Vous êtes sur la page 1sur 2

Federal Register / Vol. 70, No.

19 / Monday, January 31, 2005 / Notices 4843

located in a channel excavated in the proof of service on all persons listed on to serve a copy of that document on
right abutment; (5) a 40-acre reservoir the service list prepared by the each person in the official service list
(Tanasee Creek Lake), with a normal Commission in this proceeding, in for the project. Further, if an intervenor
reservoir elevation of 3,080 feet National accordance with 18 CFR 4.34(b), and files comments or documents with the
Geodetic Vertical Datum and a storage 385.2010. Commission relating to the merits of an
capacity of 1,340-acre-feet; (6) a 176- issue that may affect the responsibilities
Magalie R. Salas,
acre reservoir (Wolf Creek Lake), with a of a particular resource agency, the
normal reservoir elevation of 3,080 feet Secretary. intervenor must also serve a copy of the
National Geodetic Vertical Datum and a [FR Doc. E5–336 Filed 1–28–05; 8:45 am] document on that resource agency.
storage capacity of 10,040-acre-feet; (7) BILLING CODE 6717–01–P l. Description of Proposed Action: The
a concrete powerhouse containing one licensee seeks to surrender the license
generating unit having an installed because its lease of the project lands and
capacity of 8.75 MW. DEPARTMENT OF ENERGY facilities has been cancelled and it does
m. A copy of the application is not have the means or the intent to
available for review at the Commission Federal Energy Regulatory reacquire the project lands and to
in the Public Reference Room or may be Commission operate the project. The 500 kilowatt
viewed on the Commission’s Web site at project is currently not operating.
Notice of Application for Surrender of
http://www.ferc.gov using the m. Locations of Application: A copy
License andSoliciting Comments, of the application is available for
‘‘eLibrary’’ link. Enter the docket
Motions To Intervene, and Protests inspection and reproduction at the
number excluding the last three digits in
the docket number field to access the January 19, 2005. Commission in the Public Reference
document. For assistance, contact FERC Take notice that the following Room, located at 888 First Street NE,
Online Support at hydroelectric application has been filed Room 2A, Washington, DC 20426, or by
FERCOnlineSupport@ferc.gov or toll- with the Commission and is available calling (202) 502–8371. This filing may
free at 1–866–208–3676, or for TTY, for public inspection: also be viewed on the Commission’s
(202) 502–8659. A copy is also available a. Application Type: Surrender of Web site at http://www.ferc.gov using
for inspection and reproduction at the License. the ‘‘eLibrary’’ link. Enter the docket
address in item (h) above. b. Project No.: 8535–039. number, here P–8535, in the docket
You may also register online at c. Date filed: December 20, 2004. number field to access the document.
http://www.ferc.gov/docs-filing/ d. Licensee: Virginia Hydrogeneration For assistance, call toll-free 1–866–208–
esubscription.asp to be notified via e- and Historical Society, LC. 3676 or e-mail
mail of new filings and issuances e. Name of Project: Battersea Dam. FERCOnlineSupport@ferc.gov. For TTY,
related to this or other pending projects. f. Location: Located on the call (202) 502–8659. A copy is also
For assistance, contact FERC Online Appomattox River, in Chesterfield and available for inspection and
Support. Dinwiddie Counties, Virginia. reproduction at the address in item h.
n. Public notice of the filing of the g. Filed Pursuant to: Federal Power above.
initial development application, which Act, 16 U.S.C. 791(a)–825(r). n. Individuals desiring to be included
has already been given, established the h. Licensee Contact: Paul V. Nolan, on the Commission’s mailing list should
due date for filing competing Esq., 5515 North 17th Street, Arlington, so indicate by writing to the Secretary
applications or notices of intent. Under Virginia 22205, (703) 534–5509. of the Commission.
the Commission’s regulations, any i. FERC Contact: Regina Saizan, (202) o. Comments, Protests, or Motions to
competing development application 502–8765. Intervene: Anyone may submit
must be filed in response to and in j. Status of Environmental Analysis: comments, a protest, or a motion to
compliance with public notice of the This application is ready for intervene in accordance with the
initial development application. No environmental analysis at this time, and requirements of Rules of Practice and
competing applications or notices of the Commission is requesting Procedure, 18 CFR 385.210, 385.211,
intent may be filed in response to this comments, reply comments, and 385.214. In determining the appropriate
notice. recommendations for terms and action to take, the Commission will
All filings must (1) bear in all capital conditions. consider all protests or other comments
letters the title ‘‘COMMENTS’’, ‘‘REPLY k. Deadline for filing responsive filed, but only those who file a motion
COMMENTS’’, documents: comments, motions to to intervene in accordance with the
‘‘RECOMMENDATIONS,’’ ‘‘TERMS intervene, protests, and Commission’s Rules may become a
AND CONDITIONS,’’ or recommendations for terms and party to the proceeding. Any comments,
‘‘PRESCRIPTIONS;’’ (2) set forth in the conditions concerning the application protests, or motions to intervene must
heading the name of the applicant and shall be filed with the Commission by be received on or before the specified
the project number of the application to February 22, 2005. All reply comments comment date for the particular
which the filing responds; (3) furnish must be filed with the Commission by application.
the name, address, and telephone March 7, 2005. p. Filing and Service of Responsive
number of the person submitting the Comments, protests, and Documents—Any filings must bear in
filing; and (4) otherwise comply with interventions may be filed electronically all capital letters the title
the requirements of 18 CFR 385.2001 via the Internet in lieu of paper; see 18 ‘‘COMMENTS’’, ‘‘REPLY COMMENTS’’,
through 385.2005. All comments, CFR 385.2001(a)(1)(iii) and the ‘‘RECOMMENDATIONS FOR TERMS
recommendations, terms and conditions instructions on the Commission’s Web AND CONDITIONS’’, ‘‘PROTEST’’, OR
or prescriptions must set forth their site under the ‘‘e-Filing’’ link. The ‘‘MOTION TO INTERVENE’’, as
evidentiary basis and otherwise comply Commission strongly encourages applicable, and the Project Number of
with the requirements of 18 CFR 4.34(b). electronic filings. the particular application to which the
Agencies may obtain copies of the The Commission’s Rules of Practice filing refers. Any of the above-named
application directly from the applicant. and Procedure require all intervenors documents must be filed by providing
Each filing must be accompanied by filing documents with the Commission the original and eight copies to: Magalie

