Vous êtes sur la page 1sur 41

Tuesday,

March 29, 2005

Part III

Department of
Defense
Office of the Secretary

32 CFR Part 184


Contractors’ Safety for Ammunition and
Explosives; Proposed Rule

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00001 Fmt 4717 Sfmt 4717 E:\FR\FM\29MRP2.SGM 29MRP2
16038 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

DEPARTMENT OF DEFENSE the Department of Defense Explosives promulgated, shall be exempt from the
Safety Board as a joint activity of the requirements under 5 U.S.C. 601–612.
Office of the Secretary Department of Defense subject to the This proposed rule does not have a
direction, authority and control of the significant economic impact on small
32 CFR Part 184 Secretary of Defense. The majority of the entities as defined in the Act.
RIN 0790–AH76 standards impacting upon the public
Unfunded Mandates Act of 1995 (Sec.
were adopted prior to the enactment of
202, Pub. L. 104–4)
[DoD 4145.26–M] the Administrative Procedure Act. This
proposed rule is intended to ensure This proposed regulatory action does
Contractors’ Safety for Ammunition public awareness of the extent of the not contain a Federal mandate that will
and Explosives explosives safety standards as well as result in the expenditure by State, local,
offer the public an opportunity to and tribal governments, in aggregate, or
AGENCY: Office of the Secretary of by the private sector of $100 million or
comment on the standards. The
Defense. more in any one year.
information addresses the HCSDS
ACTION: Proposed rule for comment. sometimes furnished with solicitations Paperwork Reduction Act of 1995 (44
SUMMARY: The Department of Defense or contracts to provide an insight into U.S.C. Chapter 35)
(DoD) is codifying its revised explosives potentially hazardous characteristics of
the materials involved in the production Paperwork Reduction Act. The
safety standards for ammunition and proposed rule imposes no obligatory
explosives (A&E) work performed under of the item addressed in the solicitation.
Contractors retain the ultimate information requirements beyond
DoD contracts. This proposed rule is internal Department of Defense needs.
necessary to minimize the potential for responsibility for assuring the safety of
mishaps that could interrupt DoD their personnel and establishment. Federalism (Executive Order 13132)
operations, delay project completion Information provided by the HCSDS is
derived from other sources. Verification This proposed regulatory action does
dates, adversely impact DoD production not have federalism implications, as set
base or capability, damage or destroy of such data as shipping and storage
hazard division and storage forth in Executive Order 13132. It will
DoD-owned material/equipment, cause not have substantial direct effects on the
injury to DoD personnel, or endanger compatibility group information must
be done through the DoD Joint Hazard States, on the relationship between the
the general public. The benefits of this national government and the States, or
proposed rule in terms of the protection Classification System (JHCS) or Title 49,
Code of Federal Regulations. on the distribution of power and
of the public and ensuring contract responsibilities among the various
These classifications pertain to AE
performance are expected to balance its levels of government.
packaged for transportation or storage.
potential cost or administrative impacts.
Such hazard classification information Section 202, Public Law 104–4,
Only provisions related to conventional
may not be valid when applied to the ‘‘Unfunded Mandates Reform Act’’
AE operations have been included in
hazards associated with manufacturing
this proposed rule. No attempt was It has been determined that this rule
or loading processes. For such
made to encompass general industrial does not involve a Federal mandate that
processes, the materials and processes
safety, occupational health concerns, may result in the expenditure by State,
must be analyzed on a case-by-case
chemical warfare agents, radiation, or local and tribal governments, in the
basis. Sources of information to support
over-the-road transportation aggregate, or by the private sector, of
this analysis are available from service
requirements, because these are either $100 million or more and that such
research and development organizations
the responsibility of other regulatory rulemaking will not significantly or
through contract channels and other
agencies (for example DOT, DOL/OSHA, uniquely affect small governments.
sources.
or NRC) or may be addressed elsewhere
in the contract by the procuring activity. Executive Order 12866 List of Subjects in 32 CFR Part 184
Budgetary effects of this proposed rule This proposed rule does not: Ammunition and explosives, DoD
are minimal since existing DoD Federal (1) Have an annual effect of the contractors.
Acquisition Regulation Supplement economy of $100 million or more or Accordingly, 32 CFR part 184 is
coverage already requires compliance adversely affect in a material way the proposed to be added to read as follows:
with safety requirements in AE economy, a sector of the economy,
solicitations and contracts. Finally, productivity, competition, jobs, the PART 184—DOD CONTRACTORS’
because this proposed rule is needed to environment, public health or safety, or SAFETY MANUAL
minimize the potential for AE mishaps state, local, or tribal governments. Sec.
that could adversely impact DoD and (2) Create a serious inconsistency or 184.1 Introduction.
the public, timely publication in the otherwise interfere with an action taken 184.2 Mishap investigation and reporting.
Federal Register is important. or planned by another agency. 184.3 General safety requirements.
DATES: Comments are to be received not (3) Materially alter the budgetary 184.4 Quantity-distance and siting.
later than May 31, 2005. impact of entitlement, grants, user fees, 184.5 Hazard classification, storage
or loan programs or the rights and principles, and compatibility groups.
FOR FURTHER INFORMATION CONTACT: Dr.
obligations of recipients thereof; or 184.6 Electrical safety requirements for AE
Jerry M. Ward, Director, Engineer facilities.
Technical Programs Division, DDESB, (4) Raise novel legal or policy issues
arising out of legal mandates, the 184.7 Manufacturing and processing
telephone (703) 325–2525, fax: (703) propellants.
325–6227; e-mail: President’s priorities, or the principles 184.8 Safety requirements for
Jerry.Ward@DDESB.OSD.mil. set forth in this Executive Order. manufacturing and processing
Regulatory Flexibility Act of 1980 (5 pyrotechnics.
SUPPLEMENTARY INFORMATION: Pursuant 184.9 Storage of ammunition and
to the authority vested in the Secretary U.S.C. 605(b))
explosives.
of Defense in accordance with 10 U.S.C. Regulatory Flexibility Act. It has been 184.10 Fire protection.
172, DoD Directive 6055.9 established certified that this proposed rule, if 184.11 Risk identification and management.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00002 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16039

184.12 AE building design and layout. cognizant DoD Component explosives (2) Evidence of implementation of a
184.13 Safety requirements for specific AE safety office for their records. Military or safety program containing at least
and AE operations. commercial ammunition and explosives mandatory requirements described in
184.14 Test and testing requirements. shall not be procured unless their use is § 184.3.
184.15 Collection and destruction
authorized by the cognizant DoD (3) General description of proposed
requirements for AE.
184.16 Construction and siting criteria. Component explosives safety approval contract facilities, including size,
Appendix A to 32 CFR Part 184—Glossary authority. Methods of addressing non- building layouts, construction details,
compliance with mandatory and fire resistive capabilities.
Authority: 10 U.S.C. 172. requirements and requests for waivers (4) Fire prevention program and
are different during the pre- and post- available firefighting resources
§ 184.1 Introduction. award phases of a contract. including local agreements or other
(a) Purpose. This part provides safety (3) In the pre-award phase, the PCO documentation demonstrating
requirements, guidance and information will request a DoD pre-award safety coordination.
to minimize potential mishaps which survey to help determine contractor (5) Copies of required licenses and
could interrupt Department of Defense capability. During pre-award surveys, permits or demonstration of the ability
(DoD) operations, delay production, noncompliance with mandatory safety to obtain approvals necessary to support
damage DoD property, cause injury to requirements normally results in a the proposed contract.
DoD personnel, or endanger the public recommendation of ‘‘no award.’’ Any (6) A safety history including mishap
during contract work or services noncompliance should be resolved experience, safety survey or audit
involving ammunition and explosives during the pre-award survey. reports by insurance carriers or Federal,
(AE). The part contains the minimum Contractors may choose to correct the State, and local authorities, and any
contractual safety requirements to deficiencies immediately, may offer a variances, exemptions or waivers of
support the objectives of DoD. These letter of intent to correct the deficiencies safety or fire protection requirements
requirements are not a complete safety (which will become binding upon issued by Federal, state or local
program and this part does not relieve award of contract), or may request that authorities.
a contractor from complying with the PCO accept specifically identified (7) Details of proposed operations and
Federal, State and local laws and existing conditions of facilities equipment to include process flow
regulations. (contract-specific waiver). narrative/diagram, proposed facility or
(b) Applicability. These safety (4) In the post-award phase, the equipment changes, hazard analysis,
requirements apply to contractors contractor has 30 days from the date of and proposed procedures for all phases
performing AE work or AE services on notification by the administrative of AE operations.
DoD contracts, subcontracts, purchase contracting officer (ACO) to correct the (8) Subcontractor information. (i)
orders, or other procurement methods. noncompliance and inform the ACO of Identification of all subcontractors
The requirements also apply to non-DoD the corrective actions taken. The proposed for the AE work.
contractor operations to the extent contracting officer may direct a different (ii) Methods used to evaluate
necessary to protect DoD work or time period for the correction of any capability of subcontractor to comply
services. noncompliance. If the contractor refuses with the requirements of this part.
(c) Mandatory and advisory or fails to correct any noncompliance (iii) Methods used to manage
requirements. The part uses the term within the time period specified by the subcontractor compliance.
‘‘shall’’, or an affirmative statement, to ACO, the Government has the right to (f) Preoperational safety survey. The
indicate mandatory requirements. The direct the contractor to cease DoD reserves the right to conduct a
terms ‘‘should’’ and ‘‘may’’ are advisory. performance on all or part of affected preoperational survey after contract
When advisory provisions are not met, contracts. When the contractor cannot award of new items with limited
adverse consequences might develop comply with the mandatory safety contractor experience, after major new
and become proximate causes of AE requirements of the contract, the construction or major modifications, or
mishaps. contractor will develop and submit a after an AE mishap. When these
(d) Compliance with mandatory request for a waiver through the ACO to situations occur, the contractor shall
requirements. (1) The Department of the PCO for the final determination. The notify the ACO, sufficiently in advance,
Defense requires compliance with request will contain complete to provide the Department of Defense
mandatory provisions of this part and information concerning the the opportunity to schedule and
applicable portions of DoD 6055.9– requirements violated, actions planned perform a preoperational survey.
STD.1 Siting criteria for AE are provided to minimize the hazard, and a proposed (g) Post-award contractor
in quantity distance (Q–D) standards date for correction of the deficiency. responsibilities. The contractor shall:
contained in Chapter 9 of DoD 6055.9– (e) Pre-award safety survey. DoD (1) Comply with the requirements of
STD. In order to provide consistent and safety personnel conduct pre-award this part and any other safety
current information to all DoD AE surveys to evaluate each prospective requirements contained within the
contractors, Q–D requirements of DoD contractor’s ability to comply with contract.
6055.9–STD are incorporated by contract safety requirements. The pre- (2) Develop and implement a
reference in paragraph C317. award safety survey is also an demonstrable safety program, including
(2) Waivers. Procuring contracting opportunity for the contractor to request operational procedures, intended to
officers (PCO) may grant contract- clarification of any safety requirement prevent AE-related mishaps.
specific waivers to mandatory or other AE issue that may affect the (3) Designate qualified individuals to
provisions of this part. Rationale for contractor’s ability to comply. During administer and implement this safety
waiver of DoD pre-award safety surveys pre-award surveys, the contractor shall program.
must be documented and provided to provide the following: (4) Prepare, and keep available for
the cognizant ACO for transmittal to the (1) Site plans conforming to review, all hazard analyses used to
paragraphs (h)(5)(i) through (h)(5)(iv) of justify alternative methods of hazards
1 Copies may be obtained via Internet at http:// this section for proposed facilities to be control that differ from those
www.dtic.mil/whs/directives. used in contract performance. recommended in this part.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00003 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16040 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

(5) Provide access to facilities and formal site plan submission is (b) Reporting criteria. The contractor
safety program documentation to necessary. shall investigate and report to the ACO
Government safety representatives. (5) Site plans shall comply with the and cognizant Defense Contract
(6) Report and investigate AE mishaps following: Management Agency (DCMA) contract
in accordance with § 184.2. (i) Plans shall include maps and safety specialist all mishaps involving
(7) Provide identification and location drawings which are legible, accurate, ammunition or explosives that result in
of subcontractors to the ACO for and of a scale which permits easy one or more of the following:
notification or approval in accordance determination of essential details. For (1) One or more fatalities.
with terms of the contract. general layout of buildings, this is (2) One or more lost-work day cases
(8) Establish and implement normally a scale of 1 inch to 400 feet (or with days away from work as defined by
management controls to ensure AE metric equivalent) or less. Site plans 29 U.S.C. 651–678.
subcontractors comply with paragraphs may require other-scaled drawings, (3) Five or more non-fatal injuries
(g)(1) through (g)(7) of this section. which provide details of construction, (with or without lost workdays).
(h) Site and construction plans. (1) structure relationships within the (4) Damage to government property
Contractors must prepare site and project area, barricades, or other unique exceeding $20,000.
construction plans for support of the details. Plans may also include pictures (5) Delay in delivery schedule
pre-award process, and for any change to illustrate details and videotapes of exceeding 24 hours. (This requirement
in layout or construction potentially MCE testing data. does not constitute a waiver or
affecting Q–D incident to the contract. (ii) Maps and drawings shall identify amendment of any delivery schedule
Contractors shall also maintain a current distances between all PESs, all exposed required by the contract.).
site map depicting Q–D relationships for sites (ESs) within the facility, the (6) Contractually required
all AE locations within the facilities. facility boundary, any additional notifications of mishaps other than in
(2) When the place of performance of property under contractor control, ESs paragraphs (b)(1) through (b)(5) of this
the contract is at a DoD-owned facility, on adjacent property when applicable, section; or
site and construction plans shall be public railways and highways, power (7) Any mishap that may degrade
prepared and processed (content and transmission lines and other utilities. operational or production capability, or
staffing) in accordance with the (iii) Plans shall identify and briefly is likely to arouse media interest.
requirements of DoD 6055.9–STD, as describe all PESs and all ESs within any (c) Mishap investigation requirements.
well as, appropriate military service applicable fragmentation distance and/ Paragraph (e) of this section contains the
regulations contained within the or inhabitable building distance of a elements of information which a basic
contract. PES. Site plans for major new investigation shall produce. Based upon
(3) For contractor-owned, contractor- construction or modification shall also the seriousness of the mishap and
operated (COCO) facilities, the identify and briefly describe all PESs impact on munitions or munitions
contractor shall submit, through the whose inhabitable building distance are systems involved, the ACO or PCO may
ACO to the PCO, site and construction includes the proposed new or modified require an additional, more
plans for all new construction or major site. comprehensive investigation. The PCO
(iv) Plans shall include the maximum
modification of facilities for AE retains the right to participate in
net explosive weight(s) (NEW) and the
activities and for the facilities that may contractor investigations, or to perform
HC/Ds of all PESs and, when applicable,
be exposed to AE hazards if improperly an independent DoD investigation. In
shall include MCE information and
located. The contractor shall provide the event the PCO directs DoD
maximum NEW for each room or bay.
sufficient copies for the review process. participation, or an independent DoD
Plans shall also include engineering or
The contractor shall not begin investigation, the contractor shall
test data when substituting construction
construction or modification of preserve the mishap scene, taking only
or shielding for distance to protect from
proposed facilities until receiving site those actions necessary to protect life
fragmentation or overpressure.
and construction plan approval from the and health, preclude further damage, or
(v) Plans shall include a topographical
PCO through the ACO. prevent access by unauthorized persons
map in sufficient detail to permit
(4) Minor new construction, changes, in order to preserve investigative
evaluation, when the contractor uses
and modifications of existing AE evidence. The contractor shall obtain
natural terrain for barricading to reduce
facilities involving Hazard Class/ the PCO’s permission to disturb the
fragment distance.
Division (HC/D) additions and deletions (6) Construction plans for proposed evidence, with the exception of
or that add or remove small portable facilities shall contain the information paragraph (b)(2) of this section. Nothing
operating buildings and magazines may required in paragraphs (h)(5)(i) through in the reporting requirements contained
not require formal site plan submission. (h)(5)(v) of this section and construction in this part relieve the contractor of
Minor applies to all changes that details of dividing walls, venting making other notifications required by
involve only 1.4 HC/D materials. Minor surfaces, firewalls, roofs, operational Federal, State, or local requirements.
also applies to changes of other HC/D shields, barricades, exits, ventilation (d) Telephone report. The contractor
materials that do not increase the systems and equipment, AE waste shall report any mishap described in
existing maximum credible event (MCE) disposal systems, lightning protection paragraph (b) of this section by
for an AE facility or do not extend any systems, grounding systems, processing telephone to the ACO and cognizant
quantity distance arcs beyond existing equipment auxiliary support structures, DCMA contract safety specialist as soon
fragment, inhabited building, and public and, general materials of construction, as practicable, but not later than three
traffic route distance arcs for other as applicable. hours after the mishap.
nearby potential explosion sites (PES). (e) Written report. (1) The contractor
When the contractor thinks a § 184.2 Mishap investigation and shall submit a written report to the ACO
modification/change is minor, he shall reporting. and cognizant DCMA contract safety
notify the ACO and request a (a) General. This section contains specialist by the end of the second
determination. The ACO shall make the requirements for investigating and business day after mishap occurrence.
final determination as to whether a reporting mishaps involving AE. (i) Contractor’s name and location.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00004 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16041

(ii) Date, local time, and plant facility/ (2) All buildings, cubicles, cells, work involving exposure to AE. The
location of the mishap. rooms, and locations containing AE training shall include emphasis on the
(iii) Type of mishap (explosion, fire, shall have AE and personnel limits specific safety and health hazards,
loss, other). prominently posted. Include emergency operations including
(iv) Contract, subcontract, or purchase supervisors, production workers, and shutdown, and safe work practices
order. transient personnel when determining applicable to the employee’s job tasks.
(v) Item nomenclature, hazard personnel limits. Posted personnel The contractor shall ascertain that each
classification, lot number. limits are not required in storage employee involved in an AE process has
(vi) Mishap narrative. magazines, magazine areas, or transfer received and understood the training.
(vii) Number of injuries, fatalities, points. The contractor shall prepare a record
degree of injuries. (viii) Description of (3) All buildings, cubicles, cells, that contains the identity of the
property damage and cost. rooms or locations containing AE shall employee, the date of training, and the
(ix) Quantity of energetic material means used to verify that the employee
have prominently posted limits for the
involved (pounds, units, rounds). understood the training.
(x) Probable cause(s). quantities of AE permitted. The posted
limits shall not exceed the quantity (5) Emergency procedures. The
(xi) Corrective action taken or
stipulated in the site plan, and shall contractor shall instruct employees on
planned.
(xii) Effect on production. accurately reflect current process procedures to follow in the event of
(xiii) Name, title or position, and requirements. Post AE limits in storage electrical storms, utility or mechanical
phone number of person submitting the magazines when the limit differs from failures, equipment failures, process
report. that for other magazines in the block, or abnormalities, and other emergencies
(xiv) Remarks. when circumstances prevent the limit occurring during the manufacturing,
(2) The contractor shall provide to the from being readily apparent. It is not handling, or processing of AE.
ACO supplemental information to the required to express AE limits in units of (6) Revalidation. Qualified personnel
initial report within 30 days of mishap weight or in the number of items. shall review SOPs on a regular basis.
occurrence. Express limits in terms of trays, boxes, The managing authority shall change
(f) Special technical mishap racks, or other units more easily and validate SOPs as often as necessary
investigations and reports. When observed and controlled. to reflect improved methods, equipment
warranted by the circumstances of a (c) Standard operating procedures substitutions, facility modifications, or
mishap, the PCO may require a special (SOP). (1) Clearly written procedures are process revisions.
technical investigation conducted by essential to avoid operator errors and (d) Storage in operating buildings. (1)
DoD personnel. The PCO may also ensure process control. Therefore, The contractor may store limited
direct the contractor to conduct a before commencing manufacturing quantities of hazardous materials, other
special technical investigation. In either operations involving AE, qualified than AE materials, which are essential
case, the investigation report shall personnel shall develop, review, and for current operations in an operating
provide details such as fragmentation approve written procedures. building.
maps, photographs, more detailed (2) Preparation. The contractor shall (2) The contractor shall store AE
description of events of the mishap, prepare and implement written materials that exceed minimum quantity
effects on adjacent operations, structural necessary for sustained operations in a
procedures which provide clear
and equipment damage, Q–D drawings, service magazine located no closer than
instructions for safely conducting AE
detailed description of occurrence and the intraline distance (ILD) (based on
activities. The use of controlled tests is
related events, findings and the quantity in the magazine) from the
an acceptable method for developing
conclusions. If the contractor performs operating building or area. If ILD
and validating SOPs. SOPs shall include
the special technical mishap distance is not available for a separate
the following:
investigation, the contractor shall service magazine, the contractor may
(i) The specific hazards associated
forward the report through the ACO to designate storage locations within the
with the process.
the PCO within 60 days of the direction (ii) Indicators for identifying operating building. Designated storage
by the PCO to perform the investigation. abnormal process conditions. locations shall preclude immediate
Upon determination by the PCO that a (iii) Emergency procedures for propagation from the operational
DoD investigation is required, the PCO abnormal process conditions or other location to the storage location. The
will immediately advise the contractor. conditions which could affect the safety quantity of AE material in the internal
of the process. storage location shall not exceed that
§ 184.3 General safety requirements. (iv) Personal protective clothing and needed for one half of a work shift. The
(a) General. This section provides equipment required by process contractor should consider personnel
general safety requirements for all AE personnel. exposure, structural containment
operations addressed in this part. When (v) Personnel and AE limits. afforded, and the venting ability of the
these practices exceed or differ from (vi) Specific tools permitted for use by proposed storage location when
local or national codes or requirements, the process operator. determining where to locate a
the more restrictive shall apply. (vii) The chronological sequence of designated storage location. When
(b) Personnel and material limits. (1) job steps the operator is to follow in storage containers completely contain
Control of all locations or operations performing the work. all fragments, debris, and overpressure,
presenting real or potential hazards to (viii) Procedures for disposing of any AE material may be stored without
personnel, property, or the environment scrap and waste AE. regard to Q–D requirements.
is essential for safety and efficiency. (3) Dissemination. Personnel involved (3) At the end of the workday,
Control measures include minimizing with AE processes, and personnel who personnel should remove all AE
the number of personnel exposed, maintain AE equipment, shall have material from processing equipment and
minimizing the duration of the written operating procedures readily store it in an appropriate magazine or
exposure, and minimizing the amount accessible. designated storage location. If
of hazardous material consistent with (4) Training. Personnel shall receive operationally required, personnel may
safe and efficient operations. appropriate training before performing store in-process AE materials in the

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00005 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16042 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

building during non-operating hours inspecting equipment after maintenance percent. The contractor shall maintain
provided the physical characteristics work to ensure no tools or foreign records of the test that demonstrate the
and stability of the AE materials are not materials remain in AE equipment. The shields will function as planned.
degraded, and the AE material would SOPs shall identify the specific tools Analysis rather than testing of shields
not compromise the safety of the required to perform work on equipment may be acceptable on a case-by-case
process equipment or personnel when which may contain explosive residues basis.
the process is restarted. or areas which could have an explosive (5) When the doors of AE processing
(4) The contractor may use a separate atmosphere. equipment function as operational
enclosed room or bay in an operating (4) Before performing any building shields, interlocking devices are
building specifically adapted for the repair, modification or maintenance required to prevent the operator from
interim storage of production items activity, the contractor shall ensure the opening the door while the equipment
awaiting the results of testing before removal of all AE materials from areas is in operation.
final pack-out. The room or bay must that may pose a hazard. The contractor (h) Protective clothing. (1) All AE
afford the equivalent of service shall also ensure the decontamination of operations require a hazard assessment
magazine distance protection to other all places where AE material could to determine the need for protective
parts of the building, and ILD to other accumulate, such as, equipment, clothing and personal protective
buildings. Such a room or bay is limited crevices, vents, ducts, wall cavities, equipment. The assessment shall
to its defined and designed function and pipes and fittings. include an evaluation of all hazards and
items, but is not subject to the four-hour (g) Operational shields. (1) The factors contained in paragraph (g)(2) of
supply limitation for the building or the purpose of operational shields is to this section.
ultimate pack-out operation. prevent propagation of AE material from (2) The contractor shall provide a
(e) Housekeeping in hazardous areas. one AE operation or location to another, changing area for employees who must
(1) The contractor shall keep protect facilities and equipment, and remove their street clothes to wear
structures containing AE clean and provide personnel protection. Shields protective clothing, such as explosive
orderly. used for these purposes require an plant clothing, anti-contamination
(2) Explosives and explosive dusts evaluation to determine their suitability clothing, impervious clothing, and so
shall not accumulate on structural for their intended purpose. All AE forth. To avoid exposing personnel not
members, radiators, heating coils, steam, operations and processes require a involved in AE operations to
gas, air or water supply pipes, or hazard assessment prior to work unnecessary risks, employees shall not
electrical fixtures. performance to determine the type of wear or remove protective clothing from
(3) Written procedures shall include hazard involved, the level of risk the premises. Employees shall not wear
instructions for the removal of spilled associated with the AE material or item, any static producing clothing in areas
material. and the corresponding level of where static electricity is a hazard.
(4) Floor cleaning methods shall not protection required. (3) Explosives plant clothing,
create an ignition hazard or alter the (2) The primary hazards that generally referred to as powder
conductive ability of floors in AE areas, accompany explosions and deflagrations uniforms, shall have nonmetallic
nor should they result in an are blast overpressure, fragmentation fasteners and be easily removable.
environmental contamination potential. (primary and secondary) and thermal (4) When sending explosives-
(5) Cleaning methods for AE effects. The hazard assessment shall contaminated clothing to an off-plant
processing equipment shall not result in consider these hazards and the quantity laundry facility, the contractor is
any foreign material or AE remaining in of AE materials, initiation sensitivity, responsible for informing the laundry of
the equipment. heat output, rate of burning, potential the hazards associated with the
(f) Precautions for maintenance and ignition and initiation sources, contaminants and any special
repairs to equipment and buildings. (1) protection capabilities of shields, laundering or disposal requirements.
The contractor shall examine and test various types of protective clothing, fire (i) Material handling equipment. (1)
all new or repaired AE processing protection systems, and the acute and The contractor shall not refuel gasoline,
equipment prior to placing the chronic health hazards of vapors and diesel or liquefied petroleum gas (LPG)
equipment in service in order to ensure combustion products on exposed powered equipment inside buildings
that it is safe to operate. personnel. containing AE. Refueling shall take
(2) Before proceeding with (3) When the hazard assessment place at least 100 feet from structures or
maintenance or repairs to AE processing indicates an unacceptable probability of sites containing AE. Doors and windows
equipment, contractor personnel shall explosion or deflagration, conduct through which vapors may enter the
decontaminate the equipment to the operations or processes remotely. When building shall not be open during
degree necessary to perform the work an analysis of the hazard assessment refueling. Position refueling vehicles at
safely. The contractor shall protect indicates the hazards associated with an least 100 feet from structures or sites
maintenance personnel from the effects explosion or deflagration are containing AE during refueling.
of a reaction resulting from AE material controllable by using operational (2) Gasoline-, diesel- or LPG-powered
in or on other parts of the equipment. shields, the contractor shall design, equipment shall not be stored in
Contractor personnel shall tag AE install, and use shields which buildings, loading docks, or piers
processing equipment before proceeding effectively protect personnel from the containing AE. The contractor shall
with repairs. The tag shall identify the hazards. Shields complying with MIL– store gasoline-, diesel-, and LPG-
decontaminated parts of the equipment, STD–398 are acceptable protection. powered equipment at the appropriate
and those parts that contain AE. (4) The contractor shall test fire protection distance from buildings
(3) The contractor shall have SOPs for operational shields under conditions containing AE.
maintenance personnel performing that simulate the operational (3) Gasoline, diesel, and LPG powered
work on AE equipment or performing environment. AE materials or items equipment shall have spark arrestors.
building maintenance, repair, or used in the test shall correspond to The contractor shall perform and
modification activities in AE areas. The those that may be involved in a document inspections of the exhaust
SOPs shall include a provision for maximum credible event (MCE), plus 25 and electrical systems of the equipment

