Vous êtes sur la page 1sur 22



METHOD STATEMENT
FOR
INSTALLATION AND TESTING OF ABOVE GROUND
DRAINAGE PIPE WORKS

Project Name : PROPOSED 2B + G + 7 STOREY


RESIDENTIAL BUILDING
Location : DOHA QATAR
Document No. : TAK / LMRG / MS M002
Revision : 00

00
Rev
Signature :

Comments

Prepared

Checked

Reviewed

Approved

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
2

OF

Table of Contents
1. Scope
2. Related Documents
3. Definitions and Abbreviations
4. Plant and Equipment
5. Material
6. Material delivery, inspection,storage,handling and protection
7. Construction Sequence and Methodology
8. Inspection and testing
9. Responsibilities
10. Safety
11. Attachments

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS

1.0

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
3

OF

12.
Scope:
This method statement details the method for storage, installation and testing of
internal piping for soil, waste and storm drainage system as per approved drawings
and project Specification.

2.0

RELATED DOCUMENTS
2.1

Reference
2.1.1
2.1.2
2.1.3
2.1.4

2.1.5
2.1.6
2.1.7
2.1.8

3.0

QCS 2010
Construction drawings
Approved shop drawings
Approved material submittals
MAT/DR/0001 0004
MAT/DR 007 - 0010
HSE plan
Inspection & Test Plans (ITP)
TAK LMRG - ITP M 002
Risk Assessment TAK-RISK-015
Project Specification - PART A Section 4 Project Specification for
Soil, Waste, Vent and storm water system

DEFINITIONS & ABBREVIATIONS


3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.11
3.12
3.13
3.14
3.15
3.16
3.17
3.18
3.19

MS Method of Statement
ITP Inspection & Test Plan
PPE Personal Protective Equipment
QC Quality Control
QCS Qatar National Construction Standards
RA - Risk Assessment
TBT Tool Box Talk
PM - Project Manager
PE Project Engineer (Mechanical)
SE Site Engineer
QCE Quality Control Engineer
FM Foreman
SIR Site Inspection Request
SD Shop Drawing
MIR Material Inspection Request
MC Main Contractor
FD Floor drain
CO Clean out
RWO Rain Water Outlet
TEM Takyeef Electro Mechanical

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS

4.0

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
4

OF

Plant and Equipment

The following are the Plant and Equipment that shall be used:
o Cranes
o Plumbing / fitters tool box
o Tower lights
o Generator
o Scaffolds
o Ladders
o Electrical drilling machine
o Measurement tape / spirit level
o Hacksaw blade with frame
o Joining weld machine
o Line Dori
o Testing instruments
5.0

Material
Approved material shall be used, for detail please refer to the approved material
submittals

6.0

Material Delivery, Inspection, Storage, Handling and Protection


6.1

When off loading, pipes shall be lowered to the ground either manually or with
mechanical aid like crane depending on the quantity of the pipe and should not
be dropped to the ground. Refer Manufacturers instruction for transport,
handling and storage (Material submittal if applicable).

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
5

OF

6.2

Pipes shall be given adequate support at all times and shall be stacked on a flat
surface free from any sharp object.

6.3

Special care shall be taken by the storekeeper to protect the material from
physical damaged, distortion and exposure to sunlight.

6.4

Socket pipes shall be stacked in layers with sockets placed at alternate ends of
the stack and with the sockets protruding to avoid stable stacks and the
possibility of imparting a permanent set of the pipes.

6.5

Larger pipe sizes of thicker class shall always be placed at the bottom.

6.6

Store Keeper will be responsible for proper storage and maintenance of


records, as required.

6.7

On receipt of the material, QA/QC Engineer / Site Engineer shall inspect the
material internally and inspection shall be raised to the consultant for approval
through Material Inspection Request (MIR) form if found satisfactory.

6.8

Any non-conforming materials must be labeled and kept in identified area till
necessary CAPA is taken or till it is returned to the supplier.

6.9

Piping material will be inspected for quantity and quality and a formal material
inspection request will be raised for every first lot to the concerned for approval.
The material will be used to site only after getting approval for the same.