VerDate jul<14>2003 16:59 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 E:\FR\FM\31JAN1.SGM 31JAN1
4844 Federal Register / Vol. 70, No. 19 / Monday, January 31, 2005 / Notices

R. Salas, Secretary, Federal Energy j. Deadline for filing comments and The Lower Baker development
Regulatory Commission, 888 First final recommendations, terms and consists of the following existing
Street, NE., Washington, DC 20426. An conditions, and prescriptions is 60 days facilities: (1) A 285-foot-high by 550-
additional copy must be sent to the from the issuance of this notice; reply foot-long concrete thick arch dam
Director, Division of Hydropower comments are due 105 days from the impounding Lake Shannon with a
Administration and Compliance, issuance date of this notice. surface area of about 2,278 acres at a
Federal Energy Regulatory Commission, All documents (original and eight normal full pool elevation of 442.35 feet
at the above-mentioned address. A copy copies) should be filed with: Magalie R. msl; (2) a concrete intake equipped with
of any motion to intervene must also be Salas, Secretary, Federal Energy trashracks and gatehouse located at the
served upon each representative of the Regulatory Commission, 888 First dam’s left abutment; (3) a 1,410-foot-
Applicant specified in the particular Street, NE., Washington, DC 20426. long concrete and steel-lined pressure
application. Please put the project name ‘‘Baker tunnel; (4) a concrete surge tank near
q. Agency Comments: Federal, state, River Project’’ and project number ‘‘P– the downstream end of the pressure
and local agencies are invited to file 2150–033’’ on the first page of all tunnel; (5) a 90-foot-long, 66-foot-wide
comments on the described application. documents. concrete and steel powerhouse
A copy of the application may be The Commission’s Rules of Practice containing one turbine-generator unit,
obtained by agencies directly from the require all intervenors filing documents Unit No. 3 with an authorized capacity
Applicant. If any agency does not file with the Commission to serve a copy of of 79,330 kW; (6) a 750-foot-long, 115-
comments within the time specified for that document on each person on the kilovolt transmission line; (7) fish
filing comments, it will be presumed to official service list for the project. passage facilities including a 150-foot-
have no comments. One copy of an Further, if an intervenor files comments long by 12-foot-high barrier dam; and (8)
agency’s comments must also be sent to or documents with the Commission appurtenant facilities.
the Applicant’s representatives. relating to the merits of an issue that m. A copy of the application is
Magalie R. Salas, may affect the responsibilities of a available for review in the
particular resource agency, they must Commission’s Public Reference Room or
Secretary.
also serve a copy of the document on may be viewed on the Commission’s
[FR Doc. E5–341 Filed 1–28–05; 8:45 am]
that resource agency. Web site http://www.ferc.gov using the
BILLING CODE 6717–01–P
Comments and final ‘‘eLibrary’’ link. Enter the docket
recommendations, terms and number excluding the last three digits in
conditions, and prescriptions may be the docket number field to access the
DEPARTMENT OF ENERGY
filed electronically via the Internet in document. For assistance, contact FERC
Federal Energy Regulatory lieu of paper. The Commission strongly Online Support at
Commission encourages electronic filings. See 18 FERCOnlineSupport@ferc.gov or toll-
CFR 385.2001(a)(1)(iii) and the free at 1–866–208–3676, or for TTY,
