Vous êtes sur la page 1sur 63

Project: ECUMED-El Bibane

Feasibility Study for EBB Plant Upgrade For Gas


Commercialization
Project NO
AR11/12
WO3
Date

Contract NO

EPPM document NO

Client
document NO

Rev

XXXXX

XXXXX

XXXXX

XX/XX/XXXX

Page

of

53

REPORT

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

ECUMED PETROLEUM

1
0

21/06/2013

Issued For
approval
18/06/2013 Issued For
Review

001/AR11/12

SANAMCH

MCH

MLI

SANA

MCH

MLI
04/10

NO.
R1112-RPT-PR00-001
REV.A
PAGE: 2 / 63

PROCESS REVIEW
REQUIRED MODIFICATION REPORT

REV

DATE

Designation

NAME

VISA

Prepared by

NAME

VISA

Verified by

NAME

VISA

Approved by

EQUIPMENTS SIZING REPORT FOR THE FIRST


PART

NO.
REV.
0
PAGE: 3 / 63

Revisions report:
Revision No
0
1

002/AR11/12

Revision Description
Issued For Review
Issued For Approval

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 4 / 63

TABLE OF CONTENTS
1.

INTRODUCTION........................................................................................6
1.1

GENERAL................................................................................................................. 6

1.2

PROJECT DETAILED SCOPE........................................................................................... 6

1.3

DOCUMENT SCOPE..................................................................................................... 7

1.4

DEFINITIONS & ABBREVIATIONS....................................................................................7

1.4

DEFTINO.S ............................................................................................................................ 7

21.4

ABREVOITNS............................................................................................................................. 8

1.5

UNITS OF MEASUREMENT............................................................................................ 8

2.

DESIGN DATA..........................................................................................10
2.1

ENVIRONMENTAL DATA.............................................................................................. 10

12.

MCLATINDMEORG ITNS........................................................................................................................... 10

2.1

GROUNDASILCT........................................................................................................................... 11

2.2

WELLS LOCATION................................................................................................... 11

2.3

PROCESS DESIGN DATA............................................................................................ 11

12.3

WELHADRMPT.S .......................................................................................................................... 11

2.3

COMPSITN........................................................................................................................... 12

2.4

CPFDESIGNAMRT........................................................................................................................... 12

2.5

GASREQUDISPCFOTNTE(IA.) .......................................................................................................................... 12

3.

4.

CALCULATION METHODS.........................................................................13
3.1

PROCESS DESIGN TOOLS.......................................................................................... 13

3.2

THERMODYNAMICS................................................................................................... 13

3.3

MODEL DESCRIPTION, BATTERY LIMITS

13.

DFLUIRESVO........................................................................................................................... 13

23.

WELHADS........................................................................................................................... 14

3.

PIENL........................................................................................................................... 14

43.

FIRSTSEPAO.N .......................................................................................................................... 14

53.

NAMEIT.U .......................................................................................................................... 14

63.

GLYCODEHRATNI.U .......................................................................................................................... 14

73.

CONDETSARMLV.UI .......................................................................................................................... 15

83.

INJECTOGASCMPR........................................................................................................................... 16

93.

CONDETSASLBIZ........................................................................................................................... 16

AND

ASSUMPTIONS...............................................13

DESIGN OF THE NEW AMINE UNIT............................................................20


4.1

SELECTION FACTORS FOR THE TYPE OF AMINE................................................................20

4.2

CO2 SELECTIVITY................................................................................................. 20

002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART


4.3

KINETICS

4.4

CORROSIVITY.......................................................................................................... 21

4.5

AMINE

4.6

THERMODYNAMICS

4.7

MAIN EQUIPMENTS SIZING......................................................................................... 21

14.7

DETRMINOAFWL........................................................................................................................... 21

24.7

NSIZGOFCO2ABRE........................................................................................................................... 22

34.7

NAMEIRGTO........................................................................................................................... 23

4.7

LEANMICRUTOPS........................................................................................................................... 23

4.8

NSIZGOFHEATXCR........................................................................................................................... 24

14.8

NSIZGOFLEAMRC........................................................................................................................... 24

24.8

NSIZGCOFRH/LEAMTXNG.R .......................................................................................................................... 24

34.8

NSIZGOFRETACD........................................................................................................................... 25

4.8

NSIZGOFRETALB........................................................................................................................... 25

54.8

NSIZGOFAMELHDRU........................................................................................................................... 26

5.

6.

NO.
REV.
0
PAGE: 5 / 63

OF REACTION WITH

CO2..............................................................................20

CONSUMPTION AND PRICE................................................................................21


OF REACTION WITH

CO2..................................................................21

REVISION OF TEG UNIT DESIGN...............................................................26


5.1

REVISION OF TEG

5.2

CURRENT TEG REGENERATION UNIT DESIGN......................................................28

15.2

GLYCOFASHTNKPERIDMOSN........................................................................................................................... 28

25.

THECAXNGRSIPUD........................................................................................................................... 29

25.1

AIR/GLYCOHETXN.E320 .......................................................................................................................... 29

25.

GLYCO/HEATXNR........................................................................................................................... 29

25.3

GLYCOREN/DASMIZ........................................................................................................................... 29

5.3

GLYCOPUMS........................................................................................................................... 30

5.4

CONDESRILXHAG........................................................................................................................... 30

5.

REGNATOILB........................................................................................................................... 30

5.6

LGPSTRNIUCOM........................................................................................................................... 30

5.7

LGSTICOUM.N: .......................................................................................................................... 31

5.8

REGENERATION PROCESS TROUBLE SHOUTING................................................................32

15.8

PSTRNIGAFLOWE........................................................................................................................... 32

25.8

PSTRNIGAUCOMLDE(TR.) .......................................................................................................................... 33

CONTACTOR

DESIGN..................................................................26

NEW CHILLING UNIT................................................................................34


6.1

REFRIGERANT

6.2

PROPANE RECEIVER................................................................................................. 34

6.3

PROPANE COMPRESSOR............................................................................................ 35

6.4

PROPANE CONDENSER.............................................................................................. 35

6.5

PROPANE ECONOMIZER VJ-4003:...............................................................................36

6.6

GAS/PROPANE HEAT EXCHANGER EJ-4003...................................................................36

002/AR11/12

FLUID SELECTION..................................................................................34

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 6 / 63

6.7

GAS/GAS OUTLET COLD SEPARATOR HEAT EXCHANGER EJ-4001A...................................37

6.8

GAS/LIQUID HEAT EXCHANGER EJ-4002......................................................................37

6.9

COLD SEPARATOR.................................................................................................... 37

7.

NITROGEN SKID......................................................................................38

8.

SIZING OF PIPELINE................................................................................39

9.

CONCLUSION..........................................................................................42

10. APPENDICES........................................................................................... 44
10.1

APPENDIX 1:

RECIRCULATION RATE OF

10.2

APPENDIX 2:

AMINE CONTACTOR DIAMETER CALCULATION..............................................44

10.3

APPENDIX 3:

AMINE REGENERATOR DIAMETER CALCULATION..........................................44

10.4

APPENDIX 4: GPSA

10.5

APPENDIX 5: NORSOK STANDARD FOR SIZING OF GAS LINE...............................46

10.6

APPENDIX 6: AMINE UNIT HEAT EXCHANGERS TEMA SHEETS..............................47

10.7

APPENDIX 7: GLYCOL UNIT HEAT EXCHANGERS TEMA SHEETS............................49

10.8

APPENDIX 8: CHILLING UNIT HEAT EXCHANGERS TEMA SHEETS.........................52

10.9

APPENDIX 9: STRIPPING GAS COLUMN DESIGN...................................................56

STANDARD FOR

DEA

TEG

SOLUTION..................................................44

CONTACTOR SIZING........................................45

10.10 TIE-IN PROCEDURE TO ADD AMINE FLASH VAPOR TO STRIPPING GAS PROCESS
58

002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 7 / 63

1. INTRODUCTION
1.1GENERAL
El-Bibane offshore wells are located at about 18 km far from the CPF (the
onshore central processing facility) situated on the town of Zarzis.
Presently, El-Bibane field is operating as described below:
-

Producing from the offshore well EBB#5,


Gas injection in the offshore well EBB#4,
The well EBB#3 RE 2 is temporary closed.

