
Develop local plan policies and code
changes to support state projects
and facility management objectives
Refinement Planning
Complex Issues requiring more detail than
system planning
Resolve issues that are not fully addressed
in TSPs
Process allows greater detail of problem
identification and solution
recommendation
Can build broader community support
Work is used in NEPA
Management Systems
Management Systems track the location
and condition of transportation assets
The primary management systems used
in program development cover Bridges,
Pavements and Safety
Management systems are also used or
are in development for operations
(congestion), culverts, retaining walls,
slides and other features
Project Scoping
Project Prioritization
Transportation Commission (TC) sets funding
allocations
TC sets program criteria and goals
Planning and management systems list potential
projects across state
Projects from Management Systems primarily
prioritized by regions with stakeholder input
where appropriate
Modernization projects prioritized by Area
Commissions on Transportation
According to STIP criteria
At or Below Estimate
Target
80%
60%
40%
20%
0%
00
01
02
03
04
05
06
07
08
09
At or Below Estimate
Target
Stakeholder Involvement
Required throughout process
Stakeholder Groups Can Include:
Targeted Outreach
Open House / Public Meetings
Stakeholder Involvement
Other Techniques
Stakeholder involvement is front loaded
during planning, which adds time and can
be costly, but results in projects that are
better integrated into surrounding
communities and have less chance of
being challenged during design or formal
environmental process.
Bridge
Pavement
Safety
$4.5 M*
$0.5 M
$0.5 M
Costs
Phase
Modernization
Bridge
Planning/Scoping
9.1%
5.2%
Preservation Safety/Ops
0.4%
3.0%
9.1%
5.2%
0.4%
3.0%
Design
RoW / Utility
Relocation
Bid & Award
Construction
Engineering
Construction
Total (%)
Continuous Improvement
Involve design office, area, district in
system and project planning processes
Involve planners in Project Delivery to
ensure planning commitments are met
Training Planning for non-planners
Leadership teams integration Planning
Business Line Team and Project Delivery
Business Line Team
Asset Management: Expand the use of
management systems to assets other
than bridges, pavements and safety
Continuous Improvement
Future
Discussion
Project Delivery
Module 2
Design (Kick-off through Design
Acceptance Package (DAP))
Project Development
Design
Project Delivery
DAP Criteria
NEPA
Stakeholder Number & Types
Involvement of Deliverables
Preliminary
Approvals
Design
Stakeholder Involvement
Project Location
Project Location
Projects in urban locations have more
stakeholders (e.g. city government,
neighborhoods)
Require great care in design and in
construction planning (get in, get it
done, get out)
Stakeholder Involvement
State & local elected officials, local &
regional governments,
Areas/Districts, Economic
Revitalization Teams
Nine state agencies, eighteen federal
agencies, nine federally recognized
tribes
Citizen Advisory Committees,
stakeholder groups, business
organizations
Work Type
Modernization
Bridge
$76
Operations
(73)
Operations (73)
Preservation (101)
$534
Bridge (106)
Preservation (101)
Preservation
$522
Modernization (67)
Modernization (67)
Bridge (106)
Safety (63)
Safety (63)
$114
$394
Note: Pie slices which have been pulled out represent OTIA and Earmarks.
Modernization Projects
Bridge Projects
Safety Projects
Preservation Projects
Operations Projects
Note: Pie slices which have been pulled out represent OTIA and Earmarks.
What is NEPA?
NEPA requires a rigorous process,
including public involvement and scientific
analysis in order to reach an
environmentally informed decision.
NEPA requires full disclosure about
major actions taken by Federal agencies,
including alternatives to the actions,
impacts, and possible mitigation.
What is NEPA?