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00006 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16043

as necessary to ensure that the systems on enough railcars to ensure the cars breakdown, accident, damaged or
are functioning within the will not move. Personnel shall set hand leaking containers, and spilled material.
manufacture’s specifications. The brakes on the downgrade end of a group (5) Transportation containers shall not
contractor shall maintain of parked railcars. Do not rely on the allow the contents to leak or spill in
documentation of the inspections for a automatic air brakes to hold parked transit.
period of one year. railcars. (6) Non-sparking material shall cover
(j) Parking of privately owned (4) Contractor personnel shall avoid the cargo compartment when
vehicles. (1) Control of parking of rough handling of railcars. Personnel transporting AE in containers capable of
privately owned vehicles within an AE shall not disconnect railcars containing exposing their contents if damaged.
establishment minimizes fire and AE from each other or a locomotive (7) Motor vehicles transporting AE
explosion hazards and prevents while in motion. Personnel shall couple within the establishment boundaries but
congestion in an emergency. railcars gently in order to avoid outside the AE area shall bear at least
(2) Parking lots serving multiple PESs damaging the AE cargo or shipping two placards. Placards based on the fire
shall not be closer than the ILD from containers. Disconnected railcars shall division symbols discussed in § 184.10,
each PES. Parking lots serving a single not strike railcars containing AE. ‘‘Fire Protection,’’ are acceptable. Motor
PES shall not be closer than 100 feet to (5) The contractor shall maintain all vehicles or equipment with internal
the associated facility to protect it from rolling stock used for intraplant combustion engines, used near
vehicle fires, and shall be at least public transportation of AE in a safe and good explosives scrap, waste, or items
traffic route distance from unassociated contaminated with explosives shall
working condition.
PESs. Parking lots for administration have exhaust system spark arresters and
(6) Portable transmitters and railroad
areas shall be located at public traffic carburetor flame arresters (authorized
locomotives equipped with two-way
route distance from all PESs. air cleaners).
radios shall not transmit when passing (8) The contractor shall maintain
(3) Vehicles shall not obstruct access AE operating buildings where electro-
to buildings by emergency equipment or vehicles and material handling
explosive devices are in use. The equipment used to load and transport
personnel. contractor shall determine minimum
(k) Ignition sources in hazardous AE in a safe operating condition.
safe distances based on radio frequency (9) Batteries and wiring shall be
areas. The contractor shall not permit
and power output of the transmitter. located to prevent contact with
any nonessential ignition sources in
(n) Intraplant motor vehicle containers of AE material.
operating buildings.
(l) Operational explosives containers. transportation of AE. (1) The contractor (o) Inspection of AE mixing
(1) Containers shall be compatible with shall develop written procedures for the equipment. (1) The contractor shall
the material they contain. safe transportation of AE in motor establish a preventative maintenance
(2) Containers used for intraplant vehicles. The SOP shall include program which includes the inspection
transportation or storage of process procedures for vehicle inspection, of all AE mixing equipment on a
explosives and energetic materials shall vehicle operation, loading and periodic basis. The SOP for the
not leak. Because of their fragility and unloading AE materials, and emergency inspection shall include criteria for
potential for fragmentation, glass procedures, including fire fighting. inspecting the blades to bowl
containers are not acceptable. (2) The operator responsible for clearances, alignment of the blades and
(m) Intraplant rail transportation. (1) transporting AE material shall perform a bowl, and detection of any distortion of
The contractor shall develop written daily inspection of the vehicle before the blades or bowl. The inspection
procedures to ensure safe and efficient transporting materials. The operator procedures shall also include
rail movement of AE. The SOPs shall shall verify that the fire extinguisher is instructions for checking critical drive
include information covering the charged and in working order, there are system components for wear, damage or
inspection of the engine, car mover, and no fuels or other fluid leaks, and that misalignment. The procedures shall
cars, normal and emergency operating brakes, tires, steering, and other include criteria for determining that
procedures for the engine and car equipment are in good operating associated equipment used to control
mover, AE loading and unloading condition. Before transporting AE, the the mixer is functioning as designed.
procedures, and emergency procedures operator shall inspect the cargo The contractor shall maintain a record
including fire fighting. compartment to ensure it does not of all inspections. After performing
(2) Railcars positioned for loading contain any residual AE material or any maintenance of the equipment, the
shall have their brakes engaged to object which could present a hazard to contractor shall run the equipment
prevent movement. Contractor the cargo. under load to ensure it is safe to operate.
personnel shall inspect each railcar (3) When loading or unloading AE, (2) The SOPs for operating mixing
before loading to ensure it is suitable to the operator shall shutoff the vehicle’s equipment shall include instructions for
carry the specific AE cargo. Contractor engine, unless the engine is required to inspecting specific equipment
personnel shall check the cargo to provide power to equipment for loading components before each use.
ensure it is stable and secure, and close or unloading. The operator shall engage (p) Facility requirements. (1)
the railcar doors before car movement. the emergency brake and use wheel Buildings. The design, construction
If using an engine to move railcars, the chocks when the vehicle could move techniques, process layout, and siting of
contractor shall ensure that personnel during loading or unloading. The AE buildings are important
have connected the air brakes of the operator shall stabilize and ensure the considerations in explosives safety and
railcars in sequence to the engine. If load is secure to prevent damage to directly influence quantity distance (Q–
moving a railcar with a car mover the containers or their contents. The D) requirements and the degree of
contractor shall station an individual at operator shall not transport AE material exposure to personnel, equipment, and
the hand brake of the railcar. in the passenger compartment of the facilities. Construction features which
(3) A single parked railcar shall have vehicle. limit the amount of explosives involved,
the hand brakes set and the wheels (4) The vehicle operator shall attenuate the resulting blast
chocked. When more than one railcar is understand and follow established overpressure or thermal radiation, and
parked, personnel shall set hand brakes procedures involving a vehicle fire, reduce the quantity and range of

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00007 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16044 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

hazardous fragments and debris will accumulation of energetic materials. In number of exposed glass panels and
help to minimize the effects of an addition, all conductive and non- panel size to a minimum. When
explosion. Incorporating Q–D criteria, sparking floors and work surfaces window panels are necessary and risk
when locating an exposed site (ES) in require preventative maintenance to assessment determines a glass hazard
relation to a potential explosive site ensure their functional integrity. will be present, blast resistant windows
(PES), will reduce the amount of (5) Substantial dividing walls. The must be used. The framing and/or sash
damage and injuries in the event of an contractor shall design and construct of such panels must be of sufficient
incident. substantial dividing walls to prevent strength to retain the panel in the
(2) Building exteriors. The contractor simultaneous detonation of explosives structure.
should design and erect AE buildings on opposite sides of the wall. The (11) Hardware. (i) AE operations and
with the ability to allow for the venting design and construction shall meet the hazardous locations require an
of an internal explosion without criteria contained in Army TM 5–1300, evaluation to determine the safest type
collapsing. The use of lightweight Navy NAVFAC P–397, or Air Force AFR of hardware and fasteners to use in
materials in exterior wall and roof 88–22 (different designations for the order to reduce the risk of an accidental
sections designed to vent the effects of same publication). ignition. Consider using non-sparking
an explosion will help reduce the (6) Exits and doors. (i) All AE hardware and fasteners if they will meet
number of large fragments. Exceptions buildings require adequate exits and the design parameters of the intended
from using lightweight materials doors. NFPA Standard No. 101, ‘‘Life application. Depending on the potential
include earth-covered magazines, Safety Code,’’ provides information hazard, a locking device or some other
containment type structures, firewalls, concerning exits and doors. installation technique shall retain the
substantial dividing walls, special roof (ii) NFPA Standard No. 80, ‘‘Standard hardware and fasteners securely in
loadings, and walls and roofs used for for Fire Doors, Fire Windows,’’ provides place. This will prevent the hardware
external overpressure protection. Non- information on the selection and and fasteners from becoming loose,
combustible exterior wall and roof installation of fire doors and windows. entering process equipment and creating
coverings of operating buildings help (iii) No AE hazards shall occupy a spark or pinch point.
prevent the spread of fire from one area space between an operator and an exit. (ii) The contractor should avoid
of a building to another and from (7) Safety chutes. Multi-storied installing hardware, pipes, ducts, and
building to building. locations where rapid egress is vital and other items on blowout panels in order
(3) Interior walls, roofs, and ceilings. not otherwise possible require safety to prevent the materials from becoming
(i) Non-combustible material is chutes. secondary fragments. If it is necessary to
preferred for the interior surfaces of (8) Passageways. (i) Weather-
install items on blowout panels, select
buildings. The contractor should treat or protected passageways and ramps for
items made of materials which will not
cover exposed combustion supporting travel between buildings or magazines
yield heavy fragments in an explosion.
building materials with fire retardant should include features to help prevent
material. (12) Ventilation systems. (i) Well-
fire from spreading from one building to
(ii) Where hazardous locations exist, designed ventilation systems reduce
another. Fireproof construction
interior surfaces shall be smooth, free personnel exposures to airborne
materials, fire stops, fire doors, and fire
from cracks, crevices and openings contaminants and prevent the
suppression systems aid in preventing
which may create a hazardous accumulation of flammable or explosive
the spread of fire.
condition. This is important to prevent (ii) The incorporation of weak concentrations of gases, vapors or dusts.
the accumulation or migration of sections, openings, or abrupt change in A local ventilation system, which
explosive dust and vapors which could direction of passageways will aid in the removes the gases, vapors, or dusts at
result in an incident. The National Fire prevention of funneling the explosion the source, is more effective than a
Protection Association (NFPA), forces from one building to another. general ventilation system.
Standard 70 2 provides criteria for (9) Roads and walkways. (i) Only (ii) A ventilation system is required in
determining if a location is hazardous. roads servicing a single magazine or AE areas of buildings generating potentially
(iii) The contractor should use hard processing building, including its explosive dusts, gases or vapors.
gloss, easily cleanable, paint on painted service facilities, may dead end at the Testing, inspection, and maintenance of
surfaces. magazine or building. ventilation systems used for
(iv) Periodically clean any surface (ii) Hard surfaced roads and walkways contaminant control require
where explosive dust could accumulate. at the entrances to or between adjacent documentation.
Establish cleaning schedules on operating buildings containing AE will (iii) Exhaust fans through which
information obtained from the job help reduce the amount of foreign combustible dust or flammable vapor
hazard analysis. material tracked into the building by pass shall have nonferrous blades or a
(v) Do not use suspended ceilings in personnel. casing lined with nonferrous material.
hazardous locations. (iii) Avoid a road system which The electrical wiring and equipment of
(4) Floors and work surfaces. (i) requires personnel to pass through an the system should comply with
Locations where exposed explosives or AE area when traveling from one area to provisions of NFPA Standard No. 70,
hazardous concentrations of flammable another. ‘‘National Electrical Code’’. Bonding
vapor or gas are present require non- (10) Windows and skylights. (i) and grounding of the entire system is
sparking floors and work surfaces. Inhabited building distances do not required.
(ii) § 184.12 provides requirements for protect against glass breakage and the (iv) A slight negative pressure is
conductive non-sparking floors and hazards of flying glass. Buildings required in rooms where AE operations
work surfaces. separated by inhabited building generate explosive dust.
(iii) Floors and work surfaces require
distance should not have windows or (v) NFPA Standard No. 91, ‘‘Standard
periodic cleaning to prevent the
other glass surfaces exposed to PESs. for Exhaust Systems for Air Conveying
2 Obtain NFPA publications from the National
(ii) Minimize personnel hazards from of Vapors, Gases, Mists, and
Fire Protection Association at http://www.nfpa.org/ glass breakage by means such as Noncombustible Particulate Solids,’’
catalog/home/index.asp. building orientation and/or keeping the provides standards for exhaust systems.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00008 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16045

(13) Steam for processing and heating. An insulating pipe covering capable of wave of an explosion. This is important
(i) Steam used to heat buildings reducing the surface temperature of the in order to minimize the possibility of
containing explosives shall not exceed covering to 160 °F (71 °C) or less is an explosion in one building from
228 °F (108.9 °C) or have a pressure acceptable. affecting the operations in the other
greater than 5 psi (34.48 kPa). (iv) In AE handling or storage building. For further information on
(ii) Process steam shall not exceed locations where resistance to ground is tunnels go to DoD 6055.9–STD.3
249.5 °F (120.8 °C), or exceed 15 psi high, ground steam and hot water lines (q) Quantity-distance (Q–D)
(103.43 kPa). Steam pressure greater where they enter the building. requirements. (1) Minimum Q–D
than 15 psi (103.43 kPa) requires (v) When using a reducing valve, requirements are contained in DoD
procuring contracting officer (PCO) consider installing a relief valve on the 6055.9–STD, DoD Ammunition and
approval. low-pressure piping. The throttling Explosives Safety Standards.
(iii) The surface temperature of steam action of reducing valves requires a (2) For AE work involving an MCE of
and hot water pipes in contact with positive means to prevent the 0.25 kg (0.55 lbs) or less of HD 1.1
combustible materials shall not exceed production of superheated steam. materials, the use of the separation
160 °F (71 °C). Pipes with an ambient (14) Tunnels. Tunnels between distances listed in Table 1 to § 184.3 are
temperature greater than 160 °F (71 °C) buildings that contain AE shall acceptable for meeting minimum Q–D
shall not contact combustible materials. incorporate features that resist the shock requirements.

TABLE 1 TO § 184.3.—MINIMUM Q–D REQUIREMENTS FOR SMALL QUANTITIES OF HAZARD DIVISION 1.1 MATERIAL
Inhabited building and frag- Public traffic route and Intraline and fragment dis-
Net explosive weight ment distance fragment distance tance

Less than 0.003 kg (0.0066 lb) ....................................... 0 ......................................... 0 ......................................... 0.


0.003 kg–0.01 kg (0.0066 lb–0.022 lb) ........................... 5 m (16.5 ft) ....................... 3 m (9.9 ft) ......................... 2 m (6.6 ft).
0.01 kg–0.25 kg (0.022 lb–0.55 lb) ................................. 15 m (49.5 ft) ..................... 9 m (29.7 ft) ....................... 5 m (16.5 ft).

§ 184.4 Quantity-distance and siting. dusts and flammable vapors and gasses Underwriters Laboratories (UL) or other
Refer to DoD 6055.9, Chapter 9 for which, in general, are comparably recognized testing laboratory as suitable
guidance. hazardous. NFPA Standard No. 70 for use in all classes of hazardous
(Article 500) defines ‘‘hazardous locations.
§ 184.5 Hazard classification, storage (3) Change of classification. The
locations’’ according to the hazard
principles, and compatibility groups.
presented by electrical equipment specific processes performed in
Please refer to DoD 6055.9, Chapter 3 installed in environments where operating buildings and magazines
for guidance. flammable gases or vapors, combustible dictate the requirements for electrical
§ 184.6. Electrical safety requirements for dusts or flyings may exist. The presence equipment installation. If functions
AE facilities. of AE may or may not result in rating performed in the facility change,
(a) General. Initiation systems often a particular location as a ‘‘hazardous responsible personnel shall inspect,
use the controlled input of electrical location.’’ The following exceptions approve, or reclassify the hazardous
energy to initiate explosive mixtures shall be used by DoD contractors when locations.
and compounds, which start an applying the NFPA Standard No. 70 (4) Alternate power source. Facilities
explosive train. The uncontrolled definitions of Class I, Division 1, and shall have an alternate power source for
release of electrical energy in explosive Class II, Division 1 hazardous locations: special processes and operations
atmospheres or near explosives and (i) Classify areas containing explosive requiring a continuous supply of power,
explosive-loaded articles can result in dusts or explosive substances which whenever the loss of power will result
unintended initiation and serious may produce dust capable of suspension in a more hazardous condition.
mishaps. Electrical energy manifests in the atmosphere as Class II, Division (5) Portable engine-driven generators.
itself in many forms (e.g., standard 1 hazardous locations. The exposed, non-current-carrying,
electrical installations, lightning, (ii) Classify areas where explosive metallic frame and parts shall be
electrostatic discharge, electrical testing) sublimation or condensation may occur electrically grounded. In addition,
and with various intensities which as both Class I Division 1 and Class II observe the following requirements
require special precautions. This Division 1 hazardous locations. when supplying power to magazines or
chapter contains minimum electrical (iii) Exceptions are extraordinarily explosives operating facilities.
safety requirements for existing, new, or hazardous explosive substances, such as (i) Place generating units at least 50 ft
modified explosives facilities and nitroglycerin (NG), which require (15.2 m) from magazines or hazardous
equipment. special consideration, including (classified) locations.
(b) Electrical installations. (1) physical isolation from electric motors, (ii) Keep the ground area between and
National Fire Protection Association devices, lighting fixtures and the like. around the generator and the NFPA
(NFPA) Standard No. 70 and this (2) Multiple classifications. In some Standard No. 70 hazardous (classified)
section are minimum requirements for potential explosion sites (PES) (e.g., location clear of debris and other
areas containing explosives. NFPA powder blending with solvents), combustible materials.
Standard No. 70 does not specifically hazards resulting from both dusts and (iii) The exhaust from the generator
address explosives, but it does establish flammable vapors may exist. In these shall not impinge on grass or any other
standards for the design and installation cases, it is necessary for that area to combustible material.
of electrical equipment and wiring in have a dual, or multiple, classification. (iv) Position the power cord
atmospheres containing combustible Use only electrical equipment listed by connecting the generator to the load to

3 See footnote 1 to § 184.1(d)(1).

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00009 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16046 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

prevent trucks or personnel from electrical equipment approved for the Where static spark discharge may be
running over or otherwise damaging the National Electric Code (NEC) defined hazardous, NFPA Standard No. 77, shall
cord. ‘‘hazardous location’’ and listed by apply, except as otherwise specified.
(v) Do not use cable-to-cable splices Underwriters Laboratories (UL) or other (3) Static ground system. A static
within a magazine, explosive operating nationally recognized testing agencies. ground system consists of one or more
facility, or other NFPA Standard No. 70 (c) Primary electric supply. The electrodes in contact with the earth and
hazardous (classified) location. Use only primary electric supply to an entire a conductor (i.e., metal wire) bonded to
three-wire, three-prong, approved explosives area should be arranged to the electrode and routed throughout the
service type plugs and connectors. allow cutting off the supply by remote protected facility. The static ground
(vi) Refer to § 184.3(i)(1) for refueling switches located at one or more central system may use building structural steel
procedures. points away from the area. (unless structural steel is used as
(6) Electric supply systems. Electrical (d) Ventilation. Equip exhaust fans, lightning protection down conductor),
and explosives hazards may mutually through which combustible dust or metallic water pipes, ground cones,
exist when PES are in close proximity flammable vapor pass, with nonferrous buried copper plates, and rods driven
to electric supply lines. To protect these blades, or line the casing with into the earth as electrodes. The ground
hazards from each other, the following nonferrous material. Motors shall meet system shall not use gas, steam, or air
separation requirements shall apply: the proper NEC class for the hazard lines, dry pipe sprinkler systems, or air
(i) Separate overhead service lines (NFPA Standard No. 70). Clean and terminals and down conductors of
from a PES of combustible construction service exhaust systems on a regular lightning protection systems as earth
or a PES in the open by the distance schedule. Bond and ground the entire electrodes. A static ground system
between the poles or towers supporting system. provides a conductive path to earth
the lines, unless an effective means is (e) Lightning protection. When from conductive floors, conductive
provided to ensure that energized lines lightning protection systems are work surfaces, and AE equipment and
cannot contact the facility or its installed, the installation, inspection, allows any generated static charges to
appurtenances if they are severed. Four and maintenance shall comply with the dissipate.
acceptable alternatives are cable trays NFPA Standard No. 780, at a minimum. (4) Testing equipment grounds.
and messenger lines, a ground-fault Typically, six month visual tests and 24- Trained personnel shall test ground
circuit-interrupter which causes a month electrical tests of installed systems after installation, after repairs,
disconnecting means to open all systems are acceptable. and at locally determined intervals and
ungrounded conductors of the faulted (f) Static electricity and grounding. (1) shall keep all records. Remove all
circuit, weighted triangle line separators Two unlike materials (at least one of exposed explosive or hazardous
or similar weights which ensure broken which is non-conductive) produce static materials from the room or area before
lines fall straight down away from PES, electricity due to contact and testing. The resistance of the electrode
and constructed physical barriers. separation. Contact creates a to earth shall not exceed 25 ohms. The
(ii) Separate electric distribution lines redistribution of charge across the area electrical resistance from any point on
carrying less than 69 kV, the tower or of contact and establishes an attractive the conductor to the electrode shall not
poles supporting those lines, and force. Separation of the materials exceed 1 ohm. The ground system
unmanned electrical substations from overcomes these attractive forces and design shall provide for interconnecting
PES by public traffic route distance sets up an electrostatic field between the all ground electrodes of structures
(PTRD). two surfaces. If no conducting path is equipped with a lightning protection
(iii) Separate electric transmission available to allow the charges to system.
lines carrying 69 kV or more and the equalize on the surfaces, the voltage (5) Grounding of equipment.
tower or poles supporting them from difference between the surfaces can Contractor maintenance personnel shall
PES by: easily reach several thousand volts as bond all AE equipment (e.g., mixers,
(A) Inhabited building distance (IBD) they separate. grinding mills, screening and sifting
if the line in question is part of a grid (2) The potential hazard of static devices, assembly and disassembly
system serving a large area off the electricity arises when an accumulated machines, conveyors, elevators, steel
establishment. electrical charge subsequently work tables, presses, hoppers) to the
(B) PTRD if loss of the line does not discharges as a spark in the presence of ground system wherever ESD presents
create serious social or economic hazardous atmospheres, flammable an ignition hazard. The resistance of the
hardships. (Note: Base PTRD and IBD on vapors, dusts, exposed sensitive AE equipment to the grounding system
airblast overpressure only. Fragment explosives, or electro-explosive device shall not exceed 1 ohm. Trained
distances shall not apply.) (EED). Electrostatic discharge (ESD) personnel shall test this resistance
(C) Distances in accordance with does not present a substantial hazard initially at installation and at least
paragraph (b)(6)(1) of this section when during the handling of most bulk semiannually thereafter, and shall keep
the line(s) in question can be explosive substances if the explosives all records. Exclude the resistance of
interrupted without loss of power (i.e., are in approved containers. It also does conductive belting when testing for
other lines or networks exist for not present a hazard near explosives resistance of belt-driven machinery to
rerouting power). totally contained and unexposed within the ground system. Bonding straps shall
(iv) Avoid locating permanent electric loaded articles. It is not possible to bridge contact points where oil, paint,
installations in NFPA Standard No. 70 prevent the generation of static or rust could disrupt electrical
Class I or Class II hazardous locations. electricity entirely. Elimination of continuity. Permanent equipment in
When practical operating reasons potential ESD hazards requires proper contact with conductive floors or
prevent locating permanent electrical grounding to dissipate static charges tabletops does not meet the bonding
installations outside of hazardous before they accumulate to dangerous requirement to the ground system.
locations, or require the use of portable levels. The NFPA, UL and the U.S. Maintain compatibility of metallic
electrical equipment (e.g., lighting Department of Commerce publish bonding and grounding cables, straps, or
equipment) in hazardous locations, detailed discussions of the hazards of clamps with the explosives involved in
contractors shall only install or use static electricity and ways of reducing it. the process.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00010 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16047

