List of important documents (SOPS)

QUALITY ASSURANCE
S/N
1

TITLE
Good Laboratory Practice

2.

Document Signatory in the Laboratory

3.

Cleaning in the Laboratory and Glassware used in the Laboratory


area

4.

Workbook Procedure and Validation

5.

Air and Environmental Contamination

6.

Contract Manufacturing and Analysis

Product Complaints

8.

Batch Review

9.

Product Recall

10.

Handling of Returned Drug Product

11.

Preparation of Bench Solutions and Reagents

12.

Preparation and Standardization of Volumetric Solutions and


Reagents

13.

Preparation of Media for Microbiological Use

14.

Disposal of Reagents in the Laboratory

15.

Receiving Manufacturing and Testing Instructions For New Process


from Overseas

16.

Documentation

17.

Batch Documentation

18.

Retesting and Re-sampling of Materials

19.

Handling of Retention Samples

20.

In-Process Inspection of Area

pmgman - audit checklist

21.

Identification of Raw Materials Before Weighing

22.

In-process Control (General)

23.

In-Process Control (Weighing)

24.

In-Process Control (Mixing and Blending)

25.

In- Process Control (Compression)

26.

In-Process Control (Packaging)

27.

Care of Instrument Room

28.

Maintenance, Operation and Calibration of


Weighing Balances

29.

Calibration of Weighing Scales in the Plant

30.

Maintenance and Calibration of Equipment and


Laboratory Instruments

31.

Maintenance, Calibration and Operation of


Dissolution Rate Tester (Type DT6)

32.

Operation and Maintenance of Tablet Hardness


Tester

33.

Validation Exercise

34.

Validation Committee

35.

Analytical Validation

36.

Cleaning Validation

37.

Retrospective Validation

38.

Monitoring of Relative Humidity and Temperature


(Procedure/Validation)

39.

Stability Testing

40.

Audit Check (Packaging)

41.

Evaluating Out-of- Specification (OOS) Laboratory Results

42.

Microbiological Control of Manufacturing

pmgman - audit checklist

Environment
43.

Microbial Analysis of Water Samples

44.

Disinfection of the Floors and Surfaces in the


Manufacturing Areas

45.

Operating Instruction for various lab equipment

45.

Validation Procedure for Autoclave

46.

Tube Coagulase Test

47.

Use and Care of Microscope

48.

Keeping Reference Samples and Standard Cultures

49.

Microbiological Examination of Washed Securitainers

50.

Microbiological Tests for Sterility of Bottles

51.

Sampling of Products for Microbiological Tests

52.

Regulations of the Microbiology Laboratory

53.

Use and Care of various lab equipments

54.

Sampling Plan for Raw Materials & Auxiliaries

55.

In-Process Control (Liquid Packaging)

56.

Annual Product Review

57.

Monitoring and Fumigation of the Manufacturing Areas

58.

in-Process Control (Water)

59.

Sanitization of Water Pipe lines & Storage Vessels

60.

Release of Finished Products for Sale

pmgman - audit checklist

WAREHOUSE
S/N

TITLE

1.

Cleaning Procedure in Warehouse

2.

Storage and Warehousing Conditions

3.

Material and Equipment Handling Procedures

4.

Receiving and Handling of Raw and Packaging Materials

5.

Supply of Raw Materials to Other Party

6.

Collection of Finished Goods

7.

Dispatches of Finished Goods

8.

Safety In Warehouse

9.

Materials Returns Procedure

10.

Storage and Materials Movement ( FIFO Principle )

11.

Air control sampling room

pmgman - audit checklist

PRODUCTION AND PACKAGING


S/N
1.

TITLE
Facilities in the Locker Room

2.

Cleaning of the Changing Room

3.

Painting of Facilities in the Factory (Production Areas)

4.

Entry into Manufacturing Area

5.

Preventing Contamination

6.

Maintenance of Equipment

7.

Fixing Manufacturing Parameter

8.

Batch Identification

9.

Manufacturing and Packaging Protocols

10.

Yield

11.

Coating Operations

12.

Process Validation

13.

Process Change

14.

Re-processing

15.

Retrospective Batch Review

16.

Product Change

17.

Recovered Materials/ Reprocessing

18.

Removal of Waste from Production Department

19.

Weighing Process

20.

Material Flow

21.

Manufacturing Procedures for Various Stages of Production

22.

Manufacturing of New Drug products

pmgman - audit checklist

23.

Cleaning of oven

24.

Transfer of Raw Materials

25.

Cleaning of Manufacturing Utensils and other containers (each)

26.

