Vous êtes sur la page 1sur 36

Interval Velocity Model

0
1934
1

DEPTH X1000 M

2376

Stacking velocities are


used to derive interval
velocities for depth
conversion

5
DISTANCE

Interval Velocity Model


The stacking velocities supplied to the interpreter by
the processing contractor are usually far from ideal
for deriving interval velocities.
Why are they usually not ideal?

10.1

Exercise 10.1

Interval Velocity Model

A digital version of this exercise is available as Ex 10.1.xls.


Given this stacking velocity function (the nearest to the well A location) find: 1. the interval stacking velocities,
2. the thicknesses of the units
3. the average velocity to each of the interfaces.
Compare your results to the results of Exercise 2.1 at the end of the Definitions 1 page
2.10 (File Ex 2.1.xls)
What are the possible sources of error in your resulting depth model?

VIS =

tbase - ttop

SP 78355
Time
msec
0
50
290
489
840
900
945
1030
1330
1586
1740
2070

VS,base2 tbase - VS, top2 ttop

VS
m/s
1480
1480
1710
1810
2140
2190
2278
2430
2810
2985
3260
3570

10.2

1/2

Interval Velocity Model

n Optical stacking velocity


o Refraction analysis
p Stacking velocity analysis
q Dip Corrected stacking velocities
r Interval Stacking velocities
s Interval velocity analysis
t Migration velocities
u Depth migration velocity analysis
v Residual velocity analysis
w Tomographic velocity analysis

Interval Velocity Model

We need the best RMS interval velocity model we can get


out of the stacking velocity data.
We may need to dip correct our stacking velocities.
We may need a bias correction.
We may need to interpolate the RMS velocities to the
times of our picked horizons.
After deriving the interval RMS velocities we will almost
certainly need to filter and smooth.

10.3

Dip Correction

Interval Velocity Model

Stacking velocity values can be dip corrected without recourse to


reprocessing with DMO.
Levins Dip Correction for 2D data is VSapp VS / Cos where
is the apparent dip, giving: VS VSapp x dx / [dx2 + (dt. VSapp )2].
Distance
mic
g seis
Dippin ent
ev

dx
Time

dt

Cos = dx / [dx2 + (dt. VA )2]


dx / [dx2 + (dt. VSapp )2]

Dip Correction

Interval Velocity Model

VS VSapp x dx / [dx2 + (dt. VSapp )2].


Given VSapp = 2476 m/s and a time dip of 170 msec / 240 m
find VS (remember dT = 2.dt and you need the time in seconds).

VSapp = 2476 m/s

dT =170 msec
dx = 240 m

10.4

Dip Correction

Interval Velocity Model

Levins dip correction VSapp VS / Cos works well for a


single dipping reflector on a dip line.
It also works for the case of a dip line with parallel dips in
the subsurface.
Only use in areas of steep dip (>25) on legacy data

Dip Correction

Interval Velocity Model

In the case of multiple


arbitrary dips Levins
formulae fails to make an
adequate correction. In fact,
a dip correction cannot be
made directly and one has to
resort to modelling the
observed stacking velocity.

V2

NMO

1
Tocos2ro

k=1

ij
j

V2t
k

rj
tn

n
k-1

ro

cos2ij
k
j=0 cos2r
j

Vn
n

with

To = tk
1

Everett and Hubral (1974) offer a recursive procedure for modelling VS


whereas Shah and Levin (1974) did not.
10.5

Bias Correction

Interval Velocity Model

When: maximum offset is greater than 1500m or


there are large contrasts in formation velocities
then the stacking velocity will not be a good approximation to
the RMS velocity.
We need to correct for this bias before we compute the
interval velocity.
There are four ways we can do this; the first three are
numerically the same.

Bias Correction

Interval Velocity Model

Method 1
This approach is used in velocity modelling software and
returns the Interval RMS Velocities.
M. Al-Chalabi gives:
Bias = VS - VRMS = Xmax2(VRM44-VRMS4)/(8To2VRMS5)
where

VRM44 = ( VIm4tm)/to

for m = 1 to current layer.

