Académique Documents
Professionnel Documents
Culture Documents
a.
b. To achieve the highest expected payoff, management should build large plant.
#17, p.68:
a.
b. The company should buy 2 machines initially. The expected payoff for this
alternative will be $90,000 if demand is low and $180,000 if demand is high.
#20, p. 68:
Benjamin Moses should try the new facility. Since the payoff for the case that new
technology works is $8 million ($20 million* 0.4) is bigger than the payoff for when
the new facility fail ($10 million * 0.6)
#3, p. 238:
If the demand is expected to increase from 70 customers per day to 84 customers
per day, the demand is expected to increase by 20 percent, hence the capacity
requirements also need to increase by 20 percent.
If the desired capacity cushion is 25 percent, management should plan for enough
capacity to serve [84/(1-0.25)]= 112 customers in 3 years.
#4, p. 238:
a. The number of hours of operation per year, N, is:
N= (2 shifts/day)(8 hours/shift)(260 days/ machine-year)= 4160 hours/machine-year
- The number of machines required to meet minimum (pessimistic) demand,
Mpessimistic, is:
[ ( )] [ ( )] [ ( )]
Dp+
Mpessimistic=
D
D
D
s A+ Dp+
s B+ Dp+
s C
Q
Q
Q
( 100C )]
N [1
( 150000.05 )+
10000
17000
1.0 + ( 100000.20 ) +(
4.5 +[ ( 170000.05 ) +(
8.2]
( 15000
)
)
]
[
]
60
80
120 )
4160[1
20
]
100
1.675 or 2 machines
Mexpected= =
Dp+
( 180000.05 )+
13000
25000
+ ( 130000.20 ) + (
4.5 + ( 250000.05 ) + (
8.2
( 18000
)
)
]
[
]
[
60
80
120 ) ]
4160 1
1200+3331.25+ 2958.4
=2.2504
=
3328
20
100
or 3 machines
[ ( )] [ ( )] [ ( )]
Dp+
Moptimistic= =
D
D
D
s A+ Dp+
s B+ Dp+
s C
Q
Q
Q
( 100C )]
N [1
( 250000.05 )+
17000
40000
+ (170000.20 ) + (
4.5 + (400000.05)+(
8.2
( 25000
)
)
]
[
]
[
60
80
120 ) ]
4160 1
20
100
Lot Size
(Units/lot)
120
160
240
[ ( )] [ ( )] [ ( )]
D
D
D
s A+ Dp+
s B+ Dp+
s C
Q
Q
Q
Dp+
Mpessimistic=
( 100C )]
N [1
( 150000.05 )+
10000
17000
1.0 + ( 100000.20 ) +(
4.5 +[ ( 170000.05 ) +(
8.2]
( 15000
)
)
][
]
120
160
240 )
4160[1
875+2281. 25+1430.8
3328
20
]
100
1.378 or 2 machines
Mexpected= =
Dp+
( 180000.05 )+
13000
25000
+ ( 130000.20 ) + (
4.5 + ( 250000.05 ) + (
8.2
( 18000
)
)
]
[
]
[
120
160
240 ) ]
4160 1
20
100
1050+ 2965.6+2104.2
=1.838 or 2 machines
3328
Moptimistic= =
Dp+
( 250000.05 )+
17000
40000
+ (170000.20 ) + (
4.5 + (400000.05)+(
8.2
( 25000
)
)
]
[
]
[
120
160
240 ) ]
4160 1
20
100
Component
A
B
C
Setup (hr/lot)
0.8
3.6
6.56
time:
[ ( )] [ ( )] [ ( )]
Dp+
Mpessimistic=
D
D
D
s A+ Dp+
s B+ Dp+
s C
Q
Q
Q
( 100C )]
N [1
( 150000.05 )+
10000
17000
0.8 + ( 100000.20 ) + (
3.6 +[ ( 170000.05 )+ (
6.56]
( 15000
)
)
]
[
]
60
80
120 )
4160 [1
275+ 650+1779.4
3328
20
]
100
0.812 or 1 machine
For pessimistic demand, if the operations manager has 3 machines, the plant has
adequate capacity if they want to reduce the setup time by 20 percent without
increasing lot sizes.
- The number of machine required to meet expected demand, M expected, is:
[ ( )] [ ( )] [ ( )]
Dp+
Mexpected= =
D
D
D
s A+ Dp+
s B+ Dp+
s C
Q
Q
Q
( 100C )]
N [1
( 180000.05 )+
13000
25000
0.8 + ( 130000.20 ) + (
3.6 + ( 250000.05 ) +(
6.56
( 18000
)
)
][
][
]
60
80
120 )
4160 1
1140 +3185+2616.7
=2.085
3328
20
100
or 3 machines
For expected demand, if the operations manager has 3 machines, the plant has
adequate capacity if they want to reduce the setup time by 20 percent without
increasing lot sizes.
- The number of machine required to meet maximum (optimistic) demand, M optimistic,
is:
Moptimistic =
Dp+
( 250000.05 )+
17000
40000
0.8 + (170000.20 ) + (
3.6 + (400000.05)+ (
6.56
( 25000
)
)
]
[
]
[
]
60
80
120 )
4160 1
20
100
For optimistic demand, if the operations manager has 3 machines, the plant has
adequate capacity if they want to reduce the setup time by 20 percent without
increasing lot sizes.
#8, p.238:
The number of hours of operation per year, N, is:
N= (2 shifts/day)(8 hours/shift)(200days/ machine-year)= 3200 hours/machine-year
The number of machine required to meet upcoming years demand are:
[ ( )] [ ( )]
Dp+
M=
D
D
s kites+ Dp+
s wind socks
Q
Q
N [1
( 300000.3 )+
( 100C )]
12000
3.0 +[ ( 120001.0 ) +(
4.0 ]
( 30000
)
]
20
70 )
3200 [1
25
]
100
13500+12685.7
=10.9 or 11
2400
machines
Currently the company has 4 machines, 7 more machines need to be purchased in
order to meet the upcoming years demand without resorting to any short-term
capacity solutions.