Design and Construction

of Rock Socketed Piles


in Land Conditions
Manfred Schpf
BAUER Maschinen GmbH Schrobenhausen

Workshop
Deep Foundation Technologies for Infrastructure Development
in India
November 14, 2013, IIT Bombay Campus, MUMBAI
BAUER Maschinen GmbH, D-86529 Schrobenhausen

Agenda
Design aspects
Reference to international standards

Plant and Equipment


Effective use of drilling tools
Project references
Productivity

Logistics aspects
Health and safety features
Automation
BAUER Maschinen GmbH, D-86529 Schrobenhausen

Bangalore
Metro
Text
Typical bore log

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Depth-Time diagram Pier P 354

other drilling rig

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Questions
How to avoid unefficient work
drilling depth too deep because of rig power (Example 1)
using chisel for rock socketing (Example 2)
using combined system to save expensive drill rig (Example 2)
Definition of termination criteria for rock socket with rotary drilling rig

2
1

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Design German practice

Every structure has to be classified in Geotechnical Categories GC


GC 1 GC 3

for GC 2 GC 3 a geotechnical expert has to decide if base


pressure alone or base pressure + shaft resistance can be
assumed

based on soil report


decision cannot be made by piling contractor

pile design can be made on the basis of empiric values


DIN 1054: 2010-12 Baugrund Sicherheitsnachweise im Erd- und Grundbau
EAPfhle (2012) Empfehlungen Arbeitskreis Pfhle" der DGGT e.V.

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Design Experience values in German Code


unconfined compressive
strength quk
(MN/m)

base resistance
(MN/m)

ultimate shaft resistance


(MN/m)

0,50
5,00
20,00

1,50
5,00
10,00

0,08
0,50
0,50

Table B.5 Pile base resistance qb,k and shaft resistance qs,k in rock
(DIN 1054-2005)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Design Experience values in German Code


unconfined compressive
strength quk
(MN/m)

base resistance
(MN/m)

ultimate shaft resistance


(MN/m)

0,50
5,00
20,00

1,50 2,50
5,00 10,00
10,00 20,00

0,07 0,25
0,50 1,00
0,50 2,00

Range of experience values


for Pile base resistance qb,k and shaft resistance qs,k in rock
(EA Pfhle 2012)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Design German Practice


simplified example (for soil)
empiric values
DIN tables

1m
3

10

Fill

Sand
q (CPT) = 7,5 MN/m

highly weath. rock


UCS = 0,5 MN/m

friction
qsk = 0

Rsk = 0

friction
qsk = 0,05 MN/m

Rsk = 1,57 MN

friction
qsk = 0,07 MN/m

Rsk = 0,67 MN

base
qbk = 1,5 MN/m

Rbk = 1,17 MN

Rtot, ult. = 3,4 MN

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Design German Practice


simplified example (for soil)
0,4

srg = 0,5xQrg+0,5
= 1,6 cm

1,2

2,8

3,4

4,2 [MN]

Qall= 1,7MN

1
2

2,0

Qall= 1,3MN

3
4
5
6
7
8

sg = 0,1x
= 10 cm

9
10
[cm]

F.S.= 2

BAUER Maschinen GmbH, D-86529 Schrobenhausen

10

Design Hongkong Practice


The Code of Practice for Foundation
(Building Department BD)
for all private structures
Housing Department or Architectural Service
Department (ASD)
for all public structures.
Additional: Civil Engineering Development
Departments (CEDD).
They all follow in principle the codes of BD.
ASD more stringent requirements such as:
Minimal socket length 0,6 m
Pile resistance only in base
BAUER Maschinen GmbH, D-86529 Schrobenhausen

11

Design Hongkong Practice


(Clause 2.2)

Allowable bearing capacity for non-driven piles shall be determined by:


Rational Design Method:
interpretation of the results of the site investigation
assessment of test results []
analysis based on the laws of physics and recognized engineering
principles. Normally a factor of safety of 3 is applied.
Presumed values
allowable capacity may be taken as presumed values derived from
empirical correlations
Table 2.1 for allowable vertical bearing pressure
Table 2.2 for allowable friction between rock and concrete

BAUER Maschinen GmbH, D-86529 Schrobenhausen

12

Design Hongkong Practice


Presumed allowable vertical bearing pressure
Category Rock (granites & volcanics)

Presumed bearing
pressure (kPa)

1 (a)

Fresh strong to very strong rock GRADE I


100% total core recovery, no weathered joints
minimum uniaxial compressive strength 75 MPa

