OCTOBER 2015
1
INDEX
SECTION 1 Invitation for Bids ................................................................................ 2
SECTION 2 Instructions to Bidders ........................................................................... 4
SECTION 3 Evaluation and Qualification Criteria .......................................................30
ECTION 4 Bid Forms.. ...........................................................................................38
SECTION 5 Technical Specifications and Drawings ...................................................66
Schedule of Contract Drawings ...............................................................................93
A. Meet storage Plans ..........................................................................................94
B. Bills of Quantities. ...........................................................................................95
SECTION 6 Contract.. ......................................................................................... 128
SECTION 1
2
SECTION 1
Invitation for Bids
1.
2.
The Ministry of Agriculture, Livestock and Fisheries, now invites eligible Polish
entrepreneurs or its joint ventures or consortia to submit their sealed bids in order
to Supply, Install, Test and Commission the projects in accordance with the bidding
documents.
3.
The Goods and Services included under the scope of the Project must comply with
the requirements of origin established in the Bidding Documents.
4.
5.
In Kenya, the Bidding Documents will be available to eligible bidders from the
website in 4 above.
6.
7.
8.
9.
Bids in Plain sealed envelopes, marked with the tender number and corresponding
description to be sent or deposited in the tender box provided at Kilimo House,
reception to be received on or before 27th November, 2015 at 12.00 noon
(East African Time). Late bids will be rejected.
SECTION 1
3
10. Bids will be opened on 27th November, 2015 at 12.00 noon (East African
Time) in the presence of duly authorised representatives of Bidders wishing to
attend and a representative of the Polish Embassy in Kenya. The opening date for
the tenders will be notified to the Polish Embassy in Kenya.
11. All Bids must be accompanied by a Bid Security, denominated in US Dollar (USD),
duly issued by a bank of renowned international repute in the sum of 1% of the
tender sum valid for a time period of One Hundred and Fifty (150) days from the
date of bid opening.
12. One hardcopy and one electronic copy of each of the submitted Bids shall be given
to the representative of the Government of the Republic of Poland Office in Kenya at
the time of the opening of the Bids.
SECTION 1
4
SECTION 2
Instructions to Bidders
INDEX
SECTION 2 Instructions to Bidders ........................................................................... 4
A. GENERAL PART ............................................................................................. 6
1. Scope of Bids .............................................................................................. 6
2. Source of Funds .......................................................................................... 6
3. Bidding Process Schedule ............................................................................. 7
4. Eligibility .................................................................................................... 7
5. Technical, Economic and Financial Capacity of Bidders ..................................... 9
6. Bidding Documents .....................................................................................11
7. Clarification of Bidding Documents ................................................................11
8. Amendment of Bidding Documents ...............................................................12
9. Site Visit / Clarification Meeting ....................................................................12
10. Cost of Bidding ...........................................................................................12
11. Language of Bid .........................................................................................12
12. Bid Price ....................................................................................................12
13. Documents Comprising the Bid .....................................................................13
14. Documents Establishing the Eligibility of the Bidder ........................................15
15. Documents Confirming that the Project Meet the Bidding Documents Technical
Requirements. ...........................................................................................17
16. Period of Validity of Bids ..............................................................................18
17. Bid Security ...............................................................................................18
B. SUBMISSION OF BIDS .................................................................................20
18. Format and Signing of Bid ...........................................................................20
19. Submission, Sealing and Marking of Bids .......................................................20
20. Deadline for Submission of Bids ...................................................................22
21. Late Bids ...................................................................................................22
22. Modification of or withdrawal of Bids .............................................................22
C. BIDS OPENING AND EVALUATION .................................................................22
23. Bid Opening ...............................................................................................22
24. Confidentiality ............................................................................................23
25. Clarification of Bids .....................................................................................23
26. Responsiveness of Bids ...............................................................................23
27. Evaluation of Bids .......................................................................................24
28. Nonconformities, errors and omissions ..........................................................24
29. Right of the Contracting Authority to accept or reject any Bid ..........................25
SECTION 2
5
D. CONTRACT AWARD ......................................................................................26
30. Notification of Award ...................................................................................26
31. Signing of Contract .....................................................................................26
32. Performance Security ..................................................................................27
33. Ethics Clauses ............................................................................................27
SECTION 2
6
INSTRUCTIONS TO BIDDERS
A.
1.
2.
GENERAL PART
Scope of Bids
1.1
1.2
(b)
(c)
(d)
any terms set out shall be interpreted pursuant to the definitions given
under the General Conditions of Contract included in SECTION 6 of
these Bidding Documents.
Source of Funds
2.1
2.2
The award procedure for this Project will be governed by the provisions
established under the Inter-Governmental Credit Agreement signed on
September 22nd, 2015 entered into between the Treasury of the Republic of
Kenya (hereinafter referred to as the Government of Kenya) on behalf of the
Republic of Kenya and the Republic of Poland, as well as, by public
procurement law and any other applicable law in the beneficiary country.
2.3
SECTION 2
7
2.4
3.
4.
26/10/2015
27/11/2015
26/03/2016
13/11/2015
20/11/2015
27/11/2015
Eligibility
4.1
Eligible Bidders
4.1.1
SECTION 2
(b)
fully
by
Polish
(i)
(ii)
8
(iii) If the Bidder is in the form of JV or Consortium, any
resources of the parties under the JV or Consortium shall
be mutually bound as a one entity resource.
4.1.2
4.1.3
4.2
SECTION 2
4.1.4
4.1.5
Bidders must provide evidence that they have complied with the
provisions set down in international agreements entered into by
Poland with regard to company liability, labour rights and gender
equality rights and, particularly, in agreements regarding the fight
against corruption and environmental concerns of the Credit for
Export Group of the Organisation for Economic Co-operation and
Development (hereinafter, OECD). Bidders must provide evidence
that they have not been sanctioned for any violations of human
rights, for having participated in any corrupt practices nor for having
breached any agreements regarding workers rights, childhood rights
or any other ethics in contradiction of international agreements
ratified by Poland.
4.1.6
4.1.7
4.3
4.2.1
The origin of the Goods, Services and Works of the Project and to be
financed by the Government of Poland must adhere to the provisions
set down within the Bilateral Financial Cooperation Agreement
between the Government of Kenya and the Government of Poland as
well as those set down in the General Agreement regarding guidelines
for export credit matters officially approved by the OECD.
4.2.2
4.2.3
Bidders must expressly state, at the time the Bid is submitted, that
all the goods and services duly comply with requirements regarding
origin and set out the corresponding countries of origin in Form 8
Price Lists (SECTION 4 of these Bidding Documents). Documents
submitted as evidence of eligibility of Goods and Services must
comprise a sworn declaration of country of origin for the Goods and
Services, duly confirmed, with regard to the Goods, by submission of
an official certificate of origin, as issued by the Polish Chamber of
Commerce if the aforesaid certificate is issued in Poland and at the
time of shipment. Failure to submit such certificates or breach of
requirements regarding origin might imply the termination of the
Contract.
4.2.4
For all purposes with regard to this Clause, the term origin of Goods
must be specified pursuant to Community Customs Code (European
Community (EEC) Regulation No 2913/92 and corresponding
legislation for execution, European Commission (EC) Rules No
2454/93). Furthermore, the country of origin of the Services shall be
the same as that of the company providing the Services.
5.
Bidders must set out in detail within the Bid all the main elements to
be subcontracted, stating the name and nationality of such proposed
sub-contractor companies. The Bidder must ascertain that all
proposed subcontractors duly meet eligibility requirements as set
down under Clauses 4.1 and 4.2 of these Instructions to Bidders.
SECTION 2
10
5.1
In order to take part in this Bidding Process, the Bidders must provide
sufficient evidence to the Contracting Authority to show that they meet the
minimum compulsory technical, economic and financial specifications, i.e. that
they have the necessary capacity and sufficient resources to perform the
Contract effectively.
5.1.1
5.1.2
Current Ratio 1
Bidders must comply with a Current Ratio (=Total current assets /
Total current Liabilities) 1.
Bidders must provide evidence of compliance with this ratio for the
last 3 (three) available audited financial years as set down under
Clause 14.2. In case of a Bid submitted by a Joint Venture or
Consortium this minimum requirement is to be fulfilled by each of the
members of the Joint Venture or Consortium.
5.1.3
5.1.4
SECTION 2
11
5.1.5
Bank References
Bidders must submit bank references from two major financial
institutions of renowned international repute with which the Bidder
customarily does business.
5.2
6.
Bidding Documents
6.1
7.
The Bidding Documents comprise the documents set out below, together with
any changes made by the Contracting Authority pursuant to Clause 8
(Amendment of Bidding Documents) of these Instructions to Bidders:
SECTION 1:
SECTION 2:
Instructions to Bidders
SECTION 3:
Evaluation of Bids
SECTION 4:
Bid Forms
SECTION 5:
Technical Requirements
SECTION 6:
Contract Agreement
6.2
The Contracting Authority does not accept liability for completeness and
accuracy of the Bidding Documents and its amendments, unless they were
obtained directly from the Contracting Authority.
6.3
Bidders are responsible for checking instructions, forms, terms and conditions
and specifications of the Bidding Documents.
Any Bidder requiring clarification of any kind with regard to the Bidding
Documents must submit his request to the Contracting Authority, in writing,
at the following address:
Ministry of Agriculture, Livestock and Fisheries
State Department of Livestock
Address: P. O. Box 34188-00100 Nairobi, Kenya
Contact Person: Head, Supply Chain Management Services
Telephone: +254 020 2718870
Email:pslivestock@kenya.go.ke
Website: www.kilimo.go.ke
SECTION 2
12
8.
9.
7.2
The Contracting Authority will reply in writing to all requests for clarification,
as long as these are received before the end of the time period set out under
Clause 3 (Bidding Process Schedule) of these Instructions to Bidders. The
Contracting Authority will forward a copy of the clarifications, including a
description of the enquiries raised, without identifying the source, to all
parties that obtained the Bidding Documents directly from the Contracting
Authority. If, as a result of these clarifications, the Contracting Authority
deems it necessary to amend the Bidding Documents the procedure set out
under Clause 8 (Amendment of Bidding Documents) of these Instructions to
Bidders shall apply.
7.3
8.2
The Contracting Authority will organise site visit/ Clarification Meeting to the
successful bidders
SECTION 2
The Bidders, prior to submitting their Bid, are deemed to have satisfied
themselves that the Bid is correct and sufficient; that they have duly taken
into account all factors as necessary to fully and properly fulfil the Contract
and that they have included all costs within their rates and prices.
13
12.3 The Bidders must quote the total cost of the project, under their sole
responsibility and in such a manner that the total Price Proposal covers all
Contractor obligations with regard to design, manufacturing, including any
purchases or subcontracted items, delivery, works, assembly, installation,
tests and commissioning of the Project as set out in the Bidding Documents or
as may be reasonably inferred from the aforesaid documents. This is deemed
to include all Contractor obligations with regard to testing, inspections and
trials prior to commissioning, as well as Contractor obligations regarding
operation, maintenance and training services and other concepts and services
as specified within the Bidding Documents, all pursuant to the Contract
provisions. Any prices given for items for which the Bidder has not included a
description shall be deemed to have been included under other items.
12.4 The Contractor must ensure that its Technical Proposal, duly complying with
the Technical Requirements set down by the Contracting Authority, fulfils and
is adequate to the purpose of the Project.
12.5 The Bidder must, when drawing up the Price Proposal, bear in mind variations
in currency which may occur due to Goods, Services or Works either locally
contracted or contracted from third countries and having an effect on the
Contract costs, that they do so at the risk of the Bidder.
12.6 The prices of the Price Proposal must remain fixed during execution of the
Contract and may not vary on any grounds. Any Bid filed with adjustable
prices shall be deemed not to correspond to the Bid request and shall,
therefore, be refused.
12.7 The Bidders must file a breakdown of the Price Proposal in such a manner and
providing such details as required in Form 8 Price Lists (SECTION 4 of these
Bidding Documents).
12.8 Prices quoted by the Bidders shall correspond to 100% (one hundred per
cent) of the items specified in SECTION 5, Technical Requirements. All items
as per SECTION 5, Technical Requirements, shall be awarded in a single
Contract.
12.9 Bidders shall include prices in accordance with the Technical Requirements
specified under SECTION 5, Technical Requirements of these Bidding
Documents.
13. Documents Comprising the Bid
13.1 The Bid comprises the following documents:
13.1.1 Administrative Documents (to be placed in envelope A):
i)
SECTION 2
Form 1 Bid Form, by means of which the Bidder duly accepts the
terms and conditions set out within these Bidding Documents.
This Form must be signed either by a person with sufficient legal
rights to oblige the Bidder or by a person with sufficient legal
rights to oblige the Joint Venture or Consortium, in the event that
such rights have been granted.
14
ii) Form 2 Bidder Information, together with documents as
evidence of Bidder eligibility pursuant to Clause 14.1 of these
Instructions to Bidders.
iii) Form 3 Economical and Financial Capacity, together with
documents as evidence of technical, economic and financial
capacity pursuant to Clause 14.2.1 of these Instructions to
Bidders.
iv) Bank references from at least two (2) first class financial entities
with whom the Bidder operates pursuant to Clause 14.2.2 of these
Instructions to Bidders.
v) The ISO 9001 Certificate pursuant to Clause 14.2.3 of these
Instructions to Bidders.
vi) Bid Security, pursuant to Clause 17 of these Instructions to
Bidders and as required in Form 9 Bid Security (SECTION 4 of
these Bidding Documents).
vii) The compact disk which is un-editable.
SECTION 2
15
vi)Any other documents as specified under SECTION 5, Technical
Requirements of these Bidding Documents.
13.1.3 Documents regarding the Price Proposal (to be placed in envelope C).
i)
Form 8 Price Lists a Price Proposal for the Project subject of the
Bidding Process, to be submitted as stipulated within these
Bidding Documents. This form must be signed by the person with
sufficient legal power to oblige the Bidder or the person with
sufficient power to oblige the Joint Venture or Consortium, in the
event that such power have been granted.
SECTION 2
16
14.1.3 Original or duly authorized copy of the power of attorney authorizing
the signatory of the Bid to sign the Form 1 Bid Form and all
submitted documents.
14.1.4 Documents evidencing that the Bidder has properly fulfilled the due
and payable obligations relating to taxes and Social Security
obligations as required by Polish laws. For these purposes, Bidders
shall submit certifications issued by their national State Taxs and
Social Securitys entities, not before 6 (six) months before the date of
publication of this Bidding Documents.
14.1.5 A solemn declaration signed by an authorized representative of the
Bidder stating that no enforced settlement, bankruptcy or liquidation
proceedings have been initiated against the Bidder by virtue of a
court decision or some other enforceable decision including also that
the Bidder is not under supervision of the court, having the business
activities suspended, and/or executive directors acting for and on
behalf of companies are not serving criminal sanction.
14.1.6 A solemn declaration evidencing that the Bidder is not under a
declaration of ineligibility to contract in accordance with the Polish
Law on Public Procurement and that they had not been punished with
the prohibition of being awarded a project.
14.2 The Bidder shall submit the following documents as evidence of, technical,
economic and financial eligibility, as stipulated under Clause 5 of these
Instructions to Bidders, together with the Bid.
14.2.1 Economic and Financial Capacity according to the Form 3 Economic
and Financial Capacity, together with Certified Financial Statements,
including Balance Sheets, Statements of Loss and Profit, Annual
Reports, Statements of Changes in Equity, Cash-Flow Statements
(this document shall not be submitted if the Bidder is able to file his
annual accounts using the abbreviated model or the model for small
and medium enterprises under the regulation in force) and auditors
reports for the last 3 (three) fiscal years. Such documents shall have
been audited and registered in English. In case the Bidder has no
obligation to audit its accounts, he shall provide information of the
legal grounds on the basis of which he benefits from this exemption.
14.2.2 Bank references from at least two (2) first class financial entities with
whom the Bidder operates. These references must state the number
of years of the Bidders relationship with the Bank.
14.2.3 The ISO 9001 Certificate in force. If the Bidder is not the equipment
manufacturer, then the Bidder must also submit the Manufacturer
ISO 9001 Certificate for the Key Equipment pursuant to the
provisions set down under the Technical Requirements, SECTION 5 of
these Bidding Documents.
14.3 Bids submitted by a Joint Venture or Consortium shall comply with the
following requirements:
SECTION 2
17
14.3.1 The Bid shall include all the documents included in Clauses 14.1,
14.2.1 and 14.2.2 above individually, for each member of the Joint
Venture or Consortium as well as all further documents to be
submitted on an individual basis.
14.3.2 Any members comprising at least 50% (fifty per cent) of the Joint
Venture or Consortium or bearing the role of leader must provide
evidence of holding the ISO 9001 Certificate in force. In any case the
Joint Venture or Consortium must also submit the Manufacturer ISO
9001 Certificate for the Key Equipment pursuant to the provisions set
down under the Technical Requirements, SECTION 5 of these Bidding
Documents.
14.3.3 One of the members shall be appointed as main partner responsible
for the Contract and the appointment confirmed by submission of
powers of representation (i.e. original or authenticated copy) duly
signed by legally authorised signatories representing each of the
members.
14.3.4 The Bid and the Contract, in the event that formally selected, shall be
signed by all companies forming part of the Joint Venture or
Consortium in such a way and is to create an obligation that is legally
binding on all the partners.
14.3.5 All the partners will be deemed jointly and severally liable with regard
to the Bid and fulfilment of the Contract pursuant to the conditions
set out therein should the Bid be chosen; this must be set down in
writing within the documents referred to in Clause 14.3.6 of these
Instructions to Bidders.
14.3.6 The original or a notarized copy of the Joint Venture or Consortium
agreement signed by all the partners must be submitted together
with the Bid and this must set out the percentage stakeholding in the
Project of each partner together with either the joint liability of all the
partners regarding performance of the Contract, pursuant to the
Contract conditions, or a letter of intent that the Joint Venture or
Consortium will enter into an agreement if selected, duly signed by all
the partners and with a copy of the proposed agreement attached
thereto.
15. Documents Confirming that the Project Meet the Bidding Documents
Technical Requirements.
15.1 In order to establish that the Bid subject of this Bidding Process are in
compliance with the requirements of these Bidding Documents, the Bidders
shall, as part of the Bid, provide documents as evidence that the Project duly
comply with Technical Requirements specified under SECTION 5, Technical
Requirements of these Bidding Documents. The documents provided by the
Bidders shall be, at least, the following:
a. Equipment layout plan
b. Technical Specification of the Cold Storage Rooms for Meat and
Associated Facilities;
c. Performance Schedule;
SECTION 2
18
d. Warranty, Preventive Maintenance and After-sales Service Programme;
e. Training proposal
15.2 The documents provided as evidence may be submitted in the form of printed
literature, drawings or information and shall include a detailed description of
the essential technical and operational characteristics for each particular
Goods, Services and Works included in the Bid showing that the Technical
Requirements do meet the compulsory Technical Requirements.
15.3 Bidders shall submit documents as evidence that the Bid meets the
established Technical Requirements and that it is suitable for the intended
purposes as defined within these Bidding Documents.
16. Period of Validity of Bids
16.1 Bids shall remain valid for the period of 120 (one hundred and twenty) days
after the date of the Deadline for submission of Bids. A Bid valid for a shorter
period shall be rejected by the Contracting Authority as non-responsive.