The production is handled to the CPF through an 8 sea line and the treated gas
is rerouted from the CPF to be re-injected through 6 sea line.

Figure 1: The Onshore Wellheads Configuration


1.2PROJECT DETAILED SCOPE
The main engineering tasks for this project can be summarized into three (3)
parts as follows:
1/ Feasibility study for selling 1/3 of gas production and injection of the
remaining quantity:
-

Prepare the required simulations to sell 4-5 MMSCFD and inject 9-11
MMSCFD of gas in order to recover condensate.

Define the required process modifications for the first phase.

Perform needed calculations for modified or potential additional required


equipments.

002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 8 / 63

Develop the cost estimation for the related modifications.

Based on the recovered condensate quantity and the gas sales, develop
the first phase economic analysis.

2/ Feasibility study for selling the total gas production:


-

Prepare the required simulations for treatment of 15 MMSCFD of gas to


the sales specification: the total gas production will be sold and no reinjection to be considered. Thus, no condensate recovery optimization to
be considered other than the gas treatment required to meet commercial
specifications. Condensate recovery will still be possible and it will be sold
separately.

Define the required process modifications for the second phase.

Perform needed calculations for modified or potential additional required


equipments.

Develop the cost estimation for the related modifications.

Based on the gas sales develop the second phase economic analysis.

As an alternative economic option, one analysis will be made for the


implementation of the required modifications on the facilities to treat the
complete 15 MMSCFD in one time and to start treatment of only 4-5
MMSCFD in the first phase and use the remaining quantity to recover
condensate.

3/ Feasibility study for sales gas transportation


-

Assessment of the different types of gas transportation methods, depend


on the tie-in point location and gas characteristics. The option of
transportation of non treated gas will be also assessed.

Prepare the required simulations/hydraulic calculations for transport of


15 MMSCFD of gas to a tie-in point to the STEG network.

Based on the gas sales develop an economic analysis.

The present report is devoted to the first phase; the feasibility study for
selling 1/3 of gas production and injection of the remaining quantity.
1.3DOCUMENT SCOPE
The objective of this document is to check the operability and the adequacy of
the existing facilities and to size required additional equipments on both CPF
002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 9 / 63

and other units relevant to El Bibane Field Development Project. This study has
been carried out for a total gas production of 15MMSCFD, case of selling 1/3 of
gas production and injecting the remaining quantity in order to recover
condensate.
1.4DEFINITIONS & ABBREVIATIONS
1.4.1DEFTINOS
For the purpose of this document the following definitions shall apply:

Owner/Client

ECUMED Petroleum

Contractor

EPC contractor

Engineering company

Engineering

Procurement

and

Project

Management (EPPM)
Project

El Bibane-Detail Engineering for Gas Cycling


Production Pilot Project

Supplier/ Vendor

The

party

(s)

supplies

which

manufactures

equipment,

and/or

technical

Documents/drawings and services to perform the


duties specified
1.4.2 ABREOVITNS
The following abbreviations will be used:
BHP
CPF
EBB#
EOS
HP
HHV
JT
LP
PCV
PFD
SEEB

:
:
:
:
:
:
:
:
:
:
:

Bottom-Hole Pressure
Central Processing Facility
El Bibane Wellhead number
Equation of State
High Pressure
Higher Heating Value
Joule Thomson
Low Pressure
Pressure Control Valve
Process Flow Diagram
Electricity Company of El-Bibane ( Socit dElectricit El-

STEG

Bibane )
Tunisian Company of Electricity and Gas ( Socit Tunisienne

TEG

dElectricit et de Gaz)
Tri Ethylene Glycol

1.5UNITS OF MEASUREMENT
002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 10 / 63

In general, SI units will be used. However, there are recognized exceptions and
preferred units that are used in the Oil & Gas industry.
Table 1: Units of Measurement
Measured Quantity
Corrosion Allowance

Preferred Unit
Millimeters

Designation
mm

Density

kilogram per cubic meter

kg/m3

Ampere

milli-ampere

mA

Volt

Watt

Kilowatt

kW

Megawatt

MW

Electric Resistance

Ohm

Ohm

Enthalpy

Kilo Joule per kilogram

kJ/kg

Force

Newton or kilo Newton

N or kN

Frequency

Hertz

Hz

Head

Meters

Heat Loading
Heat Transfer
Coefficient
Latent Heat

Kilowatts
watts per square meter per
degree Celsius
kilo Joules per kilogram

kW

Length

millimeters, meters, kilometers

mm, m, km

Luminance

Lux

Lx

Mass

Kilogram

kg

Mass Flow Rate

kilogram/hour

kg/h

Mechanical Power

kilowatts, megawatt

kW, MW

Diameter

In

Stress

Inches
bar gauge, bar absolute,
Kilopascal
revolutions per minute
kilocalories per Standard cubic
meter
kilojoules per kilogram degree
Celsius
Newton per square meter

Temperature

degree Celsius

Thermal Conductivity

watt per meter Celsius

W/m C

Time

y, d, hr, min, s

Vessel Dimensions

year / day/hour/minute /second


meters per second or meters
per hour
meters, millimeters

Volume (actual)

cubic meters

m3

Standard Gas Volume

Standard cubic meter

SCM (Note 1)

Electric Current
Electric Potential
Electric Power

Pressure
Rotational Speed
Lower Heating Value
(LHV)
Specific Heat

Velocity

002/AR11/12

W/m2 C
kJ/kg

barg, bara, kPa


RPM
kcal/SCM
kJ/kg C
N/m2

m/s, m/h
m, mm

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Measured Quantity
Volume Gas Flow
Volume (liquid)

Volume Flow (liquid)

Pipe/Nozzle sizes
Dynamic Viscosity
Kinematic Viscosity

NO.
REV.
0
PAGE: 11 / 63

Preferred Unit
meter /day (per hour)
Million Standard cubic feet/day
Cubic meter
Cubic meter/ hour
Cubic meter/ day
Barrel/day, Barrel Oil/day, Barrel
Water/day, Barrel
Condensate/day
Inches

Designation
SCMD (SCMH)
MMSCFD
m3

Centipoises

cP

Centistokes

cSt

m3/h
m3/day
BPD, BOPD,
BWPD, BCPD
In

Standard conditions are 1.01325 bara at 15.56C.


Normal conditions are 1.01325 bara at 0C.
2. DESIGN DATA
2.1ENVIRONMENTAL DATA
2.1.1CTLIMCANDMEORGCTIS
El-Bibane weather is characterized by moderate winter and smoother summer;
meanwhile some occasional storms may occur.
Onshore Data:

Wind Direction and speed:


Dominant wind direction ENE.

Maximum wind speed:

One hour wind speed: 130 km/h.

One minute wind speed: 164 km/h.

Design Ambient Temperatures:

Mean minimum air temperature: 0 C;

Mean maximum air temperature: 32 C;

Maximum air temperature: 50 C.

Relative Humidity: 60-68%

Air pressure: 14.73 psia.

Rainfall:

Minimum monthly rainfall: 1 mm.

Maximum monthly rainfall: 41 mm.


Offshore Data:

Minimum seabed temperature: 13 C;


002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Still water level (average): 7.0 m;

Maximum centenary wave height: 5.5 m;

Swell height : 3.5 m

Period associated with maximum wave: 12.1 s;

Maximum tide elevation above still water: +1.1 m;

One hour wind speed: 130 km/h;

One minute wind gust: 164 km/h;

Surface current speed: 1.1 m/s;

50% depth current speed: 0.9 m/s;

Bottom current speed: 0.5 m/s;

Conductivity (20C): 50 mS/cm.

