Académique Documents
Professionnel Documents
Culture Documents
Page | 1
CONTENTS:
1.
2.
3.
4.
Synopsis
Company Profile
About the Project
Introduction
ACKNOWLEDGEMENTS
Page | 2
First and foremost we would like to thank God for providing the immense opportunity to
have Industrial Training at GHV Pvt. Lmt.
We want to express our gratitude to Er. Suman Kumar (D.P.M. Planning & Billing), Er
MI Haq(D.P.M. Structure), Er. Gaurav Sharma (Site Engineer) , Er. Davendra Sahni, Er.
Pankaj Kumar, Er. Arun Kumar, Er. Gaurav Sharma, Er. SH Pande and Er. Tarun Kumar.
Our acknowledgements would be incomplete if we wouldnt thank our HOD Dr. SP
Guleria for encouraging us. The concept told by our Highway lecturer Er. Sanjay Kumar
has eased us to grasp the practical work going at the site. So, we want to thank them too.
Last but not the least we want to thank each other for being such a wonderful team
members.
1. SYNOPSIS:
In the following report we have explicated about Kiratpur-Nerchowk Express way NH21, needs of transport, techniques followed by developers of the projects, testing of
materials, construction of Four lane, construction pattern followed, instruments and
machinery used.
Page | 3
2. COMPANY PROFILE:
Page | 4
Page | 5
Supervision Consultant
Total length (flexible pavement)
VIL
IL&FS
84.375km (from km 104.298 to km
Road work
No. of minor bridges
No. of major bridges
No. of main tunnels
No. of toll plaza
Estimated project cost
Total cost for land acquisition
188.837)
67.3km
29
18
05
02
2356.20crore
537.37crore
1436.08crore
382.75crore
Page | 6
Share of IL&FS
Share for GHV Pvt Ltd.
1210.50crore
225.58crore
382.75crore
*DBFOT-Design-Build-Finance-Operate-Transfer
These projects involve designing and building the infrastructure, operating them for a specific period and
transferring the ownership of the project to the government after specific timeframe which runs normally
between 10 and 30 years.
Page | 7
4. Introduction
4.1 Importance of transportation
Development is related at improving the welfare of a society through appropriate social,
political and economic conditions. The expected outcomes are quantitative and qualitative
improvements in human capital (e.g. income and education levels) as well as physical
capital such infrastructures (utilities, transport, telecommunications). While in the previous
decades, development policies and strategies tended to focus on physical capital, recent years
has seen a better balance by including human capital issues. Irrespective of the relative
importance of physical versus human capital, development cannot occur without both as
infrastructures cannot remain effective without proper operations and maintenance while
economic activities cannot take place without an infrastructure base. Because of its intensive
use of infrastructures, the transport sector is an important component of the economy and a
common tool used for development. This is even more so in a global economy where
economic opportunities are increasingly related to the mobility of people, goods and
information. A relation between the quantity and quality of transport infrastructure and the
level of economic development is apparent. High density transport infrastructure and highly
connected networks are commonly associated with high levels of development. When
transport systems are efficient, they provide economic and social opportunities and
benefits that result in positive multipliers effects such as better accessibility to markets,
employment and additional investments. When transport systems are deficient in terms of
capacity or reliability, they can have an economic cost such as reduced or missed
opportunities and lower quality of life.
At the aggregate level, efficient transportation reduces costs in many economic
sectors, while inefficient transportation increases these costs. In addition, the impacts of
transportation are not always intended and can have unforeseen or unintended consequences.
For instance congestion is often an unintended consequence in the provision of free or low
cost transport infrastructure to the users. Transport also carries an important social and
environmental load, which cannot be neglected. Assessing the economic importance of
transportation requires a categorization of the types of impacts it conveys. These involve core
(the physical characteristics of transportation), operational and geographical dimensions.
Page | 8
development, a particular transport technology has been developed or adapted with an array of
impacts. Five major ways of economic development where a specific transport technology
created new economic, market and social opportunities can be suggested:
Seaports. Linked with the early stages of European expansion from the 16th to the 18th
centuries, commonly known as the age of exploration. They supported the early
development of international trade through colonial empires, but were constrained by
limited inland access.
Rivers and canals. The first stage of the industrial revolution in the late 18th and early
19th centuries was linked with the development of canal systems in Western Europe and
North America, mainly to transport heavy goods. This permitted the development of
rudimentary and constrained inland distribution systems.
Railways. The second stage of industrial revolution in the 19th century was linked with
the development and implementation of rail systems enabling more flexible and high
capacity inland transportation systems. This opened up substantial economic and social
opportunities through the extraction of resources, the settlement of regions and the
growing mobility of freight and passengers.
Roads. The 20th century saw the rapid development of comprehensive road
transportation systems, such as national highway systems, and of automobile
manufacturing as a major economic sector. Individual transportation became widely
available to mid income social classes, particularly after the Second World War. This was
associated with significant economic opportunities to service industrial and commercial
markets with reliable door-to-door deliveries. The automobile also permitted new forms
of social opportunities, particularly with suburbanization.
Airways and information technologies. The second half of the 20th century saw the
development of global air and telecommunication networks in conjunction with economic
globalization. New organizational and managerial forms became possible, especially in
the rapidly developing realm of logistics and supply chain management. Although
maritime transportation is the physical lynchpin of globalization, air transportation and IT
support the accelerated mobility of passengers, specialized cargoes and their associated
information flows.
Page | 9
The soft dirt track roads were never built to carry those sort of vehicles and were not able to
cope with this heavy traffic. So came the era of the Turnpike trusts - an imaginative new way
of getting the roads built and maintained. Turnpike trusts were made up of a group of people
who would get together and ask for permission from Parliament to take over a section of road,
or build a new one, for about 21 years. They would pay for its maintenance by collecting tolls
Page | 10
from the people who used them. These roads were commonly called turnpike roads. You can
still see some signs of the location of these roads where you see tiny houses on the edge of the
road. Where the man who collected the tolls lived. Many roads were improved this way and
the Turnpike trusts experimented with new ways to build roads, adding new methods of
making roads stronger and last longer so that wheeled traffic could travel more easily.
New Road construction techniques were developed by John MacAdam, Thomas Telford and
John Metcalfe. Each of them put forward the idea of building raised, cambered roads which
allowed water to drain off them as fast as possible. MacAdam's technique, which used tar
mixed with roadstone and called tarmacadam, became widely used and, eventually developed
into the modern method of road building.
Metcalf Construction
By the late 18th and early 19th centuries, new methods of highway construction had been
pioneered by the work of two British engineers, Thomas Telford and John Loudon McAdam,
and by the French road engineer Pierre-Marie-Jrme Trsaguet.