16.2 Under exceptional circumstances and prior to the date on which the initial
planned validity period expires, the Contracting Authority may request an
extension of the aforesaid time period from the Bidders in writing. Bidders
accepting that request will not be authorised to amend their Bid. If a Bid
Security has been required pursuant to Clause 17 of these Instructions to
Bidders, then this must also be extended by the corresponding time period.
Bidders may refuse that request without the Bid Security being rendered ineffective. Nevertheless, the Contracting Authority will exclude the Bid from
the Bidding Process, once the Bid Validity Period has expired.
17. Bid Security
17.1 The Bidders shall submit a Bid Security amounting to 1% of bid price as part
of their Bid, to be issued in the same currency as the Bid (USD).
17.2 The Bid Security must:
a. be in the form of a bank guarantee issued by a banking institution;
b. be issued by an institution of renowned international repute chosen by the
Bidder;
c.
d. be set down in abstract terms and payable at first call, upon written
request from the Contracting Authority in the event that any of the
scenarios set down under Clause 17.5 of these Instructions to Bidders
occurs;
e. be submitted as an original document; no copies will be accepted;
f.
SECTION 2
remain valid for a period of 30 (thirty) days beyond the period of validity
of the Bids, as extended, if applicable, in accordance with Clause 16
Period of Validity of Bids of these Instructions to Bidders;
19
g. if the particular Bid is the successful Bid, then the validity of the Bid
Security must be extended and will remain in force from the date of
issuance until the earliest of the following:
17.3 Any Bids without an attached Bid Security duly responding to the
requirements set down in the Instructions to Bidders, shall not be considered
by the Contracting Authority.
17.4 Bid Security from unsuccessful Bidders will be returned within a maximum
time period of 30 (thirty) days from the Notice of Award.
17.5 The Bid Security will be executed if:
a. the Bidder withdraws its Bid during the Bid validity period specified by the
Bidder on the Bid Form included in SECTION 4 Bid Forms of these
Bidding Documents; or
b. the awarded Bidder:
SECTION 2
20
17.6 The Bid Security from a Joint Venture or Consortium must be issued in the
name of the Joint Venture or Consortium that submits the Bid. In the event
that the Joint Venture or Consortium concerned has not been legally
constituted at the time the Bid submitted, then the Bid Security must be
drawn out jointly and severally in the name of all future partners or members
of the Joint Venture or Consortium.
B.
SUBMISSION OF BIDS
SECTION 2
21
c. the specific identity reference for this Bidding Process as set out in these
Bidding Documents; and
d. the warning DO NOT OPEN
OPENING BIDS.
If the external envelope does not have a security seal and is not marked as
established under this Clause, the Contracting Authority may not be deemed
liable for the loss or premature opening of the Bid.
19.7 The internal envelopes shall:
a. refer, as appropriate, Envelope A: Administrative Documents; Envelope
B: Technical Proposal; Envelope C: Price Proposal.
b. Contain the original documents, clearly marked ORIGINAL and the
copies of the aforesaid original documents marked COPY.
c. Incorporate the specific Bidding Process identification as set out in these
Bidding Documents.
SECTION 2
22
20. Deadline for Submission of Bids
20.1 The Bidders shall submit their Bids at the address specified under Clause 19.6
of these Instructions to Bidders, prior to the date set out in the Invitation for
Bid and Clause 3 (Bidding Process Schedule) of these Instructions to Bidders.
20.2 The Contracting Authority may extend the deadline for the submission of Bids
by amending the Bidding Documents, pursuant to Clause 8 of these
Instructions to Bidders. In that event, all rights and obligations of the
Contracting Authority and Bidders will be extended for an identical period of
time.
21. Late Bids
21.1 The Contracting Authority shall not consider any Bids that are received after
the deadline for submission of Bids, in accordance with Clause 20 (Deadline
for Submission of Bids) of these Instructions to Bidders. All Bids delivered to
the Contracting Authority after the deadline for submission of Bids will be
declared late, rejected, and returned unopened to the Bidder.
22. Modification of or withdrawal of Bids
22.1 Bidders may modify or withdraw their Bids providing written notice prior to
the deadline for submission of Bids in accordance with Clause 20 of these
Instructions to Bidders. No further changes may be made to the Bids after
this deadline. Bids may be withdrawn unconditionally and the party
withdrawing the Bid may not thereafter participate in the Bidding Process.
22.2 No Bid may be withdrawn during the time period between the final deadline
for submission of Bids, as referred to in Clause 20 of these Instructions to
Bidders, and expiry of the time period for validity of these Bids. In the event
that any Bid is withdrawn during the aforesaid period then the Bid Security
will be executed.
C.
SECTION 2
23
23.3 The names of Bidders, prices of Bids, the existence of the required Bid
Security and any other details the Contracting Authority may deem
appropriate to communicate shall be announced at the Bid opening session
and shall be recorded by the Opening Committee in the minutes of the Bid
opening session and signed by the representatives of the Opening Committee,
the representatives of the Bidders and the representatives of any relevant
bodies present.
23.4 A representative of the Government of the Republic of Poland or its duly
authorized representative in Nairobi shall be invited to attend the Bid Opening
Session.
23.5 The Contracting Authority shall send one (1) hard copy and one (1) electronic
copy of the documents included in the envelopes, Administrative Documents,
Technical Proposal and Price Proposal to the Polish Government Nairobi or its
duly Authorised representative.
24. Confidentiality
24.1 The Evaluation Committee will not disclose any information regarding
checking, explanations, rulings or comparison of these Bids, nor make any
recommendations regarding awarding the Contract to any party not officially
taking part in the proceedings up until the name of the successful Bidder is
advised.
24.2 Any attempt on the part of a Bidder to influence the Evaluation Committee or
the Contracting Authority during the review, clarification, evaluation or
comparison of these Bids, to obtain information regarding how the procedure
is progressing or to affect the decision of the Contracting Authority regarding
awarding the Contract shall imply immediate rejection of the Bid concerned.
25. Clarification of Bids
25.1 The Contracting Authority may, at its own discretion, ask a Bidder to correct
errors that can be remedied, or to clarify certain aspects of the Bid whenever
this is necessary in order to check the Bids.
25.2 Such request for clarification and/or remedy and the corresponding replies
must be set down in writing. They may in no circumstances alter or try to
change the price or content of the Bid, except to correct arithmetical errors
noticed by the Evaluation Committee when analysing the Bids pursuant to
Clause 28 (Nonconformities, errors and omissions of these Instructions to
Bidders.
25.3 The Bidder shall respond to the Contracting Authority within the time period
established by the latter in the request for clarification or remedy and if it fails
to do so the Bid will be rejected.
25.4 All clarifications/remedies are deemed to form an integral part of the Bids
submitted.
26. Responsiveness of Bids
26.1 Bids may be rejected, subjected to conditions, if incomplete, illegible, and
unclear, if they contain additional information not required or any other
irregularities.
SECTION 2
24
26.2 Prior to commencing the detailed analysis and evaluation of these Bids, the
Tender Processing Committee shall ascertain whether each of the Bids:
a. Has duly been signed by the person with legal powers to oblige the Bidder;
b. contains the required Bid Security;
c. contains the Price Proposal;
d. meets eligibility criteria as well as minimum technical and financial
solvency conditions;
e. is substantially prepared according to the Bidding Documents.
26.3 Bids shall be deemed to be substantially responsive whenever they have been
substantially prepared according to the requirements set out in the Bidding
Documents without any material deviation or reservation. The following are
considered material deviations and reservations:
a. Any that in some manner affect the scope, quality or execution of the
Technical Requirements, or
b. Which essentially limit the rights of the Contracting Authority or the
Bidder contractual obligations and contradict the Bidding Documents, or
c. Whenever correction might affect the competitive position of other
Bidders that presented substantially responsive Bids.
27. Evaluation of Bids
27.1 The Evaluation Committee shall only evaluate and compare Bids deemed
substantially responsive pursuant to Clause 26 Responsiveness of Bids of
these Instructions to Bidders.
27.2 In order to evaluate and compare the Bids, the Evaluation Committee shall
apply the evaluation criteria as defined and considered under SECTION 3 of
the Bidding Documents, Evaluation Criteria, in order to ascertain which the
most favourable Bid is. No other criteria or methodology shall be permitted.
27.3 The Polish Embassy in Nairobi or its duly authorized representatives may be
present during the Bid Evaluation Process.
SECTION 2
25
b. If there is an error in the total amount corresponding to adding or
subtracting sub-totals, then the sub-totals will prevail and the total
amount will be corrected;
c. If there is a discrepancy between words and figures, then the amount in
words will prevail unless the amount in words corresponds to an
arithmetical error and in that event the amounts in figures, pursuant to
the aforementioned paragraphs (a) and (b), will prevail.
28.2 In the event of a discrepancy between the tender amount as stated in the bid
form and the corrected tender figure in the grand summary of the bills of
quantities, the amount as stated in the bid form shall prevail.
28.2.1 The error correction factor shall be computed by expressing the
difference between the tender amount and the corrected tender sum
as a percentage to correct the unit rates. If the Bidder does not
accept the correction, then the Bid will be rejected and the Bid
Security executed.
28.2.2 The error correction factor shall be applied to all unit rates (as a
rebate or addition as the case may be) for the purposes of
regularizing the rates
29. Right of the Contracting Authority to accept or reject any Bid
29.1 The Contracting Authority reserves the right to cancel the entire Bidding
Process and to reject all the Bids. The Contracting Authority equally reserves
the right to initiate a new Bidding Process. Cancellation may take place in the
following scenarios:
a. If the Bidding Process is abandoned, i.e., if no Bid has been received or if
none of the Bids received deserves to be selected from the qualitative or
economic point of view;
b. whenever technical or price project elements need to be fundamentally
changed;
c. whenever exceptional circumstances or circumstances of force majeure
render it impossible a normal execution of the Project;
d. Whenever serious irregularities have occurred in procedure preventing
the process from being carried out under fair competitive conditions.
SECTION 2
26
29.2 The decision not to accept any of the Bids, together with the corresponding
reasons, must be notified immediately by the Contracting Authority to all
Bidders and to the Representative of the Polish Government in Nairobi.
29.3 If the Bidding Process is cancelled before any external Bidder envelopes has
been opened, then all unopened envelopes still security sealed will be
returned to the Bidders.
29.4 The Contracting Authority shall not in any event be obliged to pay damages or
interest, whatever the nature thereof and however related to cancellation of a
Bidding Process.
D.
CONTRACT AWARD
SECTION 2
27
31.2 In the event that the successful Bidder fails to sign and return the Contract
Agreement providing the required bank guarantees within a time period of 30
(thirty) days after receipt of the Notice of Award, then the Contracting
Authority may deem the award carried out null without prejudice to any legal
action that the Contracting Authority may be entitled to initiate in order to
claim for damages caused by non-compliance in respect of such failure and
the successful Bidder may not make any claim against the Contracting
Authority.
31.3 If the successful Bidder fails to sign the Contract, this shall be deemed
sufficient cause to cancel the award of the Contract and to execute the Bid
Security. The Contracting Authority may, in that event, award the Contract to
the Bidder with the second best evaluated Bid.
31.4 In the event that any amendments or clarifications have been made to the
Contract Agreement and to the General Conditions of Contract, the
Contracting Authority shall submit to the Council of Ministers of Poland or
their authorized body through the Polish Embassy in Nairobi the wording for
approval prior to the signature.
32. Performance Security
32.1 Upon signature of the Polish Governments tied aid credit, the Contracting
Authority will notify the Contractor the obligation of furnishing the
Performance Security that will replace the Bid Security. Within 30 (thirty)
days of the receipt of this notification from the Contracting Authority, the
Contractor shall furnish the Performance Security in accordance with the
Article 17 of the General Conditions of Contract, using for that purpose the
Performance Security Form included in Annex I, SECTION 6 Contract of
these Bidding Documents.
32.2 In the event that the successful Bidder fails to submit the aforesaid
Performance Security, this will be deemed sufficient grounds to cancel the
award of the Contract and to execute the Bid Security.
33. Ethics Clauses
33.1 All attempts on the part of the Bidder to obtain confidential information, to
enter into illegal agreements with competitors or influence the Evaluation
Committee or the Contracting Authority at any time during the procedure for
review, clarification, evaluation and comparison of the Bids will lead to the
Bidder or Bid concerned being rejected and the possibility of administrative
sanctions being applied.
33.2 The successful Bidder (hereinafter referred to as the Contractor) or its
personnel, or any other Company with which the Contractor is associated or
has ties, may not carry out any other work or supply any other works that
may arise in relation to the Project, without the prior authorisation in writing
of the Contracting Authority. The aforesaid prohibition also applies, as
appropriate, to other projects in which the Contractor may, due to the nature
of Contract, find itself in a conflict of interest scenario.
SECTION 2
28
33.3 At the time of submitting the Bid, the Bidder must declare that no potential
conflict of interest exists and that the latter has no equivalent type of
relationship in that regard with other Bidders or with other parties involved in
the Project. If such a situation were to occur during the time period for
performance of the Contract, the Contractor is under an obligation to inform
the Contracting Authority without delay.
33.4 The Contractor must act impartially at all times, with good faith, fairness and
maximum diligence also serve as legal adviser pursuant to the ethics code for
the particular profession. The Contractor must refrain from making any public
declarations regarding either the Project or services without prior approval of
the Contracting Authority. The Contracting Authority may not be obliged in
any way without its prior consent in writing.
33.5 The Contractor and its personnel must respect human rights throughout
performance of the Contract.
33.6 The Contractor may not accept any payment in relation to the Contract and
not provided for within the Contract. The Contractor and its personnel must
refrain from carrying on any business activity or from receiving any bonus
that comes into conflict with its obligations with regard to the Contracting
Authority.
33.7 The Contractor and its personnel will remain subject to professional secrecy
throughout the Contract term and beyond termination. All reports and
documents received or drawn up by the Contractor within the framework of
performance of the Contract are deemed confidential.
33.8 Use by the contracting parties of all reports and documents drawn up,
received or handed over throughout the period of operational performance of
Contract is governed by the conditions set out therein.
33.9 The Contractor must not enter into any relationship which may compromise
its independence or that of its personnel. In the event that the Contractor
ceases to be independent, then the Contracting Authority may terminate the
Contract without any requirement to provide notice in view of any harm they
may have incurred as the result of such loss of independence. The Contractor
shall furthermore not be entitled to claim compensation of any kind.
33.10 The Government of the Republic of Poland reserves the right to suspend or
cancel the financing for this Project in the event that any fraudulent practices
or corruption are found to have occurred, if the Ethics Clauses established
under these Instructions to Bidders are not adhered to or if any other
irregularity occurs in the Bidding Process that contravenes the principles of
competition and transparency, in case of any objection of OECD as to
accordance of the projects or individual contracts financed under this
Agreement with the provisions of arrangement on officially supported Export
Credits, the contract will not be financed under the Agreement irrespective of
the fact that individual contracts within the projects have been accepted by
both contracting parties according to Article 3 of the agreement on the
extended tied aid credit
SECTION 2
29
33.11 If the award or operational performance of the Contract gives rise to any
unusual commercial costs, the corresponding Bid will be rejected or the
Contract terminated. Unusual commercial costs are deemed to refer to any
commission not referred to within the Contract and not arising from a
Contract set down in a valid form and referring to this main Contract; any
commission not comprising consideration for a legitimate and effectively
provided service; any commission paid to a tax haven and any commission
paid to a beneficiary that is not clearly identified or to a company that
appears to be a front company.
33.12 The Contractor undertakes to submit all documents as evidence of compliance
with these conditions for performance of the Contract to the Polish
government or to such persons as the latter may designate and at the request
of the latter. The Polish government, or its representative, may carry out all
document or site checks, among other, at the company headquarters and at
the Site, as it deems necessary to gather evidence to corroborate any
suspicion that unusual commercial costs have occurred.
SECTION 2
30
SECTION 3
Evaluation and Qualification Criteria
Table of Contents
1. Introduction.. ...........................................................................................31
2. Evaluation Criteria ...........................................................................................31
3. Evaluation Table.. ............................................................................................36
SECTION 3
31
1.
Introduction
This SECTION complements the Instructions to Bidders. It contains the criteria that
the Contracting Authority shall use to evaluate a Bid and determine whether a
Bidder has the required qualifications.
Only Bids considered to be substantially responsive, in accordance with Instructions
to Bidders Clause 26, shall be evaluated. The evaluation shall take into account not
only the Bid Price, but also the Technical Proposal of the Bid, and the capability to
perform the Contract.
The purposes of the evaluation process is to identify the Bidder most likely to enable
the Contracting Authority to achieve its objectives of having the Project completed
on time, meets the published criteria and are within the budget available.
Before the evaluation process, the Evaluation Committee will check the fulfilment
and justification of all administrative requirements and documents comprising the
Bid according to Instruction to Bidders Clause 13.
2.
Evaluation Criteria
The Evaluation Committee shall use the scoring system described hereunder,
resulting in an Evaluated Bid Score.
The maximum Evaluated Bid Score is 1,000 (one thousand) Points, to be distributed
according to the following criteria:
1. Technical Proposal evaluation (TP) shall have a maximum score of
600 (six hundred) points.
2. Price Proposal (PP) shall have a maximum score of 400 (four
hundred) points.
The calculation to determine the best evaluated Bid shall be conducted by the
following formula:
Evaluated Bid score = TP +PP
Where,
TP shall be the score for Technical Proposal
PP shall be the score for Price Proposal
The purpose of Bid Evaluation is to compare Bids, which conform to the Project and
are substantially responsive to the Bidding Documents, on the basis of their
evaluated cost. Among the Bids which conform to the Project, the Bid with the
highest evaluated score, not necessarily the lowest submitted price shall be selected
for award. The criteria to be met by the Bidders are set out here below.
2.1. Technical Proposal (TP) Maximum 600 (six hundred ) points
The evaluation of the Technical Proposal shall be calculated based on following
criteria. All Bids with a Technical Proposal score lower than 400 (four hundred)
points shall be rejected and not considered for further evaluation.
SECTION 3
32
2.1.1. Bidders Experience. Maximum 100 (one hundred) points:
The Bidder shall demonstrate his total experience in projects as
principal contractor, which shall be evaluated according to the following
criteria:
Company experience
Maximum
score
General experience
From 1 to 3 completed projects that exceed a value of 100,000 USD
30
60
60
Specific experience
Experience in African countries.
20
20
40
General experience:
Each Bidder shall be assessed on his general experience in projects
executed by itself in the last 10 (ten) years by providing evidence of
executed projects with a value that exceed 2m (two million) USD.
Specific experience:
Each Bidder shall be assessed on his specific experience in executed
projects carried out in the region (African countries) and/or of similar
nature of the Project. Projects shall be considered to be of similar
nature if they are related to Cold Storage Rooms for Meat and
Associated Facilities, including design, supply and installation of the
equipment as a whole.
A maximum of 10 (ten) references, not older than 10 (ten) years, shall
be submitted by each Bidder in this item. Only references above
100,000 (one hundred thousand US dollars) shall be considered.
Each project reference shall be assessed for compliance with the two
sub-criteria and the maximum score that can be allocated to each
experience in each of the sub-criteria is 6 (six) points.
SECTION 3
33
In the case the Bidder is a Joint Venture or a Consortium, the
evaluation of the Bidders experience shall consider a maximum of 10
(ten) references submitted by all the members of the association.
