Vous êtes sur la page 1sur 5

Method Statement for Cable

Conduit & Tray Installation


PROJECT NAME

: Khabat Thermal Power Plant Units 1&2

DOCUMENT NO.

: KP-00+++-CY712-B7201

TITLE

: Method Statement for

TOTAL 5 PAGES
(Including Cover)

Purpose
For Information
For Review
For Approval

Cable Conduit & Tray Installation


OWNER

For Construction

: Ministry of Electricity (MOE) of


Kurdistan Regional Government

11.08.2015

Rev.
No.

DATE

As-Built

For Review
PREPARED
DESCRIPTION

CHECKED

REVIEWED

APPROVED

GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

Owner

Ministry of Electricity (MOE)


of Kurdistan Regional Government
Contractor

POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor

GAMA POWER SYSTEMS


ENGINEERING & CONTRACTING,INC.

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-B7201

Method Statement for

Rev. No.

Cable Conduit & Tray Installation

Page

2 of 5

Contents
1. PURPOSE...
2. SCOPE..
3. RESPONSIBILITIES
4. PROCEDURES.......

5. ACCEPTANCE CRITERIA

6. REFERENCES

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-B7201

Method Statement for

Rev. No.

Cable Conduit & Tray Installation

Page

3 of 5

1. PURPOSE
The purpose of this method statement is to outline the sequences&methods of works
intended to be used for the Cable Conduit & Tray Installation.
2. SCOPE
This procedure is applicable to the KHABAT Project.Also including to the cable tray
installation according to the agreement.

3. RESPONSIBILITIES
Participate in and provide input to Safety Task Analysis Risk Reduction Talk
(START)/Job Hazard Analysis. Provide HSE coverage for Commissioning activities and
walk downs.
Cable tray supervisor shall be ensuring that work area facilities are safe prior to cable
tray work activities.
Personel Protection Equipment have to be used by workers
Our staff has the responsibility to check if workers are wearing the proper PPE at site.
If a worker is not working proper to the HSE rules; supervisor will stop him.

Related Personnel
Project Manager; directs and coordinates the work execution and the administration of
the worksso as to ensure to compliance with the established schedule ,budgets and quality
requirements.
Construction Manager, manage the activity of construction personnel ,to ensure that
the construction and installation work is in accordance with the established construction
schedule .
QC Department;responsible controlling and directing the activities complying with the
quality requirements given in the references and reports to the Project Manager.
Administering and approving project inspection and test plan.
Reporting quality problems to the Project Manager.

4. PROCEDURES
NOTE: The vendors instruction manual takes precedence over this procedure in the
event of conflicts. Detailed equipment installation procedures and parameters shall be
according to the vendors manuals.

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-B7201

Method Statement for

Rev. No.

Cable Conduit & Tray Installation

Page

4 of 5

Installation&Manufacturing of Cable Tray Supports shall be suitable to the project


design.Strength of the supports have to be proportional to the cable tray size and pulling
cable.Welding Quality of the supports are important if support manufacturing will be welded.
Ensure that proper materials are available and are approved for use, as well as
the approved drawings.
Verify site access/routing and mark support locations.
Obtain work permit, if required.
Fix the support on the natural structures.
Fix the vertical ladder trays channel on the support.
The cable trays and ladders shall be installed in such a way that ,as often as
possible the cables can be laid directly in place rather than being pulled through.
Clearance shall be maintened according to the approved drawing and
specifacations.
Sharp edges of trays & ladders shall be reamed to smooth and paint.
Connect earth bonding.
Cable Conduit;
Support interval shall not exceed 1500mm unless otherwise specified.
Tools and Equipment;
Electrical Grinder
Electrical Drill
Conduit Bender
Hand Tools
Scaffolding,if required
Crane, if required
Hi Up , if require

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-B7201

Method Statement for

Rev. No.

Cable Conduit & Tray Installation

Page

5 of 5

5. ACCEPTANCE CRITERIA
Installation of cable conduit & tray installation shall be within project design and vendor
requirements and tolerances.

6. REFERENCES

Cable Tray Layout

Cable Tray Support Layou

E&I Standart Detail Drawings

Vendors Instruction Manual and Associated Drawings

Vous aimerez peut-être aussi