(6) Belts. Use conductive belting may use conductive wrist straps in (ii) To protect against electrocution,
wherever ESD is an ignition hazard. The place of conductive floors and shoes for the minimum resistance of the floor to
resistance of conductive conveyor belts grounding personnel at small scale and the ground system and the minimum
shall not exceed one million ohms as isolated operations. When using wrist resistance of the tabletop to the ground
measured between two electrodes straps, operators shall test wrist straps system shall exceed 11,000 ohms in
placed on the belt and as measured before each use (whenever removed and areas with 110 volts service and 22,000
between an electrode placed on the re-worn) and record test results. The ohms in areas with 220 volts service. A
conductive conveyor belt and an resistance of the wrist strap while the ground fault interrupt (GFI) circuit also
electrode attached to the ground system. operator is wearing the strap shall fall meets this requirement.
Do not use static combs to drain off within a range of 25,000 ohms (iii) Tabletop test criteria. The
static charges generated from belts or (minimum) and 1,200,000 ohms maximum resistance of conductive
pulleys used in hazardous locations. (maximum) when measured from tabletops to the ground system shall not
(g) Conductive floors, tabletops, and opposite hand to ground. Use test exceed 1 million ohms.
footwear. Contractors shall use equipment capable of testing 1,200,000 (iv) Conductive footwear. All
conductive tabletops and, shall use ohms + 10%. (Note: Operators with dry personnel shall test conductive footwear
conductive floors and conductive shoes skin may use special contact creams to daily before use to ensure that the
for grounding personnel at operations decrease the resistance to the required combined resistance of the person’s
involving exposed explosives with value.) body and the conductive shoes do not
electrostatic sensitivity of 0.1 J or less (3) Conductive floor and tabletop exceed the limit specified in paragraph
(e.g., primer, initiator, detonator, igniter, specifications. Conductive floors and (g)(5)(i) of this section. Supervisors shall
tracer, and incendiary mixtures). tabletops, made of, or covered with non- keep documentation of all test results,
Bonding wires or straps shall connect sparking materials such as lead, including calibration of test equipment.
the tabletops and floors to the static conductive rubber, or conductive The test voltage of the shoe tester shall
ground system. Materials sensitive to compositions, shall meet the following not exceed 500 volts. The short circuit
initiation by ESD sparks include lead requirements: current across the shoe tester electrodes
styphnate, lead azide, mercury (i) Provide a continuous electrical (plates) should be limited between 0.5
fulminate, tetrazene, path to the static ground system and the ma and 2.0 ma. The design of the test
diazodinitrophenol, potassium chlorate- electrical resistance shall not to exceed instrument shall include built-in
lead styphanate mixtures, igniter the limits specified in paragraph (g)(5)(i) safeguards to prevent the test subject
compositions, grade B magnesium of this section. from experiencing electric shock.
powder, and exposed layers of black (ii) Provide a reasonably smooth Personnel shall not test shoes in rooms
powder dust. Dust from solid surface which is free from cracks. and or areas with exposed explosives or
propellants can be ignited from spark (iii) Maintain compatibility of flammable gas mixtures. Personnel shall
energy, making conductive floors and conductive floor and tabletop materials not wear static generating stockings
shoes necessary where such dust is with the energetic materials present. such as silk, wool, and synthetics; and
present. Air and dust mixtures of (4) Conductive footwear. Operators shall not use foot powders, which have
ammonium picrate, tetryl, tetrytol, and shall wear conductive shoes in areas a drying action which can increase
solid propellants are also sensitive to requiring conductive mats, floors, or resistance. Dirt and grit increase
initiation by ESD. Testing indicates runners. Personnel visiting such areas resistance of conductive shoes.
mixtures of air with vapors from many shall wear conductive shoes, ankle Personnel should avoid wearing
flammable liquids (e.g., ethyl ether, straps, or similar devices, one on each conductive shoes outdoors and shall
ethyl alcohol, ethyl acetate, acetone, and leg. Prominent markings should identify keep shoes clean.
gasoline) may ignite by ESD from the conductive shoes to help supervisors (v) Trained personnel shall test
human body. Therefore, contractors ensure personnel compliance. Personnel conductive floors and tabletops upon
shall equip areas where personnel might required to work on electrical installation and at least annually
contact these kinds of explosives or equipment in areas where conductive thereafter using test equipment
with conductive floors and tabletops, floors are installed shall not wear specifically designed for this purpose
except when hazard analysis indicates conductive shoes and shall not begin and shall keep records of all test results
adequate housekeeping, dust collection, work until operators remove all AE. for at least five years. Testing shall
ventilation, or solvent recovery methods (5) Testing conductive footwear, proceed only when the room or area is
eliminate the ignition hazard. floors, and tabletops. (i) Test criteria. free from exposed explosives and
(1) Unless hazard analyses indicate The maximum resistance of a body, plus flammable gas mixtures. The test
otherwise, conductive tabletops, floors, the resistance of the conductive shoes, procedure shall measure the resistance
and shoes shall also protect operations plus the resistance of the floor to the of the floor between an electrode
involving the following: ground system shall not exceed 1 attached to the ground system and an
(i) Unpackaged detonators and million ohms total. That is, if 500,000 electrode placed at any point on the
primers and electro-explosive devices. ohms is the maximum resistance floor or tabletop and also as measured
(ii) Electrically initiated items, such allowed from the floor to the ground between two electrodes placed 3 ft (1 m)
as rockets, with exposed circuit and system, then 500,000 ohms is the apart at any points on the floor or
(iii) Hazardous materials capable of maximum combined resistance allowed tabletop. Each electrode shall weigh 5 lb
initiation by ESD from the human body. for the person’s body plus the resistance (2.3 kg) and shall have a dry, flat,
(2) When a hazard remains localized, of the conductive shoes (i.e., 500,000 + circular contact area diameter of 2.5 in
the contractor may use conductive mats 500,000 does not exceed 1 million). The (64 mm). The contact area shall have a
or runners instead of conductive floors contractor can set the maximum surface of aluminum or tin foil which is
throughout an entire building or room. resistance limits for the floor to the 0.0005 in to 0.001 in (0.013 mm to 0.025
These mats and runners shall meet all ground system and for the combined mm) thick and is backed by a layer of
the specifications and test requirements resistance of a person’s body plus the rubber 0.25 in (6.4 mm) thick. The
that apply to conductive floors. When shoes, as long as the total resistance surface hardness shall measure between
justified by hazard analysis, contractors does not exceed 1 million ohms. 40 and 60 Shore A when measured by

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00011 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16048 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

a Shore Type A Durometer (see able to provide ample warning, signals accumulations and subsequent
American Society for Testing and a work stoppage until the problem has discharges. This technique involves pre-
Materials (ASTM) D–2240–68, Institute been located and corrective action operational checks and regular
of Electrical and Electronics Engineers taken. monitoring of the humidity levels
(IEEE) Standard 14 and NFPA Standard (6) Check relative humidity and throughout the day. Do not use
No. 99. Make both electrode-to-electrode temperature before starting operations humidification with metallic powders
and electrode-to-ground system and throughout the workday where such unless hazard analysis indicates the
measurements at five or more locations conditions are used to mitigate or powders are not susceptible to
in each room with at least two of the prevent safety problems (i.e., spontaneous ignition in air with 60
points in heavily trafficked areas. If the hydroscopicity or static control). percent relative humidity.
resistance measurement changes (7) Do not paint metal surfaces (2) Ionization is electrical
appreciably with time, record the subjected to rubbing or friction. If a neutralization and serves as an effective
resistance at the 5-second interval. To lubricant is necessary, use a method of removing static charges from
prevent biased measurements, locate the composition which allows the metal’s certain processes and operations.
electrodes for both the electrode-to- surface resistance to remain at or below Methods of application can be found in
electrode and electrode-to-ground 25 ohms. NFPA Standard 77.
measurements a minimum of 3 ft (1 m) (8) Work on or with low-energy (3) Contractors may use ionization or
away from an earth ground or other initiators only in areas equipped with humidification to augment their ESD
grounded items such as a door frame, conductive floors and table tops. control program but, may not use them
ordnance handling equipment, or any Exceptions may be made when the in lieu of conductive floors and
grounded item resting on a conductive initiators are in their original packaging, footwear (where required).
floor. (Note: The size of the floor or or are part of a finished metallic end
item affording them complete protection § 184.7 Manufacturing and processing
tabletop may make it impractical to
from electromagnetic or electrostatic propellants.
conduct five surface resistance
(electrode-to-electrode) or resistance-to- energy. (a) General. (1) These requirements
ground measurements and still remain 3 (9) Do not work in the vicinity of apply to propellant manufacturing and
ft (1 m) away from all grounded items. actual or potential electromagnetic or augment other requirements contained
In such cases, take enough electrostatic fields (e.g., radio in this part.
measurements to ensure adequate transmission, electrical storms, (2) The safety precautions for
testing of all parts of the conductive transformer stations, high voltage fabrication of propellants, propellant
surface and document the justification transmission lines, improperly loaded items, gun ammunition, and
for a reduced number of electrode-to- grounded electric circuitry, rotating rocket motors follow the generally
electrode or electrode-to-ground equipment, belts, etc.). Establish accepted principles used for many types
measurements in the grounding system adequate lightning protection and of explosives and energetic materials.
test plan.) Only trained personnel shall grounding and adequate resistances for Solid propellants can be divided into
operate and maintain test instruments. fixed sources of energy for locations general categories such as single,
(h) Handling low-energy initiators. with low-energy initiator operations. double, and triple base, castable
Supplement typical precautions, such as Shield these areas to afford protection composite, and modified double base
shielding and safety glasses, with the against local mobile radio transmission. composite. (e.g., castable composite
following measures, as appropriate, (10) Locate electrical equipment out propellant modified with explosive
when manufacturing, processing, using, of the range of an operator working with plasticizer such as nitroglycerin). Liquid
or testing low-energy initiators initiated a low-energy initiator. With soldering propellants include a wide range of
by 0.1 J of energy or less. irons, it may be advisable to ground and liquid fuels, liquid oxidizers and fuel-
(1) Electrically bond and ground all limit energy to levels below initiating oxidizer monopropellants.
metal parts of equipment. thresholds. (3) Although processing safety
(2) Ensure personnel wear clothing (11) When not part of an end item or considerations for finished propellant
which prevents generation of static end item subassembly, transport AE and loaded rocket motors are
electricity. Test conductive shoes with a initiators only when packed according similar, each propellant type has its
resistance meter before entering an area to the latest packing specifications for own characteristics for processing of
where low-energy initiators are being low-energy initiators. raw materials, intermediate
processed. (i) Electrical test equipment. Use the compositions, and final processing.
(3) When low-energy initiators are lowest possible power source for all Hazards data for intermediate and
being handled, ground personnel electrical and electronics test finished propellant can help to define
directly by wrist straps. The acceptable equipment. When possible, use batteries the requirements that ensure safety in
resistance reading, taken once daily in lieu of 110 Vac power sources. processing. Hazards data includes
when the operator is wearing the strap, During testing, do not use power initiation thresholds to such stimuli as
shall be between 250,000 and one sources capable of initiating the AE. impact, friction, heat, and electrostatic
million ohms when measured from When test specifications require using discharge for specific processes and
opposite hand to ground. Special electrical energy at or above the handling situations. In evaluating and
contact creams may be used to decrease initiating threshold level of explosive properly applying the guidelines of this
the resistance to the required value. devices, use test chambers or provide chapter, consider the response of the
(4) Periodically coat glass, acrylic, or shielding capable of containing all materials in terms of energy input
polycarbonate materials required for hazards and apply energy remotely. sensitivity and magnitude of energy
transparent shielding with an anti-static Provide safeguards against the release. Follow the general requirements
material to prevent buildup of static possibility of human error. for manufacturing and processing of
electricity, when static sensitivity is (j) Humidification and ionization. (1) pyrotechnics given in Chapter 8 for
indicated to be a hazard. Humidification which maintains safety precautions for ignition system
(5) The sounding of a static electricity relative humidity above 60 percent fabrication. (Note: An exception to this
alarm, installed with the setting best effectively prevents static electricity requirement is processing of a

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00012 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16049

propellant grain igniter the same as oxidizers dispersed in fuel matrix with are H/D 1.1, no testing would be needed
motor propellant until the grain is the binder normally being made of to adopt this classification.
mated with the initiator assembly.) plastic material. Nitrates and (ii) If testing shows that uncured
(4) In addition to generally accepted perchlorates are commonly used as propellant will detonate, the casting and
safety precautions for handling of oxidizers. Common binders include:
explosives and other energetic curing operations are HD 1.1 hazards.
hydroxyl terminated polybutadiene,
materials, the following paragraphs carboxyl terminated polybutadiene, (iii) If detonation tests show that the
provide general guidance pertinent to polybutadiene-acrylonitrile, cured propellant will detonate, all
the manufacturing of propellants, polyurethane, polybutadieneacrylic operations with cured or curing
propellant loaded items, gun acid, and polysulfides. This propellant propellant are HD 1.1 hazards.
ammunition and rocket motors. is typically cast into its final shape. (4) Make safety information for all
(b) Properties of propellants. (5) Composite modified double base materials used in the formulation
Knowledge of the properties and types propellants. Composite modified double
available as required. Train personnel
of propellants is critical to the base propellants contain a dispersed
establishment of proper hazard controls. on the hazards involved in propellant
phase of finely ground oxidizer and
Propellants present a wide range of usually powdered fuel additive. This process situations.
hazard characteristics even within the propellant is typically cast into its final (d) Q–D requirements. Operate new
various types due to variations in grain shape. manufacturing and support facilities for
size of ingredients and energy content of (6) Liquid propellants. Liquid processing of propellants and propellant
additives, both solid and liquid. As propellants include a wide range of loaded items to conform to the latest QD
described below, test data is essential liquid fuels, liquid oxidizers and fuel- requirements for the HD of the
for determining the chemical, physical, oxidizer monopropellants. (Note: Refer propellant in its in-process condition.
physiological and explosive properties to the DOD 6055.9–STD, 9.6 for more
and hazards of raw materials, information and requirements (e) Separation of operations and
intermediate compositions, processing associated with specific liquid buildings. (1) Perform propellant and
aids, and liquid or solid propellant, both propellants. rocket motor manufacturing and
uncured and cured. (c) In-process hazards. (1) During processing in special areas (i.e.,
(1) Single base propellants. Single scale up from research and development operating lines) whose boundaries are
base propellants have the principal of new propellants to an existing separated from all other areas outside
explosive ingredient of nitrocellulose. manufacturing process, determine the the line in accordance with applicable
Remaining ingredients include chemical, physical, physiological, QD criteria. Table 1 to § 184.7 provides
stabilizers as well as other additives. explosive properties, and hazards of raw remote control and personnel protection
The mixture is shaped into tubes, materials, intermediate compositions, requirements for certain propellant
perforated tubes, flakes, etc. by processing aids, and liquid or solid processing operations.
extrusion and cutting. propellant, both uncured and cured.
(2) Double base propellants. Double (2) Unless available from other (2) Generally treat sequential
base propellants contain nitrocellulose sources, conduct testing to determine operations on rocket motors as one
and nitroglycerine (or other liquid thermal stability, chemical process operation in one building.
nitrate ester) as the two main compatibility of ingredients, exothermic (3) When the hazard classification of
ingredients. Remaining ingredients reactions, and sensitivity to ignition or a propellant has not been established,
include stabilizers as well as other detonation from friction, impact, and classify the propellant during site and
additives. This propellant can be electrostatic discharge. Additionally, construction planning as the most
extruded/cut or cast into its final shape. deflagration-to-detonation and card gap hazardous class/division that might
(3) Triple base propellants. Triple test data can be valuable. Applicable possibly apply during manufacturing
base propellants contain three main tests are described in TB 700–2, and processing.
components: nitrocellulose, Explosives Hazard Classification
nitroglycerine (or other liquid nitric Procedures. (4) Locate safety shelters, lunchrooms,
acid ester), and nitroguanidine. This (3) Minimum testing may satisfy the convenience buildings, and private
propellant can be extruded, cut or cast classification requirements for several vehicle parking for personnel working
into its final shape. in-process operations. For example: in an operating building in accordance
(4) Composite propellants. Composite (i) If reliable data exist that indicate with applicable QD criteria.
propellants consist of finely divided that the propellant mixing operations

TABLE 1 TO § 184.7.—CONTROL AND PERSONNEL PROTECTION REQUIREMENTS FOR CERTAIN PROPELLANT PROCESSING
OPERATIONS
Operation Remote control Personnel protected 1

Blending and screening of ammonium perchlorate ....................................................... Mandatory .......................... Mandatory.


Blending, screening of nitramines and Mandatory perchlorates other than ammonium Mandatory 2 ........................ Mandatory.2
Grinding, and mechanized drying of perchlorates and nitramines ............................... Mandatory .......................... Mandatory.
Grinding, blending, screening, and mechanized drying of ammonium nitrates ............ Advisory .............................. Advisory.
Rotating blade propellant mixing ................................................................................... Mandatory .......................... Mandatory.4
Power-driven cutting, machining, sawing, planing, drilling, or other unconfined oper- Mandatory 3 ........................ Mandatory.3
ations in which rocket motors or propellant of Hazard Division 1.1 and 1.3 are in-
volved.2
Mandrel break away removal from cured propellant ..................................................... Mandatory 3 ........................ Mandatory.3
Pressing, extruding, pelletizing or blending ................................................................... Mandatory .......................... Mandatory.
Casting Propellants ........................................................................................................ Mandatory 3 ........................ Mandatory.3
1 Operating personnel shall be at K24 or in a control room that will limit overpressure to less than 2.3 psi.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00013 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16050 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

2 Attended screening of wet material may take place if shown acceptable by hazard analysis.
3 Attended operation permitted if shown to be acceptable by hazard analysis.
4 The attended operation may take place when a hazard analysis shows the MCE to only be fire hazard.

(f) Equipment and facilities. (1) contact between fixed and movable needed to ensure a safe and efficient
Except as provided for in other parts. Design mix bowl lift mechanisms workflow, when conducting operations
applicable documentation, follow the (i.e., elevators) to assure adequate blade- in an operating building. Short-term
mandatory requirements of this part for to-blade and blade-to-bowl clearances storage of larger quantities in an
the design, layout, and operation of during the complete operation cycle. operating building is permissible when
facilities and equipment for propellant (9) Provide positive controls to it is not in use for other operations.
operations. Where there is no guidance, physically block or stop bowl or mixer (2) Completed assemblies with or
govern operations by the results of head movement in case of drive without installed ignition system may
hazard tests and analyses (see § 184.12) mechanism malfunction. Assure be stored in operating buildings
performed and documented to address maintenance of blade-to-blade and provided there are no other operations
specific operations. As some propellants blade-to-bowl clearance at all times. in progress and quantity/distance
can be sensitive to initiation by static (10) Use rigid and strong mix blades complies with requirements.
electricity, consider bonding and and shaft to ensure minimum flex from (3) Production igniters may be stored
grounding of equipment, tooling, and viscosity of the mix and speed of the in designated areas within an assembly
rocket motor conductive components shaft. or disassembly facility.
along with other means of static (11) Use electrical components of all (4) Indoor storage is preferable for all
elimination and control. Use conductive mixers that meet the appropriate types of explosives and is mandatory for
work surfaces and floors or floor mats electrical classification or remotely bulk HE, solid propellants, and
for assembly of igniters and igniter locate them or shroud and purge them pyrotechnics. Give priority of existing
subassemblies. with inert gas. Design purged systems to indoor storage to AE requiring the most
(2) Use non-sparking and non-rusting provide automatic warning upon loss of protection from the weather (based on
materials, which are chemically gas pressure. the method of packing). Protect
compatible with the propellant material, (12) Equip mixer blade shafts with propellant and propellant materials
for equipment, tooling, and machinery seals or packing glands that prevent from overheating by exposure to direct
that will come in contact with migration of liquids or solvent vapors sunlight when in transit or on
propellant or propellant ingredients. into bearings. Avoid submerged temporary hold.
(3) Certain propellant operations bearings and packing glands. However, (5) Consider the propulsive
involve significant energy input that if used periodically test them for characteristics and the ignition
enhances the possibility of ignition. contamination and clean them. probability of AE (e.g., propellant
Examples are rolling mills, machining (13) Establish a program to detect loaded devices, rocket motors, assist
and drilling operations. In these significant changes in blade/shaft take-off units and missiles) during all
situations, conduct complete hazard position relative to mixer head. Check logistical phases in order to obtain as
analysis and evaluation prior to starting
clearances between mix blades and much safety as possible under the
the operation.
mixer bowls at regular intervals based circumstances. Because of the great
(4) Special requirements of this part
apply to heat-conditioning equipment. on operating time and experience to number of types and sizes of propellant
(5) Exposed radiant surfaces in the make sure the clearance is adequate. loaded devices and conditions of
form of S-shaped smooth pipe or fin- Maintain a record of such checks, mixer assembly encountered, only general
type radiators are easy to clean. Other blade adjustments, and any damage to safety guidance is provided in this part.
types of radiators are acceptable, but are the mixer blades and bowls. Thus, the contractor should make every
less desirable because of cleaning (14) Electrically bond and ground mix effort to prevent ignition of any units
difficulties. bowl, blades, and drive unit. being manufactured, assembled,
(6) When mechanical ventilating (15) Inspect blades and other moving disassembled, handled, stored,
equipment is used in operations parts of new mixers and replacement transported or deployed. Use approved
involving potential concentrations of parts for old mixers. Inspect (i.e., flight restraining devices (tie-downs) to
solvent vapors, dusts, and nitroester magnaflux or X-ray) for cracks, crevices, the maximum extent possible. When
vapors, do not locate the electric motor and other flaws. doubt exists as to whether a given AE
and motor controls directly in the (16) Interlock electric service to or configuration (state of assembly) is
potentially contaminated air stream. propellant mixers with fire protection propulsive or nonpropulsive, treat the
Provide the ventilation system with a system controls so that the mixer cannot AE as propulsive until pertinent
suitable means of collecting condensate. start when the fire protection system is technical information can be obtained.
(7) Design air conditioning and cure inoperative. (h) Ingredients processing. (1)
oven air-circulating equipment of the (17) Regularly check and maintain all Weighing, measuring, and handling raw
closed system type to prevent process equipment that applies energy materials. (i) Electrically ground scales
contaminated air from contacting the air to in-process propellant for wear and for weighing raw materials, where
motor and controls. Monitor misalignment. Keep a record of these needed, to properly protect the
recirculated air to ensure concentration checks and any maintenance performed operation. This grounding is especially
of vapors and dusts do not reach for the process equipment. important where flammable or
flammable (or explosive), or personnel (18) Control equipment performing combustible materials are involved.
threshold limits. Use dustproof and sequential operations on propellants (ii) Provide separate weight or
vaporproof electric motors and controls. (e.g., extrusion and cutting) to prevent measurement rooms, cubicles, or areas
Preferably use air mover blades that are interference. (dependent upon the quantity and
nonmetallic. (g) In-process quantities and storage. sensitivity of the materials handled)
(8) Rigidly fix and stabilize the (1) Allow only the quantity of provided. Separate oxidizer and
equipment during mixing to preclude propellant and loaded subassemblies metallic powder weighing from each

