Académique Documents
Professionnel Documents
Culture Documents
on
impacts
of
blasting
activities
Nakatooke quarry.
An Assessment of the baseline survey.
in
the
vicinity
of
1.
INTRODUCTION .......................................................................................................................................... 3
1.1.
ABSTRACT ................................................................................................................................................. 3
1.2.
EARTH
2.
3.
3.1.
THE
OF
LEVELS OF
AND
GROUND VIBRATIONS
AND
4.
5.
CONCLUSIONS ...................................................................................................................................... 11
6.
7.
RECOMMENDATIONS.......................................................................................................................... 12
7.1.
IMPLEMENTATION
OF
LIMITS ............................................................................................................. 12
6.1.1
6.1.2
8.
REFERENCES ........................................................................................................................................ 13
9.
APPENDICES ......................................................................................................................................... 14
9.1.
APPENDIX-1 :RECORDS
OF
9.1.1
9.1.2
1. Introduction
1.1.
Abstract
blasting
activities
at
Nakatooke
quarry
on
the
structures
of
the
at
mitigating
or
limiting
the
possibility
of
damages
due
to
structural
Uganda.
integrity
The
report
of
also
mud
and
covers
wattle
structures
recommendations
vernacular
to
operation
of
for
1.2.
In scientific
terms,
earth is
referred
to
as
loam.
It
is
a mixture of
clay, silt (very fine sand), sand and occasionally, larger aggregates. It is
used
all
over
unbaked
bricks
the
world
(mud
in
several
bricks/adobes);
forms,
these
compressed
being
unbaked
handmade
bricks
(soil
Owing
to
the
fact
that
loam
is
not
standardized
has
been
scarce.
However,
the
need
for
an
analysis
of
its
were excavated by
blasting, which was carried out within the framework of conditions that
take
into
account
standardized
structures
built
with
the
or concrete blocks.
conventional
However, the
performance of mud and wattle structures does not seem to have been
factored
into
compliances
the
required
framework
for
the
of
considerations
attainment
of
that
permits
govern
for
the
blasting
activities.
In light of this, the need for an assessment of the performance of mud
and wattle structures under the cited conditions cannot be understated
since blasting activities can have a significant vibration output that has
been known to damage structures.
In order to assess the performance of the subject structures, a baseline
survey was carried out on the structures within a 2 km radius of the
blasting
epicenter
so
as
to
assess
their
initial
conditions.
During
the
initial survey it was noted that the structures varied in terms of the
characteristics. This was attributed to the differences in the amounts
and
types
of
workmanship
clay
as
used
well
as
for
the
the
construction,
form
of
the
silt
construction,
be
content,
the
adobes,
soil
it
vicinity
of
communities
the
for
quarry
whom
were
the
previously populated by
only
option
in
terms
of
several
building
rural
material
was and still is, the use of mud and wattle. This is because mud and
wattle is the most abundantly available building material, requiring little
or
no
technology
for processing.
This
lead to
a significant population
675 within the proximity of the dam area alone. These Project Affected
People
were
compensated
and
the
land
was
handed
over
to
the
Power
Plant.
However
the
communities
adjacent
to
the
Project
boundaries are still impacted by the blast waves that occur due to the
detonation
of
between
500
and
as
much
as
3500
Kg
of
ammonium
in
place
to
protect
the
interests
of
the
local
communities.
change
communities
warns
the
of
fact
will
imminent
that
have
to
blasting
structures
bear
the
activities.
cannot
impacts
be
of
However,
shifted
the
and
blasting
this
does
the
local
activities.
temporarily
moved
further
from
the
epicenter
of
the
blasting
does
little
or
nothing
to
restore
or
maintain
structure
It has been observed that the impacts of the blasting activities are not
so easily ascertained mainly due to the varying degrees of workmanship
during
the
construction
of
the
mud
huts.
However,
there
have
been
claims that some brick houses have developed cracks as a result of the
blasting at the quarry. In view of the claims the EPC Contractor has
been
requested
to
conduct
vibration
monitoring
at
varying
distances
differing
amounts
characteristics,
preparation
differ.
of
In
therefore,
the
order
necessary,
by
and
types
may
correct
to
judge
applying
of
clay,
differ
mix
its
or
silt,
from
a
site
specific
characteristics
additives,
one
and
needs
to
aggregates.
Its
site,
and
the
application
may
also
and
to
alter
know
these,
the
when
specific
cracks
between 3% and
will
occur.
The
linear
ratio
is
usually
and mud bricks), and between 0.4% and 2% with drier mixtures (used
for rammed earth, compressed soil blocks). Shrinkage can be minimised
by reducing the clay
and the
water
must
be
protected
against
rain
and
frost
especially
in
its
wet
state.
The above stated have made it difficult to determine the actual impact
of
the
blasting
activities.
In
addition,
some
of
the
structures
had
due
resistance.
to
the
However,
shrinkage
it
was
of
said
the
that
soil
the
as
well
as
the
pre-existing
poor
water
damage
was
3.2.
exerted
on
mechanisms
of
breakage
fragment
the
rock
mass
(crushing,
intensity,
unable
to
cause
permanent
deformation
to
the
rock
mass. The Strain waves propagate through the medium as elastic waves,
oscillating the particles through which they travel. These waves in the
elastic
zone
display
visco-elastic
behaviour
and
as
such,
the
strain
waves are attenuated over distance since a fixed amount of energy gets
spread
over
larger
mass
of
material
with
increase
in
distance.
ground
vibrations
large
enough to
cause
damage
to
structures
by
3.3.
Type of
Structure
Type of Damage
Rigidly Mounted
Trip Out
Mercury Switches
Houses
Plaster Cracking
0.5
50
2
Set initial Limit of
125 mm/s (5 in. per
sec) Maximum at the
Crusher
Cracks in Blocks
Concrete Block
as in a New
House
Cased Drill Holes
Horizontal Offset
Retaining Walls.