10,000

1 (b)

Fresh to slightly decomposed strong rock GRADE II


> 95% total core recovery
minimum uniaxial compressive strength 50 MPa

7,500

1 (c)

Slightly to moderately decomposed moderately


strong rock GRADE III
> 85% total core recovery
minimum uniaxial compressive strength 25 MPa

5,000

1 (d)

Moderately decomposed, moderately strong to


moderately weak rock GRADE IV,
> 50% total core recovery

3,000

BD 2004 Table 2.1


BAUER Maschinen GmbH, D-86529 Schrobenhausen

13

Design Hongkong Practice


Presumed allowable friction for piles
Category Rock (granites & volcanics)

Presumed friction
(kPa)

1 (c)
Slightly to moderately decomposed moderately
or better strong rock GRADE III
> 85% total core recovery
minimum uniaxial compressive strength 25 MPa
1 (d)
Moderately decomposed, moderately strong to
moderately weak rock GRADE IV,
> 50% total core recovery

700

300

under compression or transient tension

BD 2004 Table 2.2


BAUER Maschinen GmbH, D-86529 Schrobenhausen

14

Design Minimum socket length


Comparison of international codes
Country

Condition

min. socket length (m)

Germany
(EA Piles)

quk 5 MN/m
quk 0,5 MN/m

0,5 m
2,5 m

Hongkong
(BD 2004, 2.2.2)

Grade I (UCS >75 Mpa)


Grade II (UCS >50 Mpa)
Grade III (UCS >25 Mpa)

0,5 m
0,5 m
0,3 m
0,6 m

(ADS 2012)
USA
(IBC 2009)

min. 1

UK
Australia

no values stated

India
(IRC 78-2000)

UCS >12,5 Mpa


UCS 2,5 12,5 MPa

0,6 m
1,5 m

BAUER Maschinen GmbH, D-86529 Schrobenhausen

15

Design Termination Criteria


Germany
no criteria in code, if rock is harder than stated in SI: check condition with
geotechnical consultant with possibility of
modifying pile design (bigger diameter, 2 piles instead of one)
increasing bearing values with resulting shorter socket length
USA
no general criteria, earlier termination can be reached by a specific alternative
proposal or based on pile test results
Australia
no general criteria, rule of thumb (not backed up in codes: terminate if progress
< 100 300 mm/h
Comment: dangerous as general rule (rock condition, diameter, type of drilling
system, ability of operator!!!)
UK and Hongkong
no general criteria
BAUER Maschinen GmbH, D-86529 Schrobenhausen

16

Design Termination Criteria


India
Pile termination criteria as a quality control tool in rocks
IRC: 78-2000 (established initially for driven piles)
For bored piles:
Basis of consideration Pile Penetration Ratio (PPR)
PPR = (2*n*T*t) / (A*P)
and
HP (of rig) = (2*n*T) / 4.5
Ganpule (2005)
Dr. S. Basarkar

Comments of an equipment manufacturer and


foundation engineer

BAUER Maschinen GmbH, D-86529 Schrobenhausen

17

Design Termination Criteria


India
Results of formulae are only reliable if the input data are created in a
reproducible manner with standardized procedures and components.
Engine power:

only valid for one specific rig


rated power = theoretic value
actual efficiency: 30% - 60%
actual HP may vary from rig to rig
efficiency 10% during operation

Efficiency hydraulic system

BAUER Maschinen GmbH, D-86529 Schrobenhausen

18

Design Termination Criteria


India
Results of formulae are only reliable if the input data are created in a
reproducible manner with standardized procedures and components.
Influence of tool:

type of tool, status of wear


not standardized or normalized

Operator:

human factor, qualification


rough or smooth operating style
T

n
BAUER Maschinen GmbH, D-86529 Schrobenhausen

19

Termination criterion Visual inspection

gravel, pebbles, cobbles

rock cuttings

only indicative requires geotechnical experts approval

BAUER Maschinen GmbH, D-86529 Schrobenhausen

20

10

Drill rig BG
Main components
Kelly bar
3 4 parts (telescopic)
carries drilling tool
transfer M and V

Mast
torsion resistant
Extensions
Mast head
Connection base carrier

Rotary drive (KDK)


slides vertically
on mast
M = 120 500 kNm

Winches
Main winch
Auxil. winch
Crowd winch
(reeved)

Drilling tools
type and dimensions
variable
depends on
soil and pile design

170 600 kN
40 170 kN
200 600 kN

Base carrier
on crawlers
Engine
Hydraulic station

Controls
electronic
hydraulic

BAUER Maschinen GmbH, D-86529 Schrobenhausen

21

Development Drilling depth

1.