When assessing the project references provided by each member, the
aspects to be considered shall be those that relate to the role that the
company undertakes in the association.
Bidders shall submit a Bidders Experience Form (SECTION 4, Bidding
Forms) per executed Contract. In addition, Bidders shall attach to each
of these Bidders Experience Forms, references from the End Users
(beneficiaries), such as a certificate, or a letter signed by the
responsible person stating that the project was successfully
implemented by the Bidder. The Bidders shall submit the documents
translated into English.
If the Bidder has participated in a Joint Venture or a Consortium, he
must indicate the percentage of his participation in order to calculate
the corresponding proportional value of the Projects.
2.1.2. Technical Requirements. Maximum 500 (five hundred) points.
Technical Proposals will be evaluated in accordance to the fulfilment of
the Technical Requirements according to SECTION 5 of the Bidding
Documents.
2.1.2.1
SECTION 3
34
1. Documentary evidence that the equipment offered by
the Bidder conforms to the technical specifications
and standards specified in SECTION 5, Technical
Requirements. The documentary evidence may be in
the form of literature, catalogues, drawings or data.
The catalogues will be in English.
2. Manufacturer / Official Distributor Authorization for
the Key Equipment included in SECTION 4 Bid
Forms in accordance with Instructions to Bidders
Clause 13.1.2.
3. ISO 9001 Certificate in accordance with Instructions
to Bidders Clause 5.1.1 and 14.2.3.
Evaluation of the technical specifications of the Key Equipment shall be made according
to the following chart:
Technical specifications
Score
225
200
175
150
2.1.2.3
Rejected
SECTION 3
35
2.1.2.4
Technical
Warranty,
Preventive
Maintenance
Programme and After-sales Service. Maximum 25
(twenty five) points.
Warranty, Preventive Maintenance and After-sales Service
Programme shall be evaluated according to the fulfilment of
the requirements specified in the Technical Requirements
(SECTION 5, Bidding Documents) and establishing a criterion
for comparing Bids. The Bids to be submitted shall include all
adequate documentation in order to be able to evaluate the
fulfilment of said requirements.
2.1.2.5
75
(seventy
five)
Where:
SECTION 3
36
3.
Evaluation Table
MAXIMUM
BIDDER 1
BIDDER 2
BIDDER N
CONCEPTS
POINTS
Bidders Name
Bidders Name
Bidders
Name
Bidders
Name
TECHNICAL PROPOSAL
EVALUATION
600
Bidder's Experience
100
General Experience
60
Specific Experience
40
Technical Requirements
500
Design
150
225
Performance Schedule
25
25
Training Programme
75
400
EVALUATED
SECTION 3
37
TOTAL SCORE
1,000
OFFERED PRICE
If there are two (2) or more Bids that have obtained the same Total Score, the Contracting Authority will choose the Bidder who
has the highest score obtained in the Technical Proposal Evaluation.
SECTION 3
38
ECTION 4
Bid Forms
INDEX
Form 1.
Form 4.
Form 5.
Form 6.
Form 9.
SECTION 4
39
Form 1.
Bid Form
[Include in envelope A]
<The Bidder must complete this form in accordance with the instructions given between square brackets [ ]. No alterations to
this form or replacements will be accepted>
Project: Supply, Installation and Commissioning of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
The persons signing below declare that:
a.
We have reviewed and do accept the entire content of the Bidding Documents [state reference] of [state date] and do
accept the provisions and amendments thereto in their entirety, without reservations or limitation;
b.
We propose to execute the following scope of the project " Development of Cold Storage Rooms for Meat Products, pursuant to
the Bidding Documents:
Works including:
Supply, delivery, installation, testing and commissioning of Meat Products Cold Storage facilities and Associated
accessories in varied locations in Kenya.
Services including:
a. Design including all documents necessary to define, manufacture, delivery, installation, testing, commissioning,
handing over and maintaining the Project and all the associated accessories.
b. All supplementary services necessary to supply the goods, including delivery and transport to Project Site,
inspection prior to delivery, installation, commissioning, start up, preventive maintenance, technical guarantee for
12 (twelve) months, after-sales service and training.
SECTION 4
40
c.
The total price of our Bid is: [state the total Bid price in words and in figures];
d.
The attached Bid Security no. ___________ [insert the number], issued by _________ [insert the Bank] is an original, valid and
legal Bid Security;
e.
This Bid will be deemed valid and binding for a period of one hundred and fifty (150 no.) days calculated from the Bid submission
deadline. This Bid obliges us and may be accepted at any time before expiry of the aforesaid period;
f.
If our Bid is awarded, we undertake to obtain a Performance Security pursuant to Clause 32 of the Instructions to Bidders
(SECTION 2 of these Bidding Documents) and Article 17 of General Conditions of the Contract, (SECTION 6 of the Bidding
Documents).
g.
Our Company duly complies with the eligibility requirements established under Clause 4 of the Instructions to Bidders (SECTION 2
of the Bidding Documents).
h.
We have nationality from Poland, and the Goods, Services and Works include in our Proposal fulfil the origin of the Goods and
Services requirements established in the Bidding Documents.
i.
We declare that we are neither involved in any prohibitions established under OECD conditions, nor have been sanctioned by
prohibition from being favourably awarded a project or operation financed and charged to the Polish Government.
j.
We declare that we comply with the provisions of international agreements to which Poland is a signatory regarding commercial
liability, labour rights and gender equality and particularly agreements regarding the fight against corruption and environmental
concerns of the Credit for Export Group of the Organisation for Economic Co-operation and Development (OECD). Compliance
with the aforesaid agreement also implies not having contributed to any breach of human rights, no involvement in corruption
practices and no infringement of workers rights, childhood rights or any other ethics which may contravene international
agreements ratified by the Government of the Republic of Poland.
k.
We undertake to respect the ethics clauses established under Clause 33 of the Instructions to Bidders (SECTION 2 of these
Bidding Documents) and we particularly declare that we are not involved in any possible conflict of interest scenarios nor any
equivalent type of relationship with other Bidders or parties having an interest in the Bidding Process at the time this application
is submitted.
SECTION 4
41
l.
We understand that this Bid, together with the appropriate acceptance in writing from the Contracting Authority by means of a
Notice of Award, comprises a contractual obligation between us, until replaced upon signing the firm and final Contract. The
Successful Bidder must, for that purpose, complete the Contract Agreement pursuant to instructions set out therein and no
changes or replacements will be permitted either to the Contract Agreement and the General Conditions of the Contract (SECTION
6 of the Bidding Documents).
m.
We are responsible for the veracity of documents and information submitted together with our Bid.
n.
We understand that you are not under any obligation to accept the best Bid as evaluated, nor any other Bid you may receive,
pursuant to the terms established under Clause 29 of the Instructions to Bidders (SECTION 2 of the Bidding Documents).
Name: <state the full name of the person signing the Bid Form>
Acting as <state the legal status of the person signing the Bid Form>
Duly authorised to sign the Bid for and on behalf of: <state the full name of the Bidder>
Date ___of month ____ of year _________ [state date of signature]
SECTION 4
42
Form 2.
<The Bidder must complete this form in accordance with the instructions given between square brackets [ ]. No alterations to this
form or replacements will be accepted >
Project: Supply, Installation and Commissioning of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
Bidder Company Name:
Country of nationality:
Registered business address of the Bidder:
SECTION 4
43
Name: [state the full name of the person signing the Bid Form]
Acting as [state the legal status of the person signing the Bid Form]
Duly authorised to sign the Bid for and on behalf of: [state the full name of the Bidder]
Date ___ of month ____ of year _____ [state date of signature]
SECTION 4
44
Form 3.
<The Bidder must complete this form in accordance with the instructions given between square brackets [ ]. No alterations to this
form or replacements will be accepted >
Project: Development of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
The Bidder must complete the following financial data table on the basis of the provisions of the Certified Financial Statements,
including Balance Sheets, Statements of Loss and Profit, Annual Reports, Statements of Changes in Equity, Cash-Flow Statements (this
document shall not be submitted if the Bidder is able to file its annual accounts using the abbreviated model or the model for small and
medium enterprises under the regulation in force) and auditors reports for the last 3 (three) fiscal years. Such documents shall be
audited and registered before the relevant public registry and translated into English. In case the Bidder has no obligation to audit its
accounts, he shall provide information of the legal grounds on the basis of which he benefits from this exemption.
Figures given in all columns must be set out on the same basis in such a way as to permit direct year-on-year comparison (or, if
submitted on a different basis, the change must be explained in a footnote beneath the table). Any clarification or explanation
considered necessary must also be included.
If this Bid is submitted by a Joint Venture or Consortium, then a financial data table must be submitted corresponding to each of the
members of the Joint Venture or Consortium as well as a table for the Joint Venture or Consortium as a whole, which must be as
calculated from the data submitted by the members, pursuant to Clause 5 of the Instructions to Bidders (SECTION 2 of the Bidding
Documents).
Financial data
Prepenultimate
financial
year
USD
SECTION 4
Penultimate
financial
year
USD
Last
financial
year
USD
Average
USD
45
Financial data
Prepenultimate
financial
year
USD
1. Equity
2. Total assets
3. Current assets
4. Total liabilities
5. Current liabilities
6. Turnover
7. Ordinary Profits
8. Profits before taxes
9. Profits after taxes
10. Solvency ratio (= Total
Equity1 / Total
Liabilities) 10%
11. Current ratio (=Total
current assets / Total
SECTION 4
Penultimate
financial
year
USD
Last
financial
year
USD
Average
USD
46
Financial data
Prepenultimate
financial
year
USD
Penultimate
financial
year
USD
Last
financial
year
USD
Average
USD
current Liabilities) 1)
The Bidder must attach copies of the documents referred to in Clause 14.2.1of the Instructions to Bidders (SECTION 2 of the Bidding
Documents) to this Form.
Name: [state the full name of the person signing the Bid Form]
Acting as [state the legal status of the person signing the Bid Form]
Duly authorised to sign the Bid for and on behalf of: [state the full name of the Bidder]
SECTION 4
47
Form 4.
<The Bidder must complete this form in accordance with the instructions given between square brackets [ ]. No alterations to this
form or replacements will be accepted >
Project: Supply, Installation and Commissioning of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
Page _______ of_______
Number of similar contracts:
____ of ___ required.
Information
Contract identity
Locality (City/Country)
Award Date
Termination Date
Role within contract
Total contract amount
SECTION 4
Contractor
Sub-Contractor
Amount:
Amount:
__________________
______________ EUR(1)
__________%
Total Contract
Value:
Bidders Amount:
48
Information
_________USD
_______ USD
_________________________________________
Address:
_________________________________________
Tel/Fax Nos.:
_________________________________________
Email:
_________________________________________
The Bidder must attach certificates of satisfactory execution issued by the corresponding Beneficiaries together with the Bid, in the
original language and attaching a translation to the Bidding Process language.
Name: [state the full name of the person signing the Bid Form]
Acting as [state the legal status of the person signing the Bid Form]
Duly authorised to sign the Bid for and on behalf of: [state the full name of the Bidder]
Date ___of month ____ of year __________ [state date of signature]
SECTION 4
49
Form 5.
[The Bidder must attach the proposed Programme for Contract execution]
Project: Supply, Installation and Commissioning of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
The Programme must comprise, at least:
Schedule in the form of a Bar Chart to include:
The order in which the Bidder proposes to carry out the Project;
A general description of the method the Bidder proposes to use for execution of the Project;
Name: [state the full name of the person signing the Bid Form]
Acting as [state the legal status of the person signing the Bid Form]
Duly authorised to sign the Bid for and on behalf of: [state the full name of the Bidder]
Date __of month ______ of year _________ [state date of signature]
SECTION 4
50
Form 6.
<The Bidder must complete this form in accordance with the instructions given between square brackets [ ]. No alterations to this
form or replacements will be accepted >
Project: Supply, Installation and Commissioning of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
6.1 Personnel assigned to execute the Project
Name of Bidder:
The Bidder must provide the following data set out below with regard to personnel assigned to execute de project.
1.
Title position:
Name of candidate:
Title position:
2.
Name of candidate:
Title position:
3.
Name of candidate:
SECTION 4
51
Title position:
4.
Name of candidate:
Name: [state the full name of the person signing the Bid Form]
Acting as [state the legal status of the person signing the Bid Form]
Duly authorised to sign the Bid for and on behalf of: [state the full name of the Bidder]
Date __of month ______ of year _________ [state date of signature]
SECTION 4
52
6.2
(One form for each person. Candidate name to be at the top of each page if more than one page. CVs should not be longer than five
(5) pages)
Page _______ of_______
1.Name of Bidder
2. Title position
3.Name of candidate
4.Candidate Information
Date of birth
Academic background
Languages and
level (VG, G, A)
Experience
Specialist fields
5.Present Employment
Name of Employer
Address of Employer
Summarize professional experience over the last 15 (fifteen) years in reverse chronological
order. Indicate particular technical and managerial experience relevant to the Project
From
SECTION 4
To
53
Name: [state the full name of the person signing the Bid Form]
Acting as [state the legal status of the person signing the Bid Form]
Duly authorised to sign the Bid for and on behalf of: [state the full name of the Bidder]
Date _____ of month _____of year ________ [state date of signature]
SECTION 4
54
Form 7.
[The Bidder must ask the Manufacturer/Official Distributor to complete this form in accordance with the instructions given. Letters of
authorisation should be set out on Manufacturer/Official Distributor headed note paper and signed by the person duly authorised to
sign documents in such a manner as to oblige the Manufacturer/Official Distributor.]
Project: Supply, Installation Testing and Commissioning of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
WHEREAS
We [full name of Manufacturer/Official Distributor], who are Manufacturer/Official Distributor of [state type of manufactured
or distributed goods], with facilities located at [state full address] hereby authorise [state Bidder name] to submit a Bid for the
sole purpose of supplying the following Goods [name and brief description of goods], for the Project Installation, Testing and
Commissioning of Cold Storage for Meat and Associated Facilities.
We hereby extend our full warranty, with respect to the Goods offered by the above firm.
We declare to be in possession of sufficient normalized spare parts and consumables for the offered Goods, necessary for the proper
and continuing functioning of the Goods for a period of time no lower than 5 (five) years.
We declare that our representative in Kenya, [insert complete name of the representative in the Republic of Kenya] is duly authorized
to act on our behalf with respect to any or all matters relating to the Goods represented, to warranty the proper and continue
functioning of the Goods.
[Choose one of the following options]
SECTION 4
55
We declare that the Manufacturer of the equipment we distribute is in possession of the ISO 9001 Certificate [in case Official
Distributor].
SECTION 4
56
Form 8.
<The Bidder must complete this form in accordance with the instructions given between square brackets [ ]. No alterations to this
form or replacements will be accepted >
Project: Supply, Installation and Commissioning of Cold Storage Rooms for Meat and Associated Facilities
Date: [Insert date (day, month and year) of submission of Bid]
No: [Insert number of Bidding Process]
To: [Insert full name and address of the Contracting Authority]
A.1
PRICE FOR IMPORTED GOODS (Cold Storage Rooms for Meat and Associated Facilities, Spare Parts, Consumables
and Accessories (POLISH /OR THIRD COUNTRY ORIGIN)
A.1.1 Price for Cold Storage Rooms for Meat and Associated Facilities
1
Item
No.
2
Description
3
Quantity
4
Supplier
5
Manufacturer
TOTAL
SECTION 4
Model
Country of
origin*
Unit price**
(USD)
Total Price**
(col. 3 x col. 8)
(USD)
57
A.1.2 Price for Spare Parts, Consumables and Special Tools
Item No.
of the
spare
part/consu
mable
Item No. of
the equipment
related to the
spare
part/consumab
le
Description
Quantity
Supplier
Manufacturer
Model
Country of
origin*
9
Unit
price**
(USD)
10
Total Price**
(col. 4 x col. 9)
(USD)
TOTAL
*
The term origin of Goods must be specified pursuant to Community Customs Code (European Economic Community (EEC))
Regulation No 2913/92 and corresponding legislation for execution, European Commission (EC) Regulations No 2454/93).
Only one origin may be given: Poland or third country. Any item having assigned more than one country of origin shall be
considered of a third country. Any item with no assigned country of origin shall be deemed to be of third country.
** Prices for imported Goods shall be quoted on a DAP Incoterms 2010 basis including inspection prior delivery, freight, transport
insurance, warranty, preventive maintenance and after-sales services and manuals.
Name: <state the full name of the person signing the Bid Form>
Acting as <state the legal status of the person signing the Bid Form>
Duly authorised to sign the Bid for and on behalf of: <state the full name of the Bidder>
Date ___of month ____ of year _________ [state date of signature]
SECTION 4
58
A.1.3 Summary of Prices for imported Goods Polish /or third country origin)
COLD STORAGE ROOMS FOR MEAT AND ASSOCIATED FACILITIES
Total Price
Unit Price
ITEM
Description
TOTAL QTY.
(USD)
Name: <state the full name of the person signing the Bid Form>
Acting as <state the legal status of the person signing the Bid Form>
Duly authorised to sign the Bid for and on behalf of: <state the full name of the Bidder>
Date ___of month ____ of year _________ [state date of signature]
SECTION 4
(USD)
59
A.2
Item No.
Description
Quantity
Supplier/SubContractor
Country of
origin*
7
Unit price
(USD)
TOTAL
* It is understood that the country of origin of the services is the same as the entity providing the services
State the different items, for example:
-
Design.
Works.
Training courses.
Name: <state the full name of the person signing the Bid Form>
Acting as <state the legal status of the person signing the Bid Form>
Duly authorised to sign the Bid for and on behalf of: <state the full name of the Bidder>
Date ___of month ____ of year _________ [state date of signing]
SECTION 4
8
Total Price Project
Site/Location
(col. 3 x col.7)
(USD)
60
B. LOCAL COST*
1
Item No./
Service
Description of
Goods/
Services
Quantity
Supplier/SubContractor
Manufacturer
Model
Unit price
(USD)
Total Price
Project Site/ Location
(col. 3 x col.7)
(USD)
TOTAL
*The local cost is defined as the part of the commercial contract relative to the disbursements for payment of the goods and services
supplied by local companies in the Republic of Kenya under the surveillance of the contractor and conducive to the implementation of
the commercial contract..
State the different items, for example:
- Goods.
- Services.
- Works.
- Other local cost (if required).
Name: <state the full name of the person signing the Bid Form>
Acting as <state the legal status of the person signing the Bid Form>
Duly authorised to sign the Bid for and on behalf of: <state the full name of the Bidder>
Date ___of month ____ of year _________ [state date of signature]
SECTION 4
61
C. BID SUMMARY PRICE
Total
USD
A.1 IMPORTED GOODS (POLISH
AND/OR THIRD COUNTRY ORIGIN)
A.2 SERVICES (POLISH AND/OR
THIRD COUNTRY ORIGIN)
B. LOCAL COST
TOTAL(A1+A2+B)
Name: <state the full name of the person signing the Bid Form>
Acting as <state the legal status of the person signing the Bid Form>
Duly authorised to sign the Bid for and on behalf of: <state the full name of the Bidder>
Date ___of month ____ of year _________ [state date of signature]
SECTION 4
62
D. INFORMATION REGARDING ORIGIN OF THE GOODS AND SERVICES AND LIST OF SUPPLIERS, MANUFACTURERS AND
/OFFICIAL DISTRIBUTORS OF THE PROJECT
D 1. Breakdown of the Goods and Services by origin:
Description
Value (USD)
100 x
The percentage of third country origin of goods and services or local cost is calculated over the total exported goods and services of the
Project, i.e., over the amount of Polish origin goods and services plus third country origin goods and services (third country is anyone
else other than Poland and Kenya).