7.0 Construction Sequence and Methodology


7.1

Pre- Installation
7.1.1 Ensure that all safety requirements are in place in accordance with
project safety plan & Qatar Authority Health & Safety codes in practice.
7.1.2 Ensure that the latest revisions of the approved shop drawings are being
used. Note that any areas on the drawings are subject to modification
and work should not proceed in these areas until an updated drawing
has been obtained as revision with consultant approval.
7.1.3 Ensure that all plumbers and helpers are aware of the correct materials
handling and installation procedure to ensure best quality of
workmanship.
7.1.4 All the pipes and fittings shall be cleaned prior for installation.
7.1.5 Work shall be carried out by the site personnel under strict supervision
and guidance of the concerned Supervisors / Foreman (Plumbing) &
Site Engineer.
7.1.6 Ladders, step ladders and scaffoldings during construction will be used
at site as per the safety plan.

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
6

OF

7.1.7 Installation of pipes and fittings including shall be coordinated with


architectural, structural and MEP works for a fit for purpose installation.
Any deviation shall be intimated to the engineer for approval prior to
start of the work.
7.1.8 Supervisor / Foreman shall ensure equipment and correct tools are
available for installation to achieve compliance with the contract
requirements.

7.2

Installation
7.2.1 Prior to start of work, FM & SE assigned for the execution of the activity
shall be provided with latest approved drawings for site implementation.
7.2.2 Necessary sleeves and boxes shall be provided as per the approved
drawings.
7.2.3 For the above ground drainage piping installation make sure that
approved drawing and material submittal is available.
7.2.4 Ensure that the approved material is been used at site for the execution.
7.2.5 Ensure that all marking for the pipe lines shall be carried out by FM, with
reference to the floor plans and sectional details drawings. All routes
shall be carefully marked utilizing markers and care shall be taken over
to proceed. All the fixing lines shall be marked out on the out on the soffit
of the slabs from the bench marks, marked by the MC, above finished
floor levels in coordination with other services as per the approved shop
drawings/ coordinated drawings.
7.2.6 The pipe shall be cut to the required lengths and shall be chamfered at
the ends to remove burrs and smooth finish shall be done.
7.2.7 Remove all dust made by the surface preparation and any trace of
grease inside & outside the edge of the pipe with dry & clean cloth.
7.2.8 The pipes shall be fixed on the supports as per approved drawings.
7.2.9 Distance between the supports, size of rods etc are to be maintained as
per details given in approved SD.
7.2.10 All pipes shall be fixed in neatly arranged lines as possible, and
adequately pitched horizontal lines to allow the system to be properly
vented and drained.
7.2.11 A minimum slope shall be provided for the drainage piping as shown in
the drawing.
7.2.12 All pipes shall be installed at maximum possible height avoiding
structural interference so as to obtain maximum head room.
7.2.13 Pipe and fittings shall be examined for damage and the joint surfaces
and components shall be cleaned immediately before laying.
7.2.14 Before making the joint ensure that both pipe ends and the sealing ring in
the socket are clean.
7.2.15 Pipes will be laid in the opposite direction to the flow so that spigot end of
the pipe is drawn into the socket.