Cleaning of Stainless Steel containers

27

Cleaning of Floor Drainage Sinks

28

Cleaning Procedure for Different processing areas

29

Cleaning of Aluminium Pallets

30

Line Clearance and Line Release

31

Line Release for Production

32

Written Instructions for Packaging

33

General Hygiene For Packaging Staff

34

Removal of Packaging Waste

35

Packaging Plan

36

Operation of various Machines (individually)

37

Validation of various packaging machines

38

Mistake/Mix-Up/Contamination

39

Printing Exercise

40

Transfer of Finished Products

41

Line Release for Packaging Operations

42

Manual Packaging Line Operation

43

Batch Identification in Packaging

44

Yield Determination in Packaging

pmgman - audit checklist

GENERAL
S/N
1.

TITLE
Guidelines for Writing Standard Operating Procedure

2.

G.M.P Committee

3.

Working Conditions of Personnel

4.

Training

5.

Qualification of Newly Recruited Employees

6.

Follow-up/Refresher Courses

7.

Staff Clinic / first aid

8.

Drug Safety

9.

Guidelines for Self Inspection

10.

Removal of Detergent Residue after Cleaning

11.

Clearing of Septic Tanks

12.

Control Procedure for Pest Control and Fumigation Materials

13.

Pest Control and Fumigation Exercise

14.

Destruction of Materials

15.

Installation and Qualification of Equipment

16.

Manufacturing Prescription

17.

Suppliers Audit

18.

General Principles: Change Handling Procedures

19.

SOP Actualization Programme

20.

Time Limits For Various Processes

21.

Document Change Control & Actualization

22.

Documentation: General Principles

23.

Handling Deviations

pmgman - audit checklist

24.

Treatment of Personnel with Infectious Diseases

25.

Returned Goods

26.

Training on SOP

27.

Protective Clothing Guidelines

28.

Product Recall

29.

Product Complaints

30.

Maintenance and Calibration of Equipment

pmgman - audit checklist

ENGINEERING
S/N

TITLE

1.

Engineering Maintenance Programme

2.

Preventive Maintenance

3.

Preventive Maintenance Programme for the Plant Building

4.

Lubrication

5.

Cleaning and Maintenance of Air Filters in the Manufacturing area

6.

Cleaning of the Generator Plant and the Room

7.

Air Handling Units

8.

Changes/Modification in the Air Handling Unit

9.

Water Treatment Process and Plant Maintenance

10.

Cold room Cleaning, Maintenance and Validation

11.

Maintenance equipments

12.

Boiler Operations

13.

Cleaning of Drainage within Production & Packaging Area

pmgman - audit checklist

LIST OF REQUIREMENTS
1.

Personnel Details

2.

Organogram

3.

List of Products

4.

List of Equipment for Production

5.

List of Equipment for Quality Assurance/Control

6.

Quality Policy

7.

Sample Batch Manufacturing Records (BMR)

8.

Evidence of Training

9.

Evidence of Medical/Clinic Services

10.

Evidence of Medical Check-up

11.

Evidence of Fumigation & Pest Control

12.

Evidence of Food Handling Certification

13.

Evidence of Environment, Health and Safety (EHS) Policy

pmgman - audit checklist

10

QUALITY AUDIT CHECKLIST


INSPECTION OF MANUFACTURING PLANT

INTRODUCTION:
This Quality Audit is performed on behalf of the Pharmaceutical Manufacturers Group of
the Manufacturers Association of Nigeria (PMG-MAN). As an active member of the
Group, we believe that every member company will maintain at least the minimum
standard of the requirements of current Good Manufacturing Practices (GMP) and Good
Laboratory Practices (GLP).
The planning and effective performance of this audit is aimed at ensuring these minimum
standards.
The non-conformities detected during this audit must be corrected within the agreed time
frame.

pmgman - audit checklist

11

QUALITY AUDIT CHECKLIST


INSPECTION OF MANUFACTURING PLANT

Name /Address of Factory:

Product Lines:

Date of Audit:

Auditors:

Audited Persons/Units:

pmgman - audit checklist

12

QUALITY AUDIT CHECKLIST


INSPECTION OF MANUFACTURING PLANT

GENERAL IMPRESSION

pmgman - audit checklist

13

QUALITY AUDIT CHECKLIST


INSPECTION OF MANUFACTURING PLANT

PRIORITY ACTIONS

pmgman - audit checklist

14

QUALITY AUDIT CHECKLIST


INSPECTION OF MANUFACTURING PLANT

pmgman - audit checklist

15

PMG-MAN STANDARD QUALITY AUDIT

QUALITY RATING SYSTEM

RATING

MEANING

INTERPRETATION

Excellent

Item/Area/System/Knowledge is Superior

Adequate

Item/Area/System/Knowledge Meets
Basic Minimum Requirements

Poor

Item/Area/System/Knowledge is weak
and not up to Acceptable Standard

Unacceptable

Item/Area/System/Knowledge is
Missing or of such Nature to Warrant
Serious Quality/Compliance Concerns

pmgman - audit checklist

16

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

SECURITY
1.

Is the environment very clean?

2.

Are the toilets and changing rooms clean and


devoid of offensive odour?

3.

