Académique Documents
Professionnel Documents
Culture Documents
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\01N
DATE OF ISSUANCE:
20 July 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date July 20, 1999, ref.No. 002/LP-I/VII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
b. Total approved VO
Update contract value
SUBSEQUENT CHARGE ORDER
NUMBER
0.00%
2,600,000,000.00
100.00%
APPROVED
V.O.
100.00%
(DATED)
0.00
0.00%
259,778,583.71
9.99%
e. Achieved progress (d - c)
259,778,583.71
9.99%
-51,955,716.74
(-e% x DP.)
g. Retention 5%
Total recommended to be paid
-12,988,929.19
(-5% x e.)
194,833,937.78
(e+f+g)
By word:
Thirty four million nine hundred ninety seven thousand and fifty rupiah
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
2,600,000,000.00
NUMBER
APPROVED
259,778,583.71
V.O.
(DATED)
488,455,432.91
e. Achieved progress (d - c)
228,676,849.20
-45,735,369.84
g. Retention 5%
-11,433,842.46
171,507,636.90
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
100.00%
0.00%
100.00%
9.99%
18.79%
8.80%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
2,600,000,000.00
NUMBER
APPROVED
488,455,432.91
V.O.
(DATED)
849,921,363.77
e. Achieved progress (d - c)
361,465,930.86
-72,293,186.17
g. Retention 5%
-18,073,296.54
271,099,448.15
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
100.00%
0.00%
100.00%
18.79%
32.69%
13.90%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
2,600,000,000.00
NUMBER
APPROVED
849,921,363.77
V.O.
(DATED)
1,180,282,726.50
e. Achieved progress (d - c)
330,361,362.73
-66,072,272.55
g. Retention 5%
-16,518,068.14
247,771,022.05
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
100.00%
0.00%
100.00%
32.69%
45.40%
12.71%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
2,600,000,000.00
NUMBER
APPROVED
1,180,282,726.50
V.O.
(DATED)
1,246,205,440.15
e. Achieved progress (d - c)
65,922,713.65
-13,184,542.73
g. Retention 5%
-3,296,135.68
49,442,035.24
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
100.00%
0.00%
100.00%
45.40%
47.93%
2.54%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
441,841,777.50
3,041,841,777.50
NUMBER
APPROVED
1,246,205,440.15
V.O.
(DATED)
1,482,470,326.12
e. Achieved progress (d - c)
236,264,885.97
-40,389,260.75
g. Retention 5%
-11,813,244.30
184,062,380.92
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
85.47%
14.53%
100.00%
40.97%
48.74%
7.77%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
441,841,777.50
3,041,841,777.50
NUMBER
APPROVED
1,482,470,326.12
V.O.
(DATED)
1,587,388,579.69
e. Achieved progress (d - c)
104,918,253.57
-17,935,677.08
g. Retention 5%
-5,245,912.68
81,736,663.81
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
85.47%
14.53%
100.00%
48.74%
52.19%
3.45%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
970,212,071.36
3,570,212,071.36
NUMBER
APPROVED
1,587,388,579.69
V.O.
(DATED)
1,896,520,724.90
e. Achieved progress (d - c)
309,132,145.21
-45,024,976.75
g. Retention 5%
-15,456,607.26
248,650,561.20
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
72.82%
27.18%
100.00%
44.46%
53.12%
8.66%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
1,494,109,071.36
4,094,109,071.36
NUMBER
APPROVED
1,896,520,724.90
V.O.
(DATED)
2,293,129,810.37
e. Achieved progress (d - c)
396,609,085.47
-50,374,018.10
g. Retention 5%
-19,830,454.27
326,404,613.10
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
63.51%
36.49%
100.00%
46.32%
56.01%
9.69%
(-e% x DP.)
Teruskan
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
1,494,109,071.36
4,094,109,071.36
NUMBER
APPROVED
2,293,129,810.37
V.O.
(DATED)
3,276,793,162.47
e. Achieved progress (d - c)
983,663,352.10
-117,034,979.29
g. Retention 5%
-49,183,167.61
817,445,205.20
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
63.51%
36.49%
100.00%
56.01%
80.04%
24.03%
(-e% x DP.)
Oke
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
1,494,109,071.36
4,094,109,071.36
NUMBER
APPROVED
3,276,793,162.47
V.O.
(DATED)
3,665,323,518.40
e. Achieved progress (d - c)
388,530,355.93
0.00
g. Retention 5%
-19,426,517.80
369,103,838.13
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
63.51%
36.49%
100.00%
80.04%
89.53%
9.49%
(-e% x DP.)
