Académique Documents
Professionnel Documents
Culture Documents
November6,2015
TABLEOFCONTENTS
TableofContents..........................................................................................................................................ii
1.0
Introduction.....................................................................................................................................1
1.1
Background......................................................................................................................................2
2.0
PurposeandNeedfortheProject...................................................................................................6
3.0
DescriptionofProposedProject......................................................................................................7
4.0
DescriptionofPotentialRouteAlternatives..................................................................................10
4.1
BardwellGeographicGroup...........................................................................................................12
4.2
CorsicanaGeographicGroup.........................................................................................................13
4.3
IH45GeographicGroup................................................................................................................14
4.4
MiddleGeographicGroup.............................................................................................................15
4.5
HockleyGeographicGroup............................................................................................................16
4.6
DowntownHoustonGeographicGroup........................................................................................18
5.0
AlternativesEvaluation..................................................................................................................19
5.1
LevelIScreening............................................................................................................................19
5.2
LevelIScreeningConclusion..........................................................................................................22
5.3
LevelIIScreening...........................................................................................................................24
5.4
LevelII,StageIEnvironmentalConstraintsScreening...................................................................24
5.5
LevelII,StageIEnvironmentalConstraintsScreeningResults......................................................29
5.6
LevelII,StageIICostandConstructionScreening.........................................................................32
6.0
Conclusion......................................................................................................................................35
LISTOFTABLES
Table51:LevelIScreeningResults............................................................................................................21
Table52:RatioMethodology....................................................................................................................24
Table53:EnvironmentalEvaluationCriteria.............................................................................................26
Table54:LevelII,StageIEnvironmentalConstraintsScreeningResults..................................................30
Table55:LevelII,StageIEnvironmentalConstraintsScreeningResultsandStandardDeviation...........32
Table56:LevelII,StageIICostandConstructionScreeningResults........................................................34
Table61:DraftAlignmentAlternativeDevelopmentSegmentation........................................................35
Table62:DraftEISEndtoEndAlignmentAlternatives............................................................................37
ii
LISTOFFIGURES
Figure11:UtilityCorridor............................................................................................................................4
Figure31:ShinkansenTrainset....................................................................................................................7
Figure32:AtgradeTypicalSection.............................................................................................................8
Figure33:RetainedFillTypicalSection.......................................................................................................8
Figure34:ViaductTypicalSection...............................................................................................................9
Figure41:PotentialRouteAlternatives.....................................................................................................11
Figure42:BardwellGeographicGroup.....................................................................................................12
Figure43:CorsicanaGeographicGroup....................................................................................................13
Figure44:IH45GeographicGroup...........................................................................................................14
Figure45:MiddleGeographicGroup........................................................................................................15
Figure46:HockleyGeographicGroup.......................................................................................................17
Figure47:DowntownHoustonGeographicGroup...................................................................................18
Figure51:PotentialRouteAlternativesFRACarriedForwardtoLevelIIScreening................................23
Figure52:StandardDeviationExample....................................................................................................31
Figure61DraftAlignmentAlternativesCarriedForwardtotheDraftEIS................................................36
Figure62:DraftEISEndtoEndAlignmentAlternativeA..........................................................................38
Figure63:DraftEISEndtoEndAlignmentAlternativeB..........................................................................39
Figure64:DraftEISEndtoEndAlignmentAlternativeC..........................................................................40
Figure65:DraftEISEndtoEndAlignmentAlternativeD.........................................................................41
Figure66:DraftEISEndtoEndAlignmentAlternativeE..........................................................................42
Figure67:DraftEISEndtoEndAlignmentAlternativeF..........................................................................43
APPENDICES
AppendixAGISMethodology
LISTOFACRONYMS/ABBREVIATIONS
ACS
BA
BNSF
CAD
CEQ
CR
CS
DH
EIS
EJ
FEMA
FHWA
FM1488
FRA
FTA
GIS
GNIS
IH10
IH45
IH610
AmericanCommunitySurvey
BardwellGeographicGroup
BNSFRailroad
computeraideddesign
CouncilonEnvironmentalQuality
CorsicanaGeographicGroup
CommonSegmentGeographicGroup
DowntownHoustonGeographicGroup
EnvironmentalImpactStatement
EnvironmentalJustice
FederalEmergencyManagementAgency
FederalHighwayAdministration
FarmtoMarket1488
FederalRailroadAdministration
FederalTransitAdministration
GeographicInformationSystems
GeographicNamesInformationService
InterstateHighway10
InterstateHighway45
InterstateHighway610
iii
HC
km/h
kV
MD
mph
MPO
NEPA
NHD
NLCD
NRCS
NRHP
NWI
ROW
SH99
SSURGO
STB
TCEQ
TCR
THC
TPWD
TxDOT
TXNDD
UPRR
US290
USACE
USFWS
HockleyGeographicGroup
kilometerperhour
kilovolt
MiddleGeographicGroup
mileperhour
MetropolitanPlanningOrganization
NationalEnvironmentalPolicyAct
NationalHydrographyDataset
NationalLandCoverDataset
NationalResourcesConservationService
NationalRegisterofHistoricPlaces
NationalWetlandInventory
RightofWay
StateHighway99
SoilSurveyGeographicDatabase
SurfaceTransportationBoard
TexasCommissiononEnvironmentalQuality
TexasCentralHighSpeedRailway
TexasHistoricalCommission
TexasParksandWildlifeDepartment
TexasDepartmentofTransportation
TexasNaturalDiversityDatabase
UnionPacificRailroad
U.S.Highway290
U.S.ArmyCorpsofEngineers
U.S.FishandWildlifeService
iv
1.0 INTRODUCTION
This report forms the framework for conducting an environmental impact analysis in accordance with
the National Environmental Policy Act (NEPA) and its implementing regulations. The purpose of this
reportistodocumenttheFederalRailroadAdministrations(FRA)independentevaluationofpotential
routealternativesfortheproposedDallastoHoustonHighSpeedRailProject(Project).
FRAinitiatedaNEPAevaluationofTexasCentralHighSpeedRailway,LLCsanditsaffiliates(TCRorthe
Proponent) proposal to construct and operate a private, forprofit, highspeed passenger rail system
connecting Dallas and Houston using the Japanese N700I Tokaido Shinkansen highspeed rail
technology.TheProjectencompassesanapproximately240milelongcorridorbetweenthetwocities.
TCRs proposed highspeed rail system requires a fully sealed corridor with gradeseparated crossings
anddedicatedrightofway(ROW)thatisapproximately125feetwideinordertoaccommodateatwo
track railroad and an access road. It requires a closed system, meaning that the train must run on
dedicatedhighspeedrailtracksforpassengerrailserviceonlyandcannottravelonexistingorplanned
freightraillinesorsharetrackswithotherpassengerservices,suchasAmtrak.
FRAhastheauthoritytoregulatethesafetyofrailroads,includingtheProject.FortheProject,FRAmay
issueaRuleofParticularApplicability(regulationsthatapplytoaspecificrailroadoraspecifictypeof
operation),aseriesofwaivers,oranotheractiontoensuretheProjectisoperatedsafely.Thisregulatory
action(s)constitutesafederalactionrequiringanenvironmentalreviewunderNEPA.
AsrequiredbyNEPA,FRAinitiatedanEnvironmentalImpactStatement(EIS)todocumentthepossible
environmentalimpactsoftheProject.Thisevaluationisrequiredby42U.S.C.4321etseq.,Councilon
Environmental Quality (CEQ) NEPA regulations (40 CFR 15001508), and the FRAs implementing
regulations,FRAProceduresforConsideringEnvironmentalImpacts,assetforthin64FR28545(1999).
AnEISisbeingpreparedbytheFRAincooperationwithFederalHighwayAdministration(FHWA),U.S.
Army Corps of Engineers (USACE), Federal Transit Administration (FTA), the Surface Transportation
Board (STB), and U.S. Fish and Wildlife Service (USFWS). The Texas Department of Transportation
(TxDOT)isprovidingtechnicalassistancetoFRAinthepreparationoftheEIS.
Supporting the early development of the EIS, this report defines the scope of the Project and the
reasonablealternativesFRAwillevaluateintheEIS.FRAsalignmentalternativesanalysisreflectsFRAs
independentevaluationandjudgmentinitscapacityasthefederalleadagencyfortheEIS.Giventhat
TCR, the Proponent of the Project, is a private railroad, it is incumbent on TCR to develop feasible
alternatives that would achieve its operational criteria for FRAs consideration and evaluation. This
report serves as the basis for evaluating those potential route alternatives in relation to the Projects
purpose and need. FRA concludes the report by identifying the potential route alternatives, or build
alternatives that fully meet the Projects purpose and need and that FRA will carry forward for
evaluationintheDraftEIS.TheDraftEISpotentialalignmentswillcontinuetoberefinedandevaluated
as potential environmental impacts are identified, as required by NEPA. The No Build or No Action
Alternative,asrequiredbyNEPA,willserveasthebasisforcomparisonoftheenvironmentalimpactsof
thebuildalternativesandwillbeevaluatedintheDraftEIS.
Thisdocumentprovidesthe:
Projectbackground
Evaluationofpotentialroutealternatives
Alternativesconsideredbuteliminatedfromfurtherconsideration
Alternativescarriedforwardforfurtherconsideration
1.1
Background
A formal alternatives analysis is critical to the decisionmaking process and to ultimately fulfill
obligations under NEPA. Section 102(C) of NEPA requires that agencies include in every
recommendation or report on proposals for legislation and other major federal actions significantly
affectingthequalityofthehumanenvironment,adetailedstatementbytheresponsibleofficialon:
(i) Theenvironmentalimpactoftheproposedaction;
(ii) Any adverse environmental effects which cannot be avoided should the proposal be
implemented;
(iii) Alternativestotheproposedaction;
(iv) Therelationshipbetweenlocalshorttermusesofman'senvironmentandthemaintenanceand
enhancementoflongtermproductivity;and
(v) Any irreversible and irretrievable commitments of resources which would be involved in the
proposedaction,shoulditbeimplemented.
CEQNEPAregulationsregardingtheanalysisofalternativesrequireagenciesto:
(a) Rigorously explore and objectively evaluate all reasonable alternatives, and for alternatives
which were eliminated from detailed study, briefly discuss the reasons for their having been
eliminated;
(b) Devote substantial treatment to each alternative considered in detail including the proposed
actionsothatreviewersmayevaluatetheircomparativemerits;
(c)Includereasonablealternativesnotwithinthejurisdictionoftheleadagency;
(d)Includethealternativeofnoaction;
(e) Identify the agency's preferred alternative or alternatives, if one or more exists, in the draft
statementandidentifysuchalternativeinthefinalstatementunlessanotherlawprohibitsthe
expressionofsuchapreference;and
(f) Include appropriate mitigation measures not already included in the proposed action or
alternatives.(40CFR1502.14)
As described in FRAs Corridor Alternatives Analysis Technical Report, dated August 10, 2015 and
available online at https://www.fra.dot.gov/eLib/Details/L16978), FRA undertook a two stage
alternativesanalysisscreeningprocess.Thefirststageidentifiedcorridoralternativesfortheproposed
highspeedrailsystemfromwhichpotentialroutealternativeswithincorridorscouldbedeveloped.The
secondstageinFRAsalternativesanalysisscreeningprocessisdocumentedinthisreport.Theresultsof
thisalternativesanalysisprovidethebasisforindepthenvironmentalstudiesofthemostfeasibleand
practicalpotentialroutealternativesintheDraftEIS.
