Académique Documents
Professionnel Documents
Culture Documents
X
X
X
X
Computer can
indirectly help
X
X
Figure 1
t is possible that more microcomputers have been
purchased by the construction industry and its practitioners than by any other industry. Many software
p ro g rams for the construction industry are now
available to perform functions such as accounting, estimating and scheduling. Because accounting and estimating software programs follow most contractors existing manual procedures, the contractor has to adjust
his operating procedures only slightly to benefit from
computerization in these areas. Un f o rt u n a t e l y, the
same cannot be said of computer software for planning
and scheduling.
duration
20 days
___________________
Erect Wall Forms
Figure 2
by itself cannot obtain accurate input data. These data
must come from the constructor, who must derive them
from his own, accurate manual procedures.
forming walls, placing reinforcing bars and placing concrete walls is defined as three jobs or just one function,
erecting walls. Breaking jobs down into too many separate activities tends to discourage jobsite personnel from
using such detailed schedules. On the other hand, too
little detail makes a project schedule practically useless.
When defining activities, keep in mind that they
should be compatible with the intended purpose and
use of the schedule, compatible with the estimate breakdown, compatible with field reporting for cost control,
and compatible with the billing system that is used for
making progress pay requests.
Determine activity logic. Whether a project schedule
is produced manually or by computer, its activities
should be sequenced to model or represent the planned
actual construction process. For example, the pouring of
concrete walls must follow the placing of footings. In
addition to this technical logic, the project schedule
must also recognize resource logic and preference logic
of the builder. Resource logic may in fact take into account limited resources, such as too few carpenters to allow forming both the north and east walls at the same
time. Preference logic is the reasoning behind the decision of a contractor to do one activity after another, despite the ability and availability of resources, usually for
economic reasons.
Determine activity duration. A project schedule is only as good as the accuracy of its activity durations. The
only way to calculate an activity duration is to determine
it based on the quantity of work to do, the estimated productivity, and the establishment of a crew size. The computer by itself cannot determine the durations for the
contractor.
Figure 3
DUR
EST
EFT
LST
LFT
FF
FFP
TF
11
16
16
16
24
24
26
24
26
26
28
13
11
16
16
20
16
20
20
28
20
28
28
34
28
34
20
22
37
39
17
17
17
34
39
34
39
Figure 4
Legend:
DUR = Duration
EST = Earliest Start Time
EFT = Earliest Finish Time
LST = Latest Start Time
LFT = Latest Finish Time
FF = Free Float
FFP = Free Float Prime
TF = Total Float
should incorporate meaningful activity logic and durations from all contractors working on the project. These
c o n t ra c t o r s, in turn, should understand the schedule
and cooperate with it.
Draw the project schedule. Figure 3 illustrates a very
small drawn schedule. While a computerized plotting
program yields impressive results, a bar chart is not difficult to plot or draw manually once activities are defined, logic determined, and durations established.
Pe rf o rm schedule calculations. For big projects with
numerous activities, the computer user saves seve ra l
hours and perhaps even days at this point. If a mathematical scheduling technique such as CPM is used, the
calculations necessary to determining project duration,
activity start and finish times, and activity floats can be
done by a computer in almost no time at all. Example
output from one of these programs is shown in Figure 4.
Use computerized software to plan and manage resources. Modern computer software can use CPM as a
basis for leveling or allocating various project resources
such as labor, equipment or cash for specific purposes
like minimizing project costs. Although sophisticated
p ro g rams can do almost every type of resource allocation imaginable, it is important to question the usefulness of every application.
Obtain field data to update schedule. Two months into a 10-month project, one can argue that a new 8month project is just beginning. Obtaining field data to
reflect the events to date is fundamental to the updating
of a project schedule. Ac c u ra t e, complete and timely
field reporting is essential to the updating of a project
plan and, clearly, cannot be accomplished by the computer alone.
Make calculations to prepare a revised or working
schedule. A schedule that is not revised and kept current may be worse than no schedule at all. The strongest
argument for computerized planning is the ease and
speed of performing the otherwise tedious and timeconsuming mathematics necessary to the preparation of
revised schedules throughout the duration of a project.
Take steps to react to problems determined from
analysis of schedule. The purpose of using a formalized
schedule during the construction project is to detect
possible problems in time to take corrective action. The
computer only processes information that can clarify
such problems. Follow-up must take the form of manual interpretation and intervention.
The majority of the above steps can be perf o rm e d
manually, and many of them can only be perf o rm e d
manually. Yet the computer can play an important role
in getting the most out of effective manual scheduling
procedures.
PUBLICATION#C860153
Copyright 1986, The Aberdeen Group
All rights reserved