Do the personnel appear neat and properly


dressed?

4.

Is there evidence of regular disposal of waste in


the refuse drum?

5.

Are the windows, walls and floors clean and


properly maintained?

6.

Is there evidence of growth of mould and fungi or


presence of rodents in the area?

pmgman - audit checklist

T I

N
0

REMARKS

N/A

17

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

N
0

REMARKS

N/A

RAW AND PACKAGING MATERIALS


WAREHOUSE
1.

When was the last inspection conducted?

2.

Are the walls, floors and shelves cleans?


Is there absence of rodents, vermin fungi and
mould?
Are there physically separated areas for:
- Raw materials
- Semi finished products
- Packaging materials?
Is there a quarantine area for raw materials and
active ingredients under test?
Is there a separated area for rejected materials?

3.
4.

5.
6.
7.

Are there identification labels on all containers that


have materials in them?

8.

Are the warehouse lightning and ventilation


adequate?

9.

Is there any programme for pest control and is


such documented?

10.

Are there warehouse operating instructions and


procedures and are they followed?

11.

Are untested drug components, drug product


containers and closures separated from the tested
and certified ones?

12.

Is the arrangement of materials in the warehouse


adequate?

13.

Is there evidence of safety consciousness in the


personnel working in this area?

14.

Is incoming materials Quarantined until it is


checked, analysed and released? Is it properly
stored?
Is there sufficient accountability system for labels?

15.
16.

Are there written procedures on inventory control


and reconciliation and are these followed?

pmgman - audit checklist

18

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

17.

18.
19.
20.
21.
22.
23.
24.
25.

TITLE

T I

N
0

REMARKS

N/A

RAW AND PACKAGING MATERIALS


WAREHOUSE
Is there a written procedure describing the
scheduled for retesting of materials in the
inventory and is it followed?
Are the records of retesting available?
Is a separate sampling room available?
Is the sampling room designed to prevent
microbial and/or product contamination?
Is a returned material store available?
Is a cold store available?
Is an area available for storing of reference
samples?
Is a separate room available for explosive
substances?
Is it ensured that for all materials a First in First
out system is followed?

26.

Are all containers legibly and completely labeled?

27.

Are there SOPs describing in detail the receipt,


identification and handling of starting materials,
packaging and auxiliary materials as well as the
status of the material after testing?

28.

Is rejected materials adequately controlled?

29.

Are SOPs available for the general storage and


handling procedures and are these followed?

30.

Are there material storage and handling procedures


documented?

31.

Are SOPs available describing the material flow to


manufacturing areas and vice-versa and are these
followed?

32.

Are obsolete and outdated materials destroyed?


Any record of such destructions?

pmgman - audit checklist

19

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT
GUIDE
LINE
No.

TITLE
FINISHED GOODS WAREHOUSE

1.

When was the last inspection conducted?

2.

Are the walls, floors and shelves cleans?


Is there absence of rodents, vermins, fungi and
mould?
Are there physically separated areas for:
- Finished goods
- Returned items?
Is there a separated area for rejected materials?
Are there identification labels on all containers that
have materials in them?

3.
4.

5.
6.
7.

Is there any programme for past control and is


such documented?

8.

Is the arrangement of materials in the warehouse


adequate?

9.

Is there evidence of safety consciousness in the


personnel working in this area?

10.

Do distribution records indicate the:


- Name and address of the consignee
- Loading date
- Name, quality and control number of the item?
Is the establishment system sufficient to facilitate
the recall of the finished product, if necessary?

11.
12.

Is there materials nearing expiry?

13.

Are such materials reported for necessary action?


Any written evidence?

14.
15.
16.

Has a positive action been taken?


Are warehouse lighting and ventilation adequate?
Are different batches of finished products
separated physically?

17.

Is there a system to ensure that only products


released for sale are distributed?

18.

Are the trucks conveying the goods to their


destinations able to project the goods from rain
and sunshine?

pmgman - audit checklist

T I

N
0

REMARKS

N/A

20

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
PRODUCTION AREA - LIQUIDS
WEIGHING

1.

Are raw materials properly identified during


weighing?

2.

Is the weighing area clear of other materials that


are not necessary for this operation?

3.

Are materials for weighing checked physically


before and after? Are such checks confirmed by
a second person and such record weighed?

4.

T I

N
0

REMARKS

N/A

Is the balance for the weighing the appropriate


one for the material(s) being weighed?

5.

Are there records for the periodic calibration of


the balances in the weighing room?

6.

Where measurement instead of weighing is


involved are the appropriate containers used?
Are there such containers well calibrated?

7.

Are the personnel wearing appropriate uniforms


for the operation - Nose masks, Hand gloves,
Safety-shoes etc?

8.

Is there any personnel in the weighing area that has


open sore or lesion that may pose problem to the
product under processing?

9.

Is there any material in the weighing area that can


shed fiber or other contaminations or wooden
pallets and are such close to clean containers?
MIXING

10.