NO.
REV.
0
PAGE: 12 / 63

2.1.2GROUNDALSICT
The offshore soil properties are investigated by pressure-metric survey, the main
results could be summarized in the following table:
Table 2: El-Bibane Offshore Soil Profile

Depth

Soil Type

Effective
Limit
Pressure

Sub-Grade
Modulus

Friction
Angle

Sandstone +

35 bars

700-1000

30-35

Hard
Silt

40 bars

1000-1100

35-40

12m-20m

sandstone

The Seismic Zone: zone 0


2.2WELLS LOCATION
The table given below indicates wells location.
Table 3: Wells Location
Well

Statu
s

UTM x
(m)

UTM y
(m)

EBB#3RE2
(Horizontal)

None

713942

3702310

Same
as
unknown.

EBB#4
(Horizontal)

Inject
or

713570

3702746

Intersection of M82-1046 and M84-20.


Deviation unknown.

002/AR11/12

Remarks
EBB#3RE.

Deviation

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

EBB#5

Produ
cer

714321

3703214

NO.
REV.
0
PAGE: 13 / 63

Intersection of M82-1025 and M84-20


close to EBB#1. Subject to change.

Appendix 1 shows a schematic of the CPF and wellheads positions.


2.3PROCESS DESIGN DATA
2.3.1WELHADPRMTS
The table given below illustrates wellhead process parameters.
Table 4: Wellheads Process Conditions
Parameter
Pressure

(after

choke

valve) (barg)
Injection pressure(barg)
Temperature (C)
Design
Flow
rate
(MMSCFD)

EBB#5

EBB#4

wellhead

wellhead

36

64

158
-

10

10

2.3.2COMTPSIN
EBB#5 fluids compositions inlet and outlet HP separator are detailed in process
simulation reports
2.4CPFDESIGNARMT
The design parameters of the CPF are illustrated in the following table:
Table 5: CPF Design Parameters
Parameter
Equipment
HP
Separator(V1001)
V-100
V-101
Glycol Contactor (T710)
Gas/Gas Heat
Exchanger (EJ-4001)
Cold
4001)

002/AR11/12

Separator

(VJ-

Design
Pres. (barg)

Design
Temp. (C)

100

50

41.4

46

100

97.5

-29 to 65.5

Shell/Tube

Shell/Tube

Tubes: OD, 14

75.8/75.8

121.1/121.1

BWG, Length=40 ,

69.98

-45.5 to 51.6

Capacity/Dimensio
ns
60 OD 20
Length
36 OD 28
Length
22 Shell Diameter

No. 350
40 OD 120
Length

NO.
REV.
0
PAGE: 14 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Equipment
Compress
or (K-400
A/B)

Parameter
First
Stage
Second
Stage

Design
Pres. (barg)
Suction/discha
rge
30/84.5
Suction/discha
rge
84.2/228

Heater (H-102)

Design
Temp. (C)

Capacity/Dimensio
ns

Outlet Temp. 55C

2.5GASREQUDISPFCTON(TEGIA)
The required sales gas specifications are summarized in the table below:
Table 6: Required Gas Specifications
Parameter

Unit

Value

Higher Heating
Value

kcal/Nm3

9300 10228

Wobbe Index

kcal/Nm3

11961 12640

Water content

(ppm)

<= 80

H2S content
Sulfur content
Gas temperature
CO2 content
H2
and
content
O2 content

N2

mg/Nm

<2

mg/Nm

< 50

10 50

% mol

< 0.5

% mol

<6

% mol

3. CALCULATION METHODS
3.1PROCESS DESIGN TOOLS
The software HYSYS (version 7.3) is used for the process simulation under
steady state conditions.
Schlumbergers PIPESIM modeling Software version 2009 is used for process
calculation and hydraulic simulation for the study at steady state for the pipeline
connecting the piping outlet the CPF with the tie-in point on the STEG gas
network.
3.2THERMODYNAMICS
The simulations have been performed based on Amine package in amine unit
simulation and Peng/Robinson EOS using the binary coefficient data provided
by HYSYS.
3.3MODEL DESCRIPTION, BATTERY LIMITS AND ASSUMPTIONS
002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 15 / 63

3.3.1FUIDLRESVO
The gas and oil compositions (Appendix 2) respectively inlet and outlet the HP
separator are recombined and reintroduced as a feed stream. Hence the
separated gas composition is given in the table below:
Table 7: Estimated separated Gas composition
COMPONENTS
CO2
Nitrogen
Methane
Ethane
i-Butane
n-Butane
i-Pentane
n-Pentane
n-Hexane
Propane
Benzene
Cyclohexane
2-Mpentane
3-Mpentane
2-Mheptane
Toluene
n-Heptane
n-Octane
n-Nonane
2-Mhexane

MOLE FRACTION
0.0177
0.0172
0.8256
0.0783
0.0067
0.0098
0.0037
0.0031
0.0015
0.0336
0.0002
0.0002
0.0007
0.0003
0.0001
0.0001
0.0007
0.0001
0.0001
0.0002

3-Mhexane

0.0001

3.3.2WELHADS
The wellhead stream from EBB#5 conditions are as follows:
o

Maximum operating pressure: 148 barg.

Operating pressure: 35 barg.

Built up pressure: 160 barg.

Operating temperature: 64C.

An automatic/electric choke valve is used to adjust the well stream flow rate and
the pressure which will define the optimal CPF inlet pressure.
The injected gas in EBB#4 is at pressure 158 barg.
3.3.3PPELIN
A roughness of 45.7 m (Carbon steel) will be used for the pressure loss
002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 16 / 63

calculations.
A thermal conductivity of the pipe material of 45 W/m.K will be assumed.
3.3.4FRSTISEPAON
The CPF inlet production is carried into the HP three phases separator (V-1001)
as a first removal of water and condensate. This separator has a design pressure
of 100 barg which can limit the CPF inlet pressure. The gas at the inlet of
separator is considered at 31 barg and 31C.
3.3.5AMINEUT
In order to remove carbon dioxide from inlet gas, an amine unit is foreseen
downstream HP three phase separator (V-1001).
The Amine unit will be designed to treat 16 MMSCFD of gas with 1.77 mol %
CO2, by circulating lean amine solution (30 wt% DEA) through the contactor to
remove carbon dioxide from inlet gas and satisfy the customers requirement of
0.5% CO2.

Rich amine from the bottom of the Contactor is flashed from

approximately 32 bara to 5 bara through a level control valve and sent to the
Amine Flash Drum to separate the hydrocarbon gas from DEA solution. The rich
DEA is heated to approximately 75C by the Rich/Lean Amine Exchanger and
then fed to the Amine Regenerator. The lean amine is cooled through the
Rich/Lean Amine Exchanger and pumped via the Amine Booster Pumps to the
Lean Amine Air Cooler and then through lean amine filters. The lean amine is
cooled to approximately 40C and routed back to the Amine Contactor after
adjustment of amine solution flow rate and composition by the water make-up.
3.3.6GLYCODEHTRINAU
In order to prevent hydrate formation, a TEG contactor unit is foreseen
upstream of the J-Thomson condensate removal unit.
In order to prevent hydrate formation, a TEG contactor unit is foreseen
upstream of the J-Thomson condensate removal unit.
The sweet gas from the Amine Contactor is routed to the Glycol contactor (T710) near its bottom and flows upward through the bottom tray to the top tray
and out at the top of the column. Lean glycol is fed at the top of the column and
its flows down from tray to tray, absorbing water vapor from gas. The Contactor
operates at @ 50 C and 30 bara with a lean TEG. Dehydrated gas from the

002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 17 / 63

Contactor overhead is heated through the Gas/Glycol Heat Exchanger (E-310) to


55 C and routed to the J-Thomson unit to recover condensate.
Rich TEG from the contactor (T-710) will be preheated through the overhead
condenser on the glycol stripper still column and flashed to approximately 4.4
bara in the glycol flash tank (V-120). The flashed gas is sent to the flare network.
The rich TEG is next filtered before entering the Glycol reconcentrator (H-410)
to remove the absorbed water. The lean TEG separated from water is cooled in
the Air/Glycol heat exchanger (E-320) and pumped through two Glycol pumps
(P-510A/B) to the Gas/Glycol heat exchanger (E-310) for further cooling before
returning to Glycol contactor T-710.
3.3.7CONDESATRMVLUI
In order to remove any condensate, the gas should pass through a liquid
removal unit by reduction of temperature by using a Joule-Thomson expansion
unit. The condensate removal unit consists of the following items:
Heat Exchanger (EJ-4001): gas/gas heat exchanger
The heat exchanger design pressure is 75 barg for both shell and tubes side
which will limit the maximum operating pressure before the Joule-Thomson
expansion.
JT-Valve (PCV-4001)
The expansion pressure 30 barg is considered the lowest value reached by the
valve and which define the compressor first stage suction pressure. Actually the
JT valve is fully opened.
Separator (VJ-4001)
It is provided to separate gas from the formed condensate after pressure
expansion.
The figure given below shows a schematic of the condensate removal unit.