Kelly bar
Depth = 3 4 x A - overlap

BAUER Maschinen GmbH, D-86529 Schrobenhausen

22

11

Bauer Kelly System

Interlocking Kelly Bar

Friction Type Kelly Bar

standard 3- 4 part kelly bar


practical depths: 80 m
with 4 part kelly bar

not lockable
standard 5 fold kelly bar
(reduced torque)
max depths: 100 -110 m

Mechanical interlock
Friction surface

BAUER Maschinen GmbH, D-86529 Schrobenhausen

23

Rock Drilling Tools


for
BG Rigs

24

BAUER Maschinen GmbH, D-86529 Schrobenhausen

12

Kelly Drilling

Drilling with auger in dry soil


(typical sand, gravel, clay, weathered rock)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

25

Kelly Drilling

Penetrating rock layers or cemented layers with core barrel

BAUER Maschinen GmbH, D-86529 Schrobenhausen

26

13

Kelly Drilling

Drilling with bucket below groundwater level


(typical sand, gravel, clay, weathered rock)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

27

Kelly Drilling

What tools for socketing into rock?


BAUER Maschinen GmbH, D-86529 Schrobenhausen

28

14

Kelly Drilling Selection of tools

BAUER Maschinen GmbH, D-86529 Schrobenhausen

29

Rock Augers
moderately strong to
strong not laminated
rock
(10 100 MPa)
uncased bores or for
bigger diameters

Single cut auger with pilot bit

Tapered auger

very dense sand and gravel,


weak rock up to 20 MPa
very good for pile walls

Double cut auger


without pilot bit

moderately weak to
moderately strong
rock (5 50 Mpa)
very suitable in fractured
rock
BAUER Maschinen GmbH, D-86529 Schrobenhausen

30

15

Drill buckets

BAUER Maschinen GmbH, D-86529 Schrobenhausen

31

Tools Suitability of teeth types

BG operation

Excavator operation

3- dimensional movement

2- dimensional movement

BAUER Maschinen GmbH, D-86529 Schrobenhausen

32

16

Tools Flat teeth


Why special BG Flat Teeth?

Bauer Flat Tooth

Standard Flat Tooth

variable cutting angle


adaption to soil condition possible
tooth holder turnable

fixed cutting angle


no adaption to soil condition
tooth holder allows a fix position only
BAUER Maschinen GmbH, D-86529 Schrobenhausen

33

Tools Flat teeth

steep angle for hard soil conditions

flat angle for soft soil conditions

BAUER Maschinen GmbH, D-86529 Schrobenhausen

34

17

Tools Positioning of flat teeth


center of each tooth is located on
an exact reference circle on the tool

bearbeiten

midth of cutting shape creates


an 90 angle with tangential line
reference circle
elongation of cutting edge
to run through the center

BAUER Maschinen GmbH, D-86529 Schrobenhausen

35

Tools Positioning of flat teeth

correctly positioned teeth result in:


complete cutting edge is working

homogeneous wear and tear

outside teeth transfer soil into bucket

optimal filling of bucket

outside teeth create annulus

reduction of friction

BAUER Maschinen GmbH, D-86529 Schrobenhausen

36

18

Tools Positioning of flat teeth


unfavourable setting of teeth (example FZ 80)

elongination of cutting edge does not


guide through center of tool

inhomogeneous wear and tear

BAUER Maschinen GmbH, D-86529 Schrobenhausen

37

Tools Round shank chisel (bullet teeth)


exact three dimensional positioning
of the round shank chisel is essential for a proper function of this tool !!
8 - 30