The first professional road builder to emerge during the Industrial Revolution was John Metcalf,
who constructed about 180 miles (290 km) ofturnpike road, mainly in the north of England, from
1765, when Parliament passed an act authorising the creation of turnpike trusts to build
Page | 11
new toll funded roads.He believed a good road should have good foundations, be well drained
and have a smooth convex surface to allow rainwater to drain quickly into ditches at the side. He
understood the importance of good drainage, knowing it was rain that caused most problems on
the roads. He worked out a way to build a road across a bog using a series of rafts made from
ling (a type of heather) and furze (gorse) tied in bundles as foundations. This established his
reputation as a road builder since other engineers had believed it could not be done. He acquired
a mastery of his trade with his own method of calculating costs and materials, which he could
never successfully explain to others.
Trsaguet Construction
Pierre-Marie-Jrme Trsaguet is widely credited with establishing the first scientific
approach to road building in France at the same time. He wrote a memorandum on his method
in 1775, which became general practice in France. It involved a layer of large rocks, covered
by a layer of smaller gravel. The lower layer improved on Roman practice in that it was based
on the understanding that the purpose of this layer (the sub-base or base course) is to transfer
the weight of the road and its traffic to the ground, while protecting the ground from
deformation by spreading the weight evenly. Therefore, the sub-base did not have to be a selfsupporting structure. The upper running surface provided a smooth surface for vehicles, while
protecting the large stones of the sub-base.
Trsaguet understood the importance of drainage by providing deep side ditches, but he
insisted on building his roads in trenches, so that they could be accessed from the sides, which
undermined this principle. Well-maintained surfaces and drains protect the integrity of the subbase and Trsaguet introduced a system of continuous maintenance, where a roadman was
allocated a section of road to be kept up to a standard.
Page | 12
Telford Construction
The surveyor and engineer Thomas Telford also made substantial advances in the engineering
of new roads and the construction of bridges. His method of road building involved the digging
of a large trench in which a foundation of heavy rock was set. He also designed his roads so
that they sloped downwards from the centre, allowing drainage to take place, a major
improvement on the work of Trsaguet. The surface of his roads consisted of broken stone. He
also improved on methods for the building of roads by improving the selection of stone based
on thickness, taking into account traffic, alignment and slopes. During his later years, Telford
was responsible for rebuilding sections of the London to Holyhead road.
Macadam Construction
It was another Scottish engineer, John Loudon McAdam, who designed the first modern roads.
He developed an inexpensive paving material of soil and stone aggregate (known
as macadam). His road building method was simpler than Telford's, yet more effective at
protecting roadways: he discovered that massive foundations of rock upon rock were
unnecessary, and asserted that native soil alone would support the road and traffic upon it, as
long as it was covered by a road crust that would protect the soil underneath from water and
wear. Also unlike Telford and other road builders, McAdam laid his roads as level as possible.
His 30-foot-wide (9.1 m) road required only a rise of three inches from the edges to the center.
Cambering and elevation of the road above the water table enabled rain water to run off into
ditches on either side.
Page | 13
Size of stones was central to McAdam's road building theory. The lower 200-millimetre
(7.9 in) road thickness was restricted to stones no larger than 75 millimetres (3.0 in). The upper
50-millimetre (2.0 in) layer of stones was limited to 20 millimetres (0.79 in) size and stones
were checked by supervisors who carried scales. He also wrote that the quality of the road
would depend on how carefully the stones were spread on the surface over a sizeable space,
one shovelful at a time.
McAdam directed that no substance that would absorb water and affect the road by frost should
be incorporated into the road. Neither was anything to be laid on the clean stone to bind the
road. The action of the road traffic would cause the broken stone to combine with its own
angles, merging into a level, solid surface that would withstand weather or traffic
Through his road-building experience McAdam had learned that a layer of broken angular
stones would act as a solid mass and would not require the large stone layer previously used to
build roads. By keeping the surface stones smaller than the tyre width, a good running surface
could be created for traffic. The small surface stones also provided low stress on the road, so
long as it could be kept reasonably dry. In practice, his roads proved to be twice as strong as
Telford's roads.
Although McAdam had been adamantly opposed to the filling of the voids between his small
cut stones with smaller material, in practice road builders began to introduce filler materials
such as smaller stones, sand and clay, and it was observed that these roads were stronger as a
result. Macadam roads were being built widely in the United States and Australia in the 1820s
and in Europe in the 1830s and 1840s.
Page | 14
Page | 15
from anywhere and take them to wherever they want to be dropped. Door-to-door collection and
delivery are possible in the case of road transport. But in the case of railways, the lines are fixed
and the railways do not have the flexibility of the roadways. Passengers and goods will have to
be taken to the railway stations.
3) Roads are a necessary complement to railways. India is a country of villages and it is only
roads which can connect villages and railways can connect towns. The railway stations will have
to be properly served by a network of feeder roads. Only through these roads the railways can
receive their passengers and goods. If railways are essential for the movement of goods and
people for long distances, road transport is essential for such movement for short distances.
Roads and railways are, therefore, not competitive but complementary.
4) Road transport is of particular advantage to the farmers. Good roads help the farmers to move
their products, particularly the perishable products; like vegetables, quickly to the mandis and
towns. Only by developing the road system, the farmer can be assured of a steady market for his
products. It is the road system which brings the villagers into contact with the towns and the new
ideas and the new systems from the towns.
5) Roads are highly significant for the defence of the country. For the movement of troops, tanks,
armoured cars, and field guns etc. roads are essential. The great importance given to the
construction of border roads to facilitate the movement of troops for the protection of the
northern borders against the Chinese aggression is an example of the great importance of roads
in the defence of the country.
Page | 16
6. Road transport is more flexible than the railway transport. Buses and trucks may be stopped
anywhere and at any time on the road for loading and unloading passengers and goods whereas
trains stop only at particular stations.
7. Perishable commodities like vegetables, fruits and milk are transported more easily and
quickly by roads than by railways.
In the present era planning is considered as a pre-requisite before attempting any development
programme. This is particularly true for any engineering work, as planning is the basic need for
any new project or an expansion programme. Thus highway planning is the basic need for
highway development. Particularly planning is of great importance when the funds available are
limited whereas the total requirement is much higher. This is actually the problem in all
developing countries like India as the best utilization of available funds has to be made in a
systematic and planned way. The objectives of highway planning are briefly given below:
i.
To plan a road net work for efficient and safe traffic operation, but at minimum cost. Here
the costs of construction, maintenance and renewal of pavement layers and the vehicle
ii.
iii.
Page | 17
iv.
v.
developments.
To work out financing system.
The planning of road projects is a process becom- ing more detailed stage by stage. At
each stage, the level of planning accuracy and decision- making is adapted in accordance
with land use planning. the planning process has four stages: feasibility study,
preliminary engineering plan- ning, final engineering planning and construction planning.