1.1.1 FRAsCorridorAlternativesAnalysis
FRAcompletedacorridorlevelalternativesanalysistoidentifyandevaluatethepotentialcorridorsthat
couldbecomealternativesintheEIS.Thisfirststepnarrowedtheuniverseofpotentialalternativesby
identifying viable highspeed rail corridors within which specific highspeed rail potential route
alternativescouldbedeveloped.
FRAdevelopedtherangeofpotentialcorridorsusingthehighspeedrailcorridorsidentifiedinprevious
studiesandthoseusingexistinglinearinfrastructurecorridors.FRAdidnotcompleteanyengineeringor
designworkaspartofthisanalysis.ThefourpotentialhighspeedrailcorridorsFRAevaluatedincluded:
BNSFCorridor
UPRRCorridor
IH45GreenfieldCorridor
UtilityCorridor
FRAalsoconsideredalternativestohighspeedrailservicethatincludedhigherspeedandconventional
speedrailservices,directbusservice,andexpansionofInterstateHighway45(IH45).
Through the corridor alternatives analysis, FRA determined that the Utility Corridor be retained for
further investigation of potential route alternatives during the next stage of the alternatives analysis.
The Utility Corridor follows the CenterPoint Energy and Oncor Electric Delivery highvoltage electrical
transmission lines (345 to 500 kilovolts (kV)). The utility easement does not extend into downtown
DallasordowntownHouston.TheeasementoriginatesnearPalmerandterminatesnearHockleytothe
south. Therefore, between Dallas and Palmer, the Utility Corridor follows and uses the Union Pacific
Railroad (UPRR) Corridor to the downtown Dallas area. Between Hockley and Houston, the Utility
CorridorfollowsandusestheUPRREurekaSubdivisionintodowntownHouston.Figure11showsthe
Utility Corridor, which includes the use of the UPRR Corridor, in the terminus areas in Dallas and
Houston.
FRAalsodeterminedthatportionsoftheBNSFRailroad(BNSF),UPRR,andIH45GreenfieldCorridorsbe
retained for further investigation in the event that constraints arise along the Utility Corridor that
warrant potential route alternatives within portions of these eliminated corridors that avoid the
constraints.
Figure11:UtilityCorridor
1.1.2 TCRsLastMileAnalysis
AspartofthisProject,TCRproposedterminusstationsinDallasandHoustonthatwouldserveintercity
travel demand and commerce, provide for economic redevelopment, and provide connectivity with
eachregionsmajortransitandroadwaysystems.TCRsstationanalysisisdocumentedinitsLastMile
Analysis Report (TCR 2015a), dated March 27, 2015, and available online at
http://www.texascentralhighspeedrail.com/page4/index.html.Initsreport,TCRsstatedgoalinlocating
stationswastominimizeimpacts,maximizemultimodalconnectivity,optimizeridershipwithrespectto
revenue,andoptimizeadjacentlandusestoprovidelongtermlocaldevelopmentopportunities.
TCR also determined that its stations should be configured to support nearterm operating goals and
allowforfutureexpansionsandextensions(stationsaswellastracks)sothattheProjectcouldserveas
anextendablepassengerrailnetworkspine,connectingwithregionaltransportationservices.
BothDallasandHoustonhavemultiplecommercialandeconomiccentersspreadacrosstheirrespective
metropolitanareas,includingeachhavingadowntowncentralbusinessdistrict.Thesemanycommercial
centersareservedbyhighlydevelopedhighwayandroadwaynetworks.Consequently,TCRdetermined
that it was appropriate to consider opportunities for downtown and suburban locations in Dallas
andHouston.TCRalsoidentifiedanintermediatestationtoservetheBryan/CollegeStationareaalong
theUPRRCorridorandaShiroStationareaalongtheUtilityCorridor.
Based on its screening criteria, TCR determined that the most viable terminus locations in Dallas and
HoustonalongtheUtilityCorridorareDowntownDallas(notedintheirreportasLastMileAlternativeC)
andU.S.Highway290/InterstateHighway610(US290/IH610)inHouston(notedintheirreportasLast
Mile Alternative B). TCR determined that a station near Shiro is viable due to its proximity to
Bryan/CollegeStationandHuntsville.
1.1.3 TCRsStep2ScreeningofAlternativeAlignments
AftercompletingitsStep1ScreeningofAlternativesandLastMileAnalysis,TCRinitiateditsnextlevelof
analysis to develop potential alignment alternatives within the Utility Corridor. TCR issued its Step 2
Screening of Alternative Alignments Report (TCR 2015b) dated November 5, 2015 (available online at
http://www.texascentralhighspeedrail.com/page4/index.html). In its report, TCR proposed a Base
AlignmentparallelingtheexistingCenterPointEnergyandOncorElectricDeliveryutilityeasementsand
recommended 21 potential route alternatives. TCR identified constraints along the Base Alignment,
including areas of environmental concern, construction complexity, geometric challenges, economic
impactandothermajorconcerns,"insixgeographicareasfromwhichitidentifiedthepotentialroute
alternatives.Thesepotentialroutealternativeswerecreatedusingthealignmentobjectivesanddesign
guidelinesdevelopedbyTCR.Thesixgeographicareasinclude:
Corsicana(CR)
Bardwell(BA)
InterstateHighway45(IH45)
Middle(MD)
Hockley(HC)
DowntownHouston(DH)
TCR completed a twophase alternatives analysis. In its Phase 1 Analysis, TCR quantitatively evaluated
theBaseAlignmentandthepotentialroutealternativesusingthefollowingcriteria:
5
Engineering:alignmentlengthandadjacencytotheexistingutilityline
Alignmentgeometry:superelevation,1totalnumberofcurves,andcurvesandspeedrestrictions
Viaductlengthandmajorstructures:totalviaductlengthandnumberofcomplexstructures
Crossings: major road crossings, moderate road crossings, minor road crossings, freight
crossings,andutilitycrossings
Hydrology: tier 1 hydrologic features Federal Emergency Management Agency (FEMA)
crossingsandtier2hydrologicfeaturesothercrossings
Environmental:streams,waterbodies andwetlands;naturalresourcesandlandcover;cultural
resources;environmentaljustice;andhazardoussites
In its Phase 2 Analysis, TCR qualitatively evaluated the Base Alignment and the potential route
alternativesusingprojectdeliveryconcerns.TCRsPhase2Analysisevaluationcriteriaincludedcapital
cost,constructionduration,andconstructability.
TCR concluded its Step 2 Screening of Alignment Alternatives Report (2015b) by recommending four
endtoendalignmentalternativestoFRAforfurtherevaluationintheDraftEIS.
2.0 PURPOSEANDNEEDFORTHEPROJECT
As defined by TCR, the purpose of the privately proposed Project is to provide reliable, safe and
economically viable passenger rail transportation using proven highspeed rail technology between
DallasandHouston.Itwouldprovideaconvenientandcompetitivealternativetoautomobiletravelon
IH45orairtravelbetweenthetwomajormetropolitanareasandintroducerailcapacityinthevicinity
ofthecorridor.ToachieveTCRseconomicviabilityandsafetyrequirements,theProjectmustmeetthe
followingtechnicalrequirements:
Technological: bullet train vehicle and operating procedures based on the N700I Tokaido
Shinkansen
Operational:approximate90minutetraveltimebetweenDallasandHouston,withachievable
speedsexceeding200milesperhour(mph)inafullysealedcorridor
Environmental:minimalimpactstothenaturalandbuiltenvironmentsbymaximizingadjacency
toexistinginfrastructureROW
FRA,inaccordancewithfederalrequirements,mustensurethatthesystemcanbeoperatedsafely.As
the federal lead agency for the NEPA analysis, FRA is obligated to avoid and minimize impacts to the
human and natural environment. FRA must also ensure that the Project complies with all applicable
federallawsandexecutiveorders.
Superelevationistheverticaldistancebetweentheheightsofinnerandouteredgesortheslopeoftherailroad
rails.
thetwometropolitanareasandpotentialridershipdemand,TCRidentifiedanopportunitytodevelopa
profitable privatelyfinanced and operated highspeed passenger rail system. The mobility and
congestion issues on the IH45 corridor that TCRs proposed Project potentially addresses represents
identificationofthetypicalneedforaFRAproject,whichFRAusuallyaddressesthroughservicelevel
corridorplanning.
3.0 DESCRIPTIONOFPROPOSEDPROJECT
AsdescribedinSection2.0,PurposeandNeed,theDallastoHoustonHighSpeedRailProjectmustmeet
specific technological and operational criteria. This includes the deployment of an electricpowered,
highspeed rail system based on Central Japan Railway Companys N700I Tokaido Shinkansen. To
minimizeriskandenhancepassengersafety,theProjectwouldoperateinafullysealedcorridor.Afully
sealedcorridorisnotinterconnectedwithanyotherrailroadsystemsandthehighspeedrailtrainwill
either travel below or above existing roadways and other infrastructure. This will enable trains to
achieve speeds exceeding 200 mph and maintain the 90minute travel time between Dallas and
Houston.
Figure31:ShinkansenTrainset
Source:TCR
The following figures illustrate atgrade, retained fill and viaduct typical sections of the train
infrastructurerequirements.
Figure32:AtgradeTypicalSection
Source:TCR
Figure33:RetainedFillTypicalSection
Source:TCR
Figure34:ViaductTypicalSection
Source:TCR
4.0 DESCRIPTIONOFPOTENTIALROUTEALTERNATIVES
FRAs responsibility is to evaluate the alternatives that TCR developed and proposed. TCR proposed
potentialroutealternativesinsixgeographicgroupsCorsicana,Bardwell,IH45,Middle,Hockleyand
downtownHoustontohelpavoidknownenvironmentalorengineeringconstraintsitidentifiedalong
the Base Alignment. Figure 41 shows the 21 potential route alternatives. Note that some geographic
groups overlap one another. The potential route alternatives were developed based on conceptual
engineeringcompletedasofJune25,2015.
Commonsegments(CS)oftheBaseAlignmentarelocatedbetweenseveralofthegeographicgroups:
DallastothenorthendoftheBardwellgeographicgroup;thesouthendoftheIH45geographicgroup
tothenorthendoftheHockleygeographicgroup;andthesouthendoftheHockleygeographicgroup
tothenorthendofthedowntownHoustongeographicgroup.Thesecommonsegmentsdidnotcontain
known environmental and/or engineering constraints. Therefore, TCR did not propose potential route
alternativesintheseareas.Giventhattherewerenorecommendedpotentialroutealternativeswithin
thesecommonsegments,FRAcollecteddataforpurposesofidentifyingfatalflaws,butdidnotconduct
an evaluation for the purpose of narrowing the range of alternatives. Descriptions of the common
segmentsthatwillbecarriedforwardintheDraftEISareprovidedbelow.
NorthTerminusCommonSegment(CS1)
CS1beginsonthesouthsideofdowntownDallasandparallelstheexistingUPRRfreightlinetowards
IH45.CS1crossestheTrinityRiveronthewestsideofIH45andparallelsIH45untiltheEllisCounty
line.