cutting angle

inclination to ensure
rotation
BAUER Maschinen GmbH, D-86529 Schrobenhausen

38

19

Tools Round shank chisel positioning

side inclination of chisel to


ensure rotation
homogeneous wear
at chisel
increased lifetime of
chisel

39

BAUER Maschinen GmbH, D-86529 Schrobenhausen

39

Rock Drilling with Kelly


New bullet tooth

Used bullet tooth

Used in abrasive soil


Bullet tooth did not
turn
Tungsten carbide not
worn
Holder is probably
destroyed

BAUER Maschinen GmbH, D-86529 Schrobenhausen

40

20

Core barrel

BAUER Maschinen GmbH, D-86529 Schrobenhausen

41

Core barrel

round shank chisel with up to


four different positions,
in order to create an uniform
annulus

4
3

2
1

BAUER Maschinen GmbH, D-86529 Schrobenhausen

42

21

Roller bit core barrel

Suction pipe

BAUER Maschinen GmbH, D-86529 Schrobenhausen

43

Roller bit core barrel


pressurized air

flush head
pressurized air

compressor

lockable
kelly bar

roller bit
core barrel
BAUER Maschinen GmbH, D-86529 Schrobenhausen

44

22

Roller
bitder
core
barrel
Ziele
Bodenverbesserung
Destroying of core

rock auger

OR

cross-cutter

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Cross-Cutter

BAUER Maschinen GmbH, D-86529 Schrobenhausen

46

23

Rock Drilling with Kelly

BG 36 # 1366 - Dura/ South Africa


Drilling Rig:

BG 36

Drilling depth:

25 - 45 m

Drilling Diameter:

1.350 mm

Drilling system:

Kelly, uncased

Rock strenght:

250 - 350 mpa

Performance:

25 cm/ h

BAUER Maschinen GmbH, D-86529 Schrobenhausen

47

Rock Drilling with Kelly


BG 40 # 988 - ZAP/ Singapore

48

Drilling Rig:

BG 40

Drilling depth:

45 m

Drilling Diameter:

1350 mm

Drilling system:

Kelly, uncased

Rock strength:

250 mpa

BAUER Maschinen GmbH, D-86529 Schrobenhausen

48

24

Roller bit tools with air flushing


Casing
drive
adapter
Kelly bar
Flushing
head

Advantage

Disadvantage

easy adaption
rock strength up to
250 MPa
little air consumption
780 1800 mm
quick discharge
(FFC)

solid rock required


water needed
high crowd force
required
not suitable for
boulders

Full face
cutter
Full Face Cutter FFC

Roller bit core barrel


49

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Full Face Cutter


Project reference Finland
Bored piles for bridge foundation
Diameter:

1500 mm

Pile length:

6 -25 m
inclined piles 6
dipping level of
bedrock

strength:

> 150 Mpa


increasing with depth
socket length: 1-3 m

BAUER Maschinen GmbH, D-86529 Schrobenhausen

50

25

Full Face Cutter


Project reference Finland

0,5

1,5

1,0

drilling progress
[cm/min]

0,5
1,0
1,5

socket
length [m]

1,2 m socket length => 2 hours


average advancement 0,6 m/h
vertical pressure required approx. 60 t
vertical pressure available approx. 30 t
51

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Rock Drilling
How to cope with boulder and Granite?
0m

Fill
3m

Boulders
100 MPa

Typical project
Diameter

1500 mm

Boulders from 3 to 23 m
Rock socketing in Granite
Options

10 m

Sand and
boulders

Conventional tools?

No

Roller bit tools?

No
Solution

Multi single down the hole hammer


23 m

Granite
250 MPa
BAUER Maschinen GmbH, D-86529 Schrobenhausen

52

26

MHD Cutting edge technique for rock

53

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Rock Drilling
How to cope with boulder and Granite?
Typical project

0m

Fill
3m

Diameter

1500 mm

Boulders from 3 to 23 m
Boulders

Rock socketing in Granite

100 MPa
10 m

Sand and
boulders

23 m

Granite
250 MPa

Watch the boulders


laying in soft spots
BAUER Maschinen GmbH, D-86529 Schrobenhausen

54

27

MHD Cutting edge technique for rock

+/- 360

Chippings get
flushed upwards

View into Calyx Basket

Advantage: No Air swivel required!


BAUER Maschinen GmbH, D-86529 Schrobenhausen

55

MHD Cutting edge technique for rock


Key advantages

1. Can be attached to Kelly bar (no drill pipes required)


2. No impact into the rotary drive or Kelly bar
3. Boulders any size can be drilled
4. Rock up to 300 MPa and above
5. Dry boreholes are most suitable
6. Uniform hammer and bits for every diameter
Economical bit costs
BAUER Maschinen GmbH, D-86529 Schrobenhausen

56

28

Multi Hammer Drill Case study


secant pile wall
Quantity
Depth
Rock socket

135 no / dia 1180 mm


25 m
Fully cased to 18 m
7 m in Sandstone
150 - 170 MPa

Performance MHD 7 m rock drilling


2 h 20 min (3 m/h)
including emptying calyx basket
Wear and tear
maintenance after 120 m rock
exchanged bits and chucks
Comparison

secondary piles
(with concrete overcut)
with rock auger on BG 40.
1,20 m in 2 hours (0,6 m/h)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