VS - VRMS - Xmax2(VRM44-VRMS4)/(8To2VRMS5) = error


Using the Dix derived interval velocities to calculate the VRMS
and VRM4 terms the modulus of the error is minimised by
changing the values of the interval velocities. (This could be
done in Excel using the Solver tool.)
10.6

Bias Correction

Interval Velocity Model

Method 1
Note that the equation is based on the three term Taylor series
expansion and as such will be in error because of the
neglected terms. However, since the expression is an infinite
series, including additional terms does not measurably
increase the accuracy of the solution as demonstrated by alChalabi (1974) when he first introduced the concept.
The XMAX term in the equation is the maximum offset, this
varies with the reflection time according to the mute that was
used before velocity analysis, not the mute that was applied to
remove NMO stretch after the NMO correction.

Bias Correction

Interval Velocity Model

Method 1
The file Bias.xls illustrates this method on worksheet exercise 1.

10.7

Bias Correction

Interval Velocity Model

Method 2
As before
VS - VRMS - Xmax2(VRM44-VRMS4)/(8To2VRMS5) = error
Using the Dix derived interval velocities (VIS) to calculate the
VRMS and VRM4 terms the error is made as small as possible,
recursively, by changing the values of VIS layer by layer.
A second tool in Excel, Goal Seek, can be used to do this.
Applying it to the second layer of our model we obtain VI =
3990 m/s compared to the original model value of 4000 m/s.

Bias Correction

Interval Velocity Model

Method 2
Interval Velocity Model

RMS & Stacking Velocity


Velocity/1000 m /s

Interval Velocity m /sec


0

2000

4000

1.4

6000

2.2

2.6

0
500

500

1000

1000

1500

1500

2000

2000

Depth m

Depth m

1.8

2500

2500

3000

3000

3500

3500

4000

4000

4500

4500

5000

5000
RMS Velocity
Theoretical Stacking Velocity

Original Model

10.8

Bias Correction

Interval Velocity Model

Method 2
Bias

Depth Conversion Error


Error in m

Bias - Percent
0.2 0.4 0.6 0.8

-5

1.2 1.4 1.6

1000

1000

2000

2000
Depth m

Depth m

-0.2 0

3000
4000

10

15

20

25

30

35

3000

4000

5000

5000
6000

6000

Theoretical Stacking Velocity

Theoretical Stacking Velocity

Bias Correction

Bias Correction

Bias Correction

Interval Velocity Model

Method 2
The file Bias.xls illustrates this method on worksheet exercise 2.

10.9

Bias Correction

Interval Velocity Model

Method 3
The bias correction can be estimated by modelling, an
approach that was used before optimisation was available in
spreadsheets:
Assume
VS=VRMS

Calculate
VIrms

Build model
using VIrms
for VI

Compute VS
for new
model*

Modelled
bias is
estimate.

* To compute the stacking velocity for the model it is necessary to:


Model Tx2 using the T0, x2 and x4 terms of the moveout
equation.
Plot Tx2 against x2
Fit a straight trend line.
VS is the inverse of the slope of the trendline.

Bias Correction

Interval Velocity Model

Method 3
Assume
VS=VRMS

Calculate
VIrms

Build model
using VIrms
for VI

Compute VS
for new
model*

Modelled
bias is
estimate.

For our 2 layer model we had: T0


VS
1.5
2000
2.0
2699
assuming the above are RMS velocities, then
T0
VRMS
VIrms
1.5
2000
2000
2.0
2699
4140

10.10

Bias Correction

Interval Velocity Model

Method 3
Assume
VS=VRMS

Calculate
VIrms

Build model
using VIrms
for VI

Compute VS
for new
model*

Modelled
bias is
estimate.

* To compute the stacking velocity for


the new model it is necessary to:
Model Tx2 using the T0, x2 and x4
terms of the moveout equation.
Plot Tx2 against x2
Fit a straight trend line.
VS is the inverse of the slope of the
trendline.

New Model
To = 1.5 sec
VI = 2000 m/s
To = 2 sec
VIRMS = 4140 m/s

Bias Correction

Interval Velocity Model

Method 3
Assume
VS=VRMS

Build model
using VIrms
for VI

Calculate
VIrms

Bias Correction by Modelling

y = 0.1316x + 4.0051

5.5

Compute VS
for new
model*

Modelled
bias is
estimate.