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
7

OF

7.2.16 For the push fit pipe joining ensure that both the pipe and the sealing ring
are clean. Lubricate both the pipe ends and the sealing ring in the socket
with silicone lubricant. (for further details please refer to the attachment
11.5)
7.2.17 Ensure that components to be joined (by push-fit method) are correctly
aligned and then push the spigot fully into the socket.
7.2.18 The joining of larger diameters is generally accomplished by applying
leverage to the following socket end using timber block to prevent
damage.
7.2.19 For the pipes joining with solvent cement, before joining make sure that
both the surfaces are clean.
7.2.20 The solvent cement shall be applied evenly over the mating surfaces of
both the pipe and socket.
7.2.21 The pipe shall be inserted to the socket with a slight twisting action to full
socket depth. Surplus cement shall be removed with a cloth.
7.2.22 The joint shall be handled after proper curing.
7.2.23 All the open ends of the installed pipes shall be plugged with end caps or
wrapped with PE sheets to prevent dry of dust and other foreign
particles.
7.2.24 Provide vent for each system as per the drawings.
7.2.25 Vertical piping will be installed parallel and close to the wall of the
building particularly for those in the shaft area.
7.2.26 Fix the approved floor trap for waste drainage system with pipes and
required fittings as per the approved shop drawings and connect to the
approved gully trap.
7.2.27Fix the approved uPVC waste line from the wash basin, bath tub and
bidet and connect to the floor trap as shown in the approved SD.
7.2.28Fix flexible connectors on the building expansion joints as per the
approved SD.
7.2.29 RWO shall be as per the approved type and installed with piping as per
the approved drawings.
7.2.30 All floor drains/ clean outs shall be installed as per the approved SD and
are accessible for proper maintenance and are coordinated with
architectural layouts.
7.2.31 The SE/ QCE shall ensure that the FD/ RWO are as per the approved
material submittal.
7.2.32 Where drainage pipes passing through fire rated walls / partitions,
provide collars as per project specification.
7.2.33 Ensure that the pipe works systems are at least 150mm away from any
electrical conduits, cable or wiring. Piping shall be avoided to run over
any Electrical Equipment or panel if it is unavoidable, protection shoul
be provided below the pipe work to protect the equipment as per the
standard requirements.
7.2.34 Ensure that identification and labeling of piping shall be provided as per
the project specification.

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS
8.0

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
8

OF

INSPECTION & Testing


8.1 After completing the installation of piping works gravity leak test is conducted to
ensure and prove the tightness of the joints and ensure there is no leakage in the
piping system.
8.2 The whole pipe work as one system and / or the part of the completed pipe work
as highlighted in the concerned area based on the concrete pour progress and site
conditions shall be tested in accordance with the following steps.
8.3 Test plugs are inserted at the lower end of the drain or sewer and at the head of
any connections with proper supports.
8.4 A suitable bend together with a vertical length of pipe is fitted at the head of the
sewer or drain to provide the necessary test head. The system is then filled with
water from top.
8.5 No section shall be tested to less than a 3- meters head of water. In testing
successive sections at least the upper 3-meters of the next preceding section shall
be tested so that no joint or pipe, except the upper most 3-meters of the whole
system shall have been subjected to a test of less than a 3- meters head of water
for 24 hours.
8.6 The sewer or drain under test should be filled with water for at least 4 hours before
inspection.
8.7 The loss of water over a period of 30 minutes should be measured by adding
known quantities of water every 10 minutes to maintain the original level of
standpipe. The loss water should not exceed the equivalent 1 liter per hour, per
linear meter, per meter of nominal diameter.
8.8 While system is under pressure, all the system is inspected thoroughly for any
leaks in joints. Pipe or fittings is found defective shall be corrected immediately by
replacing defective parts with new joints and materials.
8.3 After repairing any leaks and defects. After rectification retest piping portion thereof
until satisfactory results are obtained.
8.4 For the installation and testing necessary SIR shall be raised by TEM QA/QC as
per the ITP.
8.5 Test result shall be recorded and documented.

9.0

RESPONSIBILITIES
Please refer project quality plan for detailed job description.

10.0

SAFETY
10.1

All safety precautions shall be followed as per established project safety plan
and procedures.

10.2

Only experienced and skilled Technicians shall be engaged for carrying out
sanitary wares installation work.
The people involved in the installation shall use PPE such as Safety Helmets,
Safety Shoes, Gloves, etc. as required.