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00014 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16051

other and from other materials by cleaning and inspection shows it is free (ii) Establish compatibility of
physical barriers rather than distance. of any residual contamination. materials. Develop procedures that
(iii) It is important that containers, (4) Screening oxidizers. (i) Construct preclude the formation of highly
equipment, hand tools, scale pans, etc., screening equipment so it cannot sensitive compositions or hazardous
used for weighing processes do not mix subject oxidizer material to pinching, conditions during processing, such as,
with those weighing or measuring friction, or impact as a result of metal- dry AP and powdered metal mixtures.
oxidizers and fuels, particularly where to-metal contact. Keep rooms in which (iii) Preferably bond equipment,
distance rather than physical barriers screening units are operated thoroughly piping, and vessels used in fuel
separates these areas. Use positive clean to eliminate hazardous preparation to form a continuous
measures to ensure the complete accumulations of dust. electrical path with each other and to
separation of such equipment and tools. (ii) Electrically ground oxidizer building ground. When pouring metallic
(iv) Do not change the designated use screens and bond them to the receiving powder or flammable liquids from one
of space and equipment without a vessel. container to another, bond the
thorough cleaning and inspection to (5) Blending oxidizers. (i) If blending containers together prior to the transfer.
make sure that all traces of the previous of oxidizers generates gases, design and (iv) Minimize the formation and
material have been removed, if any install a suitable means of gas pressure accumulation of dust in all preparation
possibility exists that materials are relief into the blender. operations.
incompatible. (ii) Electrically bond the blender
(v) Use fume hoods, dust socks,
(2) Oxidizer Processing. Solid throughout.
(iii) Construct blending equipment so closed systems, and dust/fume vacuum
propellant oxidizing agents are
it cannot subject oxidizer material to exhaust hoses, as appropriate, to
perchlorates, nitrates, nitroesters, and
pinching, friction, or impact between prevent vapors and dust getting into the
nitramines used in solid rocket motor
metal-to-metal surfaces. operating areas.
propellants.
(i) Avoid contaminating an oxidizer (iv) When blending ammonium (8) Transfer operations. (i) Transfer
agent with any metal or chemical (fuel) perchlorate using powered mechanical finely divided powdered ingredients by
which may result in a more sensitive equipment, protect operating personnel. methods that control flow rate and
composition. Use remote controls for mechanical minimize electrostatic charge
(ii) Use closed systems as much as blending. generation.
possible for dust, humidity, and tramp (v) When using powered mechanical (ii) Before transferring flammable
material control. methods for blending HD 1.1 substances solvents, electrically bond the transfer
(iii) Use fire-retardant materials to (such as RDX or HMX), use remote and receiving vessels to eliminate
make flexible connections (socks) in controls and personnel protection (See electrostatic potential differences.
pipes or duct systems that convey Note 1 to Table 1 to § 184.7). (i) Mixing. (1) Secure hardware and
oxidizer materials and dust socks in (6) Grinding oxidizers. (i) When using associated equipment to prevent loose
collectors or hoppers. Only use impact type mills, provide sufficient items falling into mixers.
connection materials that are chemically clearance between stationary and (2) Pass liquids and powders to be
compatible with the oxidizers. moving parts to prevent metal-to-metal added to the mix vessels through a
(iv) Make the pipes and duct systems contact. Check clearances as often as screen or orifice with an opening(s) less
electrically continuous. Avoid threaded needed to ensure they are adequate. Air than the smallest clearance in the mixer.
joints and fittings in contact with purge mill bearings to prevent You may directly add smaller amounts
oxidizer. Preferably use quick clamp contamination. Do not use impact type of material, provided a positive means
neuter end pipe joints. grinders for HD 1.1 substances. exists to ensure the material does not
(v) Use static electricity control (ii) Pass oxidizer feed materials contain any foreign material.
measures to dissipate static charges to through a screen mesh with openings no (3) Use other means such as x-rays to
an acceptable level if transporting greater than the clearance between examine materials that you cannot
oxidizer by fluidization. hammer and plate. Use the smallest screen or that are opaque or not easily
(3) Oxidizer drying. (i) Establish the screen mesh size for ammonium nitrate inspected.
safe temperature for drying each that allows free flow of the prills. Use (4) When consistent with the process
material and do not exceed that magnetic separators if screening is not system and requirements, cover the
temperature at any point in the drying possible. mixer bowl after completing charging or
apparatus or drying room. (iii) Use only compatible lubricants in mixing to prevent the accidental
(ii) Use thermostatic controls to grinding equipment. introduction of foreign objects into the
prevent exceeding the maximum safe (iv) Install and use heat sensing
mixer and to prevent sunlight impinging
temperature in the drying process. devices for the bearing housing of
directly on the materials in the bowl.
Install and use redundant temperature grinding and conditioning equipment.
controls. (v) Determine the optimum cleaning (5) Use only non-sparking devices for
(iii) Do not use electrical heating cycle and method for grinding hand scrapping the sides and blades of
elements that may contact the oxidizer equipment and include them in SOP. mixers. Set up controls to prevent
or oxidizer dust. (vi) Provide grinding operations with accidental introduction of these and
(iv) Hold dust to a minimum in the wet dust collection systems, where other devices into the mixer.
drying process. Use a dust collection appropriate. (6) Account for all loose tools and
system if dusting can create a potential (vii) Thoroughly ground and bond equipment before starting or continuing
hazard. pneumatic grinding operations to mixing operations.
(v) Exercise care to prevent drying of provide for electrostatic charge (7) Do not allow loose objects such as
incompatible materials simultaneously dissipation. jewelry, pens and coins in the mixer
in the same drying process. Do not dry (7) Preparation of fuel compositions. operating area where accidental
oxidizers in an oven, drying room, etc., (i) Determine the sensitivity introduction into the mixers might
used for processing flammable or other characteristics of fuel compositions occur. Pocketless coveralls should be
incompatible materials until after prior to production mixing operations. used.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00015 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16052 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

(8) Provide direct and unobstructed (11) Pressurize and depressurize (iii) To facilitate removal of dust and
routes for personnel egress from mixer propellant cure operations remotely. chips, and to afford personnel
buildings or bays. (12) Physically and electrically protection. If there is a possibility that
(9) Do not attempt to fight propellant disconnect casting vessels from lifting a metal or other foreign object may be
fires. devices during cast operations. in the propellant, x-ray the motor or
(10) Preferably equip propellant (k) Extrusion processes. (1) Design grain prior to machining.
mixers, inside and outside of the mixing solventless extrusion presses and (6) Frequently remove propellant
vessel, with a high-speed deluge system. compression molding equipment to dust, chips and shavings from the work
(j) Casting and curing. (1) Personnel remove air from the propellant before area during machining and contouring.
may attend cast operations if you first compaction and extrusion begin. Assure
conduct a thorough safety review of the (7) Preferably position rocket motors
that procedures provide for checking in final assembly process to permit
operation is conducted. operation of the vacuum system and for
(2) Multiple or single production line ready access to all sides of the motor.
cleaning it of propellant residue and Keep aisles and exit doors clear and
type casting is permitted. However, condensed vapors such as those
when the survivability of the production unobstructed. Install quick release
generated from nitroglycerin hardware on all exit doors.
facility is critical or the risk to the volatilization.
program is significant, the PCO may (2) Check ramheads for alignment (8) Keep the number of items in the
require the contractor to provide with the press bore to preclude metal- final assembly building at the minimum
protection that prevents propagation of to-metal contact. Include flashing consistent with a safe and efficient
an incident from the casting operation removal in the process procedures. operation.
to adjacent bells or pits. (3) Provide interlocks to preclude (9) Grounding of propellant loaded
(3) Use only smooth cast piping press operation during loading or other assemblies in storage is optional, based
surfaces in contact with propellant. Use attended operations. on a case-by-case review.
tooling free of cracks, pits crevices, and (l) Propellant loaded AE. (1) When (10) If the process requires removing
weld slag for propellant casting and performing operations on cured an igniter-shorting clip, keep the igniter
curing operations. Avoid threaded joints propellant contained in pressure vessels shorted until immediately before
as much as possible, especially at or rocket motor cases and there may be insertion. Minimize the time that the
unions requiring disassembly for
a risk of ignition due to energy inputs igniter remains unshorted.
process operation or cleaning.
(e.g., electrical check of pyrotechnic (11) Provide means for controlled
(4) Do not design or use cast tooling
and mandrels that permit metal-to-metal devices). In such cases, secure the unit dissipation of static electrical charges
friction or impact sites. in a fixture capable of withstanding 2.5 during igniter insertion.
(5) Design and use propellant flow times the rated thrust of the assembly. (12) Conduct operations that involve
valves that prevent propellant pinching (2) Use remote control to apply electrical continuity checking/testing of
or compression between two metal mechanical force to ‘‘breakaway’’ the ignition systems installed in rocket
surfaces. mandrel or other tooling embedded in motors according to thoroughly
(6) Design and use pressurized casting propellant. However, see Table 1 to reviewed and approved procedures.
vessels capable of withstanding at least § 184.7 for exceptions. Conduct these checks by remote control
twice the maximum allowable working (3) Avoid moving loaded rocket with the motor mounted in a test stand
pressure. motors with cores in place. If loaded designed to withstand 2.5 times the
(7) Secure lids to pressurized casting motors containing cores must be moved, thrust of the motor.
vessels so that they will withstand the however, support the core and motor
case by or suspended from a common (m) Disassembly. (1) As much as
rated pressures of the vessels. possible, avoid metal-to-metal
(8) Do not exceed the working line source or in some manner locked or tied
together to prevent independent movement and trapping of explosive
pressure of casting vessels. Install a
movement of either. substance in process equipment or
relief valve downstream of the regulator
(4) When determining the safest tooling that require disassembly in a
on pressure lines.
(9) Equip each vessel with a blowout method to use, evaluate and consider process operation.
disk (burst diaphragm) designed to blow the hazard characteristics of individual (2) Use clean, external clamp fittings
out at less than 120% of the vessel’s propellants you will cut, machine, or on pipe assemblies for propellant
maximum allowable working pressure. contour. transfer.
Allow for the release of the potential (5) Design propellant machining (3) Before starting non-routine
rapid rise of pressure in the vessel equipment: disassembly of equipment or tooling
should the propellant ignite. (i) To prevent contact of cutting tools (such as that necessary for equipment
(10) When curing or casting or blades with motor cases and other repair or for securing the process),
propellant under pressure, provide metal objects. evaluate potential hazards of trapped
emergency pressure relief. (ii) To minimize generation of heat. material or process residuals.

TABLE 1–1 TO § 184.7.—CONTROL AND PERSONNEL PROTECTION REQUIREMENTS FOR CERTAIN PROPELLANT
PROCESSING OPERATIONS
Operation Remote controls Personnel protected 1

Blending and screening of ammonium perchlorate ....................................................... Mandatory .......................... Mandatory.


Blending, screening of nitramines and perchlorates other than ammonium ................ Mandatory 2 ........................ Mandatory.2
Grinding, and mechanized drying of perchlorates and nitramines ............................... Mandatory .......................... Mandatory.
Grinding, blending, screening, and mechanized drying of ammonium nitrates ............ Advisory .............................. Advisory.
Rotating blade propellant mixing ................................................................................... Mandatory .......................... Mandatory.4

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00016 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16053

TABLE 1–1 TO § 184.7.—CONTROL AND PERSONNEL PROTECTION REQUIREMENTS FOR CERTAIN PROPELLANT
PROCESSING OPERATIONS—Continued
Operation Remote controls Personnel protected 1

Power-driven cutting, machining, sawing, planing, drilling, or other unconfined oper- Mandatory 3 ........................ Mandatory.3
ations in which rocket motors or propellant of Hazard Division 1.1 and 1.3 are in-
volved 2.
Mandrel break away removal from cured propellant ..................................................... Mandatory 3 ........................ Mandatory.3
Pressing, extruding, pelletizing or blending ................................................................... Mandatory .......................... Mandatory.
Casting propellants. ....................................................................................................... Mandatory 3 ........................ Mandatory.3
1 Operatingpersonnel shall be at K24 or in a control room that will limit overpressure to less than 2.3 psi.
2 Attendedscreening of wet material may take place if shown acceptable by hazard analysis.
3 Attended operation permitted if shown to be acceptable by hazard analysis.
4 The attended operation may take place when a hazard analysis shows the maximum credible event (MCE) to only be fire hazard. For guid-
ance on ENERGETIC (PROPELLANT) LIQUIDS, please refer to DoD 6055.9, Section 9.5.

§ 184.8 Safety requirements for liberate oxygen gas, or substances which and prevent contamination which may
manufacturing and processing act as oxidizers with active metal fuels. result in a reaction.
pyrotechnics. Typical inorganic oxidizers are nitrates, (3) Binders. Homogeneity of the
(a) General. (1) Pyrotechnics, as well chlorates, perchlorates, oxides, mixtures governs the effectiveness of
as propellants and explosives, are chromates, and dichromates. Fluorine pyrotechnic compositions. Some
chemical mixtures which release large and chlorine, as in hexachloroethane pyrotechnics (e.g., black powder) are
amounts of energy. The amount of and Teflon (brand of fluorine containing self-bound by the manufacturing
energy released, the speed of reaction, compound) are examples of organic process to maintain the charcoal, sulfur,
and the form of the output energy are compounds used as oxidizers. All and potassium nitrate in the correct,
the characteristics that distinguish oxidizers, if not well controlled, tend to proportionate, intimate mixture needed.
between pyrotechnics and other forms increase the risk of undesired reactions, Other mixtures, because of differences
of high-energy (HE) mixtures, and particularly in the presence of organic in particle size or weight of ingredients,
between types of pyrotechnics. The materials (including wood). Potassium require the use of a binder to retain the
safety precautions for manufacturing chlorate compositions are particularly homogeneous blend. Other binders
and processing pyrotechnics parallel susceptible to accidental ignition. include lacquers, epoxies, and a variety
those of many types of explosives and Impurities in process materials, or of polymers activated by heat or
propellants. However, incident introduced by poor process control (e.g., solvents. Some solvents are similar in
mitigation techniques must recognize oils, lubricants) can readily increase the composition to fuels, and the binder
the unique characteristics of the sensitivity of mixtures or result in may also be a fuel or burn rate modifier.
particular mixtures, and not rely on ignition. Some oxidizers with trace Some binders are flammable, others
techniques appropriate to other types of impurities, or by themselves (i.e., require the use of a highly flammable
explosive substances (e.g., HE). Rates of ammonium perchlorate (AP)), can solvent, and thus the ignition
reaction of pyrotechnic mixtures vary detonate when subjected to severe characteristics of these materials are
greatly, from mixtures with very low stimuli such as an adjacent explosion or important risk factors.
rates of reaction to rates equivalent to thermal energy. Safety requires absolute (4) Types of pyrotechnic
high explosives. Energy output also control of oxidizers to prevent compositions. Pyrotechnic compositions
varies from very low to very great. contamination, uncontrolled moisture are usually grouped by the function of
Process variables, such as ingredient absorption (many are hydroscopic), fires the end item. There is no universal
particle size, can affect reaction rate and or explosions from accidental mixing single grouping, but typical major
output to the extent that a change in with fuels. groupings are: heat and delay
process variables can negate protective (2) Fuels. Fuels react with the compositions (e.g., ignition, delay, heat,
measures. Complicating safety in oxidizers to produce heat and an and propellant), color and light
pyrotechnics operations is the variety of oxidized product. It is the proper compositions, smoke (e.g., obscuring
highly flammable solvents often used as pairing of the fuel with an appropriate and signal smokes, noise). The range of
processing aides. oxidizer that determines the reaction sensitivity to initiation and the rate/
(2) Pyrotechnics are mixtures of fuels characteristics, and the use for the amount of output energy varies greatly
and oxidizers, typically held together by mixtures. Metals, such as magnesium or both within and between groups.
binders. Pyrotechnics display many aluminum, create high heat or light (i) Heat and delay compositions.
different characteristics, because they output. Fuels include an almost Pyrotechnic fuzes, electric matches, first
are formulated for different purposes. unlimited variety of organic (sugars and fires, primers, igniters, delay
General categories of pyrotechnics are: red gum) and a more limited variety of compositions are all members of this
initiators (igniters); illuminants; smokes. inorganic materials (e.g., sulfur boron, group. The end products must function
gas generators; sound generators; heat phosphorus, and sulfides). Although with very little stimulus, and thus the
producers; and timing compositions. generally more stable than oxidizers, mixtures, as well as individual
Each has its own characteristics and fuels also have unique characteristics ingredients, are sensitive to initiation.
attendant processing requirements. that contribute to risk. These include First fire, igniter and primer mixtures
(b) Properties of pyrotechnic materials the liberation of hydrogen from are generally the most sensitive to
and mixtures. Knowledge of the various magnesium and aluminum powders initiation stimuli (i.e., heat, friction,
pyrotechnic properties is critical to the which become wetted. Again, storage impact, static electricity). (Note: Primer
establishment of proper hazard controls. and handling of fuels requires tight mixes containing initiating explosives
(1) Oxidizers. Oxidizers are oxygen process controls which respect the such as lead azide or lead styphnate are
rich substances which decompose to characteristics of the specific materials properly classed as explosives.) These

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00017 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16054 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

mixtures often use black powder or likelihood of accidental initiations, but temperature or extended heating. Use
potassium chlorate/metal combinations also to minimize the effects of a mishap. the minimum temperature necessary for
or potassium chlorate/phosphorous (1) Do not allow ingredient or drying component and pyrotechnic
mixtures. This group also contains composition dusts to accumulate, materials. Dust and residue control is
mixtures with high heat outputs for whether on the exterior work surfaces or very important in drying operations, as
such purposes as document destroyers the interior of process equipment and elevated temperatures frequently results
and welding. These high heat producers ventilation systems. (Note: Accident in increased sensitivity of materials. The
are generally metallic fuels and metallic investigations frequently identify dust requirements for drying apparatus are
oxidizers, as in the iron oxide/ buildups as the source of initiation described in § 184.8.
aluminum powder formulations for when items are dropped on, or scraped (7) Mixing and blending. Mixing,
Thermite. Black powder, when used to across them.) Dust accumulations also blending, and cleanup of pyrotechnic
launch or expel items is a propellant provide a propagation path, which can compositions from equipment apparatus
and is included in this group. follow from initiation to a significant require attention because of the high
(ii) Color or light producing source of material, causing an accident. potential for mishaps during these
compositions. There are a wide variety (2) Similarly, where flammable operations. As compositions vary, no
of mixes and compositions which solvents are part of the process, positive single type of mixer or blender can be
produce light, color, or both. Illuminant vapor control is mandatory to prevent the exclusively approved equipment for
candles, photoflash, decoy flares all are initiation of a solvent vapor cloud, pyrotechnic mixing and blending
part of this very broad category. Many which may be injurious in itself, or may operations.
of the compositions, notably the be the propagation path which ignites a (i) Select the mixing equipment and
photoflash and decoy flare mixture. Just as dusts in ventilation methods appropriate for each
compositions, are characterized by very systems may provide a propagation path composition. Hazard analysis or test
rapid reactions, and extreme for an event, solvent vapors in shall determine the type of mixer or
temperature outputs. Both have resulted ventilation systems, hallways, conduits, blender and batch size. Devices using a
or pipes may also provide a propagation tumbling action eliminate many of the
in fatal accidents. Metallic fuels are
path. problems associated with rotating blade
characteristic of the high light (visible,
(3) As many pyrotechnic ingredients, mixers, plows and scrapers. Rotating
IR) output mixtures. Output mixtures or the solvents used in their blade type mixers create points where
temperatures exceeding 2000 °F (1093 production are highly susceptible to frictional heat may develop or where
°C) characterize many of the items in initiation by static electricity, static accidentally introduced foreign material
this category. Accidental initiation of control systems (i.e., conductive floors/ can create hot spots through friction or
large mix batches of some compositions mats, shoes, wrist straps, grounding of crushing of the composition. Equip
may have a significant pressurization equipment, etc.) are mandatory where enclosed mixers and blenders with
effect in addition to the heat, with hazard analysis indicates a need for pressure relief, to preclude a transition
resultant structural damage. static control. from burning to detonation. Minimize
(iii) Smoke and noise producing (4) For all pyrotechnic operations, a personnel exposure when charging and
compositions. Obscurants, colored documented hazard analysis and risk emptying mixers and blenders. Unless
markers, weapons simulators and assessment is mandatory to validate the hazard analysis indicates otherwise,
weapons effects simulators comprise layout of operations, selection of charge, operate and empty mixers and
this category. Smoke compositions are materials and equipment, and process blenders remotely. Use appropriate
characteristically slow burning in control parameters. See § 184.11. interlocks, clutch brakes, and similar
finished form, but must burn at a (5) Weighing raw materials. Positive devices to preclude personnel exposure
temperature high enough to vaporize the means of separation of fuels and during mixer or blender operation, and
dye compound (usually organic). oxidizers is mandatory. The scale of the to preclude the movement of mixer or
Chlorates are often the oxidizer in operation will dictate whether separate blender parts during periods when
colored smoke mixes. ‘‘Flash-bang rooms, cubicles, areas, or other means operators are present.
compositions’’ used in weapons for separation are required. It is (ii) Mixing and blending operations
simulators and weapons effects important that equipment (e.g., often present a high risk of explosion.
simulators are actually explosives in containers, hand tools, scale pans, etc.) Facility construction and procedural
most instances, and will detonate with used for weighing fuels or oxidizers are controls, guided by hazard analysis or
adequate stimulus in unconfined bulk not interchanged or shared among test, must reflect this risk. Prevention of
form. ‘‘Flash-bang’’ compositions, incompatible operations, unless propagation, protection of production
particularly in display or commercial thoroughly cleaned between fuel and capability and personnel require
fireworks, but also in military items, oxidizer use, particularly where separation and isolation of these
were the cause of many injury- distance rather than physical barriers operations. At least one wall or
producing accidents. Similarly, separates these areas. A hazard analysis equivalent panel area in each bay shall
‘‘whistle’’ compositions are very shall determine appropriate personnel be frangible to provide pressure relief in
sensitive to ignition and can detonate. protective equipment for personnel case of an incident. Preclude personnel
(c) Process requirements. Pyrotechnic weighing or handling exposed oxidizers exposure to pressure relief areas.
operations, because of the sensitive or fuels. (iii) Flammable solvents used in
nature of the ingredients and (6) Drying materials. Drying materials mixing operations present a potential
compositions, the dangerous effects of may result in the generation of fire or explosion vapor hazard. When
contamination, including cross flammable vapors or dust which have flammable solvents are used, install
contamination of oxidizers and fuels, the potential to create an explosive ventilation equipment, interlocked to
and the amount of open or exposed atmosphere. The dust settling out of the the mixers. Design interlocks to
ingredients and mixtures, require atmosphere may increase in sensitivity. preclude mixer operation without
stringent housekeeping and cleanliness. Operational hazard analysis must ventilation. Ventilation systems must
Materials control and cleanliness are address these possibilities and the operate in the presence of solvent
mandatory not only to reduce the possibility of initiation by over- vapors. Vapor sensors provide warning

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00018 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16055

of flammable vapor levels approaching operate without personnel and facility pyrotechnics, including those in
the lower explosive limit. Design protective features. Omit protective components to the smallest quantity
ventilation systems to prevent features only when documented hazard necessary for safe and efficient
propagation of an incident from one bay analysis supports direct personnel operations.
to others served by the same system. involvement. Use substantial dividing (10) Granulation, grinding and
(iv) Prohibit direct viewing of blender walls, barricades, operational shields or screening. Operations which reduce
or mixer operations. Use remote means intraline distance (ILD) to protect particle size are particularly hazardous
such as television or mirrors, or personnel from pressing, extruding or due to the energy imparted to a material
interpose transparent shields. pelleting operations. (Note: ILD alone with an increasing surface area,
(v) Prohibit part mixing, blending or does not provide adequate personnel including dusts. The materials are often
scraping of pyrotechnic composition. protection. For personnel protection by in their most sensitive form during these
(vi) The following are the minimum separation alone, use public traffic route operations.
criteria for rotating-blade mixing distance (PTRD).) When it is necessary (i) Remove foreign materials using
operations: to repair, adjust, or otherwise clear a mechanical or magnetic screening from
(A) Assure the stability of mixers, and jam on a press or extruder, remove the compositions reduced in particle size
platforms, to prevent distortion during pyrotechnic material from the hopper both before and after the size reduction
operation and resultant contact between and the bay or press room before making operation.
the bowl and blade. such repairs or adjustments. Only those (ii) Provide positive personnel
(B) Provide positive controls to adjustments of ram speed or conveyor protection for the operation of ball
physically block or stop bowl or blender speed routinely controlled by the mills, hammer mills, granulators, or
head movement in case of malfunction operator may proceed with material in screeners. It is highly desirable to fill
to assure maintenance of clearances the bay. Under no circumstances shall and discharge grinding, granulating, and
between mixer bowl and blades. repair or adjustment require the use of screening equipment remotely. Hazard
(C) Mixer blades and shaft shall be tools with pyrotechnic material in the analysis may dictate that the cleaning of
rigid and structurally strong to ensure bay. such devices also requires operator
minimum flex from weight of the mix (ii) Limit the quantity of composition protection.
and speed of the shaft. at the pressing location behind the (iii) Bond and ground working
(D) All mixer electrical components barricade to that required for the surfaces, containers, and hand tools.
shall meet the appropriate NFPA components undergoing the pressing (11) Transportation. Transport
Standard No. 70 electrical classification. operation. Separate all other quantities pyrotechnic compositions in closed
(E) The mixer blade shaft shall in the bay to prevent propagation from containers only. Fabricate individual
include adequate and compatible seals an event in the press. The quantity of containers and the transport vehicle
or packing glands to prevent migration composition in the remainder of the (e.g., handcart, hand truck, etc.) of the
of mix or solvent vapor into bearings. building at any one time shall not lightest materials compatible with the
Submerged bearings and packing glands exceed the minimum required for a safe, composition and having the requisite
should be avoided. If used, periodically efficient operation. strength. This minimizes fragment
test packing glands and bearings for (iii) Each individual press, extruder, generation if an incident occurs. ‘‘Dead
contamination and clean them as or loading device shall be located in a man’’ brakes are often desirable on
necessary. separate building, room, or cubicle, and transport vehicles. Transport vehicles
(F) Establish a maintenance program be designed to limit an incident to that require protection from the weather
to monitor wear in the mixer blade shaft area and protect operators. Tests or a when loading or unloading. Provide
and bearings to avoid excess play. hazard analysis may be used to racks or other support, suited to the size
Maintain a record of such checks, mixer demonstrate that multiple operations in and shape of composition containers, to
blade adjustments, and any damage to a bay or cubicle do not jeopardize stabilize them in transport.
the mixer blades and bowls. Perform personnel or the facility. Due to the (12) Rebowling. These operations
operational checks of blade/plow and difficulty in positively excluding transfer materials, typically sensitive
bowl clearances prior to the propagation to feed hoppers or similar and in small quantities, from one
introduction of materials. feeds to the equipment, designs for container to another, to recover remains
(G) Procedures must exclude dry pressure relief in case of an incident of small quantities of materials, or to
mixing. Starting the mix with dry must include the quantities in such subdivide large masses for processing.
pockets of materials has been the cause hoppers when present. Rebowling of dry pyrotechnics
of several serious accidents. Unless (9) Assembly operations. Cleanliness compositions with characteristics
adequate amounts of solvent are added and isolation are important safety similar to initiating explosives require
in an appropriate sequence with dry requirements for assembly operations. operational shields to protect operators.
ingredients, pockets of dry mix may Keep individual assembly operations (13) Machining of pyrotechnic
remain after solvent addition. separate from other assembly, mixing, material. (i) Conduct machining of
(H) Interlock power to mixers with blending, and consolidation operations. pyrotechnic materials remotely.
fire protection system controls so that Use separate cubicles, bays, or buildings (ii) Drilling and facing operations
the mixer cannot start when the fire as dictated by hazard analysis. To must be done to minimize friction and
protection system is inoperative. reduce the possibility of accidental heat build-up. Hazard analysis should
(I) Maintain grounding during initiation, keep pyrotechnic address factors including feed rate, type
charging or discharging of mixes. compositions (including fuels and of composition and tooling.
(J) Maintain torque limits or amperage oxidizers) in closed or covered (iii) Perform hand trimming and
overload protection. containers at all times, except during cutting of pyrotechnic candles only
(K) Maintain appropriate solvent traps physical processing (i.e., requiring when supported by results of a hazard
for vacuum mixing. access to the material). This is analysis specific to that composition
(8) Pressing, extruding, and pelleting. especially important when materials are and candle configuration.
(i) Few pressing, extruding, or pelleting accumulating or in transit between (iv) Sawing operations require
operations are sufficiently safe to operations. Limit quantities of particular care to prevent work from