Is the production area effectively ventilated with


filtered air?

11.

Are there systems for processing and transfer that


can protect the products from contamination?

12.

Are Tanks, Containers, Pipe works and Pumps


designed and installed to facilitate easy cleaning
and sanitation if necessary?

pmgman - audit checklist

21

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
MIXING

13.

Any device to ensure that materials transferred


through pipes are delivered to their correct
destination?

14.

Are there presence of materials likely to shed


fibers into the mixing tank(s) in the preparation
area?

15.

Are all processes documented at the time of


performance?

16.

Is there a step-by-step procedure for this operation


and is such a protocol followed?

17.

Where procedures are altered, are such alterations


recorded and reasons adduced for the alterations?

18.

Are there records of unplanned deviations from


manufacturing specifications? Are such brought to
the attention of the head of Quality and
Production?

19.

Are laid down criteria for acceptance of such


deviations devised by the Quality Control?

T I

N
0

REMARKS

N/A

FILLING
20.

Are the glass bottles maintaining an appropriate


degree of cleanliness at the time of filling?

21.

Any device to detects presence of particulate


matter in the bottle before and after filling and is
such a device effected? If bright background
illumination is used, are observers changed
frequently?

22.

Is the working area where liquids are prepared


disinfected periodically and records of such kept?
Is efficacy of such disinfectant assured?

23.

Are the filling constantly monitored to assure


uniformity of volume?

24.

Are there constant physical inspections of closures


for firmness or otherwise?

pmgman - audit checklist

22

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

LABELLING AND PACKAGING


25.

Is the labeling constantly monitored and rough


and squeezed ones on the containers replaced
manually?

26.

If labeling is not automated, are the filled bottles


properly stored and identified awaiting manual
labeling?

27.

Is the Batch Packaging Record employed at the


time of exercise and are appropriate
documentation made?

28.

Are any deviations from the standard operating


procedures for packaging documented?

29.

Is there adequate separation of packaging lines to


avoid mix-up?

30.

Is Batch identity maintained throughout the


packaging operation?

31.

Are there records of reconciliation for quantity of


packaging material issued, used, destroyed and
returned?

pmgman - audit checklist

T I

N
0

REMARKS

N/A

23

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
PRODUCTION AREA - TABLETTING

1.

2.

Is dust extraction device available at an


appropriate area and is it functional?

4.

Do the personnel use the protective clothing


(gloves, caps, nose masks, etc) in these working
areas?

5.

Are the personnel clothing clean?

6.

Is there absence of other materials not necessary


for operation in?
- Weighing
- Mixing
- Granulation and
- Tableting rooms

7.
8.

Are the utensils in-use clean?


Are these utensils kept in an adequate place free
from contamination?

9.

If weighing was carried out during the


inspections, are the containers of raw materials to
be weighed cleaned before being opened?
During weighing, are weights and raw materials
double-checked and is the in-process inspector
present?
Are raw materials and components for each batch
segregated after weighing?

11.
12.

13.

T I

N
0

REMARKS

N/A

Are the following areas clean?


-Weighing room
- Mixing room
- Granulation
-Tableting room
-Washing room
Are lighting and ventilation adequate in:
- Weighing
- Mixing
- Granulation and
- Tableting areas

3.

10.

Does these identification include


- the name of raw materials
- the batch number of the raw material
- the quantity that was weighed
Are weighing record sheets filled and duly signed
during weighing?

pmgman - audit checklist

24

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
PRODUCTION AREA

14.

Are processing areas clean and properly


maintained according to standard operating
procedures?

15.

Is the air supply system for all processing areas


adequate to eliminate cross-contamination of drug
products?
Are equipment identified as to their status (clean,
duty, batch contents)?

16.

17.
18.

T I

N
0

REMARKS

N/A

Are written operating procedures for equipment


readily available to operators and are they in-use?
Are written procedures available for cleaning,
maintenance and sanitizing of equipment?
Are they followed?

19.

In mixing and granulation rooms is the adding of


raw materials components verified separately by
two individuals? Is it documented at the time of
performance? Any records?

20.

Are there physical separation or other measures to


avoid cross-contamination during production of
different batches and different products?
Is there any lesion or wound on any operator
handling materials which can affect the product
adversely?
Are correct documentations done in the batch
manufacturing protocols at the time of
performance of operations?

21.

22.

23.
24.
25.
26.
27.

Are there adequate areas for the orderly storage of


semi-finished and bulk products?
Do SOPs exist for the cleaning of the various
equipment and machines used in the production
area? Are they followed?
Does SOP exist for reprocessing of production?
Are frequent calibration and servicing of balances
performed and documented?
Are BMPRs kept at the work stations during the
entire operation?

pmgman - audit checklist

25

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
PRODUCTION AREA

28.

Are Master and BMPRs properly assembled?

29.