In minor road projects with limited impacts, planning and decision-making stages can be
combined. When a new highway or the improvement of an existing highway is planned,
the planning must be based on a land use plan meeting the requirements of the Land Use
and Building Act. Road planning phases are connected to land use planning as follows:
At the feasibility study phase, the necessity and timing of road projects are studied
at the same approximate planning level as the re- gional land use plan and the
plans.
Construction planning is related to the implementation of a road project and is
performed before and during construction.
In different phases of the planning process, alter- natives are reduced as road planning becomes
more accurate. As the process progresses, plan- ning can be more and more focused. For the
public and other parties to the plan- ning process, it is important to participate in the planning at
the right time. Planning can also be interrupted, if sufficient reasons no longer exist to continue
the planning process.
A road project is given its form and details during a planning process which becomes more and
more detailed in phases, adjusted to correspond to land use planning.
Page | 18
Dividing project-specific planning into phases makes specifying the order and time of road
project implementation easier.
A road project is given its form and details during a planning process which becomes more and
more detailed in phases, adjusted to correspond to land use planning.
1. Road planning
Transport system Planning:
o Transport system planning, road network planning,
development
of Environment
General Planning:
o Compiled and approved by the municipality. Road location is approved
in the plan.
Town Planning:
o Compiled and approved by the municipality.
3. feasibility study:
Planning a transport system involves interactive planning of land use and traffic. Thus, a
frame- work is created for the arrangement of different traffic modes and land use.
Planning gener- ates traffic policy objectives and goals, network plans for different traffic
modes, implementation strategies for the system and assessments of the impacts. More
detailed plans for pedestrian and bicycle traffic, public transport, parking etc. are made
when needed. transport system plans have been drawn up for many urban areas and some
provinces. In smaller urban areas, the planning emphasis is usually on traffic network
planning. For various purposes, feasibility studies can have different names and content.
Page | 19
The most common project-specific feasibility studies are the development study, needs
assessment and development/action plan. The starting points of a feasibility study are
existing land use and current road and traffic con- ditions. Societal development causes
changes in travel needs and traffic conditions. These changes are examined during the
feasibility study phase and the actions required to meet the goals set for the development
of traffic conditions are planned.
The outcome of the feasibility study is a project or several projects for which preliminary
examinations have been conducted of possible alternative actions, including the related
impacts and costs. During the feasibility study, the need for interaction varies according
to the nature of the project. Participation by municipalities and regional councils are
usually emphasized during co-operation. The decision to begin planning can be made
based on the feasibility study. Such a decision consists of the road authoritys statements
con- cerning the necessity, timing and further planning of development actions. Actions
deemed neces- sary proceed for further development and imple- mentation. The related
timetables are determined according to the funding available.
Outcomes of feasibility studies:
goals
alternatives
approximate actions
preliminary impact assessments
cost forecasts
Preliminary engineering Plan:
Preliminary engineering planning determines the approximate location of the
road, the roads con- nections to the existing and future road network and land
use, basic technical and traffic solutions and the principles underlying the
prevention of negative impacts to the environment. Planning is performed at a
level of detail which ensures that the plan is technically, financially and environmentally feasible. When legislation requires an environmental impact assessment
(EIA), the road projects environmental impact is assessed according to the Act on
Environmental Impact Assessment Procedure during the preliminary engineering
planning phase. The approval decision is made on the preliminary engineering
plan. The project can then be included in near-future implementation programmes
(the Finnish Transport Agencys operating and financial plan, the programmes of
Page | 20
Construction Plan:
Construction planning belongs to the road construction phase and covers the
drafting of the documents required for construction. In many cases, the contractor
is often responsible for drawing up the construction plan. Within limits of the final
engineering plan, interaction between road constructors and landowners and other
concerned parties continues throughout the entire planning and construction
phase. In minor projects, the final engineering and construction planning phases
can be combined. Compensation is paid for any damage caused to external
property during final engineering or construction planning and construction.
Outcome of construction planning:
Documents required in construction
1. Flexible pavement- Flexible pavements support loads through bearing rather than
flexural action. They comprise several layers of carefully selected materials designed to
gradually distribute loads from the pavement surface to the layers underneath. The design
ensures the load transmitted to each successive layer does not exceed the layers loadbearing capacity. A typical flexible pavement section is shown in Figure 1. Figure 2
depicts the distribution of the imposed load to the subgrade. The various layers
composing a flexible pavement and the functions they perform are described below:
a) Bituminous Surface (Wearing Course). The bituminous surface, or wearing course, is made
up of a mixture of various selected aggregates bound together with asphalt cement or other
bituminous binders. This surface prevents the penetration of surface water to the base course;
provides a smooth, well-bonded surface free from loose particles, which might endanger aircraft
Page | 22
or people; resists the stresses caused by aircraft loads; and supplies a skid-resistant surface
without causing undue wear on tires.
b) Base Course. The base course serves as the principal structural component of the flexible
pavement. It distributes the imposed wheel load to the pavement foundation, the subbase, and/or
the subgrade. The base course must have sufficient quality and thickness to prevent failure in the
subgrade and/or subbase, withstand the stresses produced in the base itself, resist vertical
pressures that tend to produce consolidation and result in distortion of the surface course, and
resist volume changes caused by fluctuations in its moisture content. The materials composing
the base course are select hard and durable aggregates, which generally fall into two main
classes: stabilized and granular. The stabilized bases normally consist of crushed or uncrushed
aggregate bound with a stabilizer, such as Portland cement or bitumen. The quality of the base
course is a function of its composition, physical properties, and compaction of the material.
c) Subbase. This layer is used in areas where frost action is severe or the subgrade soil is
extremely weak. The subbase course functions like the base course. The material requirements
for the subbase are not as strict as those for the base course since the subbase is subjected to
lower load stresses. The subbase consists of stabilized or properly compacted granular material.
d) Frost Protection Layer. Some flexible pavements require a frost protection layer. This layer
functions the same way in either a flexible or a rigid pavement.
e) Subgrade. The subgrade is the compacted soil layer that forms the foundation of the
pavement system. Subgrade soils are subjected to lower stresses than the surface, base, and
subbase courses. Since load stresses decrease with depth, the controlling subgrade stress usually
lies at the top of the subgrade. The combined thickness of subbase, base, and wearing surface
must be great enough to reduce the stresses occurring in the subgrade to values that will not
cause excessive distortion or displacement of the subgrade soil layer.
Page | 23
2. Rigid pavement- Rigid pavements normally use Portland cement concrete as the prime
structural element. Depending on conditions, engineers may design the pavement slab
with plain, lightly reinforced, continuously reinforced, prestressed, or fibrous concrete.