GrimesCountyCommonSegment(CS2)
CS2parallelstheCenterPointEnergyutilityeasementandbeginsjustsouthofthenorthernborderof
GrimesCounty.CS2parallelstheutilityeasementthroughtheentirecounty,passingwestofSingleton,
RoansPrairieandPlantersvilleandendsatthesouthernborderofthecounty.
SouthTerminusCommonSegment(CS3)
CS3extendssoutheastfromjustsouthofCypressalongUS290.JustwestofBeltway8,CS3continues
toIH610alongtheexistingUPRRfreightlineandHempsteadRoad.
10
Figure41:PotentialRouteAlternatives
11
Descriptionsofthepotentialroutealternativesbygeographicareaareprovidedbelow.
4.1 BardwellGeographicGroup
TheBardwellpotentialroutealternatives(Figure42)fallwithinEllis,Navarroand
Freestone counties between the cities of Ferris and Wortham. In addition to the
Base Alignment, three potential route alternatives were proposed to improve
geometric design and to avoid environmentally sensitive areas. Two of the
potentialroutealternativesextendtothewestofBardwellLakeandoneextends
totheeast.
Note: only one color is shown where potential route alternatives overlap one
anothertoindicatethattheyshareanalignmentinthisarea.
Figure42:BardwellGeographicGroup
Source:TexasCentralHighSpeedRailwayStep2ScreeningofAlignmentAlternativesReport
4.1.1 BardwellBase(BABase)
BA Base begins west of Ferris and joins the utility easement near Palmer. BA Base extends along the
utility easement, curving southwest at Reagor Springs, staying west of Bardwell Lake. Extending
southeast,itcloselyfollowsseveralutilityeasementseastofRankinandBarry,andwestofCurrie.BA
BaseendsnearWorthamonthewesternsideoftheutilityeasement.
4.1.2 Bardwell1(BA1)
BA1divergesfromtheBaseAlignment(BABase)northofPalmerwhereitemploysamoredirectroute
tocurvewestofBardwellLake,stayingnorthandwestoftheutilityeasement.BA1rejoinsBABaseat
Barry.
12
4.1.3 Bardwell2(BA2)
BA2 diverges from the Base Alignment (BA Base) west of Ferris and closely parallels BA Base near
Palmer.Itcurvestotheeasternsideoftheutilityeasement,closertoBardwellLakeandrejoinsBABase
justsouthoftheNavarroCountyline.
4.1.4 Bardwell3(BA3)
BA3divergesfromtheBaseAlignment(BABase)nearFerrisandcrossesoverIH45,extendingeastof
Palmer.BA3continueseastofIH45untilitrecrossesIH45nearAlmaandpasseseastofOakGrove.
BA3crossestheutilityeasementandrejoinsBABasenortheastofPursley.
4.2
CorsicanaGeographicGroup
TheCorsicanapotentialroutealternativesarewithinEllis,NavarroandFreestone
counties and extend between approximately Rankin and Wortham. One base
alignmentandtwopotentialroutealternativeswereproposed(Figure43).
Note: only one color is shown where potential route alternatives overlap one
anothertoindicatethattheyshareanalignmentinthisarea.
Figure43:CorsicanaGeographicGroup
Source:TexasCentralHighSpeedRailwayStep2ScreeningofAlignmentAlternativesReport
4.2.1 CorsicanaBase(CRBase)
CRBaseparallelstheutilityeasement.ItstartsjustnorthoftheNavarroCountylineandextendsalong
theutilityeasementeastofBarrytoapointwestofCurrie.CRBaseextendssouthfollowingtheutility
easementonthewesternside,eastofWortham.
13
4.2.2 Corsicana1(CR1)
CR1 separates from the Base Alignment (CR Base) east of Rankin and extends in a southeasterly
direction, staying west of Corsicana. CR1 curves southeast and crosses a floodplain just north of
Richland.CR1crossestheutilityeasementandcurvessoutheasttorejoinCRBasenearCurrie.
4.2.3 Corsicana2(CR2)
CR2followstheBaseAlignment(CRBase)untilsouthofBarry,whereittakesastraighterroute.CR2
crossestheutilityeasementnorthofPursleyandrejoinsCRBasenearCurrie.
4.3 IH45GeographicGroup
A potential route alternative on IH45 was proposed to eliminate construction risks
through densegaswellfieldsandformerminingareas,andminimize private property
impacts.
Figure44:IH45GeographicGroup
Source:TexasCentralHighSpeedRailwayStep2ScreeningofAlignmentAlternativesReport
4.3.1 IH45Base
IH45 Base aligns with the utility easement as it extends south from a point just north of Navarro
County. IH45 Base separates from the utility easement to pass through the oil and gas fields east of
Lake Limestone and west of Teague and Donie. Just south of Concord, IH45 Base rejoins the utility
easementandendsatthesouthernedgeofMadisonCounty.
14
4.3.2 IH45Alternative(IH45Alt)
IH45 Alt separates from the Base Alignment (IH45 Base) and follows the IH45 highway corridor for
approximately 57 miles starting six miles north of Fairfield to north of Madisonville. IH45 Alt runs
southwestandrealignswiththeBaseAlignmentsouthoftheGrimesCountylineuntilisseparatesjust
northofBedias.
4.4 MiddleGeographicGroup
TheMiddlegeographicgroup(Figure45)beginsattheFreestone/Navarrocounty
line and continues south to the Grimes/Madison county line. Near Jewett where
severalelectricaltransmissionlinesconverge,therearemajorelectricalfacilitiesat
grade,andseveraltownsanddevelopments.Allofthepotentialroutealternatives
closely follow the utility easement along either the west or east side until the
GrimesCountyline.TheBaseAlignment(MDBase)andfourMiddlepotentialroute
alternativeswereproposedtoprovideoptionstoavoidorminimizeimpactstothe
abovementionedelectricalfacilities,townsanddevelopments.
Note:onlyonecolorisshownwherepotentialroutealternativesoverlaponeanothertoindicatethat
theyshareanalignmentinthisarea.
Figure45:MiddleGeographicGroup
Source:TexasCentralHighSpeedRailwayStep2ScreeningofAlignmentAlternativesReport
4.4.1 MiddleBase(MDBase)
MD Base begins at the Freestone/Navarro county line and continues south adjacent to the utility
easementandcurvesalongtheeastsideofBrownsLake.MDBaseseparatesfromtheutilityeasement
topassthroughthedenseoilandgaswellfieldswestofDonieandeastofLakeLimestoneandrealigns
with the utility easement ten miles south of Jewett. MD Base extends south on the east side of the
utilityeasementandendsattheGrimes/Madisoncountyline.
15
4.4.2 Middle1(MD1)
MD1followstheBaseAlignment(MDBase),exceptatapointabouttenmilessouthofJewett,whereit
separatesfromMDBaseandcontinuestoparalleltheutilityeasementonthewestside.
4.4.3 Middle2(MD2)
MD2 separates from the Base Alignment (MD Base) east of Wortham. MD2 extends west around
BrownsLakeandrejoinsMDBasesouthoftheoilandgasfields.
4.4.4 Middle3(MD3)
MD3separatesfromtheBaseAlignment(MDBase)nearWorthamandextendswestofLakeLimestone
andcrossestheNavasotaRiver.ApproximatelyahalfmilesouthofSimmsLake,MD3crossestheutility
easementandrejoinsMDBase.
4.4.5 Middle4(MD4)
MD4separatesfromtheBaseAlignment(MDBase)northofTeagueandcurvesaroundthenorthand
eastsideofTeaguetopasstheoilandgasfields.MD4extendssouththroughtheoilandgasfieldsnear
DonieandpasseswestofJewett.JustsouthofConcord,MD4crossesovertotheeastsideoftheutility
easementandrejoinsMDBasewestofCottonwood.
4.5
HockleyGeographicGroup
The Hockley geographic group begins west of Todd Mission in Grimes County and
endswestofCypressinHarrisCounty(Figure36).Thepotentialroutealternativesall
begin near Todd Mission. The three potential route alternatives were proposed to
provideoptionstocrossStateHighway(SH99)andextendthroughHarrisandWaller
counties before aligning along the east side of the utility easement. The potential
route alternatives curve east to cross over SH 99 and generally follow the utility
easementsouthtowardsHouston.
16
Note:onlyonecolorisshownwherepotentialroutealternativesoverlaponeanothertoindicatethat
theyshareanalignmentinthisarea.
Figure46:HockleyGeographicGroup
Source:TexasCentralHighSpeedRailwayStep2ScreeningofAlignmentAlternativesReport
4.5.1 HockleyBase(HCBase)
HC Base begins west of Todd Mission and continues south following the east side of the utility
easement.HCBasecrossestothewestsideoftheutilityeasementandextendssouthalongHegarRoad.
To accommodate maximum operating speed, HC Base curves south, east of the City of Hockley, and
crossesUS290beforeextendingeasttocrossbothSH99andtheutilityeasementandendsnearthe
townofCypress.
4.5.2 Hockley1(HC1)
HC1beginswestofToddMissionandparallelstheutilityeasement,crossingoverUS290.WestofSH
99,HC1sharplyturnstotheeast.HC1maximizesthelengthadjacenttotheutilityeasementthrough
theHockleyareaandrequirestwosharphorizontalcurvestoturneasttowardsHouston.
4.5.3 Hockley2(HC2)
HC2 follows the Base Alignment (HC Base) to a point south of FarmtoMarket 1488 (FM1488). From
here,itcurvestothewestparallelingHegarRoadbeforecurvingeastoverUS290,eastofHockley,and
rejoiningHCBase.
4.5.4 Hockley3(HC3)
HC3 begins west of Todd Mission and extends south following the east side of the utility easement
beforecrossingtheutilityeasement.HC3thencurvessouthwesttowardsKickapooRoadandcontinues
southparalleltoKickapooRoad.HC3crossesoverUS290andthencurvessouthtothewestofHockley.
HC3crossesbothSH99andtheexistingutilityeasementasitcurveseastandendsnearCypress.
17
4.5.5 Hockley4(HC4)
HC4beginswestofToddMissionandextendssouthfollowingtheeastsideoftheutilityeasement.HC
4 crosses the easement and extends southwest and parallels an existing underground pipeline as it
continuestothesouth.HC4crossesoverUS290andthenapproximately3.3mileswestofHockleyand
justafterBinfordRoad,curvestothesouthandextendseast.HC4crossestheutilityeasementandSH
99andendsnearthetownofCypress.
4.6
DowntownHoustonGeographicGroup
ForthepurposeofthisProject,thedowntownHoustonareabeginssouthwestof
US 290 and IH610 interchange near the Northwest Mall or the Northwest
TransitCenter.TheBaseAlignmentisproposedtoterminatenearIH610atthe
NorthwestMallsite.Twopotentialroutealternativeswereproposedtoextend
easttodowntownHouston.
Note:onlyonecolorisshownwherepotentialroutealternativesoverlaponeanothertoindicatethat
theyshareanalignmentinthisarea.