002/AR11/12

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Wet Gas

Heat Exchanger
Gas/Gas

Dry Gas

002/AR11/12

NO.
REV.
0
PAGE: 18 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 19 / 63

Figure 2: Condensate removal unit (J-Thomson unit)


3.3.8IENCTJIOGASCMPR
A multistage injection gas compressor is simulated to increase the injection gas
pressure from 30 barg to approximately 158 barg via two stages compressor. At
the level of the compressors scrubbers, the possible formed condensate is
recycled to the MP separator (V-100).
3.3.9CONDESATSLBIZ
The removed condensate from different CPF units is sent to conventional two
phases separators (V-100 & V-101) requiring a long residence time for
condensate stabilization. Then the heated condensate flowing from the heater
(H-102) is sent to the storage tanks (T-101 A/B).
The recuperated quantity of condensate shall be stabilized at a suitable process
operating conditions.

002/AR11/12

NO.
REV.
0
PAGE: 20 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

The HYSYS flowsheet of the CPF considering the new configuration is shown in the following figure.

Figure 3: HYSYS PFD of the CPF

002/AR11/12

04/10

NO.
REV.
0
PAGE: 21 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART


The sub-flowsheet of Amine Unit is modeled as shown in this figure:

Figure 4: The Amine Unit Modeled Flow sheet

002/AR11/12

04/10

NO.
REV.
0
PAGE: 22 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART


The sub-flowsheet of Dehydration Unit is modeled as shown in this figure:

Figure 5: The TEG Unit Modeled Flow sheet

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 23 / 63

4. DESIGN OF THE NEW AMINE UNIT


4.1 SELECTION FACTORS FOR THE TYPE OF AMINE
The choice of the process solution is determined by the pressure and temperature
conditions at which the gas to be treated is available, its composition with respect to
major and minor constituents, and the purity requirements of the treated gas.
MEA: eliminates simultaneously and non-selective hydrogen sulfide and carbon
dioxide. It is inexpensive. However, it has several drawbacks. First, it reacts in an
irreversible manner with mercaptans. In addition, its vapor pressure is relatively
high, resulting in greater losses compared to other amines. For these reasons, it is
mainly used when the concentration of acid gases is relatively low, therefore we
cannot use it.
DGA: It is more expensive than the DEA and has also the disadvantage of
hydrocarbons absorption, therefore we cannot use it.
DIPA: applications mainly concern the treatment of gas containing COS, as well as
the recovery and recycling of H2S.
The two types of amines commonly used for removal of CO 2 from natural gas are
DEA and MDEA.
The main selection factors of types of amines for the purification of natural gas are
listed hereby:
-

CO2 Selectivity

Kinetics of reaction with CO2

Corrosivity

Amine consumption and price

Amine degradation

Thermodynamics of reaction with CO2

4.2CO2 SELECTIVITY
Selectivity is a balance between the mass transfer rates of the acid gases competing
for the amine in the solvent. The less reactive the amine, the better the selectivity
MDEA is fairly selective towards H2S removal gases containing both H 2S and CO2
because it does not react directly with CO2. In such case, DEA is the best solution.

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 24 / 63

4.3KINETICS OF REACTION WITH CO2


The reaction between CO2 and DEA amines is significantly faster than the reaction
between CO2 and MDEA, therefore the DEA is favored kinetically.

4.4CORROSIVITY
The DEA is more corrosive than MDEA but in this case the corrosion is not an
important factor for the selection of the amine type because the existing facility is
sized for the most corrosive amine type.
4.5AMINE CONSUMPTION AND PRICE
The boiling temperature of DEA is higher than that of MDEA therefore the losses of
amine are greater for the case of MDEA.
The DEA is less expensive than MDEA; therefore the DEA is favored according to
price factor.
4.6THERMODYNAMICS OF REACTION WITH CO2
Both

types

of

amine

solutions

are

almost

total;

therefore

they

are

thermodynamically favored. However, the MDEA does not react directly with CO 2;
therefore its conversion rate is lower compared to DEA conversion rate.
Hence in this case the DEA is thermodynamically favored.
To summarize, as per Selectivity for CO2, Price of amine, Kinetics of reaction with
CO2, Corrosivity, Amine degradation and Amine consumption, and thermodynamics
of reaction with CO2, the performed amine for the gas treatment is the DEA.
The criteria of choice of the type of amine are summarized in the following table:
Table 8: criteria of choice of the type of amine
Choice criteria

002/AR11/12

DEA (30)

MDEA (40%)

Selectivity for CO2

Thermodynamic

Price of amine
Kinetics of reaction with
CO2
Corrosivity

Amine degradation

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Choice criteria
Amine consumption

NO.
REV.
0
PAGE: 25 / 63

DEA (30)

MDEA (40%)

Therefore we have chosen to use the DEA solution for natural gas treatment.
4.7MAIN EQUIPMENTS SIZING
4.7.1DETNRMOAIFLWE
The method to calculate the minimum amine flow rate in case of DEA solution is
shown in Appendix 1.
The main outcomes are summarized in the following table:

Table 9: amine flow rate calculation


Parameter

Actual Process
scheme

MM

15

Xa

(1.77 0.5)/1.77 =
0.717

8.59

ML

0.3

WT

30

DEA recirculation rate


(USGPM)

26.73

DEA recirculation rate


(m3/h)

6.07

For amine solutions with DEA, the minimum capacity of lean amine circulation
pumps for the actual process scheme shall be over than 6.07 m3/h.
Using the chemical reaction, to eliminate the acid gas the amine molar flow shall be
twice of the CO2 flow rate, in this case the DEA circulation rate is equal to 10.47
m3/h using a correction factor of 10%.
4.7.2SZINGOFCO2ABSRE
The method for calculating the diameter of the absorption column is shown in
Appendix 2.
002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 26 / 63

The main design data are illustrated in the following table:


Table 10: CO2 Absorber Design Data
Parameters

Value

Gas processed flowrate (MMSCFD)


Gas
processed
flowrate

16

(MMSCMD)
Contactor pressure (kPaa)
Contactor diameter (m)

0.453
3200
0.962

The main HYSYS simulation results for the CO 2 absorber are illustrated in the
following table:
Table 11: CO2 Absorber Main Sizing Results
Parameters

Value

Gas processed flowrate (MMSCFD)

15.95

Contactor pressure (bara)

32

Number of stages

10

Absorber diameter (m)


Section height (m)
Tray spacing (m)
Amine solution liquid volume flow
(m3/h)
Mol % CO2 inlet contactor
Mol % CO2 outlet contactor

0.762
6.1
0.61
10.47
1.772
0.304

Considering the above calculation results, the sizing results of the worst case are
considered:
Table 12: Results of sizing of absorption column
Design Parameter
Diameter of column (m)

Value
0.962

Height of column (m)

6.1

Number of plates

10

4.7.3AMINERGATO
The method for calculating the diameter of the regeneration column is shown in
Appendix 3.
Tacking in consideration the design capacity of the recirculation pump of 10.47
m3/h; the minimum diameter of the amine regenerator column should be of 517.72
mm.
002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 27 / 63

The main HYSYS simulation results for the Amine regenerator are illustrated in the
following table:
Table 13: Amine Regenerator Main Sizing Results
Parameters

Value

amine processed volume flow (m /h)


Fraction of CO2 in reach amine

10.47

outlet

1.62

absorber (mol %)
Regenerator pressure (bara)