Notice Soliciting Comments, and Final instructions on the Commission’s Web (202) 502–8659. A copy is also available
Recommendations, Terms and site http://www.ferc.gov under the ‘‘e- for inspection and reproduction at the
Conditions, and Prescriptions Filing’’ link. address in item h above.
k. This application has been accepted n. All filings must (1) bear in all
January 19, 2005. for filing. capital letters the title ‘‘COMMENTS,’’
Take notice that the following l. Project Description: The Baker River ‘‘REPLY COMMENTS,’’
hydroelectric application has been filed Project has two developments. The ‘‘RECOMMENDATIONS,’’ ‘‘TERMS
with the Commission and is available Upper Baker development consists of AND CONDITIONS,’’ or
for public inspection. the following existing facilities: (1) A ‘‘PRESCRIPTIONS;’’ (2) set forth in the
a. Type of Application: New Major heading the name of the applicant and
312-foot-high by 1,200-foot-long
License. the project number of the application to
concrete gravity dam impounding Baker
b. Project No.: 2150–033.
c. Date Filed: April 30, 2004. Lake with a surface area of about 4,980 which the filing responds; (3) furnish
d. Applicant: Puget Sound Energy. acres at a normal full pool elevation of the name, address, and telephone
e. Name of Project: Baker River 727.77 feet mean sea level (msl); (2) a number of the person submitting the
Hydroelectric Project. 122-foot-long, 59-foot wide concrete and filing; and (4) otherwise comply with
f. Location: On the Baker River, near steel powerhouse at the base of the dam the requirements of 18 CFR 385.2001
the Town of Concrete, in Whatcom and containing two turbine-generator units, through 385.2005. All comments,
Skagit Counties, Washington. The Unit No. 1 with an authorized capacity recommendations, terms and conditions
project occupies about 5,207 acres of of 52,400 kilowatts (kW) and Unit No. or prescriptions must set forth their
lands within the Mt. Baker-Snoqualmie 2 with an authorized capacity of 38,300 evidentiary basis and otherwise comply
National Forest managed by the U.S. kW; (3) a 115-foot-high by 1,200-foot- with the requirements of 18 CFR 4.34(b).
Forest Service. long earth and rock-fill dam, known as Agencies may obtain copies of the
g. Filed Pursuant to: Federal Power West Pass dike, located in a depression application directly from the applicant.
Act 16 U.S.C. 791(a)—825(r). about 1,500 feet north of Upper Baker Each filing must be accompanied by
h. Applicant Contact: Connie dam; (4) a 22-foot-high by 3,000-foot- proof of service on all persons listed on
Freeland, Puget Sound Energy, P.O. Box long earth-filled dike, known as the service list prepared by the
97034 PSE–09S Bellevue, WA 98009– Pumping Pond dike, which impounds Commission in this proceeding, in
9734; (425) 462–3556 or Depression Lake with a surface area of accordance with 18 CFR 4.34(b) and
connie.freeland@pse.com. 44 acres at a normal full pool elevation 385.2010.
i. FERC Contact: Steve Hocking, of 699 feet msl; (5) a water recovery You may register online at http://
Federal Energy Regulatory Commission, pumping station adjacent to Pumping www.ferc.gov/docs-filing/
888 First Street, NE., Washington, DC Pond; (6) fish passage facilities and fish esubscription.asp to be notified via
20426; (202) 502–8753 or spawning facilities; and (7) appurtenant email of new filings and issuances
steve.hocking@ferc.gov facilities. related to this or other pending projects.

VerDate jul<14>2003 16:59 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 E:\FR\FM\31JAN1.SGM 31JAN1