Name: <state the full name of the person signing the Bid Form>
Acting as <state the legal status of the person signing the Bid Form>
Duly authorised to sign the Bid for and on behalf of: <state the full name of the Bidder>
Date ___of month ____ of year _________ [state date of signature]
SECTION 4
63
D.2 List of suppliers, manufacturers and /official distributors of the Project
POST
TAX
SUPPLIERS
STREET/NO. TOWN
CODE/
TEL
EMAIL
CODE
PROVINCE
WEB
PAGE
NATIONALITY*
MANUFACTURER/
OFFICIAL
DISTRIBUTOR
TAX
CODE
STREET/NO.
TOWN
POST
CODE/
PROVINCE
TEL
WEB
PAGE
NATIONALITY*
SUBCONTRACTOR
TAX
CODE
STREET/NO.
TOWN
POST
CODE/
PROVINCE
TEL
WEB
PAGE
NATIONALITY*
SECTION 4
64
Form 9.
<The Bidder must complete this form in accordance with the instructions given between
square brackets [ ]. No alterations to this form or replacements will be accepted >
[The bank must complete this Bank guarantee form according to the instructions given]
[State name of Bank, and address of the branch issuing the guarantee]
Beneficiary: [state full name and address of the Contracting Authority]
Date:
[state date]
has withdrawn its Bid during the Bid validity period specified by the Bidder on the
Bid Form; or
b.
This guarantee will remain in force up to and including 30 (thirty) days after the final
validity deadline for the Bids, and any demand in respect thereof should reach the Bank
not later than the above date.
SECTION 4
65
In case the Bidder results to be the successful Bidder, the Bid Security will remain in
force from the date of issuance up to the date in which the successful Bidder submits the
Performance Security in accordance with the Clause 32 of the Instructions to Bidders
(SECTION 2 of the Bidding Documents) and the Clause
of the General Conditions of
the Contract (SECTION 6 of the Bidding Documents) or until the expiration of the 3
(three) years deadline as per established in Article 45.2 of the General Conditions of the
Contract (SECTION 6 of the Bidding Documents).
This Letter of Guarantee is subject to the Uniform Rules for Demand Guarantees (URDG)
as set out in the International Chamber of Commerce (ICC) publication 758.
[Signature(s) of the authorised representative(s) of the bank]
SECTION 4
- 66 -
SECTION 5
Technical Specifications and Drawings
INDEX
SECTION 5 Technical Specifications and Drawings .................................................. 66
1. Scope of Bid. ........................................................................................... 68
2. Quality of Materials ......................................................................................... 68
3. Packing. ........................................................................................... 68
4. Performance Schedule ..................................................................................... 69
5. Inspection.. .......................................................................................... 70
6. Transport. .......................................................................................... 70
7. Insurance ........................................................................................... 71
8. Manufacture. ........................................................................................... 71
9. Commissioning of the Goods ............................................................................ 72
10. Spare parts, Consumables and Special Tools ...................................................... 72
11. Technical Warranty, Preventive Maintenance and After-sales Services ................... 72
12. Training. .......................................................................................... 73
13. Test and Inspections ....................................................................................... 74
14. Local Costs. .......................................................................................... 75
15. Project Site ........................................................................................... 75
16. Cold Storage Rooms for Meat and Associated Facilities ........................................ 75
17. Design Requirement ........................................................................................ 75
18. Key Equipment.. .......................................................................................... 75
19. Technical specification for the supply, installation , Testing and Commissioning of Cold
Storage for meat and associated facilities .......................................................... 76
19.1.
19.2.
19.3.
SECTION 5:
- 67 -
SECTION 5:
- 68 -
A. Technical Specifications
1. Scope of Bid
The scope of the Bid shall be as follows:
a.
b.
c.
Functional Requirement:
d.
Cold storage facilities for meat shall be installed in abattoirs owned by the
government institutions or as shall be directed by the contracting
authority.
2. Quality of Materials
2.1. All Goods supplied under this Contract shall be new and of the best quality and
of the class most suitable for working under the conditions specified and shall
withstand the variations of temperature and atmospheric conditions arising
under working conditions without distortion or deterioration in the setting up of
undue stresses in any parts and also without affecting the suitability of the
various parts of the works for which they were designed.
2.2. All Goods offered shall be the product of recognized and experienced
manufacturers and shall be proven equipment of the same basic design and size
similar to that which has been in successful continuous operation for at least 3
(three) years.
2.3. All the Goods offered must comply with its corresponding Norm and Directive
and with the regulations established by the Kenyan Bureau of Standards (KEBS)
of the Republic of Kenya.
2.4. The Goods offered shall be designed to operate normally under the conditions of
Kenya. The conditions include power supply, climate, temperature, humidity,
etc.
3. Packing
SECTION 5:
- 69 -
3.1. Packing shall give adequate protection to the Goods against mechanical damage
during transport to its final destination, including rough handling during sea, rail
and road transportation and transition from one mode of transport to another.
3.2. The successful Bidder shall pack and mark the Goods in such form, quality and
quantity and will assure the secure, complete, intact and undamaged arrival of
the Goods at the Project Site as per distribution list of the Technical
Requirements of this SECTION 5.
3.3. During transit, the packing shall be sufficient to withstand, without limitation,
rough, handling and exposure to extreme temperatures, salt and precipitations
and open storage. Packing case size and weights shall take into consideration,
the remoteness of the Project Site and the absence of heavy handling facilities
at all points in transit and final destination.
3.4. Steel works sections and similar items may be bundled provided that the ends
are adequately protected and the enclosing bands or wires are robust.
3.5. Indoor electrical equipment must be enclosed in welded polythene envelopes
inside packing cases and the envelopes shall be evacuated or have a desiccant
inside.
3.6. All items in cases or crates shall be secured so that they are not free to move
and cannot work loose in transport. If rotating parts are shipped within their
bearings or mountings, they must be adequately braced and restrained to
prevent relative movement. Loose items shall be placed in bags in a case, each
bag having stitched onto it a label indicating the number and nature of its
contents. Where a filler material is used in a case to restrict movement or
provide additional protection, it must be inorganic and non-hygroscopic.
3.7. All surfaces liable to corrosion shall be thoroughly cleaned and special steps
adapted to the nature of the materials and the time interval between packing
and unpacking shall be taken to prevent corrosion. These steps may constitute
the greasing on surfaces, the application of a protective coat, enclosure of the
items in a hermetically sealed container, the addition of vapour phase inhibitor
paper to the package or other approved means.
3.8. Steps shall be taken to ensure that moisture, moulds, insects or rodents cannot
damage insulated materials. Items that include materials liable to be damaged
by moisture shall be packed in hermetically sealed containers in which silica gel,
or some other approved desiccant has been inserted.
3.9. Cases shall be marked with large lettering to show which side of the case is to
be up, and if the contents are fragile, marked "FRAGILE" in large letters with the
international wineglass symbol. Packages shall be marked with their place of
destination in such a way that rough handling or the effect of weather cannot
remove or obliterate the marking. Each item shall be marked with its gross
weight and, for all lifts over two tonnes, marks on the cases shall show the
correct positions for the slings.
3.10. Special steps shall be taken to guard against theft during transport.
3.11. A descriptive and fully itemized list shall be prepared of the contents of each
packing case. A copy of this list shall be placed in a waterproof envelope inside
and outside of the case.
4. Performance Schedule
SECTION 5:
- 70 -
4.1. The Bidders are required to submit a detailed time programme schedule to the
Contracting Authority. The maximum time period provided for execution of the
Contract is 18 (eighteen) months plus the Warranty Period form the date of
signature of the Project Site Availability Certificate (Article 20, Execution
Period/Project Site Availability, of the General Conditions of the Contract,
SECTION of these Bidding Documents..
4.2. The Bidder shall submit a Performance Schedule within a bar diagram containing
at least the following:
a)
The order in which the Bidder proposes to perform the Contract, including,
Manufacturing, delivery, installation, testing, commissioning and handover
of Cold Storage Rooms for Meat and Associated Facilities.
b)
c)
d)
e)
5. Inspection
5.1. The Bidders shall include in their Bids the cost of a pre-shipment inspection, and
shall take into consideration that all equipment to be imported into Kenya must
comply with the standard regulations established in Kenya by the Kenyan
Bureau of Standards of the Republic of Kenya (KEBS).
5.2. Prior to each shipment, the awarded Bidder shall engage, at his own expense, a
reputed international inspection company, in order to carry out a pre-shipment
inspection at the port of shipment or at the Bidders or sub-contractor
workshops or warehouses in order to check if the Goods comply with the
description, quantity and packing characteristics stated in the Contract.
6. Transport
6.1. The Bidders shall include in their Bids the cost of:
SECTION 5:
the handling and the transport of the Goods to the Project Site, under
usual conditions, through a usual route and in the usual manner, under all
the circumstances;
- 71 -
6.2. The Bidder shall have the right of choice the points of loading of the Goods, and
the modality of transport subject to final delivery.
6.3. Partial shipments to transport the Goods will be allowed in accordance with the
programs as mentioned in item 4.2 on performance schedule.
7. Insurance
7.1. The Bidders shall include in their Bids the cost of the following insurance that
shall cover:
a. Insurance of Goods during transportation
To cover any loss or damage incurred to the Goods (including spare parts
repositions) during transportation from Contractor or sub-contractor
workshops or warehouses to the Project Site. The insurance must at least
cover the price set out within the Contract plus ten per cent (i.e. 110%) and
must be agreed in the Contract currency.
b. Construction and Assembly All Risk Insurance
The Contractor must take out a combined Construction and Assembly All
Risk insurance policy to cover any damage that may occur to the Works,
Goods, provisional installations and materials, from commencement of the
Works or arrival of the Goods to the Project Site until Final Acceptance of
the Project.
The Contractor must insure the Works, Goods, provisional installations and
materials for a sum amounting to not less than the complete cost of
reconstruction, including demolition costs, removal of debris and
professional fees and expenses.
c. Contractor Equipment Insurance
Sufficient insurance cover to replace any equipment and other objects
brought in by the Contractor to carry out the Works on Project Site.
8. Manufacture
8.1. The Bidders shall consider in their Bid the cost of manufacturing including all
documents necessary to define/design and properly execute the Project and
requirements to enable the Cold Storage Rooms for Meat and Associated
Facilities obtain accreditation and to meet European legislation requirements in
terms of quality control and food safety, detail of the Works to be developed
during the execution of the Project and a basic drawing for Cold Storage Rooms
for Meat and Associated Facilities, as well as, the protocol for Completion Test.
8.2. An indicative description and drawings of each Cold Storage Rooms for Meat and
Associated Facilities are indicated in part B of this SECTION 5, schedule of
contract drawings.
8.3. For evaluation proposes, the Bidders must submit as part of its Proposal a Cold
Storage Rooms for Meat and Associated Facilities manufacturing plant process
layout.
SECTION 5:
- 72 -
reagents
and
consumables
and
10.4. A list of recommended spare parts, reagents and consumables for 1 (one) year
operation shall be listed separately and not included in the Bid price. This list
must be coherent with the breakdown of the scope.
11. Technical Warranty, Preventive Maintenance and After-sales Services
11.1. Bidders shall include in their proposals a Technical Warranty and Preventive
Maintenance Programme. The warranty period shall be 12 (twelve) months from
the date of issuance of the Practical completion Certificate in each of the cold
storage facility sites.
11.2. Preventive Maintenance: The Contractor shall make the necessary preventive
maintenance, visiting the Cold Storage Rooms for Meat and Associated Facilities
in order to warrant and maintain all the equipment in good working conditions
and ensure its proper and efficient use. A Maintenance Certificate shall be drawn
up after each visit and signed by the person in charge of the equipment and/or
the group Chairman.
11.3. The Bidders shall include in their proposals a Preventive Maintenance
Programme. This Programme shall include at least 3 (three) visits per year of
warranty period, for the Key equipment, during the Warranty Period. The last
visit, at the end of the Warranty Period shall be compulsory in order to get the
Final Acceptance Certificate conformed. The brush-up training shall take place
during this visit.
11.4. The above-mentioned programmes shall indicate all details regarding the way
chosen by the Bidder to carry out the aforementioned services.
SECTION 5:
- 73 -
11.5. The Bidder shall provide or secure the provision of a local reliable after-sales
service thereafter guaranteeing maintenance and the rapid replenishment of
spare parts and consumables for 5 (five) years. His technical offer shall include
a description of how the service will be provided by a local organization
authorized by the Manufacturer/Official Distributor including name of the service
organisation, postal address, telephone and facsimile number and e-mail
address.
12. Training
12.1. The training should be running in the course of the commissioning of the
equipment installed. In addition a brush-up training shall be carried out at least
6 (six) month after the provisional acceptance date, during the warranty period
and shall be compulsory in order to get the Final Acceptance Certificate
conformed.
12.2. The training programme shall include specific courses regarding to the following
production chain actors:
12.3. The following courses shall be given the production chain actors listed below:
a.
b.
Sampling techniques.
12.4. Bidders shall adapt their training proposal to the specific needs and
requirements of the personnel in charge of the operation and maintenance of
the equipment. Bidders shall combine different approaches and teaching
methods to obtain the highest possible level of efficiency of the equipment.
12.5. When elaborating their proposal, the Bidders shall take into account, as part of
their methodology, the following:
SECTION 5:
- 74 -
12.6. Bidders shall propose a training programme covering all the aforementioned
requirements. Therefore, Bidders shall submit, at least, the following
information:
Bidders shall take into account that the team of trainers responsible for
implementing the training programme must have a proven record of
experience in all the training areas. This record must be proved by the
relevant certificates.
12.7. In order to facilitate the training programme, the Contracting Authority shall be
responsible of providing qualified personnel for the training stage.
13. Test and Inspections
13.1. The Bidders shall include in their proposal the cost to carry out the tests and
inspections of the Cold Storage Rooms for Meat and Associated Facilities in
order to check that they comply with the quality, quantity and characteristics
required under these Technical Requirements at his own risk and at no cost for
the Contracting Authority.
13.2. Cold Storage Rooms for Meat and Associated Facilities will be only accepted
after successful Completion Tests. The Completion Tests required are the
following:
a.
SECTION 5:
- 75 -
b.
operational test period, to show that the Cold Storage Rooms for Meat
and Associated Facilities or stage thereof is operating satisfactorily.
+2oC to -1oC
27oC DB
85%
42.0 KW
Description
001
Evaporator
002
SECTION 5:
- 76 -
Key Equipment
Item
Description
004
Control Boards.
006
Prefabricated panel
007
Standby Generator
009
Regarding the above Key Equipment, the Bidders shall submit in their Bids the
following documentation:
ISO 9001 Certificate of the Manufacturer/Official Distributor in the event that
the Bidder is not the manufacturer of the Key Equipment.
Manufacturer/Official Distributor authorization in the event that the Bidder is
not the manufacturer of the Key Equipment according to the Form 7 provided
in SECTION 3, Bidding Forms.
19. Technical specification for the supply, installation , Testing
Commissioning of Cold Storage for meat and associated facilities
and
19.3.
SECTION 5:
- 77 -
SECTION 5:
- 78 -
- Filter drier
- Sight glass with moisture indicator
- Solenoid valve
- HP/LP cut out
- Suction & delivery gauges
- Room thermostat
-100mm diameter surface mounted dial thermometer in degree
Celsius
19.6. Control Panel
The control panel shall be fabricated from mild steel sheet of minimum SWG18
with a hinged door and then powder coated after manufacture. It shall be
provided with an integral lock. It shall be complete with;
1. Isolator fitted on the door
2. Controlling thermostat with temp rang from -100C to 300C
3. 80mm dial thermometer with temp rang from -100C to 300C
4. Contactors for defrosting Coils
5. Motor starters ¤t overload relays
6. MCBs
7. Phase failure relay with over and under voltage protection
8. Timer switch for defrost control
9. Push buttons for start and stop
10. Audible and visual high temperature alarm with manual reset
The panel shall also have green light running indicators, red door open light
and equipment circuit trip lights.
19.7. Electrical Installation
The electrical sub-contractor shall be responsible for providing power to the control
panel and for providing a local Isolator and connecting power to it. The cold room
sub-contractor shall be responsible for the final connections to the above equipment,
all control wiring and for all wiring within the control panel.
19.8. Shelves
The sub-contractor shall supply and fix fully fabricated 3 tier stainless steel metal
shelves and set them in the cold room as shown on the drawing. Shelf size to be 900
x 500 x 1350mm high.
SECTION 5:
- 79 -
Electric weighing scale: This is to weigh finished products into 25 and 400 kg carcasses.
PARTICULAR SPECIFICATION FOR THE STAND-BY GENERATING SYSTEM.
1
Location of site
The site for the proposed Contract Works is in Kenya.
Climatic Condition
The following climatic conditions apply at the site of the Contract Works and the
equipment, materials and installations shall be suitable for these conditions:
33.0C
Maximum Temperature:
Minimum Temperature
50C
45% - 99%
Dust in Atmosphere:
Longitude (approximately):
360 40E
Latitude (approximately):
010 18S
Altitude:
SECTION 5:
- 80 -
Operating Conditions
The equipment and all components shall be suitable for the operation in ambient
conditions of 50C to 400C and up to 100% relative humidity
i)
ii)
Functional Objectives
The set shall be capable of operating continuously and satisfactorily in a medium
dust laden atmosphere as defined in BS 1701 and in accordance with BS 649.
The generating set is required for standby duty and will be connected to the
switchboard through a circuit. It shall have an automatic mains failure control,
appropriately interlocked with the other incoming supply. Provisions shall be made
in the control circuit of the generator for automatic and remote push button
control, including the terminals and cable glands for all external cables, which will
be supplied by others, where specified. It shall also be possible to start, operate
and stop the set manually, independent of any automatic features.
Within the operating conditions specified in part 3 above the set shall be capable
of starting and accepting full load within the shortest possible time, and in any
case, in not more than 10 seconds. Any special features included to achieve this
shall be stated in Section F.
5.
Push button starting, starting battery and mains power supply trickle
charger to be included.
b)
72 hour operational running capacity auxiliary fuel oil storage tank, loose
transfer pump and duplex oil strainer.
c)
An integral belly/ base fuel tank for daily service with an operational
running capacity of 8 hours
d)
All interconnecting pipe work, valves and fittings between the storage tank,
base tank and the diesel engine.
e)
SECTION 5:
- 81 -
f)
g)
h)
i)
Performance Objective
The output rating of the set in KVA, the voltage, the number of phases and the frequency
shall be as specified in Schedule 3 of the Electrical Bills of Quantities.
Within the operating conditions specified the set, equipped with its standard air intake
filters, shall be capable of delivering its rated output continuously at rated voltage and
0.8 lagging power factor and of delivering 10% in excess of the continuous maximum
rating for a period of one hour in any 12 hour period.
