Académique Documents
Professionnel Documents
Culture Documents
BILL OF QUANTITIES
ITEM
NO.
I
ITEM DESCRIPTION
QUANTITY
UNIT
80.00
sq.m.
100.00
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
TOTAL
SITE WORKS
I - 1. Clearing and Lay-out
A. Materials
25 - 2" x 2" x 12' Coco Lumber
bd. ft.
18.00
1,800.00
Nylon #0.80
1.00
kgs.
350.00
350.00
3" CWN
7.00
kgs.
70.00
Sub-Total
490.00
2,640.00
B. Labor
1.00
day/s
1.00
350.00
350.00
Laborer
1.00
day/s
2.00
260.00
520.00
29.55
cu.m.
3.00
day/s
Sub-Total
I - 2. Structural Excavation
Column Footing, Wall Footing & Septic Vault
870.00
A. Labor
6.00
260.00
Sub-Total
4,680.00
4,680.00
I - 3. Embankment:
Filling, Grading & Compaction
A. Materials
Filling Materials
5.00
cu.m
350.00
Sub-Total
1,750.00
1,750.00
B. Labor
2.00
day/s
6.00
260.00
Sub-Total
I - 4. Soil Poisoning
3,120.00
3,120.00
1.00
lot
0.50
gals.
A. Materials
Termite Solution
1,600.00
Sub-Total
800.00
800.00
B. Labor
Laborer
II
1.00
day/s
1.00
260.00
260.00
Sub-Total
260.00
14,120.00
CONCRETE WORKS
15.46
cu.m.
Wall Footing, Columns & Footings, Floor Slab, Lintel Beams. Roof
Beam and Septic Tank
A. Materials
Portland Cement
Washed Sand
Washed Gravel
140.00
bags
280.00
39,200.00
8.00
cu.m.
900.00
7,200.00
16.00
cu.m.
1,000.00
16,000.00
Sub-Total
62,400.00
B. Labor
Page 1
Mason
7.00
day/s
2.00
350.00
4,900.00
Laborer
7.00
day/s
6.00
260.00
10,920.00
Sub-Total
15,820.00
78,220.00
ITEM
NO.
III
ITEM DESCRIPTION
QUANTITY
UNIT
1,436.84
Kgs.
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
TOTAL
A. Materials
10mm dia. x 6.0m RSB
197.00
length
729.29
140.00
35.00
length
186.48
210.00
7,350.00
55.00
length
521.07
360.00
19,800.00
15.00
10.00
kgs.
70.00
70.00
1,050.00
Steelman
7.00
day/s
2.00
350.00
Laborer
7.00
day/s
4.00
260.00
Hacksaw Blade
pcs.
Sub-Total
27,580.00
700.00
56,480.00
B. Labor
Productivity Rate: Cut, Bend and Place RSB (30.0 kgs./ man-day)
IV
4,900.00
7,280.00
Sub-Total
12,180.00
68,660.00
1.00
Lot
Materials
100 - 2" x 3" x 12' Coco Lumber
600.00
bd.Ft
18.00
10,800.00
67.00
bd.Ft
18.00
1,206.00
12.00
shts.
420.00
5,040.00
#4 CWN
15.00
kgs.
70.00
1,050.00
#2 CWN
5.00
kgs.
70.00
350.00
#1 CWN
5.00
kgs.
70.00
Sub-Total
350.00
18,796.00
Labor
Carpenter
2.00
day/s
2.00
350.00
1,400.00
Laborer
2.00
day/s
2.00
260.00
1,040.00
Sub-Total
2,440.00
MASONRY WORKS
21,236.00
125.44
sq.m.
V - 1. CHB Laying
A. Materials
Portland Cement
Washed Sand
75.00
bags
280.00
6.50
cu.m.
900.00
5,850.00
pcs.
21.00
27,930.00
1,330.00
21,000.00
236.00
pcs.
24.00
5,664.00
60.00
length
140.00
8,400.00
16.00
length
210.00
3,360.00
10.00
kgs.