National Environmental Policy Act of 1969 (NEPA)
Goals include avoiding, minimizing or mitigating
the impact to socioeconomic, natural, and
cultural resources by
Ensuring consideration of environmental
impacts prior to taking action
Preventing or mitigating damage to the
environment,
Enhancing the health and welfare of people,
Enriching understanding of natural resources
important to the nation
Iterative Process
Full public disclosure
Natural environment
(flora, fauna, wetlands, endangered
species, air quality, water quality)
Section 404, Clean Water Act
Cultural resources
(archaeological, historic, parks)
Section 4 (f) & 6(f), Land and Water
Conservation Fund Act of 1965
Environmental Classification
Class 1 Environmental
Impact Statement
1
66
Class 2 Categorical
Exclusion
Programmatic Exclusion
15
211
Class 3 Environmental
Assessment
26
Undetermined
Class 1 EIS
Class 2
NEPA Deliverables
Can include:
Technical reports including mitigation
plans
Project alternatives
Traffic modeling
Draft document and public hearing
Recommended alternative
Land Use actions/decisions
Final environmental document
FONSI or ROD
MOA for mitigation agreements
Design Acceptance
Package (DAP)
Major decision point. Project go/no go to
final design
Design footprint finalized for R/W,
environmental actions
All elements included
Project team agrees to be bound by
footprint
Area Manager, Design Manager certify
Start Permit Process
Continuous Improvement
Initiatives
Improve environmental scoping
methods
Annual reporting to regulatory agencies
& FHWA (TAC2)
Develop/Expand Mitigation Banking
Programs (include other resources)
Expand use of performance standards
Develop new programmatic
agreements with regulatory agencies
Process Challenges
Right sizing public & stakeholder
involvement
Resource challenges (design, drafting,
technical specialties, environmental)
FHWA regulatory oversight role
inconsistencies
Streamlined Processes
Time Reductions
Continuous Improvement
Initiatives
Batch projects by similar type:
Bridge replacements
Culvert replacements
Interchanges (Rural Category &
Urban Category)
Preservation
Process Challenges
CAT-EX Environmental Sign-off
FHWA requires no final design or ROW
purchase with federal dollars until permits
are in-hand, all environmental work
complete
States can cover ROW purchase with state
funds with state funds being used as
credited for state match
Will add up to one year to project
development for some Class 2 projects
Discussion / Break
Project Delivery
Module 3
Project Delivery Process
Modules 3, 4, & 5
Bruce Johnson, P.E.
Design
(Design Acceptance Package (DAP) through
Plans, Specifications & Estimates (PS&E))
February 1, 2010
Design
(Design Acceptance Package (DAP) through Plans,
Specifications & Estimates (PS&E))
Environmental permitting
Right of Way
Construction (PS&E)
documents
Project Delivery methods
Mobility
Stakeholder involvement
Advanced Plans
95% Complete
Final Plans
100% Complete
PS&E
Roadway Plans
Bridge Plans
Traffic Structures Plans
Retaining Wall Plans
Soundwall Plans
Material Source and Disposal
Site Plans
Roadside Development Plans
Geotechnical Plans
Hazardous Materials Plans
Wetland Mitigation Plans
Erosion Control Plans
Hydraulic Plans
Water Quality and Detention
Plans
Traffic Control Plans
Sign Plans
Striping Plans
Signal Plans
Illumination Plans
Construction Cost Estimate
Construction Schedule
Special Provisions
Utility Conflict List
Constructability Review
Value Engineering Study
Insurance Risk Assessment
Access Management
PS&E Submittal Plan Review
Assemble and Submit Final
PS&E to Office of Pre-Letting
Bidding Package
Phase
Modernization Bridge
Preservation
Safety/
Ops
Planning
9.1%
5.2%
0.4%
3.0%
Design
9.1%
5.4%
6.7%
13.0%
RoW / Utility
Relocation
3.4%
1.3%
1.6%
4.5%
21.6%
11.9%
8.7%
20.5%
Costs
* Right of way expenditures uncommonly low due to specific projects included in this report (largest projects completed were in rural areas or
areas that did not involve significant right of way expenses.
Permittable
Biddable
Buildable
Maintainable
Supported by the community
Process Challenges
Unforeseen issues, scope changes,
new information resulting in
design modification
DAP completeness issues
Environmental Approval prior to
ROW and Final Design for Class 2
projects
Regulatory expectations are
subject to change
Leadership Teams
Better, timelier communications:
Operational notices, technical bulletins,
documented procedures
Decentralization (SASC)
Cradle-to-grave management
Focus on performance measures
OTIA III
Alternative Delivery business models
Judicious selection of technology
improvements.