The concrete slab usually lies on a compacted granular or treated subbase, which is
supported, in turn, by a compacted subgrade. The subbase provides uniform stable
support and may provide subsurface drainage. The concrete slab has considerable flexural
strength and spreads the applied loads over a large area. Figure 1 illustrates a typical rigid
pavement structure. Rigid pavements have a high degree of rigidity. Figure 2 show how
Page | 24
this rigidity and the resulting beam action enable rigid pavements to distribute loads over
large areas of the subgrade. Better pavement performance requires that support for the
concrete slab be uniform. Rigid pavement strength is most economically built into the
concrete slab itself with optimum use of low-cost materials under the slab.
Page | 25
c) Stabilized Subbase. All new rigid pavements designed to accommodate aircraft weighing
100,000 pounds (45,000 kg) or more must have a stabilized subbase. The structural benefit
imparted to a pavement section by a stabilized subbase is reflected in the modulus of subgrade
reaction assigned to the foundation.
d) Frost Protection Layer. In areas where freezing temperatures occur and where frostsusceptible soil with a high ground water table exists, engineers must consider frost action when
designing pavements. Frost action includes both frost heave and loss of subgrade support during
the frost-melt period. Frost heave may cause a portion of the pavement to rise because of the
nonuniform formation of ice crystals in a frost-susceptible material (see Figure 3). Thawing of
the frozen soil and ice crystals may cause pavement damage under loads. The frost protection
layer functions as a barrier against frost action and frost penetration into the lower frostsusceptible layers.
e) Subgrade. The subgrade is the compacted soil layer that forms the foundation of the
pavement system. Subgrade soils are subjected to lower stresses than the surface and subbase
courses. These stresses decrease with depth, and the controlling subgrade stress is usually at the
top of the subgrade unless unusual conditions exist. Unusual conditions, such as a layered
subgrade or sharply varying water content or densities, may change the locations of the
controlling stress. The soils investigation should check for these conditions. The pavement above
the subgrade must be capable of reducing stresses imposed on the subgrade to values that are low
enough to prevent excessive distortion or displacement of the subgrade soil layer.
Since sub grade soils vary considerably, the interrelationship of texture, density, moisture
content, and strength of sub grade material is complex. The ability of a particular soil to resist
shear and deformation will vary with its density and moisture content. In this regard, the soil
profile of the sub grade requires careful examination. The soil profile is the vertical arrangement
of layers of soils, each of which may possess different properties and conditions.
Page | 26
Soil conditions are related to the ground water level, presence of water-bearing strata, and the
properties of the soil, including soil density, particle size, moisture content, and frost penetration.
Since the sub grade soil supports the pavement and the loads imposed on the pavement surface, it
is critical to examine soil conditions to determine their effect on grading and paving operations
and the need for under drains.
Page | 27
7.1 Design for traffic- The recommended method considers design traffic in
terms of the cumulative number of standard axles (80 kN) to be carried by
the pavement during the design life. Axle load spectrum data are required
where cementitious bases are used for evaluating the fatigue damage of
such bases for heavy traffic. Following information is needed for estimating
design traffic:
(i)
Page | 28
Page | 29
Axel load kN 4
)
64
Axel loadkN
)
80
Axel loadkN 4
)
148
AxelloadkN 4
Tridem axle with dualwheel on either side=(
)
224
VDF should be arrived at carefully by carrying out specific axle load surveys
on the existing roads. Minimum sample size for survey is given in Table 7.1.
Axle load survey should be carried out without any bias for loaded or
unloaded vehicles. On some sections, there may be significant difference in
axle loading in two directions of traffic. In such situations, the VDF should be
evaluated direction wise. Each direction can have different pavement
thickness for divided highways depending upon the loading pattern.
under various classes with class intervals of 10 kN, such as 10 kN, 20 kN and
30 kN for single, tandem and tridem axles respectively. 4.4.6 Where
sufficient information on axle loads is not available and the small size of the
project does not warrant an axle load survey, the default values of vehicle
damage factor as given in Table 7.2 may be used.
Table 7.2 Indicative VDF Values
Initial traffic volume in
terms of commercial n
vehicles per day
Rolling/Plai
n
Terrai
Hilly
0-150
1.5
0.5
150-1500
3.5
1.5
4.5
2.5
7.5
Distribution
Carriageway
of
Commercial
Traffic
over
the
Page | 31
(iv) Dual carriageway roads The design of dual two-lane carriageway roads
should be based on 75 per cent of the number of commercial vehicles in
each direction. For dual three-lane carriageway and dual four-lane
carriageway, the distribution factor will be 60 per cent and 45 per cent
respectively.
Where there is no significant difference between traffic in each of the two
directions, the design traffic for each direction may be assumed as half of the
sum of traffic in both directions. Where significant difference between the
two streams exists, pavement thickness in each direction can be different
and designed accordingly. For two way two lane roads, pavement thickness
should be same for both the lanes even if VDF values are different in
different directions and designed for higher VDF. For divided carriageways,
each direction may have different thickness of pavements if the axle load
patterns are significantly different.
365 [(1+r )n 1]
r
ADF
Where,
N = Cumulative number of standard axles to be catered for in the design in
terms of msa.
A = Initial traffic in the year of completion of construction in terms of the
number of Commercial Vehicles Per Day (CVPD).
D = Lane distribution factor (as explained in para 7.5.)
F = Vehicle Damage Factor (VDF). n = Design life in years.
r = Annual growth rate of commercial vehicles in decimal (e.g., for 5 per
cent annual growth rate, r = 0.05). The traffic in the year of completion is
estimated using the following formula:
x
A = P(1+r )
Page | 32
Where,
P = Number of commercial vehicles as per last count.
x = Number of years between the last count and the year of completion of
construction
As the stress transmitted through the road structure from the vehicles above spreads and lessens
with depth, stronger and more expensive materials are needed in the upper levels. Additionally,
the nearer the surface, the flatter the profile must be. This is obviously because an uneven
surface will be uncomfortable for vehicle occupants and will wear more quickly (each time a
vehicle hits a bump, it is in effect hammering the surface). These factors are the main reasons for
the layered construction of the road.Weight on any unbound material will compact it down with
time, as material is forced down and fills gaps. For this reason during construction of each layer,
artificial compaction is carried out. In fact, each of the layers of the road structure are usually
Page | 33
laid in layers themselves, with further compaction taking place each time. The life time of a road
can be reduced by greater than expected increase in traffic, though a certain amount of traffic
growth is allowed for when the road is designed. The only factor taken into account here is the
expected amount of commercial vehicles. This is because the damaging effect of an 8200kg axle
load is 100 times that of a 2700kg axle load, even the latter being greatly more than the axle load
of a private vehicle.