1.5

Number of stages

10

Regenerator diameter (m)

0.609

Section height (m)

6.1

Reboiler duty (MMBTU/h)


Fraction of CO2

4.529

outlet regenerator (mol %)

0.2

Considering the above calculation results, the sizing results of the worst case are
considered:
Table 14: Results of sizing of regenerator column
Design Parameter

Value

Diameter of column (m)

0.61

Height of column (m)

6.1

Number of plates

10

4.7.4LEANMICRULOTPS
The data of lean amine circulation pumps are summarized in the following table:
Table 15: Data for lean amine circulation pumps calculation
Design Parameter

Unit

Value

Volume flow for the amine solutions

m /h

10.47

Suction pressure

bara

1.4

Discharge pressure

bara

32.2

Vapor pressure

bara

Mass density

Kg/m

0.43
3

1009

Sizing results are shown in the table given bellow:


Table 16: Lean amine circulation pumps main design parameters
Design Parameters

002/AR11/12

Unit

Value

Hydraulic power

kW

8.214

Electrical power

kW

14

04/10

NO.
REV.
0
PAGE: 28 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Design Parameters
HMT

Unit

Value

mCE

302

4.8SNIZGOFTHEACXR
4.8.1SZINGOFLEAMRC
The sizing of the lean amine air cooler is performed using the software HTFS.
The data of lean amine air cooler are summarized in the following table:
Table 17: Calculation data of lean amine air cooler
Design Parameter
Unit
Temperature of amine solution inlet air
C
cooler
Temperature of amine solution outlet air
C
cooler
Amine solution flow rate
Kg/h
Air cooler inlet pressure

Value
80
40
9623.16

bar

32.2

Sizing results are mentioned in the table given bellow:


Table 18: Lean amine air cooler main design parameters
Design Parameter

Unit

Value

Tubes per bundle

45

Tube passes

4
2

Area required

Tube length

745
9.74

See TEMA sheet of amine air cooler in appendix 6.

4.8.2SZINGOFCRH/LEAMTXNGR
The sizing of the rich/lean amine heat exchanger is performed using the software
HTFS.
The data of rich/ lean amine heat exchanger are summarized in the following table:
Table 19: Calculation data of lean/rich amine heat exchanger
Design Parameter

Unit

Value

Temperature of rich amine inlet heat exchanger


Temperature of rich amine outlet heat
exchanger
Temperature of lean amine inlet heat exchanger

40.25

75

112

Kg/h

10055.72

Rich amine flow rate

002/AR11/12

04/10

NO.
REV.
0
PAGE: 29 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Design Parameter
lean amine flow rate
Heat exchanger inlet pressure

Unit

Value

Kg/h

9623.16

bar

Sizing results are mentioned in the table given bellow:


Table 20: Calculation results of lean/rich amine heat exchanger
Design Parameter
Tube passes

Unit

Value

2
2

Area required

Tube length

7.1
3.048

See TEMA sheet of rich/ lean amine heat exchanger in appendix 6.


4.8.3SZINGOFREATCDS
The data of condenser are summarized in the following table:
Table 21: Design parameters of amine condenser
Design Parameters

Unit

Value

Temperature inlet condenser

99.5

Temperature outlet condenser

60

Condenser inlet pressure

bar

1.2

kg/h
MMbtu/
hr

1525.12

flow rate
Heat duty

2.26

4.8.4SZINGOFREATBL
The data of Regenerator Reboiler are summarized in the following table;
Table 22: Reboiler main design parameters
Design Parameters
Temperature inlet Reboiler
flow rate

Unit

Value

112.5
11598.5
2
1.6

kg/h

Reboiler inlet pressure


Heat duty

bar
MMbtu/
hr

4.472

4.8.5SZINGOFAMELSHDRU
The sizing of amine flash drum is determined by referring to standard DEP.
The data of amine flash drum are summarized in the following table.
Table 23: Amine flash drum input data
002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Design Parameters
Mass flow rate

Unit

Inlet vessel

kg/h

9717.08

Volumetric flow rate

m /h

Pressure

bara

11.23
3

Temperature

40

Mass density

kg/m3

NO.
REV.
0
PAGE: 30 / 63

Liquid outlet
9661.4

Gas outlet
55.68

1.87

9.36

40

40

1084

1.593

The results of sizing are summarized in the following table:


Table 24: Amine flash drum sizing results
Design Parameter

Unit

Value

Diameter

0.75

Length

3.37

5. REVISION OF TEG UNIT DESIGN


5.1REVISION OF TEG CONTACTOR DESIGN
Using GPSA standard
The review of the TEG contactor is performed using the GPSA standard, the
calculation procedures are attached in Appendix 4.
The integral scrubber is already modeled as per the actual process scheme.
The table below shows integral scrubber dimensions:
Table 25: integral scrubber dimensions

Parameter

Unit

Value

Diameter

0.9144

Height

2.286

The following data are considered for contactor sizing:

Table 26: Glycol contactor Input parameters

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Parameter

NO.
REV.
0
PAGE: 31 / 63
Value

Contactor operating pressure


(bara)
Gas density (kg/m3)

23.65

Liquid density (kg/m3)

1106

Gas flow rate (Sm3/h)

18630

30

The main results are summarised in the following table:


Table 27: Glycol contactor Main Results

Parameter

Value

The water content inlet contractor


(mg/Sm3)

2835.19

The water content outlet


contractor (mg/Sm3)
Water removal (kg/h)

133.93
50.32

Glycol flowrate (m3/hr)

0.78

Diameter (m)

0.84

Number of trays

Tray spacing (m)

0.61

Absorber height (m)

4.88

Using HYSYS simulation

A HYSYS simulation performed to model the actual contactor T710 including its
diameter, internals (bubble cap trays) estimate the TEG contactor size considering
the following input data:
Table 28: Glycol contactor main simulation Input data

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Parameter

NO.
REV.
0
PAGE: 32 / 63

Value

Contactor pressure (bara)

30

Gas Temperature inlet


contactor (C)
Maximum Glycol flowrate
(m3/hr)
Gas processed flowrate
(MMSCFD)

45
0.8
15.77

Absorber diameter (m)

0.914
Bubble Cap
Trays

Trays type
Number of trays

Section height (m)

4.877

Tray spacing (m)

0.61

The main Simulation results are shown in the following table:


Table 29: Glycol contactor Main sizing Results
Parameters

Water
(kg/h)
Water
(ppm)
Water
(kg/h)
Water
(ppm)

Value

content inlet contactor

50.17

content inlet contactor

3235.8

content outlet contactor

1.71

content outlet contactor

111.3

The water content downstream the Glycol contactor T-710 is 111.3 ppm, It doesnt
comply with STEG requirement (Wc <80 ppm), for this raison a design review of
regeneration unit with the expected gas flow rate is made available in next
paragraph.
5.2CURRENT TEG REGENERATION UNIT DESIGN
5.2.1GLYCOFASHTNKPERIGDMOSN
The data of Glycol flash drum are summarized in the following table.
Table 30: Glycol flash drum operating data
Design Parameters
Mass flow rate
Volumetric flow rate
Temperature
002/AR11/12

Unit

Inlet vessel

kg/h

873

3.93
80

m /h
C

Liquid outlet
870

Gas outlet
3

0.813

2.577

80

80
04/10

NO.
REV.
0
PAGE: 33 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Design Parameters
Mass density

Unit
kg/m

Inlet vessel

Liquid outlet
1070

257.5

Gas outlet
1.168

The dimensions of Glycol flash drum are summarized in the following table:
Table 31: Glycol flash drum dimensions

Diameter

Existing
Value
0.406

Length

1.5

Design Parameter

Unit

5.2.2HEATXCHNGRSIPUD
5.2.2.1

AIR/GLYCOHETXNE320

The data of Glycol air cooler are summarized in the following table.
Table 32: Calculation data of Glycol air cooler
Design Parameter