Are process parameters for each step laid down in


writing?

30.

Are yield limits established at each significant step


of production?

31.

Are all yield calculations and reconciliations


documented in the BMPRs?
Are adequate procedures utilized to reconcile the
quantities of starting materials issues, used and
returned, are these followed?

32.

33.
34.
35.

36.

37.

T I

N
0

REMARKS

N/A

Are written product related in-process control


procedures available?
Is the processing procedure approved by Quality
Control/Quality Assurance?
Is change control performed in the case of:-Changes in starting Materials?
- changes in packaging materials?
- changes in processes?
- changes in equipment
- change of standard batch size?
- changes in production area and support
system?
- changes in environmental conditions
- changes in suppliers
Unexpected changes
Are products quarantine between their
manufacture and packaging
Are products quarantine between their
manufacture and release
Do these manufacture/Packaging protocols include
the followings: - and control records include also
the followings: - Name and strength of the product?
- Description of the dosage form?
- Batch product number and pack size?
- Name/weight (measure) of each ingredient
per dosage form?
- Total weight (measure) of each dosage unit?
- Standard batch size?
Specifications and compendia reference of
ingredients?

pmgman - audit checklist

26

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
PRODUCTION AREA

38.

Any calculated excess ingredient and packaging


materials?
- Statement of theoretical weight (measure)
quantity at appropriate phases of
manufacturing?
- Statement of theoretical yield at appropriate
phases of manufacturing, including the
minimum and maximum allowed limits?

39

Date of preparation (initiation of operation) of the


updated Master Formular edition number?
- Date and edition number of updated, original
product
and manufacturing prescriptions?
- Product related procedures?
- Statement of important steps to be signed during
manufacturing?
- Product related precautions to be followed
- Process related precautions to be followed
- Product environmental specifications, where
applicable?
-Procedure for handling equipment and machines?
- Cleaning Procedures?
- In-process control procedures?
- In-process bulk and drug product specifications?
- Specification of primary and other packaging
materials?
- Quantity (weight) of packaging materials per
dosage form?
- Total quantity (weight) of packaging materials
per batch?
- Packaging and labeling procedures?
- Quality Assurance/Quality Control approved
specifications?
- Quality Assurance/Quality Control approved and
testing procedures? sampling
- Storage conditions?
- Shelf life information?

40.

Are the manufacturing/Packaging Protocols, dated


and signed by responsible person?

41.

Are all the signatures full and hand written?

pmgman - audit checklist

T I

N
0

REMARKS

N/A

27

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
PACKAGING - BLISTERING

1.

Is the blistering hall clean and orderly managed?

2.

Is the blistering hall having adequate lighting and


ventilation?

3.

Are the batch packaging records kept at the work


stations during the entire operation?

5.

Is the printing room clean and well arranged?

6.

Is one product printed at a time?

7.

Is there line identified for such a product?

8.

Is there risk of labels/inserts mix-up?

9.

Are the personnel wearing appropriate uniforms in


performing their duties?

10.

Are the personnel in packaging hall wearing neat


uniforms?
Is each packaging line identified with product
name, packaging size and batch number?
Is there only one product, batch and packing size
on a line at any given time?

12.

13.

Is there presence of previous during product and


labeling materials?

14.

For container that have been used previously for a


certain materials and now been used for another
materials, are old labels removed before using
them?
Are drums containing blisters for packaging
properly
labeled at all times until the blisters in the drum
are exhausted?
Are blisters being left on the floor?
Is the number of blisters in a pack size correct as
declared?
Is the number of pack size in outer carton correct
as declared?

15.

16.
17.
18.

T I

N
0

REMARKS

N/A

Is each blistering line identified with product


name and batch number?

4.

11.

pmgman - audit checklist

28

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE
PRODUCTION AREA

19.

20.

T I

N
0

REMARKS

N/A

Do SOPs exist for the cleaning of the various


equipment and machines used in the production
area? Are they followed
Does SOP exist for reprocessing of products?

21.

Are frequent calibrations and servicing of balances


performed and documented?

22.

Are validation procedures available for:


- Procedures
- Process
- Machines and equipment in
- Production and packaging areas?

23.

Is there SOP for pre-clearance procedures


employed in order to assure that any packaging
material from the previous hatch has been removed
and are these followed?

24.

Are master and packaging records properly


assembled?

25.

Are batch packaging records kept at the work


station during the entire operation?

26.

Are process parameters laid down for every step in


writing?

27.

Are in-process control results available?

28.

Is there a documented label instructions prior to


use?

29.

Are all containers, machines, installation and


equipment used during and after packaging
properly identified?

30.

Are yield limit established at each significant step


of packaging?

31.

Are adequate procedures to reconcile the quantities


of packaging materials issued, used and returned
and are these followed?

pmgman - audit checklist

29

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

ENGINEERING (WORKSHOP)
1.

2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.