The Sub-base
The sub-base should be laid as soon as possible after final stripping to formation level, to prevent damage from
rain or sun baking which could cause surface cracks. The fact that this is required when roads are constructed,
emphasises the importance of backfilling excavations quickly and properly and preventing ingress of moisture
when roads have been excavated for utility works.
The most commonly used material for use in sub-bases is termed Type 1. This is an unbound material made
from crushed rock, crushed slag, crushed concrete, recycled aggregates or well burnt non-plastic shale. It
contains particles of various sizes, the percentage of each size being within a defined range. Up to 10% may be n
predefined and calculated range of material sizes contained means that once compacted, it
will resist further movement within its structure. In other words, it tends not to sink with time (though it will
sink if not compacted properly when laid).
Other materials used for the construction of sub-bases include bituminous-bound materials and concrete and
cement-bound materials, including wet-lean concrete.
Again, Type 1 is most commonly used. Other materials include Type 2 and Type 3. Slag bound material used
to be known as Wet Mix. It is a plant manufactured granular aggregate. It must be laid and compacted quickly,
as this must take place within 6 hours of the GBS and activator components. Various other materials are less com
Page | 34
All materials on arrival from the plant must be protected from the weather, as drying or wetting changes the com
must be spread evenly. They are laid in layers of 110mm - 225mm compacted thickness, the thickness of the laye
by various means including pegs and lines, sight rails and a guide wire. In initial build and reinstatement, the thic
layers depends on the compaction plant being used.
Bituminous base materials are either dense base macadam or rolled asphalt. Various concrete and cement
bound materials are used, the specifications for these being different to those applying for sub-base materials.
Surfacing
Both the surface course and binder course are included in the part of the road structure termed the surfacing. Occ
surfacing is laid as a single course. Normally, it is layed as two course binder and surface.
The binder course helps distribute the load of traffic above onto the base course, which is usually a weaker
material. It also provides a flat surface onto which the normally thinner surface course is laid. In new
construction, typical thickness is between 45mm and 105mm. Thickness may vary considerably where a new
binder course is laid to an existing road structure for strengthening purposes. Stone sizes used are 20, 28 or
40mm. The thicker the binder course, the larger the stone size. Materials used include open graded macadam,
dense coated macadam and rolled asphalt.Surface courses are laid in a wide range of bituminous materials,
ranging in thickness from 20 to 40mm. The material selected is dependent on the anticipated traffic intensity.
Hot rolled asphalt is made with high fines and asphaltic cement content with crushed rock, slag or gravel added.
thickness is 40mm with 20mm coated chippings rolled into the surface providing better skid resistance.
Stone mastic asphalt is not as susceptible to rutting as other surfaces and reduces surface noise. Normal layer
thickness is between 20mm and 40mm.
Drainage
DRAINAGE is VERY! VERY! VERY! IMPORTANT, both in relation to road pavement construction
and maintenance.
Page | 35
Good drainage will help to keep the water table (and strength) of the road pavement in equilibrium.
Water below the road pavement must be kept low and not be allowed to rise up into the
construction layers
The road pavement must be constructed so that it will drain in the event of a failure of the integrity of the
surfacing layers, i.e. if water is able to enter the road pavement there must be a path for it to exit.
Page | 36
Page | 37
Camber
Camber or cant is the cross slope provided to raise middle of the road surface in the transverse
direction to
drain o
rain water from road surface. The objectives of providing camber are:
Surface protection especially for gravel and bituminous roads
Sub-grade protection by proper drainage
Quick drying of pavement which in turn increases safety
Too steep slope is undesirable for it will erode the surface. Camber is measured in 1 in n or n%
(Eg. 1 in 50 or
Page | 38
2%) and the value depends on the type of pavement surface. The values suggested by IRC for
various categories
of pavement is given in Table 12:1 The common types of camber are parabolic, straight, or
combination of them as shown below:
Friction:
Friction between the wheel and the pavement surface is a crucial factor in the design of
horizontal curves and
thus the safe operating speed. Further, it also a_ect the acceleration and deceleration ability
of vehicles. Lack
of adequate friction can cause skidding or slipping of vehicles.
_ Skidding happens when the path traveled along the road surface is more than the
circumferential movement
of the wheels due to friction
_ Slip occurs when the wheel revolves more than the corresponding longitudinal movement
along the road.
Various factors that a_ect friction are:
_ Type of the pavement (like bituminous, concrete, or gravel),
_ Condition of the pavement (dry or wet, hot or cold, etc),
_ Condition of the tyre (new or old), and
_ Speed and load of the vehicle.
The frictional force that develops between the wheel and the pavement is the load acting
multiplied by a factor
called the coe_cient of friction and denoted as f. The choice of the value of f is a very
complicated issue since
it depends on many variables. IRC suggests the coe_cient of longitudinal friction as 0.35-0.4
depending on the speed and coecient of later friction as 0.15. The former is useful in sight
distance calculation and the
Page | 39
Unevenness:
Page | 40
Total Station
A total station is an electronic/optical instrument used in modern surveying and building
construction. The total station is an electronic theodolite (transit) integrated with an
electronic distance meter (EDM) to read slope distances from the instrument to a particular
point.
Robotic total stations allow the operator to control the instrument from a distance via remote
control. This eliminates the need for an assistant staff member as the operator holds the
reflector and controls the total station from the observed point.
Page | 41
fe
Grader
A grader, also commonly referred to as a road grader, a blade, a maintainer, or a motor
grader, is a construction machine with a long blade used to create a flat surface during
the grading process. Typical models have three axles, with the engine and cab situated
above the rear axles at one end of the vehicle and a third axle at the front end of the vehicle,
with the blade in between. In civil engineering, the grader's purpose is to "finish grade" (to
refine or set precisely) the "rough grading" performed by heavy equipment or engineering
vehicles such as scrapers and bulldozers. Graders are also used to set native soil
foundation pads to finish grade prior to the construction of large buildings. Graders can
produce inclined surfaces, to give cant(camber) to roads. In some countries they are used to
produce drainage ditches with shallow V-shaped cross-sections on either side of highways.
Page | 42
Excavator
Excavators are heavy construction equipment consisting of a boom, stick, bucket and cab on a
rotating platform known as the "house. The house sits atop an undercarriage
with tracks or wheels. A cable-operated excavator uses winches and steel ropes to accomplish
the movements. They are a natural progression from the steam shovels and often called power
shovels. All movement and functions of a hydraulic excavator are accomplished through the use
of hydraulic fluid, with hydraulic cylinders and hydraulic motors. Due to the linear actuation of
hydraulic cylinders, their mode of operation is fundamentally different from cable-operated
excavators.
Page | 43
Compactor
A compactor is a machine or mechanism used to reduce the size of waste material or soil
through compaction. A trash compactor is often used by a home or business to reduce the
volume of trash.Normally powered by hydraulics, compactors take many shapes and sizes.