Unit

Value

Temperature of glycol inlet air cooler

187.4

Temperature of glycol outlet air cooler

140

Glycol flow rate

Kg/h

897.9

Air cooler inlet pressure

bar
Btu/
hr

1.103

Duty

5.2.2.2

120000

GLYCO/HEATXNR

The data of rich glycol/lean glycol heat exchanger are summarized in the following
table.
Table 33: Calculation data of glycol/ glycol heat exchanger
Design Parameter
Temperature of lean glycol inlet heat
exchanger
Temperature of
lean glycol outlet heat
exchanger
Temperature of rich glycol inlet heat
exchanger
Temperature of
rich glycol outlet heat
exchanger
heat exchanger inlet pressure

5.2.2.3

Unit

Value

199.8

188

70

80

bar

5.5

GLYCOREN/DASMIZ

The data of glycol regen/dry gas economizer are summarized in the following table:

002/AR11/12

04/10

NO.
REV.
0
PAGE: 34 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Table 34:Glycol regen/Dry gas economizer heat exchanger data


Design Parameter
Unit
Temperature of
glycol regen inlet heat
C
exchanger
Temperature of
glycol regen outlet heat
C
exchanger
Temperature of dry gas inlet heat exchanger
C

Value
139
54
48

Temperature of dry gas outlet heat exchanger

53.4

heat exchanger inlet pressure

bar

30.1

5.3GLYCOUMPS
The data of glycol pumps are summarized in the following table:
Table 35: Data for Glycol pumps sizing
Design Parameter

Unit

Value

Volume flow for the glycol

GPH

210

Suction pressure

bara

1.1

Discharge pressure

bara

30

138

Suction temperature
Vapor pressure
Mass density

bara
Kg/m

1.18
3

1087

5.4CONDESRCILXHAG
The data of condenser are summarized in the following table:
Table 36: Main Design parameters of Glycol unit condenser
Design Parameters
Type
Heat duty

Unit

Value

Coil exchanger

Btu/hr

47250

5.5REGNTROARBLI
The data of Regenerator Reboiler are summarized in the following table;
Table 37: Reboiler main design parameters
Design Parameters
Type
Heat duty

002/AR11/12

Unit
Btu/hr

Value
Fired heater
exchanger
480000

04/10

NO.
REV.
0
PAGE: 35 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART


5.6LGSTRNIPUCOML

The lean glycol downstream the reboiler passes through the Lean Glycol
Stripping Gas Column that contacts the lean glycol with dry gas from flash drum,
further removing water from the glycol to the higher purities required by this
operation, the main design data for the LG stripping gas are summarized in the
following table:
Table 38: LG stripping gas data
Unit

Value

psia

20

Inlet temperature

80

Column outer diameter

0.273

Column height

1.4

Internals

packed

Packing Type

1 random packing
pall rings

Design Parameters
Inlet pressure

5.7LGLSTICOUMN:
The vapors leaving the glycol reboiler are contacted with cooler liquid on random
packing in the TEG still column and are further cooled by the still column condenser
to provide reflux to minimize glycol losses out of glycol reboiler.
Table 39:LG still column data
Design Parameters

Unit

Value

psia

16

Inlet temperature

80

Column outer diameter

0.355

Column height

3.81

Internals

packed

Packing Type

1 random packing
pall rings

Inlet pressure

The maximum allowable reboiler stage temperature in the distillation column is


204.4c in order to avoid glycol characteristics degradation. the purity of the
regenerated glycol downstream of regeneration column is 96.25% , this leads to a

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 36 / 63

higher water content in the dry gas stream leaving the contactor. The lower purity is
the higher dry gas water content is.
The next step is to perform the regeneration process trouble shouting as long as
the lean glycol purity is low.
the following regeneration parameters has to be reviewed to improve regenerated
glycol purity:

stripping gas flowrate


stripping gas column design
still column design

5.8 REGENERATION PROCESS TROUBLE SHOUTING

5.8.1 STPRINGAFLOWE
when increasing stripping gas flowrate

feeding LG stripping column , it will

condense the heavier component ( TEG ) in the stream leaving reboiler stage ,and
the water vapour goes back to the still column and will be rejected from the top, as
a result the regenerated glycol purity is improved.
The proposed solution is to add additional amounts of stripping gas coming from
amine flush drum to the existing one coming from glycol flash tank.
The following process scheme shows the glycol purity improvement , to bring it
from 96.2% to 98.65% when increasing stripping gas flowrate.

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 37 / 63

The new regenerated glycol purity 98.65% is sweet able decrease the dry gas water
content from 111.3 ppmH2o to 64.4 ppmH2o so that it meets closely the STEG
requirement ( < 80 ppmH2o ).
The following process flow scheme shows the main simulation results using the
improved regenerated TEG purity.

The stripping gas column diameter shall be reviewed since the feed gas flowrate
increased
5.8.2 STPRINGACOLUMDE(TR)

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 38 / 63

The stripping gas column diameter is being recalculated via HYSYS software ( tray
sizing utitlity ), the actual stripping gas diameter is 0.27 m , and as per the attached
sizing results the diameter should be 0.3 m.
The following table shows the required stripping gas column design:

stripping gas column


Section Start

1__TS-1

Section End

3__TS-1

Internals

Packed

Section Diameter

(m)

0.3048

Max Flooding

(%)

X-Sectional Area

(m2)

8.45
7.297e002

Section Height

(m)

1.354

Section DeltaP

(bar)

---

DP per Length

(kPa/m)

---

Flood Gas Velocity

(m3/h-m2)

3320

(m/s)

0.9223

(kg)

47.4

Flood Gas Velocity


Estimated Mass of
Packing
Estimated Packing Cost
(US$)
HETP

66.30
(m)

0.4514

HETP Correlation
Packing Correlation

Norton
SLEv73

6. NEW CHILLING UNIT


6.1REFRIGERANT FLUID SELECTION
Propane is a proven refrigerant used in operation worldwide; it does not have ozone
depletion potential and a negligible direct global warming.
As shown from its envelope phase, this refrigerant is suitable for decreasing the
temperature of the gas to -36C.
The main physical and chemical properties of Propane are summarized in the table
below:
Table 40 : Chemical and Physical Properties of Propane

Refrigerant
Chemical
Formula
Molecular
weight
Boiling point
@1bar (C)
Danger
002/AR11/12

Propane
C3H8
44.09
-42
Extremely
04/10

NO.
REV.
0
PAGE: 39 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Refrigerant

Propane
flammable gas

Appearance
Skin
Corrosion/Irritati
on
/inhalation

Colorless
Not expected to
be irritating.
Not expected to
be irritating.
No classified
hazard
Protect from
sunlight. Store in
a well-ventilated
place

Eye Damage
Toxicity
Storage

6.2PROPANE RECEIVER
The sizing of Propane receiver drum is determined by referring to standard DEP.
The data of Propane receiver drum are summarized in the following table.
Table 41: Propane Receiver Input Data
Design Parameters

Unit

Inlet vessel

Liquid outlet

Gas outlet

Mass flow rate

kg/h

5741

0.58

5740

Volumetric flow rate

m /h

2514

0.0009

2514

Pressure

bara

1.06

1.06

1.06

Temperature

-39

-39

-39

2.3

585

2.3

Mass density

kg/m

The results of sizing are summarized in the following table:


Table 42: Propane Receiver Main sizing Data
Design Parameter

Unit

Value

Diameter

0.98

Height

2.25

6.3PROPANE COMPRESSOR
The main data required for compressor sizing are as follow:
Table 43 : Stage 1 Main Data

Property

002/AR11/12

Value

Gas Molecular Weight

44.1

Compressibility Factor

0.97

Gas Mass Flowrate (kg/hr)

5741

04/10

NO.
REV.
0
PAGE: 40 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Property

Value

Suction Temperature (C)

-37

Suction Pressure (bara)

1.1

Discharge Pressure (bara)

4.5

Duty (kW)

143
Table 44 : Stage 2 Main Data

Property

Value

Gas Molecular Weight

44.1

Compressibility Factor

0.93

Gas Mass Flowrate (kg/hr)

5758

Suction Temperature (C)

24.2

Suction Pressure (bara)

4.5

Discharge Pressure (bara)

19

Duty (kW)

165

6.4PROPANE CONDENSER
The sizing of the condenser is performed using the software HTFS (see Appendix8).
The main data required for the simulation are as follow:
Table 45: Propane Condenser Input Data
Inlet

Outlet

19

18.8

Temperature (C)

104

54

Flowrate (kg/hr)

5758

5758

Parameters
Pressure (bara)

The results of sizing are summarized in the following table:


Table 46: Propane Condenser Main sizing Data
Design Parameter
Heat Exchanged

Unit

Value

kW

391

6.5PROPANE ECONOMIZER VJ-4003:


The sizing of Propane economizer drum is determined by referring to standard DEP.
The data of Propane economizer drum are summarized in the following table.