The steady state voltage shall be maintained within 2 % of the rated voltage under
control of the voltage regulator between the cold start ambient conditions and the
maximum working temperature, from no load to 10% overload and from unity to 0.8
lagging power factor. After any change of load the voltage shall not vary by more than +
15% of the rated voltage and shall return to within +/- 3% within 3 seconds and to
within 2 % of rated voltage within 1 seconds. On starting the voltage overshoot shall
not exceed 15% and shall return to within 3% in not more than 3 seconds.
The governing of the set shall be such that the steady load speed band shall not exceed
1% of rated speed. Sudden removal of the full load at rated frequency shall not cause the
frequency to rise above 110% of the rated frequency and it shall return to within 105%
of the rated frequency within 3 seconds. The resultant steady state frequency shall return
to 104% within 15 seconds. If full load is then reimposed the frequency shall not fall
below 94% of rated frequency and shall return to 99% within 3 seconds and to the rated
frequency within 15 seconds. The cyclic irregularity of the set at full load shall not be
worse than 1/150.
The deviated interference shall be suppressed to the limit specified in BS 800 and BS
833.
7.
Unless otherwise indicated the set and its auxiliaries shall be mounted on sufficiently
substantial underbase. All items which must be held in correct relative alignment shall be
located by means of dowels.
The set shall be designed and supplied for operation bolted to the floor on robust antivibration and shock absorbing devices. They shall have adjusting screws for optimum
setting and levelling and be so designed and installed that no appreciable engine
vibration shall be transmitted to the floor or to any surrounding.
Bearings shall be suitable for operation over long periods without the need for
replacement of the lubricant. Oil lubricated bearings shall be fitted with a visible oil level
gauge.
8.
Diesel Engine
8.1
General
SECTION 5:
- 82 -
The engine shall comply in design and performance with BS.649 Diesel Engines for
General purposes or its approved equivalent. The engine shall be designed for
satisfactory operation on fuel oil and lubricating oils complying with BS. 2869.
The engine shall be totally enclosed, with forced lubrication from an integral pump having
on the suction side a course strainer and on the delivery side a dual full flow fine filter
with a changeover cock incorporating pressure by-pass, so that the oil flow to the engine
is maintained if the filter should choke. Alternatively a single filter of the self-cleaning
type fitted with a by-pass relief valve and having the same filtration performance may be
provided. Manual lubrication of any part of the engine will not be accepted. The capacity
of the lubricating oil system shall be sufficient to enable the engine to run continuously
for 12 hours at any load without replacement.
A filter with a by-pass relief valve shall be inserted in the fuel line immediately before the
pump(s). The fuel filter element shall be incapable of passing particles larger than
micrometers. The fuel system shall be so arranged that fuel resulting from filter, pump or
pipe spillage shall be incapable of entering the engine sump.
Air filters complying with KS 06-294: 1986, Grade A and Grade B suitable for use in a
dusty atmosphere shall be fitted on the engine air intake(s)
No significant critical speed of the complete shaft system, including the generator, shall
be within 15% of the rated speed.
A manually reset overspeed trip shall be fitted to stop the engine if its speed exceeds the
rated speed by 15%. A mechanical trip is preferred but an electrical overspeed trip may
be offered. Both types shall be equipped with a pair of contacts which close on operation
of the trip. If the device is belt driven, at least two belts shall be provided and the drive
shall be capable of carrying full load with one belt removed.
The set shall be arranged such that on shut-down the cooling water temperature shall not
rise with residual heat so that the high water temperature lock-out operates. The engine
may be naturally aspirated as pressure charged, or as indicated.
The starting shall be by means of electricity supplied from a starter battery. The starter
motor shall be of axial type, de-energizing by a device operated from the engine. A
means of manual starting shall also be provided.
Suitable means shall be provided for running by hand the engine main shaft and the
associated generator to facilitate inspection and overhaul.
If weekly test runs are insufficient to prevent the drying out of the bearings, means shall
be provided to ensure that the bearing surfaces are adequately and automatically wetted
with lubricating oil either periodically or immediately prior to every start.
The engine shall be capable of being started from any crank position.
A thermostatically controlled 240-volt immersion heater may be fitted in the engine
lubricating oil sump to facilitate starting. The heating surface loading of any lubricating oil
heater(s) shall not exceed 0.015 watt per square millimeter to avoid carbonization of oil.
An efficient exhaust silencer with adequate draining facilities shall be supplied, and shall
either be mounted on the set or installed in a generator room constructed as shown on
the drawing indicated. The exhaust silencer system shall be so arranged that it may be
readily relocated if required. Where any additional piping bends and fittings are specified,
the manufacturer shall advise on any problems involved.
SECTION 5:
- 83 -
8.2
An auxiliary fuel storage tank whose minimum capacity shall be sufficient to run the
engine continuously on full load for 72 hours shall be installed in the position indicated in
the contract drawing. It shall be supplied complete with supports.
The tank shall be fitted with a hand operated fuel with a flexible suction hose to permit
filling from a drum on the floor.
A three way cock shall be fitted in the line from tank to the engine to enable the fuel to
be supplied from a source other than the storage tank.
The position of the cock shall be clearly marked MANUAL, AUTOMATIC, OFF as
applicable.
A duplex oil filter shall be supplied between the storage tank and the diesel engine. The
duplex filter shall be capable of being cleaned without dismantling, or in interruption of
the fuel flow, and shall be easily maintainable. The tank shall be equipped with a
graduated dipstick, a clearly visible contents gauge (not of the site glass type) and with
drain, vent, overflow and inlet and outlet connection.
The set shall also have an integral belly/base fuel tank for daily services with an
operational running capacity of 8 hours.
8.3
An engine driven integral gear type lubricating oil pump shall be provided. The lubricating
oil system shall include an oil cooler and fine mesh filters, together with devices to
indicate lubricating oil pressure and to initiate a 240 volt A.C. Lubricating oil Low
pressure Alarm, Lubricating Oil High Temperature Alarm and Cooling Water High
Temperature Alarm.
As separate 240 volt A.C. Motor driven automatic lubricating oil priming pump shall be
provided for intermittent operation when the diesel is lying idle.
8.4
Starting of Engine
The diesel generator set shall have facilities for local and remote push button starting,
with a Local/ Remote/ Automatic selector switch at the local panel.
On mains failure the engine shall be capable of being automatically started from battery
located near the generator set.
The battery shall be complete with drip tray and trickle charger.
All necessary relays, contacts, switches and miscellaneous items for the starting
sequence shall be supplied and installed in the local control panel.
The system shall be designed to give maximum reliability in starting.
The Contractor shall state in detail his proposals to ensure reliable starting and
prevention of deterioration of the diesel engine, generator and exciter during idle periods.
SECTION 5:
- 84 -
All manually operated valves and controls on whose setting the correct operation of the
automatic starting equipment depends shall be provided with locking devices.
8.5
Cooling System
SECTION 5:
- 85 -
Governing System
Governing shall conform to B.S. 640 Class A. The governor shall control the frequency
within the limits stated in Section 6 Part. Manual speed adjustment shall be provided over
a range of +/-15% of the rated speed at any load. The governor system shall be of the
mechanical or hydraulic type. In addition the engine shall be fitted with an approved
overspeed trip device which shall operate independently of the normal speed governor
and shall act directly upon the fuel supply to the engine.
The overspeed shall act at a speed of 12% to 15% in excess of normal operating speed.
8.7
Exhaust System
The diesel engine shall be provided with a suitable exhaust system for horizontal
discharge outside the diesel generator room.
The silencer shall be of spark arresting type and shall be equipped with cleaning and
draining arrangements.
If an exhaust driven turbo-charger is supplied it shall include air intake filters, mani-folds
and outlet manifolds.
All necessary ducting, piping, supports and lagging required for the system shall be
included.
Weatherproof wall boxes permitting expansion shall be fitted where the exhaust piping
passes through the building wall or roof. Pipe work shall be connected at site by butt
weld connections or use of flanged joints. The use of screwed connectors shall be
avoided.
Flanges shall conform to the appropriate Table of B.S.10: 1962. Welding of flanges at site
shall be carried out in accordance with B.S.806. The faces of flanges shall be machined
and the backs shall be machined or spot faced to receive the bolt heads.
Valves and fittings shall be of approved design and manufacture and shall be subject to
the same tests as the highest pressure piping or vessel to which they are connected.
SECTION 5:
- 86 -
8.8
Engine Instruments
(b)
(c)
A tachometer
(d)
A water thermometer
(e)
(f)
Lubricating oil thermometers on the inlet to and outlet from the engine, when a
lubricating oil cooler if fitted
(g)
8.9
9.
9.1
General
The generator shall comply with B.S.2613:197, for service in tropical conditions,
and shall withstand being idle for considerable periods without any harmful drop in
the insulation resistance.
The generator shall have a prime rated net output of 150KVA as specified in the
schedules of the Bills of Quantities, at 0.8 lagging power factor, 415 volts, 3
phase, 4 wire, 50 Hertz with brushless rotating rectifier excitation system and
voltage regulator. It shall be directly coupled to the engine and be sized such that
it will accept the maximum output of the engine including overload. The output
voltage shall be maintained within plus or minus 2 % from no load to full load
conditions. The alternator shall be capable of operating within the range of plus or
minus 15% of the nominal voltage according to the automatic voltage regulator.
Three phase machines shall be star connected, and a diagram showing the
terminal marking and phase rotation shall be provided in the terminal box. Cables
connecting the machine winding and machine terminals shall not have a higher
de-rating factor for temperature than the windings.
The insulation shall comply with BS 2757 excluding Classes Y and A. The
insulation shall have an oil, moisture and fungus proof finish, with a surface which
will not retain dust or condensation. It shall be possible to put the set in service
after long periods in unheated storage without necessarily drying out the
insulation.
SECTION 5:
- 87 -
The alternator shall be capable of withstanding a short circuit for three seconds
when under the control of the automatic voltage regulator.
9.2
Excitation
Excitation shall be by means of brushless direct coupled exciter armature.
The alternators shall be designed for an excitation voltage at full load of not less
than 50 Volts unless prior approval is given.
9.3
A frequency meter
The meters shall comply with BS 89, table 7.
9.3.1 General
The set is to be used for mains failure duty and an automatic starting panel shall
be provided which shall contain all necessary equipment for controlling the
automatic starting and stopping of the set, lubricating oil priming (if necessary),
all auxiliaries, fault warnings and shut downs. All faults, warning and shut-downs
shall be separately indicated. There shall be test facilities for indication lamps, etc,
preferably by means of a single test button.
Means shall be provided for isolating all supplies to the starting panel either by an
isolating switch or by withdrawable fuses.
When the set is stopped other than under lock-out conditions, it shall be selfresetting ready for the next start.
The set shall be suitable for starting by manual means. e.g. by cranking or direct
operation of the starter solenoid.
All switches and push buttons shall be clearly marked to indicate their function.
SECTION 5:
- 88 -
It shall be possible to operate the Start and Stop buttons and to see the Set Failure
indications without opening the panel doors.
9.3.2 Automatic Changeover Controls
The controls shall be installed and wired in the machine control panel.
The control shall be provided such that on failure of the normal electricity supply, it will
automatically initiate the starting of and effect the transfer of load to the standby
generator. The schematic for the controls shall be approved by the Electrical Engineer
before manufacture commences.
Where failure of the normal supply is referred to, it shall be defined as follows:
a) Complete loss of voltage in one line 0r in all the three lines
b) Falling of voltage below 85% of the normal voltage between two lines or line and
neutral
c) Voltage overshoot to 110% of the normal voltage between two lines or line and neutral
d) Incorrect phase sequence
On failure of the normal supply, the unit shall operate in the following manner:
(a)
(b)
On receipt of a signal from the standby generating set that it is ready to take load,
and providing that the failure of the normal supply still persists, the normal supply
contactor in the control panel shall open and the standby contactor shall close. If
the normal supply has been restored before the changeover has taken place, the
contactor shall not operate and the starting relay contacts shall open to initiate
the shutting down of the standby generating set.
When the standby supply is in operation and the normal supply is restored and remains
within 10% of rated voltage on all phases for a pre-set time (adjustable up to 120
second) the standby contactor shall open and the normal supply contactor shall close;
the starting relay contacts shall then open to shut down the generating set.
Provision shall be made so that automatic return to normal supply can be prevented if
required.
Once a start signal has been sent to standby generating set, the engine starting
sequence shall be allowed to continue until the set is ready to take the load before a
stopping signal is sent.
A push button labelled Test shall be provided to enable a failure of normal supply to be
simulated. If the button is pressed and released the equipment shall complete the
starting sequence, and when the set is ready to take load it shall be shut down. If the
button is held depressed the equipment shall change over to the standby supply when
the set is ready to take load.
Indicating lamps or illuminated panels shall be provided on the front of the panel. They
shall be appropriately labelled, easily visible and shall give the following information:
Main Supply Available
SECTION 5:
- 89 -
Lock out
9.4.1 General
The set shall stop and lock out to prevent further starting when:
a)
It fails to start when the electric starter motor has been in operation for 20
seconds under automatic start condition.
b)
The lubricating oil pressure falls to a value at which it would be unsafe to continue
running the engine.
c)
The cooling water does not flow, when the engine is fitted with a visible flow
indicator on the cooling water system.
d)
(i)
(ii)
In air cooled engines the cylinder head temperature exceeds a safe
maximum.
e)
9.4.2 Failure of the circuits concerned in sub-section 9.4.1 (b) to 9.4.1(e) shall cause a
set to shut down. Reset of lock out shall be by hand.
9.5
Fault indication
Each lock-out detailed in section 9.4.1 shall be indicated by a lamp on the panel together
with an indication of the fault causing the shut-down. The fault warning lights shall be set
to operate before the lock-out.
9.6
The battery shall be 24 volts and capable of with-standing the loads imposed upon it by
its specified duties. It may be of lead-acid or alkaline type and shall be of sufficient
capacity for four starts in succession once in an eight-hour period. Auxiliary circuits
connected to the battery shall be protected by fuses.
The battery shall be used to supply an automatic starting and control equipment, and
relay operation shall not be impaired when the battery is supplying current to the starter
motor.
A single phase supply for battery charging shall be available from the main LV
SWITCHBOARD.
A charger shall be provided which will recharge the battery after engine starting and
maintain it in a charged condition when the set is standing or is in service. It may also
supply the load of any automatic starting and control equipments, and an additional load
up to 24 watts when the set is running and in service.
SECTION 5:
- 90 -
An alternative quick charge rate shall be provided. The charger shall be fitted with an
ammeter to measure the charger and discharge current excluding the starter motor
current.
9.7 Wiring and Earthing
Power cables and small wiring cables interconnecting major components shall be of the
heat and oil resistant type and shall be metal sheathed or run in metal ducts or metal
conduit, which shall be coded and terminated with lugs or eyes or to be soldered, the
terminations shall be clearly marked with the numbers and letters of the terminals to
which they are connected. Terminals shall be numbered or lettered, easily accessible and
fitted with individual insulating barriers or adequately spaced. Barriers shall be fitted to
separate control terminals from power wiring terminals.
All metal work housing electrical equipment shall be bonded to a brass earthing terminal
and connected to station Earth and as detailed in the schedule.
9.8
Contactors
Contactors shall have magnetic circuits designed for a.c or d.c operation and shall be
rated in accordance with ks 04-182:1982.Four pole- contactors shall be fitted for three
phase-equipment and two-pole contactors for single phase equipment. Main and auxiliary
contacts shall be silver faced or better.
9.9
Relays
Relays shall preferably be of sealed type mounted in approved plug-in bias with spring
loaded retainers but if this is not practicable they shall be mounted on individual subbases and wired so that easy access is obtained to soldered connections. Unsealed relays
shall be enclosed in individual or common dust protecting cases.
Time delays, if of the pneumatic type, shall operate on filtered air. The thermal type of
time delay relay will not be accepted.
9.10
Fuses
Fuses shall comply with KS-183:1978. A spare fuse cartridge for each pole shall be
mounted inside each equipment.
9.11
Rectifiers, capacitors and solid state components shall be suitable for any transient
voltage and high currents likely to be uncounted during the operation of the equipment
and for the internal operating temperature of the enclosures at the specified maximum
external ambient temperature.
9.12
Enclosures for electrical and control equipment shall be drip proof and dust protecting,
with adequate front and rear access as necessary for maintenance and repair. Special
attention shall be given to the method of construction and to the mounting of the
components to minimize the effect of vibration. Diagrams of connections in durable form
shall be mounted inside the enclosures.
SECTION 5:
- 91 -
10
Provision shall be made for ready handling of all parts of the plant during assembly or
disassembly of the unit. Adequate provision shall be made for attaching lifting devices,
slings and eyebolts.
11
Commissioning
The Contractor shall include for fully commissioning the set and its control equipment and
for the purpose of the required tests, shall provide all necessary instrument s, tools, fuel
and lubricating oil.
The following tests and checks as applicable shall be carried out by the contractor in the
presence of the electrical engineer or his representative.
a) Check that the main frame is level in all directions, engine and generator shafts are in
proper alignment and the vibration absorbing devices are properly installed and
located.
b)
Check water and sump oil levels and that the water jacket and radiation heaters
(if fitted) are in working order.
c)
d)
Examine the containers in which the fuel and lubricating oils were delivered and
check that the type and grade of oils are as recommended for the unit.
e)
Ensure that sufficient fuel oil is in the fuel tank for a two hours test run.
f)
Check that all radiator and engine block water drain points are free from sludge
and other blockages.
g)
Check engine bolts, main drive coupling, valve clearance, fuel pumps settings,
governor settings, pipeline connections, water hose, exhaust couplings, flexible
pipe work etc, and where a separate cooling water tank is fitted, that the water
levels is satisfactory and the ball valve and overflow work.
h)
Check all outgoing connections on the generator and the control panel. All lugs for
principal connections shall have clean and bright contact surfaces. A suitable
abrasive shall be used where necessary.
i)
Check access panels and doors for proper opening and closing and for functioning
of any interlocks fitted.
j)
With the set isolated from the main supply and the selector switch in the manual
position, start the engine by means of the start push button and allow it to run
up to normal speed. Check that the main battery charger is automatically
switched off to avoid its being overloaded by the reduction in voltage across the
battery. Where a battery charging dynamo is fitted, check that the main battery
charger is disconnected by the operation of the auxiliary contact during the time
the engine is running.
k)
Check instruments and gauges for normal operation and response and that the
generator voltage is being maintained within the prescribed limits, making due
allowance for no-load conditions. Compare the reading of the frequency meter
with that of engine tachometer, where both are fitted
SECTION 5:
- 92 -
i)
Stop engine by turning selector switch to off position and verify that the generator
contactor opens at between 95% and 85% of normal voltage. Re-check water and
oil levels.
m)
Turn selector switch to Auto position. Disconnect the sensing circuit supply and
check that the set starts, the mains contactor opens, and the generator contactor
closes in correct order. Reconnect the sensing circuit to verify that the engine
stops on restoration of the mains supply and the contactors operate correctly.
Check voltage sensing and time delays on each phase in turn and also the push
buttons for mains failure simulation and engine stopping operate correctly.