57

Multi Hammer Drill Case study


PROJECT:

Hot Rolling Processing


Facility, Pittsburgh, PA

DIMENSIONS:

128 Holes / dia 1067 mm


19m Overburden
7m Rock Socket
(UCS > 150 MPa

EQUIPMENT:
Calweld Rotary Attachment and Flushing Air
Kelly

Performance in rock: 2,9 m/h

BAUER BG 36 and BG 40
installing 19m of 1080 mm Segmental Casing

BAUER Maschinen GmbH, D-86529 Schrobenhausen

58

29

MHD Cutting edge technique for rock


Limitations

MHD
Only this one
is working

These 2 do
not exhaust
the air

casing

DRILLING DIPPING ROCK SURFACE?

Yes, it is possible

MHD does not require high crowd force

Start with little crowd force until bottom is


flattened

Good indicator is the air pressure

Dipping rock

BAUER Maschinen GmbH, D-86529 Schrobenhausen

59

MHD Cutting edge technique for rock


Limitations

DRILLING UNDER WATER?

Yes, it is possible
The hydrostatic pressure must be considered when chosing
air compressors
High pressure air compressor required for water depth > 12m

BAUER Maschinen GmbH, D-86529 Schrobenhausen

60

30

MHD Cutting edge technique for rock


Limitations

DRILLING UNDER BENTONITE

No, the standard MHD cannot be used


under bentonite slurry, if there is no
casing!

use segmental casings or even a casing


liner (no bentonite in the borehole)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

61

Project Reference BG 38
KL MRT Piling Project, Malaysia 2013

BAUER Maschinen GmbH, D-86529 Schrobenhausen

62

31

Project Reference Rock


KL MRT Piling Project, Malaysia 2013
KR-R 900
for pilot hole drilling

BAUER Maschinen GmbH, D-86529 Schrobenhausen

63

Project Reference Rock


KL MRT Piling Project, Malaysia 2013

Ordinary sandstone

Sandstone with
quartzite

3 piles during site visit,


all hit the sandstone with
quartzite
from 4m down to 12~14m!
Estimated rock strength
exceeds 150 MPa.

BAUER Maschinen GmbH, D-86529 Schrobenhausen

64

32

Project Reference Work sequence


KL MRT Piling Project, Malaysia 2013
Pile no.:
Pile diameter:
Pile depth:

BK 36/3
2,800 mm
18.8 m

G.L 0.0m to G.L. -8.0m:


rock auger

Net drill time:

34.6 hrs

G.L. -8.0m to G.L. -18.8m

2800

4 nos. pilot holes

KR-R 900

break remaining rock


on the left and right

KR-R/KR-X 1500

then enlarge step by step KR-R/KR-X1800,


KR-R/KR-X 2800

BAUER Maschinen GmbH, D-86529 Schrobenhausen

65

Project Reference
Stonecutter Bridge Hongkong

East Tsing Yi Viaduct


1.1km long + ramps
6 lane highway
263 nos. of bored piles
dia. 1500mm and 2000mm
depth up to 80m
and rock socket 5m to 8m
Courtesy:
Bauer Construction Malaysia
Dr.K.S.Rama Krishna L&T-ECC Division
BAUER Maschinen GmbH, D-86529 Schrobenhausen

66

33

Project Reference General soil profile


Stonecutter Bridge Hongkong

Reclaimed sand, loose to medium


dense (with obstruction in form of
seawalls)

Marine clays soft


Alluvium
Decomposed granite with boulders
Granite bedrock GI-GIII
UCS 100-200 Mpa

BAUER Maschinen GmbH, D-86529 Schrobenhausen

67

Project Reference Rock cores


Stonecutter Bridge Hongkong
Solid rock core
recovered on
Stonecutter Approach
Viaducts

BAUER Maschinen GmbH, D-86529 Schrobenhausen

68

34

Project Reference Performance


Stonecutter Bridge Hongkong

263 nos. of Bored Piles with extensive rock drilling were


completed in 9 months

4 nos. of Bauer BG 40 rigs were used


Production equivalent to 2.5 days per pile and rig
Rig output was doubled compared to conventionally production
of RCD-Drilling Rigs