Figure47:DowntownHoustonGeographicGroup
Source:TexasCentralHighSpeedRailwayStep2ScreeningofAlignmentAlternativesReport
4.6.1 DowntownHouston1(DH1)
ExtendingfromtheBaseAlignment,DH1continuessoutheastbetweentheUPRRROWandHempstead
RoadandcontinuessouthoftheNorthwestMallsite.DH1crossesoverIH610andtheexistingUPRR
freightline.ItthenfollowsthefreightlinebeforecrossingoverInterstateHighway(IH10)andcurving
east towards downtown Houston. DH1 continues east along the south side of the UPRR ROW and
terminatesnearAmtraksHoustonStation.
18
4.6.2 DowntownHouston2(DH2)
ExtendingfromtheBaseAlignment,DH2continuessoutheastbetweentheUPRRROWandHempstead
Road,crossesoverIH610,andextendsalongthenorthsideoftheexistingfreightline.DH2thencurves
easttoalignwiththemedianofIH10.AtStudemontStreet,DH2turnsnorthfromthemediantofollow
thenorthsideofIH10highwayROW.DH2crossesoverIH45entranceandexitrampsbeforecurving
easttopassovertheWhiteOakBayouandterminateatUPRRsHardyYard.
5.0 ALTERNATIVESEVALUATION
The following section describes FRAs independent evaluation of the potential route alternatives by
geographic group. This evaluation consists of a twolevel process. The Level I Screening evaluates the
potentialroutealternativesbasedonProjectpurposeandneed,TCRsalignmentobjectivesandTCRs
designguidelines.ThepotentialroutealternativesthatmettheLevelIScreeningrequirementsmoved
on to the Level II Screening, in which potential route alternatives were evaluated based on
environmentalconstraintsdefinedbyNEPA,andTCRscostandconstructionfactors.
5.1
LevelIScreening
FRAsLevelIScreeningusedtheProjectspurposeandneed,alignmentobjectivesanddesignguidelines
asscreeningcriteria.
5.1.1 PurposeandNeed
Table51showstheevaluationofthepotentialroutealternativestotheProjectPurposeandNeedas
definedinSection2.0ofthisreport.
5.1.2 AlignmentObjectives
TCR developed alignment objectives that all potential route alternatives must meet to be considered
feasible.Thesealignmentobjectives,usedbyFRAinitsLevelIScreening,include:
Alignments must be configured as a dedicated, fully grade separated, twotrack alignment to
meetsafety,serviceplanningandtraveltimegoalswithnoshareduseoftrackorconnectionsto
existingrailroadnetwork
Maximizecolocationopportunitieswithtransportationandutilitycorridors
Minimizerelocationofanyexistingroadwaysorfreightrailroadtracks
Optimize the alignment to allow for the desired maximum operating speed and operational
efficiency
Minimize the number of times the highspeed rail tracks must cross existing freight tracks or
majorroadways
Minimizeexpectedimpactsofconstructiontotrafficandfreightoperations
Minimizeexpectedenvironmentalimpactsandconstructabilityconcerns
Minimize expected ROW and construction costs associated with heavy infrastructure
requirements
Achieveboththetraveltimeandeconomicobjectives
The results of the FRA evaluation of the potential route alternatives to the alignment objectives are
showninTable51.
19
5.1.2 DesignGuidelines
TCR developed alignment design guidelines based on their engineering judgment and professional
experience. The guidelines focused on alignment curvature, profile gradient, and constructability
considerations. These are requirements all potential route alternatives must meet to be considered
feasible.Thegeneraldesignguidelines,usedbyFRAinitsLevelIScreening,are:
MaximumOperatingSpeed:adesiredmaximumoperatingspeedof205mph(330kilometers
perhour(km/h))waschosentobeconsistedwithN700ITokaidoShinkansentechnology.The
alignment was designed to provide for maximum operating speeds throughout to the extent
practical, but in some locations alignment curvature to minimize property and environmental
impactswouldrestrictspeeds.
SeparationfromExistingFreightRailLines:theproposedHSRsystemwouldnotoperateonany
existing freight rail lines. It is expected that reconfiguration of existing freight lines in select
locationsmayberequiredtosupportconstructionandoperationsoftheHSRsystem.
Alignment Curvature: a desired minimum radius of 17,000 feet (5,200 meters) was used for
development of the preliminary alignments. This minimum radius curve would allow for
operationsat205mph(330km/h)usingthemaximumpermissiblecant(actualsuperelevation)
of7inches(175millimeters).
MaximumGrade:thedesiredmaximumgradewassetat1.5percent
Special Trackwork: for the design of the trackwork at the approaches to stations, where all
trainswouldstop,anassumptionof31mph(50km/h)specialtrackworkcomponentswasused
toestablishthefootprintofthestationapproachlimits
Recommended Minimum Offset between HSR and Utility ROW: a 165foot (50 meter) offset
was established as the minimum separation distance from the centerline of the electrical
transmissionlinecorridortothecenterlineoftheHSRcorridor.Thiswasdeterminedbytaking
approximately half of the minimum assumed transmission line ROW width of 215 feet (65
meters)foranelectricaltransmissionlinecorridorandaddingittohalfoftheassumed100feet
(30meters)minimumhighspeedrailROWwidth.
Table51showstheresultsoftheFRAdesignguidelinesevaluation.
20
Table51:LevelIScreeningResults
PotentialRouteAlternatives
Criteria
CorsicanaGeographic
Group
CRB
CR1
CR2
BardwellGeographicGroup
BAB
BA1
BA2
IH45GeographicGroup
BA3
IH45B
MiddleGeographicGroup
HockleyGeographicGroup
IH45Alt
MDB
MD1
MD2
MD3
MD4
HCB
DowntownHouston
GeographicGroup
DH1
DH2
Purpose
Economic
Technological
Operational
Environmental
Need
Improveintercitymobility
improvepassengeraccessibilityandconnectivity
improveoveralltransportationsystemsafety
AlignmentObjectives
Dedicated,fullygradeseparated,twotrackalignmenttomeet
safety,serviceplanning,andtraveltimegoals
Maximizecolocationopportunities
Minimizerelocationofexitingroadwaysorfreightrailroad
tracks
Optimizealignmenttoallowfordesiredmaximumoperating
speed
MinimizeHSRtrackscrossingexistingfreighttracks
Minimizeexpectedimpactsofconstructiontotrafficand
freightoperations
Minimizeexpectedenvironmentalimpactsandconstructability
concerns
MinimizeexpectedROWandconstructioncostsassociated
withheavyinfrastructurerequirements
Achieveboththetraveltimeandeconomicobjectives
DesignGuidelines
MaximumOperatingSpeed330km/h(205mph)
SeparationfromExistingFreightRailLines
AlignmentCurvatureminof17,000feet(5,200m)
MaximumGrademaxgradeof1.5%
SpecialTrackwork
RecommendedMinimumOffsetbetweenHSRandUtilityROW
min50m(165feet)offset
CarriedtoDetailedEnvironmentalAnalysis
21
5.2
LevelIScreeningConclusion
FRA used the Level I Screening to eliminate those potential route alternatives that did not meet the
Projectspurposeandneed,alignmentobjectivesordesignguidelines.
TwoalternativesfortheDowntownHoustongeographicgroup,DH1andDH2,havepotentialtocreate
significant environmental impacts, thereby resulting in higher per mile costs (TCRs Last Mile Analysis
Report2015a).GiventhecosttobuildtheDowntownHoustonpotentialroutealternatives,theydonot
meettheeconomicviabilityoftheProjectpurposeandneed.Accordingly,FRAeliminatedDH1andDH
2fromfurtherconsiderationforthisProject.
DH1hasthepotentialtocreatesignificantenvironmentalimpactstosixareasofconcernsNational
HistoricDistrictHeightsBoulevardEsplanade,theUSHealthworksHospital,HoustonandTexasCentral
Railroad archeology site, and Cottage Grove Park. Additionally, DH1 also has a potential to
disproportionatelyimpactminoritypopulations.Duetothesepotentialenvironmentalimpacts,aswell
asTCRsestimatedhighcapitalcosts(TCRsLastMileAnalysisReport2015a),FRAdeterminedthatDH1
does not meet the stated purpose and need of the Project and FRA eliminated it from further
considerationforthisProject.
DH2hasthepotentialtocreatesignificantenvironmentalimpactstonineareasofconcernNational
Historic District Heights Boulevard Esplanade, U.S. Healthworks Hospital, Houston and Texas Central
Railroadarcheologysite,CottageGrovePark,StudePark,WhiteOakPark,andHoggPark.Duetothese
potentialenvironmentalimpacts,aswellasTCRsestimatedhighcapitalcost(TCRsLastMileAnalysis
Report 2015a), FRA determined that DH2 does not meet the stated purpose and need of the Project
andFRAeliminateditfromfurtherconsiderationforthisProject.
Additionally,FRAdeterminedthatHC1doesnotmeetthedesignguidelinesfortheProject.Basedon
conceptual engineering as of June 25, 2015, HC1 contains two curves that would require a speed
restrictionof160mph,whichfailstomeettheminimumalignmentcurvaturenecessarytoachievethe
intended travel time of 90 minutes (TCRs Step 2 Screening of Alignment Alternatives Report 2015b) .
Therefore, FRA determined that HC1 does not meet the stated purpose and need of the Project and
FRAeliminateditfromfurtherconsiderationforthisProject.
FRAcarriedthefollowingpotentialroutealternativesforwardintotheLevelIIScreening(Figure51):
o MDBase
BardwellGeographicGroup
o MD1
o BABase
o MD2
o BA1
o MD3
o BA2
o MD4
o BA3
HockleyGeographicGroup
CorsicanaGeographicGroup
o HCBase
o CRBase
o HC2
o CR1
o HC3
o CR2
o HC4
IH45GeographicGroup
o IH45Base
o IH45Alt
MiddleGeographicGroup
22
Figure51:PotentialRouteAlternativesFRACarriedForwardtoLevelIIScreening
23
5.3
LevelIIScreening
FRAs Level II Screening consisted of two stages. The first stage looked at 16 environmental evaluation
criteria (Table 53) to determine areas of potential environmental impact, as required by NEPA. These
includedprimefarmland,wetlandsandfloodplains,communityfacilities,historicalproperties,threatened
andendangeredspecies,androadcrossings.Thesecondstageincorporatedcostandconstructionfactors
intothescreeninganalysis.
Thisanalysisisbasedondesktoplevelresearchanddatacollection.Nofieldsurveysorsiteverificationwas
conductedtocompletethisanalysis.Fieldwork,modelinganddetailedtechnicalevaluationinaccordance
withNEPAandFRAsprocedureswillbecompletedaspartoftheDraftEISonthefeasibleandpracticable
alternatives.
5.4
LevelII,StageIEnvironmentalConstraintsScreening
In the Level II, Stage I Environmental Constraints Screening, FRA quantitatively evaluated the potential
route alternatives that were carried forward from Level I Screening using a Geographic Information
Systems (GIS)based analysis of environmental constraints pursuant to NEPA. FRA conducted the GIS
analysis on 16 environmental evaluation criteria using readily available state and federal databases, as
describedinAppendixA.ThemethodologyandcriteriausedtocompletetheLevelII,StageIEnvironmental
ConstraintsScreeningareexplainedbelow.