Oke
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
1,494,109,071.36
4,094,109,071.36
NUMBER
APPROVED
3,665,323,518.40
V.O.
(DATED)
3,895,523,714.03
e. Achieved progress (d - c)
230,200,195.63
0.00
g. Retention 5%
-11,510,009.78
218,690,185.85
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
63.51%
36.49%
100.00%
89.53%
95.15%
5.62%
(-e% x DP.)
Oke
(-5% x e.)
(e+f+g)
Teruskan
CERTIFICATE
FOR PAYMENT
PROJECT:
CERTIFICATE NO.:
LS\02N
DATE OF ISSUANCE:
03 August 1999
PROJECT NO.:
10
CONTRACTOR:
CONTRACT FOR:
MAGELANG, JATENG
TO:
(Employer)
PROJECT PHASE I
CONTRACT DATE:
28 June 1999
In accordance with this Contract and the attached Application for payment date August 03, 1999, ref.No. 010/LP-I/VIII/1999, the Contractor is entitled
to payment in the amount stipulated below. The present status of the account for this Contract is as follows:
ADDITION RP.
DEDUCTION RP.
a. Original Contract
2,600,000,000.00
1,494,109,071.36
4,094,109,071.36
NUMBER
APPROVED
3,895,523,714.03
V.O.
(DATED)
4,094,109,071.36
e. Achieved progress (d - c)
198,585,357.33
0.00
g. Retention 5%
-9,929,267.87
188,656,089.46
By word:
Seventy seven million three hundred sixty three
thousand and sixty hundred rupiah
0.00
TOTAL
SUPERVISOR:
CONTRACTOR:
EMPLOYER:
PT. LUPITA AMANDA
Signed:
Signed:
Signed:
Name:
Name:
Name:
Date:
Date:
Date:
This certificate is negotiable. It is payable only to the payee herein and its issuance, payment and acceptance are without prejudice to any rights of the Employer or Contractor
under their contract. If application for payment or other application form containing satisfactory evidence of payment for work previously completed DOES NOT ACCOMPANY
THIS CERTIFICATE, the Contractor shall first provide the equivalent certification by completing and executing the following:
The undersigned that the works covered by this Certificate for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid for
for which previous Certificate for Payment issued and payments received, and that the current payment shown herein is now due.
TIFICATE
PAYMENT
Contractor is entitled
63.51%
36.49%
100.00%
95.15%
100.00%
4.85%
(-e% x DP.)
Oke
(-5% x e.)
(e+f+g)
Oke
No.
%
1
2
3
4
5
6
7
8
9
10
11
12
13
9.99%
8.80%
13.90%
12.71%
2.54%
7.77%
3.45%
8.66%
9.69%
24.03%
9.49%
5.62%
4.85%
Total
Progress
Nilai (Rp)
Total Pot.
Uang Muka s/d
12,988,929.19
11,433,842.46
18,073,296.54
16,518,068.14
3,296,135.68
11,813,244.30
5,245,912.68
15,456,607.26
19,830,454.27
49,183,167.61
19,426,517.80
11,510,009.78
9,929,267.87
194,833,937.78
171,507,636.90
271,099,448.15
247,771,022.05
49,442,035.24
184,062,380.92
81,736,663.81
248,650,561.20
326,404,613.10
817,445,205.20
369,103,838.13
218,690,185.85
188,656,089.46
3,369,403,617.79
Uraian
Kontrak
VO
Total
Selisih
259,778,583.71 51,955,716.74
228,676,849.20 45,735,369.84
361,465,930.86 72,293,186.17
330,361,362.73 66,072,272.55
65,922,713.65 13,184,542.73
236,264,885.97 40,389,260.75
104,918,253.57 17,935,677.08
309,132,145.21 45,024,976.75
396,609,085.47 50,374,018.10
983,663,352.10 117,034,979.29
388,530,355.93
0.00
230,200,195.63
0.00
198,585,357.33
0.00
Total
( Rp )
Nilai (Rp.)
DP 20%
Retensi 5%
Yg harus dibayarkan
1,950,000,000.00
1,494,109,071.36
74,705,453.57
1,419,403,617.79
3,369,403,617.79
0.00
0.00
0.00
0.00
0.00
51,955,716.74
97,691,086.58
169,984,272.75
236,056,545.30
249,241,088.03
289,630,348.78
307,566,025.86
352,591,002.61
402,965,020.71
520,000,000.00
520,000,000.00
520,000,000.00
520,000,000.00
Total
194,833,937.78
366,341,574.68
637,441,022.83
885,212,044.88
934,654,080.11
###
###
###
###
###
###
###
###