In landfill sites for example, a large bulldozer with spiked wheels called a landfill compactor is
used to drive over waste deposited by waste collection vehicles (WCVs).
9. Testing of material
a. TESTS FOR CONCRETE:
a) CONCRETE TESTING MACHINE:
Page | 44
Aim: To determine the compressive strength of concrete specimens as per IS: 516 1959.
APPARATUS:
Page | 45
AGE AT TEST
Tests should be done at recognized ages of the test specimens, usually being 7 and 28 days. The
ages should be calculated from the time of the addition of water to the drying of ingredients.
NUMBER OF SPECIMENS
At least three specimens, preferably from different batches, should be taken for testing at each
selected age.
PROCEDURE:
i) The specimens, prepared according to IS: 516 - 1959 and stored in water, should be tested
immediately on removal from the water and while still in wet condition. Specimens when
received dry should be kept in water for 24hrs. Before they are taken for testing. The dimensions
of the specimens, to the nearest 0.2mm and their weight should be noted before testing.
ii) The bearing surfaces of the compression testing machine should be wiped clean and any loose
sand or other material removed from the surfaces of the specimen, which would be in contact
with the compression platens.
iii) In the case of cubical specimen, the specimen should be placed in the machine in such a
manner that the load could be applied to the opposite sides of the cubes, not to the top and the
bottom. The axis of the specimen should be carefully aligned with the centre of thrust of the
spherically seated platen. No packing should be used between the faces of the test specimen and
the steel platen of the testing machine. As the spherically seated block is brought to rest on the
specimen, the movable portion should be rotated gently by hand so that uniform seating is
obtained.
iv)The load should be applied without shock and increased continuously at a rate of
approximately 140kg/sq.cm/minute until the resistance of the specimen to the increasing load
breaks down and no greater load can be sustained. The maximum load applied to the specimen
should then be recorded and the appearance of the concrete and any unusual features in the type
of failure should be noted.
CALCULATION
The measured compressive strength of the specimen should be calculated by dividing the
maximum load applied to the specimen during the test by the cross - sectional area calculated
from the mean dimensions of the section and should be expressed to the nearest kg/sq.cm. An
Page | 46
average of three values should be taken as the representative of the batch, provided the individual
variation is not more than 15% of the average. Otherwise repeat tests should be done.
REPORTING OF RESULTS
The following information should be included in the report on each test specimen:
i) Identification mark
ii) Date of test
iii) Age of specimen
iv) Curing conditions, including date of manufacture of specimen
v) Weight of specimen
vi) Dimensions of specimen
vii) Cross-sectional area
viii) Maximum load
ix) Compressive strength
x) Appearance of fractured faces of concrete and type of fracture, if unusual.
Page | 47
Apparatus:
1 Moulds with Base Plate, Stay Rod and Wing Nut - These shall conform to 4.1, 4.3 and 4.4 of IS
: 9669 - 19801.
2 Collar - It shall conform to 4.2 of IS : 9669 - 1980$.
3 Spacer Disc - It shall conform to 4.4 of IS : 9669 - 1980$.
4 Metal Rammer - As specified in IS : 9198 - 19795.
5 Expansion Measuring Apparatus - The adjustable stem with per- forated plates and tripod shall
conform to 4.4 of IS : 9669 - 1980$.
6 Weights - This shall conform to 4.4 of IS : 9669 - 1480$.
7 Loading Machine - With a capacity of at least 5 000 kg and equipped with a movable head or
base which enables the plunger to penetrate into the specimen at a deformation rate of 125
mm/min- The machine shall be equipped with a load machine device that can read to suitable
accuracy.
NOTE - In the machine priming ring can also be used.
8 Penetration Plunger - This shall conform to 4.4 of IS : 9669 - 1980*.
9 Dial Gauges - Two dial gauges reading to 001 mm.
10 Sieves - 475 mm IS Sieve and 19 mm IS Sieve [ see IS : 460 ( Part 1 ) - 1985: I.
Page | 48
Undisturbed specimen
Attach the cutting edge to the mould and push it gently into the ground. Remove the soil from
the outside of the mould which is pushed in . When the mould is full of soil, remove it from
weighing the soil with the mould or by any field method near the spot.
Fix the extension collar and the base plate to the mould. Insert the spacer disc over the
base (See Fig.38). Place the filter paper on the top of the spacer disc.
Compact the mix soil in the mould using either light compaction or heavy compaction. For
light compaction, compact the soil in 3 equal layers, each layer being given 55 blows by the 2.6
kg rammer. For heavy compaction compact the soil in 5 layers, 56 blows to each layer by the
4.89 kg rammer.
Remove the collar and trim off soil.
Turn the mould upside down and remove the base plate and the displacer disc.
Weigh the mould with compacted soil and determine the bulk density and dry density.
Put filter paper on the top of the compacted soil (collar side) and clamp the perforated base plate
on to it.
Page | 49
Static compaction
Calculate the weight of the wet soil at the required water content to give the desired density
when occupying the standard specimen volume in the mould from the expression.
W =desired dry density * (1+w) V
Where W = Weight of the wet soil
w = desired water content
V = volume of the specimen in the mould = 2250 cm3 (as per the mould available in
laboratory)
Take the weight W (calculated as above) of the mix soil and place it in the mould.
Place a filter paper and the displacer disc on the top of soil.
Keep the mould assembly in static loading frame and compact by pressing the displacer disc till
the level of disc reaches the top of the mould.
Keep the load for some time and then release the load. Remove the displacer disc.
The test may be conducted for both soaked as well as unsoaked conditions.
If the sample is to be soaked, in both cases of compaction, put a filter paper on the top of the soil
and place the adjustable stem and perforated plate on the top of filter paper.
Put annular weights to produce a surcharge equal to weight of base material and pavement
expected in actual construction. Each 2.5 kg weight is equivalent to 7 cm construction. A
minimum of two weights should be put.
Immerse the mould assembly and weights in a tank of water and soak it for 96 hours. Remove
the mould from tank.
Note the consolidation of the specimen.
Page | 50
Seat the penetration piston at the center of the specimen with the smallest possible load, but in no
case in excess of 4 kg so that full contact of the piston on the sample is established.
Set the stress and strain dial gauge to read zero. Apply the load on the piston so that the
penetration rate is about 1.25 mm/min.
Record the load readings at penetrations of 0.5, 1.0, 1.5, 2.0, 2.5, 3.0, 4.0, 5.0, 7.5, 10 and 12.5
mm. Note the maximum load and corresponding penetration if it occurs for a penetration less
than 12.5 mm.