NOTE:
Running of the engine for any length of time under no load condition is
undesirable and
tests calling for such operation should be carried out in as
short time as possible
consistent with thoroughness.
n)
Operate the necessary isolators and switches to put the set on standby for
essential services network with the mains failure simulation push, verify that the
set operates correctly with the appropriate time delay for taking up load and that
the carrying of the load and its distribution over three phases are satisfactory.
o)
Run the set at various loads for periods totalling at least 30 minutes. Check that
the voltage and frequency are being maintained within the required limits with
large alterations of load. Note the rate of charge on the dynamo ammeter with the
engine running (if a dynamo is fitted), and the rate of charge on the battery
charging ammeter with the engine stopped. Check against manufacturers
recommendations and adjust charging rates if necessary.
p)
q)
Check the vibration absorbing devices for proper operation and that performance
of all flexible connections, both mechanical and electrical, is satisfactory.
r)
When all tests are satisfactory and agreed with the Engineer or his representative,
the lubricating oil and water levels shall be finally checked, the fuel oil tank
replenished and set left in normal operating order.
s)
An initial supply of all lubricating oils and greases shall be provided by the
Contractor.
t)
Additional lubricating oil shall be provided for recharging the engine sump once
together with a supply of lubricating oils and greases to cover the normal use and
serving of the set during the 12 months maintenance period referred to in Part 14
of Section D.
SECTION 5:
- 93 -
DRAWING NO.
DRAWING TITLE
MS 1
Floor Plan
MS 2
Roof Plan
MS 3
Section
MS 4
Elevation
SECTION 5:
- 94 -
SECTION 5:
- 95 -
B. Bills of Quantities
BILLS OF QUANTITIES
A)
Prices will be inserted against item of preliminaries in the Contractors Bills of Quantities
and specification. These Bills are designated as Bill No.1 in this Section. Where the
Contractor fails to insert his price in any item he shall be deemed to have made adequate
provision for this on various items in the Bills of Quantities. The preliminaries form part
of this contract and together with other Bills of Quantities covers for the costs involved in
complying with all the requirements for the proper execution of the whole of the works in
the contract.
The Bills of Quantities are divided generally into three sections:
(a)
(b)
(ii)
(c)
Summary
The summary contains tabulation of the separate parts of the Bills of Quantities carried
forward with provisional sum, contingencies and any prime cost sums included. The
bidder shall insert his totals and enter his grand total tender sum in the space provided
below the summary.
This grand total tender sum shall be entered in the Bid Form provided elsewhere in this
document.
SPECIAL NOTES TO BILLS OF QUANTITIES
1.
The Bills of Quantities form part of the contract documents and are to be read in
conjunction with the contract drawings and general specifications of materials and
works.
2.
The prices quoted shall be deemed to include for all obligations under the Contract
including but not limited to supply of materials, labour, delivery to site, storage on
site, installation, testing, commissioning and start up with initial charge as may be
SECTION 5:
- 96 -
All prices omitted from any item, section or part of the Bills of Quantities shall be
deemed to have been included to another item, section or part thereof.
4.
The brief description of the items given in the Bills of Quantities are for the
purpose of establishing a standard to which the Contractor shall adhere.
Otherwise alternative brands of equal and approved quality will be accepted.
Should the Contractor install any material not specified here in before receiving
written approval from the Project Manager, the Contractor shall remove the
material in question and, at his own cost, install the proper material.
5.
The grand total of prices in the price summary page must be carried forward to
the Bid Form for the tender to be deemed valid.
6.
The brochures are to be used to ascertain the suitability of the Equipment being offered
by the bidders, and bidders not complying with this requirement may be considered nonresponsive and may subsequently be disqualified from technical evaluation.
SECTION 5:
- 97 -
2.22
STATEMENT OF COMPLIANCE
(a) I confirm compliance with all clauses in this tender specification.
(b) I confirm that I have not and will not make any payment to any person which
can be perceived as in inducement to enable me win this tender.
DateStamp..
SECTION 5:
- 98 -
ITEM
DESCRIPTION
Initial maintenance
QTY
UNIT
Total for Bill No. 1 carried Forward to Grand summary page (USD)
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 99 -
DESCRIPTION
QTY
UNIT
73
SM
73
SM
83
CM
CM
17
CM
12
CM
93
CM
60
CM
39
SM
39
SM
39
SM
25
SM
B
C
D
E
I
J
K
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 100 -
ITEM
DESCRIPTION
QTY
UNIT
SUBSTRUCTURES-(CONTINUED)
Vibrated reinforced concrete grade 20/20 (1:2:4) in:
A
Strip footing
CM
39
SM
17
SM
26
LM
110
KG
62
KG
39
SM
lm
12mm Diameter
8mm Diameter
Steel fabric mesh reinforcement to B.S. 4483
SUBSTRUCTURES-(CONTINUED)
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 101 -
ITEM
DESCRIPTION
QTY
UNIT
52
SM
Plinths
B
16
SM
16
SM
ITEM
ITEM
SECTION 5:
16
SM
RATE
(USD)
AMOUNT
(USD)
- 102 -
ITEM
DESCRIPTION
QTY
UNIT
ELEMENT NO. 2
REINFORCED CONCRETE SUPERSTRUCTURE
Vibrated reinforced concrete grade 20/20 (1:2:4) in:
A
CM
150 mm Suspended
CM
150
SM
12 mm Diameter bars
146
KG
10 mm Diameter bars
98
KG
720
KG
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 103 -
ITEM
DESCRIPTION
QTY
UNIT
ELEMENT NO. 3
WALLING
A
41
LM
76
SM
48
SM
Ditto to gables
14
SM
84
LM
Lintel
E
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 104 -
ITEM
DESCRIPTION
QTY
UNIT
ELEMENT NO.4
ROOFING
Galvanized steel IT5 box profile sheets; 26 gauge;
prepainted
A
50
SM
LM
11
LM
16
LM
54
LM
66
LM
27
LM
11
LM
65
LM
Ditto purlins
50
LM
20
NO
Mild Steel
L
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 105 -
ITEM
DESCRIPTION
QTY
UNIT
ROOFING - (CONTINUED)
The following in second grade celcured and well
seasoned cypress timber
A
30
LM
LM
20
NO
20
NO
18
LM
LM
30
LM
30
LM
Eaves
E
NO
NO
Carried to Collection 4b
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 106 -
ITEM
DESCRIPTION
QTY
UNIT
ROOFING - (CONTINUED)
Downpipe
A
LM
NO
NO
10
SM
10
LM
SM
12
SM
From Collection 4a
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 107 -
ITEM
DESCRIPTION
From Collection 4b
From Collection 4a
SECTION 5:
QTY
UNIT
RATE
(USD)
AMOUNT
(USD)
- 108 -
ITEM
DESCRIPTION
QTY
UNIT
ELEMENT NO.5
DOORS
NO
NO
26
SM
Painting
SECTION 5:
CARRIED TO
RATE
(USD)
AMOUNT
(USD)
- 109 -
ITEM
DESCRIPTION
QTY
UNIT
ELEMENT NO.6
EXTERNAL FINISHINGS
Walls
A
78
SM
SM
Beams
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 110 -
ITEM
DESCRIPTION
QTY
UNIT
40
SM
ELEMENT NO. 7
INTERNAL FINISHES
FLOORS
Cement and sand (1:4) screeding smooth
trowelled
A
To floor.
40
SM
50
LM
140
SM
40
M2
40
M2
Ceiling
CEILING FINISHES
12mm thick two coat steel trowelled gauged lime
Plaster to:E
Carried to Collection 7a
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 111 -
ITEM
DESCRIPTION
QTY
UNIT
129
SM
129
SM
135
sm
No
Walls
Plastered walls
Collection 7b
COLLECTION
From Collection 7a
SECTION 5:
RATE
(USD)
AMOUNT
(USD)
- 112 -
ITEM
DESCRIPTION
From Collection 7b
SECTION 5:
QTY
UNIT
RATE
(USD)
AMOUNT
(USD)
- 113 -
ITE
M
DESCRIPTION
QTY
SECTION SUMMARY
A
B
C
D
E
F
G
SUBSTRUCTURES
REINFORCED CONCRETE
SUPERSTRUCTURE..
WALLING
..
ROOFING
.
DOORS
..
EXTERNAL
FINISHES.
INTERNAL
FINISHES..
SECTION 5:
UNIT
RATE
(USD)
MOUNT
(USD)
- 114 -
MECHANICAL WORKS
Item
Description
Unit
Qty
No.
No.
Insulated door
No.
No.
Thermostat
No.
Dial Thermometer
No.
Solenoid valve
No.
No.
No.
No.
No.
Sight glass
No.
Vapour seal
M2
150
SM
150
SM
193
SM
193
LM
30
Item
No.
200
T
U
Filter drier
Electrical works associated with the coldroom
installations
No.
Item
Item
Item
Rate
(USD)
SECTION 5:
Amount
(USD)
- 115 -
ELECTRICAL WORKS
SCHEDULE NO.1 - ELECTRICAL INSTALLATION WORKS
ELECTRICAL INSTALLATION WORKS FOR MEAT COLD STORAGE
Rate
Description
Qty
Unit
(USD)
Item
Amount
(USD)
12
No.
0.00
No.
0.00
No.
0.00
No.
0.00
No.
0.00
No.
0.00
No.
0.00
No.
0.00
No.
0.00
SWITCHES
1.02
1.03
LIGHTING FITTINGS
1.04
Item
SECTION 5:
Description
Qty
Unit
Rate (USD)
Amount
- 116 -
(USD)
Sub- Total B/F From Previous Page
0.00
1.06
1.07
14
No.
a) Single.
No.
b) Twin.
No.
No.
No.
No.
No.
No.
0.00
No.
0.00
No.
0.00
1.08
1.09
1.10
1.11
1.12
SECTION 5:
- 117 -
Item
Description
Qty
Unit
Rate (USD)
Amount
(USD)
0.00
30
LM
0.00
No.
0.00
1.14
No.
0.00
1.15
No.
0.00
b) 20Amp SP MCB
No.
0.00
c) 30Amp SP MCB
No.
0.00
d) 30Amp TP MCB
No.
0.00
No.
0.00
METER BOX
1.16
1.17
SECTION 5:
No.
15
LM
- 118 -
Item
Description
Rate
(USD)
Amount
(USD)
0.00
Qty
Unit
No.
0.00
No.
0.00
No.
0.00
No.
0.00
LM
0.00
No.
1.19
1.20
No.
1.21
No.
1.22
No.
1.23
SECTION 5:
- 119 -
Item
2.00
25
LM
2.01
15
No.
2.02
No.
25
LM
No.
40
LM
No.
No.
No.
No.
No.
2.03
2.04
2.05
DOWNWARD CONDUCTOR
Downward conductor comprising 25mm x 3
mm thick bare copper tape as FURSE
Copper square tape clamp for making crossing
tape joints
Steel conduits32mm diam. for securing the
down conductors complete with saddles
2.06
2.07
2.08
2.09
2.10
SECTION 5:
Amount
(USD)
- 120 -
ITEM
DESCRIPTION
QTY
UNIT
3.00
No
3.01
15
LM
3.02
Item
3.03
Item
SECTION 5:
RATE
AMOUNT
(USD)
- 121 -
ITEM
DESCRIPTION
QTY
UNIT
3.04
3.05
3.06
3.09
3.10
3.11
3.12
No
No.
No.
No.
40
LM
40
LM
40
LM
Item
SECTION 5:
AMOUNT
(USD)
0.00
RATE
- 122 -
ITEM
3.13
DESCRIPTION
Sub- Total B/F From Previous Page
Supply, deliver to site and install, to the
approval of the project manager, and connect to
the daily service base/belly fuel tank, an
auxiliary fuel tank with level indicator and with
an operational running capacity of 72hours.
The tank is to be complete with stand and all
interconnecting G.I pipe work.
QTY
UNIT
AMOUNT
(USD)
0.00
No
3.14
Item
3.15
Item
3.16
lot
SECTION 5:
RATE
- 123 -
DESCRIPTION
QTY
UNIT
3.17
No
3.18
No
No
3.20
No
3.21
No
3.22
No
3.23
No
3.24
SECTION 5:
AMOUNT
(USD)
0.00
3.19
RATE
- 124 -
0.00
3.25
No
3.26
Fuel Filters
No
3.27
No
3.28
No
3.29
No
1
1
No
No
3.30
3.31
3.32
SECTION 5:
- 125 -
DESCRIPTION
SECTION 5:
QTY
UNIT
RATE
Item
TOTAL(USD)
4,500.00
- 126 -
ITEM
DESCRIPTION
BILL NO 3. BILL SUMMARY
SECTION 5:
TENDERER'S
AMOUNT (USD)
OFFICIAL USE
ONLY(USD)
- 127 -
Description
Contingency
Amount (USD)
10,000.00
Multiply by 5
X5
Total Amount For Five (5 No.) Meat Cold Store and Associated
Accessories Carried to Bid Form
Amount in words:
......
Tenderer's Name and Stamp.
Address ..........
Tenderer's Signature
Date.....
Witness Name:.
Witness Signature .....
Date.
SECTION 5:
- 128 -
SECTION 6
Contract
INDEX
A.
SECTION 6
- 129 -
SECTION 6
- 130 -
A.
CONTRACT AGREEMENT
INDEX
SECTION 6
- 131 -
CONTRACT AGREEMENT
<The Contracting Authority must complete this form in accordance with the instructions
given. No alterations to this form or replacements will be accepted >
THIS AGREEMENT made between:
<MINISTRY OF AGRICULTURE, LIVESTOCK AND FISHERIES STATE DEPARTMENT OF
LIVESTOCK> (hereinafter referred to as the Contracting Authority)
And
<Official Name of Contractor> (hereinafter referred to as the Contractor)
The parties mutually acknowledge each other as having due jurisdiction and capacity,
respectively, to formally set down this Contract and to that effect:
STATE
I) Whereas the Government of Poland has made financial facilities available to the
Government of Kenya charged against the Tied Aid Fund for Modernization of
Agriculture using Polish entrepreneurs to finance the procurement of Meat cold
storage and Associated facilites in Kenya.
II) Whereas the Contracting Authority has convened a Bidding Process to contract the
Project and has accepted the Bid submitted by the Contractor to execute the said
Project in the amount of --------------<insert Contract price expressed in words and
figures>.
On the basis of the above, the persons here present agree to execute this Contract
pursuant to the following:
SECTION 6
- 132 -
ARTICLES
1. Scope
1.1. This contract includes the supply, delivery, installation, testing, commissioning
and handing over to the certification of the engineer and maintenance for a
period of twelve months, five (5 No.), Cold Storage Rooms for Meat and
associated facilities complete with associated accessories.
1.2. The terms and expressions of this Contract shall be interpreted in the same
sense as given in the General Conditions of Contract set out in to this Contract.
2. Price
2.1. The Contract price amount, to be financed with resources from the Tied Aid
credit, amounts to the sum of USD ______________________ [insert amount
in figures and words]
2.2. Said amount is deemed to be a fixed non-reviewable price.
2.3. This price breaks down as follows:
Total
COST CENTRE
USD
SECTION 6
- 133 -
One (1) original and two (2) copies of the commercial invoice;
One (1) original and one (1) copy of the Advance Payment Bank
Guarantee issued by a bank of renowned international repute in the
same amount and to be issued on a prorated basis according to
completion of Contract provisions and the acceptance documents
signed by the Contracting Authority in accordance with the
Advanced Payment Bank Guarantee Form provided in Annex I of
the Contract;
SECTION 6
- 134 -
b. 45% (forty five per cent), of the value of Cold Storage Rooms for
Meat and Associated facilities as per Incoterms 2010 regulations
being the amount of <______ (state amount in figures and
words)> upon Installation, Testing and Commissioning . The
following documents should be provided by the contractor to the
paying bank:
c. 5% (five per cent), of the value of Cold Storage Rooms for Meat
and Associated facilities as per Incoterms 2010 regulations being the
amount of <______ (state amount in figures and words)> upon
Installation, Testing and Commissioning. The following documents
should be provided by the contractor to the paying bank:
3.2. All payments to the Contractor will be carried out in accordance with Tied Aid
Credit agreement.
4. Entry into force
4.1. This Contract will enter in force on the date on which each and every one of the
following conditions have been met:
a. That the Contractor has submitted a Performance Security pursuant to
Article 17 (Performance Security) of the General Conditions of Contract.
b. That the Polish authorities have issued all the necessary administrative
permits, pursuant to applicable Polish law, permitting this Contract to be
validly entered into and executed.
c.
That the authorities of the Republic of Kenya have issued all the necessary
administrative permits, pursuant to applicable law in the Republic of Kenya,
permitting this Contract to be validly entered into and executed.
d. That the Tied aid agreement to finance the Contract Price has been entered
into by authorities with jurisdiction and come into force.
e. That the Contractor has received the advance payment referred to under
Article 3 of this Contract Agreement.
SECTION 6
- 135 -
4.2. Each party must do its best to meet the conditions referred to in the previous
Article 4.1 and from which they are responsible.
4.3. This Contract will be automatically terminated in the event that it does not give
rise to any payment over a period of 3 (three) years from the date of signature.
5. Execution Period
5.1. The Contract Execution Period is deemed to commence on the date of signature
of the Project Site handing over Certificate by representatives of the
Contracting Authority and the Contractor pursuant to Article 19 (Execution
Period / Project Site Handing Over Certificate) of the General Conditions of
Contract, without prejudice to any extensions to said time period which may be
agreed in accordance with the provisions of this Contract.
5.2. The maximum time period provided for execution of the Contract is 12 (twelve)
months plus the Warranty Period from the date of signature of the Project Site
handing over Certificate pursuant to the Performance Schedule agreed by the
Contracting Authority and the Contractor.
6. Order of prevalence of contractual documents
6.1. The following documents shall be deemed to form, be read and be interpreted
as forming an integral part of this Contract and shall have the following order of
prevalence:
a. This Contract Agreement.
b.
c. The Bidding Documents, any clarification and any addenda prior Bid
submission deadline and official records of the clarification meeting/site
visit (Annex II)
d. The Technical Proposal of the Successful Bidder (Annex III).
e. Budget breakdown of the Successful Bidder including Price List
for Imported Goods (including Cold Storage Rooms for Meat and
Associated facilities, Spare Parts,
Consumables and Special
Tools, as established in the definition of Goods), Services, Local
Cost and Total Price List of the Contract the following documents.
<add any other document>.
<THE SUCCESSFUL BIDDER MAY NOT IN ANY EVENT CHANGE THE ORDER
ESTABLISHED UNDER THIS ARTICLE>
6.2. Any addenda will prevail according to the order of prevalence of the amended
document.
6.3. The various different documents comprising the Contract are deemed selfexplanatory, in the case of ambiguity or variation, the order of prevalence set
out above will apply.
7. Communications
SECTION 6
- 136 -
7.1. Communications between the Contracting Authority and the Contractor will be
carried on in writing and in English language as established in the General
Conditions of Contract.
7.2. For that purpose, the parties provide the following business addresses and
details:
inistry of Agriculture, Livestock and
Fisheries
State Department of Livestock
Address: P. O. Box 34188-00100
Nairobi, Kenya
Telephone: +254 020 2718870
<state
the
Contractor>
full
name
of
the
Email:pslivestock@kenya.go.ke
Website: www.kilimo.go.ke
In witness whereof the parties hereto have caused this agreement in two original copies,
one for the Contracting Authority and another for the Contractor.
Ministry of Agriculture, Livestock and
Fisheries
State Department of Livestock
Name: <state the full name of the
person signing the Contract>
Acting as <state the legal status of
the person signing the Contract>
Signature:
Date: <state date of signing>
CONTRACTOR:
<state
the
Contractor>
full
name
of
the
In the presence of the appointed nominee of the Polish Embassy in the Republic of
Kenya, who signs this Contract acting as witness.