10.3

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

INSTALLATION AND
TESTING OF ABOVE
GROUND DRAINAGE PIPE
WORKS

10.4

11.0

M.S No.: TAK-LMRG.-MS-M002


Rev. 0
SERVICE:
Page No.:

Drainage
9

OF

Safety Officer shall check and ensure that all safety precaution are allowed

ATTACHMENTS
11.1
11.2
11.3
11.4
11.5

QC checklist for the installation of drainage pipes and fittings


Gravity test report
Inspection and Test plan (ITP) - TAK-LMRG-ITP-M002
Risk Assessment TAK-RISK-015
Manufacture recommendations

This document is the property of TAKYEEF Electromechanical. No part of this publication may be reproduced, stored in a
retrieval system in any form, or transmitted by any means,

ATTACHMENT11.1

1/1

TAKYEEF ELECTROMECHANICAL W.L.L

INSTALLATIONCHECKSHEET

P. O. Box 22471, DOHA, QATAR

INSTALLATIONOFABOVEGROUNDDRAINAGEPIPES

Fax: +974 4451 4411

Tel: +974 4451 4400

ITPNO.

PROJECTNAME

SERVICE

DRAWINGNO

Isapprovedmaterialsubmittalavailable

Isapproveddrawingsavailable

STATUS
YES NO

CHECKPOINTS

S.No.

TAKCL003

Isspecified/approvedmaterialavailableforconstructionandthe
sameisbeenapprovedbyconsultant.
VerifythecorrectsizeofA/Gdrainagepipe,accordingtoassociated
drawings.

Checkthepiperouteaccordingtoapplicabledrawing(s).

Verifythefallandinvertlevelsofthepipinginstallationwiththe
approveddrawings.

Checkthestraightnessandalignmentofpipewithconnectingpipes.

Checkthecleanoutsareprovidedasshowninthedrawing.

10

Checkwhetheracousticlaggingisprovidedasperdrawings.

11

Checkforpropersupportsasperthedrawings

12
13
14

REMARKS

InstallationofRWO,FDsandotherdrainsareinstalledasperthe
drawings
Verifytheabsenceofanyleakintheconnections/jointsasperthe
requirementsandisrecorded.
Identificationasperprojectrequirement

COMPANY

NAME

SubContractor
MainContractor
Consultant

1/1

SIGNATURE

ATTACHMENT11.2

1/1

TAKYEEF ELECTROMECHANICAL W.L.L

P. O. Box 22471, DOHA, QATAR

GRAVITYTESTREPORT

Tel: +974 4451 4400


Fax: +974 4451 4411

ITPNO.

PROJECTNAME

SERVICE

DRAWINGNO

S.No.

Area/Location

Timestart

TAKCL002

Timeend

STATUS
NO

YES

REMARKS

1
2
3
4
5

COMPANY

NAME

SubContractor
MainContractor
Consultant

1/1

SIGNATURE

ATTACHMENT11.3

Project Name:

INSPECTION AND TEST PLAN


INSTALLATION AND TESTING OF ABOVE GROUND DRAINAGE
PIPE WORKS
Client:
GULF TRADING AND CONTRACTING
Discipline:
Drainage works
Activit
Activity Description
y No.
1

Approval of Drawings

Approval of Material
Submittal
Approval of Method
statements
In-coming Material
Inspection / Storage and
Handling: Identification

3
4

Inspection of Above ground


drainage pipe works

Gravity test for piping


network

Final inspection including


identification

Consultant:
LACASA
ITP Sequence No.:

Contractor:
CHALLENGER

RESIDENTIAL BUILDING (2B+G+7)


BIN MAHMOUD

MEP Contractor :
TAKYEEF ELECTRO MECHANICAL

Rev. No.- 00

TAK-LMRG-ITP-M002
Reference Documents
Project Specification
Part A Section 1 # 7
Part A Section 1 # 7
Construction Drawings
Project Specification

Acceptance Criteria

Page: 1 of 1

Frequency

Verifying
Document

Inspection
TEM
CTC
LACASA

Drawing submittal approval as


Code A or Code B

Prior to start
of work.

Approved
Drawings

H/R

Approval of material submittal as


code A or code B.
Approval of method statement as
Code A or Code B.
Perform receiving inspection for
all permanent project material.
Comply with the approved
material submittal.

Prior to start
of work
Prior to start
work
For every first
delivery

Approved Material
submittal
Approved Method
statement
Material
Inspection
Request

H/R

H/R

W/H

Project specification
/Approved Drawing /
Method statement /
Manufacturer
Installation instruction
Project specification
/Approved Drawing /
Method statement / ITP

Inspection as per the attached


check list.