BAUER Maschinen GmbH, D-86529 Schrobenhausen

69

Project Reference Quality control


Stonecutter Bridge Hongkong
Hong Kong has one of the most stringent pile testing regimes

100% predrilling prior to pile drilling

100% Sonic Logging

100% verticality check, 10% verticality check by Koden or as


per Specifications

100% Interface
Full core of pile 5% to 10% depending on Specifications
Material testing such as cube crushing and Rebar Tensile Test
as per Specifications

BAUER Maschinen GmbH, D-86529 Schrobenhausen

70

35

Project Reference Interface cores


Stonecutter Bridge Hongkong

BAUER Maschinen GmbH, D-86529 Schrobenhausen

71

Logistics Preparation of working platform


flat and stable platform required
if soft surface conditions use steel plates or similar
rig is top-heavy => careful movements
=> beware of badly covered open holes or soft backfill
=> avoid inclined hoist
housekeeping for safety reasons and for economy reasons

BAUER Maschinen GmbH, D-86529 Schrobenhausen

72

36

Logistics Working platform

BAD INSUFFICIENT
BACKFILL

BAUER Maschinen GmbH, D-86529 Schrobenhausen

73

Logistics Housekeeping at pile location

where is the borehole??

clean with good slurry management

=> unsafe and inefficient operation

=> safe and economic operation


BAUER Maschinen GmbH, D-86529 Schrobenhausen

74

37

Logistics Planning of work sequence


finished
pile

next
pile

traffic road
work area

work direction
drill spoil

traffic road
finished
pile

next
pile

traffic road
work area

work direction
drill spoil

traffic road
BAUER Maschinen GmbH, D-86529 Schrobenhausen

75

Logistics Selection of rig type

confined space
small diameter
limited number of piles
=> smaller rig

sufficient work space


large, deep piles
big number of piles
=> larger rigs
BAUER Maschinen GmbH, D-86529 Schrobenhausen

76

38

Logistics - BG kinematic system (V-System)


Criteria of
mast connection system:

developed by Bauer
2 big backstay cylinders
stiff and sturdy load transfer
for optimum flow of forces
(torque!)

typically used for rigs with high


torque

BAUER Maschinen GmbH, D-86529 Schrobenhausen

77

Logistics - BG kinematic system (V-System)

H
L

BAUER Maschinen GmbH, D-86529 Schrobenhausen

78

39

Logistics- Transport (V-System)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

79

Logistics - BG kinematic system (H-System)

Backstay Cylinder
Kinematics Triangle

Support Boom
Boom
Boom Cylinder

3 Connecting Points
with base frame
BAUER Maschinen GmbH, D-86529 Schrobenhausen

80

40

Logistics - BG kinematic system (H-System)


Transport position

BAUER Maschinen GmbH, D-86529 Schrobenhausen

81

Logistics - BG kinematic system (H-System)

BAUER Maschinen GmbH, D-86529 Schrobenhausen

82

41

Modern cabin
increases safety, economy and comfort

83

BAUER Maschinen GmbH, D-86529 Schrobenhausen

B-Tronic screen

Mast
inclination and
positioning

Winches
and Crowd
info

Kelly
visualization:
Locking
position
Visualization of the
borehole and the Kelly bar
BAUER Maschinen GmbH, D-86529 Schrobenhausen

84

42

B-Tronic a fully integrated system


USB-Stick

PC

equipment

B-Report

Browser

files

B-tronicscreen
machine
control

DTR

Internet

Bauer
customer centre

BauerWeb-BGM

BAUER Maschinen GmbH, D-86529 Schrobenhausen

Bauer
data host

85

B-Report Analysis of pile production time

BAUER Maschinen GmbH, D-86529 Schrobenhausen

86

43

Safety Handling Assistant


1. Step:
NO

OK

Indication of safe and


critical work ranges
=> Operator has to react

2. Step:
!

Electronic control reacts


=> Operator controls

BAUER Maschinen GmbH, D-86529 Schrobenhausen

87

Safety Fall protection (Working at height)


Catwalk on
uppercarriage

Catwalk around
the base carrier

BAUER Maschinen GmbH, D-86529 Schrobenhausen

88

44

Safety Camera controls

Cameras:
1. Back View
2. Right hand side
Automatic view when
when slewing or travelling

BAUER Maschinen GmbH, D-86529 Schrobenhausen

89

Environment - Emissions reduction

BAUER Maschinen GmbH, D-86529 Schrobenhausen

90

45