SECTION 6
- 137 -
B.
1. Definitions............................................................................................................... 139
2. Applicable law and language ........................................................................... 142
3. Interpretation ........................................................................................................ 142
4. Communications................................................................................................... 143
5. Assignment and Sub-contracting .................................................................. 143
6. Joint Venture or Consortium ........................................................................... 144
7. Confidentiality ....................................................................................................... 144
8. Patents and Licences .......................................................................................... 144
SUBJECT AND SCOPE OF THE CONTRACT .............................................................. 145
SECTION 6
- 138 -
176
SECTION 6
- 139 -
PRELIMINARY PROVISIONS
1. Definitions
Bid
Commissioning
Means satisfactory
Authoritys needs.
Completion Tests
Contract
Contracting Authority
Contracting Authority
Technical Requirements
or Technical
Requirements
Contractor
SECTION 6
trial
run
for
Contracting
- 140 -
Contractor Equipment
Refers to all
equipment, machinery,
tools,
apparatus, devices and objects of all kinds necessary
to execute the Contract, not including Goods or
other objects forming part of or intended to form
part of the Project.
Day
Design
Execution Period
Final Acceptance
Certificate
Goods
ICC
Incoterms
Installation
ILS
SECTION 6
- 141 -
ITC
Plant
Notice of Award
OECD
Organisation for
Development.
Party
Paying Bank
Performance Schedule
Project
Project Site
SECTION 6
Economic
Co-operation
and
- 142 -
Practical Completion
Services
Technical
Proposal/Technical
Specifications
Warranty Period
Works
3. Interpretation
3.1. Whenever the context permits, plural terms are also deemed to refer to the
singular and vice versa; equally, masculine references are deemed to include
the feminine and vice versa.
3.2. The meanings of commercial terms and also of the rights and obligations of the
parties shall be as established under Incoterms, published by the ICC, 2010
edition, unless there is a discrepancy with any provision of the Contract.
SECTION 6
- 143 -
3.3. No modification or other variation to the Contract will be deemed valid unless it
is set down in writing, dated and refers expressly to the Contract, signed by a
duly authorised representative of each of the parties.
3.4. In the event that any provision or condition of the Contract is prohibited, void or
unenforceable, then that prohibition, nullity or lack of enforceability shall not
affect the validity or fulfilment of the remaining Contract provisions or
conditions, as long as the main provision is not altered nor the balance of
provisions affected in any extraordinary manner.
4. Communications
4.1. Communications between the Contracting Authority and the Contractor may
only take place in writing. Any communications between the Contracting
Authority and the Contractor must be sent by post, telegram, fax, e-mail or be
delivered by hand to the appropriate addresses provided by Parties for that
purpose.
4.2. If the sender requires an acknowledgement of receipt, this must be stated in
the communication and the sender must further request the acknowledgement
if a deadline exists for receipt of the communication. At all events, the sender
must take such steps as necessary to guarantee the communication is received.
4.3. Whenever the Contract provides, on the part of either Party, for a notice,
agreement, approval, authorisation, certificate or decision then these must be
set down in writing, unless otherwise provided, and the terms notify, agree,
approve, authorise, certify or decide shall have an identical effect. Such
agreement, approval, authorisation, certificate or decision may neither be
denied nor delayed unreasonably.
SECTION 6
- 144 -
5.1.6 Subcontracting shall only be deemed valid when set down in a written
contract in which the Contractor entrusts third parties with execution of
part of its Contract.
5.1.7 The Contractor may not subcontract any part of the Project without the
prior written authorisation from the Contracting Authorities. If
subcontracting was referred to within the Bid, then any changes thereto
shall require the prior authorisation of the Polish Government.
5.1.8 Sub-contractors must meet eligibility criteria applicable to the award of
the Contract pursuant to Clause 4.3 of the Instructions to Bidders.
5.1.9 The Contractor will be deemed liable for any actions, breaches or
negligence on the part of its subcontractors, their agents or employees,
as if these had been actions, breaches or negligence on the part of the
Contractor, its agents or its employees. In the event that the
Contracting Authority has approved the subcontracting of any part of
the Contract or the subcontractor, this shall not exonerate the
Contractor from any of its contractual obligations.
5.1.10 In the event that the subcontractor has entered into obligations with the
Contractor which will continue beyond the Warranty Period established
within the Contract, with regard to the provisions and works carried out
by the subcontractor, then the Contractor, at the request and at the
expense of the Contracting Authority shall, immediately and at any
given time, assign the benefit of such obligations after the Warranty
Period has expired to the Contracting Authority with regard to the
period remaining in force.
7. Confidentiality
7.1.
The Contractor must treat all information and documents received in relation
to this Contract as private and confidential and shall not, other than to the
extent as may be necessary to ensure it is executed, either publish or
disclose any detail thereof without the prior consent in writing of the
Contracting Authority. If any dispute arises as to need, for the purposes of
the Contract, to publish or disclose information, then the final authority shall
be on the Contracting Authority.
SECTION 6
The Contractor must compensate the Contracting Authority for any claim
arising out of the use, pursuant to the provisions of the Contract, of patents,
licences, drawings, designs, models, trademarks or registered signs, unless
the infringement came about by adherence to the Technical Requirements of
the Contracting Authority.
- 145 -
9.
The Contractor must Supply, Install, Test and Commission Cold Storage
Rooms for Meat and Associated facilities, including all associated
accessories and Consumables for start-up, in order to execute the Project
pursuant to the provisions set out in the Contract, finish it and correct any
possible defects of that design with due care and diligence and strictly
complying with the provisions set down in the Contract. After completion,
the Project must be suitable for the intended purposes as defined in the
Contract.
9.2.
9.3.
The Project must include all works as necessary to meet the Technical
Requirements, the Technical Proposal or any other work implicit in the
Contract, as well as any necessary to ensure adequate stability, termination,
security and operation of the Project.
9.4.
The Contractor accepts full liability with regard to compatibility, stability and
security of all operations and methods provided for in the Contract.
9.5.
9.6.
The Contractor must draw up and submit to the Contracting Authority, for its
approval, a Contract Performance Schedule, pursuant to the provisions set
out under Article 25 (Performance Schedule) of these General Conditions of
Contract.
9.7.
The Contractor must respect and adhere to the legislation and regulations in
force in the country of the Contracting Authority and must ensure that its
personnel, persons dependent on the Contractor and its local employees also
respect and adhere to said legislation and regulations. The Contractor must
compensate the Contracting Authority for any claims or legal actions arising
out of any breach of said legislation and regulations on the part of the
Contractor, its employees or anyone dependent upon them.
9.8.
SECTION 6
- 146 -
9.9.
10.6. The Contracting Authority must provide sufficient numbers of duly qualified
operation and maintenance personnel and must carry out all works and
services of any kind, including those required by the Contractor in order to
properly carry out inspections and trials prior to start-up, within the time
period specified in the Performance Schedule and in the manner set out
therein or in any other way agreed between the Contracting Authority and
the Contractor.
SECTION 6
- 147 -
10.7. The Contracting Authority shall receive the Cold Storage Rooms for Meat and
Associated facilities as per Incoterms 2010 and to sign off the Goods
Delivery Certificate according to Article 28 (Delivery, Transport and
Insurance of Goods) of these General Conditions of Contract.
10.8. The Contracting Authority shall issue the practical completion of the Project
subject of this Contract, undertaking to attend tests and provisional
acceptance acts convened, and to sign off the Handing Over Certificate
according to Article 39 (Handing Over) of these General Conditions of
Contract.
10.9. The Contracting Authority shall issue the final acceptance of the Project
within a maximum period of 12 (twelve) months, calculated from the date
the Handing Over Certificate is issued, undertaking to attend final
acceptance acts convened and to sign off the Final Acceptance Certificate
according to Article 43 (Final Acceptance) of these General Conditions of
Contract.
SECTION 6
- 148 -
12.3. .To the extent that the Contracting Authority considers all or part of the
aforesaid artificial impediments or physical conditions to comprise
unforeseeable circumstances for an experienced Contractor, the Contractor
shall be entitled to:
i) an extension to deadline with regard to any such delays, as established
in Article 20 (Extension of Execution Period) of these General Conditions;
or
ii) Propose amendment of the Contract.
12.4. After having received the aforesaid notice and having inspected or
researched the physical conditions, the Contracting Authority shall then,
having previously notified Polish Government, decide to what extent the
physical conditions concerned were in fact unforeseeable and whether the
matters described under above Articles 12.1, 12.2 and 12.3 may have had
anything to do with the unforeseeable nature of it.
12.5. Any amendment or modification of the Contract by virtue of this Article must
have the prior approval of The Polish Government, pursuant to Article 22
(Amendments) of these General Conditions of Contract.
12.6. Tied Aid Fund may not be used to finance any extra costs arising out of the
amendments carried out by virtue of this Contract.
SECTION 6
- 149 -
13.5. To show the origin of the Goods, the Contractor must submit an original
certificate of origin (from Polish Chamber of Commerce if the certificate is
obtained in Poland) of the Goods at the time of shipment. Failure to comply
with this obligation will imply termination of the Contract. The Contracting
Authority of the Government of the Republic of Kenya, or its designated
representative, may require more detailed information from the Contractor
about compliance in this regard.
13.6. The origin of Goods will be ascertained pursuant to Community Customs
Code (European Community Council (ECC) Regulation No 2913/92) and
other implementation regulations (European Commission (EC) Regulation is
No 2454/93).
13.7. For Purposes of this Article "origin" of the Goods or Services must be
determined according to the nationality of the provider of the Goods and
Services.
14. Insurances
14.1. The Contractor must take out and keep in force at its own expense,
throughout the Execution Period of the Contract, insurances established as
follows:
a.
b.
c.
14.2. The Contractor must take out insurance to cover its liability with regard to
accidents at work arising in performance of the Contract and public liability
with regard to persons employed by the Contractor, by the Contracting
Authority and by the employees of said authority at the works. Insurance
cover with regard to personal injury must be unlimited.
SECTION 6
- 150 -
14.3. The Contractor must take out a Risk and Public Liability insurance to cover
third-party damages for acts or omissions on the part of the Contractor or of
another for whom the Contractor is responsible, their executors or
representatives. The Contractor must furthermore ensure that all its
subcontractors take out similar insurance.
14.4. All the insurances referred to in this Article must be taken out at the time of
issuance of the Site handing over Certificate. The insurances must be
effective from the date the Contract comes into force and continue in force
up until the Final Acceptance Certificate is issued. The Contractor must
submit the insurance policy to the Contracting Authority and provide
evidence of being up-to-date with payments of premiums whenever required
to do so by the Contracting Authority.
14.5. Without prejudice to Contractor obligations with regard to insurance as
provided for under this Article, the Contractor shall be the only party
responsible and shall compensate the Contracting Authority with regard to
any third party claim for material or personal damages as arising out of
performance of the Contract by the Contractor, its subcontractors or its
employees.
CONTRACT PRICE AND PAYMENT
15. Price
15.1. The Contract price will be as specified under Article 2 (Price) of the Contract
Agreement.
15.2. The Contract price is deemed to be a fixed non-reviewable price.
15.3. The Contractor is deemed to have accepted the Contract price as correct and
sufficient and, unless otherwise provided in the Contract, the price must
cover all the Contractor contractual obligations.
SECTION 6
- 151 -
SECTION 6
- 152 -
17.9. The Performance Security will be released after a period of 28 (twenty eight)
days after the date of issue of the Practical Completion Certificate of the
Project. In the case the Contractor may request a Practical Completion
Certificate for each Cold Storage Rooms for Meat and Associated facilities,
the Performance Security will be released after a period of 28 (twenty eight)
days after the date of issuing the Practical Completion Certificate of the last
Cold Storage Rooms for Meat and Associated facilities.
SECTION 6
a.
b.
c.
d.
e.
any suspension of Works not due to any breach on the part of the
Contractor;
- 153 -
f.
force majeure;
g.
any other grounds for delay referred to in the Contract and not due to
any breach on the part of the Contractor.
20.2. Any request on the part of the Contractor to extend the Execution Period
must be for a just and reasonable period in all circumstances and must fairly
reflect the delay or impediment suffered by the Contractor.
20.3. The Contractor shall be entitled to an extension of the Execution Period in
any event not attributable to the Contractor which implies a delay or
impediment for the Contractor to comply with the Execution Period initially
established.
20.4. Unless otherwise specifically provided in Contract, the Contractor must
submit a notice of application to extend the Execution Period to the
Contracting Authority, together with details of the event or circumstance
justifying the particular extension as soon as reasonably possible after the
event or circumstance concerned commenced. The Contracting Authority
and the Contractor will agree the duration of the extension as soon as
reasonably possible after the aforesaid notice and details supporting the
application have been received.
20.5. The Contractor shall make reasonable efforts at all times to keep any delay
in compliance with its obligations pursuant to the Contract to a minimum.
20.6. Any extension of the Execution Period agreed by the Contracting Authority
must be approved in advance by the Government of Poland, according to the
procedure established in Article 22 of these General Conditions of Contract.
If each of the Cold Storage Rooms for Meat and Associated facilities was
subject of a partial handing over, then the stipulated compensation may be
reduced in the proportion represented by the value of the accepted part
with regard to the total Contract value.
21.3. In the event that failure to comply with handover of part of the delivery of
the Goods, provision of the Services or execution of Works prevents the
Project from being used in a normal manner, then the stipulated
compensation will be calculated on the basis of the total Contract value.
SECTION 6
- 154 -
21.4. If the Contracting Authority is entitled to claim up to 10% (ten per cent) of
the Contract price, then it may, having provided written notice to the
Contractor:
a.
b.
terminate the Contract, and in that event the Contractor shall not be
entitled to claim any compensation whatsoever;
21.5. In the event that the Contractor fails to complete the Project within the time
period specified in the Contract, or fails to handover the Project in
operational conditions pursuant to the Performance Schedule agreed, due to
an event of Force Majeure as defined in article 46 (Force Majeure), the
Contracting Authority shall not be entitled to claim any penalties or request
any compensation to the Contractor for the damages incurred under the
provisions of this clause.
22. Amendments
22.1. The Contracting Authority may order any changes to the scope of the
Contract as necessary for the good outcome and operation thereof, as long
as there is no variation to the total Contract price as a result of the
particular change.
22.2. Prior to issuing any instruction to carry out a change, the Contracting
Authority must notify the Contractor of the nature and manner of the
change. The Contractor must, as soon as possible after having received the
notice, submit a proposal to the Contracting Authority setting out:
a.
a description of the tasks to be carried out, as the case may be, or the
measures that must be taken, financially and time related, together
with a Performance Schedule;
b.
22.3. The Contracting Authority must, after having duly received the proposal
from Contractor as referred to under the Article 22.2 above, decide as soon
as possible whether the modification should be implemented or not.
22.4. Any change or modification of the Contract must be set down in writing in
the form of an Addendum and must be approved in advance by the Polish
Government, duly attached to this Contract is deemed to form part thereof
to all effects.
22.5. The financial resources of the Tied Aid Credit may not be used to finance any
extra costs arising out of modifications carried out by the Contracting
Authority.
SECTION 6
- 155 -
23. Suspension
23.1.
If the Contracting Authority so requires, the Contractor must suspend
execution of all or part of the Contract for the time period and in the manner
deemed necessary by the Contracting Authority. The Contractor shall,
throughout the suspension period, take all such measures as necessary in order
to protect the Goods or the part of the Cold Storage Rooms for Meat and
Associated facilities already executed, and also the Project Site, against
deterioration, loss or damage. Any suspension of the Contract must be
approved in advance by the Polish Government.
23.2. Any additional costs caused by such protective measures will being incurred
as payable by the Contracting Authority unless the suspension:
a.
b.
c.
d.
23.3. The Contractor will not be entitled to reimbursement of any costs unless it
has duly notified the Contracting Authority of its intention to claim such
costs within a period of 30 (thirty) days from the date on which the order to
suspend execution of the Contract was received. The Contracting Authority
must decide the amount payable for such costs and/or the duration of the
extension of Execution Period that it considers fair and reasonable to grant
the Contractor when considering the claim.
23.4. If the suspension period exceeds 180 (one hundred and eighty) days and as
long as the suspension is not due to any breach on the part of the
Contractor, then the latter, by providing notice to the Contracting Authority,
may request permission to restart the Contract execution or to terminate it
within a period of 30 (thirty) days.
23.5. Financial resources from the Tied Aid Credit may not be used to finance any
extra costs arising out of such suspensions carried out by the Contracting
Authority and not the fault of the Contractor.
23.6. If any errors or material irregularities or fraud come to light during the
award procedure, upon entering into or executing the Contract, then the
Contracting Authority may suspend execution of the Contract concerned.
The purpose of such suspension of Contract is to ascertain the truth extent
of such errors or material irregularities or alleged frauds. In the event that
these are not confirmed, then execution of Contract will re-commence
following verification.
SECTION 6
- 156 -
24. Representatives
24.1. The Contractor may designate a qualified professional as a Project Manager
having the qualifications and experiences specified in the Technical Proposal.
24.2.
SECTION 6
- 157 -
the order in which the Contractor proposes to carry out the Project;
b.
c.
d.
25.2. Unless the Contracting Authority informs the Contractor within 7 (seven)
days of receipt of the Performance Schedule, as to which schedule items are
not in compliance with the Contract, then the Contractor must work in
accordance with the schedule provided and subject to further obligations
deriving from the Contract.
25.3. Approval of the Performance Schedule by the Contracting Authority shall not
release the Contractor from any of its contractual obligations.
SECTION 6
- 158 -
26. Design
26.1. General Design Obligations
26.1.1 The Contractor carries out and is responsible for the layout designs.
The Designs must be carried out by qualified professionals according
to the Technical Proposal and the Technical Requirements. Equally,
the Contractor must draw up technical documents required pursuant
to the modalities defined in the Contract, the Technical
Requirements and the Technical Proposal.
26.1.2 The layout designs must be submitted for approval to the
Contracting Authority according to the Performance Schedule and
be corrected at the expense of the Contractor in order to meet the
Technical Requirements of the Contracting Authority as well as the
Technical Proposal, eliminating any errors, omissions, ambiguities,
including incoherencies and any other flaws.
26.2. Specifications and drawingsTechnical Documents
26.2.1 The Contractor must carry out the Design to include all drawings,
specifications and any other technical documents pursuant to the
provisions set down in the Technical Requirements, the Technical
Proposal and, wherever not specified, pursuant to good engineering
practices, together with all documents as necessary for compliance
with legislation and regulations in force. The Contractor technical
documents comprising the plant layout designs must include
documents that define the Project and particularly:
SECTION 6
Description;
Calculations annexes;
Detailed drawings;
- 159 -
SECTION 6
- 160 -
SECTION 6
- 161 -
28.2. The Contractor shall verify that all Goods to be imported into Kenya comply
with the regulations established by the Kenyan Bureau of Standards (KEBS),
and any other applicable standard in the Republic of Kenya
28.3. The Contractor will request authorisation to the Contracting Authority prior
to delivery of the Goods, providing by fax and/or email, all details related to
the delivery including: number of Contract, name and specification list of
delivery subject, quantity, number and date of specific transportation
document, delivery date and expected arrival date.