5.4.1 Methodology
Scoringforeachoftheenvironmentalevaluationcriteriawasbasedonthelowestscorehavingtheleast
potential to create an environmental impact (best). A ratio method was used to distribute the scores
among potential route alternatives within each geographic group. An example of how this is displayed is
provided in Table 52, which contains four potential route alternatives within the Bardwell geographic
groupandtheirscoringforthewetlandscriteria.Becausetherearefouralternatives,thescoresrangefrom
1.0to4.0.Foreachcriterionthelowestimpactisscoreda1.0(BA2)andthegreatestimpactisscoreda4.0
(BA3).(Note:Ifageographicgroupcontainstwoalternatives,thescoresrangefrom1.0to2.0.And,ifthe
geographic group contains three alternatives, the scores range from 1.0 to 3.0). The remaining potential
routealternativesarescoredrelativetotheminimumandmaximumscores.
Table52:RatioMethodology
Scoring
(Bardwell)
Bardwell
Geographic
Group
Wetlands
Acreage
Points
BABase
BA1
BA2
BA3
5.243
6.357
3.542
20.560
1.300
1.496
1.000
4.000
A different measurement is used for each environmental evaluation criterion. These measurements
encompass the potential for direct or indirect impacts. For the purposes of this analysis, potential
impacts due to the implementation and operation of a potential route alternative are considered direct
impacts.Forexample,ifahospitalsitswithinthealignmentROW(125feet),itisconsideredadirectimpact
under Community Facilities. Potential indirect impacts represent those that may occur outside of the
proposedROW(upto1,000feet).Forexample,ifahospitalissetback250feetfromthealignmentROW,it
24
is considered an indirect impact. A description of each environmental evaluation criterion and the
measurementusedisprovidedbelowinTable53.
25
Table53:EnvironmentalEvaluationCriteria
Criterion
UrbanLandCover
NLCD
From
Total
Centerline Width
(feet)
(feet)
500
1000
Structures
AerialPhotography
62.5
125
Direct
Acountofrooftopsasseenonaerialphotography thatarewithinthe
buffer
ParcelTakes
AppraisalDistricts,inhouse
digitization
62.5
125
Direct
Parcelswithaffectedstructures+Parcelswithoutaffectedstructures
whereatleast40%ofareaisimpacted
Parks
TPWD,MPOs
500
1000
Indirect
Stateandlocalparkland
PrimeFarmland
NRCS
62.5
125
Direct
NRCSsoilsurveyprimefarmlandimpacted
Wetlands
NWI
62.5
125
Direct
NWIwetlandsimpacted
Waterways
NHD
Direct
Directalignmentcrossingsofwaterways
Floodplains
FEMA
62.5
125
Direct
100and500yearfloodplainimpacted
RoadCrossings
TxDOT
Direct
Directalignmentcrossingsofroads
Infrastructure
Adjacency
TxDOT(roads),Platts
(transmissionlines),USNational
TransportationAtlas(railroads)
CensusBureau(Census2010)
500
1000
Indirect
Percentageofthealignmentthatisparalleledbyroads,transmission
lines,orexistingrailroads
500
1000
Indirect
Estimatedminoritypopulationaffected(tractdensitytimesalignment
tractintersectionarea)
Cemeteries
THC
62.5
125
Direct
Cemeteryacreageimpacted
Ecology
TXNDD
62.5
125
Direct
AcreageofTXNDDElementoccurrencesimpacted
HistoricProperties
NRHP
500
1000
Indirect
NRHPpropertiesanddistricts
Community
Facilities
Hazardous
Materials
GNIS
500
1000
Indirect
TCEQ
62.5
125
Direct
Populationbelow
PovertyLine
CensusBureau(20135yearACS)
500
1000
Indirect
IncludesthefollowingGNISfeatureclasses:Building(publicfacilities),
Church,Hospital,PostOffice,School
Includes:municipalsettingdesignations,municipalsolidwastelandfills,
radioactivesites,Superfundsites,municipalwaterwells,and
undergroundpetroleumstoragetanks.
Estimatedpopulationbelowpovertylineaffected(tractdensitytimes
alignmenttractintersectionarea)
Minority
Population
DataSource
Direct/
Indirect
Indirect
Description
Lowintensity,mediumintensity,highintensity,andopenspace
developedarea
26
5.4.2 UrbanLandCover
Theurbanlandcovercriterionisanapproximatequantificationinacresofpotentiallanduseimpacts.This
criterion looks at the difference between lowintensity, mediumintensity, highintensity and open space
land uses. Generally, the more urbanized or complex the property use is, the greater the number of
potentialimpacts.
Initially, the land use criteria considered residential, commercial and industrial land uses. When land use
datasetswereonlypartiallyavailableforthe1,000footbuffer,andwhereavailabletheyhadinconsistent
classification/schema,UrbanLandCoverfromtheNationalLandCoverDataset(NLCD)wasusedduetoits
consistencyovertheentirescreeningbuffer.
5.4.3 ParcelTakes
This criterion represents the number of potential parcels that could be acquired by implementing a
potentialroutealternative.
Thiscriterioncombinesstructures(rooftops)identifiedbyaerialphotographywithparceldatafromcounty
appraisal districts to calculate the number of properties potentially impacted. This criterion counts the
impactedparcelsastakesif:
Anyparcelwithoneormorestructuresonitthatfallswithin62.5feetofthealignmentcenterline
(125feettotalwidth)
Parcelswithoutstructureswithin62.5feetofthealignmentcenterlinewhereatleast40percentof
theparcelareafallswithinthealignmentbuffer(125feettotalwidth)
5.4.4 Parks
Thiscriterionmeasuresthepotentialacreageofimpacttoareasdesignatedbystateandlocalagenciesfor
recreation and wildlife habitat are substantially forested, largely undisturbed, and used for recreational
activities. Impacts to these lands may require avoidance under Section 4(f) of the Department of
TransportationActormaynotbeabletobeconsideredifprudentorpracticalalternativesexist.
ParksdatawasavailableinGISpolygonformfromtheMetropolitanPlanningOrganizations(MPO)andthe
TexasParksandWildlifeDepartment(TPWD)datasets.
5.4.5 PrimeFarmland
This criterion measures the acreage of land designated by the Natural Resources Conservation Service
(NRCS)SoilSurveyGeographicDatabase(SSURGO)asprimefarmland,whichisdefinedaslandthathasthe
best combination of physical and chemical characteristics for producing food, feed, forage, fiber, and
oilseedcropsandisavailablefortheseuses.
5.4.6 Wetlands
This criterion measures the acreage of impacts to wetlands within 62.5 feet of the alignment center line
(125feettotalwidth).IncreasedimpactstowetlandswouldincreasethecomplexityofProjectpermitting
and also require a higher amount of wetland mitigation to offset Project impacts. Wetland data was
obtainedfromtheUSFWSNationalWetlandInventory(NWI)dataset.
27
5.4.7 Waterways
The total number of waterways (e.g., rivers and streams) a potential route alternative crosses was
calculated using data obtained from the National Hydrography Dataset (NHD). Increased impacts to river
and stream crossings would increase the complexity of permitting the Project and also require greater
mitigationtooffsetProjectimpacts.
5.4.8 Floodplain
Acres of floodplain were tabulated based on the number of acres within 62.5 feet from the alignment
centerline(125footbuffer)ofeachpotentialroutealternative.FloodplaindatawasobtainedfromFEMA
andincludedboththe100and500yearfloodplainclassifications.Increasedimpactstofloodplainswould
increase the complexity of permitting the Project and also require higher mitigation to offset Project
impacts. Construction through these areas would also result in higher potential implementation costs to
designandmaintainstructuresthatwouldberesilienttopotentialfloodingimpacts.
5.4.9 RoadCrossings
This criterion is a count of the number of roadway crossings, regardless of ownership or roadway
classification(e.g.,state,countyandprivate).TxDOTwasthedatasourceforroadways.
5.4.10 InfrastructureAdjacency
OneofTCRsalignmentobjectivesisforpotentialroutealternativestomaximizecolocationopportunities
with transportation and utility corridors. Therefore, the infrastructure adjacency criterion estimates the
percentage of the potential route alternative that parallels existing infrastructure. This analysis uses the
roads dataset from TxDOT, railroads dataset from the U.S. National Transportation Atlas, and electrical
transmissionlinedatasetfromPlatts.
5.4.11 MinorityPopulation
EnvironmentalJustice(EJ)populationsincludelowincomeandminoritypopulations.Minoritypopulation
wasanalyzedtodetermineifapotentialroutealternativemightdisproportionatelyaffectEJpopulations.
MinoritypopulationdatawasobtainedattheU.S.CensusBlocklevelfromthe2010DecennialU.S.Census.
Forthepurposesofthisanalysis,minoritypopulationisdefinedasthetotalpopulationminuspersonsthat
reported themselves as White, Not Hispanic or Latino. This information was converted into a metric by
countingthenumberofU.S.CensusBockswithaminoritypopulationover50percentintersectinga1,000
footbufferaroundeachpotentialroutealternative(500feetfromthealignmentcenterline).
5.4.12 Cemeteries
CemeterydatawasobtainedfromtheTexasHistoricalCommission(THC)toevaluateboththenumberof
impactedcemeterieswithinthe125footbufferofthepotentialroutealternativeandtotalacreagewithin
thecemeterythatmightbeimpacted.Animpacttocemeteriescouldrequiremitigationincludingpotential
localizedalignmentmodificationstoavoidand/orminimizeimpacts.Ifalignmentmodificationscouldnot
beaccommodated,additionalcoordinationwithTHCand/orconsultationunderSection106oftheNational
HistoricPreservationActwouldrequireinvestigationthatcoulddelayProjectimplementation.
28
5.4.13 Ecology
Thiscriterionmeasuresthepotentialimpacttoenvironmentallysensitiveareasthatcouldprovidehabitat
forthreatenedandendangeredspeciesbasedonacreageofpotentialimpactstoobservedoccurrencesof
the species. Impacts to individual species of plants and wildlife or the habitat of threatened and
endangeredwildlifespecieswouldrequiremitigationincludingpotentiallocalizedalignmentmodifications
to avoid and/or minimize impacts. If alignment modifications could not be accommodated, additional
coordination with the USFWS and TPWD would be required, increasing the complexity of permitting the
ProjectandalsorequirehighermitigationtooffsetProjectimpacts.
TheTexasNaturalDiversityDatabase(TXNDD)elementoccurrencedatafromTPWDdepictsareaswhere
threatenedandendangeredspecieshavebeenobserved.Thisdoesnotnecessarilymeanthatthesespecies
arepresent,butitisanindicatorthataspeciesisorwaspresentandhaspracticalconservationvalue.
5.4.14AdditionalEnvironmentalEvaluationCriteria
There are four environmental evaluation criteria community facilities, historic properties, hazardous
materials and U.S. Census block groups with over 50 percent poverty population for which data was
collected. However, when evaluated, they did not create any differentiation between the scoring of the
potentialroutealternativesatthislevelofanalysis.Forexample,thisdesktoplevelanalysisdidnotidentify
anyhistoricpropertieswithinthe125footbuffer(62.5feetfromthealignmentcenterline),althoughthey
are expected to be present. Therefore, for the purposes of this analysis, these four environmental
evaluation criteria were not used in the Level II, Stage I Environmental Constraints Screening. Additional
researchandanalysiswillbeconductedforthesefourenvironmentalevaluationcriteria,amongresource
topicsasrequiredbyNEPA,aspartoftheDraftEIS.
