Total marks:15
Time: 10 min
-- 15X1=15 Marks
1. What should a project manager do or follow to ensure clear boundaries for project completion?
a)
Scope verification
b)
scope definition
c)
d)
7. The amount of time an activity can be delayed and yet not delay the project is termed
a) Total slack
b) Free slack
c)
critical float
d) Slip pad
8. Which of the following is not one of the basic rules to follow when developing project networks?
a) An activity cannot begin until all preceding activities have been completed.
b) Each activity must have a unique identification number
c) Conditional statements are allowed but looping statements are not allowed.
d) An activity identification number must be larger that that of any preceding activities.
9. An item on a project network is Design Software Completed. This is best described as a(n)
a) path
b) Event
c) Activity
d) milestone
10. The critical path in a project network is the
a) network path with the most difficult activities
b) shortest path through the network
c) network path with the most merge activities
d) longest path through the network
11. Information to develop a project network is collected from the
a) organization breakdown structure
b) wok breakdown structure
c) budget
d) project proposal
12. If the initial investment in a project is $100,000 and the expected annual net profit for the project is $20,000
the payback period is:
a) 5 years
b) 4 years
c) 10 years
d) Insufficient information to determine the payback period.
13. The most important consideration in budgeting is:
a) Cost control.
b) Maximizing projects return on investment.
c) Meeting the projects schedule.
d) Estimating project resource costs.
e) All of the above.