After
installation.

Site Inspection
Request (SIR) /
Check list

W/H

Check all joints for leakage. No


leakage allowed. Test duration:
as
per
the
specification
requirement.

After
installation for
all joints

Site Inspection
Request (SIR) /
Check list

W/H

Approved Drawing /
Method statement

As per the check list

Final stage
after
identification

Site Inspection
Request (SIR) /
Check list

W/H

Project Specification,
Approved Drawings `
Project Specification
and Approved material
submittal

For code use - H- Hold point Mandatory work cannot proceed without approval -W- Witness point (Optional) S- Surveillance or monitoring R- Review
TEM Takyeef Electro Mechanical, CTC - Challenger

ATTACHMENT11.4

HAZARDIDENTIFICATION&RISKASSESSMENT
Location(Department/Project):

2B+G+7StoreyResidentialBuildingonPlotNo.23090015/23090013/23090017
th

AssessmentNo.

TAKRISK015

Conducted&Preparedby:

BERNALDOC.MADRUGABA

Date:

4 June2015

RiskAssessmentRevision

002

Checkedby:

MGRABBANEE

Date:

NextReviewDate

4thDec.2015

INSTALLATIONOFU/G&A/GDRAINAGEPIPES

MAINACTIVITY

RISKANALYSIS
LIKELIHOOD

VALUE

LIKELIHOOD(L)XSEVERITY(S)=RISK(R)

SEVERITY

VALUE

LIKELIHOOD

SEVERITY
2

RISKASSESSMENTRESULTRANKING

RiskScore

Ranking

Unlikely

Minor

69

High(H)

Likely

Moderate

34

Medium(M)

Frequent

Catastrophic

12

Low(L)

No.

Hazard

Risk

Existing Control

Risk Analysis
(Existing
Control)
L

1.

Excavation

1. Collapse of
Excavation sides &
spoils
2. Cave-ins

1. Engineers & Supervisors must ensure


to conduct soil survey before
excavating any location to see if there
are any UG utilities and also to
determine soil quality &/or texture.
2. Provide slopes or install shoring to
prevent collapse of excavation sides
and observe 3 feet or 1 meter spoil
distance from edge of excavation.
3. Avoid super-impose loads.
4. Ensure to provide water control or
Socalo to prevent water from
entering the excavation area.

NOTE: For detailed definition of SEVERITY, LIKELIHOOD & RANKING, please refer to TAK-014

Whattodo?
Immediateattentionandactionrequired. Shallconsiderwhetherto
eliminateormodifytheactivity.(Stopthework)
Specificmonitoringproceduresrequired,managementresponsibility
mustbespecified.Shallconsiderwhatcanbedonetoeliminatethe
risktopreventanynegativeoutcomes.
Managethroughroutineprocedures.
Canproceedwiththeactivityasplanned

1st
Eval.

Required Additional Control Measures

1. Close supervision must be done by


site Engineers, Supervisors & Team
Leaders to ensure work is being done
as per plan.
2. Supervisor to assess the physical
condition and competence of persons
assigned for the job, duration of the
job and weather conditions.
3. Proper monitoring by HSE personnel
to ensure Safety Guidelines are being
observed or complied.
4. Hand digging must be done to check
UG utilities prior to using mechanical
means.

Risk Analysis
(Additional
Controls)
L

2nd
Eval.

FORM NO. TAK-014-002 REV. 1

Final Evaluation

HAZARDIDENTIFICATION&RISKASSESSMENT

2.

External works
&/or Exposure
under the heat of
sunlight.

3.

Use of fixed and


mobile scaffold

4.

Moving on the
platform

5.

Use of ladder
(straight and AType)

1. Dehydration
2. Heat stress (Heat
cramps, heat
exhaustion and
heat stroke)
3. Eye strain/damage
due to Ultraviolet
rays
4. Skin disease

Multiple body injury


due to collapse of
scaffold

Fall from height,

1.
2.

