JSA WORKSHEET Appendix 1

Area of Work Considered: A-2401 Cooling Tower Project: ____ Project No.____________________

1) 2 3) 4)
5) 6 8)
JSA Participants: 9) 10) 7) 12)

11)

Job location and details A-2401 Cooling Tower Pond Cleaning

Prepared By:
Distribution:
Reviewed By:

Type of Permit Required Additional PPE Requirements


Special tools or equipment required
(Please indicate by ticking box) (Please list)
Gum Boot
1) Shovels 5)
Disposal Coverall 2) Scrappers 6)
Cold work permit
Isolation Certificate 3) Vipers 7)
Confined space 4) 8)

JSA Review Process Y N Comments


Was the work crew involved in formulating the JSA?
Did the work crew review the JSA prior to task? Y
Was the JSA referred to during the task? Y
Were the job steps followed?
Can you suggest improvements to the JSA? (Provide details)
Provide details of any incidents

Reviewed by: Signature: Date:

INCIDENT SUMMARY

Report
PROCEDURE FOR WORK PLACE RISK ASSESSMENT

Situation/Activity Hazards Identified Controls & Checks Required Action By

• Water overflow in ditch • Drain in control manner through main drain header.
• Contaminated water on • Drain in the ditch and then pump out to ground
ground • Report spills in the ground
Draining of the Cooling Tower Mechanical /
• Slip in the pond • Use gum boots around pond walls walking.
pond Production
• Do not allow unskilled labor to climb pond walls
without supervision

• •
Isolation of equipment • Failure to isolate • Identify and isolate the P-2411A/B/C Mechanical /
• Pump damage • Lock and chain the inlet lines Production
• • Make sure the Circulation lines are empty.
• • Make sure plant is in isolated condition else blind the Electrical
• water Inlet outlet lines
Opening of Tower Louvers • Falling in the pond • Make sure the standing surface is dry Mechanical /
• Improper tools • Make sure body posture is not too much leaning Production
• Unskilled manpower forward
• • Right tool for the specific job
• Skilled manpower
Entry in First Pond to remove • Confine space entry • Obtain Confine space entry certificate Mechanical /
sludge / • Fluid in flow from somewhere • Make sure isolation is properly done Production
Piping Nozzle inspection / • Work at Night • Check O2 level and LEL before entry.
cleaning • Oxygen deficiency • Place one detector inside for continuous monitoring
• H2S in the bottom • Entry attendant
• Sludge • Rescue equipment on site.
• Slipping • External communication available
• Algae and fungus • Inform ERT for vessel entry
• Residual chemicals • Not more then 2 person in each pond section
• Bad weather, Temperature • Proper Lighting if sun sets.
• Heat related disorders • Wear Gum boots
• Physical Exhaustion • Wear Disposal coveralls
HSEQ-PK-11-06-00 Page 2 of 4 /opt/scribd/conversion/tmp/scratch2653/31902694.doc
PROCEDURE FOR WORK PLACE RISK ASSESSMENT

• High wind. • Avoid skin contact


• Snake & Scorpion Bite • Wear splash Goggles
• Work In night • Wear Rubber Gloves. Dispose sludge in Hazard waste
• H2SO4 chemical injection • Use basic PPE’s and additional PPE identified in PTW
• Adequate drinking Water / ORS
• Do not over exhaust crew
• Stop Maintenance activities in severe weather
condition.
• No lonely person at work
• Provide adequate lighting for night.
• Isolate H2SO4 pump
Second Pond entry for Sludge • Confine space entry • Obtain Confine space entry certificate Mechanical /
removal / • Fluid in flow from somewhere • Make sure isolation is properly done Production
Piping Nozzle inspection / • Work at Night • Check O2 level and LEL before entry.
cleaning • Oxygen deficiency • Place one detector inside for continuous monitoring
• H2S in the bottom • Entry attendant
• Sludge • Rescue equipment on site.
• Slipping • External communication available
• Algae and fungus • Inform ERT for vessel entry
• Residual chemicals • Not more then 2 person in each pond section
• Bad weather, Temperature • Proper Lighting if sun sets.
• Heat related disorders • Wear Gum boots
• Physical Exhaustion • Wear Disposal coveralls
• High wind. • Avoid skin contact
• Snake & Scorpion Bite • Wear splash Goggles
• Work In night • Wear Rubber Gloves. Dispose sludge in Hazard waste
• H2SO4 chemical injection • Use basic PPE’s and additional PPE identified in PTW
• Adequate drinking Water / ORS
• Do not over exhaust crew
• Stop Maintenance activities in severe weather
condition.
• No lonely person at work
• Provide adequate lighting for night.
• Isolate H2SO4 pump

HSEQ-PK-11-06-00 Page 3 of 4 /opt/scribd/conversion/tmp/scratch2653/31902694.doc


PROCEDURE FOR WORK PLACE RISK ASSESSMENT

Washing of the both pond • Unskilled manpower • Wear Gum boots Mechanical /
section • Slipping • Wear Disposal coveralls Production
• Avoid skin contact
• Wear splash Goggles
• Wear Rubber Gloves during water collection
• OMV supervision at all times
Filling of the pond • Trapped Manpower inside • Make sure all permits are closed and filling is Mechanical /
• Leakage of the pipe authorized by permit controller. Production
• Water loss • Before filling physically confirm no manpower or
material is inside the pond.
• Make sure all drained closed

HSEQ-PK-11-06-00 Page 4 of 4 /opt/scribd/conversion/tmp/scratch2653/31902694.doc