Académique Documents
Professionnel Documents
Culture Documents
Retrofit
Trevor Hallberg
Sarah Scribner
Outline
Mixed Integer Linear Programming (MILP)
Pinch Technology Theory for Retrofit
Improvements on Pinch Technology
Crude Distillation Unit Example
Discussion
128C
H1
170C
35.5C
CU
10 kW/C
30C
55 kW
HU
C1
200C
76.7C
1110 kW
9 kW/C
30C
420 kW
HU
109.1C
C2
200C
11 kW/C
925 kW
1000 kW
Retrofit Options :
25C
Optimal Results :
Based on transportation-transshipment
m 1
2
3
4
5
6
7
8
model
Hot stream, i
z ,H
qijm
z
qim
, jn
z ,C
qijn
Cold stream, j
1
33
44
55
66
88
MILP
Model parameters
Area adjustment
Existing heat exchangers
New heat exchangers
Re-piping
Area Adjustments
Area Addition
Existing Exchangers
Increase area of existing shell
Install a new, larger shell
New Exchangers
Limit number of new
exchangers
Limit area (size) of new
exchangers
Enforce realistic area
adjustments
Area addition 20%
Area Reduction
Plug Tubes
By-pass fluid
adjustments
Area reduction 50%
Re-piping
Re-piping scenarios
Exchanger relocation
Stream splitting
Exchanger by-pass
MILP
Objective Functions
Maximize value of savings
Value of Savings = Utility Cost Savings Annual Capital
Cost
MILP
INPUT Parameters
Stream data (FCp)
Stream temperatures (Inlet & Target)
Cost functions
OUTPUT Data
Optimized objective function
Exchanger locations
Cost requirements
Utility savings
Pinch Technology
Pinch Technology
Pinch Technology
Pinch Technology
analyzed separately
Heat Sink region above the pinch
Heat Source region below the pinch
Pinch Technology
3 Pinch Rules
No heat transfer across the pinch
No external cooling above the pinch (only
HU)
No external heating below the pinch (only
CU)
Violating these
results in crosspinch heat
transfer
Increases heat
Pinch Technology
regions
Assumes equal area of each exchanger
Vary Tmin
Aideal = A1+A2++Ai
Pinch Technology
Retrofitting
Energy vs. Area diagram
Blue curve = Aideal for
energy requirements
Pinch Technology
Retrofitting continued
Why would we increase
Pinch Technology
Pinch Technology
Area Efficiency ()
Agrassroots
Aexisting
Pinch Technology
Area Efficiency
Aideal
Aretrofit
Agrassroots
Aexisting
Assume = and
Aideal Agrassroots
Aretrofit
Aexisting
Aideal
Agrassroots
Aretrofit Aexisting
curve
Process:
Tmi
n
Qu,min
Aideal
Aretrofi
t
Pinch Technology
Which do we use?