Fall from heights


Ladder fall or tipover

1. Ensure to provide temporary shade to


avoid direct sunlight exposure.
2. Ensure to provide appropriate PPE
such dark glasses and coverall
uniform for skin protection.
3. Ensure to implement work rotation to
avoid personnel from long sunlight
exposure.
4. Reschedule jobs to cooler times
(night shift) if possible.
1. Ensure to conduct tool box meeting
regarding the proper use of scaffold.
2. Ensure erection of aluminium scaffold
must be done according to
manufacturers guidelines.
3. Ensure the erection/dismantling of
scaffold being done by qualified
scaffolder.
4. Only scaffold with green tag will be
used and refrain from using scaffold
with red tag.
1. Operatives must ensure to wear full
body harness while working @ height
of 2m and the lanyard hook properly
secured to rigid post / structure
strong enough to support weight of
persons working
1. Ensure to conduct tool box meeting
regarding the correct use of ladder
2. Operatives must ensure to check the
ladder prior to use.
- Oil or slippery on rungs
- Rungs and rails are not split or
broken
- Rubber footings and spreaders are
in good condition.
3. PFAS must be observed or
implemented when working 2 meters
& above.
4. Ensure to assign ladder attendant to
hold ladder while a person is working
on it.

NOTE: For detailed definition of SEVERITY, LIKELIHOOD & RANKING, please refer to TAK-014

1. Supervisor to assess the physical


condition and competence of persons
assigned for the job, duration of the
job and weather conditions.
2. Proper monitoring by HSE personnel to
ensure Safety Guidelines are being
observed or complied.

1. Prior to start of job, supervisor to


assess the working at elevation
irrespective of the height and consider
primary fall protection devices for
heights.
2. Supervisor to assess the physical
condition and competence of persons
assigned for the job, duration of the
job and weather conditions.

1. Worksite Supervisors shall monitor the


operatives and ensure to wear safety
harness with lanyards properly
hooked.

1. Supervisor to assess the physical


condition and competence of persons
assigned for the job, duration of the
job and weather conditions.
2. Work that involves restricted vision or
hot work such as welding or oxy
cutting should preferably not be
performed from a ladder. Preference
should be given to the use of
temporary work platforms

FORM NO. TAK-014-002 REV. 1

HAZARDIDENTIFICATION&RISKASSESSMENT

6.

7.

Spillage and loose


materials/tools

Tools, equipment
and materials
from height.

1. Slip
2. Trips

Body injury of person


working down due to
accidental fall.

1. Fire / Explosion
2. Inhalation
of
Fumes
3. Eye Injury
4. Suffocation
5. Skin Irritation
6. Ingestion

8.

Paints / Chemical
Cleaners /
Thinners Petrol /
Lubricants &
Aerosols

9.

Flying/airborne
particles

Eye injury

10.

Striking objects hit


with installed
protruding utilities

1. Eye injury
2. Head injury.

1. Platform is kept neat, tidy and free of


loose materials/tools. Spillage shall be
cleaned
up
immediately
using
absorbent materials and any slippery
surfaces cleaned and degreased.
2. Maintain good housekeeping around
the work area.
1. Operatives shall ensure that all items
of equipment and tools are positioned
in a safe and secured manner.
2. Never place any tool near the edge of
working platform if not secured.
3. Operatives shall ensure to use rope &
basket for lifting & lowering of
materials
1. Secure MSDS & conduct special TBT
or COSHH meeting on use of
chemicals and hazardous substances.
2. No smoking on undesignated areas.
3. Forbid open flame or heat and
ignition sources from workplaces
where accumulation of fumes is
evident.
4. Proper ventilation on Storage areas
and workplaces; provide exhaust
blower inside rooms or congested
areas where people are working.
5. Provide and use appropriate PPEs
such as, but not limited to, respirators
/ masks, Face shield, rubber gloves.
6. Wash hands properly before eating,
use hand soap to remove chemical
resins from hands.
1. Operatives shall ensure to wear the
required eye protection for the task at
hand, ie goggles or face shield when
grinding, handling chemicals etc.
1. Operatives shall remain vigilant when
moving around the platform and
ensure to wear hard hat and eye
protection always to avoid head
injury.