Trendline slope = 1/VS2


Slope = 0.1316 x 10-6
So for new model: VS = 2756 m/sec
and VRMS = 2699 m/sec

T squared

4.5

4
0

Modelled offsets

X squared

10

Linear (Modelled offsets)

10.11

Bias for new model is 57 m/s


This is estimate of bias in
original data.

Bias Correction

Interval Velocity Model

Method 3
Assume
VS=VRMS

Calculate
VIrms

Build model
using VIrms
for VI

Compute VS
for new
model*

Modelled
bias is
estimate.

For our 2 layer model:


VS = 2699 m/sec and the bias is estimated to be 57 m/sec.
Estimate the interval velocity of the second layer after applying
a bias correction.
Use VI = [(V2RMS2t2 - V2RMS1t1)/(t2 - t1)]1/2

Bias Correction

Interval Velocity Model

Method 4
Another method is suggested by the fact that VS tends to VNMO
at small offsets.
This method has to be implemented during processing or
reprocessing and was popular with contractors in the
1980s for determining VRMS.
The stacking velocity is determined at a number of different
offsets, a cross plot generated, and extrapolated back to zero
offset.

10.12

Bias Correction

Interval Velocity Model

Method 4
Bias Correction
y = 6E-06x + 2646

Applying the technique to


the T - X values for our
model:

2700

2695

2690

2685
Stacking Velocity

For the second layer of our


model we obtain 2646
m/sec giving VI = 4000
m/s.

2680

2675

2670

2665

2660

2655
0

2000000

4000000

6000000

8000000

10000000

Offset squared

Interpolation

Interval Velocity Model

Unless the stacking velocities have been picked to be


consistent with the horizons that define the boundaries in the
macrovelocity model there will be a need to interpolate.
The way in which we interpolate stacking velocities affects
the interval velocities derived from the interpolated values.

10.13

Interpolation

RMS Velocity
1000
2000

0.2

500

0.4

1000

0.6

1500

0.8

2000

4000

2000

2500

1.2

3000

1.4

3500

1.6

4000

Linear interpolation VRMS = 2273 m/sec

Interpolation

Interval Velocity Model

RMS Velocity
1000
2000

Interval Velocity

3000

2000

0.2

500

0.4

1000

0.6

1500
Depth

One Way Time

Interpolation needs
to take account of
the interval velocity
model. It should
either leave the
interval velocity
model obtained
from the
observations
unaltered or use a
proiri interval
velocity information
from well control.

Interval Velocity
3000

Depth

One Way Time

Linear
interpolation is
usually used
(being the default
in software) but
this is not
necessarily
correct since it
modifies the
interval velocity
model given by
the observations.

Interval Velocity Model

0.8

2000

2500

1.2

3000

1.4

3500

1.6

4000

Constant interval velocity


interpolation VRMS = 2338 m/sec

10.14

4000

Exercise 10.2

Interval Velocity Model

You have stacking velocities picked from Horizon based Velocity Analysis for two horizons
and find that you need to interpolate the stacking velocities at a constant time value which
just happens to lie mid way between the two sets of picks. The software you are using
offers you a choice of interpolation methods to use: linear in V, linear in V2, linear in V2t,
linear in sqrt(V2t) and with a user supplied compaction factor. You dont have a value for K
and decide to interpolate between your picked horizons so that the interval velocity remains
unchanged.
Which method do you choose?
Confirm your answer by interpolating between
T secs
1.315
1.885

VS m/s
1997
2548

at a time of 1.6 secs.

If you had chosen the other methods what would be the error in your interpolated value for
VS?

10.15

Interval Velocity Model

Frequently we find that the RMS velocity profiles or maps


are very noisy and it is quite common to find these being
smoothed before being used to compute interval velocities.
This may lead to erroneous interval RMS velocities.
It is preferable to derive the interval RMS velocities and then
smooth the data.

Interval RMS Velocity

Interval Velocity Model

Having corrected as far as possible the stacking velocities so


that they better approximate the RMS velocities and having
interpolated to the horizons of interest we can now compute
the interval RMS velocities.
Whether we use stacking velocities or time migration RMS
velocities we use Dix inverse RMS equation to produce an
estimate of the interval RMS velocities known as interval
stacking velocities or interval RMS velocities.