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00019 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16056 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

plunging into the saw blade, and to (g) Personal protective equipment. (1) basis. However, all rework and reuse
ensure chip removal from saw teeth Engineering controls remain the primary concepts require careful analysis to
before subsequent cutting passes. and preferred means of providing assure safety. Manage all unused
Plunging can occur when thin sections personnel protection. Unattended materials in accordance with local, State
are force fed into coarse pitch saw operations, remote controls, substitution and Federal requirement.
blades. To prevent this, the work feed of less hazardous materials, and reduced (i) Fire protection. When compatible
rate shall be controlled. Chip quantities are all more effective than with process materials, use deluge
accumulation in the saw teeth is a personal protective equipment or systems for the protection of mixing and
function of the material being sawed, apparel. Personal protective equipment blending operations, screening,
rate of feed, blade speed, tooth design, shall not be relied upon as the primary granulation, drying, and pressing or
and flushing arrangement. means of operator protection. extrusion operations. Select the
(d) Spill control. Spills of pyrotechnic Operational shields and high-speed response time of the deluge system to
composition and energetic ingredients deluge systems may offer supplemental minimize the damage to process
pose potential hazards. Notify the protection. Operators must use only the equipment and facilities. Hazard
responsible supervisor before any action protective equipment and apparel analysis of the operation may dictate
to clean or contain the spills. SOP for prescribed by the SOP, and that apparel other applications.
pyrotechnic operations shall cover spill or equipment must be that prescribed by
cleanup, either as part of the various § 184.9 Storage of ammunition and
hazard analysis.
operations detailed or as a separate explosives.
(2) The minimum protective apparel
procedure. The procedures shall specify for personnel exposed to open (a) General. A properly sited storage
which actions are to be taken by whom containers of pyrotechnic or energetic area is mandatory for AE. Earth-covered
and in what order. The procedures shall raw materials shall consist of the magazines (ECM) offer the greatest
also address recovery of the spilled following: protection for the stored AE, and
material and decontamination of the (i) Cotton socks. provide some mitigation of fragments
area. (ii) Conductive-soled safety shoes. and over pressures from internal
(e) Management of pyrotechnic scrap (iii) Flame-retardant coveralls, and explosions. Such magazines are
and rejects. (1) At regular intervals, (iv) Hair coverings. preferred for the storage of all AE.
remove all pyrotechnic reject materials (3) All employees exposed to (b) Magazine operational regulations.
and scraps from all operating areas. hazardous quantities of pyrotechnic (1) Do not store unpackaged AE and
Segregate such materials by type and compositions shall wear: ammunition components, packing
compatibility, and keep it separate from (i) Aluminized, thermally protective materials, conveyors, skids, empty
common wastes. Use positive suit with hood and faceplate. boxes, or other such items in magazines
identification systems for containers of (ii) Aluminized, thermally protective containing AE. Limited dunnage lumber
these materials. Place filled containers trousers. and may be stored in the magazines, if it
at designated collection points. (iii) Aluminized, thermally protective does not block exits or aisles.
(2) To prevent undesired reactions, gloves or equivalent. (2) All AE containers shall be marked
use special care to preclude the mixing (Note: The definition of hazardous with a DoD hazard classification/
of water with powdered or finely quantities will depend on the division, storage compatibility group
granulated metals. Plastic liners for composition’s energy output and and item nomenclature.
waste containers facilitate cleaning. sensitivity (as determined by hazard (3) While crews are working inside
Liners should be conductive when analysis or tests) and the nature of the magazines, keep doors unlocked to
contents are subject to initiation by operation.) permit rapid egress.
static electrical discharge. (4) Required levels of protective (4) Do not store flammable liquids in
(f) Cleaning of pyrotechnic processing apparel shall be specified in appropriate magazines containing AE, except as the
equipment. (1) Since pyrotechnic SOP steps. chemical filler of ammunition, or as a
materials are sensitive to friction, (5) When the protective clothing prepackaged storable liquid propellant.
impact, or static discharge, cleaning described in paragraphs (g)(2) and (g)(3) (c) Stacking. (1) Store AE in original
equipment contaminated with of this section is required, the design shipping containers or equivalent.
pyrotechnic materials poses hazards. and wearing shall ensure no exposure of When stacking, group and identify AE
Because personnel are near the any area of the body. Use appropriate according to lots, if practicable.
equipment being cleaned, risks may seals or joints to preclude flame (2) Use dunnage to provide
exceed those of processing. Therefore, intrusion where apparel items overlap ventilation to all parts of the stack.
cleaning shall receive the same planning or join. Give particular attention to (3) Maintain aisles between each stack
and SOP coverage as production. possible gaps in coverage provided by to allow inspection, inventory, and
(2) Cleaning procedures must satisfy the hood in order to prevent flame or removal for shipment or surveillance
environmental and safety concerns. The hot gas impingement on the face, head, tests. Block storage configuration is
use of flammable solvent solutions for or neck. Protection of the employee’s permitted, provided ventilation of
flushing may require remote control. throat and lungs may require use of a stacks exists. Maintain unobstructed
Minimize the quantity of solvents used. self-contained breathing apparatus or aisles to permit rapid egress.
Control possible run-off from cleaning supplied-air respirator from the effects (4) Avoid more than one light
operations to preclude the spread of of a fireball. (partially filled) box or pallet per lot in
contamination. (h) Reworking pyrotechnic storage. Stack light units to be readily
(3) Select personal protective components. (1) Perform all repair, visible and immediately accessible.
equipment based on hazard analysis and reassembly, or similar operations on Conspicuously mark incomplete boxes
test data. Protective equipment must loaded pyrotechnic compositions in a to identify contents and quantities.
withstand the maximum credible event separate bay used only for that purpose. (d) Unpackaged AE items and
(MCE) when personnel perform cleaning (2) Reworking and reusing damaged containers. (1) When
in the vicinity of equipment and pyrotechnic material is desirable from necessary, store unpackaged AE items in
contamination. both an economic and environmental separate magazines.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00020 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16057

(2) Do not store damaged containers of in storage, the greater the likelihood that (see paragraph (i) of this section).
AE in a magazine with serviceable stocks of AE for issue or use will Contractor officials are responsible for
containers of AE. Repair such containers deteriorate. Older unstable AE material informing the firefighters of AE hazards.
or transfer the contents to new or should be tracked, identified and (c) Smoking. Smoking may take place
serviceable containers. Close and prioritized in the contractor inventory only in safe, specifically designated and
securely fasten covers on containers of management programs. posted ‘‘smoking locations.’’ Personnel
AE allowed in magazines. Close (2) Dispose of unstable AE stock shall not wear clothing contaminated
containers that have been opened before material in accordance with the with explosives or other dangerous
storing them again. Keep stored procedures and requirements of material in smoking locations.
containers free from loose dust and grit. § 184.15, Collection and Destruction (d) Hot work permits. A written
(3) Do not permit loose powder, Requirements for AE. Disposition of permit shall be required for the
grains, powder dust, or particles of unserviceable AE will be under local temporary use of heat-producing
explosive substances from broken AE or procedures based on the latest available equipment or devices when explosives
explosive substance containers in technical data. Unstable AE includes or highly flammable materials are
magazines. In addition, clean up any substances with totally depleted involved.
spilled explosive substance as soon as stabilizer, misfired ordnance, explosive
devices rendered safe by explosive (e) Portable fire extinguishers. Hand
possible and suspend all other work in extinguishers within buildings can
the magazine until accomplished. (Note: ordnance disposal and any similar
items. Unstable AE material is extinguish fires before major damage is
Manage explosive residue as a waste in done. Portable equipment may prove
accordance with § 184.15.) incompatible with all other AE material
in storage. When available store similarly valuable outside aboveground
(e) Maintenance and repairs to magazines (AGM) and other buildings
magazines. Perform and document a different types of unstable AE material
in separate magazines. with AE. Portable fire extinguishers will
hazard analysis, and implement the be maintained in accordance with NFPA
recommendations resulting to support (3) Treat AE with unknown stability
as unstable. Examples of AE to treat as Standard No. 10.
the plans for maintenance and repairs of
unstable include non-stock material, (f) Fire hazard identification system.
magazines containing AE.
(f) Open storage (outdoors). Do not dropped or damaged material, material (1) The contractor shall establish a fire
store AE outdoors. in substandard packaging, unidentified hazard identification system. This
(g) Storage of bulk initiating material and material not receipt system shall assess the relative dangers,
explosives. Bulk initiating explosives inspected. up to the most hazardous material
must neither be stored dry nor exposed stored. The system must include
§ 184.10 Fire protection. placards on AE buildings.
to the direct rays of the sun. Containers (a) General. This section provides:
of ample size to hold the double bag of (2) One such system is the DoD Fire
(1) General requirements for Identification System, which consists of
explosives are used for normal storage. developing and implementing AE fire
Types of AE range from highly sensitive, six fire divisions (1–6) which
protection and prevention programs, correspond to Hazard Division (HD) 1.1
bulk explosive substances (e.g., and
pyrotechnics, propellants and through HD 1.6. Fire Division 1
(2) Standard fire fighting hazard
explosives) to less sensitive, metal-cased indicates the greatest hazard. The
identification measures to ensure a
AE (e.g., bombs, torpedoes and artillery hazard decreases with ascending fire
minimum practicable risk in fighting
projectiles). For appropriate guidance, division numbers from 1 to 4. Fire
fires involving AE.
refer to DoD 6055.9–STD or industry Divisions 5 and 6 refer to explosion
(b) Fire plan. (1) A written fire plan
standards for specific storage hazards from less sensitive substances
shall be prepared which itemizes the
requirements applicable to the various and extremely insensitive articles.
emergency functions of each department
types of AE. or outside agency and indicates (3) Fire division symbols.
(h) Hazards of long-term storage. (1) responsible individuals and alternates. (i) The six fire divisions are indicated
AE may deteriorate in storage. The (2) When the contractor has an by four distinctive symbols (see Table 1
method of packaging, extremes of internal fire department or brigade, to § 184.10 and Figure 1 to § 184.10) in
temperature and humidity during plant officials have the responsibility for order to be visually recognized by the
storage, the length of time the AE is firefighting procedures, training of firefighting personnel from a distance.
stored, the nature of the deterioration, firefighting personnel, the use and The number is shown on each symbol
and the explosive substance maintenance of firefighting equipment indicating the type of AE present.
compositions used are factors in the rate and vehicles, the provision of water Reflecting or luminous symbols should
and criticality of the deterioration. Any supply and alarm systems and first aid be used. For application on doors or
deterioration that decreases the stability measures required in firefighting. lockers inside buildings, half-sized
of the AE increases the risk of auto- (3) Firefighting agreements. Voluntary symbols may be used.
ignition or a handling mishap due to and mutual agreements with local (ii) The symbols are orange and each
friction, impact or electrostatic municipalities or industrial centers number identifying the fire division is
discharge. The longer that AE remains shall include AE firefighting guidelines black.

TABLE 1 TO § 184.10—FIRE DIVISION MARKINGS


Fire Hazard involved Shape
division

1 .............................. Mass detonation .......................................................................................................................... Octagon.


2 .............................. Explosion with fragment hazard .................................................................................................. Cross.
3 .............................. Mass fire ...................................................................................................................................... Inverted triangle.
4 .............................. Moderate fire ............................................................................................................................... Diamond.
5 .............................. Mass Explosion (blasting agents) ............................................................................................... Octagon.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00021 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16058 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

TABLE 1 TO § 184.10—FIRE DIVISION MARKINGS—Continued


Fire Hazard involved Shape
division

6 .............................. Nonmass explosion (EIDS article) .............................................................................................. Cross.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00022 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16059

(g) NFPA Standard no. 704 standard and understood system of marking hazard symbols. The system identifies
system for the identification of the which many fire departments prefer for the hazards of a material in terms of
hazards of materials for emergency response. This system identifies the three categories: Health, flammability
response. NFPA Standard No. 704 hazard and severity of materials and and stability. This system indicates the
EP29MR05.000</GPH>

provides a simple, readily recognized may be used in lieu of the DoD fire degree of severity by a numerical rating

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00023 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16060 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

which ranges from four (4), indicating relative rather than absolute values. For No. 325.4 Figure 2 to § 184.10 through
severe hazard, to zero (0), indicating assignment of hazards, see NFPA Figure 4 to § 184.10. present an
minimal hazard. The system is based on Standard No. 49 and NFPA Standard overview of the NFPA marking system.

4 NFPA Standard No. 704, NFPA Standard No. 49 ‘‘Fire Protection Guide to Hazardous Materials,’’ 2001 Edition, ISBN# 087765435, available at
EP29MR05.001</GPH>

and NFPA Standard No. 325 are all contained in http://www.nfpa.org/catalog/home/index.asp.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00024 Fmt 4701 Sfmt 4725 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16061

(h) Firefighting procedures. (1) known hazards and conditions existing fought immediately with all available
General. (i) Firefighters of AE fires must at the scene of the fire before proceeding means. However, if the fire involves
have a thorough knowledge of the to its location. explosive substance, is supplying heat
specific reactions of AE exposed to heat (ii) Fire involving AE shall be fought to them, or if the fire is so large that it
or to fire. The firefighting forces and according to the appropriate response cannot be extinguished with the
other essential personnel shall be for hazard or fire division and the stage equipment at hand, the personnel
briefed before approaching the scene of of the fire. involved shall evacuate and seek safety.
the fire. They shall be informed of the (iii) All fires starting in the vicinity of
AE should be reported and should be

EP29MR05.002</GPH>

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00025 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16062 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

(iv) Emergency withdrawal distances the withdrawal distance based on the (2) Specific. (i) Contractors shall train
for non-essential personnel are intended situation at hand. operational personnel on the
for application in emergency situations (vi) Structures or protected locations characteristics of explosive substances,
only and not facility siting. Emergency offering equivalent protection for the including their reactions to heat and
withdrawal distances depend on fire distances listed in Table 2 to § 184.10 fire, as well as what to do in case of fire.
involvement and on whether fire may be used in lieu of relocating Personnel shall not attempt to fight fires
division and net explosive weight personnel from the structure and/or involving Hazard Division (HD) 1.1 and
(NEW) are known. Emergency location to the specified emergency HD 1.2 AE. These AE detonate with a
authorities shall determine the withdrawal distance.
fragmentation hazard, and personnel
withdrawal distance for essential (vii) Contractors should develop
evacuation plans for their facilities shall evacuate immediately, using
personnel at the fire. Emergency protective cover where available and
which reference the appropriate
authorities shall determine who are activating deluge systems and fire
withdrawal distances as part of the
essential personnel. alarms while escaping. Individuals
emergency response plan. Contractor
(v) If a fire involves explosive personnel are responsible for alerting remain in danger until they reach
substance, the initial withdrawal local authorities of any imminent shelter, although reaching IBD in the
distance applied shall be at least to the explosive accident on the facility which open affords some safety. Exit drills
inhabited building distance (IBD). See may affect the local community and for should be conducted annually and
Table 2 to § 184.10. If fire does not providing local authorities with the during exit drills, employees shall be
involve explosive substances, appropriate emergency withdrawal advised of the safest escape routes and
emergency authorities shall determine distances. evacuation points.

TABLE 2 TO § 184.10.—EMERGENCY WITHDRAWAL DISTANCES FOR NONESSENTIAL PERSONNEL

Hazard division Unknown quantity Known quantity

Unknown, located in facility, truck and or 4,000 ft (1,220 m) 4,000 ft (1,220 m).
tractor trailer

Unknown, located in railcar 5,000 ft (1,524 m) 5,000 ft (1,524 m).

1.1 and 1.5 1 Same as unknown facility, For transportation, use 2,500 ft (762 m) minimum distance for 500 lb (227 kg) and below. Above
truck trailer or railcar as 500 lb (227 kg), for rail cars use 5,000 ft (1,524 m) minimum distance, otherwise use 4,000 ft
appropriate (1,220 m) minimum distance. Use 4,000 ft (1,220 m) minimum distance for bombs and projec-
tiles with caliber 5 in (127 mm) or greater.
For facilities, use 2,500 ft (762 m) minimum distance for 15,000 lb (6,804 kg) and below. Use
4,000 ft (1,220 m) minimum distance for net explosive weights above 15,000 lb (6,804 kg) and
less than or equal to 50,000 lb (22,680 kg). Above 50,000 lb (22,680 kg), use
d = 105 W 1⁄3.
EP29MR05.003</GPH>

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00026 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16063

TABLE 2 TO § 184.10.—EMERGENCY WITHDRAWAL DISTANCES FOR NONESSENTIAL PERSONNEL—Continued


1.2 (1.2.1, 2,500 ft (762 m) 2,500 ft (762 m).
1.2.2, and
1.2.3) 1.6 1

1.3 2 600 ft (183 m) Twice the IBD (Table C9.T10.) with a 600 ft (183 m) minimum range.

1.4 300 ft (91 m) 300 ft (91 m).


1 For HD 1.1 and HE 1.2 AE, if known, the maximum range fragments and debris will be thrown (including the interaction effects of stacks of
items, but excluding lugs, strongbacks, or nose and tail plates) may be used to replace the minimum range.
2 For accidents involving propulsion units, it is not required to specify emergency withdrawal distances based upon the potential flight ranges of
these items.
3 This is the quantity-distance formula. 105 is the K-factor, a constant, and respresents the degree of damage which is acceptable in this situa-
tion. The distance d is in feet and W is the net explosive weight in pounds.

(ii) If the fire in a HD 1.1 or HD 1.2 (k) Deluge systems. (1) Contractors long vegetation of 6 to 8 in (152 to 203
building does not directly involve may use deluge systems to supplement mm) in length, which is green or
explosive substances and is small or in sprinklers, when the hazards are high, sparsely spread, is acceptable. Do not
a segregated container, an attempt such as in powder hoppers and cutters. allow vegetation to become dry or
should be made to extinguish the fire. Rate of rise, light actuating, ultraviolet, dense. This could allow rapid
After summoning firefighters, or other quick-action devices for transmission of fire.
responsible contractor personnel shall automatic control of deluge systems are
§ 184.11 Risk identification and
meet them as they approach the facility recommended. Part controls should management.
to brief them. When HD 1.1 or HD 1.2 serve as backup.
(a) General. AE operations involve
AE is directly involved, firefighting (2) To ensure immediate drenching of
many hazards and risks. These include
forces should maintain IBD from the AE material, the distribution outlets
the type of hazards associated with any
fire. The safety of personnel fighting a (nozzles, sprays, heads, etc.) should be
industrial enterprise (e.g., lifting,
HD 1.1 or HD 1.2 fire depends on the as near the explosive’s exposed surface
slipping, tool use, toxic chemicals,
accuracy of the information made as permitted by the outlet discharge
potential exposures to environmental
available to all firefighting forces. No pattern. When explosives are under
extremes, etc.).
person shall re-enter a burning building tight hoods or covers inside machines, (1) The evaluation of hazards and risk
containing HD 1.1 or HD 1.2 AE. distributing outlets belong inside the of mishap addressed in this section
(iii) Personnel in the immediate enclosed space. relate to processes not end products.
vicinity of HD 1.3 AE should activate (3) Nonmetallic, internally-spring- The safety of operations is a contractor
deluge systems and alarms. Unless the held caps should protect outlets responsibility. Only the Government
fire is minor, involves no explosive, and exposed to explosive vapors, gases, or can accept risk for the AE it acquires
appears controllable, firefighters shall dust. Upon exertion of pressure within and uses.
confine their efforts to prevent it from the outlet, the cap shall immediately (2) A basic risk identification and
spreading to other buildings. Fire in HD pop. Caps should be attached to outlets management system is a necessary
1.3 AE creates a wide area of intense to prevent their dropping into element of a comprehensive AE safety
radiant heat, dangerous to personnel equipment during a deluge. program. The purpose of this chapter is
and equipment. The firefighters should (4) Water flow and pressure should be to address risk identification and
exercise extreme caution. determined for the hazard. management for all AE operations.
(iv) HD 1.4 AE presents a moderate (5) Periodic inspections of deluge (b) Risk management system.
fire hazard. Fires involving this material systems shall ensure that they are in Contractors shall have a risk
shall be fought until extinguished proper operating condition. identification and management system,
unless emergency authorities determine (6) The deluge valve should allow for which, as a minimum, results in the
to evacuate. automatic and part activation. Part analysis of materials, equipment, and
(i) Emergency planning. Contractors activation devices shall be placed at the personnel capabilities. This analysis
shall develop procedures or plans to operator station or at exits in explosive will aide in the development of a
provide safety, security, and operating buildings as determine by a written SOP for AE contract operations.
environmental protection. Plans shall be hazard analysis. The contractor shall document the
coordinated with the applicable Federal, (7) NFPA Standard No. 13 and NFPA analysis and keep it as long as the SOP
state, and local emergency response Standard No. 15 contain basic is active.
authorities (e.g., law enforcement, fire installation rules. The analysis shall include such
departments, and hospitals, etc.). At a (l) Firebreaks. A firebreak is an area of factors as: Initiation sensitivity, quantity
minimum, those procedures or plans bare ground or vegetation intended to of materials, heat output, rate of
shall include provisions for complying limit the probability of fires causing a burning, potential ignition and
with Section 301–312 of the Emergency hazard to AE areas. A firebreak, at least initiation sources, protection
Planning Community Right to Know Act 50 ft (15 m) wide shall be maintained in capabilities of shields, various types of
(EPCRA). all directions around magazine and AE clothing, fire protection systems, and
(j) Automatic sprinkler systems. operating buildings or locations. personnel exposure with special
Properly installed and maintained Barricades and other sloping ground, considerations (such as toxic or
automatic sprinklers reduce fire losses. within the firebreak area, should retain corrosive chemicals).
They are particularly useful for load enough vegetation to prevent significant (1) The contractor shall perform risk
lines, AE manufacturing, receiving, erosion. Growth of vegetation within a analysis using personnel knowledgeable
shipping, inspection, and workshops, firebreak shall be controlled to prevent in the process, materials, equipment and
and demilitarization. rapid transmission of fire. Relatively relevant safety requirements.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00027 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16064 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

(2) Hazard and risk. (i) A hazard is and its likelihood of occurrence over seriousness of the risk before and after
any condition, which, by itself or by time. action is taken to control it. Table 1 to
interacting with other variables, may (iii) Evaluation of the hazard provides § 184.11 shows one risk matrix used by
result in death or injury to personnel or information useful for ranking the the Department of Defense. Definitions
damage to property. Controls only degree of risk associated with a hazard. of the code numbers and letters are
reduce the likelihood or severity of The degree of risk indicates which contained in Table 2 to § 184.11.
hazards. They do not eliminate them. hazardous conditions should receive
priority for corrective action when TABLE 1 TO § 184.11.—SAMPLE RISK
(ii) After identifying a hazard,
compared to other hazardous MATRIX FORMAT
qualified contractor personnel shall
determine the associated risk. The risk conditions. One technique for ranking
Mishap probability
analysis shall address both the severity hazardous conditions is the assignment Mishap
of a Risk Assessment Code (RAC). Table severity
of a resulting mishap and the A B C D
probability of occurrence of a mishap. A 1 to § 184.11 is an example of a risk
matrix. The evaluation of the hazard I ................. 1 1 2 4
risk deals with the mishap which arises II ................ 1 2 3 4
from a hazard, considering both the results in the assignment of a narrative
III ............... 2 3 4 5
severity of its potential consequences, or numerical risk assessment such IV .............. 4 4 5 5
which management can judge the
TABLE 2 TO § 184.11.—RISK ASSESSMENT DEFINITIONS
Risk assessment
Mishap severity Mishap probability codes (RAC)

I. A mishap which could result in the death or permanent disability, or result in A. Likely to occur immediately .............. 1. Critical.
the inability to deliver the contract item.
II. A mishap which could result in permanent partial disability or temporary total B. Probably will occur in time ................ 2. Serious.
disability, in excess of three months, or result in late delivery, 30 days or
more, of the contract item.
III. A mishap which could result in lost workdays or compensation for employ- C. Possible to occur in time .................. 3. Moderate.
ees, or result in the late delivery, less that 30 days, of the contract item.
IV. A mishap which could result in first aid or minor supportive medical treat- D. Unlikely to occur ............................... 4. Minor
ment, or damage to process equipment or product but would not affect the 5. Negligible.
delivery of the contract item.

