Académique Documents
Professionnel Documents
Culture Documents
On
14/10/2015
Licensed copy from CIS: uninorth, University of Northumbria, 14/10/2015, Uncontrolled Copy.
Licensed copy from CIS: uninorth, University of Northumbria, 14/10/2015, Uncontrolled Copy.
1989.
INTRODUCTION
All participants in construction projects
take risks. Contractual provisions
distribute risks between the parties who,
in turn, seek compensation, usually
financial, for the risks which they assume.
However, despite the acknowledged
importance of risk bearing and
consequent compensation, assessments
are quantitative only rarely - experience
plays the major role.
a
b
a'
a"
Licensed copy from CIS: uninorth, University of Northumbria, 14/10/2015, Uncontrolled Copy.
WORLD
RISK MANAGEMENT
Management of risk involves four primary
steps:
l
l
l
l
risk identification;
risk quantification;
risk allocation;
risk response.
and
Risk quantification
By definition, quantification can be applied
Risk identification
What constitutes a risk (or uncertainty)
may depend upon which project
participant is considering the situation.
However, the overall areas of risk (time
and cost over-runs and quality problems)
are common to all participants. Thus, if
the identification of risks is common
ground, the differentiations must lie in the
other aspects of risk management.
Risks and uncertainties have many
sources and can be classified in various
ways. An important concept is to identify
which risks can be controlled and those
which cannot. A projects environment
can be viewed as a stratified hierarchy of
risks, as shown in Figure 2.
At any level of the hierarchy, risks due to
Licensed copy from CIS: uninorth, University of Northumbria, 14/10/2015, Uncontrolled Copy.
variance;
standard deviation;
semi-variance;
coefficient of variation.
a = P- O
6
if O and P are determined as O and 100
percentile points.
More realistically, if O and P are
determined as 5 and 95 percentile points
then the standard deviation is:
P - O
3.2
EMV
-100
0.05
-5
20
0.20
80
0.50
40
140
0.20
28
260
0.05
13
1.00
80
PROFIT/LOSS
Sensitivity analyses
What if? questions are of increasing
importance to managerial decision
making. Computer techniques (packages)
facilitate answers to such questions but it
is essential not to lose appreciation of the
basic data used and assumptions made.
Sensitivity analysis seeks to answer the
what if? question through isolating the
key variable(s) and evaluating the effects
assuming
a
risk,
the
more
compensation is required for its
assumption
Licensed copy from CIS: uninorth, University of Northumbria, 14/10/2015, Uncontrolled Copy.
Risk allocation
(i)
Licensed copy from CIS: uninorth, University of Northumbria, 14/10/2015, Uncontrolled Copy.
Risk response
Response is linked closely to risk
allocation, particularly as risks can be
passed back (a contractor returning
tender documents). A common form of
risk response is compensation, usually
monetary - increasing the price - the
more risk averse the constructor is, the
greater the price increase to compensate
for the risk assumption will be.
Responses to risk allocation occur in five
ways:
l
l
l
l
l
Remove
Reduce
Avoid
Transfer
Accept
PORTFOLIO EFFECT
Licensed copy from CIS: uninorth, University of Northumbria, 14/10/2015, Uncontrolled Copy.
CONCLUSlONS
Many quite straightforward techniques
are available to assist in the
management of risks. The process of risk
management employs a variety of
techniques to facilitate identification,
quantification and allocation of risks and
to determine appropriate responses.
Despite the obvious advantages of using
risk management, there is little evidence
yet of its application by the construction
industry.