Académique Documents
Professionnel Documents
Culture Documents
1.0 INTRODUCTION
Out of the estimated 15000-16000 MW of power transfer requirement from Raigarh (Kotra),
Champa, Raigarh (Tamnar) and Raipur generation complex in Chhattisgarh, about 5000 MW
power is indicated for transfer to Northern region. Considering the long distance viz. approx.
1300 km as well as quantum of power transfer requirement to NR from IPP generation
projects in Chhattisgarh, it is proposed that power from IPP generation projects in
Chhattisgarh can be transferred over HVDC system. Initially the system shall be able to carry
3000 MW of power although provision to upgrade the HVDC Bipole to 6000MW at a later
date shall also be kept. Development of such HVDC transmission corridors shall facilitate in
establishing transmission corridors with hybrid technology. This shall also facilitate in
meeting controlled power flow requirement, flexibility of operation as well as maintaining
system parameters within limits through its control mechanism.
Presently, almost all the HVDC Bipole lines in India & abroad are being constructed with
earth electrode lines earthed at earth electrode station. However design of such earth
electrode stations is associated with a lot of uncertainties w.r.t. the magnitude of the ground
currents & its anticipated path. As a result, ground currents appear unexpectedly, thereby,
severely impacting electrical installations, oil & natural gas pipelines, railway lines, hand
pumps & water bodies. Existence of rocky surfaces & low water table in vast stretches of
land near Champa & Kurukshetra ends have made the selection of suitable site for earth
electrode station all the more difficult.
Considering such constraints with respect to the environmental impact of earth electrode
station as well as right of way requirement of earth electrode lines, POWERGRID has opted
for using Dedicated Metallic return with 2X Twin Lapwing conductors running on the same
tower. Although, separate towers for DMR running all along the Bipole line between the
converter stations would also have been a viable alternative and would have lesser
complicacies wrt insulation design. However, this would have considerable environmental &
financial impact as separate ROW would have been required.
However, installation of DMR on same tower has severe consequences for DMR insulator
string for which the string must be designed. Some of such constraints are occurrence of
backflashovers on DMR during pole backflashovers; Transfer surges due to pole-ground
1 | Page
fault; switching type overvoltages on the DMR due to system start up, system shut down and
converter commutation failure.
The paper elaborates the step-by-step procedure involved in design of +/-800 kV HVDC
Champa-Kurukshetra Bipole line with DMR and the various aspects taken into account for
integration of DMR on the Bipole line.
2 | Page
Increase in the total project cost due to inclusion of DMR instead of ground return mode is
quite marginal viz. 5 to 6 %. Further, the % losses in DMR vis--vis total line losses in the
HVDC line during bipole operation is entirely negligible. Even the increase in % losses due
to usage of DMR instead of earth return during contingencies result in a very marginal
additional losses (approx. 2 % of total line losses in the HVDC line assuming 10 days/year of
monopolar operation with one pole under maintenance/shutdown)
Conductor Bundle
Nominal
carrying
current Short
term
current
1.
(corres. To 85C)
4 X 802 A = 3208 A
To 95C)
4 X 940 A = 3760 A
2.
4 X 935 A = 3740 A
4 X 1100 A = 4400 A
3.
4 X 1035 A =4140 A
4 X 1222 A = 4888 A
4.
6 X 706 A = 4236 A
6 X 825 A = 4950 A
From the table above, it can be seen that Quad Bersimis marginally misses the required
nominal current carrying capacity. Further, Quad Lapwing easily meets the nominal current
capacity requirement. Additionally, it can be seen that Quad Lapwing conductor meets the
requirement of reduced voltage operation withion its nominal current carrying capacity itself
thereby elevating the reliability of the high capacity bipole line.
3 | Page
In view of the above, Quad Lapwing conductor was selected as the most optimal conductor
bundle from amongst the selected conductor bundles for DMR.
B. Tower Geometry w.r.t. Placement/ Position of DMR
After the selection of conductor bundle for DMR, following alternative tower configurations
with DMR have been analysed.
i)
Alternative 1: 2 X Twin Lapwing DMR above the conductors and below each
earthwire.