5.5
LevelII,StageIEnvironmentalConstraintsScreeningResults
Table53showstheresultsoftheLevelII,StageIEnvironmentalConstraintsScreeningforthe18potential
routealternativesthatwerecarriedforwardfromtheLevelIScreening.
29
Table54:LevelII,StageIEnvironmentalConstraintsScreeningResults
PotentialRoute
Alternatives
Corsicana
Geographic
Group
Bardwell
Geographic
Group
IH45
Geographic
Group
Middle
Geographic
Group
Hockley
Geographic
Group
UrbanLandCover
ParcelTakes
(40%)
Percent
Score
Number Score
CRBase
4.91%
3.000
CR1
4.58%
2.566
CR2
3.38%
BABase
Parks
PrimeFarmland
Wetlands
Waterways
Floodplains
RoadCrossings
Infrastructure
Adjacency
Minority
Population
Cemeteries
Ecology
(TXNDD)
Total
Score
Acres
Score
Acres
Score
Acres
Score
Number
Score
Acres
Score
Number
Score
Percent
Score
Number
Score
Acres
Score
Acres
Score
1.333
0.00
1.000
198.79
1.659
2.39
1.000
47
1.833
93.92
2.504
37
1.000
56.79%
1.000
14
3.000
0.00
1.000
12.56
1.364
19.69
17
3.000
0.00
1.000
187.26
1.000
4.83
1.571
42
1.000
41.09
1.000
47
3.000
20.54%
3.000
1.000
0.00
1.000
69.03
3.000
22.14
1.000
1.000
0.00
1.000
222.22
3.000
10.94
3.000
54
3.000
111.34
3.000
40
1.600
40.90%
1.877
13
2.750
0.00
1.000
0.00
1.000
23.23
4.12%
1.726
14
1.000
0.00
1.000
455.41
3.734
5.24
1.300
83
1.000
141.10
1.000
68
1.167
51.24%
1.000
50
4.000
0.00
1.000
12.56
1.000
18.93
BA1
4.07%
1.481
20
1.720
0.00
1.000
470.53
4.000
6.36
1.496
91
4.000
144.23
1.720
68
1.167
33.74%
2.999
40
2.846
0.00
1.000
12.56
1.000
24.43
BA2
3.97%
1.000
18
1.480
0.00
1.000
436.10
3.393
3.54
1.000
85
1.750
150.29
3.114
66
1.000
50.81%
1.050
48
3.769
0.00
1.000
12.56
1.000
20.56
BA3
4.61%
4.000
39
4.000
0.00
1.000
300.25
1.000
20.56
4.000
85
1.750
154.14
4.000
102
4.000
24.98%
4.000
24
1.000
0.00
1.000
25.82
4.000
33.75
IH45Base
5.04%
1.000
47
1.000
0.00
1.000
423.30
2.000
25.83
1.000
185
2.000
189.49
2.000
115
1.000
52.23%
2.000
14
1.000
0.00
1.000
276.89
2.000
17.00
IH45Alt.
27.19%
2.000
79
2.000
246.73
2.000
355.12
1.000
31.11
2.000
166
1.000
169.72
1.000
147
2.000
63.51%
1.000
20
2.000
0.00
1.000
172.62
1.000
18.00
MDBase
5.15%
3.161
41
1.000
0.00
1.000
222.51
4.024
21.22
1.245
134
1.800
79.81
4.014
77
2.714
49.12%
1.000
1.000
0.00
1.000
264.33
5.000
26.96
MD1
4.99%
2.834
42
1.049
0.00
1.000
229.74
5.000
20.61
1.000
146
5.000
79.81
4.014
65
1.000
44.16%
1.939
1.000
0.00
1.000
264.33
5.000
29.84
MD2
4.97%
2.778
46
1.244
0.00
1.000
212.38
2.655
24.47
2.551
143
4.200
105.93
5.000
78
2.857
34.81%
3.707
3.000
0.00
1.000
264.33
5.000
34.99
MD3
4.15%
1.000
49
1.390
0.00
1.000
213.08
2.750
30.56
5.000
131
1.000
104.23
4.936
93
5.000
27.97%
5.000
5.000
0.27
5.000
169.54
1.000
38.08
MD4
5.99%
5.000
123
5.000
0.00
1.000
200.12
1.000
21.20
1.237
136
2.333
0.00
1.000
93
5.000
35.88%
3.504
3.000
0.00
1.000
228.41
3.484
32.56
HCBase
12.07%
4.000
28
3.250
0.00
1.000
191.97
1.000
50.64
1.370
34
3.786
69.10
4.000
41
4.000
62.19%
1.000
18
4.000
0.00
1.000
107.43
4.000
32.41
HC2
8.79%
1.669
25
1.000
0.00
1.000
209.35
1.549
56.33
4.000
35
4.000
57.34
2.339
33
1.000
36.83%
2.811
16
1.000
0.00
1.000
105.88
3.940
25.31
HC3
10.29%
2.737
29
4.000
0.00
1.000
252.77
2.920
51.80
1.906
21
1.000
54.71
1.966
35
1.750
32.66%
3.109
17
2.500
0.00
1.000
73.29
2.671
26.56
HC4
7.85%
1.000
26
1.750
0.00
1.000
286.99
4.000
49.83
1.000
29
2.714
47.87
1.000
33
1.000
20.18%
4.000
17
2.500
0.00
1.000
30.35
1.000
21.96
30
The scores for each criterion were totaled for each potential route alternative within its geographic
group.FRAdeterminedthatthelowestscoringpotentialroutealternativewouldmoveforwardtoLevel
II, Stage II Cost and Construction Screening for further evaluation. Additionally, FRA used a standard
deviation2toquantifythevariationofthedata.
After the scores were totaled, the standard deviation was then calculated for each geographic group.
Thepotentialroutealternativesthatfellwithinonestandarddeviationofthelowestscorewerecarried
intotheLevelII,StageIICostandConstructionScreening.Therefore,onestandarddeviationfromthe
scorewasusedtostatisticallycapturethosepotentialroutealternativesclosesttothelowestscore,as
wellasthelowestscore.
For example, as shown in Figure 52, the Hockley geographic group scores ranged from 21.964 to
32.406.Onestandarddeviationfromthelowestscoreis3.77or25.73,soanyscoreslessthan25.73fall
within one standard deviation of the lowest score. Using this methodology, HC4 (21.964) and HC2
(25.307)werecarriedforwardtotheLevelII,StageIICostandConstructionScreening.
Figure52:StandardDeviationExample
Standarddeviationisastatisticusedtomeasurethedispersionorvariationinasetofnumbers.Itisequalto
thesquarerootofthevariance.
31
AttheconclusionoftheLevelII,StageIEnvironmentalConstraintsScreening,FRAcarriedtenpotential
routes alternatives forward for further consideration. Table 54 identifies all of the potential route
alternativesthatadvancedtotheLevelII,StageIICostandConstructionScreening.
Table55:LevelII,StageIEnvironmentalConstraintsScreeningResultsandStandard
Deviation
PotentialRouteAlternative
Corsicana
GeographicGroup
Bardwell
GeographicGroup
IH45Geographic
Group
MiddleGeographic
Group
HockleyGeographic
Group
CRBase
CR1
CR2
BABase
BA1
BA2
BA3
IH45Base
IH45Alt.
MDBase
MD1
MD2
MD3
MD4
HCBase
HC2
HC3
HC4
TotalScore
19.69
22.14
23.23
18.93
24.43
20.56
33.75
17.00
18.00
26.96
29.84
34.99
38.08
32.56
32.41
25.31
26.56
21.96
StandardDeviation
1.48
5.75
N/A
3.88
3.77
CarriedForward
Yes
No
No
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
No
No
No
No
Yes
No
Yes
5.6
LevelII,StageIICostandConstructionScreening
FRAsLevelII,StageIEnvironmentalConstraintsScreeningidentifiedtenpotentialroutealternativesfor
further consideration. As the Project Proponent, TCR identified several preferred alignments from the
potential route alternatives in its Step 2 Screening of Alignment Alternatives Report (TCR 2015b) that
bestmetitscostandconstructiongoals.ToincludeTCRsprimarycriteriaofcostandconstructability,
FRAundertookaLevelII,StageIICostandConstructionScreening.Eventhoughtheywereeliminatedin
the Level II, Stage I Environmental Constraints Screening, FRA carried three additional potential route
alternatives(MD4,BA3andCR1)intotheLevelII,StageIICostandConstructionScreeningtofurther
evaluate TCRs preferred alignments. These 13 remaining potential route alternatives were evaluated
usingacombinationofenvironmental,cost,andconstructionfactors.
FRA was not provided TCRs proprietary cost and construction data; instead, TCR provided cost and
construction factors normalized against to the Base Alignment.3 In order to use TCRs cost and
constructionfactorsaspartofFRAsLevelII,StageIICostandConstructionScreening,FRAdeveloped
normalized environmental factors from the Level II, Stage I Environmental Constraints Screening Base
Alignmentscores.ThisallowedFRAtocompleteanindependentevaluationusingcomparablefactors.
Normalizationisusedtobringdifferenttypesofdataintoacommonunitforthepurposesofcomparison
32
FRA calculated the environmental factor using the environmental evaluation criteria from the Level II,
Stage I Environmental Constraints Screening. Each geographic group contained a Base Alignment (CR
Base,BABase,etc.).TheBaseAlignmentfromeachgeographicgroupwasassignedafactorof1.0.The
difference between the base factor and the other geographically grouped potential route alternatives
was calculated to assign a factor at, above or below 1.0. For example, BA Base has an environmental
scoreof18.926(seeTable43above).Tocreatenormalizedfactor,itsenvironmentalfactoris1.0.BA2
has an environmental score of 20.556, which is 9 percent higher than the base factor, and creates a
factorof1.09.
TCRprovidedcostandconstructionfactorsforall13potentialroutealternativesintheLevelII,StageII
Cost and Construction Screening (TCR 2015b). Similar to the environmental factors, within each
geographic group, the Base Alignment was assigned a factor of1.0 for cost and construction, and the
otherpotentialroutealternativesfactorswerecalculatedfromthebase.TCRscostfactorwasbasedon
typical heavy infrastructure types (i.e., embankment vs. viaduct), trackwork, grade crossings,
transmission line relocations, estimated environmental mitigation costs, and complexity factors
associated with development and environmentally sensitive areas that are normalized to an average
cost in order to compare potential route alternatives against each other within a geographic group.
TCRsconstructionschedulefactorswerecalculatedbasedontypeofinfrastructuretobebuiltandan
estimatedtimetobuildeachtypeofinfrastructure(Step2ScreeningofAlternativeAlignmentsReport
2015b).
In order to complete the Level II, Stage II Cost and Construction Screening, the cost and construction
factorswereaveragedtogethertocreateasinglefactorthatcouldbecomparedtotheenvironmental
factor, giving each an equal weight to environmental factors as the combined cost and construction
factor.Table55showstheresultsoftheLevelII,StageIICostandConstructionScreening.
