Vous êtes sur la page 1sur 3

1338 Federal Register / Vol. 70, No.

5 / Friday, January 7, 2005 / Rules and Regulations

Alternative Methods of Compliance AD is prompted by reports that airplanes (collectively called A300–
(AMOCs) interference was noticed during 600). That action, published in the
(h) The Manager, Seattle Aircraft production between the wire looms Federal Register on November 4, 2004
Certification Office, FAA, has the authority to located near the door hinge of rack (69 FR 64260), proposed to require
approve AMOCs for this AD, if requested in 107VU and the terminals of contactor relocating contactor 9DG located at rack
accordance with the procedures found in 14 9DG. We are issuing this AD to prevent (relay box) 107VU and adding protective
CFR 39.19.
possible short circuits in the wire looms sleeves to the two wire (cable) looms
Material Incorporated by Reference supplying the fuel pump systems and near the door hinge of rack 107VU.
(i) You must use Boeing Alert Service the pitot probe heating system, which
Comments
Bulletin 747–28A2033, Revision 1, dated could lead to a possible loss of function
December 18, 2003, to perform the actions of flight-critical systems and reduced We provided the public the
that are required by this AD, unless the AD controllability of the airplane. opportunity to participate in the
specifies otherwise. The Director of the development of this AD. No comments
DATES: This AD becomes effective
Federal Register approves the incorporation have been submitted on the proposed
by reference of this document in accordance February 11, 2005.
The incorporation by reference of AD or on the determination of the cost
with 5 U.S.C. 552(a) and 1 CFR part 51. For
copies of the service information, contact certain publications listed in the AD is to the public.
Boeing Commercial Airplanes, P.O. Box approved by the Director of the Federal Conclusion
3707, Seattle, Washington 98124–2207. Register as of February 11, 2005.
For information on the availability of this We have carefully reviewed the
ADDRESSES: For service information
material at the National Archives and available data and determined that air
identified in this AD, contact Airbus, 1
Records Administration (NARA), call (202) safety and the public interest require
741–6030, or go to http://www.archives.gov/
Rond Point Maurice Bellonte, 31707
adopting the AD as proposed.
federal_register/code_of_federal_regulations/ Blagnac Cedex, France. You can
ibr_locations.html. You may view the AD examine this information at the National Costs of Compliance
docket at the Docket Management Facility, Archives and Records Administration This AD affects about 167 airplanes of
U.S. Department of Transportation, 400 (NARA). For information on the U.S. registry. The required actions will
Seventh Street SW., Room PL–401, Nassif availability of this material at NARA,
Building, Washington, DC. take about 3 work hours per airplane, at
call (202) 741–6030, or go to: http:// an average labor rate of $65 per work
Issued in Renton, Washington, on
www.archives.gov/federal_register/ hour. Required parts will cost about
December 27, 2004. code_of_federal_regulations/ $290 per airplane. Based on these
Kevin M. Mullin,
ibr_locations.html. figures, the estimated cost of the AD for
You can examine the contents of this U.S. operators is $80,995, or $485 per
Acting Manager, Transport Airplane
AD docket on the Internet at http:// airplane.
Directorate, Aircraft Certification Service.
dms.dot.gov, or in person at the Docket
[FR Doc. 05–162 Filed 1–6–05; 8:45 am] Authority for This Rulemaking
Management Facility, U.S. Department
BILLING CODE 4910–13–P
of Transportation, 400 Seventh Street, Title 49 of the United States Code
SW., room PL–401, on the plaza level of specifies the FAA’s authority to issue
the Nassif Building, Washington, DC. rules on aviation safety. Subtitle I,
DEPARTMENT OF TRANSPORTATION
This docket number is FAA–2004– section 106, describes the authority of
Federal Aviation Administration 19527; the directorate identifier for this the FAA Administrator. Subtitle VII,
docket is 2004–NM–71–AD. Aviation Programs, describes in more
14 CFR Part 39 FOR FURTHER INFORMATION CONTACT: Tim detail the scope of the Agency’s
Backman, Aerospace Engineer, authority.
[Docket No. FAA–2004–19527; Directorate International Branch, ANM–116, FAA,
Identifier 2004–NM–71–AD; Amendment 39–
We are issuing this rulemaking under
13932; AD 2005–01–08]
Transport Airplane Directorate, 1601 the authority described in subtitle VII,
Lind Avenue, SW., Renton, Washington part A, subpart III, section 44701,
RIN 2120–AA64 98055–4056; telephone (425) 227–2797; ‘‘General requirements.’’ Under that
fax (425) 227–1149. section, Congress charges the FAA with
Airworthiness Directives; Airbus Model promoting safe flight of civil aircraft in
A310 Series Airplanes; and Model Examining the Docket
air commerce by prescribing regulations
A300 B4–600, B4–600R, and F4–600R The AD docket contains the proposed for practices, methods, and procedures
Series Airplanes, and Model C4 605R AD, comments, and any final the Administrator finds necessary for
Variant F Airplanes (Collectively Called disposition. You can examine the AD safety in air commerce. This regulation
A300–600) docket on the Internet at http:// is within the scope of that authority
AGENCY: Federal Aviation dms.dot.gov, or in person at the Docket because it addresses an unsafe condition
Administration (FAA), DOT. Management Facility office between 9 that is likely to exist or develop on
a.m. and 5 p.m., Monday through products identified in this rulemaking
ACTION: Final rule.
Friday, except Federal holidays. The action.
SUMMARY: The FAA is adopting a new Docket Management Facility office
airworthiness directive (AD) for certain (telephone (800) 647–5227) is located on Regulatory Findings
Airbus Model A310 series airplanes; the plaza level of the Nassif Building at We have determined that this AD will
and Model A300 B4–600, B4–600R, and the DOT street address stated in the not have federalism implications under
F4–600R series airplanes, and Model C4 ADDRESSES section. Executive Order 13132. This AD will
605R Variant F airplanes (collectively SUPPLEMENTARY INFORMATION: The FAA not have a substantial direct effect on
called A300–600). This AD requires proposed to amend 14 CFR part 39 with the States, on the relationship between
relocating contactor 9DG located at rack an AD for certain Airbus Model A310 the National Government and the States,
(relay box) 107VU and adding protective series airplanes; and Model A300 B4– or on the distribution of power and
sleeves to the two wire (cable) looms 600, B4–600R, and F4–600R series responsibilities among the various
near the door hinge of rack 107VU. This airplanes, and Model C4 605R Variant F levels of government.