VIS =

VS,base2 tbase - VS,top2 ttop


tbase - ttop

10.16

1/2

Interval RMS Velocity

Interval Velocity Model

Using the three time-velocity pairs derived in the exercise at the


end of the last section (page 9.44) compute the two interval
RMS velocities.
VIS =

VS,base2 tbase - VS,top2 ttop


tbase - ttop

Interval RMS Velocity

1/2

Interval Velocity Model

The class results are:


Upper interval

Lower interval

10.17

Interval RMS Velocity

Interval Velocity Model

Mean = 5445

S. D. = 236

Interval RMS Velocity

Interval Velocity Model

Mean = 5020

S. D. = 294

10.18

Interval RMS Velocity

Interval Velocity Model

Sensitivity
The error in interval velocity is proportional to the error in
RMS velocity.
The error in interval velocity is proportional to the travel
time error.
The error in interval velocity is proportional to the ratio of
RMS to interval velocity.
Interval velocity error is proportional to the ratio of time
thickness to depth.
See Hajnal and Sereda, Maximum uncertainty of interval velocity estimation, Geophysics November 1981.

Interval RMS Velocity

Interval Velocity Model

Rule
Rule of thumb:
Try to avoid applying Dix equation to intervals
thinner than 200msec TWT.

Field Statics
If field statics are applied to a datum other than the average
of the topography / shot receivers, the interval stacking
velocities will be distorted.
From our 2 layer model we had VS = 1978 and 2680 m/s
after a 40 msec static. This results in an interval stacking
velocity of 4153 m/s compared to the 4140 m/s without the
static.
10.19

Smoothing

Interval Velocity Model

No matter how much care we have taken we will almost


certainly have a noisy interval RMS velocity map so what
can we do to reduce the noise?

Smoothing

Interval Velocity Model

No matter how much care is


taken in picking and correcting
the stacking velocity values,
resulting interval RMS velocity
maps and profiles will always
be noisy and contain artefacts.
These data usually need to be
edited or smoothed before
being incorporated into a
macrovelocity model.

8 miles

Data courtesy of Amoco

10.20

Smoothing

Interval Velocity Model

High frequency noise

Artefacts caused
by a fault zone
We may not always be as
fortunate in having so little noise.

8 miles

Data courtesy of Amoco

Smoothing

Interval Velocity Model

Editing
The use of Dix equation on thin intervals is unstable.
Consequently geologically unreasonable interval velocities
often result. These can be edited, either removed or replaced
by geologically reasonable values.

Data courtesy of Amoco

10.21

Smoothing

Interval Velocity Model

Noise
Most commonly our first
interval RMS velocity
maps will look like this,
noisy.
The effect is caused by
noise in the data and
misties between different
velocity profiles.
It is advisable to filter out
the worst points before
smoothing.

Data courtesy of Amoco

Smoothing

Interval Velocity Model

Filtering
There are several high
frequency features in this
map that are removed by
filtering.
The filter used in this
example was a robust
filter set at one standard
deviation.

Data courtesy of Norsk Hydro

10.22

Smoothing

Interval Velocity Model

Filtering
This map shows the result
of the robust filtering.
Several of the high
frequency anomalies have
been removed.
Notice the fenceline
anomalies between the
green and black surveys
in the centre.
Network error adjustment
algorithms minimise such
mistie errors.
Data courtesy of Norsk Hydro

Smoothing

Interval Velocity Model

Smoothing
Almost always we find that the interval RMS velocity profiles
or maps are noisy even after editing and filtering and it is
quite common to smooth them.
Techniques which are used, depending on availability of
software, include:
spatial averaging (mean and median)
polynomial fitting,
locally weighted regression (LOESS),
kriging.

10.23

Smoothing

Interval Velocity Model

Spatial Averaging
Smoothing techniques are applied as spatial running
averages. Commonly mean and median filters are available.
In mean filtering the smoothed value is the arithmetic
average of the data points in the filter window. In mean
filtering weights may be applied to the data values - usually
inverse with distance from the centre of the filter - so that
values closer to the centre of the filter have more influence
on the result.
In median filtering the data are rank ordered and the middle
value taken.