(c) Analytical methods. There are a (d) Information for analysis. (1) (b) Building exteriors. Fire, fragment
number of analytical methods or Contractors shall develop and use a generation, venting, and evacuation are
approaches to the performance of methodology to address any change to critical design parameters. Exterior wall
hazard/risk analyses. The complexity of an AE operation which may present a and roof coverings of AE operating
the process involved, the number of new hazard or increase the risk of a buildings shall be designed with
variables, and the severity of the present hazard before incorporating the noncombustible and, whenever
consequences of failure should change into an operation. possible, frangible (breakaway)
determine the level and methodology of (2) Before introducing a change to an construction. AE buildings should be
the analysis used. The contractor shall AE operation, contractors shall perform one story, except to meet process
select the level and best method for a hazard analysis. Contractors shall requirements. Basements should not be
performing the analysis. maintain documentation explaining used, since they expose personnel above
(1) As a minimum, contractors shall how they will control the hazard or and make evacuation difficult.
break the total process into successive hazards if the analysis indicates the
steps and assess the hazards and risks (c) Interior walls, roofs and ceilings.
change will result in any new hazards, Roofs and walls of AE buildings shall be
for each process step. A sample format
or increase the risk of present hazards. as light as practicable to vent an internal
for conducting such an analysis is
Contractors shall validate the hazard explosion and produce the smallest
contained in Table 1 to § 184.11. Any
controls for the changed operation, and number of fragments. Firewalls and
format, which provides essentially the
maintain documentation of the dividing walls constitute exceptions. AE
same information, is acceptable.
validation. buildings which might house loose,
(2) A significant percentage of
accidents occur during intermittent (3) Contractors shall use the finely divided explosive substances
operations such as setup, startup, information acquired from the hazard require smooth, fire resistive walls and
maintenance, repair, response to out-of- analysis and validation process to revise ceilings which are free from cracks and
tolerance operation, and shut down/ SOPs and retrain employees. crevices. When appropriate, paint walls
clean-up. Therefore analyses must and ceilings with high gloss paint to
§ 184.12 AE building design and layout. minimize dust accumulation and
consider intermittent operations as well
as normal operations. (a) General. The design and layout of facilitate cleaning. Avoid ledges that
(3) Risk decisions must not only AE buildings are critical considerations collect dust. Bevel and keep clean all
consider the severity and probability of in explosive safety and directly impact existing ledges. Seal all wall joints and
a process change failure, but also Q–D requirements and hazardous openings for wiring and plumbing
recognize the criticality of operations exposures to operating personnel and against dust. Do not install suspended
(e.g., dollar value, lead time to procure, valuable equipment. Preplanning and ceilings or construct hollow walls in
significance to end item or process, proper design can significantly reduce Class II Hazardous Locations as defined
etc.). risk of injury and property loss. by the NFPA Standard No. 70. Install

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00028 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16065

insulation and covering directly on the glazing with conventional glass is used, material. Motors shall meet NFPA
underside of the roof deck. properly fixed plastic or wire mesh Standard No. 70 rating for the hazard
(d) Floors and work surfaces. screening may reduce the hazard. classification of its location.
Construct and finish floors and work (k) Drains and sumps. (1) All drain Maintenance personnel shall electrically
surfaces to facilitate cleaning, with no lines handling explosive wastes shall bond and ground the entire exhaust
cracks or crevices in which explosives have sumps or basins of sufficient system and clean and service it on a
could lodge and no exposed nails, capacity for the removal of explosives regular schedule.
screws, or bolts. Cove bases at the by settling. The drains shall have (n) Steam for processing and heating.
junctions of walls and floors should be adequate capacity. be free of pockets. Process steam is that which is in direct
used. All locations where exposed and have slopes of at least 0.25 in/ft (21 contact with explosives, used directly in
explosives or hazardous concentrations mm/m) to prevent explosives settling- their manufacture, or which, in case of
of flammable vapor or gas are present out in the drain line. Design of sumps equipment failure, would exhaust
require non-sparking floors and work shall prevent suspended and settleable directly into contact with explosives or
surfaces. solid explosive material from passing explosive fumes. Avoid steam or hot
(e) Substantial dividing wall. (1) beyond the sumps in the wash water, water pipes contacting wood, paper, or
Substantial dividing walls, constructed and prevent overflow from disturbing other combustible materials.
in accordance with the requirements of any floating solids. The settling rate of (1) Steam temperature. The exterior of
Army TM 5–1300, Navy NAVFAC P– the material and the usual rate of flow pipes shall not exceed 160 °F (71 °C).
397, or Air Force AFR 88–22 (different shall determine the sump capacity. The Maximum steam temperature should
designations for the same publication), design shall also permit easy removal of not exceed 228 °F (109 °C). When steam
separate independent quantities of HE collected explosives, and shall allow for temperature must exceed 228 °F (109 °C)
so they do not need to be added when retention of those that float on water
in hazardous locations, cover and paint
determining Q–D requirements. until they can be removed. Sump tanks
(2) Avoid openings in dividing walls the steam lines with an impervious
or other types of construction (e.g.,
for conveyors, pass-through boxes, or material or otherwise protect them
bolted) that permit the explosives to
other uses when possible. When against contact with explosives.
settle in obscure or hidden spaces are
operationally necessary, design closures not acceptable. (2) Steam pressure. Steam used for
with equivalent wall-strength (2) Care shall be taken to preclude heating AE operating buildings should
characteristics. deposition of explosives from sump have a maximum pressure of 5 psi (34.5
(f) Exits and doors. Facility design effluent due to drying, temperature kPa). Steam pressure shall not exceed 15
and operational flow shall eliminate all changes, or interaction with other psi (103.4 kPa). When a reducing valve
explosive hazards between an operator industrial contaminations. Sweeping is used, never bypass the relief valve in
and an exit. AE building design should and other dry collecting measures a manner permitting circumvention of
include casement-type exit doors glazed should be used to keep appreciably the pressure reduction equipment.
with non-shattering plastic material. All water-soluble explosives out of the Positive means shall prevent the
interior doors should open in the drainage system. production of superheated steam caused
direction of the flow of material through (3) Drains between the source of by the throttling action of reducing
the building and should open onto explosive and the sump shall have valves. The use of a ‘‘water leg’’ or water
unobstructed passageways. troughs with rounded bottoms and with column is recommend to control steam
(g) Emergency egress. When hazard removable ventilated covers to facilitate pressure of 5 psi (34.5 kPa) or less.
analysis determines that standard exits inspection for accumulation of When close control of steam
and fire escapes are inadequate from explosives. Waste liquids shall not run temperature is necessary, install
work levels above the ground floor, into closed drains and sewers. Inspect indicating and recording pressure or
other means of emergency egress (e.g., and clean out drains periodically to temperature gauges. Maintenance
safety chutes) shall aid evacuation. prevent the excessive buildup of personnel should test such devices
(h) Passageways. Design of weather- explosives. Drains and sewers periodically and record the test results.
protected passageways between containing explosive waste materials When electrical resistance to ground is
buildings or magazines should include shall not connect into the normal high, properly ground steam lines where
noncombustible construction and fire sewage systems. they enter buildings.
stops. (l) Hardware. (1) Facility design shall (o) Tunnels. The design and
(i) Roads and walkways. The road provide for non-sparking hardware in construction of tunnels between AE
system should provide alternate routes AE areas when hazard analyses buildings requires special consideration
between inert locations without entering determine sparks provide sufficient due to possible communication of an
AE areas. Roads in AE areas shall not energy to initiate exposed explosive explosion by shockwave and blast.
dead end unless they dead end at, and materials, explosive dusts, or flammable
serve a single AE location. Facility § 184.13 Safety requirements for specific
vapors. Avoid installing hardware (e.g.,
AE and AE operations.
design should provide hard-surface piping and ducts) on blowout panels or
walkways and roads at the entrance to walls (a) General. This section provides the
or between AE buildings to prevent (2) Some fasteners (e.g., nuts and minimum safety requirements necessary
employees from tracking such potential bolts) on or near operating equipment for the prevention of mishaps involving
hazards as stones, grit, and other foreign can fall into explosives or explosive specific AE and AE operations. The
material into operating buildings. constituents and cause friction, heat, contractor is responsible for analyzing
(j) Windows and skylights. The use of and initiation. Operating personnel each operation and developing
conventional glass in areas with a shall secure such fasteners using safety procedures to control or eliminate
potential blast overpressure hazard wire or other methods. hazards.
creates a serious secondary (m) Ventilation. Exhaust fans through (b) Properties of explosives.
fragmentation hazard. Use safety glass which combustible dust or flammable Knowledge of properties of specific
or non-shattering plastic materials (e.g., vapor pass shall use nonferrous blades, types of explosives is critical to the
Lexan, Plexiglas) when practical. When or a casting lined with nonferrous establishment of proper hazard controls.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00029 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16066 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

(1) Primary (initiating) explosives. press and machine, and mix-cast-cure (4) Review each proposed program for
Initiating explosives include lead azide, versus sensitivity characteristics). Do the laboratory or test facility to
lead styphnate, and tetracene. They are not permit alkaline cleaning agents or determine all potential hazards
extremely sensitive to friction, heat, other alkaline products in buildings including the following considerations:
electrostatic discharge and impact. where large quantities of these (i) Structural limitations of the
When involved in a fire, they may explosives are handled. facility.
detonate. (4) Other explosives. Other common (ii) Remote control viewing and
(i) In storage, initiating explosives military explosives encountered include operating equipment, if required.
shall be kept wet with water or water/ black powder and nitroglycerin (NG). (iii) Special safety precautions for
alcohol mixtures to reduce sensitivity. Black powder is a mixture of potassium personnel elsewhere in the building.
Take every precaution to prevent the or sodium nitrate, charcoal, and sulfur, (iv) Safe separation distances.
liquid from freezing since this increases which is highly sensitive to friction, (v) Required deviations from other
sensitivity. Handling of frozen initiating heat, and impact. It deteriorates rapidly sections of this part.
explosives is prohibited. Assure the after absorption of moisture, but retains
water used for storage is free of bacteria (vi) SOP, which shall, at a minimum,
its explosive properties indefinitely if include the following:
forming impurities which could react to kept dry. NG’s extreme sensitivity to
form gases and rupture containers. (A) Protective clothing.
impact and friction is such that it is
(ii) Operators shall keep work areas (B) Warning signals.
manufactured only as needed. Frozen
and equipment clean and maintain good nitroglycerin, while less sensitive than (C) Fire and other emergency
housekeeping to prevent contamination liquid, may undergo internal changes procedures.
of these explosives with foreign, upon thawing and, if enough heat is (D) Special testing of equipment
particularly gritty, material markedly generated, may detonate. needed before operations (e.g., stray
increases their sensitivity. (5) Research of additional properties. voltage and calibration checks).
(iii) Do not allow lead azide to contact (E) Removal of all explosives not
Contractors must investigate pertinent
copper, zinc, or alloys containing any needed for the operation.
properties before handling other
concentration of such metals because of (F) Arrangements for overnight
explosive substances. Sensitivity data
the likely formation of other azides that storage of necessary explosives.
for the same characteristic, generated on
are more sensitive than the original. (G) Inspection and cleanup
different types of equipment, are not
Similar hazards exist for other procedures after a test or detonation.
necessarily comparable. Contractors
explosives.
(2) Secondary (boostering and must thoroughly understand the (5) Use no more explosives than
bursting) explosives. Boostering and sensitivity test method employed, the absolutely required for a given
bursting explosives include tetryl, RDX, unit of measure in which data are operation. Perform particularly
PETN, HMX and compositions presented, and the relative ranking of hazardous laboratory operations
manufactured with these explosives. the explosive verses other similar involving new or relatively unknown
These explosives have sensitivities explosives. explosives by remote control. Use
between initiating explosives and those (c) Laboratory operations. (1) operational shields in these operations
of explosives used as main charges such Research and development laboratories and in new or untested applications of
as TNT. They may be ignited by heat, and testing facilities constitute a explosives.
friction, or impact and may detonate separate category involving guidance, (6) When laboratories and testing
when burned in large quantities or at restrictions, and relief from certain facilities are shielded properly to
too great a depth. Some of these requirements prescribed in this part. prevent the release of fragments, the
materials are toxic when taken (2) Review each operation at facilities minimum incremental safe separation
internally or by skin contact and special designed for blast and fragment distances shown in Table 1 to § 184.13
precautions are necessary to protect confinement to ensure that the apply to operations, facilities, and
personnel. Use local exhaust explosives limits are within the personnel.
ventilation, enclosed process systems, laboratory or test area capability. (7) If the proposed storage facilities
automatic handling systems, etc., to Decrease explosives limits and increase will confine the blast and fragments, or
minimize dust in the employee’s safe separation distances as the if the incremental safe separation
breathing zone. capability to confine fragment and blast distances are as indicated in paragraph
(3) Main charge explosives. Main decreases. (c)(6) of this section, up to 15 lbs (6.8
charge explosives include TNT, tritonal, (3) Inspect a total confinement facility kg) of explosive substance may be stored
RDX , HMX, CL–20, and compositions after a detonation to ensure structural without consideration of storage
manufactured with these explosives. integrity. It may become necessary to compatibility. Review the operation to
Use process hazard analysis to evaluate reduce the explosives limits to prevent determine all potential hazards prior to
the safety of the processing future blasts from exceeding the use as outlined in paragraph (c)(6) of
methodology, (e.g., melt-cast, extrusion, retention capability. this section.

TABLE 1 TO § 184.13—LABORATORY Q–D REQUIREMENTS


Quantity (lbs) Distance (ft) 1

Over Not over IBD PTRD ILD

Hazard Division 1.1

0 1 40 25 20
1 2 50 30 25
2 5 70 40 30
5 10 90 55 35

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00030 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16067

TABLE 1 TO § 184.13—LABORATORY Q–D REQUIREMENTS—Continued


Quantity (lbs) Distance (ft) 1

Over Not over IBD PTRD ILD

10 20 110 65 45
20 30 125 75 50
30 40 140 85 55
40 50 150 90 60

Quantity (lbs) Distance (ft)

Over Not over IBD PTRD ILD

Hazard Division 1.3

0 5 10 10 10
5 10 15 15 15
10 20 20 20 20
20 30 25 25 25
30 50 30 30 30
50 80 35 35 35
80 100 40 40 40
100 150 45 45 45
150 200 50 50 50
1 The distance above may be used only when structures, blast mats, and so forth, can completely contain fragments and debris. If fragments
cannot be contained or the quantity of high explosives exceeds 50 pounds, then the distances shall be obtained from the Q/D tables of DoD
6055.9 (reference (a)).

(d) Heat conditioning of AE. (1) All hazardous atmosphere in question in or (iii) Check heat-conditioning device
ovens, conditioning chambers, dry on a heat-conditioning device used for temperatures at specified intervals
houses and other devices and facilities explosives or flammable material. during operation.
which are capable, in ordinary service, (7) Ensure the interior of a heat- (iv) Clean the conditioning devices,
of heating AE to temperatures in excess conditioning device is free of crevices, ducts, vacuum lines, and other parts of
of 90° F (32° C) are heat-conditioning openings, and other protuberances not the equipment subject to contamination
devices. Provide heat-conditioning easily cleaned, where dust or flammable by hazardous materials, before
devices with dual independent fail-safe material could lodge. introducing a different item or
heat controls. For devices or facilities composition for conditioning.
(8) Interconnect and electrically
heated by steam only, the requirement (e) Spray painting. (1) Do not
ground all non-current-carrying metal
for dual heat controls is satisfied if the electrostatically spray paint loaded AE.
parts of a heat-conditioning device. (2) Use water wash or dry filter-type
steam pressure is controlled by a
reducing valve (maximum pressure of 5 (9) Install heat-conditioning devices spray booths for loaded AE.
psi, (34.45 kPa), unless otherwise in isolated locations, set up to give (3) Interlock controls for ventilating
authorized) on the main building steam personnel maximum protection from the fan motors for spray painting booths
supply, and a thermostat. effects of an explosion. Use operational with the controls for the paint sprayer.
(2) Ensure heat-conditioning devices shields and other personnel protection With this arrangement, failure of the
are able to discharge overpressure from measures when warranted. ventilating system will shut off power to
an internal explosion. Use barriers or (10) Safe separation distances or the paint sprayer.
catching devices to restrain blowout protective construction ensures against (4) Install high-voltage, electrically-
panels, doors, and other venting an explosives accident in one heat- powered, paint-spraying equipment in
apparatus and prevent excessive conditioning device from propagating to accordance with the requirements of
displacement during an accidental others. Do not place hazardous materials NFPA Standard No. 33 as applicable.
explosion. in a room or cubicle containing a heat- (5) Ensure conventional equipment
(3) Heat-conditioning devices must be conditioning device, unless it can be used for spray painting in standard
vented to allow any gases produced to shown that a mishap in the conditioning spray booths meets the requirements of
escape. device would not involve the other NFPA Standard No. 33. Electrically
(4) Steam heat conditioning devices materials. ground the nozzles of all spray guns to
are preferred. However, when using suppress static electricity.
(11) Operating procedures for heat-
electrical heating elements, locate them (f) Drying AE. Use ovens which
conditioning devices must:
where there is no possibility of contact comply with the NFPA Standard No. 70
with explosives or flammable materials. (i) Limit the explosive materials in the to dry loaded AE. Other requirements
(5) Ensure the blades of a fan in a device to the type and quantity include the following:
heat-conditioning device are non- authorized for the specific device. (1) Ensure automatic thermostatic
sparking and install its electric motor (ii) Address the critical parameters of controls regulate temperatures once they
externally. Do not re-circulate the air if explosives compositions before reach a maximum determined by the AE
the heating surfaces exceed 228° F (109° processing in a heat-conditioning involved.
C) or if the air contains materials which device. Ensure the device does not (2) Equip each oven with automatic
could collect on the heating coils. exceed limits established for the internal sprinkler systems which
(6) Permit only electrical equipment hazardous composition being conform with NFPA Standard No. 13.
and fixtures approved for use in the conditioned. Approved electrical heat actuated

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00031 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16068 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

devices, installed as required for NFPA °F (121 °C) to melt or maintain TNT- HMX compositions with greater than
Standard No. 70, Class I, Division 1, based explosives in a molten state. 60% HMX, Cyclotols, Composition B
Group D, hazardous locations may be (ii) Construct and maintain melt unit and RDX compositions with
used for automatic operation of the valves and melt mix draw-off or other concentrations of RDX greater than
system. lines carrying molten explosives to 60%.
(3) Hot air or other means may supply prevent friction or impact capable of (iii) Machine other HE by remote
heat, provided AE does not contact igniting the explosives. Disassemble and control, and protect the operators by a
coils, radiators, and heating elements. regularly inspect diaphragm type valves. suitable operational shield. Do not
(4) In case of power failure, the heat Replace damaged or old diaphragms machine primary explosives if you can
supply for any conveyor system must before cracks develop to prevent metal- obtain desired shapes or sizes by other
automatically stop. to-metal contact. Construct draw-off means (e.g., forming).
(5) Design electric drying units not lines to prevent exposure of threads, (iv) Use only a single drill bit with a
approved for use in Class I hazardous fastening screws, and bolts, both outside diameter greater than 0.25 in (0.064 cm)
locations so that solvent vapor and between the flanges. Use a sealing when an unprotected operator is
concentration in the oven is kept below compound to prevent explosives involved in drilling.
25% of its lower explosive limit. seepage or vapor condensation on the (v) Permit machining of cased
(g) Rework, disassembly, renovation, contacting surfaces of the bolts, flanges, explosives in an operation requiring
and maintenance. (1) Avoid conducting screws, and nuts. Electrically bond melt removal of metal before or after tool
AE rework and disassembly operations mix kettle draw-off pipes to items being contact with the explosives filler.
with other AE or inert operations. When filled during draw-off operations. Protect operators with operational
concurrent scheduling cannot be Individually ground AE unless tests shields and machine by remote control.
avoided, operations shall be sufficiently indicate that contact ground is adequate. (vi) Where wet machining is
separated from one another to protect (iii) Wet-type collectors remove dust performed, use automatic interlocking
adjacent personnel and equipment, and and vapors from exhausted air, and are devices to prevent machining unless
prevent propagation to adjacent AE. effective for melt mix exhausting coolant is flowing. Establish controls
Separation may be accomplished with systems. Do not re-circulate water in the capable of stopping the machining if the
Q–D, operational shielding, or the wet collector unless the system removes coolant flow is interrupted. When
remote control of operations. hazardous suspensions. Discharge water coolant flow must stop for adjustment of
(2) Protect the worker and all other retaining explosives to a containment machining tools, provide positive means
personnel from possible initiation when unit designed to keep them wet. to ensure that flow of coolant is restored
the force applied during rework or Regularly inspect and flush the exhaust and all automatic control devices are
disassembly is known or expected to and collecting equipment of explosives operating before machining resumes.
exceed assembly force. accumulations. Equip each kettle with a (vii) Maintain the lineal and rotational
(3) Personnel protection required complete dust and vapor collection speeds of tools used for the machining
during assembly operations is normally system when protective construction of explosives at the minimum required
also required during disassembly or prevents propagation of a detonation to perform the operation safely and
rework operations. Use lesser protection between melt kettles. efficiently. The rate of feed should be
only if fully supported by a risk (4) Agitation. Equip agitation consistent with the hazard analysis.
assessment. Verify that assembly was nitrators, washers, and other machines (viii) Use pneumatically-or
within specification, the surfaces are not with at least two means of agitation, hydraulically-driven machine tools
corroded and whether sealant is present. each operating from an independent whenever possible for machining
(4) Request specific safety guidance power source. A loss of power if using operations on HE. Install control
through contract channels when only one power source could result in mechanisms for hydraulic and
renovation or maintenance is not material decomposition. pneumatic equipment to prevent
adequately addressed in the contract. (5) Explosives machining. Awareness unauthorized personnel from tampering
(h) AE loading and associated of the friction sensitivity of explosives with speeds.
operations. (1) Screening and blending to be machined is required. Friction (ix) In all machining operations on
HE. Screen or visually inspect and pass sensitivity values of explosives listed in cased or uncased HE, ensure tool
over a magnetic separator bulk HE paragraphs (h)(5)(ii) and (h)(5)(iii) of adjustments prevent contact between
intended for processing to detect this section are available for moving parts of the machining
extraneous material. Do not subject HE comparison. Compare sensitivity values equipment and metallic parts of the case
to pinching, friction or impact in only for identical test, methods and or holding fixtures.
screening equipment. Thoroughly clean equipment. (x) Use machining tools compatible
HE screening units without exhaust (i) HE, cased or uncased, may be with the HE being processed. Remove
ventilation as necessary and after every machined without special personnel dull or damaged tools from HE
shift, to prevent hazardous protection and without coolant, if no machining operations.
accumulations of explosives dusts. metal-to-metal contact is involved, (xi) Remove explosives products
(2) Screening and blending initiating include: TNT, composition B with RDX resulting from machining operations
explosives. Provide suitable operational at or below 60%, RDX compositions with an exhaust system meeting NFPA
shields for screening and blending containing 60% or less RDX and HMX Standard No. 70 requirements or by
operations involving initiating compositions containing 60% or less immersion in a stream of water flowing
explosives. As an alternative, locate HMX. away from the operation.
operators at barricaded ILD from (ii) HE, cased or uncased, may be (xii) Machine HE with unknown
screening and blending facilities. machined without special personnel physical or chemical characteristics, by
(3) Explosives melting. (i) Do not protection provided a coolant is remote control with operators protected
exceed 228 °F (109 °F) when melting directed on the tool and explosives at by operational shields during AE
explosives and keeping explosives their point of contact and no metal-to- operations.
molten. It is permissible to use steam metal contact is involved, include: (i) Assembly and crimping of
pressures up to 15 psi (103.35 kPa) (250 Octol, Pentolite (50–50 and 10–90), complete rounds. Separate each

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00032 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16069

assembly and crimping operation from (2) Power-actuated, thread-chasing specific hazards of assembly and test. It
other operations by structures or tools may be used to clean loaded is particularly important to develop
shielding sufficient to contain any projectiles when threads are imperfect procedures for the guidance of unique
fragments produced by an accidental because of previously applied sealers. tests (e.g., fuze function, fragmentation,
detonation. However, the operation must be thermal effects, barricade test) which do
(j) Pressing explosives. (1) Conduct performed within a separate cubicle and not duplicate assembly, disassembly, or
each pelleting operation involving black by remote control. Hand-operated test requirements described in technical
powder, tetryl, TNT, or other explosives thread-chasing tools may be used when parts or other government publications.
of similar sensitivity and each operation no explosives are present in the threads. Include disposal procedures for
involving the pressing or (3) Do not cut threads or correct cross damaged energetic materials and
reconsolidation of explosives in a threads on projectiles containing ordnance items. The following are
separate room or cubicle having walls of explosives. Straightening crossed general assembly and testing safety
sufficient strength to withstand an threads is considered thread cutting. requirements.
explosion of all explosives present. (p) Profile and alignment gaging (4) Do not allow test conditions to
(2) Perform pressing or operations. (1) Use operational shields compromise basic AE safety
reconsolidating of explosives in small to enclose each profile and alignment considerations, for example,
caliber rounds, tracer bodies, tetryl lead- gauging operation, excluding small arms compatibility of materials, quantity
ins, detonators, and similar items on ammunition, to protect adjacent control, quantity distance, exposure of
machines having consolidating stations operations. Develop the layout of personnel to blast (including hazardous
designed to preclude propagation equipment and operational procedures noise levels), fragments and thermal
between stations and provide adequate to minimize personnel injury and effects, bonding and grounding, and
operator protection. Ensure operators property damage in case of an accident. personal protective equipment.
stay behind tested protective barriers (2) When chamber gauging large (5) Recognize and plan for the
during such operations. caliber fixed ammunition, point the mitigation of overpressure (including
gauge toward a dividing wall or other sound), fumes, dust, fragments, thermal
(3) Only use punches and dies in
barrier. Use the same operator to insert effects and catastrophic failure of test
matched sets which have passed
and remove each round. Never leave a equipment or barricades which can
inspection and are calibrated. Regularly
round in the gauge. Gauge rounds of occur during or as the result of testing.
inspect and test by magnaflux, X-ray or (6) Clearly identify expended
similar means, all punches and dies mortar ammunition before attaching
propellant increments and, unless ordnance contaminated with residual
used in explosives pressing operations. energetic or other hazardous materials.
(k) Protection of primers. Design prohibited by the design characteristics,
before assembly of the ignition system. Include decontamination steps in the
equipment, transportation, and test operations procedure.
operations to protect loose primers or § 184.14 Test and testing requirements. (7) Some testing, such as electrical
primers in components from accidental (a) General. The contractor is continuity, built-in-test, or weapon
impact or pressure. When feasible, use responsible for the safety of testing functionality on components or all-up-
a protecting cap to cover the primer. programs. Test programs include any rounds will require remote operations.
(l) Explosives washout and flashing and all tests, evaluations, quality Perform this testing with approved test
facilities. Separate washout operations assurance functions tests, or similar equipment at a facility site-approved for
in operating buildings or other locations situations where AE response to the operation. When this is the case, the
from other operations by operational stimulus is the objective. following requirements apply:
shields or proper distances. Inspect AE (b) Basic principles for test (i) Do not expose any test personnel
subjected to washout operations to operations. The following safety to operations that have a high
ensure against residual explosives precautions apply where pertinent: probability of resulting in a detonation,
contamination. When contamination is (1) Conduct all test operations in or to test operations that involve
confirmed, decontaminate prior to accordance with procedures developed intentional detonations. Protecting
disposal. in accordance with § 184.3 (c) and personnel from all fragments and from
(m) Heat-sealing equipment. Separate § 184.6(i), using a hazard analysis as the overpressures exceeding 2.3 psi
electric heat-sealing machines from basis for the procedures. (overpressure at k24) meets that
other operations. Establish temperature (2) Wherever possible, substitute inert requirement. Distance, operational
limits for heat-sealing equipment with a materials for live AE. When only live shields (see paragraph § 184.3(g) of this
safety factor below the ignition AE will meet test objectives, protect test part), or structural design of buildings
temperature of the explosives, personnel. Use remote control of and bays involved, or a combination of
propellants, or pyrotechnics involved. operations, barricades, shields, remote these, can provide this protection.
(n) Rebowling operations. Perform methods of shutting down the test (ii) Protection by distance must
rebowling operations involving primary operation, or other appropriate methods include consideration of fragments as
explosives or primer mixes by remote of eliminating exposure to personnel. By well as overpressure. For many test
control, with the operator protected by definition, all tests involve some level of operations involving relatively small
an operational shield. uncertainty. Therefore test methods and quantities of explosives, the distance at
(o) Thread cleaning. (1) Use procedures must address all credible which the blast over pressure drops to
nonferrous picks for thread cleaning. malfunctions, or non-function potentials the 2.3-psi level is less than the
Stainless steel brushes are acceptable or and the appropriate reaction to them. minimum fragment distance. When this
use to clean threads of explosives- (3) Assembly and testing requirements occurs, the minimum distance between
loaded projectiles if a fuze seat liner specific to each ammunition and the operation and any personnel is the
separates the thread cleaning operation weapon system are contained in the fragmentation distance. Use of
from the explosive charge. Operators appropriate technical part and end-item barricades, earth covered shelters, or
may use operational shields or quantity specifications which should be structural elements to control the
distance separation to protect them from incorporated into procedures. The fragmentation hazard are acceptable
unrelated operations. hazard analysis process should identify when it is possible to demonstrate this