T I

N
0

REMARKS

N/A

Does a written preventive maintenance


programme exist for machine and equipment in
production, packaging and laboratory as well as in
Engineering?
In all the Engineering sections, are risk of
accidents due to carelessly placed wire, equipment
and other obstacle?
Are the sinks, toilets and bathrooms clean?
Are these areas habouring cobwebs, insects and
vermins?
Are appropriate uniforms used for the performance
of function?
Are lubrication records available based on a
lubrication manual for major machines and
equipment?
Are written records or log books maintained of
maintenance and repairs?
Do standard operating procedures exist for
cleaning/ sterilizing of filters?
Do records exist for cleaning/sterilizing of filters?
Are all structural materials in the various sections
of Engineering properly arranged?
Is the entire environment generally clean and well
arranged?
Is there evidence that the personnel are safety
conscious?
Do updated schemes (drawings) of the air
handling and distribution system exist, meeting
current requirements?
Is there an adequate system for dust extraction?
Are air filtration systems (which include pre-filters
and particulate filter) used on air supplied to the
manufacturing areas?
Is there an adequate system for dust extraction?
Are updated SOPs available for all
controls/monitoring, calibrations and validations
performed and are these followed?
Are adequately constructed waste containers
located in appropriate areas?
Does a preventive maintenance programme exist
for the whole buildings in the plant? Are written
records available?

pmgman - audit checklist

30

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

N
0

REMARKS

N/A

GENERAL SERVICE
1.
2.

Are the changing rooms for production personnel


clean?
Are the doors closed always to prevent entry or
exit of dust to other area?

3.

Is the tearoom clean and well arranged?

4.

Are precautions taken to prevent microbiological


contamination where necessary?

5.

Do SOP exist regarding the policy for the entry of


visitors to the different areas and are they
followed?

6.

Are measures taken to ensure that visitors do not


jeopardise the quality of the products in any way?
Are SOPs for good personal hygiene practices
available and are these followed?

7.
8.

9.
10.

Do SOP exist regarding the policy for the entry of


visitors to the different areas and are they
followed?
Are measures taken to ensure that visitors do not
jeopardize the quality of the products in any way?
Are SOPs for good personal hygiene practices
available and are these followed?

11.

Are building and surrounding areas free from all


and other unwanted materials?

12.

Are waste and trash stored in an orderly manner?

13.

Are the grounds attractively landscape and parking


lots, fences and drive ways in a good state of
repair?

pmgman - audit checklist

31

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

N
0

REMARKS

N/A

CANTEEN
1.

Is the store well arranged and is it clean?

2.

Is the evidence of safety consciousness in the


personnel working in this area?

3.

Are the cooking utensils not in use properly kept?

4.

Is there water/oil spillage on the floor that can


cause accident?

5.

Are the changing rooms and bathrooms clean?

6.

Are the personnel wearing clean clothes and


headgears?

7.

Is the working environment kept clean?

8.

Is regular waste disposal carried out in the


canteen?

9.

Are the waste containers kept far away from the


cooking area?

10.

If washing is being carried out during this


inspection, are the utensils washed rinsed with
copious clean pure water?

11.

On inspection of the cleaned utensils, are they


really clean?

pmgman - audit checklist

32

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

QUALITY CONTROL DEPT.

1.

Are there master control procedures?


- Approved by Quality Control?
Signed and dated by a responsible person?

2.

Do established procedures include specifications,


standard test procedures or other control
procedures for:
Raw materials and components
- In-processing materials (semi-finished
products)?
Packaging and labeling materials?
Finished products? - Test materials
(reagents, media etc)

3.

Are all procedures in written form and available to


all Quality Control personnel?

4.

Do test methods describe the sources such as


pharmacopoeias?

5.

Is each finished batch checked for compliance


before being released?
Does this final release include:
- Identity and strength of active ingredient?
- Identity and strength of effective and
auxiliary raw materials?
Acceptance and rejection levels?

6.

7.
8.
9.
10.
11.
12.
13.

N
0

REMARKS

N/A

Are any deviation from established procedures and


specifications justified and recorded?
Are test methods validated for accuracy and
responsibility?
Are all drug products failing to meet established
standard and specifications rejected?
Are there procedures and specifications for
accepting reprocessed materials?
Does Quality Control maintain written records of
all tests conducted?
Does these include:
- Graph, charts, spectra, chromatograms etc?
- Record of all calculations
Are these established sampling procedures for:
Raw materials
- In-process materials
- Packaging and labeling materials
- Finished products?

pmgman - audit checklist

33

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

14.
15.

TITLE

T I

QUALITY CONTROL DEPT.

In the room for sensitive instruments


- Are temperature and humidity controlled?
- Is there any vibration - proof bench for
analytical balance?

17.

Is there a programme for calibration of laboratory


instruments?

18.

Are instruments properly maintained?

19.
20.

Are the calibration documented?