Smoothing

Interval Velocity Model

Spatial Averaging
Circle of inclusion
Data Points
Output value
may be at the
centre of the
circle

+
Centroid - average
location where
average value
may be posted

Radius of inclusion chosen interpretively


to smooth noise but not
geologically meaningful
anomalies.
10.24

Smoothing

Interval Velocity Model

Spatial Averaging
The radius of inclusion may be determined by testing a
number of different radii centred on a well location.
The resulting smoothed velocities (with calibration if
necessary) are used to make a depth conversion which is
compared to the well data:-

ERROR

The plot of depth conversion error


against radius of inclusion
demonstrates a well behaved
minimum when the radius is about
equal to the maximum offset.
RADIUS

Smoothing

Interval Velocity Model

Spatial Averaging
Alternatives are to use a square, or
a rectangle, with dimensions of the
order of twice the maximum offset.

10.25

Smoothing

Interval Velocity Model

Spatial Averaging

C.I. = 500 ft/s

C.I. = 500 ft/s

Smoothing

Interval Velocity Model

Surface Fitting
Polynomial (trend surface) fitting can be used to smooth noisy
maps. Care is needed with smoothing techniques so that
geologically meaningful gradients (such as those seen across fault
zones as in the example below) are not smoothed out too much.

Data courtesy of Amoco

10.26

Smoothing

Interval Velocity Model

Smoothing
LOESS filtering (locally weighted regression) is available in
some software as a smoothing tool. A polynomial surface is
fitted to the data points in a window and the predicted value
at the centre of the window out-put. A hybrid approach
based on mean and median filtering and trend surface fitting.

Kriging can also be used for smoothing.

Various forms of gridding also incorporate smoothing


functionality, smoothing being some form of localized
averaging over say 9 or 25 grid nodes.

Smoothing

Interval Velocity Model

Normalization
Interval velocity is often proportional to the depth of burial
or approximately proportional to reflection time.
So that none of the variation due to this dependence is
smoothed out interval RMS velocities ought to be
normalized before smoothing when depth or time ranges
are large. The remaining variations will be due to:
the noise we wish to eliminate.
lithology (which generally varies slowly)
variation in bed thickness
pressure cells (overpressure)
tectonic inversion
10.27

Smoothing

Interval Velocity Model

Normalization
When Interval Velocity is a function of depth

VI = fn(z)
it may be normalized with respect to depth.

VNI = VIobs - fn(zobs) + fn(zN)


The depth may be burial depth, depth to mid-point, etc. The
normalization depth zN is arbitrarily chosen.
The next slide illustrates the process graphically.

Smoothing

Interval Velocity Model

Normalization
Interval Stacking Velocity (ft/sec)

16000

VNI = VIobs - fn(zobs) + fn(zN)


VNI

Variation
due to depth,
fn(z), this
may or may
not be linear.

14000

12000

10000

8000
2000

4000

6000

10.28

zN

8000

10000

Mid point
depth (ft)

Smoothing

Interval Velocity Model

Normalization
Velocity - time cross
plots before and
after normalisation /
smoothing / removal
of normalisation
process showing
how smoothing has
reduced the scatter.

Smoothing

Interval Velocity Model

Carter (1993) advises


that data points from
areas of tectonic uplift
need to be corrected for
the uplift before
normalization - and the
effect of the uplift
restored after smoothing.
This presupposes that
we know the amount of
uplift.

Interval Velocity (m/sec)

Normalization

Correction?
Or estimate of
uplift?

2000

1900
1800
1700
1600
0

100

200

300

400

500

One Way Time (msec)


Data courtesy of Amoco

10.29

Smoothing

Interval Velocity Model

Normalization
A Triassic interval
velocity map from
seismic data showing
high frequency
anomalies that are
related to the geology.
Smoothing this map
would attenuate these
variations which are
related to structure.
From Carter 1993 Leading Edge

Smoothing

Interval Velocity Model

Normalization
The depth map to the
top of the Triassic. Many
of the variations are
spatially similar to the
variations in the Triassic
interval velocity map.
This suggests that the
major variations in
interval velocity are
related to depth of burial
and should not be
smoothed.