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00033 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16070 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

protection by test or engineering design. permit communication during testing (ii) The contractor may collect more
Tests normally require an overcharge of operations. sensitive explosives such as black
25% NEW greater than the maximum powder, lead azide, lead styphnate,
expected charge weight for testing, § 184.15 Collection and destruction
tracer, igniter, incendiary compositions,
requirements for AE.
when testing is the sole proof of and pyrotechnic materials by vacuum,
protection. (a) General. This section provides provided they are kept wet close to the
(iii) Provision of protection by safety requirements for the collection point of intake. Collect each type
structural design, whether by itself or in and destruction of AE. It contains more representing a different hazard
conjunction with distance, requires detailed information than other portions separately so that black powder, for
specialized structural designs. Army TM of this part due to the higher risks of example, cannot mix with lead azide.
5–1300, Navy NAVFAC P–397, or Air these operations. The Environmental The vacuum system should release any
Force AFR 88–22 (different designations Protection Agency (EPA) has developed build up of gases. Confine the use of
for the same publication, provides regulations which apply to contractors vacuum systems for collection of
assistance for these designs. When using and may impose requirements beyond sensitive explosive substances to
this publication, Protection Category 1 those in this part. Contractors shall operations involving small quantities of
is the level of design for personnel avoid compromising explosive safety for explosives, that is, operations with
protection. Designs based on lesser environmental considerations. fuzes, detonators, small-arms
levels of protection are acceptable, (b) Protection during disposal
ammunition, and black powder igniters.
depending upon the level of risk to operations. (1) Operational shields or
To minimize the fire and explosion
contract performance deemed special clothing shall protect personnel
hazard, collect scrap pyrotechnic, tracer,
acceptable by the PCO when personnel during disposal operations.
flare, and similar mixtures in No. 10
exposure is not an issue. Fragmentation hazards require, at a
mineral oil or equivalent. Collect dry
(iv) Spalling and other phenomena of minimum, overhead and frontal
explosive dust in an oil-filled receptacle
structural failure are part of the design protection for personnel. Contractors
available at each operation throughout
considerations when using the detonating AE may locate personnel
the shift. The oil level shall maintained
referenced part for protection. Spalling shelters at the appropriate IBD for the
at least 1 inch above the level of any
is the ejection of material from the back AE NEW. Personnel shall use protective
pyrotechnic mixture in the container.
face of a slab or beam as the result of structures when destroying AE by
Some pyrotechnic compositions float on
an explosion adjacent to the front face. detonation and when burning AE that
oil. If it occurs use a wooden plunger to
When not using the part for structural may detonate. Personnel shall not
submerge the material. Remove
designs, spalling protection must be part approach the burning site, but shall
containers of scrap explosive for
of the design and test of structural observe an appropriate waiting period
disposal from the operating buildings at
elements. When test cell walls do not after the fire is out.
(2) Personnel shall never work alone least once per shift. When using oil, use
extend through the ceiling of the
during disposal and destruction the appropriate rated Class B firefighting
structure, it is possible for overpressure
operations. Warning signs or lights, equipment.
and debris from an explosion to escape
over the top of the cell and injure roadblocks, or other effective means (d) Design and operation of collection
personnel near the cells. Designs must shall restrict the area. One person, systems. (1) Design collection systems
provide protection from such an available in an emergency, should and chambers to prevent pinching thin
eventuality. Similarly, when cell walls observe from a safe distance while layers of explosives or explosives dust
extend through ceilings and roofs, these another performs the operations. between metal parts. Pipes or ducts
structural elements must be strong (c) Collection of AE. (1) Water-soluble used to convey dusts require flanged,
enough to resist the effects of materials. Use sufficient water to welded, or rubber connections. The
overpressure and fragments, protecting neutralize ammonium picrate contractor shall not use threaded
personnel below. (Explosive D), black powder, and other connections. The system shall prevent
(v) Install interlocks to prevent soluble materials to ensure their explosive dusts from accumulating in
operator exposure to operations when complete dissolution. Dissolve as little parts outside the collection chamber.
doors on any equipment or cells used material as practicable at one time. Pipes or ducts conveying high
for explosives processing function as Sweeping floors before washing them explosives shall have long radius bends.
operational shields. Do not install door down reduces the amount of dissolved Systems for propellant powder may use
closure controls within cells. Design cell material in the wash water. Consult short radius bends, provided they are
door release devices to prevent experts when uncertainty exists stainless steel, with polished interiors.
personnel from being stuck by a closing concerning the purity and composition Minimize the number of vacuum
door and to allow egress from the cell. of wash water. application points. Use wet primary
These may require designs to become (2) Solid wastes. Collect explosives- collectors when possible. The design of
inoperative to prevent the overpressure contaminated solid waste material, the vacuum collection system should
of an explosion from opening the door. place in closed containers, and provide a separate exhaust line to the
Ensure that any pass-throughs between promptly deliver to buildings for primary collection chamber from each
cells prevent the transmission of treatment or holding, or to the burning room. If this is not possible, a common
fragments or damaging overpressures. ground for destruction. header shall service no more than two
Typically, such pass-throughs have (3) Explosives dusts. (i) The contractor bays. Keep short lengths of vacuum
doors interconnected so that only one may use a vacuum system to remove HE lines from the application points to the
door can open at a time. dusts such as TNT, tetryl, Explosive D, wet collectors. A single secondary
(vi) Establish a warning system of Composition B, and Pentolite. The collector shall service as few primary
flags, lights or sound signals during preferred removal method for explosives collectors as possible. The contractor
testing operations. Provide personnel is a ‘‘wet collector’’ which moistens the shall connect not more than two dry
who are not familiar with the warning dust near the point of intake and keeps primary collectors to a single secondary
system in test areas, and equipped test it wet until disposal. Collect Explosive collector (wet or dry type). Vacuum
areas with a telephone and/or radio to D in a dry system. systems that are permanently attached

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00034 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16071

to the explosive dust-producing buildings set-aside for that purpose. detonate AE on concrete, or in areas
machine may increase the likelihood of Provide a barricade or operational having large stones or crevices.
detonation propagation through the shield appropriate for the NEW (ii) For separation distances less than
collection system. Recommend using involved to protect operating personnel 1250 ft (381 m), use DoD approved
partly operated vacuum systems unless from blast (2.3 psi) and fragments from documentation to determine fragment
dust concentrations pose an explosion the collection chamber. At least 3 ft (1 and debris throw in calculating the
or health hazard. Partly operated hose m) should separate the collection appropriate IBD based on the maximum
connections to explosive dust- chamber from the barricade or NEW of AE present.
producing machines should not operational shield. (iii) Recommend keeping firefighting
interconnect. (2) When locating dry-type collection equipment available to extinguish grass
(2) Install two collection chambers in chambers outside the operating building fires and to wet down the area between
series ahead of the pump or exhauster is not feasible, set aside a separate room burnings and at the close of operations.
to prevent explosives dust from entering for this purpose in the building. The (iv) The contractor should not dispose
the vacuum producer in a dry vacuum contractor shall not allow personnel to of ordinary combustible rubbish near
collection system. work or pass through the dry-type AE and AE-contaminated material
(3) There shall be no metal-to-metal collection chamber room. Walls destruction sites.
contact on slide valves for vacuum separating the room from other portions (2) Materials and equipment for
collection systems. An aluminum slide of the operating building shall meet the detonating explosives. (i) Contractor
operating between two ebonite spacer requirements for operational shields for should initiate detonations of AE with
bars or similar compatible materials will the NEW in the collection chamber. electric blasting caps and blasting
eliminate unacceptable metal-to-metal Subdivide rooms with multiple machines or permanently installed
contact. collection chambers into cubicles with electric circuits energized by storage
(4) Install dry-type portable vacuum only one collection chamber per batteries or conventional power lines.
collectors, limited to 5 lbs (2.3 kg) of cubicle. When covering AE for disposal with
explosives, in a separate cubicle having (3) Stationary and portable wet-type
earth, do not bury the blasting cap.
substantial dividing walls, or outside collectors in operating bays or cubicles
Prime the initiating explosives with
the building. Never install type of shall not exceed 5 lbs (2.3 kg) NEW.
sufficient primacord to allow
collector in the bay or cubicle with the When placed in separate cubicles,
connecting the blasting cap above
explosives. The contractor may use wet- quantities may increase to 8 lbs (3.64
ground level.
type portable vacuum collectors in kg). See paragraphs (e)(1) and (e)(2) of
(ii) Special requirements for using
explosives operating bays or cubicles, this section for location requirements of
electric blasting caps and electric
provided limited quantities of wet collectors, containing more than 8
lbs (3.64 kg), blasting circuits follow.
explosives in the collector meet the (A) Never hold a blasting cap at the
requirements of paragraphs (e)(1) (f) AE awaiting destruction. Maintain
IBD from AE destruction sites and explosive (output) end. Hold the wire
through (e)(3) of this section. For dry lead end of the cap between the thumb
collection over 5 lbs (2.3 kg) or wet explosives stored in the open. If
adequately protected from frontal and and the index finger. Whenever
collection over 8 lbs (3.64 kg) of possible, point the explosive end of a
explosives, the provisions of paragraphs overhead hazards, ILD separation
between AE material awaiting hand-held cap down, away from the
(e)(1) through (e)(3) of this section also body, and to the rear.
apply. destruction and AE destruction sites is
acceptable. Protect all AE awaiting (B) Do not remove the shunt from the
(5) The design of wet collectors shall lead wires of the blasting cap until
provide for: destruction from accidental ignition or
explosion from fragments, grass fires, ready to connect them to the blasting
(i) Proper immersion of explosives.
(ii) Breaking up of air bubbles to burning embers, or blast originating circuit, except during electrical
prevent release of airborne particles, from the destruction site. continuity test of the blasting cap and
and (g) Containers for waste explosives. lead wires.
(iii) Prevent moistened particles of Use appropriate containers for AE waste (C) Carefully hold the lead wires so
explosives from entering the small to prevent leakage and spillage of that there is no tension where they
piping between the collector and the contents. The contractor shall not pinch connect to the cap and partly straighten
exhauster or pump or rub explosives during container the lead wires. Do not throw, wave
(6) At least once every shift, remove closing and opening. Clearly mark through the air, or uncoil by snapping
the explosives dust from the collection containers to identify contents. Do not as a whip.
chamber to eliminate unnecessary and use containers constructed of spark- (D) Use blasting circuit wires in
hazardous concentrations of explosives. producing or easily ignited material. twisted pairs. Operators shall keep
Clean entire system on a regular basis to (h) Destruction sites. (1) Site criteria. blasting circuit wires twisted together
remove residual contamination, with (i) Locate AE destruction sites as far as and connected to ground at the power
parts dismantled as necessary. possible from magazines, inhabited source and twisted at the opposite end
(7) Electrically bond the entire buildings, public highways, runways, at all times except when actually firing
explosives dust collection system to the taxiways, and operating buildings. The the charge or testing circuit for
grounding system. Test the electrical minimum separation distance is 1,250 ft continuity and extraneous electricity.
bonding/grounding system in (381 m) or the applicable fragmentation Never connect the blasting cap to the
accordance with § 184.6(f)(5). distance, unless pits or similar aids (e.g., blasting circuit wires unless the blasting
(8) Shield personnel workstations natural barricades) limit the range of circuit wires are shorted and grounded
from vacuum systems. fragments. Since burning explosives at the ends near the power source.
(e) Location of collection chambers. may detonate, contractor shall use (E) Maintain safe distances between
(1) Whenever practicable, locate dry- appropriate protective barriers or radio frequency (RF) energy transmitters
type explosives dust collection separation distances for the safety of and electric blasting, demolition
chambers, except portable units, in the personnel and property. To prevent operations, and unshielded electric
open, outside operating buildings, or in secondary fragments, do not burn or blasting caps.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00035 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
16072 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

(F) Transport blasting caps in closed when using a panel, shall lock the (3) Beds for burning explosives. (i) A
metal boxes wherever exposure to RF switch in the open position until ready bed of easily combustible material at
energy and extraneous electricity is to fire, retaining the only key. Connect least two inches thick should be
possible (i.e., vehicles equipped with blasting circuit wires to power source positioned under the explosive bed to
two-way radios). and fire the charge. ensure complete consumption of wet
(G) Operators should follow these (8) After firing, disconnect blasting explosives. The combustible material
procedures when connecting electric circuit wires from power source, twist should extend at least two inches
blasting cap lead wires to the blasting the wires together, and connect to beyond the edges of the explosive bed.
circuit wires. ground. If necessary, the thickness and extent of
(1) Test the blasting circuit wires for (9) Suspend blasting and demolition the combustible material may be
electrical continuity. operations when electrical storms are in adjusted, based on actual experience at
(2) Test the blasting circuit for the vicinity. At the first sign of an the site.
extraneous electricity. To test, arrange a electrical storm, short-circuit the (ii) The explosive bed shall be no
dummy test circuit similar to the actual blasting cap lead wires and the blasting more than 3 in (76 mm) deep.
blasting circuit, except substitute a radio circuit wires, and evacuate all personnel (iii) The ignition train of combustible
pilot lamp of suitable voltage for the from the demolition area to a safe material leading to the explosives bed
blasting cap. If the pilot lamp glows, location. shall be positioned so that both it and
indicating potentially dangerous the explosive bed can burn in a
(H) Use non-electric blasting caps and
amounts of RF energy, stop blasting controlled fashion and not propagate to
safety fuses when conditions prevent
operations using electric blasting caps. any other explosive treatment areas.
the use of electrical initiators for
Blasting operations may resume using (iv) No burning shall take place when
detonation. At the beginning of each
non-electric blasting caps and safety wind velocity exceeds 15 mph (24 km/
day’s operation and whenever using a
fuse. The contractor may substitute h).
new coil, test the safety fuse’s burning
other test instruments (e.g. the DuPont (v) For direct ignition of a
rate. The fuse shall be long enough for
‘‘Dectect-A-Meter’’ or ‘‘Voltohmeter,’’) combustible train, use either a safety
personnel to evacuate to a safe distance.
for the radio pilot lamp. If the potential fuse long enough to permit personnel to
Under no circumstances shall the fuse
source of extraneous electricity is radar, reach protective shelter or a black
length be less than that required for a 2-
television, or microwave transmitters, powder squib initiated by an electric
minute burn time. Use appropriately
test the actual blasting circuit, including current controlled from a distance or
designed crimpers to affix fuses to
the blasting cap but without other protective structure. Tying two or more
detonators. Use only fuses small enough
explosives, for extraneous electricity. squibs together may be necessary to
in diameter to enter the blasting cap
Protect personnel performing such tests ensure ignition of the combustible train.
without forcing. All personnel, except
from the effects of an exploding blasting (vi) Burning solid propellants ignited
the fuse-actuator, shall move to the
cap. by squibs do not require combustible
(3) Test the blasting cap and its lead personnel shelter or leave the
materials.
wires for electrical continuity. The demolition area before ignition.
(vii) Evacuate sites of misfires for at
individual who removes the shunt (3) Servicing of destruction site. (i) least 30 minutes, after which two
should ground himself or herself by Vehicles transporting AE to burning or qualified persons shall approach the
grasping the blasting circuit wire prior demolition grounds shall meet the position of the explosives. One shall
to performing the operation in order to requirements of this part. No more than examine the misfire and the other shall
prevent accumulated static electricity two persons shall ride in the cab. No act as backup. The backup shall watch
from firing the blasting cap. one shall ride in the truck bed. the examination from a safe distance,
(4) Assure the blasting circuit wires (ii) The contractor should unload behind natural or artificial barriers or
are shorted and grounded at the power vehicles immediately then move the other obstructions for protection. The
source and connect the blasting cap lead vehicle from the burning or demolition backup shall follow contractor
wires to the blasting circuit wires. area until completion of destruction procedures should an accident occur.
(5) Evacuate all but two persons from operations. The contractor should not (4) Burn loose, dry explosives without
the area. One person shall partially open AE containers before the vehicle combustible material, if the ground can
retreat and act as safety observer. The departs. remain uncontaminated. Check the
other person shall maintain physical (iii) The contractor shall place and ground for residual unburned explosive
possession of a safety device that locks open all AE containers set for for the safety of personnel and
out the blasting circuit (e.g., plug, key, destruction at least 10 ft (3.1 m) from operations. Do not pour volatile
pigtail, etc.) and shall place blasting cap each other and from explosives material flammable liquids, at any stage, over
onto charge. Both persons will then previously set out to prevent rapid explosives or the underlying
retreat to personnel shelter. transmission of fire if premature combustible material to accelerate
(6) Untwist blasting circuit wires at ignition occurs. burning.
power source and test for continuity. A (iv) Close and move empty containers (5) Always burn wet explosives on
galvanometer shall be used to test the to prevent charring or damage during beds of non-explosive materials.
firing circuit for electric continuity destruction of AE. Delivery vehicles (6) Burn explosive powders (e.g.,
before connection to the blasting shall pick up and remove empty RDX, HMX, etc.) in desensitized form to
machine. containers on the next trip. promote safe handling and prevent
(7) The individual assigned to make (i) Destruction by burning. (1) No detonation.
the connections shall confirm that mixing of an explosive with extraneous (7) Empty oil-covered pyrotechnic
everyone in the vicinity is in a safe material, other explosives, metal materials from containers into shallow
place before connecting the blasting powders, detonators, or similar items metal pans before burning. The
circuit wires to the power source and shall occur without authorization. contractor may burn explosives in the
signaling for detonation. This individual (2) Because of the danger of open containers.
shall not leave the blasting machine or detonation, do not burn AE in large (8) Prepare separate parallel beds of
its actuating device for any reason and quantities or in containers. explosives for burning by not less than

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00036 Fmt 4701 Sfmt 4702 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16073

150 ft (46 m). Take care to prevent The final incineration should take place which serve the entire installation. This
material igniting from smoldering at 1400 °F (760 °C), minimum. excludes offices located near and directly
residue or from heat retained in the (2) Operation of incinerators. (i) The serving explosives storage and operating
contractor shall not operate the feeding areas.
ground from previous burning
(c) Aircraft passenger transport operations.
operations. Saturate a burned-over plot conveyor until the incinerator
Passenger transport operations for the
with water, then check for hot spots, or temperature is high enough to ensure purpose of applying explosives Q–D tables
allow 24 hours to elapse before the next complete destruction. The contractor are defined as follows: Passenger transport
burn. should install temperature recording traffic involving military dependents and
(j) Destruction by detonation. (1) devices. civilians other than those employed or
Detonation of AE should occur in a pit (ii) To remove accumulated residue, working directly for DoD Components. The
of at least 4 ft (1.3 m) deep and be shut down and thoroughly cool the following are not considered passenger
incinerators. Make repairs only during transport operations.
covered by at least of 2 ft (0.6 m) of (1) Infrequent flights of base and command
earth. Place the components on their shutdown. Personnel entering the
incinerator to clean it shall wear administrative aircraft that may on occasion,
sides or in a fashion to enhance provide some space available travel to
complete destruction. Place demolition respiratory protection to prevent authorized personnel.
blocks on top of the AE and secure them inhalation of toxic dusts or fumes (e.g., (2) Travel of direct hire appropriated funds
with earth packed over them. Under mercury from tracers or lead from small- personnel employed by any DoD Component.
certain circumstances, the contractor arms ammunition). (d) Ammunition and explosives. Includes
may substitute bangalore torpedoes or (3) Operation of destruction chambers (but is not necessarily limited to) all items of
bulk HE for the demolition blocks. and deactivation furnaces. (i) Operation U.S.-titled (owned by the U.S. Government
of destruction chambers and through DoD Components) ammunition:
(Note: Detonations do not require a pit propellants, liquid and solid. pyrotechnics.
deactivation furnaces requires remote
at remote demolition areas.) high explosives. guided missiles. warheads.
control.
(2) Local regulations, atmospheric (ii) Operators shall not approach the devices. devices, and chemical agent
conditions, earth strata, etc. shall dictate unprotected side of the concrete substances and components presenting real
quantities destroyed at one time, both in or potential hazards to life, property and the
barricade, for any other reason, until environment. Excluded are wholly inert
pits and open sites. Considering these enough time has elapsed for explosives
variables, determine the acceptable items and nuclear warheads and devices,
in the chamber to react. Perform regular except for considerations of storage and
NEW based on criteria in Chapter 9, inspections to keep the feed-pipe chute stowage compatibility, blast, fire, and non-
DoD 6055.9–STD. The contractor should or conveyor obstruction free. nuclear fragment hazards associated with the
use this procedure for destruction of (iii) Feed components into the explosives.
fragmentation grenades, HE projectiles, chamber a few at a time. Post the exact (e) Ammunition and explosives aircraft
mines, mortar shells, bombs, photoflash number permitted at one time for each cargo area. Any area specifically designated
munitions, and HE rocket heads type of component in a place easily seen for:
separated from their motors. from the operator’s working position. (1) Aircraft loading or unloading of
(3) Search the surrounding area for (iv) Install guards on conveyor- transportation configured ammunition and
unexploded AE after each detonation. explosives.
feeding mechanisms to facilitate feeding (2) Parking aircraft loaded with
(4) In cases of misfires, follow and to prevent items from jamming or transportation configured ammunition and
established procedures. Wait a falling. explosives.
minimum of 30 minutes before (m) Support in disposal of waste. The (f) Ammunition and explosives area. An
approaching the site. contractor shall request instructions area specifically designated and set aside
(k) Destruction by neutralization. from the responsible ACO if, at end of from other portions of an installation for the
Methods of neutralization include contract, there is excess or residual development, manufacture, testing,
dissolving in water-soluble material or Government-owned AE and the contract maintenance, storage or handling of
chemical decomposition. The contractor does not address disposition. A ammunition and explosives.
is responsible for investigating which of contractor having difficulty safely (g) Auxiliary building. Any building
accessory to or maintained and operated to
these is most appropriate. The disposing of residual (scrap) AE related serve an operating building line, plant, or
contractor shall comply with all to contractual operations may request pier area. Explosive materials are not present
applicable local, state, and Federal help from the ACO. in an auxiliary building, such as
requirements. powerplants, change houses, paint and
§ 184.16 Construction and siting criteria.
(l) Destruction chambers and solvent lockers, and similar facilities.
incinerators. (1) General. The contractor Please refer to DoD 6055.9, Chapter 5 (h) Barricade. An intervening barrier,
should destroy small, loaded AE for guidance on facilities construction natural or artificial, of such type, size, and
components (e.g., primers, fuzes, and siting. construction as to limit in a prescribed
boosters, detonators, activators, relays, manner the effect of an explosion on nearby
Appendix A to 32 CFR Part 184— buildings or exposures.
delays, and all types of small-arms Glossary (i) Blast impulse. The product of the
ammunition) in destruction chambers or overpressure from the blast wave of an
This appendix defines terms and phrases
deactivation furnaces. The contractor used in this part, which are associated with explosion and the time during which it acts
should use explosives scrap incinerators ammunition, explosives, and other dangerous at a given point (that is, the area under the
for burning tracer and igniter materials. For those terms that are not found positive phase of the overpressure-time
compositions, small quantities of solid in this glossary please refer to DoD 6055.9– curve).
propellant, magnesium powder, sump STD for Q–D terminology. Because of (j) Blast overpressure. The pressure,
cleanings, absorbent cleaning materials, contractual reasons some terms of this part exceeding the ambient pressure, manifested
and similar materials. The contractor may be define differently. in the shock wave of an explosion.
(a) Aboveground magazine. Any open area (k) Cavern storage site. A natural cavern or
should equip destruction chambers and former mining excavation adapted for the
or any structure not meeting the
incinerators with suitable pollution requirements of an ECM which is used for storage of ammunition and explosives.
control devices (e.g., multiple chamber explosives storage. (l) Chamber storage site. An excavated
incinerators with thermal incinerator (b) Administration area. The area chamber or series or excavated chambers
afterburners) and concrete barricades. encompassing administrative buildings especially suited to the storage of