Detach the mould from the loading equipment. Take about 20 to 50 g of soil from the
top 3 cm layer and determine the moisture content.
c) SLUMP TEST:
APPARATUS:
i) Slump cone
ii) Tamping rod
PROCEDURE
i) The internal surface of the mould is thoroughly cleaned and applied with a light coat of
oil.
ii) The mould is placed on a smooth, horizontal, rigid and non- absorbent surface.
iii) The mould is then filled in four layers with freshly mixed concrete, each
approximately to one-fourth of the height of the mould.
iv) Each layer is tamped 25 times by the rounded end of the tamping rod (strokes are
distributed evenly over the cross- section).
Page | 51
v) After the top layer is rodded, the concrete is struck off the level with a trowel.
vi) The mould is removed from the concrete immediately by raising it slowly in the
vertical direction.
vii) The difference in level between the height of the mould and that of the highest point
of the subsided concrete is measured.
viii) This difference in height in mm is the slump of the concrete.
REPORTING OF RESULTS
The slump measured should be recorded in mm of subsidence of the specimen during the
test. Any slump specimen which collapses or shears off laterally gives incorrect result and
if this occurs, the test should be repeated with another sample. If in the repeat test also,
the specimen shears, the slump should be measured and the fact that the specimen
sheared, should be recorded.
Procedure:
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
Lay a straight edge across the top of the slump cone. Measure the amount
of slump in inches from the bottom of the straight edge to the top of the
slumped concrete at a point over the original center of the base. The slump
operation shall be completed in a maximum elapsed time of 2 1/2 minutes.
Discard concrete. DO NOT use in any other tests.
APPARATUS
Impact testing machine conforming to IS: 2386 (Part IV) - 1963
ii) IS Sieves of sizes - 12.5mm, 10mm and 2.36mm
iii) A cylindrical metal measure of 75mm dia. and 50mm depth
iv) A tamping rod of 10mm circular cross section and 230mm length, rounded at one end
v) Oven
PREPARATION OF SAMPLE
i) The test sample should conform to the following grading:
- Passing through 12.5mm IS Sieve 100%
- Retention on 10mm IS Sieve 100%
ii) The sample should be oven-dried for 4hrs. at a temperature of 100 to 110C and
cooled.
iii) The measure should be about one-third full with the prepared aggregates and tamped
with 25 strokes of the tamping rod. A further similar quantity of aggregates should be
added and a further tamping of 25 strokes given. The measure should finally be filled to
overflow, tamped 25 times and the surplus aggregates struck off, using a tamping rod as a
straight edge. The net weight of the aggregates in the measure should be determined to
the nearest gram (Weight 'A').
PROCEDURE
Page | 53
i) The cup of the impact testing machine should be fixed firmly in position on the base of
the machine and the whole of the test sample placed in it and compacted by 25 strokes of
the tamping rod.
ii) The hammer should be raised to 380mm above the upper surface of the aggregates in
the cup and allowed to fall freely onto the aggregates. The test sample should be
subjected to a total of 15 such blows, each being delivered at an interval of not less than
one second.
REPORTING OF RESULTS
i) The sample should be removed and sieved through a 2.36mm IS Sieve. The fraction
passing through should be weighed (Weight 'B'). The fraction retained on the sieve should
also be weighed (Weight 'C') and if the total weight (B+C) is less than the initial weight
(A) by more than one gram, the result should be discarded and a fresh test done.
ii) The ratio of the weight of the fines formed to the total sample weight should be
expressed as a percentage.
B Aggregate impact value = x 100% A
iii) Two such tests should be carried out and the mean of the results should be reported.
A sample proforma for the record of the test results is given in Annexure-III.
PROCEDURE
i) Prepare a cement paste by gauging the cement with 0.85 times the water required to
give a paste of standard consistency (see Para 1.2).
ii) Start a stop-watch, the moment water is added to the cement.
iii) Fill the Vicat mould completely with the cement paste gauged as above, the mould
resting on a non-porous plate and smooth off the surface of the paste making it level
with the top of the mould. The cement block thus prepared in the mould is the test
block.
Page | 54
The time period elapsing between the time, water is added to the cement and the time,
the needle fails to pierce the test block by 5.0 0.5mm measured from the bottom of
the mould, is the initial setting time.
REPORTING OF RESULTS
The results of the initial and the final setting time should be reported to the nearest
five minutes.
PRINCIPLE
Marshall stability is the resistance to plastic flow of cylindrical specimens of a
bituminous mixture loaded on the lateral surface. It is the load carrying capacity
of the mix at 60C and is measured in kg.
APPARATUS
i) Marshall stability apparatus
ii) Balance and water bath
SAMPLE
From Marshall stability graph, select proportions of coarse aggregates, fine
aggregates and filler in such a way, so as to fulfill the required specification. The
total weight of the mix should be 1200g.
PROCEDURE
i) Heat the weighed aggregates and the bitumen separately upto 170 C and 163
C respectively.
ii) Mix them thoroughly, transfer the mixed material to the compaction mould
arranged on the compaction pedestal.
iii) Give 75 blows on the top side of the specimen mix with a standard hammer
(45cm, 4.86kg). Reverse the specimen and give 75 blows again. Take the mould
with the specimen and cool it for a few minutes.
iv) Remove the specimen from the mould by gentle pushing. Mark the specimen
and cure it at room temperature, overnight.
Page | 55
REPORTING OF RESULTS
Plot % of bitumen content on the X-axis and stability in kg on the Y-axis to get
maximum Marshall stability of the bitumen mix.
PRINCIPLE
Flash Point - The flash point of a material is the lowest temperature at which the
application of test flame causes the vapours from the material to momentarily
catch fire in the form of a flash under specified conditions of the test.
Fire Point - The fire point is the lowest temperature at which the application of
test flame causes the material to ignite and burn at least for 5 seconds under
specified conditions of the test.
APPARATUS
i) Pensky-Martens apparatus
ii) Thermometer- Low Range: -7 to 110 Celsius, Graduation 0.5 Celsius
High Range: 90 to 370 Celsius, Graduation 2 Celsius
SAMPLE
The sample should be just sufficient to fill the cup upto the mark given on it.
PROCEDURE
A) FLASH POINT
i) Soften the bitumen between 75 and 100C
. Stir it thoroughly
to remove air bubbles and water.
ii) Fill the cup with the material to be tested upto the filling mark. Place it on the
bath. Fix the open clip. Insert the thermometer of high or low range as per
requirement and also the stirrer, to stir it.
iii) Light the test flame, adjust it. Supply heat at such a rate that the temperature
increase, recorded by the thermometer is neither less than 5C nor more than 6C
per minute.
iv) Open flash point is taken as that temperature when a flash first appears at any
point on the surface of the material in the cup. Take care that the bluish halo that
sometimes surrounds the test flame is not confused with the true flash.
Discontinue the stirring during the application of the test flame.