VerDate jul<14>2003 16:17 Jan 06, 2005 Jkt 205001 PO 00000 Frm 00014 Fmt 4700 Sfmt 4700 E:\FR\FM\07JAR1.SGM 07JAR1
Federal Register / Vol. 70, No. 5 / Friday, January 7, 2005 / Rules and Regulations 1339

For the reasons discussed above, I Effective Date Bulletin A300–24–6081, Revision 01 (for
certify that this AD: (a) This AD becomes effective February 11, Model A300–600 series airplanes); both
2005. dated December 18, 2003; as applicable.
(1) Is not a ‘‘significant regulatory
action’’ under Executive Order 12866; Affected ADs Actions Accomplished per Previous Issue of
(2) Is not a ‘‘significant rule’’ under Service Bulletins
(b) None.
DOT Regulatory Policies and Procedures (g) Actions accomplished before the
Applicability effective date of this AD in accordance with
(44 FR 11034, February 26, 1979); and
(3) Will not have a significant (c) This AD applies to Airbus Model A310 Airbus Service Bulletin A310–24–2087; or
series airplanes, as listed in Airbus Service Airbus Service Bulletin A300–24–6081; both
economic impact, positive or negative, Bulletin A310–24–2087, Revision 01, dated dated June 7, 2002; are considered acceptable
on a substantial number of small entities December 18, 2003; and Model A300 B4–600, for compliance with the corresponding
under the criteria of the Regulatory B4–600R, and F4–600R series airplanes, and actions specified in paragraph (f) of this AD.
Flexibility Act. Model C4 605R Variant F airplanes
(collectively called A300–600), as listed in Alternative Methods of Compliance
We prepared a regulatory evaluation (AMOCs)
of the estimated costs to comply with Airbus Service Bulletin A300–24–6081,
Revision 01, dated December 18, 2003; (h) The Manager, International Branch,
this AD. See the ADDRESSES section for certificated in any category. ANM–116, Transport Airplane Directorate,
a location to examine the regulatory FAA, has the authority to approve AMOCs
evaluation. Unsafe Condition
for this AD, if requested in accordance with
(d) This AD was prompted by reports that the procedures found in 14 CFR 39.19.
List of Subjects in 14 CFR Part 39 interference was noticed during production
Air transportation, Aircraft, Aviation between two wire (cable) looms located near Related Information
the door hinge of rack (relay box) 107VU and (i) French airworthiness directive F–2003–
safety, Incorporation by reference, the terminals of contactor 9DG located at rack
Safety. 412, dated November 12, 2003, also
107VU. We are issuing this AD to prevent addresses the subject of this AD.
Adoption of the Amendment possible short circuits in the wire looms
supplying the fuel pump systems and the Material Incorporated by Reference
■ Accordingly, under the authority pitot probe heating system, which could lead (j) You must use the service information
delegated to me by the Administrator, to a possible loss of function of flight-critical that is specified in Table 1 of this AD to
systems and reduced controllability of the perform the actions that are required by this
the FAA amends 14 CFR part 39 as airplane.
follows: AD, unless the AD specifies otherwise. The
Compliance Director of the Federal Register approves the
PART 39—AIRWORTHINESS (e) You are responsible for having the incorporation by reference of those
DIRECTIVES actions required by this AD performed within documents in accordance with 5 U.S.C.
the compliance times specified, unless the 552(a) and 1 CFR part 51. For copies of the
■ 1. The authority citation for part 39 actions have already been done. service information, contact Airbus, 1 Rond
continues to read as follows: Point Maurice Bellonte, 31707 Blagnac
Relocation of Contactor and Addition of Cedex, France. For information on the
Authority: 49 U.S.C. 106(g), 40113, 44701. Protective Sleeves availability of this material at the National
(f) Within 12 months after the effective Archives and Records Administration
§ 39.13 [Amended] (NARA), call (202) 741–6030, or go to http:/
date of this AD, relocate contactor 9DG
■ 2. The FAA amends § 39.13 by adding located at rack 107VU and add protective /www.archives.gov/federal_register/
the following new airworthiness sleeves to the two wire looms located at the code_of_federal_regulations/
door hinge of rack 107VU, by doing all ibr_locations.html. You may view the AD
directive (AD): actions in accordance with the docket at the Docket Management Facility,
2005–01–08 Airbus: Amendment 39–13932. Accomplishment Instructions of Airbus U.S. Department of Transportation, 400
Docket No. FAA–2004–19527; Service Bulletin A310–24–2087, Revision 01 Seventh Street, SW., Room PL–401, Nassif
Directorate Identifier 2004–NM–71–AD. (for Model A310 series airplanes); or Service Building, Washington, DC.