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00037 Fmt 4701 Sfmt 4700 E:\FR\FM\29MRP2.SGM 29MRP2
16074 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

ammunition and explosives. A cavern may be DoD property, occupational illness to DoD (ff) Exposed Site (ES). A location exposed
subdivided or otherwise structurally military or civilian personnel, injury to DoD to the potential hazardous effects (blast,
modified for use as a chamber storage site. military personnel on or off duty, injury to fragments, debris, and heat flux) from an
(m) Change house. A building provide with on-duty civilian personnel, damage to public explosion at a potential site (PES). The
facilities for employees to change to and from and private property, or injury and illness to distance to a PES and the level of protection
work clothes. Such buildings may be non-DoD personnel as a result of DoD required for an ES determine the quantity of
provided with sanitary facilities, drinking operations. ammunition or explosives permitted in a
fountains, lockers and eating facilities. (x) Donor/Acceptor. A total quantity of PES.
(n) Classification yard. A railroad yard stored ammunition may be subdivided into (gg) Firebrand. A projected burning or hot
used for receiving, dispatching, classifying, separate storage units in order to reduce the fragment whose thermal energy is transferred
and switching of cars. MCE, and, consequently, the Q–D of an to a receptor.
(o) Closure block. A protective constructive accidental detonation. The separation (hh) Fire-resistive. Combustible materials
feature designed to seal the entrance tunnel distances, with or without an intervening or structures that have been treated or have
to an underground storage chamber in the barrier, should be sufficient to ensure that a surface coverings designed to retard ignition
event of an explosion within the chamber. detonation does not propagate from one unit of fire spread.
Magae blocks are passive closures that are to another. For convenience, the storage unit, (ii) Flame-resistant. Combustible materials,
driven by the blast from a normally open to which detonates, is termed the donor and such as clothing, which have been treated or
a closed position. Klotz blocks area active nearby units, which may be endangered, are coated to decrease their burning
closures, operated by a hydraulic system to termed acceptors. The locations of the donor characteristics.
move from normally closed to an open and acceptor define the PES and ES, (jj) Flammable. A material which ignites
position (for access). respectively. easily and burns readily.
(p) Compatibility. Ammunition or (y) Earth-Covered Magazine (ECM). Any (kk) Fragmentation. The breaking up of the
explosives which may be stored or earth-covered structure that meets soil cover confining material of a chemical compound
transported together without significantly depth and soil requirements of DoD 6055.9– or mechanical mixture when an explosion
increasing either the probability of an STD. ECM has three possible structural takes place. Fragments may be complete
accident or, for a given quantity, the strength designations (‘‘7-Bar’’, ‘‘3-Bar’’, or items, subassemblies, pieces thereof, or
magnitude of the effects of such as accident. ‘‘Undefined’’). The strength of an ECM’s pieces of equipment or buildings containing
(q) Debris. Any solid particle thrown by an headwall and door(s) determines its items.
explosion or other strong energetic reaction. designation. (ll) General public. Persons not associated
For aboveground detonations, debris usually (z) Energetic liquid. A liquid, slurry, or gel, with the DoD installation’s mission or
refers to secondary fragments, which are consisting of or containing an explosive, operations such as visitors, to include guests
transported by a strong flow of detonation oxidizer, fuel, or combination of the above, of personnel assigned to the installation, or
gasses. may undergo, contribute to, or cause rapid persons not employed or contracted by DoD
(r) Debris trap. A protective construction exothermic decomposition, deflagration, or or the installation.
feature in an underground storage facility detonation. (mm) Hazardous fragment. A hazardous
which is designed to capture fragments and (aa) Engineering controls. Regulation of fragment is one having an impact energy of
debris from a detonation within the facility. facility operations through the use of prudent 58 ft-lb or greater.
This usually accomplished by using the engineering principles, such as facility (nn) Hazardous fragment density. A
inertia of the material to separate from the design, operation sequencing, equipment density of hazardous fragments exceeding
detonation gas stream. selection, and process limitations. one per 600 sq ft.
(s) Deflagration. A rapid chemical reaction (bb) Expansion chambers. A protective (oo) High explosive equivalent or explosive
in which the output of heat is enough to construction feature in an underground equivalent. The amount of a standard
enable the reaction to proceed and be storage facility which is designed to reduce explosive that, when detonated, will produce
accelerated without input of heat from the blast shock and overpressure exiting the a blast effect comparable to that which
another source. Deflagration is a surface facility by increasing the total volume of the results at the same distances from the
phenomenon with the reaction products complex. It may also function as a operating detonation or explosion of a given amount of
flowing away from the unreacted material area within the underground facility, as well the material or which performance is being
along the surface at subsonic velocity. The as a debris trap. evaluated. It usually is expressed as a
effect of a true deflagration under (cc) Explosion. A reaction of any chemical percentage of the total net weight of all
confinement is an explosion. Confinement of compound or mechanical mixture, which, reactive materials contained in the item or
the reaction increases pressure, rate of when initiated, undergoes a very rapid systems. For the purpose of these standards,
reaction and temperature, and may cause combustion or decomposition releasing large TNT is used for comparison.
transition into a detonation. volumes of highly heated gases that exert (pp) Hazard analysis. The logical,
(t) Demilitarize. Any disarming, pressure on the surrounding medium. In systematic examination of an item, process,
neutralizing, and any other action rendering addition, a mechanical reaction in which condition, facility, or system to identify and
ammunition and explosives innocuous or failure of the container causes the sudden analyze the probability, causes, and
ineffectual for military use. release of pressure from within a pressure consequences of potential or real hazards.
(u) Detonation. A violent chemical reaction vessel, for example, pressure rupture of a (qq) Holding yard. A location for groups of
with a chemical compound or mechanical steam boiler. Depending on the rate of energy railcars, trucks, or trailers used to hold
mixture evolving heat and pressure. A release, an explosion can be categorized as a ammunition, explosives, and dangerous
detonation which proceeds through the deflagration, a detonation, or pressure materials for interim periods before storage or
reacted material toward the unreacted rupture. shipment.
material at a supersonic velocity. The result (dd) Explosive. Any chemical compound or (rr) Hybrid propellants. A propellant
of the chemical reaction is exertion of mechanical mixture that, when subjected to charge using a combination of physically
extremely high pressure on the surrounding heat, impact, friction, detonation, or other separated solid and liquid (or jelled)
medium forming a propagating shock wave suitable initiation, undergoes a very rapid substances as fuel and oxidizer.
which is initially of supersonic velocity. A chemical change with the evolution of large (ss) Hygroscopic. A tendency of material to
detonation, when the material is located on volumes of highly heated gases which exert absorb moisture from its surroundings.
or near the surface of the found, is pressures in the surrounding medium. The (tt) Hypergolic. A property of various
characterized normally by a crater. term applies to materials which either combinations of chemical to self-ignite upon
(v) Dividing wall. A wall designed to detonate or deflagrate. contact with each other without a spark or
prevent, control, or delay propagation of an (ee) Explosives facility. Any structure or other external initiation.
explosion between quantities of explosives location containing ammunition and (uu) Inhabited buildings. Buildings or
on opposite sides of the wall. explosives excluding combat aircraft parking structures, other than operating buildings
(w) DoD mishap. An unplanned event or areas or ammunition and explosives aircraft occupied in whole or in part by human
series of events which results in damage to cargo areas. beings, both within and outside DoD

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00038 Fmt 4701 Sfmt 4700 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16075

establishments. They include but are not (ddd) Loading docks. Facilities, structures, sanitizing operations under the ‘‘Atomic
limited to schools, churches, residences or paved areas, designed and installed for Energy Act of 1954,’’ as amended, have been
(quarters), service clubs, aircraft passenger transferring ammunition and explosives completed (40 CFR 260.10).
terminals, stores, shops, factories, hospitals, between any two modes of transportation. (kkk) Navigable streams. Those parts of
theaters, mess halls, post offices, and post (eee) Lunchrooms. Facilities where food is streams, channels, or canals capable of being
exchanges. prepared or brought for distribution by food used in their ordinary or maintained
(vv) Inspection station. A designated service personnel. It may serve more than condition as highways of commerce over
location at which trucks and railcars one PES. A breakroom in an operating which trade and travel are or may be
containing ammunition and explosives are building may be used by personnel assigned conducted in the customary modes, not
inspected. to the PES to eat meals. including streams that are not capable of
(ww) Installation related personnel. (fff) Magazine. Any building or structure, navigation by barges, tugboats, and other
Military personnel (to include family except an operating building, used for the large vessels unless they are used extensively
members), DoD employees, DoD contractor storage of ammunition and explosives. and regularly for the operation of pleasure
personnel, and other personnel having either (ggg) Mass-detonating explosives. HE, boats.
a direct operational (military or other Federal black powder, certain propellants, certain (lll) NEQ. Net explosive quantity expressed
personnel undergoing training at an pyrotechnics, and other similar explosives, in kilograms.
installation) or logistical support (e.g., alone or in combination, or loaded into (mmm) NEW. Net explosive weight
vendors) relationship with installation various types of ammunition or containers, expressed in pounds.
activities. most of the entire quantity of which can be (nnn) Nitrogen padding (or Blanket). Used
(xx) Interchange yard. An area set aside for expected to explode virtually instantaneously to fill the void or ullage of a closed container
the exchange of railroad cars or vehicles when a small portion is subjected to fire, to with nitrogen gas to prevent oxidation of the
between the common carrier and DoD severe concussion or impact, to the impulse chemical contained therein and to avoid
activities. of an initiating agent, or to the effect of a formation of a flammable mixture, or to
(yy) Intraline distance. The distance to be considerable discharge of energy from maintain a nitrogen atmosphere in or around
maintained between any two operating without. Such an explosion normally will an operation of a piece of equipment.
buildings and sites within an operating line, cause severe structural damage to adjacent (ooo) Non-combustible. Not burnable.
of which at least one contains or is designed objects. Explosion propagation may occur (ppp) Non-DoD Components. Any entity
to contain explosives, except that the immediately to other items of ammunition (government, private, or corporate) that is not
distance from a service magazine for the line and explosives stored sufficiently close to a part of the Department of Defense.
to the nearest operating building may be not and not adequately protected from the (qqq) Operating building. Any structure,
be less than the intraline distance required initially exploding pile with a time interval except a magazine, in which operations
for the quantity of explosives contained in pertaining to manufacturing, processing,
short enough so that two or more quantities
the service magazine. handling, loading, or assembling of
must be considered as one for Q–D purposes.
(zz) K-Factor. The factor in the formula D ammunition and explosives are performed.
(hhh) Maximum Credible Event (MCE). In
= kW1⁄3 used in quantity-distance (rrr) Operating line. A group of buildings,
hazards evaluation, the MCE from a
determinations where D represents distance facilities or related work stations so arranged
hypothesized accidental explosion, fire, or
in feet and W is the net explosive weight in as to permit performance of the consecutive
pounds. The K-factor is a constant and agent release is the worst single event that is steps in the manufacture of an explosive, or
represents the degree of damage that is likely to occur from a quantity and in the loading, assembly, modification, and
acceptable. Typical constants range from 1.25 disposition of ammunition and explosives. maintenance of ammunition. Parallel
to 50. the lower the factor, the greater the The event must be realistic with a reasonable operating lines are adjacent buildings or
damage that is accepted. probability of occurrence considering the other facilities that process the same or
(aaa) Launch pads. The load-bearing base, explosion propagation, burning rate comparable ammunition or explosives,
apron, or platform upon which a rocket, characteristics, and physical protection given presenting parallel operating lines but may
missile, or space vehicle and its launcher rest to the involved. The MCE evaluated on this require physical separation or other control
during launching. basis may then be used as a basis for effects measures to ensure inventory control and
(bbb) Liquid propellants. Substances in calculations and casualty predictions. management of explosives limits.
fluid form (including cryogenics) used for (iii) Module. A barricaded area comprised (sss) Operational shield. A barrier
propulsion for operating power for missiles, of a series of connected cells with hard constructed at a particular location or around
rockets, ammunition and other related surface storage pads separated from each a particular machine or operating station to
devices (See DoD 6055.9–STD. For purposes other by barricades. protect personnel, material, or equipment
of this part, liquid fuels and oxidizers are (jjj) Military munitions. All ammunition from the effects of a possible localized fire or
considered propellants even when stored and products and components produced or used explosion.
handled separately. by for the U.S. Department of Defense or the (ttt) Parallel operating lines. Adjacent
(ccc) Loading density. Quantity of U.S. Armed Services for national defense and buildings or other facilities that process the
explosive per unit volume usually expressed security, including military munitions under same or comparable ammunition. or
as either pounds per cubic foot (lbs/ft3). As the control of the Department of Defense, the explosives presenting the same or
applied to underground storage facilities, U.S. Coast Guard, the U.S. Department of comparable hazards and using the same or
there are two types of loading densities used Energy, and the National Guard personnel. comparable process methods. Such
in Q–D calculations: The term ‘‘military munitions’’ includes ammunition or explosives processed at
(1) Chamber loading density is based on confined gaseous, liquid, and solid related work stations in the same building or
the NEW within an individual storage propellants, explosives, pyrotechnics, facility are not parallel operating lines but
chamber and the volume of the chamber chemical and riot control agents, smokes, may require physical separation or other
(Vch). incendiaries used by the DoD Components, control measures to ensure inventory control
(2) The calculations of air blast peak including bulk explosives and chemical and management of explosives limits.
pressures and IBD’s for explosions in warfare, mortar rounds, artillery ammunition, (uuu) Passenger railroad. Any steam,
underground storage facilities is based on the small arms ammunition, grenades, mines, diesel, electric, or other railroad which
shock-engulfed volume (Ve) of the facility. torpedoes, depth charges, cluster munitions carries passengers for hire.
This is the total volume filled by the and dispensers, demolition charges, and (vvv) Potential Explosive Site (PES). The
expanding gases at the time the blast front devices and components thereof. ‘‘Military location of a quantity of explosives that will
reaches the point of interest (e.g., the munitions’’ do not include wholly inert create a blast, fragment, thermal, or debris
entrance to an adjacent chamber). It includes items, improvised explosive devices, and hazard in the event of an accidental
volumes in any direction that the gases can nuclear weapons, nuclear devices, and explosion of its contents. Quantity limits for
enter, to a distance from the explosion source nuclear components thereof. However, that ammunition and explosives at a PES are
that equals the distance from the source to term does include non-nuclear components determined by the distance to an ES.
the point of interest. For IBD, the point of of nuclear devices, managed under the DoE’s (www) Prohibited area. A specifically
interest is the tunnel opening. nuclear weapons program, after all required designated area at airfields, seadromes, or

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00039 Fmt 4701 Sfmt 4700 E:\FR\FM\29MRP2.SGM 29MRP2
16076 Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules

heliports in which all ammunition and (2) Values of these parameters can usually strength on 2,500 psi (17.24 MPa) or more.
explosives facilities are prohibited. be estimated based on examinations of The capability to prevent simultaneous
(xxx) Propellant. Explosives compositions exposed rock outcrops or core samples from detonation is based on a limit of 425 net lb
used for propelling projectiles and rockets an exploratory drill hole. For the detailed (193 kg) of mass-detonating explosives. All
and to generate gases for powering auxiliary design of an underground storage facility storage plans and Q–D calculations shall be
devices. (maximum) span width, rock reinforcement, based on the total quantity of mass-
(yyy) Public highway. Any street, road, or etc.), standard rock mechanics classification detonating explosives on both sides of a
highway used by the general public for any systems should be used. dividing wall when the quantity of either
type of vehicular travel. (hhhh) Runway. Any surface on land side exceeds 425 lb (193 kg). Explosives
(zzz) Public traffic route. Any public street, designated for aircraft takeoff and landing should be 3 ft (0.91 m) or more from the wall.
road, highway, navigable stream, or operations, or a designated lane of water for (3) Retaining walls filled with earth or sand
passenger railroad (includes roads on a takeoff and landing operations of seaplanes. must be at least 5 ft (1.5 m) wide, with earth
military reservation that are used routinely (iiii) Secure explosives holding area. An or sand packed between concrete, masonry,
by the general public for through traffic). area designated for the temporary parking of or wooden retaining walls.
(aaaa) Pyrotechnic material. The explosive commercial carriers’ motor vehicles (qqqq) Support facilities. Ammunition and
or chemical ingredients, including powdered transporting DoD-owned Arms, Ammunition, explosives storage or operations that support
metals, used in the manufacture of military Explosives (AA&E). solely the functions of tactical or using units
pyrotechnics. (jjjj) Secure non-explosives holding area. as distinguished from storage depots or
(bbbb) Quantity-Distance (Q–D). The An area designated for the temporary parking manufacturing facilities.
quantity of explosive material and distance of commercial carriers’ motor vehicles (rrrr) Suspect truck and car site. A
separation relationships that provide defined transporting Categorized DoD Arms, designated location for placing trucks and
types of protection. These relationships are classified (SECRET or CONFIDENTIAL) railcars containing ammunition and
based on levels of risk considered acceptable materials, and Controlled Cryptographic explosives that are suspected of being in a
for the stipulated exposures and are tabulated Items (CCI). hazardous condition. These sites area also
in the appropriate Q–D tables. Separation (kkkk) Service magazine. A building of an used for trucks and railcars that may be in
distances are not absolute safe distances but operating line used for the intermediate a condition that is hazardous to their
are relative protective or safe distances. storage of explosives materials. contents.
Greater distances than those shown in the (llll) Single-chamber storage site. An (ssss) Taxiway or taxilane. Any surface
tables shall be used whenever practicable. excavated chamber with its own access to the designated as such in the basic airfield
Tables are contained in DoD 6055.9–STD and natural ground surface, not connected to any clearance criteria specified by a DoD
form a part. Component publication or Federal Aviation
other storage chamber.
(cccc) Ready ammunition storage. A Regulation.
(mmmm) Spall. Pieces of a material (and
location where ammunition is stored for (tttt) Toxic area. A defined area in which
the process by which they are formed) that
near-term tactical or training use. Generally, CG K or Class 6 chemical agents are handled
are broken lose from the surface of a parent
ready ammunition storage will supply one or or stored.
body by tensile forces created when a
more armament pads. (uuuu) Ufer ground. A Ufer Ground is an
compression shock wave travels through the earth electrode system which consists of
(dddd) Renovation. The work performed
body and reflects from the surface. For solid conductors encased along the bottom of
on ammunition, missiles, or rockets to restore
underground storage, spall normally refers to a concrete foundation footing or floor
them to a completely serviceable condition.
the rock broken loose from the wall of an indirect contact with the earth.
this usually involves the replacement of
acceptor chamber by the shock wave (vvvv) Unexploded ordnance. Explosive
unserviceable or outmoded parts.
transmitted through the rock from an ordnance which has been primed, fuzed,
(eeee) Risk. The product of the probability
explosion in a nearby donor chamber. armed or otherwise prepared for action, and
or frequency an accident will occur within a
(nnnn) Static missile battery. Deployed which has been fired, dropped, launched,
certain time and the accident’s consequences
ground-based missiles meant to be employed projected or placed in such. a. manner as to
to people, property or the environment.
(ffff) Robust munitions. These are in a non-mobile mission for offensive or constitute a hazard to operations,
munitions that meet two of the following defensive purposes. installations, personnel or material and
three criteria: (oooo) Static test stand. Locations on remains unexploded either by malfunction or
(1) Have a ratio of the explosive weight to which liquid propellant engines or solid design for any other cause.
empty case weight less than 1.00; propellant motors are tested in place. (wwww) Unit risk. The risk to personnel
(2) Have a normal wall thickness of at least (pppp) Substantial dividing wall. An and/or facilities that is associated with
0.4 inches; and interior wall designed to prevent debris, fragment and/or blast hazards that is
(3) Have a case thickness/NEW1⁄3>0.05 in/ simultaneous detonation of explosives on result of the detonation of a single round of
lb1⁄3. The following cartridges are by opposite sides of the wall. however, such ammunition.
definition, robust: 20mm, 25mm, and 30mm. walls may not prevent propagation (xxxx) Waste military munitions. Military
Other examples of robust ammunition (depending on quantities and types of munitions are waste when they are solid or
include MK 80 series bombs, M107 explosives involved). hazardous waste under the regulations (42
projectiles, Tomahawk and Harpoon (1) Substantial dividing walls are one way U.S.C. 9601, et seq. implementing the
penetration warheads. (Changed at 319th of separating explosives into smaller groups Resource Conservation and Recovery Act
Board Meeting). to minimize the results of an explosion and (RCRA) subpart EE of part 264 of 40 CFR),
(gggg) Rock strength. Strong, moderately allow a reduction in Q–D. These walls do not or defined as a waste under a DoD
strong, and weak rock are designators which protect personnel near the wall from high Component’s written procedures. Waste
provide a general classification of a rock explosives because the spalling of wall military munitions are defined in §266.202 of
body into one of these rankings is based on surface opposite the explosion source may 40 CFR). (Note: Decision about whether
the rock impedance factor: form dangerous secondary fragments. specific munitions are or are not waste
Rock impedance factor = p.c.10–6 (2) Reinforced concrete-type walls may should be made with reference to §260.10
and p = y/g vary in thickness, but will be at least 12 in and §§266.200 through 266.206 of 40 CFR).
(305 mm) thick. At a minimum, both will be (1) An unused military munition is a solid
where reinforced with rods at 1⁄2 in (12.7 mm) in waste when any of the following occurs:
y is the rock density, lbs/ft3 diameter. The rods will be spaced not more (A) The munition is abandoned by being
g is the gravitational acceleration, ft/sec2 than 12 in (305 mm) on centers horizontally disposed of, burned, detonated (except
p is mass density of the rock, lbs-sec2/ft4 and vertically, interlocked with footing rods during intended use), incinerated, or treated
c seismic velocity of the rock, ft/sec. and secured to prevent overturning. Rods on before disposal.
(1) The rock impedance factor will be 0.75 one face will be staggered with regard to rods (B) The munition is removed from storage
or more for strong rock. Between 0.75 and 0.5 on the opposite face and should be in a military magazine or other storage area
for moderately strong rock. and less than 0.5 approximately 2 in (50.8 mm) from each face. for the purpose of being disposed of, burned,
for weak rock. Concrete should have a design compressive or incinerated, or treated prior to disposal.

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00040 Fmt 4701 Sfmt 4700 E:\FR\FM\29MRP2.SGM 29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules 16077

(C) The munition is deteriorated or (A) When transported off range or from the (For further clarification see 40 CFR 266.202
damaged (e.g.< the integrity of the munition site of use, where the site of use is not a under ‘‘Definition of Solid Waste.’’).
is compromised by cracks, leaks, or other range, for the purposes of storage, (yyyy) Waiver. A written authority that
damage) to the point that it cannot be put reclamation, treatment, disposal, or treatment provides a temporary exception, permitting
into serviceable condition, and cannot before disposal. or, deviation from mandatory requirements of
reasonably be recycled or used for other (B) If recovered, collected, and then this Part. It generally is granted for short
purposes. or, disposed of by burial, or land filling either periods of time pending cancellation as a
(D) An authorized military official has on or off a range. result of termination of scheduled work
commitment or correction of the waived
declared the munition a solid waste. (Note: (C) For the RCRA (section 1004(27) of 40
conditions.
Declaration by and ‘‘authorized military CFR), a used or fired military munition is a
(zzzz) Wharf. A landing place or platform
official’’ that munitions are waste (Section solid waste, and therefore, is potentially built into the water or along the shore for the
266.202(b)(4) of 40 CFR) has a very limited subject to RCRA corrective action authorities berthing of vessels.
meaning and applicability. The only example under Section 3004(u) and 3004(v), and (aaaaa) Wharf yard. A yard that is close to
is a declaration by the Army in 1984 that 3008(h) of 40 CFR, the munition lands off- piers or wharves in which railcars or trucks
M55 rockets are waste. The environmental range and is not promptly rendered safe and/ are held for short periods of time before
Protection Agency expects that such a or retrieved. Any imminent and substantial delivery to the piers or wharves.
declaration would be in writing. A decision threats associated with any remaining Dated: March 15, 2005.
that munitions are unserviceable, or that they material must be addressed. If remedial Jeannette Owings-Ballard,
are to be transferred into a demilitarization action is not possible, the operator of the
OSD Federal Register Liaison Officer,
account does not, by itself, constitute a range must maintain a record of the event for
Department of Defense.
decision that the munitions are solid waste). as long as any threat remains. The record
(2) A used or fired military munition is a must include the type of munition and its [FR Doc. 05–5429 Filed 3–28–05; 8:45 am]
solid waste, it follows: location (to the extent the location is known). BILLING CODE 5001–06–P

VerDate jul<14>2003 21:15 Mar 28, 2005 Jkt 205001 PO 00000 Frm 00041 Fmt 4701 Sfmt 4700 E:\FR\FM\29MRP2.SGM 29MRP2

Vous aimerez peut-être aussi