33
Table56:LevelII,StageIICostandConstructionScreeningResults
Potential
Level1 Difference Level2ENV
TCRCost
TCRConstruction
Average
Route
Total
Score
fromBase
Factor
Factor
Factor
C/CFactor
Alternative
CRBase
19.694
0.000
1.00
1.00
1.00
1.00
2.00
CR1
22.137
2.443
1.12
0.95
0.85
0.90
2.02
BABase
18.926
0.000
1.00
1.00
1.00
1.00
2.00
BA1
24.429
5.503
1.29
1.15
1.33
1.24
2.53
BA2
20.556
1.630
1.09
0.98
1.00
0.99
2.08
BA3
33.750
14.824
1.78
1.08
1.16
1.12
2.90
IH45Base 17.000
0.000
1.00
1.00
1.00
1.00
2.00
IH45Alt.
18.000
1.000
1.06
1.04
0.92
0.98
2.04
MDBase
26.959
0.000
1.00
1.00
1.00
1.00
2.00
MD1
29.835
2.877
1.11
1.13
1.22
1.17
2.28
MD4
32.558
5.599
1.21
0.96
0.95
0.96
2.16
HCBase** 32.406
0.000
1.00
N/A
N/A
N/A
N/A
HC2
25.307
7.099
0.78
0.83
0.60
0.71
1.50
HC4
21.964
10.442
0.68
0.81
0.48
0.65
1.32
**HCBasewasnotcarriedforwardtotheLevelII,StageIICostandConstructionScreening,buttheLevelII,Stage
IEnvironmentalConstraintsScreeningscorewasusedtogenerateenvironmentalfactorsfortheremainingHC
potentialroutealternatives.
FRA carried forward the potential route alternatives with the lowest score in each geographic group.
Additionally, FRA carried forward potential route alternatives within each geographic group that were
veryclosetothelowestscoreinthegeographicgroupsuchthattherewasnodistinguishabledifference
betweenthescoresusinganaturalbreakapproach.4
FRAdeterminedeightpotentialroutealternativesmovedforwardthroughtheLevelII,StageIICostand
ConstructionScreeningfordetailedconsiderationintheDraftEIS.Thepotentialroutealternativesthat
FRAwillevaluateintheEISare:
CorsicanaBase(CRBase)
Corsicana1(CR1)
BardwellBase(BABase)
Bardwell2(BA2)
IH45Base(IH45Base)
IH45Alternative(IH45Alt.)
MiddleBase(MDBase)
Hockley4(HC4)
As discussed in Section 4.0, no potential route alternatives were proposed for the common segments
and FRA did not conduct an evaluation of the common segments for the purposes of narrowing the
rangeofalternatives.Therefore,FRAwillalsoevaluateCS1,CS2,andCS3intheEIS.
Thenaturalbreakpointclustersdatatodeterminethebestarrangementofvaluesintodifferentclasses.For
thisanalysis,FRAidentifiedclassesofhighandlowscores,withlowscoresrepresentingalowerpotentialfor
impact.
34
6.0 CONCLUSION
The eight potential route alternatives that FRA carried forward from the Level II, Stage II Cost and
ConstructionScreeningandthethreecommonsegmentswerethenpiecedtogethertocreatepotential
endtoend alignment alternatives, or alignment alternatives from downtown Dallas to the Houston
terminus at the intersection of US 290/IH610. To create the endtoend alignment alternatives, each
draftalignmentalternativewasbrokenintofivesegmentsmadeupofthepotentialroutealternatives
andcommonsegments.Table61andFigure61showsthepotentialroutealternativesthatmakeup
eachsegment.
Table61:DraftAlignmentAlternativeDevelopmentSegmentation
Segment
Segment1
Segment2a
BABase
Segment2b
BA2
Segment3a
BABase,BA2,CRBase,IH45Base
Segment3b
CR1
Segment3c
IH45Alt.
Segment4
IH45Base,MDBase
Segment5
35
Figure61DraftAlignmentAlternativesCarriedForwardtotheDraftEIS
36
The segments were then pieced together to create six endtoend alignment alternatives. Table 62
showsthecombinationofsegmentsthatcreatedraftAlignmentAlternativesAF.Becausepartsofthe
segmentsoverlap,itisnotpossibletoshowallofthealternativesononemap;therefore,aseriesofsix
maps, one for each endtoend alignment alternative, is included. Figures 62 through 67 show the
mapsofthesixdraftalignmentalternativesthatFRAwillstudyintheDraftEIS.
Table62:DraftEISEndtoEndAlignmentAlternatives
DraftAlignment
Alternative
Segments
AlternativeA
1,2a,3a,4,5
AlternativeB
1,2a,3b,4,5
AlternativeC(IH45A)
1,2a,3c,5
AlternativeD
1,2b,3a,4,5
AlternativeE
1,2b,3b,4,5
AlternativeF(IH45B)
1,2b,3c,5
Thisalternativesanalysisprovidesadesktoplevelreviewtocomparepotentialroutealternativeswithin
specificgeographicgroups.Thealignmentalternativespresentedinthisdocumentarepreliminaryand
subjecttochange.Thedraftalignmentalternativeswillcontinuetobefurtherrefinedandevaluatedas
per NEPA. For example, the Draft EIS will evaluate and document potential environmental impacts
identified through modeling, field investigations and public input. These environmental impacts may
dictate a modification to the alignment alternative to avoid and/or minimize an impact. Additionally,
TCRsengineeringteamwillrefinethealignmentalternativesduringpreliminaryengineering,whichwill
occursimultaneouslywiththepreparationoftheDraftandFinalEIS.FRAwillevaluatethemodifications
tothealignmentalternativesthroughtheEISprocess.
37
Figure62:DraftEISEndtoEndAlignmentAlternativeA
38
Figure63:DraftEISEndtoEndAlignmentAlternativeB
39
Figure64:DraftEISEndtoEndAlignmentAlternativeC
40
Figure65:DraftEISEndtoEndAlignmentAlternativeD
41
Figure66:DraftEISEndtoEndAlignmentAlternativeE
42
Figure67:DraftEISEndtoEndAlignmentAlternativeF
43
AppendixAGISMethodology
44
GISMethodology
ThefollowingisadetaileddescriptionofthemethodologyusedfortheGISdesktopanalysistoevaluate
thepotentialroutealternativesforeachofenvironmentalcriteriadescribedinSection4.0.
A.1
UrbanLandCover
Initiallythelandusecriteriaincludedresidential,commercialandindustriallanduses,butwhenit
becameapparentthatthelandusedatasetsareonlypartiallyavailableforthecorridor,andwhere
available,theyhaveinconsistentclassification/schema,UrbanLandCoverfromtheNLCDwasused.The
NLCDisconsistentthroughouttheentirecorridor.
ThefollowingdescribestheGISanalysisusedtoidentifythepotentialforimpacts:
UsedExtractbyMasktooltoclipthelargeNLCDdatasetdowntotheareacoveredwithin500
feetfromthealignmentcenterline
PerNLCDcategories,groupedalldeveloped/urbanlandcoverclassifications(low,medium,
andhighintensity,anddevelopedopenspace)intooneurbanclassificationandgroupedall
otherclassificationsintoaruralclassification
UsedArcScantocreatepolygon(vector)featuresrepresentingurban/developedland
Usedtheintersecttooltodeterminewhichoftheseareasoverlay500feetfromthealignment
centerline
Calculatedtheareaofthesepolygonsinacres
Dissolvedthefeaturestosumthetotalofpotentiallyaffectedacreageforeachbuffer(1,000
feettotalwidth)
ExportedtotalacreagesofurbanlandcoverfromArcGISintoExcel
A.2
ParcelTakes
Thiscriterioncombinesstructures(rooftops)identifiedbyaerialphotographywithparceldatatoarrive
atanestimationofthepotentialimpactsthatthepotentialroutealternativescouldhaveonproperty
owners.Thiscriterioncountstheidentifiedparcelimpactsastakes:
Anyparcelwithoneormorestructureonitthatfallswithin62.5feetofthealignment
centerline(125foottotalwidth)
Parcelswithoutstructureswithin62.5feetofthealignmentcenterlinewhereatleast40percent
oftheparcelsareafallswithinthealignmentbuffer(125foottotalwidth)
ThefollowingstepsweretakentoconducttheGISanalysis:
Collectedpreprocessedparceldatafromthe13intersectingcountiesandensuredthattheyare
inthecorrectcoordinatesystem.ForFreestoneandLeoncounties,theparceldatawasavailable
incomputeraideddesign(CAD)lineformat,sothelineswereconvertedintoashapeto
generatetheparcelareas.
Mergedtheclippedparceldatatogether
Calculatedtheareaoftheseparcelsinacres
Intersectedtheparcelswithin62.5feetofthealignmentcenterline,whichclipstheparcelsto
thealignmentbufferandjoinsinalternativeattributes
Calculatedtheintersectedareaoftheseparcelsinacres
Dividedtheintersectedareabytheoriginalwholeareatoarriveatapercenttake
Selectedthosefeaturesfromthislayerthatcontainedstructuresandcopiedthemintotheir
ownlayer,thencalculatedsummarystatisticsforthisnewlayer,groupingbypotentialroute
alternativenameandsummingthenumberofaffectedparcels
45
Reversedtheselectionintheoriginalintersectedparcelslayer,thusselectingonlythoseparcels
withoutanystructureswithin62.5feetofthealignmentcenterline.Selectedfromthisselection
onlythosewithatakepercentagegreaterthanorequalto40percent,yieldingonlythose
parcelswithoutstructureswheremorethan40percentoftheparceliswithin62.5feetofthe
alignmentcenterline.Copiedtheseselectedfeaturesintoanewlayer,andcalculatedsummary
statistics,groupingbypotentialroutealternativenameandsummingthetotalnumberof
affectedparcels
ExportedbothsummarytablesfromArcGISandimportedthemintoExcel.Addedthenumberof
parcelswithaffectedstructuresandparcelswithoutaffectedstructureswheremorethan40
percentofitsareaisaffectedtoarriveatthefinaltakesnumber.
A.3
Parks
ParksdatawasavailableinpolygonformfromtheMPOsandtheTPWD.Thedatawasmergedtogether
toformasingleshapefileforthefollowinganalysis.
Intersectedtheparksshapefilewithin500feetofthealignmentcenterline,whichclipstheparks
tothecorridorandjoinstheminthealternativesattributes
Calculatedacreageofintersectedparkfeatures
Calculatedsummarystatisticsfortheresultinglayer,groupingbypotentialroutealternative
nameandsummingthetotalaffectedparkacreage
ExportedthesummarytablefromArcGISandinserteditintotheExceltable
A.4
PrimeFarmland
PrimefarmlandwasacquiredfromtheNRCSSSURGO.Thefollowinganalysiswasconductedto
determinethepotentialimpacts.