Loose Ground
Mechanical
Equipment
Pumps
Compressors
Prefabricated
Metal Building on
Concrete Pads
Shafts Misaligned
Cracked Pads
Building Twisted
and
Distorted
3.4.
200
375
15
1000
40
Beyond 250 rwn/
(10 In per sec) Mafor
Damage Starts. Such
as Possible Cracking
of Cement Block
1500
60
Notes:
* Values in brackets are those suggested to keep claims and complaints to an acceptably low level. For complaints to be stopp ed
completely in residential areas, these values would possibly be needed to be increased still further.
Fig.
5. Conclusions
The nature of the building material used by the majority of the locals
has certain inherent characteristics which make identification of actual
impact of the vibration caused by blasting somewhat problematic. The
shrinkage which occurs as the adobe dries, causes crack which are
easily mistaken for cracks caused by vibrations due to blasting. That is
not to say that cracks due to blasting do not occur, but rather, it
implies that the material is not as strong as the Concrete or burnt
brick buildings that are within the same range from the blast
epicenter. Claims have also been made by owners of houses made of
burnt brick, however, in some instances, visual investigations of these
cracks seemed to indicate that the damage was a pre-existing condition
since the surfaces of the cracks showed signs of aging. These were
compared with cracks on buildings were it was evident that the cracks
had only recently been formed. The types of structures and the quality
of workmanship was also analyzed during the baseline survey.
It can be concluded from the findings and from comparisons with
international practices, that the determining factor in setting up a limit
for the vibrations is the human factor and its response to the
vibrations. The Effects of vibrations become intolerable to humans at a
levels appreciably lower than the levels at which structural damage
occurs. It is therefore only fair that the limits should be set based on
these limits as is common practice internationally.
It should also be noted as an example that limits used in the US of
peak particle velocity of 12.5 mm/s (0.5 in./s) have been known to
reduce the number of complaints by a factor of three compared to
50mm/s (2 in./s). In comparison, the United States Bureau of Mining
(USBM) recorded complaints on one construction site as high as 30%
at
50 mm/s, 10% at 12.5 mm/s and 1% at 2 mm/s, which is just the
perceptible range. The current blasting code for Ontario, Canada calls
for a maximum peak particle velocity of 10 mm/s.
6. Actions taken
The EPC Contractor has put in place programs to sensitize the local
residents of the possible impact of the blasting activities. This has been
done in accordance with the Explosives' management plan that was
submitted by the EPC Contractor. The local communities also stand to
gain from transfer of skills that is going on as the local workforce
interacts with foreign Contractor. This transference of skills most of
which occurred during the initial stages of the Project as the EPC
Contractor Constructed the Camps, could serve as a template for the
further development of the region as the locals lean to build better.
This is even more pertinent in view of the fact that some of the
structures/Buildings within the 2 km radius of the Blast epicenter had
showed signs of cracks. Some of these were attributed to poor
workmanship.
7. Recommendations
7.1.
Implementation of Limits
Different limits may apply depending upon whether there are national
guidelines in use prior to the introduction of this Report. The EPC
Contractor is guided by the conditions pertaining to the permits
obtained for the blasting activities. It may turn out that the limits
recommended by this report may not be consistent with National
guidelines on blasting activities. In such cases the applicable limits are
those set down in the Licence or Authority.
Ground vibration and air blast levels are generally measured at the
nearest sensitive site. However, in the interests of minimising potential
negative impacts on the local communities, monitoring has been
conducted at various distances from the blast epicentre to establish
magnitude of ground vibrations propagated to given distances.
6.1.1
Existing Recommendations
In international practice, Work Authorities
or
Licence
Conditions
set
limits for air blast and ground vibration measured at sensitive sites
and these are set as follows:
Ground vibration at sensitive sites should be below 10mm/s (ppv*)
at all times, and
Airblast at sensitive sites should be below 120dB (Lin Peak*) at
all times.
6.1.2
Recommendations for Isimba quarry site
The levels for vibrations and Airblast for the communities in the
vicinity of Isimba HPP's quarry are recommended as follows:
Ground vibration at sensitive sites should be below 5 mm/s (ppv)
for 95% of all blasts.
Airblast at sensitive sites should be below 115dB (Lin Peak) for
95% of all blasts.
In view of the above, the EPC Contractor is advised to limit the
quantities of explosives used so as to ensure that the ground
vibrations and airblast are limited to the ranges indicated above.
Note: In situations where the location or the nature of the operations
mean that this is not
subject to the relevant
achievable,
authorities
these
being
8. References
1. Standards Association of Australia (SAA). Explosives Code AS2187-983
Part, Use of Explosives.
2. Tynan A.E. (1973). Ground Vibrations, Australian Road Research Board
Special Report.
3. BS 7385-2:1993: Evaluation and measurement for vibration in
buildings. Part 2: Guide to damage levels from ground borne
vibration.
4. BS 6472-2:2008: Guide to evaluation of human exposure to vibrations
in buildings. Part 2: Blast induced vibrations
5. Surface Mining. Second Edition, edited by Bruce A. Kennedy, Society
for mining, metallurgy and Exploration (US).
9. Appendices
9.1.
9.1.1
Vibration Readings 01
400m
Number of Holes
Total Charge
(Kg)
i.
Velocity Graph
139
2034
ii.
Results:
Maximum Velocity
Frequency
0.13 cm/s
22.3 Hz
9.1.2
Vibration Readings 02
310 m
148
Total Charge
3456
(Kg)
i.
Velocity Graph
ii.
Results:
Maximum Velocity
Frequency
0.4311 cm/s
22.2 Hz