70.00
Sub-Total
700.00
72,904.00
B. Labor
6.00
day/s
4.00
350.00
Laborer
6.00
day/s
4.00
260.00
Sub-Total
V - 2. Plastering
8,400.00
6,240.00
14,640.00
244.70
sq.m.
A. Materials
Portland Cement
Washed Sand
75.00
bags
280.00
8.00
cu.m.
900.00
Sub-Total
21,000.00
7,200.00
28,200.00
B. Labor
Page 2
Laborer
8.00
day/s
4.00
350.00
8.00
day/s
4.00
260.00
11,200.00
8,320.00
Sub-Total
19,520.00
135,264.00
ITEM
NO.
VI
ITEM DESCRIPTION
QUANTITY
STEEL WORKS
UNIT
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
TOTAL
1.00
lot
A. Materials
L 50mm x 50mm x 4.5 mm
54.00
pcs.
900.00
48,600.00
32.00
pcs.
700.00
22,400.00
2.00
pcs.
380.00
760.00
28.00
pcs.
650.00
18,200.00
Roof Frame
8.00
pcs.
310.00
2,480.00
20.00
kgs.
75.00
1,500.00
2.00
gals.
850.00
1,700.00
5.00
pcs.
1,150.00
Sub-Total
5,750.00
101,390.00
B. Labor
Welders
10.00
day/s
2.00
350.00
Laborer
10.00
day/s
3.00
260.00
Sub-Total
7,000.00
7,800.00
14,800.00
VII
10.00
day/s
1.00
900.00
9,000.00
10.00
day/s
10.00
day/s
16.00
60.00
9,600.00
0.25
200.00
500.00
Sub-Total
19,100.00
135,290.00
CEILING WORKS
A. Materials
68.72
sq.m.
27.00
pcs.
120.00
3,240.00
27.00
pcs.
110.00
2,970.00
54.00
pcs.
7.00
378.00
4.00
box
250.00
1,000.00
3.00
kgs.
90.00
270.00
18.00
pcs.
60.00
1,080.00
6.00
pcs.
160.00
960.00
24.00
pcs.
440.00
10,560.00
Sub-Total
20,458.00
B. Labor
6.00
day/s
2.00
350.00
4,200.00
Laborer
6.00
day/s
2.00
260.00
3,120.00
Sub-Total
7,320.00
VIII
6.00
day/s
1.00
900.00
5,400.00
6.00
day/s
16.00
60.00
5,760.00
6.00
day/s
0.25
200.00
300.00
Sub-Total
11,460.00
39,238.00
19.05
sq.m.
5.38
sq.m.
sets
4,829.00
9,658.00
sets
4,000.00
4,000.00
sets
1,000.00
2,000.00
sets
150.00
Sub-Total
1,350.00
17,008.00
B. Labor
Page 3
B.1. Installation of Doors (Productivity Rate: 2.69 sq. m./ manday
Carpenters
day/s
1.00
350.00
Laborer
day/s
1.00
260.00
Sub-Total
700.00
520.00
1,220.00
ITEM
NO.
ITEM DESCRIPTION
WINDOWS
QUANTITY
UNIT
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
TOTAL
13.67
sq.m.
2.00
sets
5,820.00
11,640.00
4.00
sets
4,000.00
16,000.00
2.00
sets
1,950.00
3,900.00
1.00
sets
1,100.00
1,100.00
2.00
sets
900.00
1,800.00
Sub-Total
34,440.00
B. Labor
IX
Skilled Worker
7.00
day/s
1.00
350.00
2,450.00
Laborer
7.00
day/s
1.00
260.00
1,820.00
Sub-Total
4,270.00
56,938.00
ROOFING WORKS
90.78
sq.m.
36.00
shts.
450.00
16,200.00
25.00
shts.
400.00
10,000.00
5.00
pcs.
220.00
1,100.00
10.00
pcs.
220.00
2,200.00
2.00
1,300.00
lit.
pcs.
450.00
900.00
2.00
2,600.00
200.00
pcs.