From Carter 1993 Leading Edge

10.30

Smoothing

Interval Velocity Model

Normalization
A log-log plot of interval
velocity against depth to
mid-point for the Triassic
shows a strong linear
relationship.

From Carter 1993 Leading Edge

Smoothing

Interval Velocity Model

Normalization
The depth normalized
interval velocity map for
the Triassic. Variations
are due to: noise (high frequency),
probably lithology
(regional gradients)
possibly tectonics
(steep linear gradients).

From Carter 1993 Leading Edge

10.31

Smoothing

Interval Velocity Model

Normalization
Theoretically, the approach is complicated for functions
based on instantaneous velocity, because of the the
expression for interval velocity.
From Vi = Vo + kz the depth is given by:-

zn = Vo(eK t - 1)/K + zn-1 eK t


and the interval velocity is then

VI = (zn - zn-1) / t.
The formulae are equally complicated from Evjens and
Fausts formulae.

Smoothing

Interval Velocity Model

The smoothed interval RMS


velocities may be used in
depth conversion, event
migration or map migration of
interpreted time horizons to
generate a first
macrovelocity model.

From a Schlumberger GeoQuest brochure

10.32

Quality Control

Interval Velocity Model

Work Flow
Interval
RMS
Velocities

Dix
INTERPRETATION

Bias
correction

DIP
CORRECTED
STACKING
VELOCITIES

INTERPOLATION

DIP CORRECTION

STACKING
VELOCITIES

RMS
Velocities

HORIZON
CONSISTENT
STACKING
VELOCITIES

Quality Control

Interval Velocity Model

The First Macrovelocity Model


The general scheme for building the first model is as follows:

Interval
RMS
Velocities

INTERPRETATION

Depth
Conversion
(or Ray
Migration)

Dix
Compare
& Adjust
Model

RMS
VELOCITIES

STACKING
VELOCITIES

Forward
Model

10.33

INITIAL
MACROVELOCITY
MODEL

Quality Control

Interval Velocity Model

The First Macrovelocity Model


The original data have been corrected, edited,
smoothed and inverted in the process of deriving our
macrovelocity model.
What techniques are you familiar with for ensuring that
the macrovelocity model obtained from the seismic data
is consistent with the data themselves?

Quality Control

Interval Velocity Model

Stacking Value Matching


This technique ensures a macrovelocity model consistent with
the available data. It is suitable when original seismic tapes are
not available. The time picks and model velocities are iteratively
adjusted so that stacking velocity hyperbolae and modelled
moveouts are in acceptable agreement.
INITIAL
MACROVELOCITY
MODEL

OBSERVED
STACKING
VELOCITIES

MODEL OF
GATHER

To

Model
(Offset
Raytrace)

Time Horizons
and Modelled
Stacking
Velocities

Stacking
Velocity
Hyperbola

Model
Moveout
OPTIMIZE MODEL

10.34

REFINED
MACROVELOCITY
MODEL

Quality Control

Interval Velocity Model

Travel Time Inversion - Tomography


This optimisation technique ensures that the macrovelocity
model built from smoothed interval RMS velocities is still
consistent with all of the original data.
This technique is often implemented under the name of
travel time inversion. The optimisation of the offset raytraced model is a form of tomography.
The initial macrovelocity model will only be as good as the
original stacking velocity values, if they are inaccurate then
the optimised model will reflect the inaccuracy - not remove
the inaccuracy.

Summary

Interval Velocity Model

Before stacking velocities can be used to determine interval


RMS velocities they may require a dip correction.
A bias correction may be required if the maximum offsets
exceed 1500m or if there are large velocity contrasts between
formations.
It may be necessary to interpolate the RMS velocities. Any
interpolation should seek to take account of the interval velocity
model.

10.35

Summary

Interval Velocity Model

Interval RMS velocity maps may be derived from stacking


velocities by Dix equation.
The resultant maps will require editing and smoothing.
If the range of values is large, or changes abruptly,
normalization may be desirable prior to smoothing.
A number of techniques are available for smoothing.
After smoothing the resultant depth model ought to be
optimised with respect to the picked reflections and their
associated stacking velocities.

10.36