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 41 / 63

Table 47: Propane Economizer Input Data


Design Parameters

Unit

Inlet vessel

Liquid outlet

Gas outlet

Mass flow rate

kg/h

5758

3387

2371

Volumetric flow rate

m3/h

239.6

12.4

233.2

Pressure

bara

4.7

4.7

4.7

Temperature

-0.4

-0.4

-0.4

24.03

530.1

10.17

Mass density

kg/m

The results of sizing are summarized in the following table:


Table 48: Propane Economizer Main sizing Data
Design Parameter

Unit

Value

Diameter

0.45

Height

8.44

6.6GAS/PROPANE HEAT EXCHANGER EJ-4003


The sizing of the Gas/Propane is performed using the software HTFS (see
Appendix8).
The main sizing results of this heat exchanger are summarized in the table below:
Table 49: Gas/Propane Exchanger Main sizing Data
Design Parameter

Unit

Value

Exchange area

m2

19.5

Heat exchanged

kW

279.9

92

Shell ID

mm

336

Length

3.65

Tube Number

6.7GAS/GAS OUTLET COLD SEPARATOR HEAT EXCHANGER EJ-4001A


The sizing of the Gas/Gas Outlet cold separator is performed using the software
HTFS (see Appendix8).
The main sizing results of this heat exchanger are summarized in the table below:
Table 50: Gas/Gas Outlet Cold Separator heat Exchanger Main sizing Data
Design Parameter

002/AR11/12

Unit

Value

Exchange area

m2

8.5

Heat exchanged

Kw

211.4

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Design Parameter

NO.
REV.
0
PAGE: 42 / 63

Unit

Value

Tube Number

34

Number of tube passes per shell

mm

193.68

Shell ID

6.8GAS/LIQUID HEAT EXCHANGER EJ-4002


The sizing of the Gas/Liquid is performed using the software HTFS (see Appendix
8).
The main sizing results of this heat exchanger are summarized in the table below:
Table 51: Gas/Propane Exchanger Main sizing Data
Design Parameter

Unit

Value

Exchange area

m2

2.4

Heat exchanged

Kw

40.8

Tube Number

36

Number of tube passes per shell

Shell ID

mm

193.68

Length

1.22

6.9COLD SEPARATOR
The sizing of cold separator drum is determined by referring to standard DEP.
The data of cold separator drum are summarized in the following table.
Table 52: Cold Separator Input Data
Design Parameters

Unit

Inlet vessel

Liquid outlet

Gas outlet

Mass flow rate

kg/h

5616

1105

4511

Volumetric flow rate

m /h

30.53

3.26

27.27

Pressure

bara

85.21

85.21

85.21

Temperature

-35

-35

-35

183.9

338.2

165.4

Mass density

kg/m

The results of sizing are summarized in the following table:

Table 53: Cold Separator Main sizing Data


Design Parameter
Diameter

002/AR11/12

Unit

Value

0.39

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Design Parameter

Unit

NO.
REV.
0
PAGE: 43 / 63
Value

7. NITROGEN SKID
Option 1: Nitrogen injection only for the sales gas only
Table 54: Sales gas Nitrogen Skid main sizing Data
Design Parameter

Unit

Value

Nm3/h

181

Pressure

bar

85

Temperature

< 45

Purity

> 98

Nitrogen flowrate

Option 2: Nitrogen injection inlet the compressor for the total


gas flow rate
Table 55: Nitrogen Skid main sizing Data
Design Parameter

Unit

Value

Nm3/h

558

Pressure

bar

28.5

Temperature

< 45

Purity

> 98

Nitrogen flowrate

8. SIZING OF PIPELINE

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 44 / 63

A sensitive study is performed for different pipeline diameters (4 inch, 6 inch, 8


inch, 10 inch and 12 inch) to select the appropriate diameter for transferring the
treated gas from the EBB plant to the STEG network.
Simulation hypotheses are presented in following table:
Table 56: Simulation Hypotheses

Property

Value

Distance From the CPF to tie-in


point (km)
Elevation

Difference

(m)

[estimated]
Required Pressure in the tie-in
point with STEG Network (bara)
Pipeline Roughness (mm)

onshore

temperature (C)
Gas Flowrate (mmscfd)

5
76
0.045

Thermal Conductivity (W/m2.K)


Mean

25

ground

45
20
5.72

The results of this simulation are shown in the figures below:

002/AR11/12

04/10

NO.
REV.
0
PAGE: 45 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Figure 6: Pressure Profile of gas export pipeline

002/AR11/12

04/10

NO.
REV.
0
PAGE: 46 / 63

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

Figure 7: Velocity Profile of gas export pipeline

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 47 / 63

The results of this simulation for different pipeline diameter are summarized below:
Table 57: Pipeline calculation Results

Diameter
(inch)

4
6
8
10
12

Gas flow
rate
(MMSCFD)
5
5
5
5
5

Pressure
downstre

Loading
Pressure

am PCV
(bara)
85.1
77.3
76.27
76.11
76

at tie-in
point
(bara)
76
76
76
76
76

Velocit
y (m/s)

2.36
1.163
0.664
0.426
0.296

Max
velocity
(m/s)
24
24
24
24
24

Pressure

Max

drop

pressure

(bar/100

drop

m)

(bar/100m)

0.0364
0.0052
0.001
0.0004
0

0.27
0.27
0.27
0.27
0.27

According to NORSOK standard for gas line sizing shown in appendix 5 the selected
pipeline diameter is 4.

9. CONCLUSION
The product streams of Ecumed gas treatment plant are in compliance with STEG
requirements due to the follwoings
Amine unit ( sweetning gas unit ) to remove carbon dioxide (CO2) present in
raw gas.
Increasing the stripping gas flowrate in the dehydration unit in order to
improve TEG purity , as a result the water content removal increases
significantly to reach 31.26 PPMH2O.
A chilling unit is installed to cool down the gas leaving dehydration unit . this
leads to the following :
-additional amount of condensate ( heavy components in the treated gas )
approximately 400 BBl/day.
-decreasing the higher heating value as well as the wobbe index to meet STEG
requirements.
Nitrogen injection into sales gas stream to comply with STEG wobbe index
specification.
The following table shows sales gas specifications versus STEG requirements:
Table 58: Sales gas specifications versus STEG requirements

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 48 / 63

Treated Gas

STEG
Specifications

Pressure (barg)

76

75 at tie in point

Temperature (C)

20

10 - 50

5.064

Parameter

Molar flow [MMSCFD]


Higher
heating
(kcal/Nm3)

Value

Wobbe Index (kcal/Nm3)


Mass Density (kg/m3) @ TP

9300 - 10228

10,056

11961 - 12640

12,397
81.9

28.01

Water content (ppm)

64.4

< 80

CO2 content (% mol)

0.3

< 0.5

H2S content (mg/Nm3)

<2

H2 and N2 content (% mol)

<6

O2 content (% mol)

Molecular Weight

The following table shows recovered condensate specification :


Table 59: Condensate specification

Actual

Property
volume flow (barrel/day)

50C/1Atm

808.5

True VP (bara) @ 37.8C

0.7269

Reid VP (bara) @ 37.8 C

0.6055

Mass Density (kg/m3)


Viscosity (cP)

002/AR11/12

Value

684.1
0.3981

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 49 / 63

10. APPENDICES
10.1

APPENDIX 1: RECIRCULATION RATE OF DEA SOLUTION

In case of using the DEA solution the recirculation rate is calculated by the following:

LDEA =

192 MM Xa
WT ML

Where:
LDEA: DEA solution minimum recirculation rate (USGPM)
MM : gas flow MMSCFD
WT : amine solution weight percent circulated
ML : mol loading, moles acid gas/mole
Xa : required reduction in total acid gas fraction.
: Solution density (lb/gal)

10.2

APPENDIX 2: AMINE CONTACTOR DIAMETER CALCULATION

The amine contactor column diameter is determined referring to the given correlation:

Dc=10750

Q
P

Where:
Dc = Contactor diameter in mm.
P = Contactor pressure
Q = gas processed flow rate

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART


10.3

NO.
REV.
0
PAGE: 50 / 63

APPENDIX 3: AMINE REGENERATOR DIAMETER CALCULATION

The column diameter is determined using the given correlation

Dr=160 L
Where:
L =

Amine circulation rate (m3/h) = is the design capacity of the lean amine
circulation pump 330-PA-001A/B

Dr = Regenerator diameter in mm.