1.00
200.00
A. Materials
33,200.00
B. Labor
Installers/Welders
5.00
day/s
2.00
350.00
3,500.00
Laborer
5.00
day/s
3.00
260.00
3,900.00
Sub-Total
7,400.00
40,600.00
PLUMBING WORKS
1.00
Lot
2.00
pcs.
1,000.00
2.00
sets
235.00
Sub-Total
X-2 Sewer Line:
A. Materials
4" x 3.0m dia. PV Pipe
4.00
length
450.00
1,800.00
1,220.00
1,350.00
4.00
length
305.00
6.00
4.00
length
pcs.
225.00
45.00
180.00
10.00
pcs.
115.00
1,150.00
2.00
pcs.
50.00
100.00
2.00
pcs.
160.00
320.00
3.00
pcs.
145.00
435.00
pcs.
69.00
69.00
187.00
374.00
228.00
Page 4
1.00
2.00
pcs.
3.00
pcs.
76.00
Solvent Cement
1.00
pint
100.00
Sub-Total
100.00
7,326.00
ITEM
NO.
ITEM DESCRIPTION
QUANTITY
UNIT
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
TOTAL
1.00
sets
2,500.00
2,500.00
10.00
length
89.00
890.00
1.00
1.00
pcs.
pcs.
358.00
358.00
25.00
25.00
4.00
pcs.
25.00
100.00
3.00
pcs.
45.00
135.00
2.00
pcs.
50.00
100.00
pcs.
rolls
150.00
300.00
2.00
3.00
Teflon Tape
20.00
Sub-Total
60.00
4,468.00
B. Labor
XI
Plumber/ Mason
4.00
2.00
350.00
2,800.00
Laborer
4.00
2.00
260.00
2,080.00
Sub-Total
4,880.00
19,144.00
TILE WORKS
5.00
sq.m.
A. Materials
200.00
pcs.
30.00
6,000.00
3.00
kls.
95.00
285.00
Tile Trim
3.00
pcs.
100.00
Sub-Total
300.00
6,585.00
B. Labor
XII
Mason
4.00
day/s
1.00
350.00
1,400.00
Laborer
4.00
day/s
1.00
260.00
1,040.00
Sub-Total
2,440.00
9,025.00
ELECTRICAL WORKS
1.00
Lot
12.00
pcs.
40.00
480.00
7.00
pcs.
30.00
210.00
1.00
length
150.00
150.00
Screw Insulator
1.00
pc.
100.00
100.00
940.00
Sub-Total
XII. B. Electrical Wires
A. Materials
3.5mm2 THW Stranded
box
3,850.00
10.00
80.00
pcs.
m
12.00
120.00
17.00
1,360.00
3.00
pcs.
30.00
2.00
PVC Clamp
Flexible Tube 3/4" dia
Electrical Tape (Big)
7,700.00
90.00
9,270.00
Sub-Total
XII. C. Electrical Fixtures
A. Materials
Energy saving flourescent Bulb, 35 watts
4.00
pcs.
400.00
1,600.00
4.00
pcs.
175.00
700.00
2.00
pcs.
215.00
430.00
80.00
320.00
4.00
5.00
pcs.
pcs.
200.00
1,000.00
8.00
pcs.
75.00
600.00
1.00
pcs.
90.00
90.00
1.00
set
550.00
550.00
Circuit Breaker, 40 A 2P
1.00
set
300.00
300.00
Circuit Breaker, 20 A 2P
3.00
set
285.00
Page 5
Sub-Total
855.00
6,445.00
B. Labor
Electrician
7.00
day/s
1.00
350.00
2,450.00
Laborer
7.00
day/s
1.00
260.00
1,820.00
Sub-Total
4,270.00
20,925.00
ITEM
NO.
XIII
ITEM DESCRIPTION
PAINTING WORKS
QUANTITY
UNIT
374.70
sq.m.
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
TOTAL
A. Materials
Surface Primer (Red Oxide)
4.00
gals.
700.00
2,800.00
Concrete Putty
3.00
gals.