28.4. The Contracting Authority must forward authorisation for the particular
shipment to the Contractor within a period of 7 (seven) days, by fax or
electronic exchange of data. The Contractor may not proceed to ship or
dispatch the Goods without such official prior authorisation from the
Contracting Authority.
28.5. The Contractor must deliver the Goods to the Project Site as per the
Incoterms 2010 conditions, as established in the Performance Schedule. The
Contractor, for that purpose, undertakes to carry out the following tasks:
28.5.1 The Contractor must package the Goods as necessary to prevent
any damage or deterioration during transport to the Project Site.
The packaging must be suitable and able, without limitation, to
withstand damage and careless handling, exposure to extreme
temperatures, salt and rainfall, and storage in open spaces.
The distance to the Project Site and lack of heavy duty loading and
unloading equipment at all points where the Goods must be
transhipped should be taken into account, as appropriate, when
considering the size and weight of packages.
28.5.2 Packaging, identifying marks and documents placed both inside and
outside the packages must strictly comply with any special
requirements expressly stipulated in the Contract and any other
requirement, if any, established under the Technical Requirements,
Technical Proposal as well as any applicable legislation.
28.5.3 Provide and pay for the cost of prior inspection of Goods, as stated
in Article 30 (Inspection of Goods prior to Dispatch) of these
General Condition of Contract to check that they meet the quantity,
quality and characteristics agreed in the Contract.
28.5.4 The Contractor must transport Goods as well as the Contractor
Equipment to the Project Site including the unloading on its own
account and at its own risk by any means of transport that the
Contractor deems appropriate bearing in mind all the particular
circumstances.
28.5.5 The Contractor must communicate a description of Goods and where
appropriate of Contractor Equipment after each dispatch to the
Contracting Authority, including the name of vessel, port and any
other information deemed relevant for execution of the Project, by
telex, cable, fax or electronic exchange of data and notify the place
and manner of dispatch, as well as the estimated date and time and
the place of arrival of the Goods.
SECTION 6
- 162 -
SECTION 6
- 163 -
28.8. The Contractor must guarantee suitable storage of the Goods on Project Site
from the time of delivery thereof up until practical completion of the Cold
Storage Rooms for Meat and Associated facilities.
28.9. Delivery of Goods to the Project Site will be deemed to have been carried
out whenever a Goods Delivery Certificate to the Project Sites, for each
dispatch of Goods, is available and signed by the Contractor and by the
Contracting Authority. In the event, for reasons not the fault of the
Contractor, the Contracting Authority neither issues the aforesaid Goods
Delivery Certificate nor rejects the Contractor request within a period of 15
(fifteen) days, then the Certificates will be deemed to have been issued on
the last day of that time period.
29.Care of the Cold Storage Rooms for Meat and Associated facilities
29.1.
The Contractor is liable for the care and safeguarding of Cold Storage
Rooms for Meat and Associated facilities and Works or any part thereof up
until such a time as the Provisional Acceptance Certificate is issued or
deemed to have been issued. The Contractor must make good any loss or
damages incurred to the Goods or Works during this period at its own cost.
SECTION 6
- 164 -
The percentage in the terms of finance and time compared with the
percentage of completion planned in the Performance Schedule of each
particular activity; and
b.
SECTION 6
- 165 -
33.3. The Contracting Authority must obtain any local, regional or national permits
required by the Contractor to export the Contractor Equipment brought in by
the Contractor for use in executing the Contract and no longer required for
that purpose.
34. Labour
34.1. The Contractor must use sufficient numbers of personnel all having the
necessary qualifications as necessary in order to guarantee the normal
progress and satisfactory execution of the provisions subject of the Contract.
The Contractor must immediately replace any employees who, in the opinion
of the Contracting Authority, may have a detrimental effect on satisfactory
execution of the Contract. The Contracting Authority must inform the
Contractor for that purpose, by letter setting out the reasons, which must be
appropriate. It is up to the Contractor to take the necessary measures to
contract all personnel and labour.
34.2. The Contractor must, at all times whilst the Contract is in progress, do
everything possible to prevent any illegal, excessive or turbulent conduct or
behaviour on the part of its employees and of its subcontractors workers.
34.3. The Contractor must adhere to labour laws applicable to its employees,
paying them adequately and acknowledging their legal rights.
35. Clearance of the Cold Storage Rooms for Meat and Associated facilities area
35.1. The Contractor must keep the Project Site reasonably free of all unnecessary
obstructions throughout the Contract Execution Period, storing or removing
surplus materials and removing any remains, rubbish or provisional works
from the Project Site, together with Contractor Equipment no longer deemed
necessary for execution of the Contract.
35.2. Once the Cold Storage Rooms for Meat and Associated facilities have been
Installed and Commissioned, the Contractor must remove all remains,
rubbish and waste of any kind from the Project Site and leave the area and
the facilities in a good clean and secure state.
SECTION 6
- 166 -
SECTION 6
- 167 -
37.8. If the Contracting Authority and the Contractor fail to agree with regard to
the results of tests and inspections, then each of them shall send the other a
declaration stating its opinion within a period of 15 (fifteen) days following
the date on which the disagreement arises. The Contracting Authority or the
Contractor may ask that such tests are repeated under the same terms and
conditions, or, if either party so wishes, request the involvement in that
regard of an expert chosen by mutual agreement. All test reports should be
submitted to the Contracting Authority, which must communicate the results
of such tests to the Contractor without delay. Test results will be deemed
conclusive. The cost of repeating tests must be paid for by whichever party
is found to be wrong, pursuant to the aforementioned definitive tests.
37.9. Any extra cost caused under Articles 37.5 and 37.8 above shall not be paid
through the financial facilities of the Tied Aid Fund.
37.10. The Contractor accepts that neither carrying out tests nor inspections of
Goods, Services or Works, nor the presence of the Contracting Authority or
its representative, nor the production of reports pursuant to Article 37.6,
may exonerate the Contractor from any guarantees or other obligations
incumbent upon it by virtue of the Contract.
37.11. The Polish Embassy in the Republic of Kenya or its duly authorized
representatives may be present while such operational tests or inspections
are carried out.
SECTION 6
a.
b.
operational test period, to show that the Cold Storage Rooms for Meat
and Associated facilities or stage thereof is operating satisfactorily in
accordance with the performance established in the Contract.
- 168 -
b.
38.9. In the event that the Contract after suffers any delay or incurs any cost as a
result of the aforesaid delay in Completion Tests within the Contractor must
notify the Contracting Authority of this and shall be entitled to:
a.
b.
38.10. Any extra cost caused under Article 38.9 above shall not be paid through the
financial facilities of the Tied Aid Credit.
38.11. Prior to carrying out Completion Tests, the Contractor must provide
sufficiently detailed operating and maintenance manuals duly adapted for
the beneficiary personnel in such a manner as to permit the Contracting
Authority to start up, maintain, adjust and repair all parts of the Plant or
Equipment. Unless otherwise provided for within the Contract, manuals must
be in the Contract language. The Contract will not be deemed completed for
the purposes of Practical completion until such a time as the aforesaid
manuals have been delivered to the Contracting Authority.
SECTION 6
- 169 -
b.
refuse the request, expressing the grounds for this and specifying what,
in its opinion, the Contract must do for the certificate to be issued.
SECTION 6
- 170 -
40.2. The Warranty Period is for 12 (twelve) months from the date of the Practical
Completion Certificate. The Contractor is nevertheless deemed liable for the
solidity of the installation as from the date of Practical Completion, pursuant
to the provisions set down by law in the country where the Project is
located.
40.3. The Contractor shall make the necessary preventive maintenance, visiting
the Cold Storage Rooms for Meat and Associated facilities in order to
warrant and maintain all the Goods in good working conditions and ensure
its proper and efficient use. A maintenance certificate shall be drawn up
after each visit and signed by the person in charge of the equipment and/or
the Cold Storage Rooms for Meat and Associated facilities Chairman.
40.4. If any defect in design, engineering, materials or execution of the Cold
Storage Rooms for Meat and Associated facilities ied out by the Contractor
comes to light during the Warranty Period then the Contractor must, in
consultation and agreement with the Contracting Authority as to the
appropriate manner to correct the particular defects and at its own cost,
immediately repair, replace or correct such defects, as well as any damage
to the Cold Storage Rooms for Meat and Associated facilities caused by said
defects. The Contractor is not responsible for repairing, replacing or
correcting any defect or damage to Cold Storage Rooms for Meat and
Associated facilities that occurs for any of the following reasons:
a.
b.
operation of the Cold Storage Rooms for Meat and Associated facilities
not covered under the requirements provided for in the Contract; or
c.
40.5. Contractor obligations pursuant to this Article do not apply to the following:
a.
b.
40.6. The Contracting Authority must inform the Contractor of the nature of the
aforesaid defects and provide the Contractor with all available tests carried
out in that regard promptly following the discovery of the defects. The
Contracting Authority will provide the Contractor every reasonable
opportunity to inspect the defects concerned.
40.7. The Contracting Authority will permit the Contractor access as necessary to
the Cold Storage Rooms for Meat and Associated facilities and to the Project
Site say that the latter may comply with its obligations under this Article.
SECTION 6
- 171 -
40.8. The Contractor may, with the consent of the Contracting Authority, remove
from the Project Site or from anywhere in the Cold Storage Rooms for Meat
and Associated facilities if defective and if the nature of the particular defect
and/or damage to the Cold Storage for Meat and Associated Facilities and
Accessories caused by defect means that repairs cannot be carried out
expeditiously at the Project Site.
40.9. In the event that repairs, replacements or corrections may have
repercussions on the effectiveness of the Cold Storage Rooms for Meat and
Associated facilities or part thereof, the Contracting Authority may, by
notifying the Contractor, require the latter to carry out necessary tests as
soon as the repair works are completed and the Contractor will carry out
tests at that time.
40.10. If the test results are not satisfactory, the Contractor must carry out the
repairs, replacement or corrections (as the case may be) until these are in
accordance with the Contract Technical Requirements, pursuant to the
procedure established in Article 37 (Inspections and Tests) of these General
Conditions of Contract.
40.11. If the Contractor fails to commence works necessary to correct such defects
or damage to the Cold Storage Rooms for Meat and Associated facilities
caused by the defect within a reasonable period of time (never deemed to
be less than 15 (fifteen) days), then the Contracting Authority, after having
notified the Contractor, may proceed to carry out such works. The
Contractor must pay the Contracting Authority any reasonable costs incurred
by the Contracting Authority in that regard or else they may be claimed by
virtue of the Performance Security.
40.12. If the Cold Storage Rooms for Meat and Associated facilities or any part
thereof cannot be used due to the particular defects and/or corrections
thereof, then the Warranty Period will be extended by a period equal to the
period that the Cold Storage Rooms for Meat and Associated facilities or part
thereof, could not be used by the Contracting Authority due to any of the
aforementioned reasons. The latter may require the Contractor either to
increase the amount of the Performance Security in an amount equal to the
cost of replacing the assets or to provide a further appropriate guarantee.
SECTION 6
- 172 -
42. Training
42.1. The Contractor must be responsible for training the personnel of the
Contracting Authority with regard to operation and maintenance of the Cold
Storage Rooms for Meat and Associated facilities and as specified in the
Contract.
42.2. The training must take place prior to the takeover of the Plant. The training
should be running in the course of the installation and commissioning of the
Cold Storage Rooms for Meat and Associated facilities. The Cold Storage
Rooms for Meat and Associated facilities will not be deemed complete for the
purposes of handing over until such training has been provided.
42.3. In addition a brush-up training shall be carried out by the Contractor at least
6 (six) month after the Provisional Acceptance date, during the warranty
period, and shall be compulsory in order to get the Final Acceptance
Certificate conformed.
42.4. The training programme shall include specific courses regarding to the
following horticultural value chain actors: Plant technicians, Plant artisans,
Meat farmers, packers, transporters and other handlers.
42.5. The Contractor shall adapt their training to the specific needs and
requirements of the personnel in charge of the operation and maintenance
of the equipment. The Contractor shall combine different approaches and
teaching methods to obtain the highest possible level of efficiency of the
equipment and methods.
42.6. When training the personnel, the Contractor shall take into account, as part
of their methodology, the following:
a.
b.
c.
42.7. In order to facilitate the training programme, the Contracting Authority shall
be responsible of providing on time qualified personnel for the training
stage.
42.8. The Contracting Authority must issue a Practical Completion Certificate of
completion of the Training Services.
SECTION 6
- 173 -
b.
44.3. Compensation for damages as established under Article 44.2 may comprise:
a.
b.
44.4. Amounts will be paid over with regard to the compensation as provided for
in Article 44.3 above, and applying the measures provided for within the
Contract with regard to breach on the part of the Contractor, by deduction of
the corresponding amount from the Performance Security.
SECTION 6
- 174 -
44.5. Whenever termination of the Contract is due to a breach that is the fault of
the Contractor or of the Contracting Authority, then the party harmed by the
breach shall in its own right be entitled to request compensation for
damages incurred.
b.
c.
Mutual agreement
Contractor;
d.
e.
f.
g.
h.
i.
between
the
Contracting
Authority
and
the
45.2. This Contract will be automatically terminated in the event that it does not
give rise to any payment over a period of 3 (three) years from the date of
signing.
SECTION 6
- 175 -
46.2. For the purposes of this Article, force majeure is deemed to have refer to
strikes, lockouts or any other legal disputes, actions by delinquents, wars,
whether declared or not, blockades, insurrection, revolts, epidemics,
landslides, earthquakes, storms, lightening, floods, slippages, social unrest,
explosions or other similar unforeseeable circumstances beyond the control
of either party and which could not be overcome despite their diligent
efforts.
46.3. If the Contracting Authority or Contractor considers that circumstances of
force majeure have occurred which might affect compliance with their
obligations, they must notify this without delay to the other party providing
details as to the nature thereof, the probable duration and expected
repercussions of that circumstance. Unless otherwise instructed in writing by
the Contracting Authority, the Contractor must continue to comply with its
obligations pursuant to the Contract to the extent that it is reasonably
possible to do so and must seek all possible alternatives to comply with its
obligations not affected by a circumstance of force majeure. The Contractor
may not put such alternative methods into practice unless required to do so
by the Contracting Authority.
46.4. In the event that circumstances of force majeure persist for a period of more
than 180 (one hundred and eighty) days, without prejudice to any possible
extension to the time period completion of the Contract that may have been
granted to Contractor by reason thereof, each of the parties shall be entitled
to notify the other party that the Contract is terminated within a period of
30 (thirty) days. When that deadline has expired, if the circumstances of
force majeure persist then the Contract will be deemed terminated and the
parties therefore released from the obligation to continue to execute the
Contract.
SECTION 6
- 176 -
DISPUTE RESOLUTION
The aforesaid prohibition also applied, as the case may be, to any other
projects with regard to which the Contractor due to the nature of the
particular Contract may also find itself in a conflict of interest scenario.
48.3. The Contractor must, at all times, act impartially and with honour pursuant
to its professional code of ethics. The Contractor must refrain from making
any public statements regarding the Project without prior approval from the
Contracting Authority and may not in any way compromise the Contracting
Authority without its prior consent in writing in that regard.
48.4. Throughout the Contract execution period, the Contractor and its personnel
must respect human rights and undertake not to contravene and political,
cultural or religious customs of the beneficiary country.
48.5. The Contractor may not accept any payment with regard to the Contract
other than as provided therein. The Contract and its personnel must refrain
from carrying on any business activity or from receiving any bonus that may
be in conflict with its obligations towards the Contracting Authority.
SECTION 6
- 177 -
48.6. The Contract and its personnel are deemed subject to professional secrecy
throughout the duration of the Contract and beyond its termination. All
reports and documents received or drawn up by the Contractor having to do
with the Contract are deemed confidential.
48.7. Use by the contracting parties of all reports and document drawn up,
received or issued during execution of the Contract is governed by the
conditions set out therein.
48.8. The Government of the Republic of Poland reserves the right to suspend or
cancel finance of projects if any kind of corruption is discovered at any stage
of the award process or if the Contracting Authority fails to take the
appropriate measures to remedy such a situation.
48.9. Unusual commercial costs are deemed to refer to any commission not
referred to in the Contract or not arising from a valid contract referred to
within the Contract, any commission that is not payment in consideration of
a an effective legitimate service, any commission paid in a tax haven or any
commission paid to a beneficiary that is not clearly identified or to a
company that appears in all regards to be a front company.
48.10. The Contractor undertakes to provide the Government of the Republic
Poland through its representative in Nairobi and also to any persons
appointed by them, at the request of the latter, all documents as evidence
of compliance with the Contract performance conditions. The Government of
the Republic of Poland may carry out all manner of checks on documents
and to sites and at the Contractor head office or that of its subcontractors as
it may deem necessary in order to gather evidence to corroborate any
suspicion that unusual commercial costs may have occurred.
SECTION 6
- 178 -
50.2.
50.3. The Contractor agrees that the rights of the Government of the Republic of
Poland to carry out audits, checks and verifications equally apply, under the
same conditions and according to the same modalities as provided under
this Article, to any subcontractor or any other party benefitting from the
Polish funding.
50.4. The judges, courts and administrative authorities will not be entitled, due to
debts of the Contracting Authority or of the Contractor of the Project
financed and claimable in Polish territory, issue any order for execution or
seizure against the rights, funds and values product of the carrying out,
liquidation and payment by the Polish granting authority or its financial
agent, of the loans and credits charged against the Tied Aid Agreement.
SECTION 6
- 179 -
ANNEXES
Annex I Bank Guarantee
Performance Security Form
Date: [state Bid submission date (day, month and year)]
No ____: [state the Bidding Process number]
To: [state full name of the Contracting Authority]
[The bank, at the request of the Successful Bidder, must complete this form in
accordance with the instructions given]
Bank Branch or Office [full name of Guarantor]
PERFORMANCE SECURITY No.:
We have been informed that [insert complete name of Contractor] (hereinafter called
"the Contractor ") has entered into Contract No. [Insert number] dated [insert day and
month], [insert year] with you, for the performance of the Project "Installation, Testing
and Commissioning of Cold Storage Rooms for Meat and Associated faculties
(hereinafter called "the Contract").
Furthermore, we understand that, according to the conditions of the Contract, a
Performance Security is required.
At the request of the Contractor, we hereby irrevocably undertake to pay you any sum(s)
not exceeding the 10% (ten percent) of the Contract Price [insert amount in figures
and words] upon receipt by us of your first demand in writing declaring the Contractor
to be in default under the Contract, without civil or argument, or your needing to prove
or to show grounds or reasons for your demand or the sum specified therein.
This Performance Security shall expire no later than 28 (twenty eight) days after the date
of the Practical Completion Certificate issued by the Contracting Authority and any
demand for payment under it must be received by us at this office on or before that date.
In the case the Contractor may request a Practical Completion Certificate for each Cold
Storage Rooms for Meat and Associated facilities, the Performance Security will be
released after a period of 28 (twenty eight) days after the date of the Practical
Completion Certificate issued by the Contracting Authority of the last Cold Storage
Rooms for Meat and Associated facilities handed over.
This Performance Security is subject to the Uniform Rules for Demand Guarantees, ICC
Publication No. 758.
SECTION 6
- 180 -
SECTION 6
- 181 -
SECTION 6
- 182 -
SECTION 6
- 183 -
SECTION 6