PROCUREMENT STRATEGY

Summary of Requirement
This should summarise the nature of the procurement.
Background including future developments
What is being purchased - scope of work, related work that is not included, optional work
that could be beneficially provided by the supplier.
Objectives of the procurement.
The business case (see the section on Business Cases, SPD Toolkit) can be incorporated or
attached as an annex.

Customer/Contract Manager
This is the customer who has generated the requisition. The intended contract manager
should also be identified and this may be the customer or someone else in the same division.
Estimated contract value/available budget
This should show the estimate of the contract value over the whole life of the contract and the
budget available to cover the goods/works or in a service contract the contract duration.

Duration of contract
The contract period, e.g. for a cleaning contract it may be 2 years or for a consultancy the
duration would be the period from contract commencement to the delivery of the final output
etc include any options to extend the contract beyond the core period.

Market capability
This should include an evaluation of the competitive environment including suppliers.
Capability and capacity to meet your requirements and those of the rest of the public sector.
Sustainable Development
This should include consideration of sustainable development issues pertinent to the
procurement, and an assessment of the extent to which goods and services can be
manufactured used and disposed of in ways which reduce resource use, energy use, travel and
pollution. Where there may be significant Sustainable Development issues associated with
the procurement, relevant stakeholders (e.g. Accommodation - Environmental Management,
Environment Group and Sustainable Development) should be consulted at the earliest
opportunity

Risks
This should identify the relevant risks involved. Possible risks include Business Risk e.g. suppliers failure to deliver may have a significant affect on government
policy.
Service/Operational Risk should be managed by party best placed to do so e.g. design, build,
finance, operate.
External Risk e.g. Legislation (does the Transfer of undertakings (Protection of Employment)
apply); innovative product; limited number of providers.
Implications of FOI
Procurement Process
How the procurement process is conducted in terms of

Project Team - representation from key stakeholders


Procurement Options - Relate to procurement priorities; capability and capacity of
suppliers; single supplier vs. multiple suppliers option.
Procurement Route - How EU rules apply; collaborative opportunities including OGC
contracts; Open, Restricted, Negotiated procedures; Strategic partnering arrangements;
non-Competitive Action
Advertising - SE internet, OJEU, GO, press, trade journals, Potential Suppliers Database
(link) etc.
Structuring of the Invitation to Tender document - What documents will comprise the
tender (for SPD staff - UCMS format). Expected distribution. ETS
Criteria for tender evaluation - most economically advantageous tender/ lowest price.
Subject to complexity of project, it may be desirable to expand on specific criteria at this
stage.
Contract management arrangements - Contract Type, Form of Contract (recompetition),
Review periods, Payment Mechanisms (EASEbuy as applicable for SE contracts),
Incentives and Rewards.

N.B.

If Non-Competitive Action (NCA) is being proposed, supporting evidence is required.

Pricing strategy
The pricing arrangement should be set out, e.g. fixed price, daily rate, target pricing, schedule
of rates, arrangements for optional costs, payment stages, effect of e-procurement/e-trading
etc. Pricing strategy should aim to incorporate all foreseeable costs.

Tender Evaluation Team


This sets out who is in the project team, what their roles and responsibilities are including any
particular strengths and weaknesses.

Timetable
This should show all the main tasks and milestone dates for the completion of such tasks.
SPD should use UCMS action list as a guide.