400.00
1,200.00
Concrete Neutralizer
4.00
gals.
350.00
1,400.00
Polituff
1.00
gals.
600.00
600.00
6.00
gals.
3,000.00
6.00
gals.
500.00
400.00
3,000.00
2,400.00
6.00
gals.
500.00
2.00
gals.
450.00
900.00
6.00
gals.
500.00
3,000.00
6.00
gals.
450.00
2,700.00
2.00
pints
110.00
220.00
2.00
pints
110.00
220.00
pints
110.00
110.00
1.00
1.00
pints
110.00
110.00
1.00
pints
110.00
110.00
Paint Thinner
6.00
1,500.00
4.00
gals.
pcs.
250.00
60.00
240.00
2.00
pcs.
40.00
80.00
4.00
set
60.00
240.00
1.00
set
91.00
91.00
1.00
set
45.00
45.00
Sandpaper #100
5.00
pcs.
30.00
150.00
Sandpaper #80
10.00
pcs.
60.00
600.00
Sub-Total
24,716.00
B. Labor
Painter
7.00
day/s
2.00
350.00
Laborer
7.00
day/s
3.00
260.00
Sub-Total
5,460.00
10,360.00
35,076.00
4,900.00
56.00
bags
280.00
15,680.00
Washed Sand
4.00
cu.m.
900.00
3,600.00
1/2 Gravel
0.50
cu.m.
1,000.00
500.00
56.00
bags
35.00
1,960.00
Sahara
4" x 8' x 16" CHB
200.00
pcs.
21.00
4,200.00
296.00
length
140.00
41,440.00
kgs.
pcs.
70.00
630.00
70.00
210.00
9.00
3.00
Sub-Total
Communal Tapstand:
1/2" dia. Gate Valve
68,220.00
1.50
sq.m.
2.00
pcs.
358.00
716.00
2.00
pcs.
150.00
300.00
2.00
length
89.00
178.00
1.00
pcs.
45.00
45.00
3.00
pcs.
25.00
75.00
3.00
pcs.
25.00
75.00
Teflon Tape
2.00
roll
20.00
40.00
Solvent Cement
2.00
pint
100.00
200.00
1/2"
Sub-Total
1,629.00
Page 6
B. Labor
Mason
7.00
day/s
3.00
350.00
Laborer
7.00
day/s
3.00
260.00
7,350.00
5,460.00
Sub - Total
12,810.00
82,659.00
ITEM
NO.
XV
ITEM DESCRIPTION
QUANTITY
UNIT
PROJECT SUPERVISION
1.00
Lot
Project Supervision
60.00
days
No. of
Crew/
Labor
1.00
RATE PER
DAY/ UNIT
COST
450.00
FACILITIES/AMENITIES
TOTAL
27,000.00
27,000.00
1.00
Lot
1.00
set
1,500.00
1,500.00
1.00
unit
3,001.00
3,001.00
6.00
unit
1,000.00
6,000.00
30.00
unit
400.00
12,000.00
3.00
sets
3,000.00
Blackboard
Child's Chairs
Height = 0.60m , Width = 0.30m , Length = 0.30m made of
12mm thick plywood with 25mm x 44mm wooden frame.
Low shelves (0.90m - 3 layers X 2.50m.)
Sub-Total
TOTAL FOR BASIC FACILITIES/AMENITIES
XVII
PROJECT SIGNAGE
1.00
lot
Project Signage
1.00
unit
7,500.00
7,500.00
7,500.00
9,000.00
31,501.00
31,501.00
DIRECT COST
621,536.00
Material Cost
30,560.00
Equipment Rental
Labor Cost:
94,900.00
a. Skilled
75,400.00
b. Unskilled
822,396.00
Sub-Total A
B
INDIRECT COST
139,808.00
41,120.00
VAT (5%)
180,928.00
Sub-Total B
TOTAL (A+B)
1,003,324.00
ADD: Contingency
1,003,324.00
1,003,324.00
Prepared:
Approved:
Engineer III
Page 7