Infinite amount of
values
At least want current
The best is = 1
Larger = smaller Aretrfit
Assume value of 1
Aideal Agrassroots
Aretrofit Aexisting
Pinch Technology
( Aideal Agrassroots )
Aexisting
for constant
Optimum Tmin value corresponds to the
minimum
Pinch Technology
TAC
OC C HU CCU
b Aretr
CC N min a
N min
Pinch Technology
Now we need to design the HEN
economic)
Design sections above and below pinch separately
128C
H1
170C
40C
CU
35.5C
40C
10 kW/C
2
30C
55 kW
HU
C1
200C
76.7C
11 kW/C
30C
30C
30C
1110 kW
30C
420 kW
HU
109.1C
C2
200C
1000 kW
925 kW
9kW/C
25C
Pinch Technology
HEN Design
Start design at
pinch
Matching streams
AP: (FCp)hot
(FCp)cold
128C
H1
BP: (FCp)cold
(FCp)hot
170C
loads
Q = FCpT (for each
stream)
40C
200C
76.7C
10 kW/C
2
30C
45 kW
30C
30C
30C
30C
11 kW/C
230 kW
CU
35.5C
40C
HU
C1
Maximize exchanger
1300 kW
HU
109.1C
C2
200C
1870 kW
9 kW/C
2
55 kW
25C
Pinch Technology
HEN Design
flexible
Give E6 a duty of X
A web of exchangers is affected
128C
H1
170C
40C
40C
CU
35.5C
10 kW/C
30C
45 kW
HU
C1
200 C
76.7C
30C
30C
30C
30C
11 kW/C
230 + X kW
1300 - X kW
HU
109.1C
C2
200C
X kW
1870 - X kW
9kW/C
2
55 kW
25C
Pinch Technology
Q U Aexchanger TLM
TLM
T
H ,out C ,in
ln
Pinch Technology
Cost comparisons
No longer assume equal areas for each
exchanger
CC (Capital Investment Cost)
Based on area change for each exchanger in the
network
Fixed and variable costs
Includes area addition, reduction, and new
exchanger cost
Operating Costs (OC)
Pinch Technology
exchangers
May be able to cut down on
area change expenses
May decrease the number
of new exchangers needed
Incorporate Pro-II
simulation
results
Exchanger location
Pro-II Optimization
Controllers set stream target
temps
Calculator assigns cost
equations
Optimizer minimizes cost
function
Retrofit Considerations
Stream splitting
Addition of new exchangers
Allow & disallow exchanger relocation
Original Network
10 Hot streams
3 Cold streams
18 exchangers
2 hot utilities
3 cold utilities
Original
COMPARISON
Original
18 exchangers
MILP
8 new exchangers
Process Pinch
9 new exchangers
No Relocation
Allowed
MILP
Process Pinch
Retrofit Results
Allow Relocation
Original
COMPARISON
Original
18 exchangers
MILP
5 new exchangers
5 relocated
Process Pinch
9 new exchangers
7 relocated
MILP
Process Pinch
Retrofit Results
Discussion
Why?
Considers the greatest number of variables
Considers all solutions
No limiting assumptions or methodology
Optimization based on several cost
parameters
Computer does everything a person can do
Only requires input of data
Do not need experience with the methodology
The End
units
It then optimizes the area distribution and utilities
Example 1
Original Network
7 exchangers
1 heater (E7)
F
kg/s
228.5
20.4
53.8
Stream
H1
H2
H3
2 coolers (E5,E6)
Cp
kJ/kg.C
1
1
1
Tin
o
C
159
267
343
Tout
o
C
77
88
90
H
kW/m2.oC
0.4
0.3
0.25
500
499
0.53
1
1
26
118
127
265
0.15
0.5
20
40
0.53
HU (hot utility)
C1
C2
93.3
196.1
CU (cold utility)
H1
159 0
228.5
77
CU
H2
267
20.4
88
CU
H3
343
53.8
127 0
C1
90
93.3
26
HU
C2
265
196.1
7
118
New
159 0
+A
-A
5
77
CU
+A
H2
H3
267
New
4
CU
-A
+A
343
88
90
NEW SPL
C1
127
26
+A
C2
265
HU
NEW SPL
118
exchanger)
1 heater (E7), 1 cooler (E5)
E8 added to meet increase process exchange
H1
New
159 0
+A
-A
5
77
CU
+A
+A
H2
H3
267
CU
-A
+A
343
88
90
NEW SPL
C1
127
26
+A
C2
265
HU
NEW SPL
118
Example 1- MILP
159
-A
New
H2
267
+A , NS
H3
343
88
CU
-A
2
+A , NS
CU
New
77
90
+A, NS
NEW SPL
127
C1
26
NEW SPL
HU
-A
C2
265
118
Example 1- MILP
I1
159
+A
I2
267
+A, NS
I3
343
265
New
88
New
CU
New
127
10
90
26
NEW SPL
HU
J2
77
CU
+A, NS
J1
118
-A
EXAMPLE 1 RESULTS
BEYOND THIS POINT
Example 1
technology
Example 1
technology
Example 1
Example 1