Discussion
Project Delivery
Module 4
PS&E Review
Estimate
Advertisement
Procurement
Award
Stakeholder
Involvement
Small Contracting
PS&E Review/Estimate
Office of Project Letting - Review of
project package from region PDT
PS&E checklist
Final engineers cost estimate
Confidential
Advertisement
Printing state printer (2 weeks)
Copy of ad for each project to be bid for
publication to Daily Journal of Commerce
Hard copy & electronic
Ad posted on Procurement Office Website
and Bid Express
Communication with bidders exclusively
through Procurement Office and Project
Managers Office
PS&E Review/Estimate
Approval to advertise
Provide contract documents to OPO
and Project Managers Office
PS&E review process and final
engineers estimate completed in 2
weeks (5 weeks if full federal oversight
required)
Procurement
Bid opening
Bid review for responsiveness and
responsibility
Bid analysis to determine if award or
rejection is in the best interest of the
public
Recommendation to award or reject
Construction Authorization
Procurement
Final Approval
Award
Chief Engineer
Deputy Director
Transportation
Commission
FHWA
Notice to
Proceed
Timeframes
PS&E to bid opening - 45 days to 80
days
Includes advertisement. Approximately 35 weeks.
Stakeholders
(construction contractors)
Coordination via Association of
General Contractors
Key issues
Bid advertising
Rejection of bids
Protest filings
Costs
Modernization
Bridge
Planning
Phase
9.1%
5.2%
Preservation Safety/Ops
0.4%
3.0%
Design
9.1%
5.4%
6.7%
13.0%
RoW / Utility
Relocation
3.4%
1.3%
1.6%
4.5%
0.1%
0.1%
0.2%
0.8%
21.7%
12.0%
8.9%
21.3%
Construction
Engineering
Construction
Total (%)
Discussion
Construction
Project Delivery
Module 5
Contract management
Quality Assurance
Environmental
Compliance
Work Force Monitoring
Dispute/Claims
resolution process
Payment
Final documentation
Stakeholder
Involvement
Duration: 6 months 4 years
Construction Begins
Contract Management
Inspectors / Testers
What they do
Inspectors assigned to monitor and
document progress
h1
Monitor quality, quantity, workmanship
Central Materials Lab AASHTO
Materials Reference Library - Certified
Materials staff monitor quality of
materials
Contract Management
Project Manager
What they do
Project Manager assigned to administer
each contract
Assure compliance with contract
requirements
Manage contract within construction
authorization
Negotiate changes as necessary
Communicate with stakeholders
Slide 41
h1
Environmental Compliance
Require contractor submittal of plans
prior to starting work.
Inspectors monitor compliance to
plans and permits daily.
Region Environmental Coordinators
review progress and provide
assistance regularly.
Regulatory Agencies visit projects
occasionally.
Contract Management
Delegated Change Order Authority
- Project Manager
$100,000 & 14 Days
- Area Manager
$250,000 & 30 Days
- Region Manager
$250,000 & 30 Days
- Contract Administration
Engineer/Chief Engineer
Anything above
Contract Management
Other roles in Construction
Office staff to coordinate
documentation and process payment
Construction Section provides
support and statewide consistency.
Contract Management
Delegated overrun in Authorization
Authorities
- Project Manager
None
- Area Manager
$250,000
- Region Manager
$500,000
- Oregon Transportation Commission
Unlimited
Payment
Stakeholder Involvement
Daily communication with Contractor by PM staff.
Frequent communications with effected local
agencies and local businesses.
Frequent communications with effected residences.
Regular contact with impacted regulatory agencies.
Regular contact with impacted utilities and rail
road.
Monthly meetings with Industry to work global
issues.
Costs
Phase
Modernization
Bridge
Planning
9.1%
5.2%
Preservation Safety/Ops
0.4%
3.0%
Design
9.1%
5.4%
6.7%
13.0%
RoW / Utility
Relocation
3.4%
1.3%
1.6%
4.5%
0.1%
0.1%
0.2%
0.8%
Construction
Engineering
6.7%
6.7%
6.1%
9.1%
Construction
71.6%
81.3%
85.0%
69.6%
100.0%
100.0%
100.0%
100.0%
Total (%)
Discussion
Continuous Improvements
Scan 07-01
Best Practices in Project Delivery Management
Project Management Structure
cohesive, multidisciplinary teams that communicated
well
roles and responsibilities must be clearly understood
effective hand offs
accountability of PMs and technical support units
Risk Management
manage schedule risks by not including projects in the
STIP until they have a Record of Decision (ROD)
reduce project costs through a Practical Design
philosophy
Summary
Project Phases
Common Issues
STIP Composition
Complexity and Variation in projects
The right project at the right time at the right cost in the right way.
The right way means do it right the first time, avoid rework, minimize
adverse impacts to business, residents, freight haulers, the traveling
public and the environment. The right way requires you to be riskconscious, process-oriented.