TABLE 1.—MATERIAL INCORPORATED BY REFERENCE


Revision
Service bulletin Date
level

Airbus Service Bulletin A300–24–6081 ............................................................................................................. 01 December 18, 2003.


Airbus Service Bulletin A310–24–2087 ............................................................................................................. 01 December 18, 2003.

VerDate jul<14>2003 16:17 Jan 06, 2005 Jkt 205001 PO 00000 Frm 00015 Fmt 4700 Sfmt 4700 E:\FR\FM\07JAR1.SGM 07JAR1
1340 Federal Register / Vol. 70, No. 5 / Friday, January 7, 2005 / Rules and Regulations

Issued in Renton, Washington, on of Transportation, 400 Seventh Street proposed AD is addressed by the
December 27, 2004. SW., room PL–401, on the plaza level of repetitive inspections.
Kevin M. Mullin, the Nassif Building, Washington, DC. We agree with the commenter. The
Acting Manager, Transport Airplane FOR FURTHER INFORMATION CONTACT: repetitive inspections for cracking
Directorate, Aircraft Certification Service. Technical information: Ivan Li, required by AD 2001–16–02 are more
[FR Doc. 05–161 Filed 1–6–05; 8:45 am] Aerospace Engineer, Airframe Branch, extensive than the one-time inspection
BILLING CODE 4910–13–P ANM–120S, FAA, Seattle Aircraft required by this AD, and must be
Certification Office, 1601 Lind Avenue, repeated at intervals not to exceed 3,000
SW., Renton, Washington 98055–4056; flight cycles. Initiating those inspections
DEPARTMENT OF TRANSPORTATION telephone (425) 917–6437; fax (425) will find cracking before it reaches
917–6590. critical length; therefore, the one-time
Federal Aviation Administration Plain language information: Marcia inspection required by this AD is not
Walters, marcia.walters@faa.gov. necessary if the repetitive inspections
14 CFR Part 39 SUPPLEMENTARY INFORMATION: The FAA are currently being done. For airplanes
[Docket No. FAA–2004–18601; Directorate proposed to amend 14 CFR Part 39 with that are at or near the 10,000-flight-cycle
Identifier 2004–NM–34–AD; Amendment 39– an AD for certain Boeing Model 747 threshold, and have not been inspected
13933; AD 2005–01–09] series airplanes. That action, published per AD 2001–16–02, the purpose of this
in the Federal Register on July 15, 2004 AD is to close the gap between the
RIN 2120–AA64
(69 FR 42365), proposed to require a compliance time for the initial
Airworthiness Directives; Boeing one-time inspection for discrepancies of inspection required by AD 2001–16–02
Model 747–100, –200B, –200F, –200C, the frame web and inner chords on the (before the accumulation of 16,000 total
–100B, –300, –100B SUD, –400, –400D, forward edge frame of the number 5 flight cycles) and the one-time
–400F, and 747SR Series Airplanes main entry door cutout, and related inspection required by this AD. The AD
corrective action. requires that operators inspect the
AGENCY: Federal Aviation airplane at or before 10,000 total flight
Examining the Docket
Administration (FAA), DOT. cycles, or within the specified grace
ACTION: Final rule.
The AD docket contains the proposed period. Therefore, paragraph (g) of this
AD, comments, and any final AD has been changed to specify that
SUMMARY: The FAA is adopting a new disposition. You can examine the AD operators currently accomplishing the
airworthiness directive (AD) for certain docket on the Internet at http:// repetitive inspections required by AD
Boeing Model 747 series airplanes. This dms.dot.gov, or in person at the Docket 2001–16–02 are not required to
AD requires a one-time inspection for Management Facility office between 9 accomplish the one-time inspection