NOTE: For detailed definition of SEVERITY, LIKELIHOOD & RANKING, please refer to TAK-014

1. Worksites Supervisors shall monitor


the standards of housekeeping during
routine walk around and implement
clean ups when necessary

1. Supervisors shall monitor the position


of all plant, tools and equipment to
ensure that it is safe and secure.

1. Supervisor to assess the physical


condition and competence of persons
assigned for the job, duration of the
job and weather conditions.
2. Proper monitoring by HSE personnel to
ensure Safety Guidelines are being
observed or complied.

1. Supervisors shall monitor the position


of all plant, tools and equipment to
ensure that it is safe and secure.
1. Supervisors shall monitor the position
of all plant, tools and equipment to
ensure that it is safe and secure.

FORM NO. TAK-014-002 REV. 1

ATTACHMENT11.5

Sitework Instructions
Sitework Instructions
Solvent cement jointing
This technique applies to 100, 200, 400 and 500 pipes when
used with 100, 200 and 500 system fittings.

Step 1
Cut pipe square, deburr and clean mating surfaces with
Terrain cleaning fluid 9101 (Fig.1).

Step 2

Fig. 1

Fig. 2

Fig. 3

Fig. 4

Fig. 5

Fig. 6

Coat mating surfaces with solvent cement using a clean


brush, assemble joint immediately, removing any excess
cement with a clean rag. Initial set 3-minutes. Note 24 hours
is required for the joint to fully set before testing. (Fig. 2).
Brush supplied with tin is suitable only for sizes up to 50mm
for larger sizes use at least 12mm brush. Directions for use
of solvent cement are printed on the container label and
must be followed closely.

Conversion of solvent weld socket to


seal ring joint (using 109 adaptor)
Under normal use only fit 109 to upstream socket.

Step 1
Clean mating surfaces with Terrain cleaning fluid 9101 (Fig.3).

Step 2
Fit seal ring into 109 collar (Fig. 4)

Step 3
Carefully apply solvent cement to mating surfaces (Fig. 5)

Step 4
Assemble immediately applying firm even pressure until
collar is in correct position (Fig. 6)

Estimating guide: Terrain cleaning fluid, liquid weld, lubricants


Contents

Pipe sizes & number of joints achievable*

9101 Cleaning Fluid

9100 Liquid Weld

9136 Lubricant

solvent cement

32mm

40mm

50mm

82mm

110mm

160mm

125ml

80

80

80

30

20

10

250ml

160

160

160

60

40

20

30ml

10

10

10

125ml

27

27

27

10

250ml

55

55

55

20

15

250gm

400

300

250

200

150

100

* For guidance only: approximate number allowing for wastage.

54

Sitework Instructions
Seal ring jointing - 109
Step 1
File a 45 chamfer onto end of square cut pipe. Lubricate
rubber seal with Terrain lubricant 9136 (Fig.7).

Step 2
Enter pipe fully into socket, mark pipe as shown (Fig. 8).

Step 3

Fig. 7

Fig. 8

Withdraw pipe until the mark is 12mm away from socket.


This means a 12mm gap exists between the end of the pipe
and the socket register. This gap will allow the pipe to
expand without distorting the pipework. Anchor the
expansion joint with a holderbat or if not practical anchor a
fitting within 1 metre of the joint (Fig 9 & 10).
Expansion
Expansion Gap
Gap

Fig. 9

Fig. 10

Slip coupling - 111.S

Step 2

Slip couplings are used for inserting additional fittings such


as branch or for remedial work in existing soil pipework.
To insert fitting:

Slide the couplings completely over the spigot ends of the


existing pipe.

Step 1
Assemble the fitting with a short length of pipe in the
appropriate sockets. Cut out a section of the assembly,
allowing for an expansion gap. Clean and chamfer pipe ends.
Lubricate seals of the slip couplings.

Step 3
Insert and line up the new assembly, slide back the couplings
to cover over the joints. Secure slip couplings with
holderbats. (See Fig. 11).

Fig. 11

55

Vous aimerez peut-être aussi