Page | 56
v) Flash point should be taken as the temperature read on the thermometer at the
time the flash occurs.
B) FIRE POINT
i) After flash point, heating should be continued at such a rate that the increase in
temperature recorded by the thermometer is neither less than 5C nor more than
6C per minute.
ii) The test flame should be lighted and adjusted so that it is of the size of a bead
4mm in dia.
REPORTING OF RESULTS
i) The flash point should be taken as the temperature read on the thermometer at
the time of the flame application that causes a distinct flash in the interior of the
cup.
ii) The fire point should be taken as the temperature read on the thermometer at
which the application of test flame causes the material to ignite and burn for at
least 5 seconds.
PRINCIPLE
It is the temperature at which the substance attains a particular degree of softening under
specified condition of the test.
APPARATUS
i)Ring and ball apparatus
ii) Thermometer - Low Range : -2 to 80 Celsius , Graduation 0.2 Celsius
- High Range: 30 to 200 Celsius , Graduation 0.5 Celsius
PREPARATION OF SAMPLE
i) The sample should be just sufficient to fill the ring. The excess sample should be cut off by a
knife.
Page | 57
ii) Heat the material between 75 and 100 Celsius.Stir it to remove air bubbles and water, and
filter it through IS Sieve 30, if necessary.
iii) Heat the rings and apply glycerine. Fill the material in it and cool it for 30 minutes.
iv) Remove excess material with the help of a warmed, sharp knife.
PROCEDURE:
A) Materials of softening point below 80 Celsius.
i) Assemble the apparatus with the rings, thermometer and ball guides in position.
ii) Fill the beaker with boiled distilled water at a temperature 5.0 0.5 o C per minute.
iii) With the help of a stirrer, stir the liquid and apply heat to the beaker at a temperature of 5.0
0.5 Celsius per minute.
iv) Apply heat until the material softens and allow the ball to pass through the ring.
v) Record the temperature at which the ball touches the bottom, which is nothing but the
softening point of that material.
B) Materials of softening point above 80 Celsius
The procedure is the same as described above. The only difference is that instead of water,
glycerine is used and the starting temperature of the test is 35C.
REPORTING OF RESULTS
Record the temperature at which the ball touches the bottom.
Page | 58
10.1 Cracking
Cracks are fissures resulting from partial or complete fractures of the pavement surface
and underlying layers. They can range from isolated single cracks to a series of
interconnected cracks spreading over the entire pavement surface.
There are a variety of factors leading to cracking of pavement surface. They include:
- deformation
- fatigue failure of the surfacing or pavement structure
- ageing of the surfacing
- reflection of movement of underlying layers
- shrinkage
- poor construction
The detrimental effects associated with the presence of cracks are manifold and include:
- loss of waterproofing
- loss of load spreading ability
- pumping and loss of fines from the base course
- loss of riding quality
- poor aesthetics
The various types of cracks (and the page number where they are described) are:
- Block Cracks
Description
Interconnected cracks forming a series of large polygons. Cell sizes are usually
greater than 200 mm and can exceed 3000mm (synonym ladder
cracks, map cracks)
Attributes
_ Predominant width of crack (mm)
_ Predominant cell width (mm)
_ Area affected (m2)
Possible causes
_ Hardening and shrinkage of bituminous mixture
_ Fatigue cracking in embrittled bituminous wearing course
Recommended remedies
_ Cold milling and resurfacing
_ Full depth reconstruction
_ Hot-in-place recycling
Page | 59
- Crocodile Cracks
Description
Interconnected or interlaced cracks forming a series of small polygons resembling a crocodile
hide. Usually associated with wheel paths and with resilient subgrade. Cell sizes are generally
less than 150 mm across butmay extend up to 300 mm (synonym alligator cracks, crazing)
Attributes
_ Predominant width of crack (mm)
_ Predominant cell width (mm)
_ Area affected (m2)
Possible causes
_ Saturated base or subgrade
_ Rupture of surface course due to traffic load, fatigue, ageing and brittleness of the binder
_ Inadequate pavement thickness
_ Developing from a surface showing block cracking
Recommended remedies
_ Full depth reconstruction removing the wet material and installing drainage
_ Deep inlay
_ Hot-in-place recycling
_ Skin patches or sealing with emulsion and sand can be used as a temporary repair
Page | 60
- Diagonal Cracks
Description
An unconnected crack which generally takes a diagonal line across a pavement
Attributes
_ Predominant width of crack (mm)
_ Length (m)
_ Area affected (m2)
Possible causes
_ Reflection of a shrinkage crack or joint in and underlying cemented material
_ Differential settlements between embankments, cuts or structures
_ Tree roots
_ Service installation
Recommended remedies
_ Fill and seal the crack with hot bitumen or other approved crack sealant
_ Cold mill and resurface
Page | 61
- Longitudinal Cracks
Description
Crack running longitudinally along the pavement. Can occur singly or as series of almost parallel
cracks. Some limited branching may occur
Attributes
_ Width of dominant crack (mm)
_ Length of dominant crack (m)
_ Spacing (mm)
_ Area affected (m2)
Possible causes
(a) Occurring singly :
_ Poor longitudinal joint construction
_ Differential movement in the case of pavement widening
_ Bitumen hardening
_ Incipient slips for roads on slopes or loss of support due to adjacent deep excavation
_ Reflection of cracking from joints of underlying concrete pavement
(b) Occurring as a series of almost parallel cracks :
_ Volume change of expansive clay subgrade
_ Differential settlement of subgrade, e.g. between cut and fill
_ Incipient slips for roads on slopes or loss of support due to adjacent deep excavation
Recommended remedies
_ Fill and seal the crack with hot bitumen or other approved crack sealant.
_ Cold mill and resurface.
_ Improvement of stability of the slopes.
_ Provision of sufficient lateral support to road excavations
Page | 62
10.2 Deformation
Deformation can be conceived as any change of the road structure, which leaves the road
surface in a shape different from the one intended. It may be due to load associated
(traffic) or non-load associated (environmental) influences.
Deformation is an important element of pavement condition as it affects serviceability
and may reflect structural inadequacies. It also has significant impact of vehicle
operating costs.
10.3 Potholes
Potholes are bowl-shaped depressions in the pavement surface developing from another
defect (cracking, delamination etc.), and resulting in allowing the entry of water and
Page | 63
disintegration with removal of material by traffic over weakened spots on the surface.
Possible causes
_ Developing from another defect suchas too thin a surfacing layer, too many fines etc., resulting
in disintegration with removal of material by traffic over weakened spots on the surface
_ Moisture entry to base course through a cracked pavement surface
Recommended remedies
_ Temporary repair involves cleaning the hole and filling it with either instant hole filling
material or bituminous wearing course material.
_ Permanent repair by square patching or hot-in-place recycling.
Page | 64