Advantages:
a) Increased mechanical reliability of DMR i.e. when one of the conductor
bundles is damaged/under maintenance, the other conductor bundle will
continue to provide conduction path for the leakage current.
Further, during monopolar operation also (with one pole damaged/under
maintenance) if one of the DMRs will suffer damage, flow of power atleast
4 | Page
1/4th of the total bipole power can be continued, thus furthering the reliability
of the bipole system.
b) Ease of Line maintenance under one pole shutdown with the other pole in
operation (one DMR & one pole under shutdown)
ii)
Advantages
a) Existing +/-800 kV HVDC tower design could be used.
b) Better lightning protection for DMR
c) Least weight among alternatives
iii)
5 | Page
Advantages
a) Existing +/-800 kV HVDC tower design could be used.
b) Good lightning protection for DMR
c) Comparatively less weight
iv)
Advantages:
a) Increased mechanical reliability of DMR i.e. when one of the conductor
TABLE 2
A Summary of parameters corresponding to each alternative
7 | Page
ALT -1
ALT-2
ALT -3
ALT-4
Tower
Height 57
53.5
53.5
53.5
(mtrs.)
Estimated
Tower 38
36
37
37
weight(MT)
ROW Requirement 69
69
69
74
(mtrs.)
Salient Advantages
1) Increased
1) Least weight
1) Increased
mechanical reliability
among
mechanical
of DMR
alternatives
reliability of DMR
2)
Ease
of
maintenance
Line
under
In view of the above mentioned advantages of Alternative 1 and its conventional tower
geometry, the Alternative 1 has been finalised for +/-800 kV HVDC Champa-Kurukshetra
line with DMR conductor.
C. Insulator Requirement
The Dedicated Metallic Return Conductor at the inverter end shall be grounded and the other
end shall remain floating (ungrounded). Therefore, a certain potential corresponding to the
leakage current through DMR during bipolar operation shall exist at all points of DMR
(except the grounded end) with the magnitude maximum at the floating end. This potential
shall be highest during monopolar mode of operation with only DMR as the return conductor.
With the maximum design value of 4126 A & the line length of approx. 1300 km, this
potential at the floating end of DMR has been calculated to be approx. 64 kV DC. An
insulation level of 110/132 kV AC has therefore been adopted in view of the higher
requirement for equivalent AC system and the next available rating. Had the DMR been
constructed on separate transmission line towers, the insulation design considering DMR
voltage drop of 110/132 kV AC i.e. for Lightning Impulse withstand level (LIWL) of 650
kVp. Thus, 9 insulator discs for suspension towers would have been sufficient.
However, the case is not so and the DMR is to be placed on the same bipole tower. Therefore,
following additional aspects have also been considered in the insulation design for DMR:8 | Page
9 | Page
insulator is decided on the basis of UTS of the conductor. 210 kN insulators shall be required
for both types of strings.
10 | P a g e
Corona performance has been evaluated by considering bipolar as well as unipolar mode of
operation & it has been observed that worst results are obtained during unipolar mode itself
because of the presence of only one type of space charge.
It has also been observed that DMR conductor bundles produce screening effect, leading to a
reduction of the electric field on the ground wires. Therefore, compared to the +/- 800 kV
HVDC NER-Agra Bipole line with earth electrode, the ground wire surface gradients of the
+/- 800 kV HVDC Champa-Kurukshetra Bipole line with DMR are much lower under
bipolar as well as unipolar modes of operation.
4. CONCLUSION
From the various studies carried out for design of +/- 800 kV HVDC Champa-Kurukshetra
Bipole transmission line, it is observed that provision of DMR instead of ground return as
well as integration of DMR on bipole towers is a prudent solution to the uncertain soil
characteristics, low reliability & manifold issues associated with earth return. Such a higher
reliability, greater controllability & greater operational flexibility are the key advantages of
such an important high capacity link which has tremendous bearing on the health of national
grid & Indian power system.
11 | P a g e