MergedtogetherSSURGOdataforthevariousdrainagebasinsinthecorridor
SelectedandexportedonlythosepolygonfeaturesfromtheSSURGOdatathatrepresentprime
farmland
Intersectedtheprimefarmlandpolygonswithin62.5feetofthealignmentcenterline,which
clipsthedatatothebufferandjoinsthemtothealternativesattributes
Calculatedacreageofinterestedprimefarmlandfeatures
Calculatedsummarystatisticsfortheresultinglayer,groupingbypotentialroutealternative
nameandsummingtheacreagetototalaffectedprimefarmland
ExportedthissummarytablefromArcGISandplacedintotheExceltable
A.5
Wetlands
WetlanddatawasobtainedfromtheUSFWSNWIdataset.Theanalysiswasconductedasfollows:
Intersectedwetlandpolygondatawithin62.5feetofthealignmentcenterline,whichclipsthe
wetlandstothestudyareaandjoinsinthealternativesattributes
Calculatedtheacreageofintersectedwetlandfeatures
Calculatedthesummarystatisticsfortheresultinglayer,groupingbypotentialroutealternative
nameandsummingthetotalaffectedwetlandacreage
ExportedthesummarytablefromArcGISintoExcel
46
A.6
Waterways
Thenumberofwaterwaysapotentialroutealternativecrosseswascalculatedusingthefollowing
analysis.TheGISdatawasobtainedfromtheNHD.
Intersectedstreamlineswiththepotentialalignmentalternatives,whichgeneratesapointat
everycrossingjoinedwithattributesfromboththestreamsandthepotentialroutealternative
Calculatedsummarystatisticsforthispointlayer,groupingbypotentialroutealternativename
andsummingthenumberofcrossingsforeachpotentialroutealternative
ExportedthesummarytablefromArcGISintoExcel
A.7
Floodplain
FloodplaindatawasobtainedfromFEMAandincludedboththe100and500yearfloodplain
classifications.Thefollowinganalysiswasconductedtodeterminetheacresofimpactsforeach
potentialroutealternative.
Intersectedpolygonfloodplaindatawithin62.5feetofthealignmentcenterline,whichclipsthe
floodplainstothestudyareaandjoinsinthealternativesattributes
Calculatedacreageoftheintersectedfloodplainfeatures
Calculatedsummarystatisticsfortheresultinglayer,groupingbypotentialroutealternative
nameandsummingthetotalaffectedfloodplainacreage
ExportedthesummarytablefromArcGISintotheExceltable
A.8
RoadCrossings
TheTxDOTwasthedatasourcefortheroadwayswithinthecorridor.TheGISdatasetincludedallpublic
roadsregardlessofownershiporfunctionalclass.Thenumberofroadwaycrossingswascalculatedfor
eachpotentialroutealternativebyusingthefollowsteps:
Intersectedroadwaylineswiththepotentialroutealternatives,whichgeneratedapointat
everycrossingjoinedwithattributesfromboththeroadsandthepotentialroutealternative
Calculatedsummarystatisticsforthepointlayer,groupingbypotentialroutealternativename
andsummingthenumberofroadcrossingsforeachpotentialroutealternative
ExportedthesummarytablefromArcGISintoExcel
A.9
InfrastructureAdjacency
OneofTCRsalignmentobjectivesisforapotentialroutealternativetomaximizecolocation
opportunitieswithtransportationandutilitycorridors.Thiscriterionestimatesthepercentageofthe
potentialroutealternativethatparallelsexistinginfrastructure.Thisanalysisusestheroadsdataset
fromTxDOT,railroadsdatasetfromtheU.S.NationalTransportationAtlas,andelectricaltransmission
linedatasetfromPlatts.
Todeterminethepercentageofthepotentialroutealternativethatparallelsexistinginfrastructure,the
followinganalysisoccurred:
Splitthealternativelinesattheirverticessothatthebearingofindividualsegmentscouldbe
computed
ComputedthebearingoftheseindividualsegmentsusingLinearDirectionMeanandcreateda
nondissolvedflatended1,000footbuffer(500feetfromalignmentcenterlineforeachofthese
individualsegments,whichcarriesoveralternativeattributesandthebearingoftheparentline
segment
47
Mergedtheinfrastructurefeaturesintoonefeatureclassandclippedthemtothisnewbuffer
area,primarilytocutdownonprocessingtime
Intersectedtheinfrastructurefeatureswiththenewsegmentbuffer,whichbreaks
infrastructurefeatureswherethealternativechangesdirectionandjoinsalternativeattributes
(includingbearing)
Splittheseintersectedinfrastructurefeaturesattheirverticesandcalculatedthebearingof
individualsectionsusingLinearDirectionMean
Selectedonlythoseinfrastructurefeaturesthatwerewithin5degreesofthesamebearing
(substantiallyparallel)tomoveonintheanalysis
Splittheoriginalalternativelinesinto500footsegmentsforaggregationandcreatedanon
dissolved1,000footbuffer(500feetfromalignmentcenterline)flatendedbufferofthe
resultingfeatures
Selectedonlythose500feetby1,000feetbufferfeaturesthatcontainedparallelinfrastructure
Copiedtheseselectedfeaturestoanewlayerandcreatedsummarystatistics,groupingby
potentialroutealternativenameandsummingtheirtotallength.Thisrepresentsthetotal
lengthofsegmentsofthealignmentthatareparalleledbyexistinginfrastructure
Dividedthisparallellengthbythepotentialroutealternativestotallengthtoarriveata
percentageparalleledbyexistinginfrastructure
ExportedthesummarytablefromArcGISintoExcel
A.10 MinorityPopulation
Minoritypopulationwaslookedattodeterminewhichproposedroutealternativesmight
disproportionatelyaffectEJpopulations,whicharedefinedasminorityandlowincomepopulations.
MinoritypopulationdatawasobtainedattheU.S.CensusBlocklevelfromthe2010DecennialU.S.
Census.Forthepurposesofthisanalysis,theminoritypopulationisdefinedasthetotalpopulation
minuspersonsthatreportedthemselvesasWhite,NotHispanicorLatino.Thisinformationwas
convertedintoametricbycountingthenumberofU.S.CensusBockswithaminoritypopulationover50
percentintersectingthepotentialroutealternative1,000footbuffer(500feetfromalignment
centerline).
A.11 Cemeteries
PolygoncemeterydatawasobtainedfromtheTHC.Boththenumberofimpactedcemeteriesandtotal
impactedacreagewascalculated.Onlytheimpactedacreagewasusedfortheevaluationscoring.
Thefollowinganalysiswasconductedtodeterminepotentialimpacts:
Cemeterypolygondatawasintersectedwithin62.5feetofthealignmentcenterline
Theresultingimpactedcemeteriesweredissolvedbybothpotentialroutealternativenameand
cemeterynametoinsurethatthereexistedonlyonecemeteryalternativefeaturecombination
inthedatasettoavoiddoublecountinginareaswheremanypotentialroutealternativesare
closetoeachother
Calculatedtheimpactedareainacres
Generatedsummarystatistics,groupingbypotentialroutealternativenameandsumming
togetherboththenumberofimpactedcemeteriesandtotalimpactedacreage
ExportedthissummarytablefromArcGISandinserteditintotheExceltable
48
A.12 Ecology
TheTXNDDelementoccurrencedatafromTPWDdepictsareaswherethreatenedandendangered
specieshavebeenobserved.Thisdoesnotnecessarilymeanthatthesespeciesarepresent,butitisan
indicatorthatanelementisorwaspresentandhaspracticalconservationvalue.Impactswere
determinedfromthefollowinganalysis:
IntersectedtheTXNDDlayerwithin62.5feetofthealignmentcenterlineofthepotentialroute
alternative,whichclippedthelayerandjoinedinthealternativesattributes
Calculatedtheareaofthepolygonfeaturesinthisintersectedelementoccurrencelayer
Generatedsummarystatistics,groupingbypotentialroutealternativenameandsummingthe
totalpotentialimpactedacreage
ExportedthesummarytablefromArcGISandinserteditintotheExceltable
A.13 CommunityFacilities
Communityfacilitydataisavailablefromanumberofdifferentsourcesandcoversawidevarietyof
facilities,butonlytheGeographicNamesInformationService(GNIS)datasetcoverstheentirecorridor
consistently.GNISdataisdeliveredinadelimitedtextfilefortheentirestateofTexas.
Theanalysiswasconductedasfollows:
ImportedthetextfileintoExcel,cleaneditup,andsaveditasaspreadsheet
ImportedthespreadsheetintoArcGISusingExceltoTabletool
UsedtheMakeXYEventLayertooltoprojectthistabulardataintospatialpointsusingNAD83
coordinatesprovidedinthedatasetsattributes
UsedSelectByLocationtoselectfeaturesfromthislayerwithinthealignmentcounties
UsedSelectByAttributestoselectfeaturesfromtheseselectedfeaturesthatarewithinthe
followingGNISfeatureclasses:Building(publicfacilitiesincluded),Church,Hospital,Post
Office,School
Exportedthisselectionasitsownlayer,andthenintersectedthislayerwiththe1,000foot
buffer(500feetfromalignmentcenterline),whichclipstheGNISpointstothealternativebuffer
andjoinsinthealternativeattributes
Performedsummarystatisticsonthisintersectedlayer,groupingbypotentialroutealternative
nameandsummingthenumberofpointsintersectedbyeachalignmentbuffer
ExtractedthesetotalnumbersfromArcGISandinsertedthemintotheExceltable
A.14 HistoricProperties
TheNationalRegisterofHistoricPlaces(NRHP)wasusedtodeterminepotentialimpactstohistoric
properties.Bothindividualproperties(points)anddistricts(polygons)werelookedatbyusingthe
methodologydescribedbelow.
IntersectedboththepointandpolygonNRHPdatawiththe1,000footbuffer(500feetfrom
alignmentcenterline),whichclipsthesefeaturestothebufferareaandjoinstheminthe
alternativesattributes
Calculatedthesummarystatisticsforbothoftheselayers,groupingthembyalternativename
andsummingthetotalnumberofNHRPdistrictsandproperties
ExportedbothofthesesummarytablesfromArcGISandenteredthemintotheExceltable
49
A.15 HazardousMaterialsSites
HazardousmaterialsiteswereobtainedfromtheTexasCouncilonEnvironmentalQuality(TCEQ),data
includedmunicipalsettingdesignations;municipalsolidwastelandfills,radioactivesites,Superfund
sites,municipalwaterwells,andundergroundpetroleumstoragetanks.
Thefollowinganalysiswasconductedtodeterminepotentialimpacts:
Intersectedeachsetoffeatureswithin62.5feetofthealignmentcenterlineofthepotential
routealternatives,whichclippedthesitesandjoinedtheminthealternativeattributes
Generatedsummarystatisticsforeachsetoffeatures,groupingbypotentialroutealternative
nameandsummingthenumberofintersectinghazardousmaterialsites
Joinedtheresultingtablestogether,whichyieldsasingletablewitharowforeachpotential
routealternativeandcolumnforeachtypeofhazardousmaterialsite
Summedthetotalnumberofhazardousmaterialsitesforeachpotentialroutealternative,
exportedthetablefromArcGISandinserteditintotheExceltable
A.16 PopulationbelowPovertyLine
Povertydatafromthe20135yearAmericanCommunitySurvey(ACS)wasobtainedattheU.S.Census
BlockGroupleveltodeterminewhichproposedroutealternativesmightdisproportionatelyaffectEJ
populations.TheinformationwasconvertedintoametricbycountingthenumberofU.S.CensusBlock
Groupsthatintersectthepotentialroutealternatives1,000footbuffer(500feetfromalignment
centerline)where50percentormoreofthepopulationisbelowthe2013povertylineof$23,550fora
familyoffour(4).
50