Does Quality Control review and approve all
production and control records to assure
compliance with established written procedures
before a batch is released?

21.

Do retention samples meet the following criteria?


- A representative sample of the batch
- A quantity, at least two times the amount
required for all tests

22.

Is a written programme available for stability


studies?
Are containers of raw materials opened for
sampling, securely closed after and marked after
sampling?
Are printers proofs checked and approved before
mass production?
Does a documented water testing/monitoring
programme exist, indicating sampling schedule,
microbiological, chemical, filter changes,
regeneration, cleaning and distribution?
Are SOPs available for all controls and validation
of such controls on water supplied to plant?

24.
25.

26.
27.
28.

REMARKS

N/A

Do sampling procedure for finished products


include numbers of units per batch to be tested?
Are sample collected by Quality Control?
- For testing
- For retention?

16.

23.

Are there SOPs for in process control checks for


Production and Packaging?
Are in-process checks validated?

pmgman - audit checklist

34

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

N
0

REMARKS

N/A

QUALITY CONTROL DEPT.

29.
30.
31.

32.
33.

Are in-process results included in the batch


record?
How are in-process check results, which do not
conform, dealt with?
Do written procedures exist governing a
document change control system to ensure that
only updated documents are used and are these
followed?
Are written specifications for all starting,
packaging and auxiliary materials available
including updated acceptance criteria?
Are SOPs available for handling of rejected raw
materials auxiliaries and packaging materials and
are they followed?

34.

Does SOPs exist for handling of raw materials,


auxiliaries and packaging materials and are they
followed?

35.

Are all manufacturing Protocols and Packaging


Protocols approved by the Quality Assurance?

36.

Are SOPs available for signatory to any document


and are they followed?
Does Quality Control department have enough
qualified personnel for the jobs?
Does documentation of written and oral
complaints exist?
Do SOPs exist for testing, reprocessing and
destroying
of returned drug products and are these followed?
Do SOPs exist for operation of laboratory
equipment and are these followed?
Does an updated list of Laboratory equipment
exist?
Does SOP exist for discarding Laboratory
reagents that are prepared in the Laboratory and
are they followed?
Are all Laboratory solvents/reagents properly
labeled and stored?
Do SOPs exist for preparation and standardization
and expiry of volumetric solution and are these
followed?

37.
38.
39.

40.
41.
42.
43.
44.

pmgman - audit checklist

35

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

QUALITY CONTROL DEPT.

45.

Does the Quality Control monitor the handling of


approved materials in the warehouse (FIFO)?

46.

Are the following documents available?


- Sampling plan
- Specifications
- Analytical records including worksheets
- Certificate of analysis
- Data form environmental monitoring
Records of calibration, maintenance and
repair of instruments and equipment
Are raw data retained to support results in the
certificate of analysis?

47.
48.
49.

Are these SOPs for general inspection of


manufacturing areas for the in-process inspector?

51.

Does a SOP exist for each of the processing steps


for the in-process control inspector and are such
followed?
Do SOP exist for writing report of analysis in a
work book and are they followed?

53.

Is there SOP for batch review before a batch is


finally released?

54.

Is there SOP for regular microbiological testing


and documentation with respect to airborne and
surface contamination and is it followed?
Does an approved sampling plan exist indicating
the sampling procedure, sampling area,
identification of sampled container,
responsibilities and quantities, which have to be
taken?
Are there written procedures describing in detail
testing, approval and rejection of starting and
packaging materials?
Is each material tested for conformity with the
specification?

55.

56.
57.

REMARKS

N/A

Are SOPs for investigation of out of specification


laboratory results available and are these
followed?
Does SOP exist defining retesting/re-sampling
conditions and responsibilities in case of out of
specification results and is it followed?

50.

52.

pmgman - audit checklist

36

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT
GUIDE
LINE
No.

TITLE

T I

QUALITY CONTROL DEPT.

58.

Is the material released in writing and are the


containers marked accordingly and physically
separated?

59.

In case of specification discrepancies, is there a


written procedure on how to handle it?
Is the whole batch documentation including
Laboratory data kept in one safe place accessible
at all times? Who is responsible for that?

60.

61.
62.
63.
64.

Are record sheets dated and signed by a


responsible person?

66.

In the case of using person dedicated


notebook/logbook, how is dating and signing dealt
with? How are exhausted person - dedicated
notebooks handled?

67.

Are corrections of raw data not caused by writing


error justified, dated and signed by the analyst or
responsible of the Laboratory?

68.

Are corrections performed so that the previous


data can be clearly identified?
Are reading reported at the time of their
performance?
Is it assured that chromatograms, charts and
printouts can be clearly related to the
corresponding Laboratory equipment?

70.

71.
72.
73.

REMARKS

N/A

Are the batch data reviewed on periodic basis?