10.4

APPENDIX 4: GPSA STANDARD FOR TEG CONTACTOR SIZING

The quantity of water that shall be removed is:

W r =W iW o

(mg water/Sm3 wet gas)

The water content of sweet gas respectively inlet and outlet contractor can be
calculated using BUKACEK correlation:
W i=

A1
+ B1
P

W o=

A2
+ B2
P

With:
P:

The operating pressure at the TEG contactor (bara)

A1 ,

A 2 , B1 ,

B2

: constant at the operating temperature Using the KREMSER &

BROWN hart, we can define the absorption ratio (Ar=3.5)


Given this ratio the lean glycol flow rate can be determined using this correlation:

QTEG =

Wo

( E11 )

g (mg/h)
Arm

With:
E:

Efficiency of the absorber

WO : Water content outlet contractor (mg/Sm3)

m
g

: Gas flow rate (Sm3/h)

To calculate the contactor diameter, the following correlation can be used:

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

0.5
G=C( g( l g))

NO.
REV.
0
PAGE: 51 / 63

(kg/m.h)

g : Gas density (kg/m3)


l : Liquid density (kg/m3)
The contactor section can be calculated by the following equation:

S=

m g
G

With:

m
g

: Gas flow rate (kg/h)

The contactor diameter can be calculated by the following equation:

D=
10.5

4S

(m)

APPENDIX 5: NORSOK STANDARD FOR SIZING OF GAS LINE

In lines where pressure drop is not critical, gas velocity shall not exceed limits which may
create noise or vibrations problems. As a rule of thumb the velocity should be kept below:

0.43

()

V =175
Where:

V : The maximum velocity of gas to avoid noise in m/s


: The density of gas in kg/m3
or 60 m/s, whichever is ever the lowesr.

002/AR11/12

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

10.6

APPENDIX 6: AMINE UNIT HEAT EXCHANGERS TEMA SHEETS

002/AR11/12

NO.
REV.
0
PAGE: 52 / 63

Rich / Lean Amine heat exchanger

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

002/AR11/12

NO.
REV.
0
PAGE: 53 / 63

Amine Air cooler

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

10.7

002/AR11/12

NO.
REV.
0
PAGE: 54 / 63

APPENDIX 7: GLYCOL UNIT HEAT EXCHANGERS TEMA SHEETS

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

002/AR11/12

Gas/glycol heat exchanger

Gas/glycol heat exchanger

NO.
REV.
0
PAGE: 55 / 63

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

002/AR11/12

NO.
REV.
0
PAGE: 56 / 63

glycol/ glycol heat exchanger heat exchanger


04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

002/AR11/12

NO.
REV.
0
PAGE: 57 / 63

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART


10.8

APPENDIX 8: CHILLING UNIT HEAT EXCHANGERS TEMA SHEETS

002/AR11/12

NO.
REV.
0
PAGE: 58 / 63

Gas/Propane EJ-4003 TEMA Sheet

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

002/AR11/12

NO.
REV.
0
PAGE: 59 / 63

Gas/Gas Outlet cold separator EJ-4001A TEMA Sheet

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

002/AR11/12

NO.
REV.
0
PAGE: 60 / 63

Gas/liquid EJ-4002 TEMA Sheet

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

NO.
REV.
0
PAGE: 61 / 63

Air-Cooled Heat Exchanger Specification Sheet ( condenser -chilling unit )

10.9
002/AR11/12

APPENDIX 9: STRIPPING GAS COLUMN DESIGN


04/10

Tray Sizing: stripping gas column sizing ( diamater)


EQUIPMENTS SIZING REPORT FOR THE FIRST PART
SETUP

NO.
REV.
0
PAGE: 62 / 63

Tray Section: TS-1 @COL5

Liquid Draw: 0.00 %

Section_1
Section Start

1__TS-1

Section End

3__TS-1

Internals

Packed

Mode

Design

Active

Off

Status

Complete

Design Limit

Chanelling

Limiting Stage

1__TS-1

Include Vapor Head

Off

SPECIFICATIONS
Section_1
Section Start

1__TS-1

Section End

3__TS-1

Internals
Mode

Packed

LIQUID PROFILE (FROM TRAY)

Design

Number of Flow Paths


1__TS-1

Section Diameter (m)


Mass Flow (kg/h)
Tray Spacing (m)
Liquid Flow (m3/s)
Tray Thickness (mm)
Molecular Weight
High Capacity Nye Tray
Temperature (C)
Foaming Factor

922.6
2.651e-004

----

-144.0
Off
200.9
1.000

Max Delta P (ht of liq)

SLEv73

HETP (m)

0.4514 *

PACKED RESULTS
Viscosity (cP)

Internals

912.1

2.634e-004

2.607e-004

145.8

147.2

199.4

197.0

Pall Rings (Metal, random) 1_inch

Density (kg/m3)

Section End

918.8

80.00

Packing Correlation

Surface Tension
(dyne/cm)
Section Start
VAPOUR PROFILE

3__TS-1

0.4086 kPa/m

Max Flooding (%)

Packing Type

2__TS-1

966.9

968.9

971.8

0.5994

0.6072

0.6246

29.49

29.70

29.37
Section_1

(TO TRAY)

1__TS-1
3__TS-1
Packed
1__TS-1

2__TS-1

3__TS-1

Section Diameter
(m)(kg/h)
Mass Flow

0.3048
17.79

13.96

7.215

Max Flooding
(%) (ACT_m3/h)
Gas Flow

20.47 8.45

15.78

8.460

X-Sectional
Area (m2)
Molecular
Weight

7.297e-002
32.14

31.27

21.18

Section Height
(m)
Temperature
(C)

199.41.354

197.0

57.25

Section DeltaP
Density(bar)
(kg/m3)
DP per Length
(kPa/m)
Viscosity
(cP)
Flood Gas
Velocity
(m3/h-m2)
Fluid
Pressure
(bar)
Flood Gas Velocity (m/s)

0.8691

--

0.8849

0.8528

--

1.695e-002

1.212e-002

1.0143320

1.058

1.103

1.615e-002

0.9223

Estimated # Pieces of Packing

4901

Estimated Mass of Packing (kg)

47.4

Estimated Packing Cost (US$)

66.30

HETP (m)
HETP Correlation

002/AR11/12

Packing Correlation
Packing Type

0.4514
Norton
SLEv73
Pall Rings (Metal, random) 1_inch

04/10

EQUIPMENTS SIZING REPORT FOR THE FIRST PART

10.10

NO.
REV.
0
PAGE: 63 / 63

TIE-IN PROCEDURE TO ADD AMINE FLASH VAPOR TO STRIPPING GAS

PROCESS
Please refer to the piping and instrumentation diagram entitled PROCESS FLOW
GLYCOL DEHYDRATION
PACKAGE , document No R02-06-DWG-PR-00-004.
The Tie in point is located downstream of the ESDV-410 valave and the upstream of
the valve NE- 6008 ( the line in which mounted a restriction orifice RO-410).
The isolation work is guaranteed by closing , the ESDV-410 and valve NE- 6008.

002/AR11/12

04/10

Vous aimerez peut-être aussi