discrepancies of the frame web and a.m. and 5 p.m., Monday through required by this AD.
inner chords on the forward edge frame Friday, except Federal holidays. The
of the number 5 main entry door cutout, Docket Management Facility office Conclusion
and related corrective action. This AD is (telephone (800) 647–5227) is located on We have carefully reviewed the
prompted by a report of cracking of the the plaza level of the Nassif Building at available data, including the comment
frame web and inner chords on the the DOT street address stated in the that has been submitted, and
forward edge frame of the number 5 ADDRESSES section. determined that air safety and the
main entry door. We are issuing this AD Comment public interest require adopting the AD
to find and fix discrepancies of the with the change described previously.
frame web and inner chords, which We provided the public the We have determined that this change
could result in cracking, subsequent opportunity to participate in the will neither increase the economic
severing of the frame, and consequent development of this AD. We have burden on any operator nor increase the
rapid depressurization of the airplane. considered the single comment that has scope of the AD.
been submitted on the proposed AD.
DATES: This AD becomes effective Costs of Compliance
February 11, 2005. Request To Change Paragraph (g)
There are about 1,055 airplanes
The incorporation by reference of The commenter (the manufacturer) worldwide of the affected design, this
certain publications listed in the AD is asks that paragraph (g) of the proposed AD affects about 220 airplanes of U.S.
approved by the Director of the Federal AD be changed to read ‘‘For those registry. The inspection takes about 2
Register as of February 11, 2005. airplanes on which the repetitive work hours per airplane, at an average
ADDRESSES: For service information inspections required by AD 2001–16– labor rate of $65 per work hour. Based
identified in this AD, contact Boeing 02, amendment 39–12370, have been on these figures, the estimated cost of
Commercial Airplanes, PO Box 3707, done as of the effective date of this AD, the inspection required by this AD for
Seattle, Washington 98124–2207. You no further action is required.’’ The U.S. operators is $28,600, or $130 per
can examine this information at the commenter states that the inspection airplane.
National Archives and Records required by AD 2001–16–02 (referenced
Administration (NARA). For as a related AD in the proposed AD) is Authority for This Rulemaking
information on the availability of this a surface eddy current inspection and is The FAA’s authority to issue rules
material at NARA, call (202) 741–6030, more intensive than the detailed regarding aviation safety is found in
or go to: http://www.archives.gov/ inspection specified in the proposed Title 49 of the United States Code.
federal_register/ AD. The commenter notes that the Subtitle I, Section 106, describes the
code_of_federal_regulations/ repetitive inspections in AD 2001–16– authority of the FAA Administrator.
ibr_locations.html. 02 adequately detect any cracking prior Subtitle VII, Aviation Programs,
You can examine the contents of this to loss of residual strength of the chord. describes in more detail the scope of the
AD docket on the Internet at http:// The commenter adds that a nick or agency’s authority.
dms.dot.gov, or at the Docket gouge does not affect the crack growth This rulemaking is promulgated
Management Facility, U.S. Department rate, so the safety concern in the under the authority described in

VerDate jul<14>2003 16:17 Jan 06, 2005 Jkt 205001 PO 00000 Frm 00016 Fmt 4700 Sfmt 4700 E:\FR\FM\07JAR1.SGM 07JAR1