In Laboratory documentation, are raw data
documented in adequate record sheets, notebooks,
logbooks, print outs or drafts?
If record sheets are used, are these updated and
numbered consecutively by means of a paginating
stamp in order to ensure their completeness?
Are raw data reported and documented manually
or by means of computerized system?

65.

69.

Is the completeness of the run assured?


Is it assured that equipment functions properly
during runs?
Are system suitability performed?

pmgman - audit checklist

37

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

QUALITY CONTROL DEPT.

74.

Are measures taken to ensure that manual raw data


calculations are double checked by the responsible
for final batch release?

75.

Are test results transferred adequately on to the


certificate of analysis?

76.

Does the Certificate of Analysis include the


followings? Name of product?
- Dosage form?
Batch number?
Manufacturer?
- Date of manufacturing?
- Test results?
- Date of testing?
- Expiry date?
- Clear statement of release or rejection?
- Signature of responsible(s)?

77.

Does the water used for production meet chemical


and microbiological quality specified. Any
record to show quality control approval of its use?

78

Is there a formal change control system that


addresses changes to validation system including
Quality Assurance/Quality control review and
approval

79

Does validation team exist? Who are in the team


and job titles?

80

Who is responsible for the validations?

81

Are validation procedures available for:


- Procedures

82.

83.

N
0

REMARKS

N/A

- Process
- Machines and equipment?
Is a retrospective validation carried out on a
periodic basis on a particular product?
Does retrospective validation include trend
analysis?

pmgman - audit checklist

38

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT
GUIDE
LINE
No.

TITLE
MICROBIOLOGICAL TESTING

84.

85.
86.
87.
88.
89.
90.

91.

T I

N
0

REMARKS

N/A

Are the following microbiological tests performed:


- Microbiological testing of non-sterile
products?
- Microbiological testing of effectiveness of
cleaning procedures?
- Microbiological testing of effectiveness of
disinfectant?
- Microbiological testing of starting materials
(bioburden)?
Is the microbiological testing performed
according to the updated procedure?
Is special emphasis put on microbiological testing
of sterile, topical, nasal and inhalation products, if
applicable?
Are total counts and identification of contaminants
included?
Are autoclaves, hot air sterilizers and incubators
calibrated?
Are facilitaties for sterility testing similar to
facilities for sterile production?
Does an SOP exist defining retesting conditions in
the case of positive testing results and is it
followed?
Are incubation times in accordance with
specifications?

92.

Are microbiological testing procedures including


identification of contaminants validated?

93.

Do SOPs for preparation of media include expiry


dating? Is growth promotion testing included?

94.

Does the hygiene programme for the cleaning and


disinfectation of the sterility-testing laboratory
include personnel and is it followed?

95.

Are microbiological testing results entered in lobook or analytical sheets?


MICROBIOLOGICAL AND PARTICLE
MONITORING

96.

Is there a written microbial monitoring


programme for the manufacture of sterile and nonsterile products (see section 2:5)?

pmgman - audit checklist

39

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

97

Does this monitoring programme include:


- Air?
- - Surface?
- - Personnel?
- - Machine and equipment?
- - Disinfectant/cleaning?
- Material?
- Water?

98.

Are the procedures for microbiological monitoring


validated?

99.

Is there a periodic identification of contaminants


isolated in air, water, surfaces and personnel?

100.

Is there a written particles monitoring programme


for the manufacture of sterile and non-sterile
products and is it followed?

101.

Does the monitoring programme include: - Air?


- Energy (water, steam, etc)?

102

Does alert/action limits exist for all these


controls?

103

Does a statistical data register exist?

104

Is there a periodic analysis of data and trends?

105

Is corrective action documented?

pmgman - audit checklist

T I

N
0

REMARKS

N/A

40

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

TITLE

T I

N
0

REMARKS

N/A

MANAGEMENT
1.

Are the responsibilities of the person who is


responsible to the government clearly stated?

2.

Is an updated organizational chart available?

3.

Does the organizational chart include key


personnel and their respective deputies?

4.

Do the key personnel have the education, training


and experience to perform their assigned
functions?

5.

Are the competent personnel available in sufficient


number to supervise all stages of manufacture?

6.

Are the deputies able to perform key personnel


functions?

7.

Does a Quality Control unit exist?

8.

Does a Quality Assurance unit exist?

9.

Is there a person responsible for GMP related


aspects?

10.

Do updated written job description exist for the


key personnel?

11.

Are areas of competence and responsibilities of the


key personnel clearly stated and laid down in
writing with special regard to Quality Assurance?

12.

Are the procedures indicating clearly the


responsible person for quality relevant activities
who demonstrates them by checking and signing
quality relevant documents?

pmgman - audit checklist

41

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

pmgman - audit checklist

TITLE

T I

N
0

REMARKS

N/A

42

AUDIT - CHECKLIST
INSPECTION OF MANUFACTURING PLANT

GUIDE
LINE
No.

pmgman - audit checklist

TITLE

T I

N
0

REMARKS

N/A

43